157
Network Rail (Essex and Others Level Crossing Reduction) Order TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (INQUIRIES PROCEDURE) RULES 2004 THE NETWORK RAIL (ESSEX AND OTHERS LEVEL CROSSING REDUCTION) ORDER ___________________________________________________________________ SUSAN TILBROOK SUPPLEMENTARY PROOF OF EVIDENCE RELATING TO MATTERS RAISED IN JOHN RUSSELL'S LETTER DATED 12TH OCTOBER 2017 Document Reference NR/32/5

TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Embed Size (px)

Citation preview

Page 1: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Network Rail (Essex and Others Level CrossingReduction) Order

TRANSPORT AND WORKS ACT 1992

TRANSPORT AND WORKS (INQUIRIESPROCEDURE) RULES 2004

THE NETWORK RAIL(ESSEX AND OTHERS

LEVEL CROSSING REDUCTION)ORDER

___________________________________________________________________

SUSAN TILBROOK

SUPPLEMENTARY PROOF OF EVIDENCERELATING TO MATTERS RAISED

IN JOHN RUSSELL'S LETTERDATED 12TH OCTOBER 2017

Document Reference NR/32/5

Page 2: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

7

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Contents

Chapter Title Page

1 Introduction 1

2 John Russell Letter Dated 12th October 2017 2

Appendix A Stage 1 Road Safety Audit reports for Essex (Document ref 367516/RPT016 Rev A) 5

Appendix B Stage 1 Road Safety Audit reports for Havering, Hertfordshire & Thurrock (Document ref367516/RPT017 Rev A) 6

Appendix C Document Review Notice (DRN 025) 7

Appendix D Document Review Notice (DRN 026) 8

Appendix E Email Correspondence Detailing Discrepancy 9

Appendix F The updated designers response Report 11

Page 3: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

1

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

1.1 This supplemental Proof of Evidence has been prepared on behalf of Network Rail to respond toparticular matters raised in John Russell’s letter dated 12th October 2017 (with regard to theEssex and others Level Crossing Reduction Order).

1.2 Mr Russell, representing the Ramblers Association, has raised similar points with regard to roadsafety audit evidence at both the Cambridgeshire and Suffolk Level Crossing Reduction Orderinquiries. Responses were issued to the Ramblers and submitted to each inquiry that addressedthe points raised. I also gave verbal answers to questions regarding the points at each inquiry.This note addresses the same points but has been amended to reflect the specific documentreferences associated with this Order.

1.3 I believe the facts and opinions stated to be true and that my evidence conforms to the standardsand requirements of my professional body.

1 Introduction

Page 4: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

2

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

2.1 Mr Russell has stated his concern if S J Tilbrook and Sue Tilbrook transpire to be the sameperson. I can confirm that I am both named persons and I am the CEM (Contractor’s EngineeringManager) for the Anglia Level Crossing Reduction Strategy project. I can confirm that I approvedthe designer’s response report for Essex (Document ref 367516/RPT021 Rev B) and approvedthe second revision of the Stage 1 Road Safety Audit reports for Essex (Document ref367516/RPT016 Rev B) and Havering, Hertfordshire & Thurrock (Document ref 367516/RPT017Rev B), for issue as part of Mott MacDonald’s commission on the project.

2.2 Mr Russell has rightly pointed out that the Road Safety Team must be independent from thedesign team and I can confirm that this is indeed the case for the Road Safety Audit’s (RSAs)carried by Mott MacDonald for the project. In summary, the fact that I have approved the RSAreport for issue as a deliverable on the project does not mean that the RSA has not beenprepared independently, as I explain below. I do not accept that the RSAs are undermined by myfamiliarity with the proposals or any “pride” in them.

2.3 Mr Russell makes reference to RSA reports 367516/RPT016 Revision B and 367516/RPT017Revision B that were both approved by me. These documents required a very minor amendment(correcting one erroneous reference to a version of another document in the report). The principleof me approving the documents was discussed and agreed with the independent RSA team atthe time and considered appropriate due to the minor change.

2.4 This matter is documented as part of the Network Rail review and acceptance procedure (in theDocument Review Notices (DRN) 025 and DRN026) (see Appendix C and D) and the coveringemail that was issued with the reports at the time, which explains and documents the changesmade (see Appendix E). These documents / correspondences provide a contemporaneousrecord of the changes made and are appended to this document.

2.5 A copy of revision A of each of the RSA reports 367516/RPT016 and 367516/RPT017 are alsoappended to this response note to allow comparison to revision B of the reports referred to aboveand contained in NR16. (see Appendix A and B).

2.6 There is one change between Revision A and Revision B of each of the reports 367516/RPT016and 367516/RPT017, which can be seen at paragraph 1 on page 2 of each document as follows:-

· 367516/RPT016 Revision B states “A previous Stage 1 Road Safety Audit (Document Ref:354763/RPT222A) was undertaken in December”

· 367516/RPT016 Revision A states “A previous Stage 1 Road Safety Audit (Document Ref:354763/RPT222B) was undertaken in December”

· 367516/RPT017 Revision B states “A previous Stage 1 Road Safety Audit (Document Ref:354763/RPT222A) was undertaken in December”

· 367516/RPT017 Revision A states “A previous Stage 1 Road Safety Audit (Document Ref:354763/RPT222B) was undertaken in December”

2 John Russell Letter Dated 12th October2017

Page 5: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

3

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

2.7 There are no other changes between each version of the 2 documents.

2.8 It is important to note that document ref 367516/RPT016 Rev B and 367516/RPT017 Rev Bmade no changes to any of the issues raised in the original version (Rev A) of each RSAdocument.

2.9 I would also draw your attention to Section 3 of the Road Safety Audit Report, the Audit TeamStatement in each document. In this section of the RSA reports all members of the Audit Teamhave signed the document to confirm “We certify that this audit has been carried out inaccordance with the Highways England Departmental Standard HD 19/15.”. It can clearly beseen that I do not have a role within the Audit team.

2.10 Notwithstanding the above, it should also be noted that any document issued by Mott MacDonaldhas to be Checked and Approved in accordance with Mott MacDonald’s Business ManagementSystem (BMS), which is certificated to ISO 9001.

2.11 Under Mott MacDonald’s BMS, all documents and deliverables have to be checked by a person(not the originator) with the requisite experience and approved by someone at a senior level fromthe project team. In view of the minor amendment to documents ref 367516/RPT016 and367516/RPT017, which did not relate to the body of the findings of the Road Safety Audit, theapprover of revision B was considered appropriate to ensure that the document was being issuedin line with Mott MacDonald’s BMS requirements.

2.12 Based on the above, role of the approver in this instance has no bearing on the outcome of theAudit, as their role is to ensure that the deliverable is carried out in line with the projectrequirements, which in this case is to carry out Road Safety Audits in accordance with HD19/15.In other words, the approval process is to make sure that an RSA compliant with therequirements of the project has been produced. The judgments in the document are unaffected.

2.13 I will take this opportunity to identify and correct an error on the front cover of the Essex,Thurrock and Hertfordshire Stage 1 Road Safety Audit (Dec 2015) included in NR16, whichshows the Report Number as 354763/RPT219 Revision A. This is a typo and the Essex,Thurrock and Hertfordshire Stage 1 Road Safety Audit front cover should show the report numberas 354763/RPT222 Revision A.

2.14 In conclusion, I can confirm that the correct information is contained within NR16 and this is theRoad Safety Audit information that will be relied on at the inquiry. I can also confirm that theRSAs have been carried out by an independent Audit team.

2.15 It should be noted that further Stage 1 RSAs were carried out in September 2017 to consider thefinal proposals at 5 level crossing locations. The RSA reports associated with these crossings areappended to my rebuttal document ref NR32/4/2, which was submitted to inquiry in October2017. No road safety problems were identified in the additional audits. The designer’s response

Page 6: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

4

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

report ref 367516/RPT021 has been updated to Rev C to reflect the additional audits carried outand it is appended to this note (see Appendix F).

Page 7: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

5

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix A Stage 1 Road Safety Auditreports for Essex (Document ref367516/RPT016 Rev A)

Page 8: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2

Review

Essex Stage 1 Road Safety Audit

Report Number 367516/RPT016 Revision A

August 2016

Page 9: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 10: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

287864 TPN ITD 266 A

09 August 2016

Transport & Works Act Order (TWAO) Anglia Route GRIP 1 Revie

Essex Stage 1 Road Safety Audit

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review

Essex Stage 1 Road Safety Audit

August 2016

Network Rail

Mott MacDonald, 35 Newhall Street, Birmingham, B3 3PU, United Kingdom

T +44 (0)121 234 1500 F +44 (0)121 200 3295 W www.mottmac.com

Page 11: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 12: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

Revision Date Originator Checker Approver Description

A 09/08/2016 R J Collins A J Coleman T J Blaney First Draft

Issue and revision record

Information class: Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

Page 13: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 14: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

Chapter Title Page

1 Introduction 1

2 Items Raised at this Stage 1 Audit 4

2.1 E04 – Parndons Mill _________________________________________________________________ 4 2.1.1 Problem __________________________________________________________________________ 4 2.2 E05 – Fullers End (Red Route) ________________________________________________________ 5 2.3 E05 – Fullers End (Blue Route) ________________________________________________________ 5 2.4 E06 – Elsenham Emergency Hut (Red Route) _____________________________________________ 5 2.5 E06 – Elsenham Emergency Hut (Blue Route) ____________________________________________ 5 2.6 E09 – Elephant (Red Route) __________________________________________________________ 5 2.7 E09 – Elephant (Blue Route) __________________________________________________________ 5 2.8 E09 – Elephant (Green Route) _________________________________________________________ 6 2.8.1 Problem __________________________________________________________________________ 6 2.9 E10 – Dixies (Red Route) _____________________________________________________________ 7 2.10 E13 – Littlebury Gate House __________________________________________________________ 8 2.10.1 Problem __________________________________________________________________________ 8 2.11 E16 – Maldon Road _________________________________________________________________ 9 2.12 E20 – Snivellers (Red Route) __________________________________________________________ 9 2.13 E24 – Church 1 ____________________________________________________________________ 9 2.14 E25 – Church 2 ____________________________________________________________________ 9 2.15 E27 – Puddle Dock (Red Route) _______________________________________________________ 9 2.16 E27 – Puddle Dock (Blue Route) _______________________________________________________ 9 2.17 E27 – Puddle Dock (Green Route) _____________________________________________________ 10 2.17.1 Problem _________________________________________________________________________ 10 2.18 E28 – Whipps Farmers (Blue Route) ___________________________________________________ 11 2.19 E28 – Whipps Farmers (Green Route) __________________________________________________ 11 2.19.1 Problem _________________________________________________________________________ 11 2.20 E29 – Brown & Tawse (Blue Route) ____________________________________________________ 12 2.21 E29 – Brown & Tawse (Red Route) ____________________________________________________ 12 2.21.1 Problem _________________________________________________________________________ 12 2.22 E33 – Motorbike (Red Route) _________________________________________________________ 13 2.22.1 Problem _________________________________________________________________________ 13 2.23 E33 – Motorbike (Blue Route) ________________________________________________________ 14 2.23.1 Problem _________________________________________________________________________ 14 2.24 E40 – Creaksea Place 1 (Red Route) __________________________________________________ 15 2.25 E40 – Creaksea Place 1 (Blue Route) __________________________________________________ 15 2.26 E44 – Frating Abbey (Red Route) _____________________________________________________ 15 2.27 E44 – Frating Abbey (Blue Route) _____________________________________________________ 15 2.28 E48 – Wheatsheaf _________________________________________________________________ 15 2.29 E49 – Maria Street _________________________________________________________________ 15 2.30 E51 – Thornfield Wood (Blue Route) ___________________________________________________ 15 2.31 E51 – Thornfield Wood (Red Route) ___________________________________________________ 16 2.31.1 Problem _________________________________________________________________________ 16

