23
SAP ECC 6.0 EhP3 August 2008 English Product Cost Planning (169) Building Block Configuration Guide

Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

Embed Size (px)

Citation preview

Page 1: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP ECC 6.0 EhP3

August 2008

English

Product Cost Planning (169)

SAP AGDietmar-Hopp-Allee 1669190 WalldorfGermany

Building Block Configuration Guide

Page 2: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Copyright

© Copyright 2008 SAP AG. All rights reserved.

No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The information contained herein may be changed without prior notice.

Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.

Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation.

IBM, DB2, DB2 Universal Database, OS/2, Parallel Sysplex, MVS/ESA, AIX, S/390, AS/400, OS/390, OS/400, iSeries, pSeries, xSeries, zSeries, System i, System i5, System p, System p5, System x, System z, System z9, z/OS, AFP, Intelligent Miner, WebSphere, Netfinity, Tivoli, Informix, i5/OS, POWER, POWER5, POWER5+, OpenPower and PowerPC are trademarks or registered trademarks of IBM Corporation.

Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the United States and/or other countries.

Oracle is a registered trademark of Oracle Corporation.

UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.

Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc.

HTML, XML, XHTML and W3C are trademarks or registered trademarks of W3C®, World Wide Web Consortium, Massachusetts Institute of Technology.

Java is a registered trademark of Sun Microsystems, Inc.

JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented and implemented by Netscape.

SAP, R/3, xApps, xApp, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP Business ByDesign, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and in several other countries all over the world. All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary.

These materials are subject to change without notice. These materials are provided by SAP AG and its affiliated companies ("SAP Group") for informational purposes only, without representation or warranty of any kind, and SAP Group shall not be liable for errors or omissions with respect to the materials. The only warranties for SAP Group products and services are those that are set forth in the express warranty statements accompanying such products and services, if any. Nothing herein should be construed as constituting an additional warranty.

© SAP AG Page 2 of 17

Page 3: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Icons

Icon MeaningCaution

Example

Note

Recommendation

Syntax

External Process

Business Process Alternative/Decision Choice

Typographic Conventions

Type Style Description

Example text Words or characters that appear on the screen. These include field names, screen titles, pushbuttons as well as menu names, paths and options.

Cross-references to other documentation.

Example text Emphasized words or phrases in body text, titles of graphics and tables.

EXAMPLE TEXT Names of elements in the system. These include report names, program names, transaction codes, table names, and individual key words of a programming language, when surrounded by body text, for example, SELECT and INCLUDE.

Example text Screen output. This includes file and directory names and their paths, messages, source code, names of variables and parameters as well as names of installation, upgrade and database tools.

EXAMPLE TEXT Keys on the keyboard, for example, function keys (such as F2) or the ENTER key.

Example text Exact user entry. These are words or characters that you enter in the system exactly as they appear in the documentation.

<Example text> Variable user entry. Pointed brackets indicate that you replace these words and characters with appropriate entries.

© SAP AG Page 3 of 17

Page 4: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Contents

1 Purpose.................................................................................................................................... 5

2 Preparation............................................................................................................................... 5

2.1 Prerequisites.................................................................................................................. 5

3 Configuration............................................................................................................................ 5

3.1 Basic Settings for Material Costing................................................................................5

3.1.1 Costing Sheet: Components......................................................................................5

3.1.2 Costing Sheet............................................................................................................9

3.1.3 Cost Component Structure......................................................................................10

3.1.4 Assigning Cost Component Structure to CO Version..............................................14

3.2 Settings Cost Estimate with Qty Structure...................................................................14

3.2.1 Defining Valuation Variant.......................................................................................14

3.2.2 Defining Costing Variants........................................................................................16

3.2.3 Activating Cross-Company Costing.........................................................................17

© SAP AG Page 4 of 17

Page 5: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Product Cost Planning1 PurposeThis configuration guide provides the information you need to set up the configuration of this building block manually.

