Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Transportation Engineers
3853 Taylor Road, Suite G • Loomis, CA 95650 • (916) 660-1555 • FAX (916)660-1535
June 21, 2018 Ms. Cybil Bryant
BUZZ OATES CONSTRUCTION, INC.
8615 Elder Creek Road
Sacramento, CA 95828
RE: TRAFFIC IMPACT ASSESSMENT FOR MACE BLVD / ALHAMBRA DRIVE
TENTATIVE PARCEL MAP PROJECT, DAVIS, CA
Dear Ms. Bryant:
As requested, KD Anderson & Associates, Inc. has completed our assessment of the potential traffic
impacts associated with the Mace Blvd / Alhambra Drive Project (Tentative Map 5144). As we have
discussed, the project is a 65,000 sf business park combining office, R&D and limited retail uses on a 6-
acre site located on Mace Blvd the northwest corner of its intersection with Alhambra Drive / Mace Blvd
intersection in east Davis. The site has been previously approved for development in 2006 as a 70,000 sf
retail shopping center, although other site development proposals have come forward since then, most
recently as a 56 ksf office / medical office / retail center. The site currently has Neighborhood Retail
General Plan land use designation, and a change to a lower trip generating Business Park designation is
proposed.
Approach to Assessment
Because the current proposal and the proposed land use designation generates potentially less traffic than
the approved and designated uses, a focused approach to traffic impact assessment is applicable, including
the following elements:
Trip Generation. Daily, a.m. and p.m. peak hour trip generation forecasts have been made for the site
under current and previously approved plans, and under the current General Plan designation. The
relative difference in trip generation was identified.
Travel Characteristics. The share of project trips likely to be made by pedestrians, bicyclists and transit
users was identified. The directional distribution of vehicle trips was identified, and the assignment of
project trips via proposed driveways was determined.
Background Traffic Conditions. Current peak hour operating Levels of Service at the Mace Blvd /
Alhambra Drive intersection were identified based on available information. Long term cumulative
conditions were also described assuming community build out under the General Plan and with other
pending development projects based on available information.
Impact Assessment based on Level of Service. The extent to which the addition of project trips may
result in increased traffic and operating conditions in excess of adopted City of Davis minimum standards
at the Mace Blvd / Alhambra Blvd intersection was assessed. Forecast cumulative traffic conditions were
reviewed and the extent to which improvements are needed was considered.
Ms. Cybil Bryant
Traffic Impact Assessment for Mace Blvd / Alhambra Drive Tentative Parcel Map Project, Davis, Ca
June 21, 2018
Page 2
Impact Assessment based on Site Access. The feasibility of proposed left turn access from Mace Blvd
was reviewed based on left turn storage requirements for the lane and for the Mace Blvd / Alhambra
Drive intersection.
Trip Generation
The development of the project site project will generate travel to and from the project site. The amount
of additional traffic on a particular section of the street network depends on three factors:
Trip Generation, the number of new person trips that would be generated by the project,
Modal Choice , the share of site traffic made by private automobiles, by walking, by bicycle or
transit,
Trip Distribution and Assignment, the direction of travel and specific routes that the new vehicle
trip would take.
Vehicle trip generation is determined by identifying the type and size of land use being developed and
applying applicable trip generation rates to this information. Recognized sources of trip generation rate
data are used to calculate the total number of projected trip ends. This includes City-derived data from
the current city-wide traffic model or other City information as well trip generation rates from the
Institute of Transportation Engineers (ITE) publication Trip Generation Manual, 10th Edition.
Approved Project. The trip generation rates used in this analysis and the results for the approved project
are presented in Table 1. The approved project is expected to generate an estimated 4,235 vehicle trips
per day. Some of the trips based on nationally derived ITE rates would likely be made on foot, by bicycle
or by transit in Davis, and a reduction in vehicles trip was made based on available data. The Draft
Environmental Impact Report (DEIR) for the Cannery Park project identified an 8% reduction for
bicyclists and pedestrians and a 4% reduction for transit users. The site is located along a Unitrans route
and is adjacent to the City’s comprehensive bikeway network. As the project is located adjacent to
bicycle lanes and along Unitrans routes these reduction rates were considered. Since the project is located
in the east end of the City the 8% rate was reduced to 4% as it is expected that fewer residents will bike to
the project. After accounting for modal choice the approved retail project would generate 113 a.m. peak
hour trips and 265 new p.m. peak hour trips.
