TUGAS AKHIR
EVALUASI PENJADWALAN PROYEK DALAM
EFISIENSI WAKTU DAN BIAYA
( Studi Kasus Proyek Rehabilitasi Saluran Drainase Dan
Boezem Di Jalan Cumpat Kulon Baru I RT 4 Surabaya )
Disusun Oleh :
Achmad Wildan Abdillah
NBI :1411506596
Dosen Pembimbing Utama :
Istantyo Yuwono, ST., MT
NPP 20410.94.0381
PROGRAM STUDI TEKNIK INDUSTRI
FAKULTAS TEKNIK
UNIVERSITAS 17 AGUSTUS 1945 SURABAYA
2020
ii
iii
iv
v
KATA PENGANTAR
Assalamu’alaikum warahmatullahi wabarakatu…
Segala puji syukur kehadirat Allah SWT, berkat rahmat-Nya berupa
kekuatan lahir maupun batin serta jalan semangat pada penulisan sehingga dapat
menyelesaikan tahap demi tahap laporan tugas akhir yang berjudul : “EVALUASI
PENJADWALAN PROYEK DALAM EFISIENSI WAKTU DAN BIAYA
(Studi Kasus Proyek Rehabilitasi Saluran Drainase Dan Boezem Di Jalan
Cumpat Kulon Baru I RT 4 Surabaya)”
Laporan tugas akhir disusun guna memenuhi persyaratan kelulusan dalam
menyelesaikan S-1 Program Teknik Industri, Fakultas Teknik, Universitas 17
Agustus 1945 Surabaya, dan juga semoga penelitian ini dapat memberikan manfaat
bagi pembaca. Terimakasih kepada pihak yang membantu menyelesaikan penelitian
ini, yaitu:
1. Kedua orang tua bapak Mashuri Syahidan dan ibu Mudjiati yang senantiasa
selalu memberi perhatian semangat dukungan serta doa yang selalu di
panjatkan.
2. Bapak Istantyo Yuwono, S.T., M.T. selaku dosen pembimbing yang telah
memberikan banyak masukan ilmu dalam bimbingan.
3. Bapak Heri Murnawan, S.T., M.T. selaku ketua program studi jurusan
Teknik Industri Universitas 17 Agustus 1945 Surabaya.
4. Bapak dan ibu dosen Fakultas Teknik Jurusan Teknik Industri yang telah
meluangkan waktu untuk memberi saran yang berguna bagi penulis.
5. Mas Faisal selaku pengawas lapangan pada proyek yang bersangkutan telah
memberikan izin penelitian dan mendukung pada setiap tahapnnya untuk
menyelesaikan tugas akhir ini.
6. Teman-teman UNTAG Angkatan 2015, yang telah memberi dukungan dan
motivasi.
Akhirnya dengan rendah hati penulis menyampaikan banyak terimakasih sebesar
besarnya kepada semua pihak yang telah memberi motivasi dan dukungan penuh
kepada penulis dalam pembuatan laporan ini.
Surabaya, 13 Mei 2020
Penulis
vi
ABSTRAK
“EVALUASI PENJADWALAN PROYEK DALAM EFISIENSI WAKTU DAN
BIAYA (Studi Kasus Proyek Rehabilitasi Saluran Drainase Dan Boezem Di
Jalan Cumpat Kulon Baru I RT 4 Surabaya)”
Program Pemerintah Kota Surabaya untuk mencegah kawasan yang rawan banjir
dengan melakukan rehabilitasi atau pemeliharaan saluran drainase dan boozem.
Pelaksanaan proyek berlokasi di Jalan Cumpat Kulon RT.4, Kel. Kedung Cowek,
Kec. Bulak, Surabaya. Pada praktik di lapangan proyek mengalami keterlambatan,
maka dilakukannya upaya percepatan durasi proyek (crashing) untuk
mengembalikan tingkat kemajuan proyek ke rencana semula. Dengan Metode CPM
(Critical Path Method) dan dilakukannya crash duration proyek dapat dipercepat
selama 8 hari dari perencanaan semula 98 hari menjadi 90 hari.
Dengan adanya percepatan durasi proyek maka diperlukan tambahan biaya sebesar
Rp 39,704,061.84. Sehingga biaya optimal yang diperlukan untuk mempercepat
pelaksanaan proyek pemeliharaan saluran drainase dan boozem di Jalan Cumpat
Kulon RT. 4 adalah sebesar Rp 695,135,368.84 yang semula direncanakan sebesar
Rp 655,431,307.00. Maka terjadi penambahan biaya akibat percepatan pelaksanaan
sebesar = 0.39% dari biaya yang direncanakan.
Kata Kunci: Saluran Drainase, CPM, Crash Duration
vii
ABSTRACT
“EVALUATION OF PROJECT SCHEDULING IN EFFICIENCY OF TIME
AND FEES (Case Study of Rehabilitation Project for Drainage and Boezem
Channels on Jalan Cumpat Kulon Baru I RT 4 Surabaya)”
Surabaya City Government's program to prevent flood-prone areas by rehabilitating
or maintaining drainage and boozem channels. The project implementation is
located at Jalan Cumpat Kulon RT. 4, Kel. Gedung Cowek, Kec. Bulak, Surabaya.
In practice in the field the project has been delayed, so the efforts to accelerate the
duration of the project (crashing) to restore the level of project progress to the
original plan. With the CPM (Critical Path Method) method and the project crash
duration can be accelerated for 8 days from the original planning of 98 days to 90
days.
With the acceleration of the project duration, an additional fee of Rp. 39,704,061.84
is required. So that the optimal cost needed to accelerate the implementation of
maintenance projects for drainage and boozem channels in Jalan Cumpat Kulon
RT.4 is Rp. 695,135,368.84 which was originally planned as Rp. 655,431,307.00.