If you do not want to configure manually and prefer an automated installation process using the SAP Best Practices Installation Assistant and other tools, refer to the SAP Best Practices Quick Guide.

2 Preparation

2.1 PrerequisitesBefore you start installing this building block, you must install prerequisite building blocks. For more information, see the building block prerequisite matrix (Prerequisites_Matrix_[xx]_EN_CN.xls; the placeholder [xx] depends on the SAP Best Practices version you use, for example, BL refers to the SAP Best Practices Baseline Package: Prerequisites_Matrix_BL_EN_CN.xls). This document can be found on the SAP Best Practices documentation DVD in the folder ..\BBLibrary\General\.

3 Configuration

3.1 Basic Settings for Material CostingIn this section, the basic settings needed for material costing are configured, such as the Costing Sheet (for overhead surcharge) and the Cost Component Structure (for costing).

Overhead surcharge is done to take into account costs that cannot be assigned directly to materials or orders, such as warehouse or procurement costs.

The cost components in the Cost Component Structure are used to display the cost components in the cost estimate, for analysis in the information system and to transfer the cost components to Profitability Analysis (CO-PA).

3.1.1 Costing Sheet: ComponentsThe costing sheet integrates all elements of overhead costing. These are Calculation bases, Percentage overhead rates and Credits.

3.1.1.1 Defining Calculation Bases

UseCalculation Bases are used in the Costing Sheet. They define which cost elements a percentage rate refers to.

Procedure1. Access the activity using one of the following navigation options:

Transaction code SPRO

© SAP AG Page 5 of 17

Page 6: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

IMG menu Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Overhead Costing Sheet: Components Define Calculation Bases

2. Choose New Entries.

3. Create calculation bases according to the following data records:

Base Name

Y001 Material

Y002 Production

4. Save your entries and go to detail for every Base.

5. From the dialog structure on the left side of the screen, choose Calculation base Details (on the left side of the screen).

6. In the Set Controlling Area dialog box, select the relevant controlling area (for example 1000) and choose Enter.

7. On the Change View ‘Details’: Overview screen, choose New Entries.

8. Create details for every calculation bases according to the following data records.

Base Name Co Area From CElem

To CstElem

Cost Elem. Group

Cost portion

Y001 Material 1000 1200_CE total

Y002 Production 1000 4500_CE total

9. Save the entries and choose Back.

3.1.1.2 Defining Percentage Overhead

UseAn overhead rate specifies the conditions under which overhead is applied to an object.

Procedure1. Access the activity using one of the following navigation options:

Transaction code KZZ2

IMG menu Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Overhead Costing Sheet: Components Define Percentage Overhead Rates

2. Choose Create to create a new overhead rate.

3. Enter a four-character identification code and a name for the new overhead rate and assign to a dependency.

Overview of the new O/H rates:

O/H rate Name Dependency Description

Y101 Material overhead D020 Overhead Type/Plant

© SAP AG Page 6 of 17

Page 7: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Y102 Production overhead D020 Overhead Type/Plant

Y103 Administration ovh D020 Overhead Type/Plant

Y104 Sales overhead D020 Overhead Type/Plant

4. Save your overhead rate and go to detail for every Overhead Rate.

5. From the dialog structure on the left side of the screen, choose Overhead rate Details (on the left side of the screen).

6. On the Change View ‘Details’: Overview screen, choose New Entries and specify the individual overhead rates for every overhead rates.

Each record consists of a validity period, a percentage rate and several condition fields, which are taken from the condition tables.