Contents

Page 15: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.32 E53 – Josselyns (Blue Route) ________________________________________________________ 16 2.33 E55 – Lamarsh Kings Farm (Green Route) ______________________________________________ 17 2.34 E56 – Abbotts (Blue Route) __________________________________________________________ 17 2.34.1 Problem _________________________________________________________________________ 17 2.35 E56 – Abbotts (Orange Route) ________________________________________________________ 18 2.36 E57 – Wivenhoe Park _______________________________________________________________ 18 2.36.1 Problem _________________________________________________________________________ 18

3 Audit Team Statement 19

Appendices 20

Appendix A. List of Submitted Documents _________________________________________________________ 21 Appendix B. Key Plans ________________________________________________________________________ 22

Page 16: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

1 1

Network Rail is carrying out feasibility studies to explore options for the closure of level crossings

throughout Essex as part of their on-going commitment to deliver a safer, more efficient and reliable

railway. Mott MacDonald is considering Network Rail’s GRIP 0 Solution to enable the closure of level

crossings.

This report describes a series of Stage 1 Road Safety Audits carried out on highway works associated with

proposed level crossing closures throughout Essex. The scheme proposals currently consist of indicative

(high level) diversion routes as the result of closures and no formal highway works have been designed at

this stage. Therefore this report considers potential road safety problems as a result of the proposed

routes and their interaction with the highway. A detailed description of the proposed diversion routes at

each location can be read in the respective individual level crossing review reports.

The audits took place at the Birmingham office of Mott MacDonald and consisted of a detailed examination

of the submitted documentation and drawings listed in Appendix A.

A visit to each site was completed on either Wednesday 20th July 2016 between 14:00 and 20:40, during

which the weather was sunny and the road surface was dry or on Thursday 21st July between 08:00 and

11:00 during which the weather conditions were sunny and the road surface was dry.

It is confirmed that this is a Stage 1 Road Safety Audit and that the audit was undertaken upon completion

of the feasibility design. It is also confirmed that the audit was carried out in accordance with the Highways

England Departmental Standard HD19/15.

The Audit Team consisted of:

T Blaney BSc (Hons), CMILT, MCIHT, MSoRSA (Team Leader)

Mott MacDonald

R Collins BA (Hons), MSc (Team Member)

Mott MacDonald

No attempt has been made to comment on the justification of the scheme or the appropriateness of the

diversion routes. Consequently the auditors accept no responsibility for the design or construction of the

scheme. All of the issues raised in this report are considered to be required for action. The comments

contained in the report are based on safety related concerns and as such the design engineer will need to

consider carefully how to respond to each of the issues. The Audit Report Response should be completed

by the Design Team and kept on file for future reference.

An Audit Brief was submitted to the Audit Team, however, no Personal Injury Collision data was included

and has therefore not been reviewed as part of this audit. Traffic flows and speed data were also not

available to the Audit Team.

1 Introduction

Page 17: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2 2

A previous Stage 1 Road Safety Audit (Document Ref: 354763/RPT222B) was undertaken in December

2015 on level crossing closure proposals within Essex. This included some sites that have been audited

on this occasion and sites that have been re-audited due to the development of alternative route options or

amendments to the previously audited route. The table below lists the level crossing proposals that have

been subject to a stage 1 road safety audit and when the audits were undertaken.

Site December 2015 August 2016

E04 – Parndons Mill

E05 – Fullers End

E06 – Elsenham Emergency Hut

E08 – Henham

E09 – Elephant

E10 – Dixies

E11 – Windmills

E12 – Wallaces

E13 – Littlebury Gate House

E14 – Church Lane Cctv (ltn1)

E16 – Maldon Road

E17 – Boreham

E18 – Noakes

E19 – Potters

E20 – Snivellers

E21 – Hill House 1

E22 – Great Domsey

Page 18: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

3 3

Site December 2015 August 2016

E24 – Church 1

E25 – Church 2

E26 – Barbara Close

E27 – Puddle Dock (Red Route)

E27 – Puddle Dock (Blue Route)

E27 – Puddle Dock (Green Route)

E28 – Whipps Farmers (Red Route)

E28 – Whipps Farmers (Blue Route)

E28 – Whipps Farmers (Green Route)

E29 – Brown & Tawse (Blue Route)

E29 – Brown & Tawse (Red Route)

A Key Plan indicating the location of any identified safety related issues is provided in Appendix B.

Page 19: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

4 4

This section describes road safety related issues identified by the Audit Team that are associated with the

scheme as presented in Appendix A.

2.1 E04 – Parndons Mill

2.1.1 Problem

Location: Elizabeth Way / Herons Wood.

Summary: Unnecessary carriageway crossing and lack of suitable crossing point.

It is proposed that the alternative route will require pedestrians to cross Elizabeth Way to the southern side

and continue along an existing footway. This footway crosses Herons Wood at a point where no

appropriate crossing point is provided. This may result in trips or falls, or conflicts between pedestrians

and vehicles. Furthermore, there is a segregated footway / cycleway along the length of the northern side

of Elizabeth Way that would remove the need for pedestrians to cross any carriageways. Therefore, the

proposed route unnecessarily increases the risk of collisions between crossing pedestrians and vehicles.

Recommendation

It is recommended that the route continues along the northern side of Elizabeth Way.

2 Items Raised at this Stage 1 Audit

Figure 2.1: Lack of appropriate crossing facility on Herons Wood.

Source: Mott MacDonald

Page 20: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

5 5

2.2 E05 – Fullers End (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.3 E05 – Fullers End (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.4 E06 – Elsenham Emergency Hut (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.5 E06 – Elsenham Emergency Hut (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.6 E09 – Elephant (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.7 E09 – Elephant (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 21: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

6 6

2.8 E09 – Elephant (Green Route)

2.8.1 Problem

Location: Debden Road railway bridge.

Summary: Restricted carriageway width over railway bridge.

The carriageway width over the railway bridge narrows to single carriageway with no footway or verge

meaning pedestrians would have to share the carriageway with vehicles. Forward visibility of pedestrians

could be restricted (particularly eastbound) and although vehicles are travelling slowly over the bridge, this

could result in conflict between pedestrians and vehicles.

Recommendation

It is recommended that measures are provided to either warn motorists of pedestrians within the

carriageway or to further slow vehicles on the approach. However, if suitable remedial measures cannot

be provided then an alternative route should be identified.

Figure 2.2: Restricted width on Debden Road over railway line.

Source: Mott MacDonald

Page 22: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

7 7

2.9 E10 – Dixies (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 23: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

8 8

2.10 E13 – Littlebury Gate House

2.10.1 Problem

Location: Littlebury Green Road.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Littlebury Green Road where no footway or

notable verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic

was observed on Littlebury Green Road travelling at high speeds and visibility is restricted by the highway

geometry and vegetation, particularly to the west of Goodwins Close. These factors may result in

collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided.

Figure 2.3: Lack of verge or footway on Littlebury Green Road.

Source: Mott MacDonald

Page 24: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

9 9

2.11 E16 – Maldon Road

The Audit Team did not identify any road safety related issues associated with the scheme.

2.12 E20 – Snivellers (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.13 E24 – Church 1

The Audit Team did not identify any road safety related issues associated with the scheme.

2.14 E25 – Church 2

The Audit Team did not identify any road safety related issues associated with the scheme.

2.15 E27 – Puddle Dock (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.16 E27 – Puddle Dock (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 25: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

10 10

2.17 E27 – Puddle Dock (Green Route)

2.17.1 Problem

Location: St Marys Lane.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry.

These factors may result in collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Figure 2.4: Lack of verge or footway on St Marys Lane.

Source: Mott MacDonald

Page 26: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

11 11

2.18 E28 – Whipps Farmers (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.19 E28 – Whipps Farmers (Green Route)

2.19.1 Problem

Location: St Marys Lane.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry.

These factors may result in collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Figure 2.5: Lack of verge or footway on St Marys Lane.

Source: Mott MacDonald

Page 27: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

12 12

2.20 E29 – Brown & Tawse (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.21 E29 – Brown & Tawse (Red Route)

2.21.1 Problem

Location: St Marys Lane Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry

and the railway road bridge. These factors may result in collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Figure 2.6: Lack of verge or footway on St Marys Lane.

Source: Mott MacDonald

Page 28: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

13 13

2.22 E33 – Motorbike (Red Route)

2.22.1 Problem

Location: Pitsea Hall Lane.

Summary: High HGV flow and speed.

It is proposed that pedestrians will walk along a section of Pitsea Hall Lane on the western side of the

carriageway where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. A high number of HGVs generally travelling at excessive speeds were observed on Pitsea

Hall Lane. This may lead to an increased risk of collisions between pedestrians and vehicles.

Recommendation

It is recommended that suitable crossing facilities are provided to allow pedestrians to cross to the eastern

side and utilise the existing segregated footway / cycleway. Vegetation clearance will need to be untaken

to provide a suitable footway / cycleway width.

Figure 2.7: Lack of verge or footway on western side of Pitsea Hall Lane.

Source: Mott MacDonald

Page 29: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

14 14

2.23 E33 – Motorbike (Blue Route)

2.23.1 Problem

Location: Pitsea Hall Lane.

Summary: High HGV flow and speed.

