    TUNEL KLOTAR, HR

  • Estabilizao de taludes | Tunel Klotar, HR 2/6

    TUNEL KLOTAREstabilizao de taludes

    Projecto Tunel KlotarNmero do projecto 130527-HRLugar VrbovskoPas / Regio Crocia

    Ano de instalao 2015

    Cliente Hrvatske eljezniceEngenharia Geotehniki studio ZagrebContratante Octopus Rijeka

    Situao Rockfalls on a speed up railway line near tunnel Klotar.

    Descrio Active slope protection and tunnel portal with nailed DELTAX mesh and TECCO

    SYSTEM3.

    Objecto protegido Caminho de ferroSistemas TECCO G65/3, DELTAX G80/2

    Proteco contra a corroso GEOBRUGG SUPERCOATING , GEOBRUGG ULTRACOATING

    Geologia Limestone.

    rea estabilizada 3 m

    Altura do talude 10 mInclinao do talude 60 - 75

    Medida de proteco Estabilizao activa do talude

    Exposio Sudeste

  • Estabilizao de taludes | Tunel Klotar, HR 3/6

    Tunnel Klostar portal and slopes around in the final stateafter stabilization.

    Drilling works on the slope directly next to the tunnelportal.

    Drilling works and installation of nails on the tunnelportal.

  • Estabilizao de taludes | Tunel Klotar, HR 4/6

    Tunnel portal protected with TECCO SYSTEM3.

    TECCO SYSTEM3 on the slope.

  • Estabilizao de taludes | Tunel Klotar, HR 5/6

  • Estabilizao de taludes | Tunel Klotar, HR 6/6

    Tunnel portal after completion of all installation works.

    Em caso de dvidas por favor contacte com nosso especialista Geobrugg na sua rea

    Head office and production

    Telefone+1 505 771 4080

    [email protected]

    Geobrugg North America, LLC22 Centro Algodones | Algodones NM 87001 | Estados Unidos| www.geobrugg.comA company of the BRUGG Group | Certified to ISO 9001