7. Create details for every Overhead Rate according to the following data records.

O/H rate Valid from to CO Area Ovrhd type Plant Percentage

Y101 2007.01.01 2007.12.31 1000 1 1000 5

Y101 2007.01.01 2007.12.31 1000 2 1000 5

Y101 2008.01.01 2008.12.31 1000 1 1000 7

Y101 2008.01.01 2008.12.31 1000 2 1000 7

Y101 2009.01.01 2009.12.31 1000 1 1000 7

Y101 2009.01.01 2009.12.31 1000 2 1000 7

Y101 2010.01.01 2010.12.31 1000 1 1000 7

Y101 2010.01.01 2010.12.31 1000 2 1000 7

Y102 2007.01.01 2007.12.31 1000 1 1000 10

Y102 2007.01.01 2007.12.31 1000 2 1000 10

Y102 2008.01.01 2008.12.31 1000 1 1000 10

Y102 2008.01.01 2008.12.31 1000 2 1000 10

Y102 2009.01.01 2009.12.31 1000 1 1000 10

Y102 2009.01.01 2009.12.31 1000 2 1000 10

Y102 2010.01.01 2010.12.31 1000 1 1000 10

Y102 2010.01.01 2010.12.31 1000 2 1000 10

Y103 2007.01.01 2007.12.31 1000 1 1000 5

Y103 2007.01.01 2007.12.31 1000 2 1000 5

Y103 2008.01.01 2008.12.31 1000 1 1000 5

Y103 2008.01.01 2008.12.31 1000 2 1000 5

Y103 2009.01.01 2009.12.31 1000 1 1000 5

Y103 2009.01.01 2009.12.31 1000 2 1000 5

Y103 2010.01.01 2010.12.31 1000 1 1000 5

Y103 2010.01.01 2010.12.31 1000 2 1000 5

© SAP AG Page 7 of 17

Page 8: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Y103 2007.01.01 2007.12.31 1000 1 1000 5

Y103 2007.01.01 2007.12.31 1000 2 1000 5

Y103 2008.01.01 2008.12.31 1000 1 1000 5

Y103 2008.01.01 2008.12.31 1000 2 1000 5

Y103 2009.01.01 2009.12.31 1000 1 1000 5

Y103 2009.01.01 2009.12.31 1000 2 1000 5

Y103 2010.01.01 2010.12.31 1000 1 1000 5

Y103 2010.01.01 2010.12.31 1000 2 1000 5

Y104 2007.01.01 2007.12.31 1000 1 1000 6.5

Y104 2007.01.01 2007.12.31 1000 2 1000 6.5

Y104 2008.01.01 2008.12.31 1000 1 1000 6.5

Y104 2008.01.01 2008.12.31 1000 2 1000 6.5

Y104 2009.01.01 2009.12.31 1000 1 1000 6.5

Y104 2009.01.01 2009.12.31 1000 2 1000 6.5

Y104 2010.01.01 2010.12.31 1000 1 1000 6.5

Y104 2010.01.01 2010.12.31 1000 2 1000 6.5

8. Choose Enter.

9. Choose Save.

3.1.1.3 Defining Credits

UseCredits are used in the Costing Sheet and contain information about the credited sender and the cost element for the overhead posting.

Procedure1. Access the activity using one of the following navigation options:

Transaction code SPRO

IMG menu Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Overhead Costing Sheet: Components Define Credits

2. Choose New Entries to create a new credit.

3. Enter a three-character key and a name for the new credit as shown below.

Data records:

Credit Name

Y10 Credit Material 1

Y20 Credit Production 1

© SAP AG Page 8 of 17

Page 9: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Y30 Credit Admin

Y40 Credit Sales

4. Save your entries and go to detail for every Credit.

5. Select the row and choose Detail.

From the dialog structure on the left side of the screen, choose Credits Details (on the left side of the screen).

6. In the Set Controlling Area dialog box, select the relevant controlling area (for example 1000) and choose Enter.

7. On the Change View ‘Details’: Overview screen, choose New Entries.

8. Create details for every Credit according to the following data records.

Credit Co Area Valid to Cost Elem. Fxd % Cost Center

Y10 1000 9999.12.31 94111000 * 1201

Y20 1000 9999.12.31 94112000 * 1301

Y30 1000 9999.12.31 94113000 * 1101

Y40 1000 9999.12.31 94114000 * 1101

9. Save your entries.

3.1.2 Costing Sheet

3.1.2.1 Defining Costing Sheets – Costing Sheets and Rows

UseThe Costing Sheet calculates Overhead surcharges to standard cost estimates and production orders.