Proposed Project. The trip generation forecast for the proposed project is shown in Table 2. As
indicated, we considered a variety of rates associated with the various uses that might be allowed on the
site. The City traffic model’s rate for Office and Retail yield the greatest number of daily trips, and that
total is similar to, but lightly higher than forecasts derived from the model’s Business Park / Research &
Development rate. The ITE rates for Office and Retail also yield the greatest number of peak hour trips.
After accounting for modal choice, the project could generate 978 daily trips, with 82 a.m. peak hour and
74 p.m. peak hour trips. Because the project’s estimate is less than or similar to the approved project, its
traffic impacts would be similar or less that those associated with that use.
Ms. Cybil Bryant
Traffic Impact Assessment for Mace Blvd / Alhambra Drive Tentative Parcel Map Project, Davis, Ca
June 21, 2018
Page 3
TABLE 1
PREVIOUSLY APPROVED PROJECT TRIP GENERATION
Land Use (Code) Amount
Daily
Rate
Daily
Trips
AM Peak Hour PM Peak Hour
Rate % In % Out In Out Total Rate % In % Out In Out Total
Retail (820) 70.0 ksf 60.50 A 4,235 2.67 B 62% 38% 116 71 187 5.96 B 48 52% 200 217 417
Less Pass By 34% n.a. 39 25 64 68 74 142
New Trips 4,235 77 46 123 132 143 275
Trip Reductions
Walking / Biking (4%) (3) (2) (5) (4%) (2) (3) (5)
Transit (4%) (3) (2) (5) (4%) (2) (3) (5)
New Trip – Total 4,235 71 42 113 128 137 265
ksf – thousand square feet. Sum of values may not equal due to rounding A - City Travel Demand Model rate B Trip generation equation used per ITE, 10th Edition
Ms. Cybil Bryant
Traffic Impact Assessment for Mace Blvd / Alhambra Drive Tentative Parcel Map Project, Davis, Ca
June 21, 2018
Page 4
TABLE 2
PROPOSED PROJECT TRIP GENERATION
Land Use / Code Amount
Daily
Rate
Daily
Trips
AM Peak Hour PM Peak Hour
Rate % In % Out In Out Total Rate % In % Out In Out Total
General Office ( 710) 63 ksf 17.5 A
847 1.36 B
86% 14% 74 12 86 1.17 B
16% 84% 12 62 74
Research & Development
(760) 63 ksf - - 0.42
C 75% 25% 19 6 25 0.72
B 15% 85% 20 25 45
Business Park (770) 6 acres 149.9A
899 0.40C
61% 39%
63 ksf - 0.40 61% 39% 15 10 25 0.42C
46% 54% 12 24 26
Retail (820) 2.00 ksf 60.5A
131 0.94C
62% 38% 1 1 2 3.81 48% 52% 4 4 8
New Trips – Sub Total 978 75 13 88 16 66 82
Trip Reductions
Walking / Biking (4%) (3) (1) (3) (4%) (1) (3) (3)
Transit (4%) (3) (1) (3) (4%) (1) (3) (3)
New Trip – Total 978 69 11 82 14 60 74
ksf – thousand square feet. Sum of values may not equal due to rounding A - City Travel Demand Model rate B - Trip generation equation used per ITE Trip Generation Manual, 10th Ed, 2017 C - Average rate used per ITE Trip Generation Manual, 10th Ed.
Ms. Cybil Bryant
Traffic Impact Assessment for Mace Blvd / Alhambra Drive Tentative Parcel Map Project, Davis, Ca
June 21, 2018
Page 5
Travel Characteristics
Trip Distribution. The geographic distribution of vehicle trips associated with the approved and
proposed projects was determined based on the local knowledge of the City. Fifty percent of the trips are
estimated to come from either I-80 or south Davis. The remaining trips are projected to be split
approximately 30% via Covell Blvd to the north west and 20% via 5th Street.
Trip Assignment. The project trip assignment that would be generated by the proposed Alhambra Place
project is shown in Figure 1. Of the total trips generated by the project 46 a.m. peak hour trips and 41
p.m. peak hour trips are projected to travel through the Mace Blvd. / Alhambra Drive intersection.
Background Traffic Conditions
Mace Blvd / Alhambra Drive Intersection. The Mace Blvd / Alhambra Drive intersection is a signal
controlled “tee” intersection. Mace Blvd has a single northbound through lane and two southbound
through lanes at this intersection. The northbound approach provides a 250’± left turn lane with protected
left phasing. Separate “free” right turn lanes exist for the southbound and eastbound approaches. For
both movements, the vehicles departing the intersection are not required to yield to through movement
vehicles as they enter their own lane as the turn is completed.