Resulting in additional costs due to the acceleration of the implementation of =
0.39% of the planned costs.
Keywords: Drainage Channels, CPM, Crash Duration
viii
DAFTAR ISI
HALAMAN JUDUL ...................................................................................................i
LEMBAR PENGESAHAN TUGAS AKHIR .......................................................... ii
LEMBAR PERNYATAAN ORIGINALITAS TUGAS AKHIR ......................... iii
LEMBAR PERNYATAAN PERSETUJUAN PUBLIKASI ................................. iv
KATA PENGANTAR ............................................................................................... v
ABSTRAK ................................................................................................................. vi
ABSTRACT ............................................................................................................. vii
DAFTAR ISI ........................................................................................................... viii
DAFTAR GAMBAR ................................................................................................. x
DAFTAR TABEL ..................................................................................................... xi
BAB I ......................................................................................................................... 1
PENDAHULUAN ..................................................................................................... 1
1.1 Latar Belakang ............................................................................................ 1
1.2 Rumusan Masalah ...................................................................................... 4
1.3 Tujuan Penelitian ........................................................................................ 5
1.4 Ruang Lingkup Penelitian .......................................................................... 5
1.4.1 Batasan Masalah ................................................................................. 5
1.4.2 Asumsi Masalah ................................................................................. 5
1.5 Manfaat Penelitian ...................................................................................... 6
BAB II ........................................................................................................................ 7
LANDASAN TEORI ................................................................................................ 7
2.1 Manajemen Proyek .................................................................................... 7
2.2 Penjadwalan Proyek ................................................................................... 8
2.2.1 Penjadwalan Model CPM (Critical Path Method) ............................. 9
2.2.2 Jaringan Kerja (Network Planning) .................................................. 10
2.2.3 Durasi Waktu Kegiatan .................................................................... 11
2.2.4 Jalur Kritis (Critical Path) ................................................................ 11
ix
2.2.5 Jadwal Aktivitas ................................................................................ 13
2.3 Microsoft Project....................................................................................... 14
2.3.1 Keuntungan Microsoft Project .......................................................... 16
2.3.2 Kelemahan Microsoft Project ........................................................... 17
2.4 Metode TCTO (Time Cost Trade Off) ....................................................... 17
2.4.1 Crash Duration ................................................................................. 18
2.5 Penelitian Terdahulu ................................................................................. 18
BAB III ..................................................................................................................... 21
METODE PENELITIAN ....................................................................................... 21
2.1 Penjelasan Penelitian ................................................................................. 21
2.2 Flowchart Penelitian .................................................................................. 22
2.3 Perencanaan Penelitian .............................................................................. 23
BAB IV ..................................................................................................................... 25
ANALISIS DATA DAN PEMBAHASAN ............................................................. 25
4.1 Data proyek ............................................................................................... 25
4.2 Data Pelaksanaan Proyek .......................................................................... 25
4.3 Perencanaan dan Pengendalian Proyek Dengan Metode CPM ................. 31
4.4 Perhitungan Produktivitas Harian, Normal dan Percepatan ...................... 36
4.5 Perhitungan Crash Duration, Crash Cost, dan Cost Slope ....................... 39
4.6 Analisis Waktu dan Biaya Optimum ......................................................... 45
BAB V ....................................................................................................................... 47
KESIMPULAN DAN SARAN ............................................................................... 47
5.1 KESIMPULAN ......................................................................................... 47
5.2 SARAN ..................................................................................................... 47
DAFTAR PUSTAKA .............................................................................................. 48
LAMPIRAN ............................................................................................................. 49
x
DAFTAR GAMBAR
Gambar 1.1 Peta Lokasi Pekerjaan ............................................................................. 2
Gambar 1.2 Uraian dan Bobot Pekerjaan ................................................................... 3
Gambar 2. 1 Proses Manajemen Proyek ..................................................................... 8
Gambar 2.2 Kegiatan A pendahulu kegiatan B & kegiatan B pendahulu kegiatan C
.................................................................................................................................. 12
Gambar 2.3 Kegiatan A dan B merupakan pendahulu kegiatan C ........................... 12
Gambar 2.4 Kegiatan A dan B merupakan pendahulu kegiatan C dan D ................ 12
Gambar 2.5 Kegiatan B merupakan pendahulu kegiatan C dan D ........................... 13
Gambar 2. 6 Gambaran Aktivitas Proyek ................................................................. 13
Gambar 3.1 Kerangka Penelitian .............................................................................. 22
Gambar 4.1 Diagram Network Proyek dengan Microsoft Project ............................ 33
Gambar 4.2 Diagram Network Pekerjaan (Durasi Normal) ...................................... 36
xi
DAFTAR TABEL
Tabel 2.1 Penelitian Terdahulu ................................................................................. 18
Tabel 3.1 Jadwal Penelitian ....................................................................................... 23
Tabel 4.1 Rencana Anggaran Biaya pada Pekerjaan Pemeliharaan Atau Rehabilitasi
................................................................................................................................... 26
Tabel 4.2 Jadwal Kegiatan Proyek dengan Microsoft Project .................................. 31
Tabel 4.3 Kegiatan Pekerjaan Jalur Kritis ................................................................. 34
Tabel 4.4 Produktivitas Harian Percepatan Pekerjaan Kritis .................................... 37
Tabel 4.5 Kegiatan Pekerjaan Durasi Normal dan Durasi Crash .............................. 41
Tabel 4.6 Perhitungan Crash Duration, Crash Cost, dan Cost Slope ....................... 42
Tabel 4.7 Hasil Perhitungan Normal dan Percepatan ................................................ 46