It is proposed that pedestrians will walk along a section of Pitsea Hall Lane on the western side of the

carriageway where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. A high number of HGVs generally travelling at excessive speeds were observed on Pitsea

Hall Lane. This may lead to an increased risk of collisions between pedestrians and vehicles.

Recommendation

It is recommended that suitable crossing facilities are provided to allow pedestrians to cross to the eastern

side and utilise the existing segregated footway / cycleway. Vegetation clearance will need to be untaken

to provide a suitable footway / cycleway width.

Figure 2.8: Lack of verge or footway on western side of Pitsea Hall Lane.

Source: Mott MacDonald

Page 30: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

15 15

2.24 E40 – Creaksea Place 1 (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.25 E40 – Creaksea Place 1 (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.26 E44 – Frating Abbey (Red Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.27 E44 – Frating Abbey (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.28 E48 – Wheatsheaf

The Audit Team did not identify any road safety related issues associated with the scheme.

2.29 E49 – Maria Street

The Audit Team did not identify any road safety related issues associated with the scheme.

2.30 E51 – Thornfield Wood (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 31: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

16 16

2.31 E51 – Thornfield Wood (Red Route)

2.31.1 Problem

Location: Jupe’s Hill Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Jupe’s Hill between Oldhouse Farm and Willow

Cottage where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. Whilst traffic flows were observed to be low, speeds were excessive with visibility restricted

by a road bridge. These factors may result in collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

2.32 E53 – Josselyns (Blue Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

Figure 2.9: Lack of verge or footway on Jupe’s Hill.

Source: Mott MacDonald

Page 32: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

17 17

2.33 E55 – Lamarsh Kings Farm (Green Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.34 E56 – Abbotts (Blue Route)

2.34.1 Problem

Location: Harwich Road / Little Bromley Road junction.

Summary: Lack of crossing facility my result in trips and falls.

It is proposed that diverted pedestrians will utilise the footway on the northern side of Harwich Road and

the carriageway on Little Bromley Road. This will require pedestrian to cross Harwich Road in the vicinity

of its junction with Little Bromley Road. No crossing facilities are provided at this location and crossing

pedestrians may either cross at inappropriate locations or trip on the full height kerb.

Recommendation

It is recommended that an appropriately positioned crossing point is installed on Harwich Road.

Figure 2.10: Lack of crossing point on Harwich Road at its junction with Little Bromley Road.

Source: Mott MacDonald

Page 33: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

18 18

2.35 E56 – Abbotts (Orange Route)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.36 E57 – Wivenhoe Park

2.36.1 Problem

Location: Lightship Way / River Colne waterfront.

Summary: Inappropriate interaction between agricultural vehicles and non-motorised users.

It is proposed that diverted agricultural vehicles will access land to the west of the railway via Lightship

Way and the River Colne waterfront path. There was a notable presence of vulnerable road users in the

vicinity of Lightship Way whilst the River Colne path is for cyclists and pedestrians. Diverting agricultural

vehicles through this residential area and onto the recreational riverside path may increase the risk of

collisions between large vehicles and vulnerable road users.

Recommendation

It is recommended that agricultural vehicles are not diverted along this route.

Page 34: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

19 19

We certify that this audit has been carried out in accordance with the Highways England Departmental

Standard HD 19/15.

Audit Team Leader

T J Blaney BSc (Hons), CMILT, MCIHT, MSoRSA

Signed:

Date: 9th August 2016

Principal Road Safety Engineer

Mott MacDonald

35 Newhall Street

Birmingham

B3 3PU

Audit Team Member

R J Collins BA (Hons), MSc

Signed:

Date: 9th August 2016

Senior Road Safety Engineer

Mott MacDonald

9 Portland Street

Manchester

M1 3BE

3 Audit Team Statement

Page 35: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

20 20

Appendices

Appendix A. List of Submitted Documents _________________________________________________________ 21 Appendix B. Key Plans ________________________________________________________________________ 22

Page 36: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

21 21

Table A.1: Drawings

Drawing Rev Title

MMD-367516-E04-GEN-002 Parndons Mill

MMD-367516-E05-GEN-002 Fullers End

MMD-367516-E06-GEN-002 Elsenham Emergency Hut

MMD-367516-E09-GEN-002 Elephant

MMD-367516-E10-GEN-002 Dixies

MMD-367516-E13-GEN-002 Littlebury Gate House

MMD-367516-E16-GEN-002 Maldon Road

MMD-367516-E20-GEN-002 Snivellers

MMD-367516-E24-GEN-002 Church 1

MMD-367516-E14-GEN-002 Church 2

MMD-367516-E27-GEN-002 Puddle Dock

MMD-367516-E28-GEN-002 Whipps Farmers

MMD-367516-E29-GEN-002 Brown & Tawse

MMD-367516-E33-GEN-002 Motorbike

MMD-367516-E40-GEN-002 Creaksea Place 1

MMD-367516-E44-GEN-002 Frating Abbey

MMD-367516-E48-GEN-002 Wheatsheaf

MMD-367516-E49-GEN-002 Maria Street

MMD-367516-E51-GEN-002 Thornfield Wood

MMD-367516-E53-GEN-002 Josselyns

MMD-367516-E55-GEN-002 Lamarsh Kings Farm

MMD-367516-E56-GEN-002 Abbotts LTN1 (56m 17ch)

MMD-367516-E57-GEN-002 Wivenhoe Park

Source: Mott MacDonald, Sheffield

Appendix A. List of Submitted Documents

Page 37: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

22

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

Appendix B. Key Plans

2.1.1

Page 38: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

23

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.08.1

Page 39: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

24

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.10.1

Page 40: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

25

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.17.1

Page 41: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

26

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.18.1

Page 42: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

27

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.21.1

Page 43: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

28

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.22.1

Page 44: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

29

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.23.1

Page 45: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

30

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.31.1

Page 46: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

31

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.34.1

Page 47: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

32

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Essex Stage 1 Road Safety Audit

2.36.1

Page 48: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

6

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix B Stage 1 Road Safety Auditreports for Havering, Hertfordshire &Thurrock (Document ref 367516/RPT017 Rev A)

Page 49: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2

Review

Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

Report Number 367516/RPT017 Revision A

August 2016

Page 50: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 51: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

287864 TPN ITD 268 A

09 August 2016

Transport & Works Act Order (TWAO) Anglia Route GRIP 1 Revie

Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review

Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

August 2016

Network Rail

Mott MacDonald, 35 Newhall Street, Birmingham, B3 3PU, United Kingdom

T +44 (0)121 234 1500 F +44 (0)121 200 3295 W www.mottmac.com

Page 52: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 53: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

Revision Date Originator Checker Approver Description

A 09/08/2016 R J Collins A J Coleman T J Blaney First Draft

Issue and revision record

Information class: Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

Page 54: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 55: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

Chapter Title Page

1 Introduction 1

2 Items Raised at this Stage 1 Audit 3

2.1 HA3 – Manor Farm __________________________________________________________________ 3 2.1.1 Problem __________________________________________________________________________ 3 2.2 HA4 – Eve’s (Blue Route) _____________________________________________________________ 4 2.2.1 Problem __________________________________________________________________________ 4 2.2.2 Problem __________________________________________________________________________ 5 2.3 HA4 – Eve’s (Red Route) _____________________________________________________________ 6 2.3.1 Problem __________________________________________________________________________ 6 2.4 H04 – Tednambury (Blue and Red Routes) _______________________________________________ 7 2.4.1 Problem __________________________________________________________________________ 7 2.5 H05 – Pattens ______________________________________________________________________ 8 2.6 H06 – Gilston ______________________________________________________________________ 8 2.7 H07 – Twyford Road_________________________________________________________________ 8 2.8 H09 – Fowlers _____________________________________________________________________ 8 2.9 T01 – No 131 ______________________________________________________________________ 8 2.10 T05 – Howells Farm _________________________________________________________________ 8 2.10.1 Problem __________________________________________________________________________ 8 2.10.2 Problem __________________________________________________________________________ 9 2.10.3 Problem _________________________________________________________________________ 10

3 Audit Team Statement 11

Appendices 12

Appendix A. List of Submitted Documents _________________________________________________________ 13 Appendix B. Key Plans ________________________________________________________________________ 14

Contents

Page 56: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

1 1

Network Rail is carrying out feasibility studies to explore options for the closure of level crossings

throughout Thurrock, Hertfordshire and Havering as part of their on-going commitment to deliver a safer,

more efficient and reliable railway. Mott MacDonald is considering Network Rail’s GRIP 0 Solution to

enable the closure of level crossings.

This report describes a series of Stage 1 Road Safety Audits carried out on highway works associated with

proposed level crossing closures throughout Havering, Hertfordshire, and Thurrock. The scheme

proposals currently consist of indicative (high level) diversion routes as the result of closures and no formal

highway works have been designed at this stage. Therefore this report considers potential road safety

problems as a result of the proposed routes and their interaction with the highway. A description of each

proposed diversion route can be read in the respective individual level crossing review reports.

The audits took place at the Birmingham office of Mott MacDonald and consisted of a detailed examination

of the submitted documentation and drawings listed in Appendix A.

A visit to each site was completed on either Wednesday 20th July 2016 between 11:00 and 14:00, during

which the weather was sunny and the road surface was dry or on Thursday 21st July between 08:00 and

11:00 during which the weather conditions were sunny and the road surface was dry.

It is confirmed that this is a Stage 1 Road Safety Audit and that the audit was undertaken upon completion

of the feasibility design. It is also confirmed that the audit was carried out in accordance with the Highways

England Departmental Standard HD19/15.

The Audit Team consisted of:

T Blaney BSc (Hons), CMILT, MCIHT, MSoRSA (Team Leader)

Mott MacDonald

R Collins BA (Hons), MSc (Team Member)

Mott MacDonald

No attempt has been made to comment on the justification of the scheme or the appropriateness of the

diversion routes. Consequently the auditors accept no responsibility for the design or construction of the

scheme. All of the issues raised in this report are considered to be required for action. The comments

contained in the report are based on safety related concerns and as such the design engineer will need to

consider carefully how to respond to each of the issues. The Audit Report Response should be completed

by the Design Team and kept on file for future reference.

An Audit Brief was submitted to the Audit Team, however, no Personal Injury Collision data was included

and has therefore not been reviewed as part of this audit. Traffic flows and speed data were also not

available to the Audit Team.