Procedure1. Access the activity using one of the following navigation options:

Transaction code SPRO

IMG menu Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Overhead Define Costing Sheet

2. Choose New Entries and create the following Costing Sheets

Costing Sheet Description

YPP-PC BP: Costing Sheet Production

YPP-PP BP: Costing Sheet for Planning

3. Mark the corresponding Costing Sheet and double-click Costing sheet rows.

4. Enter your costing sheet as shown in the table:

© SAP AG Page 9 of 17

Page 10: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Costing Sheet

Row Base Overhead rate

Description (enter manually)

From To Credit

YPP-PC 10 Y001

YPP-PC 20 Y101 Y10

YPP-PC 30 Material usage

YPP-PC 40 Y002

YPP-PC 50 Y102 Y20

YPP-PC 60 Production Costs 40 50

YPP-PC 70 Costs of goods manufactured

YPP-PP 10 Y001

YPP-PP 20 Y101 Y10

YPP-PP 30 Material usage

YPP-PP 40 Y002

YPP-PP 50 Y102 Y20

YPP-PP 60 Production Costs 40 50

YPP-PP 70 Costs of goods manufactured

YPP-PP 100 Y103 70 Y30

YPP-PP 110 Y104 70 Y40

YPP-PP 200 COGS

5. Save your entries.

3.1.3 Cost Component Structure

UseThe Cost Component Structure structures the costs of cost objects by grouping Cost Elements in cost components such as Material Costs, Packaging, Internal Activity and so on.

This section contains the following steps:

- Define Cost Component Structure - Cost Component Structure

- Define Cost Component Structure - Cost Component with Attributes

- Define Cost Component Structure - Assign Cost Elements

- Define Cost Component Structure - Assign Organiz. Units

- Assignment of Cost Component Structure to Controlling Versions

© SAP AG Page 10 of 17

Page 11: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

Procedure1. Access the activity using one of the following navigation options:

Transaction code OKTZ

IMG menu Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Define Cost Component Structure

2. Choose New Entries and enter the following data:

Cost Comp. Str. Active Name Primary Cost Component Split

Y1 X BP Cost Component Layout

YP BP Product drilldown

3. Mark the created line and choose Cost Components with Attributes.

4. Enter the following three values (Cost Component Structure, Cost Component and Name) and theirs characteristic (Cost Rollup, Cost of Goods Sold an Inventory Valuation) on the following screen.

For all other offered fields, leave fields as they are.

Cost Comp.Struct.

Cost Component

Name of Cost Comp. Indicators

Cost Rollup

Cost of Goods Sold

Inventory Valuation

Costs of Goods Manufactured

Sales and Admin Costs

Fix and variable Costs

Not relevant

Y1 010 Direct Material Set Set Set

Y1 020 Material overhead Set Set Set

Y1 030 Third party Set Set Set

Y1 040 Personnel time Set Set Set

Y1 050 Machine time Set Set Set

Y1 060 Set-Up time Set Set Set

Y1 080 Production overhead Set Set Set

Y1 090 AdminSales overhead Set Set

Y1 100 Miscellaneous Set Set

YP 010 Direct Material Set Set Set

YP 020 Material overhead Set Set Set

YP 030 Third party Set Set Set

© SAP AG Page 11 of 17

Page 12: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

YP 040 Personnel time Set Set Set

YP 050 Machine time Set Set Set

YP 060 Set-Up time Set Set Set

YP 070 Production overhead Set Set Set

YP 080 AdminSales overhead Set Set

YP 095 WIP Set Set

YP 100 Miscellaneous Set

5. Go back to first level, choose Save, and then choose your Cost Component Structure by marking and double-click Assignment: Cost Component - Cost Element Interval.

6. Enter the following assignments of Cost Elements to Cost Components.

Cost Comp. Str.