Current Operating Levels of Service. The most recent information regarding intersections on the Mace
Blvd corridor comes from the Mace Ranch Innovation Center (MRIC) DEIR. As noted in Table 3, that
document indicated that after accounting for the overall effects of coordinated operation of signals along
the corridor, the Alhambra Drive intersection operates at LOS A in the a.m. and p.m. peak hour. These
conditions satisfy the City’s minimum LOS E standard. Current traffic peak hour volumes at the
intersection are shown in Attachment 1.
Background Cumulative Traffic Conditions. The MRIC DEIR and FEIR provide information
regarding future cumulative traffic conditions. That document considered multiple background
conditions (i.e., Cumulative, CEQA Cumulative and Modified Cumulative, all with and without the
MRIC. The results of that analysis are also presented in Table 3.
As noted in the MRIC EIR documents, the Mace Blvd / Alhambra Drive intersection operates acceptably,
at LOS E or better, under both CEQA Cumulative without and with MRIC scenarios. The intersection
will continue to operate acceptably under the Modified Cumulative without MRIC scenario, at LOS B or
better. Under the Modified Cumulative with MRIC scenario the intersection will operate below the City’s
LOS threshold, at LOS F. The mitigations identified in the MRIC EIR are dependent on the alternative
option. Under Options 1 and 2, installation of a second southbound left turn lane and installation of a
northbound shared through-right lane and northbound right turn lane between 2nd
Street and Alhambra
Drive will result in the intersection operating at LOS E or better. Under Option 3, the intersection would
require addition of an eastbound left-turn lane, re-striping the eastbound shared through-left lane to a
shared through-right lane and re-striping the dedicated northbound right-turn lane to a shared through-
right lane is needed for the intersection to operate at LOS E or better. It is noted that the projects
contained within the Modified Cumulative plus project alternative have either been delayed or abandoned.
The delayed projects will require a supplemental EIR that will further analyze this intersection.
PROJECTLOCATION
(1) 5
(3) 1
6
1 (0
)
13 (3
)
(15) 3
PROJECTLOCATION
(15) 3
(1) 5
13 (3
)
21 (4
)
(3) 1
(15) 3PROJECTLOCATION
(15) 2
17 (3)
9 (2)
(0) 4
PROJECTLOCATION
(5) 2
(25) 4 9 (2)
0 (2)
2 (13)
(3) 14
Legend
AM Peak Hour VolumeXX
PM Peak Hour Volume(XX)
N.T.S.
figure 1
PROJECT ONLY PEAK HOUR TRIPS
5015-21 RA 6/15/2018
KD Anderson & Associates, Inc.Transportation Engineers
Ms. Cybil Bryant
Traffic Impact Assessment for Mace Blvd / Alhambra Drive Tentative Parcel Map Project, Davis, Ca
June 21, 2018
Page 7
TABLE 3 BACKGROUND LEVEL OF SERVICE CONDTIONS
AT MACE BLVD / ALHAMBRA DRIVE INTERSECTION
Condition
AM Peak Hour PM Peak Hour
Average Delay
(sec/veh) LOS
Average Delay
(sec/veh) LOS
Existing 4 A 5 A
CEQA Cumulative without MRIC 11 B 55 D
CEQA Cumulative with MRIC 46 D 78 E
Modified Cumulative without MRIC 10 A 11 B
Modified Cumulative with MRIC 86 F 72 E
Assessment
Existing Plus Project Impacts. The Mace Blvd / Alhambra Drive currently operates at LOS A. There is
latent capacity for this intersection to accommodate additional traffic, and it is our opinion that the
relatively small amount of additional traffic accompanying this use will not have a significant impact;
therefore mitigation is not required.
Cumulative Impacts. The site was previously approved for development and its traffic would already be
included in the long term cumulative traffic analyses that have accompanied development proposals in
Davis, including the MRIC. The project generates fewer trips than the approved use, making the
contribution to cumulative conditions less. The cumulative impacts associated with this project,
therefore, would be similar to, or less than those previously addressed.
Summary Conclusions
The Mace Blvd / Alhambra Drive intersection currently operates at a Level of Service that is well above
the City’s minimum LOS E standard, at LOS A. The small amount of additional traffic accompanying
this use will not have a significant impact on the intersection; therefore, there is no mitigation required.
Because the site was previously approved for development its traffic has been included in the long term
cumulative traffic analyses that have accompanied development proposals in Davis, including the MRIC.
The project generates fewer trips than the existing approved use, and its contribution to cumulative
conditions would be less. The cumulative impacts associated with this project, therefore, would be
similar to, or less than those previously addressed.
Thank you for your attention to this information
Sincerely, KD Anderson & Associates, Inc. Kenneth D. Anderson, P.E., President Attachments