1 Introduction

Page 57: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

2 2

A previous Stage 1 Road Safety Audit (Document Ref: 354763/RPT222B) was undertaken in December

2015 on level crossing closure proposals within Hertfordshire and Thurrock. This included some sites that

have been audited on this occasion and sites that have been re-audited due to the development of

alternative route options or amendments to the previously audited route. The table below lists the level

crossing proposals that have been subject to a stage 1 road safety audit and when the audits were

undertaken.

Site December 2015 August 2016

HA3 – Manor Farm

HA4 – Eve’s (Blue Route)

HA4 – Eve’s (Red Route)

H04 – Tednambury (Blue and Red Routes)

H05 – Pattens

H06 – Gilston

H07 – Twyford Road

H09 – Fowlers

T01 – No 131

T04 – Jefferies

T05 – Howells Farm

A Key Plan indicating the location of any identified safety related issues is provided in Appendix B.

Page 58: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

3 3

This section describes road safety related issues identified by the Audit Team that are associated with the

scheme as presented in Appendix A.

2.1 HA3 – Manor Farm

2.1.1 Problem

Location: Ockendon Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Ockendon Road where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on Ockendon Road travelling at high speeds despite the 40mph speed limit and visibility is

restricted by the highway geometry and the railway road bridge. These factors may result in collisions

between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided. This should extend to Pea Lane with a dropped

kerb provided at a suitable position to allow pedestrians to join the carriageway on Pea Lane.

2 Items Raised at this Stage 1 Audit

Figure 2.1: Lack of verge or footway on Ockendon Road.

Source: Mott MacDonald

Page 59: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

4 4

2.2 HA4 – Eve’s (Blue Route)

2.2.1 Problem

Location: Ockendon Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Ockendon Road where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on Ockendon Road travelling at high speeds despite the 40mph speed limit and visibility is

restricted by the highway geometry and the railway road bridge. These factors may result in collisions

between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided. This should extend to Pea Lane with a dropped

kerb provided at a suitable position to allow pedestrians to join the carriageway on Pea Lane.

Figure 2.2: Lack of verge or footway on Ockendon Road.

Source: Mott MacDonald

Page 60: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

5 5

2.2.2 Problem

Location: Pea Lane.

Summary: Pedestrians walking for extended period of time in verge.

It is proposed that pedestrians will walk along the length of Pea Lane where no footway or notable verge is

present; a high volume of traffic was observed travelling at high speeds and visibility is restricted by the

highway geometry and vegetation. These factors may result in collisions between pedestrians and

vehicles.

Recommendation

It is recommended that a suitable footway is provided along Pea Lane or that the Red Route is utilised

taking into consideration issues raised in Section 2.3.

Figure 2.3: Lack of footway on Pea Lane.

Source: Mott MacDonald

Page 61: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

6 6

2.3 HA4 – Eve’s (Red Route)

2.3.1 Problem

Location: Dennis Road and West Road.

Summary: Pedestrians walking for extended period of time in verge.

It is proposed that pedestrians will walk along a section of Dennis Road and West Road where no footway

is present; pedestrians walking in the verge for extended periods of time may be vulnerable to trips and

falls or choose to walk in the carriageway. A high volume of traffic was observed travelling at high speeds

and visibility is restricted by the highway geometry and vegetation. These factors may result in collisions

between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided on Dennis Road and West Road.

Figure 2.4: Lack of footway on Dennis Road.

Source: Mott MacDonald

Page 62: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

7 7

2.4 H04 – Tednambury (Blue and Red Routes)

2.4.1 Problem

Location: A1184 Layby adjacent to The Gates.

Summary: Excessively overgrown verge.

It is proposed that pedestrians will walk along an existing footway on the eastern side of the A1184. At a

point where the footway follows the back of the layby adjacent to The Gates, excessive vegetation

encroachment prevents the footway from being used. Pedestrians stepping into the carriageway to pass

the vegetation may be struck by passing vehicles increasing the risk of personal injury.

Recommendation

It is recommended that suitable vegetation clearance is undertaken at this location.

Figure 2.5: Overgrown footway along back of layby.

Source: Mott MacDonald

Page 63: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

8 8

2.5 H05 – Pattens

The Audit Team did not identify any road safety related issues associated with the scheme.

2.6 H06 – Gilston

The Audit Team did not identify any road safety related issues associated with the scheme.

2.7 H07 – Twyford Road

The Audit Team did not identify any road safety related issues associated with the scheme.

2.8 H09 – Fowlers

The Audit Team did not identify any road safety related issues associated with the scheme.

2.9 T01 – No 131

The Audit Team did not identify any road safety related issues associated with the scheme.

2.10 T05 – Howells Farm

2.10.1 Problem

Location: Southend Road / High Road roundabouts.

Summary: Increase in conflict points between pedestrians and vehicles.

The proposed diversion directs pedestrians across a residential service road junction on High Road before

guiding them across another access on Southend Road which provides access to a garage and petrol

station directly from the roundabout. The route then directs pedestrians onto a grassed island. Each of

these crossings increases the potential for conflict between pedestrians and vehicles particularly at the

roundabout where vehicles can exit from different angles.

Recommendation

It is recommended that the diversion utilises the existing footway that runs between High Road service

road and Southend Road away from the two roundabouts. This removes the need for pedestrians to cross

the carriageway, and the potential for conflict between pedestrians and vehicles.

Page 64: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

9 9

2.10.2 Problem

Location: Southend Road.

Summary: Lack of footway potentially resulting in conflict between pedestrians and vehicles.

The available verge width on Southend Road appeared restricted which could force pedestrians into the

carriageway where they are at risk of collisions with vehicles. A cycleway is also present on Southend

Road and cyclists may swerve to avoid pedestrians in the carriageway potentially resulting in conflict either

between pedestrians and cyclists or between cyclists and vehicles.

Recommendation

It is recommended that a suitable footway are provided along Southend Road.

Figure 2.6: Restricted verge width.

Source: Mott MacDonald

Page 65: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

10 10

2.10.3 Problem

Location: High Road.

Summary: Incomplete footway provision.

The footway along the western side of High Road is incomplete in the vicinity of Fobbing Level Crossing.

As such, pedestrian will either continue along the verge or cross unnecessarily to the eastern side before

crossing back again. Both scenarios increase the risk of trips and falls or collisions with passing vehicles.

Recommendation

It is recommended that an additional section of footway is provided on the western side of High Road to

the north of the railway, to remove the incomplete section of footway.

Figure 2.7: Incomplete footway.

Source: Mott MacDonald

Page 66: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

11 11

We certify that this audit has been carried out in accordance with the Highways England Departmental

Standard HD 19/15.

Audit Team Leader

T J Blaney BSc (Hons), CMILT, MCIHT, MSoRSA

Signed:

Date: 9th August 2016

Principal Road Safety Engineer

Mott MacDonald

35 Newhall Street

Birmingham

B3 3PU

Audit Team Member

R J Collins BA (Hons), MSc

Signed:

Date: 9th August 2016

Senior Road Safety Engineer

Mott MacDonald

9 Portland Street

Manchester

M1 3BE

3 Audit Team Statement

Page 67: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

12 12

Appendices

Appendix A. List of Submitted Documents _________________________________________________________ 13 Appendix B. Key Plans ________________________________________________________________________ 14

Page 68: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

13 13

Table A.1: Drawings

Drawing Rev Title

MMD-367515-H04-GEN-002 Tednambury

MMD-367515-H05-GEN-002 Pattens

MMD-367515-H06-GEN-002 Gilston

MMD-367515-H07-GEN-002 Twyford Road

MMD-367515-H09-GEN-002 Fowlers

MMD-367515-HA3-GEN-002 Manor Farm

MMD-367515-HA4-GEN-002 Eve’s

MMD-367515-T01-GEN-002 No Name Number 131

MMD-367515-T05-GEN-002 Howells Farm

Source: Mott MacDonald, Sheffield

Appendix A. List of Submitted Documents

Page 69: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

14

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

Appendix B. Key Plans

2.1.1

Page 70: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

15

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

2.3.1

2.2.1

2.2.2

Page 71: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

16

Transport & Works Act Order (TWAO) Anglia Route GRIP 2 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

2.4.1

Page 72: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

17

Transport & Works Act Order (TWAO) Anglia Route GRIP 1 Review Havering, Hertfordshire, & Thurrock Stage 1 Road Safety Audit

2.10.1

2.10.3

2.10.2

Page 73: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

7

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix C Document Review Notice(DRN 025)

Page 74: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

DRN No: 148339 DRN025

Page 1 of 3 Document Review Notice (DRN)

Form Ref NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Project Number: 148339 Project Name: Anglia LC Reduction Strategy Phase 1 & 2

Project Manager: Natasha Davison Principal Contractor: Mott MacDonald Group Ltd

Engineering Deliverable Owner: Mott MacDonald Group Ltd CEM Name: Jason Smith

Submission Discipline: Other CRE Name: Document Number: 367516/RPT016 Revision No: A Document Title: Essex Stage 1 RSA Report. GRIP: 2 NR DPE Name: Andy Kenning CSM Significant: No Document Transmittal/Submission No: via email Date Received: 18-08-2016 Date Return Required: 01-09-2016 REVIEWERS:- DRN No: 148339 DRN025 DRN Date: 531-08-2016 Name Position Discipline Signature Andy Kenning DPE Signalling - (Lead) Natasha Davision Project Manager Level Crossings Isaac Adjei Commercial Manager Level Crossings DISTRIBUTION LIST (of completed review):- Name Position Action Required Jason Smith Project Manager (Motts) Manager response J Castle Document approver (Motts) Provide response Document Details: PDF Source Data Two Dimensional Model Number: 367516/Rpt016 Document Title: Essex Stage 1 Rsa Report. Document URL: Revision: A DOCUMENT REVIEW:- Risk Review Level: Detailed

Overall DRN Category

Rejected Non-compliant to contract

Accepted Accepted with Amendments

Not Accepted Revise & Resubmit

3 0 1 2 3 Acceptance of these documents by Network Rail is not be deemed as validation of the submission, nor does it infer fitness for

purpose. Network Rail does not accept any liability for the submission. Any changes to the documents should be undertaken in accordance with change control procedures adopted by individual

contracting organisations. Such variations are required to be formally recorded and evidence should accompany any resubmission. Without relieving the originating organisation of their contractual responsibilities my comments are as follows:

• Overall DRN Category 0 rejected and a category 3 non acceptance requires the whole document(s) to be revised and resubmitted to address the comments. Prior to any re-work a way forward shall be agreed between supplier and the Designated Project Engineer

• Overall DRN Category 2 acceptance with amendments requires the appropriate responses with additional information to be submitted to address the comments

• Comment type 0 is used to capture comments if the submission is an overall DRN Category 0 • Comment types 2A, 2B, 3A and 3B require a written response & Comment type 4 is for information only • Comment type 5 is used to identify an aspect of a submission which shows a ‘Safe by Design’ feature

For comments types 2 or 3 a suffix is added to the comment type: A) Quality of Supplier’s submission or B) Client preference/changes.