Chart of Accts

From cost element To cost element Cost Component

Y1 YACN 50010101 50010101 10

Y1 YACN 50010201 50010201 10

Y1 YACN 50010211 50010211 10

Y1 YACN 50010221 50010221 10

Y1 YACN 50010301 50010301 10

Y1 YACN 50010401 50010401 10

Y1 YACN 50010501 50010501 10

Y1 YACN 50010511 50010511 10

Y1 YACN 50010521 50010521 10

Y1 YACN 50012001 50012001 10

Y1 YACN 57010202 57010202 30

Y1 YACN 57010203 57010203 30

Y1 YACN 94111000 94111000 20

Y1 YACN 94112000 94112000 80

Y1 YACN 94113000 94113000 90

Y1 YACN 94114000 94114000 90

Y1 YACN 94301000 94301000 50

Y1 YACN 94302000 94302000 50

Y1 YACN 94303000 94303000 60

Y1 YACN 94304000 94310000 100

Y1 YACN 94311000 94311000 40

Y1 YACN 94321000 94324000 100

© SAP AG Page 12 of 17

Page 13: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

YP YACN 50010101 50010211 10

YP YACN 50010301 50010301 10

YP YACN 50010401 50010401 10

YP YACN 50010501 50010501 10

YP YACN 57010202 57010202 30

YP YACN 57010203 57010203 30

YP YACN 93111000 93200000 95

YP YACN 94111000 94111000 20

YP YACN 94112000 94112000 70

YP YACN 94113000 94113000 80

YP YACN 94114000 94114000 80

YP YACN 94301000 94301000 50

YP YACN 94302000 94302000 50

YP YACN 94303000 94303000 60

YP YACN 94304000 94310000 100

YP YACN 94311000 94311000 40

YP YACN 94321000 94324000 100

7. Save your entries and go back to the first level.

8. Double-click Assignment: Organiz. Units - Cost Component Struct (on the left side of the screen) and make the following entry:

Company Code Plant Costing Variant

Valid from Cost Comp Structure (Main CCS)

1000 ++++ ++++ <current year>01.01 Y1

9. Save all setting and go back to the first level

10. On the screen Change view ‘Cost Component Structure’: Overview make sure that the flag for Active is set for Cost Component structure Y1

11. Save your entries.

© SAP AG Page 13 of 17

Page 14: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

3.1.4 Assigning Cost Component Structure to CO Version

UseIn Cost Center Accounting, the cost component structure determines how the results of the activity price calculation are updated.

Procedure1. Access the activity using one of the following navigation options:

Transaction code SPRO

IMG menu Controlling General Controlling Organization Maintain Versions

2. Mark Version 0 and double-click Settings for each fiscal year. Enter 1000 for Controlling Area and 0 for Version.

3. Mark and double-click the fiscal year (for example: 2007) and enter Y1 for Cost Component Structure on the work sheet Price Calculation.

4. Save your entry.

5. Enter the Y1 Cost Component Structure for each fiscal year in Version 0 and save your entries.

6. Go back to Maintain Versions, mark Version 2 and double-click Settings for Each Fiscal Year. Enter 1000 for Controlling Area and 2 for Version.

7. Mark and double-click the fiscal year (for example: 2007) and enter Y1 for Cost Component Structure on the work sheet Price Calculation.

8. Save your entry.

9. Enter the Y1 Cost Component Structure for each fiscal year in Version 1 and save your entries.

3.2 Settings Cost Estimate with Qty StructureIn this section, settings are configured that enable the user to perform costing of materials.

3.2.1 Defining Valuation Variant

UseThe Valuation Variant controls various parameters regarding the valuation of input items for the object for which costs are being determined.

Procedure1. Access the activity using one of the following navigation options:

Transaction code OKK4

© SAP AG Page 14 of 17

Page 15: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

IMG menu Controlling Product Cost Controlling Product Cost Planning Material Cost Estimate with Quantity Structure Costing Variant: Components Define Valuation Variants

2. Choose New Entries and enter header data. Then for each new entry choose Details and enter remaining data.

3. Overview of data records:

Valuation Variant Name

Y01 BP:Planned Val. Version 0

Y02 BP:Planned Val Plan Vers.