**Issued By: Andy Kenning Signature: Date: 27-09-16 DRN ACCEPTANCE AND/OR CLOSED OUT (including Supplier’s responses):-

**Closed By: Signature: Date:

**Only to be signed by the Project Designated Project Engineer or person with such formally recorded delegated authority. Review comments to be returned to Supplier via control process agreed between the Project Manager and Supplier.

Andy Kenning

Andy Kenning

Page 75: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Page 2 of 4 Document Review Notice (DRN) DRN No: 148339 DRN025

Form Reference NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Network Rail (NR) Supplier NR

No Comments By Type Integration

Activity Comment Accepted

Responses By Response Accepted *

1 It is a shame that the RSA reports do not build on the previous reports produced in GRIP1 and we now have 2 reports with different numbers both saying Essex RSA Stage1 report. I would have expected the GRIP1 reports to have been up versioned and that way there would have been a full audit history visible to readers. I believe NR will be receiving a 'Designers Response Report' that pulls both the GRIP1 & 2 reports?

AK 4 Yes Our remit was to undertake the new round of RSAs which we have done and reported. It is normal for RSAs (including groupings) done at different times to be reported separately and contemporaneously. This is because different staff may have been involved and the discrete structure of the report lends itself to this. In the second report we were not revising the previous RSA but were looking at new sites and alternatives, albeit some may have been in proximity to the same level crossing. There is no need to consolidate old reports into new ones. However to help the reader we had provided a table upfront to explain which RSA were included in each of the two reports. The contract and amending CAF do not contain a requirement to consolidate into a single report. We consider our RSA reporting to be acceptable and fully in line with guidance and industry norms.

The Designer's Response will consolidate the GRIP1 and GRIP2 RSA into a single report for easy reference.

SJT

2 Why has the previous grouping of crossings into reports not been perpetuated in this round of reports? Previously there was one report for the Essex (and neighbouring counties) as this matched the way the orders were to be written. This makes reviewing RSAs for this order even more complicated as it involves reviewing 3 reports!

AK 3A Yes Our remit was to undertake the new round of RSAs which we have done and reported. It is normal for RSAs (including groupings) done at different times to be reported separately and contemporaneously. This is because different staff may have been involved and the discrete structure of the report lends itself to this.

The Designer's Response will consolidate

SJT

Page 76: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Page 3 of 4 Document Review Notice (DRN) DRN No: 148339 DRN025

Form Reference NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Network Rail (NR) Supplier NR

No Comments By Type Integration

Activity Comment Accepted

Responses By Response Accepted *

the GRIP1 and GRIP2 RSAs into a single report for all counties included within the Essex TWAO for easy reference.

3 The report references the previous RSA reports version B. Network Rail is only aware of version A on the reports and had no DRN comments on the report. What was the driver to up version the report to version B and why was Network Rail not provided with a copy?

AK 3A Yes This was an error in the document and arose as a second internal MM only revision was produced prior to issue to NR. Only 1 audit report (Rev A) for the previous Grip 1 RSAs has been produced for issue to Network Rail. Report ref 367516/RPT016 (RSA) has been amended (to Rev B)to reflect this. This has also been changed in the Designer's Response document

SJT

4 The report does not acknowledge that the project has moved on and some crossings have been removed from the project. The fact that they are still referenced in this report could confuse the reader. Other reports that have been up versioned have simply stated that the crossing has been removed from the project. The Designers Response Report must take this into account and make it clear which level crossings are being taken forward.

AK 3A Yes Comment added to the designer's response document to state that some crossings were removed from the project prior to Grip stage 2. Where a particular solution has been discounted due to a road safety issue, this has been noted in the designer's response document.

The RSA is intended to be a record of the options considered at the time and is not a live document to be updated as the project progresses. Having a record of alternative options considered provides a robust audit trail and helps demonstrate the design rationale.

SJT

5 This DRN was planned to be issued at the same time as the one for the Designers Response DRN however due to the protracted delivery of the Designers Response Report, it was felt that this DRN should be issued separately.

AK 4 Yes Noted. The Designer's response document will be issued at the same time as this response and the amended RSA report ref 367516/RPT016 Rev B

SJT

To Perform Spelling Check on the Protected Form Click Here: * Click in the last Cell (Column) to add a new row after the selected cell or to delete the selected row

Page 77: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Page 4 of 4 Document Review Notice (DRN) DRN No: 148339 DRN025

Form Reference NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Network Rail (NR) Supplier NR

No Comments By Type Integration

Activity Comment Accepted

Responses By Response Accepted *

END

Page 78: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

8

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix D Document Review Notice(DRN 026)

Page 79: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

DRN No: 148339 DRN026

Page 1 of 4 Document Review Notice (DRN)

Form Ref NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Project Number: 148339 Project Name: Anglia LC Reduction Strategy Phase 1 & 2

Project Manager: Natasha Davison Principal Contractor: Mott MacDonald Group Ltd

Engineering Deliverable Owner: Mott MacDonald Group Ltd CEM Name: Jason Smith

Submission Discipline: Other CRE Name: Document Number: 367516/RPT017 Revision No: A

Document Title: Havering, Hertfordshire & Thurrock Stage 1 RSA Report. GRIP: 2

NR DPE Name: Andy Kenning CSM Significant: No Document Transmittal/Submission No: via email Date Received: 18-08-2016 Date Return Required: 01-09-2016 REVIEWERS:- DRN No: 148339 DRN026 DRN Date: 31-08-2016 Name Position Discipline Signature Andy Kenning DPE Signalling - (Lead) Natasha Davision Project Manager Level Crossings Isaac Adjei Commercial Manager Level Crossings DISTRIBUTION LIST (of completed review):- Name Position Action Required Jason Smith Project Manager (Motts) Manager response J Castle Document approver (Motts) Provide response Document Details: PDF Source Data Two Dimensional Model Number: 367516/Rpt017 Document Title: Havering, Hertfordshire & Thurrock Stage 1 Rsa Report. Document URL: Revision: A DOCUMENT REVIEW:- Risk Review Level: Detailed

Overall DRN Category

Rejected Non-compliant to contract

Accepted Accepted with Amendments

Not Accepted Revise & Resubmit

3 0 1 2 3 Acceptance of these documents by Network Rail is not be deemed as validation of the submission, nor does it infer fitness for

purpose. Network Rail does not accept any liability for the submission. Any changes to the documents should be undertaken in accordance with change control procedures adopted by individual

contracting organisations. Such variations are required to be formally recorded and evidence should accompany any resubmission. Without relieving the originating organisation of their contractual responsibilities my comments are as follows:

• Overall DRN Category 0 rejected and a category 3 non acceptance requires the whole document(s) to be revised and resubmitted to address the comments. Prior to any re-work a way forward shall be agreed between supplier and the Designated Project Engineer

• Overall DRN Category 2 acceptance with amendments requires the appropriate responses with additional information to be submitted to address the comments

• Comment type 0 is used to capture comments if the submission is an overall DRN Category 0 • Comment types 2A, 2B, 3A and 3B require a written response & Comment type 4 is for information only • Comment type 5 is used to identify an aspect of a submission which shows a ‘Safe by Design’ feature

For comments types 2 or 3 a suffix is added to the comment type: A) Quality of Supplier’s submission or B) Client preference/changes.

**Issued By: Andy Kenning Signature: Date: 29-09-16 DRN ACCEPTANCE AND/OR CLOSED OUT (including Supplier’s responses):-

**Closed By: Signature: Date:

Andy Kenning

Andy Kenning

Page 80: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

DRN No: 148339 DRN026

Page 2 of 4 Document Review Notice (DRN)

Form Ref NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

**Only to be signed by the Project Designated Project Engineer or person with such formally recorded delegated authority.

Review comments to be returned to Supplier via control process agreed between the Project Manager and Supplier.

Page 81: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Page 3 of 4 Document Review Notice (DRN) DRN No: 148339 DRN026

Form Reference NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Network Rail (NR) Supplier NR

No Comments By Type Integration

Activity Comment Accepted

Responses By Response Accepted *

1 It is a shame that the RSA reports do not build on the previous reports produced in GRIP1 and we now have 2 reports with different numbers both saying Havering, Hertfordshire, & Thurrock RSA Stage1 report. I would have expected the GRIP1 reports to have been up versioned and that way there would have been a full audit history visible to readers. I believe NR will be receiving a 'Designers Response Report' that pulls both the GRIP1 & 2 reports?

AK 4 Yes Our remit was to undertake the new round of RSAs which we have done and reported. It is normal for RSAs (including groupings) done at different times to be reported separately and contemporaneously. This is because different staff may have been involved and the discrete structure of the report lends itself to this. In the second report we were not revising the previous RSA but were looking at new sites and alternatives, albeit some may have been in proximity to the same level crossing. There is no need to consolidate old reports into new ones. However to help the reader we had provided a table upfront to explain which RSA were included in each of the two reports. The contract and amending CAF do not contain a requirement to consolidate into a single report. We consider our RSA reporting to be acceptable and fully in line with guidance and industry norms.

The Designer's Response will consolidate the GRIP1 and GRIP2 RSA into a single report for easy reference.

SJT

2 Why has the previous grouping of crossings into reports not been perpetuated in this round of reports? Previously there was one report for the Essex (and neighbouring counties) as this matched the way the orders were to be written. This makes reviewing RSAs for this order even more complicated as it involves reviewing 3 reports!

AK 3A Yes Our remit was to undertake the new round of RSAs which we have done and reported. It is normal for RSAs (including groupings) done at different times to be reported separately and contemporaneously. This is because different staff may have been involved and the discrete structure of the report lends itself to this.

The Designer's Response will consolidate

SJT

Page 82: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Page 4 of 4 Document Review Notice (DRN) DRN No: 148339 DRN026

Form Reference NR/L2/INI/02009/F0044 Issue Date 05/09/2015 Issue 8.0

Network Rail (NR) Supplier NR

No Comments By Type Integration

Activity Comment Accepted

Responses By Response Accepted *

the GRIP1 and GRIP2 RSAs into a single report for all counties included within the Essex TWAO for easy reference.

3 HA03 - Based on the RSA comment in the Essex report about E04 - Parndons Mill, it would be well worth while re-drawing the red route to be on only one side of the road, which could lead to further RSA issues being raised due to the ambiguity of the diversion alignment.

AK 2A Yes The stage 2 consultation plan was updated to show no proposed diversion route for HA3 due to the fact that the crossing route was in effect already severed by the M25. The route in question provides part of the solution to HA4 and this route is more clearly explained on the design freeze drawings, which should remove any ambiguity

SJT

4 The report references the previous RSA reports version B. Network Rail is only aware of version A on the reports and had no DRN comments on the report. What was the driver to up version the report to version B and why was Network Rail not provided with a copy?

AK 3A Yes This was an error in the document and arose as a second internal MM only revision was produced prior to issue to NR. Only 1 audit report (Rev A) for the previous Grip 1 RSAs has been produced for issue to Network Rail. Report ref 367516/RPT017 (RSA) has been amended (to Rev B)to reflect this. This has also been changed in the Designer's Response document

SJT

5 This DRN was planned to be issued at the same time as the one for the Designers Response DRN however due to the protracted delivery of the Designers Response Report, it was felt that this DRN should be issued separately.

AK 4 Yes Noted. The Designer's response document will be issued at the same time as this response and the amended RSA report ref 367516/RPT016 Rev B

SJT

To Perform Spelling Check on the Protected Form Click Here: * Click in the last Cell (Column) to add a new row after the selected cell or to delete the selected row

END

Page 83: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

9

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix E Email CorrespondenceDetailing Discrepancy

Page 84: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

1

Tilbrook, Susan J

From: Tilbrook, Susan JSent: 17 November 2016 16:16To: Kenning Andrew ([email protected])Cc: Eddy Nicholas ([email protected]); Davison Natasha

([email protected]); Adjei Isaac ([email protected]);Smith, Jason A; Huntley, Nathan R; Price, Stephen J; Patel, Sandeep;'[email protected]'

Subject: Anglia LX - Essex and Others RSA DRN responses and RSA Designers Response

TrackingTracking: Recipient Delivery

Kenning Andrew([email protected])

Eddy Nicholas ([email protected])

Davison Natasha([email protected])

Adjei Isaac ([email protected])

Smith, Jason A Delivered: 17/11/2016 16:16

Huntley, Nathan R Delivered: 17/11/2016 16:16

Price, Stephen J Delivered: 17/11/2016 16:16

Patel, Sandeep Delivered: 17/11/2016 16:16

'[email protected]'

Andy

The following have been saved to SharePoint:

· 148339 DRN 025 - Essex GRIP2 RSA Report - DRN supplier response (PDF and Word) for report 367516/RPT016 RSA

· 367516RPT016B Essex Stage 1 RSA Revision B - Report RPT016 revision B, note the only change is to correctthe previous erroneous reference to Rev B of the earlier stage RSA report

· 148339 DRN 026 – Havering Herts and Thurrock GRIP2 RSA Report - DRN supplier response (PDF and Word)for report 367516/ RPT017 RSA

· 367516RPT017B Havering, Herts and Thurrock Stage 1 RSA Revision B - Report RPT017 revision B, note theonly change is to correct the previous erroneous reference to Rev B of the earlier stage RSA report

· RPT021A Essex and others ST1 RSA Response Report

They are saved here: Essex and Others RSAs

Kind Regards

Sue TilbrookProjects Director

D +44 (0)114 2283949 T +44 (0)114 [email protected]

Page 85: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

2

Mott MacDonaldMott MacDonald House111 St Mary's RoadSheffield S2 4APUnited Kingdom

Website | Twitter | LinkedIn | Facebook | YouTube

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered office: Mott MacDonald House, 8-10Sydenham Road, Croydon CR0 2EE, United Kingdom

The information contained in this e-mail is intended only for the person or entity to which it is addressed and may containconfidential and/or privileged material. If you are not the intended recipient of this e-mail, the use of this information or anydisclosure, copying or distribution is prohibited and may be unlawful. If you received this in error, please contact the sender anddelete the material from any computer.

Page 86: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

10

Transport & Works Act Order (TWAO) Anglia RouteRamblers Association Rebuttal

Appendix F The updated designersresponse Report

Page 87: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route

Essex Stage 1 Road Safety Audit Response Report

Report Number 367516/RPT021 Revision C

November 2017

Network Rail

Page 88: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 89: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

367516 EST YHE 021 A

C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

17 November 2016

Transport & Works Act Order (TWAO) Anglia Route

Essex Stage 1 Road Safety Audit Response Report

Transport & Works Act Order (TWAO) Anglia Route

Essex Stage 1 Road Safety Audit Response Report

November 2017

Network Rail

Network Rail The Quadrant MK Elder Gate Milton Keynes MK9 1EN

Mott MacDonald, Mott MacDonald House, 111 St Mary's Road, Sheffield S2 4AP, United Kingdom

T +44 (0)114 2761242 W www.mottmac.com

Page 90: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 91: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

Revision Date Originator Checker Approver Description

A B C

18/11/2016 25/11/2016 2/11/2017

Wahiba Jennane Wahiba Jennane Steve Price

Steve Price Steve Price Jason Smith

Sue Tilbrook Sue Tilbrook Jason Smith

First Draft Response to comments Updates for T05, E41, E45, E54, H05

Issue and revision record

Information class: Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

Page 92: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 93: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

Chapter Title Page

1 Introduction 1

2 Items Raised at the Stage 1 Road Safety Audit 4

2.1 E04 – Parndons Mill (August 2016) _____________________________________________________ 4 2.1.1 Problem __________________________________________________________________________ 4 2.2 E05 – Fullers End (Red Route – August 2016) ____________________________________________ 5 2.3 E05 – Fullers End (Blue Route – August 2016) ____________________________________________ 5 2.4 E06 – Elsenham Emergency Hut (Red Route – August 2016) _________________________________ 5 2.5 E06 – Elsenham Emergency Hut (Blue Route – August 2016) ________________________________ 5 2.6 E08 – Henham (GRIP 1 – December 2015) _______________________________________________ 5 2.7 E09 – Elephant (GRIP 1 – December 2015) ______________________________________________ 5 2.8 E09 – Elephant (Red Route – August 2016) ______________________________________________ 5 2.9 E09 – Elephant (Blue Route – August 2016) ______________________________________________ 5 2.10 E09 – Elephant (Green Route – August 2016) _____________________________________________ 6 2.10.1 Problem __________________________________________________________________________ 6 2.11 E10 – Dixies (GRIP 1 – December 2015) _________________________________________________ 7 2.12 E10 – Dixies (Red Route – August 2016) _________________________________________________ 7 2.13 E11 – Windmills (GRIP 1 – December 2015) ______________________________________________ 7 2.13.1 Problem __________________________________________________________________________ 7 2.14 E12 – Wallaces (GRIP 1 – December 2015) ______________________________________________ 7 2.15 E13 – Littlebury Gate House (December 2015 / August 2016) _________________________________ 8 2.15.1 Problem __________________________________________________________________________ 8 2.16 E14 – Church Lane CCTV (LTN1) (GRIP 1 – December 2015) ________________________________ 9 2.17 E16 – Maldon Road (August 2016) _____________________________________________________ 9 2.18 E17 – Boreham (GRIP 1 – December 2015) ______________________________________________ 9 2.18.1 Problem __________________________________________________________________________ 9 2.19 E18 – Noakes (GRIP 1 – December 2015) ______________________________________________ 10 2.19.1 Problem _________________________________________________________________________ 10 2.20 E19 – Potters (GRIP 1 – December 2015) _______________________________________________ 10 2.21 E20 – Snivellers (GRIP 1 – December 2015) _____________________________________________ 10 2.22 E20 – Snivellers (Red Route – August 2016) _____________________________________________ 10 2.23 E21 – Hill House 1 (GRIP 1 – December 2015) ___________________________________________ 10 2.24 E22 – Great Domsey (GRIP 1 – December 2015) _________________________________________ 10 2.25 E24 – Church 1 (August 2016) ________________________________________________________ 11 2.26 E25 – Church 2 (August 2016) ________________________________________________________ 11 2.27 E26 – Barbara Close (GRIP 1 – December 2015) _________________________________________ 11 2.28 E27 – Puddle Dock (GRIP 1 – December 2015) __________________________________________ 11 2.28.1 Problem _________________________________________________________________________ 11 2.29 E27 – Puddle Dock (Red Route – August 2016) __________________________________________ 12 2.30 E27 – Puddle Dock (Blue Route – August 2016) __________________________________________ 12 2.31 E27 – Puddle Dock (Green Route – August 2016) _________________________________________ 12 2.31.1 Problem _________________________________________________________________________ 12 2.32 E28 – Whipps Farmers (GRIP 1 – December 2015) _______________________________________ 13

Contents

Page 94: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

2.32.1 Problem _________________________________________________________________________ 13 2.33 E28 – Whipps Farmers (Blue Route – August 2016) _______________________________________ 13 2.34 E28 – Whipps Farmers (Green Route – August 2016) ______________________________________ 14 2.34.1 Problem _________________________________________________________________________ 14 2.35 E29 – Brown & Tawse (GRIP 1 – December 2015) ________________________________________ 15 2.35.1 Problem _________________________________________________________________________ 15 2.36 E29 – Brown & Tawse (Blue Route – August 2016) ________________________________________ 16 2.37 E29 – Brown & Tawse (Red Route – August 2016) ________________________________________ 16 2.37.1 Problem _________________________________________________________________________ 16 2.38 E30 – Ferry (GRIP 1 – December 2015) ________________________________________________ 17 2.39 E31 – Brickyard Farm (GRIP 1 – December 2015) ________________________________________ 17 2.40 E32 – Woodgrange Close (GRIP 1 – December 2015) _____________________________________ 17 2.41 E33 – Motorbike (Red Route – August 2016) _____________________________________________ 17 2.41.1 Problem _________________________________________________________________________ 17 2.42 E33 – Motorbike (Blue Route – August 2016) ____________________________________________ 18 2.42.1 Problem _________________________________________________________________________ 18 2.43 E34 – Cousins Number 1 (GRIP 1 – December 2015) ______________________________________ 19 2.43.1 Problem _________________________________________________________________________ 19 2.43.2 Problem _________________________________________________________________________ 20 2.44 E38 - Battlesbridge (GRIP 1 – December 2015) __________________________________________ 20 2.45 E40 – Creaksea Place 1 (Red Route – August 2016) ______________________________________ 21 2.46 E40 – Creaksea Place 1 (Blue Route – August 2016) ______________________________________ 21 2.47 E41 – Padget (GRIP 1 – December 2015/ GRIP2 September 2017) ___________________________ 21 2.48 E42 – Sand Pit (GRIP 1 – December 2015) ______________________________________________ 21 2.48.1 Problem _________________________________________________________________________ 21 2.49 E43 – High Elm (GRIP 1 – December 2015) _____________________________________________ 22 2.49.1 Problem _________________________________________________________________________ 22 2.50 E44 – Frating Abbey (Red Route – August 2016) _________________________________________ 23 2.51 E44 – Frating Abbey (Blue Route – August 2016) _________________________________________ 23 2.52 E45 – Great Bentley Station (September 2017) ___________________________________________ 23 2.53 E47 - Bluehouse (GRIP 1 – December 2015) ____________________________________________ 23 2.54 E48 – Wheatsheaf (August 2016) _____________________________________________________ 24 2.55 E49 – Maria Street (August 2016) _____________________________________________________ 24 2.56 E51 – Thornfield Wood (Blue Route – August 2016) _______________________________________ 24 2.57 E51 – Thornfield Wood (Red Route – August 2016) _______________________________________ 24 2.57.1 Problem _________________________________________________________________________ 24 2.58 E52 – Golden Square (GRIP 1 – December 2015) ________________________________________ 25 2.59 E53 – Josselyns (Blue Route – August 2016) ____________________________________________ 25 2.60 E54 – Bures (September 2017) _______________________________________________________ 25 2.61 E55 – Lamarsh Kings Farm (Green Route – August 2016) __________________________________ 25 2.62 E56 – Abbotts (Blue Route – August 2016) ______________________________________________ 25 2.62.1 Problem _________________________________________________________________________ 25 2.63 E56 – Abbotts (Orange Route – August 2016) ____________________________________________ 26 2.64 E57 – Wivenhoe Park (August 2016) ___________________________________________________ 26 2.64.1 Problem _________________________________________________________________________ 26 2.65 HA3 – Manor Farm (August 2016) _____________________________________________________ 27 2.65.1 Problem _________________________________________________________________________ 27