Details of data records:

Material Value

Prio Strategy sequence incl add co

Y01 1 7 Valuation Price According to Price Control Not set

Y02 1 4 Planned Price 1 Not set

Y02 2 7 Valuation Price According to Price Control Not set

Activity Types/processes

Prio Strategy sequence P/A Version

Y01 1 2 Plan price as average of all fiscal year periods 0

Y02 1 2 Plan price as average of all fiscal year periods 2

Subcontracting: quotation in purchasing

Y01 3 Net Quotation Price Quot. in purchasing: Actual Quota Arrangement

Y02 3 Net Quotation Price Quot. in purchasing: Actual Quota Arrangement

External processing

Prio Strategy sequence

Y01 1 1 Price from Operation

Y01 2 3 Net quotation price

Y02 1 1 Price from Operation

Y02 2 3 Net quotation price

Overhead

Materials Components OH on subc. Mat.

Y01 YPP-PP Baseline Costing Sheet Not set

Y01 YPP-PP Baseline Costing Sheet Not set

© SAP AG Page 15 of 17

Page 16: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

3.2.2 Defining Costing Variants

UseThe Costing Variant controls various parameters when costs for a cost object or a material are being determined, such as the costing type or the valuation variant used.

Procedure1. Access the activity using one of the following navigation options:

Transaction code OKKN

IMG menu Controlling Product Cost Controlling Product Cost Planning Material Cost Estimate with Quantity Structure Define Costing Variant

2. Choose New Entries and enter header data. Then for each new entry choose Details and enter remaining data.

3. Overview of data records (identical control for lean and full scope):

Valuation Variant Name

YPC1 SMB Standard cost est.

YPC2 SMB Standard cost V2

Lean scope:

Control

Costing Type

Val. Variant Date Control Qty. Str. Ctrl Transf. Ctrl

YPC101 Stand. Cost Est. (Mat)

Y01 BP:Planned Val. Version 0

PC01 Std.Cost Est. - Month

PC01 Std Qty. Structure Ctrl2

PC01 Transfer w/ Plant Change

YPC201 Stand. Cost Est. (Mat)

Y02 BP:Planned Val Plan Vers.

PC02Std Cost Est. - Subseq.FY

PC01 Std Qty. Structure Ctrl2

PC01 Transfer w/ Plant Change

Qty. Struct.

Pass on Lot size Ignore PCE TrCtrl can be chd Transf. act. SCE

YPC1 No not set not set not set

YPC2 No not set not set not set

Additive Costs

YPC1 1 Ignore; include AC with Stock Transfers: not set

YPC2 1 Ignore; include AC with Stock Transfers: not set

Update

Saving allowed Save Itemization Save Error Log Defaults changes

YPC1 set set set not set

© SAP AG Page 16 of 17

Page 17: Utilities_Building_Blocks_China_Product Cost Planning _169_BB_ConfigGuide.doc

SAP Best Practices Product Cost Planning (169): Configuration Guide

YPC1 set set set not set

Misc.

YPC1 2 Log and save messages, Mail inactive

YPC2 2 Log and save messages, Mail inactive

3.2.3 Activating Cross-Company Costing

UseActivating Cross-Company Costing allows the system advanced operations during costing, such as accessing information in more than one company code, taking into account additive costs (such as transportation charges for planned stock transfers) or releasing costing results for all company codes in the controlling area.

Procedure1. Access the activity using one of the following navigation options:

Transaction code OKYV

IMG menu Controlling Product Cost Controlling Product Cost Planning Selected Functions in Material Costing Activate Cross-Company Costing

2. Make the following entries:

Controlling Area Costing Type Valuation Variant Cost Across Company Codes

1000 01 Y01 X

© SAP AG Page 17 of 17