Page 95: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

2.66 HA4 – Eve’s (Blue Route – August 2016) ________________________________________________ 28 2.66.1 Problem _________________________________________________________________________ 28 2.66.2 Problem _________________________________________________________________________ 29 2.67 HA4 – Eve’s (Red Route – August 2016) ________________________________________________ 30 2.67.1 Problem _________________________________________________________________________ 30 2.68 H04 – Tednambury (Blue and Red Routes – August 2016) __________________________________ 31 2.68.1 Problem _________________________________________________________________________ 31 2.69 H05 – Pattens (December 2015 – August 2016 – September 2017) ___________________________ 32 2.70 H06 – Gilston (December 2015 – August 2016) ___________________________________________ 32 2.71 H07 – Twyford Road (August 2016) ____________________________________________________ 32 2.72 H09 – Fowlers (August 2016) _________________________________________________________ 33 2.73 T01 – No 131 (August 2016) _________________________________________________________ 33 2.74 T04 – Jefferies (GRIP 1 – December 2015) ______________________________________________ 33 2.74.1 Problem _________________________________________________________________________ 33 2.75 T05 – Howells Farm (December 2015 / August 2016) ______________________________________ 34 2.75.1 Problem _________________________________________________________________________ 34 2.75.2 Problem _________________________________________________________________________ 34 2.75.3 Problem _________________________________________________________________________ 35 2.76 T05 – Howells Farm (September 2017) _________________________________________________ 36

Appendices 37

Appendix A. Key Plans ________________________________________________________________________ 38 A.1 MMD-367516-E04-GEN-002 _________________________________________________________ 38 A.2 MMD-367516-E09-GEN-002 _________________________________________________________ 38 A.3 MMD-354763-E11-GEN-001 GRIP 1 ___________________________________________________ 38 A.4 MMD-367516-E13-GEN-002 _________________________________________________________ 38 A.5 MMD-354763-E17-GEN-001 GRIP 1 ___________________________________________________ 38 A.6 MMD-354763-E27-GEN-001 GRIP 1 ___________________________________________________ 38 A.7 MMD-367516-E27-GEN-002 _________________________________________________________ 38 A.8 MMD-367516-E28-GEN-002 _________________________________________________________ 38 A.9 MMD-354763-E29-GEN-001 GRIP 1 ___________________________________________________ 38 A.10 MMD-367516-E29-GEN-002 _________________________________________________________ 38 A.11 MMD-367516-E33-GEN-002 _________________________________________________________ 38 A.12 MMD-354763-E34-GEN-001 GRIP 1 ___________________________________________________ 38 A.13 MMD-354763-E42-GEN-001 _________________________________________________________ 38 A.14 MMD-354763-E43-GEN-001 GRIP 1 ___________________________________________________ 38 A.15 MMD-367516-E51-GEN-002 _________________________________________________________ 38 A.16 MMD-367516-E56-GEN-002 _________________________________________________________ 38 A.17 MMD-367516-E57-GEN-002 _________________________________________________________ 38 A.18 MMD-367516-HA3-GEN-002 _________________________________________________________ 38 A.19 MMD-367516-HA4-GEN-002 _________________________________________________________ 38 A.20 MMD-367516-H04-GEN-002 _________________________________________________________ 38 A.21 MMD-354763-T04-GEN-001 GRIP 1 ___________________________________________________ 38 A.22 MMD-354763-T05-GEN-002 GRIP 1 ___________________________________________________ 39 A.23 MMD-367516-T05-GEN-002 _________________________________________________________ 39

Page 96: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

1

This document is the Mott MacDonald design team’s response to independent Stage 1 Road Safety Audits

(RSA) undertaken in December 2015,August 2016 and September 2017 on Network Rail’s level crossing

closure proposals in Essex, Havering, Hertfordshire and Thurrock.

A Stage 1 Road Safety Audit was undertaken in December 2015 and its findings are reported in Document

Ref: 354763/RPT222A. A second Stage 1 Road Safety Audit was undertaken in August 2016 and its

findings are reported in Documents Ref: 367516/RPT016A and 367516/RPT017A. A third Stage 1 Road

Safety Audit was undertaken in September 2017 and its findings are reported in Document Ref: 287864-

TPN-ITD-327-003-A (Thurrock), 287864-TPN-ITD-327-001-A (Essex) and 287864-TPN-ITD-327-005-A

(Hertfordshire).

It should be noted that some crossings proposals that were audited in December 2015 were removed from

the project prior to Grip stage 2. Where a particular solution has been discounted or a proposal has been

removed from the project due to a road safety issue, it is noted in the design team response in section 2 of

this report. Some of the level crossing closure proposals in Essex, Havering, Hertfordshire and Thurrock

some were audited more than once due to the development of an alternative option or amendments to the

previously audited option. The table below lists the level crossing proposals that have been subject to a

stage 1 road safety audit and when the audits were undertaken.

Site December

2015 August

2016 September

2017

E04 – Parndons Mill

E05 – Fullers End ( Red and Blue Routes)

E06 – Elsenham Emergency Hut (Red and Blue Routes)

E08 – Henham

E09 – Elephant

E09 – Elephant (Red, Blue and Green Routes)

E10 – Dixies

E10 – Dixies (Red Route)

E11 – Windmills

E12 – Wallaces

E13 – Littlebury Gate House

E14 – Church Lane CCTV (ltn1)

E16 – Maldon Road

E17 – Boreham

E18 – Noakes

E19 – Potters

E20 – Snivellers

E20 – Snivellers (Red Route)

E21 – Hill House 1

E22 – Great Domsey

E24 – Church 1

E25 – Church 2

1 Introduction

Page 97: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

2

Site December

2015 August

2016 September

2017

E26 – Barbara Close

E27 – Puddle Dock

E27 – Puddle Dock (Red, Blue and Green Routes)

E28 – Whipps Farmers

E28 – Whipps Farmers (Blue and Green Routes)

E29 – Brown and Tawse

E29 – Brown & Tawse (Red and Blue Routes)

E30 – Ferry

E31 – Brickyard Farm

E32 – Woodgrange Close

E33 – Motorbike (Red and Blue Routes)

E34 – Cousins Number 1

E38 – Battlesbridge

E40 – Creaksea Place 1 (Red and Blue Routes)

E41 – Padget

E42 – Sand Pit

E43 – High Elm

E44 – Frating Abbey (Red and Blue Routes)

E45 – Great Bentley Station

E47 - Bluehouse

E48 - Wheatsheaf

E49 – Maria Street

E51 – Thornfield Wood (Red and Blue Routes)

E52 – Golden Square

E53 – Josselyns (Blue Route)

E54 - Bures

E55 – Lamarsh Kings Farm (Green Route)

E56 – Abbotts (Blue and Orange Routes)

E57 – Wivenhoe Park

HA3 – Manor Farm

HA4 – Eve’s (Blue and Red Routes)

H04 – Tednambury (Blue and Red Routes)

H05 – Pattens

H06 – Gilston

H07 – Twyford Road

H09 – Fowlers

T01 – No131

T04 – Jefferies

T05 – Howells Farm

Page 98: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

3

In this revision of the report the following sites were audited again and reasons for this are provided below:

• E41 – Padget: changes to the route to the west including on High Street

• E45 – Great Bentley: design changes

• E54 Bures: design changes

• T05 – Howells: additional route to the west added.

• H05 – Pattens: design changes requiring road walking along Thorley Street

Network Rail is carrying out feasibility studies to explore options for the closure of level crossings

throughout Anglia as part of their on-going commitment to deliver a safer, more efficient and reliable

railway.

The road safety audit reports considered the proposed level crossing closures throughout Essex, Havering,

Hertfordshire and Thurrock. The scheme proposals consisted of indicative (high level) diversion routes as

the result of closures and no formal highway works were designed at this stage. Therefore the road safety

audit reports considered potential road safety problems as a result of the proposed routes and their

interaction with the highway. A detailed description of the proposed diversion routes at each location can

be read in the respective individual level crossing review reports.

Page 99: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

4

This section describes road safety related issues identified by the Audit Team.

2.1 E04 – Parndons Mill (August 2016)

2.1.1 Problem

Location: Elizabeth Way / Herons Wood.

Summary: Unnecessary carriageway crossing and lack of suitable crossing point.

It is proposed that the alternative route will require pedestrians to cross Elizabeth Way to the southern side

and continue along an existing footway. This footway crosses Herons Wood at a point where no

appropriate crossing point is provided. This may result in trips or falls, or conflicts between pedestrians

and vehicles. Furthermore, there is a segregated footway / cycleway along the length of the northern side

of Elizabeth Way that would remove the need for pedestrians to cross any carriageways. Therefore, the

proposed route unnecessarily increases the risk of collisions between crossing pedestrians and vehicles.

Recommendation

It is recommended that the route continues along the northern side of Elizabeth Way.

2 Items Raised at the Stage 1 Road Safety Audit

Figure 2.1: Lack of appropriate crossing facility on Herons Wood.

Source: Mott MacDonald

Page 100: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

5

Design Team Response

Agreed – It is the intention that pedestrians are routed along the footway on the northern side of Elizabeth

Way.

2.2 E05 – Fullers End (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.3 E05 – Fullers End (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.4 E06 – Elsenham Emergency Hut (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.5 E06 – Elsenham Emergency Hut (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.6 E08 – Henham (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.7 E09 – Elephant (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.8 E09 – Elephant (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.9 E09 – Elephant (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 101: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

6

2.10 E09 – Elephant (Green Route – August 2016)

2.10.1 Problem

Location: Debden Road railway bridge.

Summary: Restricted carriageway width over railway bridge.

The carriageway width over the railway bridge narrows to single carriageway with no footway or verge

meaning pedestrians would have to share the carriageway with vehicles. Forward visibility of pedestrians

could be restricted (particularly eastbound) and although vehicles are travelling slowly over the bridge, this

could result in conflict between pedestrians and vehicles.

Figure 2.2: Restricted width on Debden Road over railway line.

Source: Mott MacDonald

Page 102: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

7

Recommendation

It is recommended that measures are provided to either warn motorists of pedestrians within the

carriageway or to further slow vehicles on the approach. However, if suitable remedial measures cannot

be provided then an alternative route should be identified.

Design Team Response

Agreed – Alternative routes have been looked at and suitable remedial measures are being considered in

this location.

2.11 E10 – Dixies (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.12 E10 – Dixies (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.13 E11 – Windmills (GRIP 1 – December 2015)

2.13.1 Problem

Location: London Road / Mutlow Hill Roundabout with Sparrowsend Hill.

Summary: Lighting columns restrict available width with a risk of conflict between pedestrians and vehicles.

The diversion route directs pedestrians along the western verge of London Road. Lighting columns are

located within the verge which could restrict the width available to pedestrians, potentially causing them to

enter the carriageway with a risk of conflict with vehicles.

Recommendation

A suitable verge or footway width should be provided behind the lighting columns.

Design Team Response

Disagree – In the absence of an existing footpath, users would make use of the existing footway on the

opposite side (western side) of London Road and therefore no further provision is proposed. Users could

then make use of the pedestrian island to join the B1052.

2.14 E12 – Wallaces (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 103: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

8

2.15 E13 – Littlebury Gate House (December 2015 / August 2016)

2.15.1 Problem

Location: Littlebury Green Road.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Littlebury Green Road where no footway or

notable verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic

was observed on Littlebury Green Road travelling at high speeds and visibility is restricted by the highway

geometry and vegetation, particularly to the west of Goodwins Close. These factors may result in

collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided.

Design Team Response

Figure 2.3: Lack of verge or footway on Littlebury Green Road.

Source: Mott MacDonald

Page 104: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

9

Agreed – Provision of a footpath to be considered so that pedestrian are able to avoid the road walking.

2.16 E14 – Church Lane CCTV (LTN1) (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.17 E16 – Maldon Road (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.18 E17 – Boreham (GRIP 1 – December 2015)

2.18.1 Problem

Location: Hanson Bulls Lodge Access Road.

Summary: Pedestrians walking within the carriageway at risk of collisions with large vehicles.

The diversion route guides pedestrians along the Bulls Lodge Quarry access road which is heavily used by

large vehicles. Although the access road is wide and has good forward visibility, it is not recommended

that pedestrians walk within the carriageway as any collision with a large vehicle is likely to result in serious

injury to pedestrians.

Figure 2.4: Bulls Lodge Quarry access road.

Source: Mott MacDonald

Page 105: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

10

Recommendation

It is recommended that a compacted footpath is provided and set back from the access road to encourage

pedestrians to stay clear of the carriageway.

Design Team Response

Agreed – This option was not taken forward and an alternative solution was proposed for this level

crossing that removed the need to use Hanson Bulls Lodge Access Road.

2.19 E18 – Noakes (GRIP 1 – December 2015)

2.19.1 Problem

See problems above (2.18 – E17 – Boreham) as proposed diversion route utilises the same quarry access

road.

Design Team Response

Agreed – This option was not taken forward and an alternative solution was proposed for this level

crossing that removed the need to use Hanson Bulls Lodge Access Road.

2.20 E19 – Potters (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.21 E20 – Snivellers (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.22 E20 – Snivellers (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.23 E21 – Hill House 1 (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.24 E22 – Great Domsey (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

Page 106: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

11

2.25 E24 – Church 1 (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.26 E25 – Church 2 (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.27 E26 – Barbara Close (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.28 E27 – Puddle Dock (GRIP 1 – December 2015)

2.28.1 Problem

Location: Warley Street railway bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

The carriageway on Warley Street narrows over the railway bridge and only a narrow hardstanding (<0.5m)

is present which would force pedestrians to walk within the carriageway. Traffic volumes and speeds were

high and pedestrians walking in the carriageway would be at risk of collisions with vehicles, which would

likely result in high severity injuries.

Figure 2.5: Reduced widths over railway bridge.

Source: Mott MacDonald

Page 107: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

12

Recommendation

Suitable footway widths should be provided over the railway bridge otherwise an alternative route should

be identified.

Design Team Response

Agreed – An appropriate width footway could not be achieved over the bridge and therefore an alternative

solution (red route referred to in 2.29 below) is under consideration. However, if this is found to be

unsuitable, this level crossing will be removed from the project.

2.29 E27 – Puddle Dock (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.30 E27 – Puddle Dock (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.31 E27 – Puddle Dock (Green Route – August 2016)

2.31.1 Problem

Location: St Marys Lane.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry.

These factors may result in collisions between pedestrians and vehicles.

Figure 2.6: Lack of verge or footway on St Marys Lane.

Page 108: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

13

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Design Team Response

Agreed – Therefore an alternative solution (red route referred to in 2.29 above) is under consideration.

However, if this is found to be unsuitable, this level crossing will be removed from the project.

2.32 E28 – Whipps Farmers (GRIP 1 – December 2015)

2.32.1 Problem

See problem above (2.28 – E27 – Puddle Dock) as proposed diversion route utilises the same highway.

Design Team Response

Agreed – An appropriate width footway could not be achieved over the bridge and therefore alternative

solutions were taken forward for consideration.

2.33 E28 – Whipps Farmers (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

Source: Mott MacDonald

Page 109: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

14

2.34 E28 – Whipps Farmers (Green Route – August 2016)

2.34.1 Problem

Location: St Marys Lane.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry.

These factors may result in collisions between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Figure 2.7: Lack of verge or footway on St Marys Lane.

Source: Mott MacDonald

Page 110: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

15

Design Team Response

Agreed – The route was dropped in favour of an alternative solution that reduced the level of road walking.

2.35 E29 – Brown & Tawse (GRIP 1 – December 2015)

2.35.1 Problem

Location: St Marys Lane where it joins with the existing footpath.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

On St Marys Lane to the east of the existing footpath no verge is present and pedestrians would have to

walk in the carriageway. A high volume of traffic was observed on St Marys Lane travelling at high speeds

and visibility is restricted around the bend. These factors could result in conflict between pedestrians and

vehicles.

Recommendation

A suitable footway should be provided otherwise an alternative route should be identified.

Figure 2.8: Lack of verge on St Marys Lane.

Source: Mott MacDonald

Page 111: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

16

Design Team Response

Agreed – An appropriate width footpath could not be achieved. The route was amended to provide a

suitable off-road footpath to the south of Saint Mary’s Road as a safer alternative.

2.36 E29 – Brown & Tawse (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.37 E29 – Brown & Tawse (Red Route – August 2016)

2.37.1 Problem

Location: St Marys Lane Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of St Marys Lane where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on St Marys Lane travelling at high speeds and visibility is restricted by the highway geometry

and the railway road bridge. These factors may result in collisions between pedestrians and vehicles.

Figure 2.9: Lack of verge or footway on St Marys Lane.

Source: Mott MacDonald

Page 112: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

17

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Design Team Response

Agreed – Due to insufficient highway space the footway could not be provided and the blue route was

progressed instead.

2.38 E30 – Ferry (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.39 E31 – Brickyard Farm (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.40 E32 – Woodgrange Close (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.41 E33 – Motorbike (Red Route – August 2016)

2.41.1 Problem

Location: Pitsea Hall Lane.

Summary: High HGV flow and speed.

It is proposed that pedestrians will walk along a section of Pitsea Hall Lane on the western side of the

carriageway where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. A high number of HGVs generally travelling at excessive speeds were observed on Pitsea

Hall Lane. This may lead to an increased risk of collisions between pedestrians and vehicles.

Figure 2.10: Lack of verge or footway on western side of Pitsea Hall Lane.

Page 113: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

18

Recommendation

It is recommended that suitable crossing facilities are provided to allow pedestrians to cross to the eastern

side and utilise the existing segregated footway / cycleway. Vegetation clearance will need to be untaken

to provide a suitable footway / cycleway width.

Design Team Response

Agreed – A crossing point will be provided.

2.42 E33 – Motorbike (Blue Route – August 2016)

2.42.1 Problem

Location: Pitsea Hall Lane.

Summary: High HGV flow and speed.

It is proposed that pedestrians will walk along a section of Pitsea Hall Lane on the western side of the

carriageway where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. A high number of HGVs generally travelling at excessive speeds were observed on Pitsea

Hall Lane. This may lead to an increased risk of collisions between pedestrians and vehicles.

Source: Mott MacDonald

Figure 2.11: Lack of verge or footway on western side of Pitsea Hall Lane.

Page 114: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

19

Recommendation

It is recommended that suitable crossing facilities are provided to allow pedestrians to cross to the eastern

side and utilise the existing segregated footway / cycleway. Vegetation clearance will need to be untaken

to provide a suitable footway / cycleway width.

Design Team Response

Agreed – A crossing point will be provided.

2.43 E34 – Cousins Number 1 (GRIP 1 – December 2015)

2.43.1 Problem

Location: A120 Underpass.

Summary: Risk of anti-social behaviour.

The proposed diversion will take pedestrians onto a suspended footbridge beneath the railway line and

above the A120. The footbridge will not be overlooked and there is a risk some people may act

inappropriately with potential to throw objects at westbound vehicles on the A120. Such behaviour may

lead to vehicle loss of control and potentially serious collisions.

Recommendation

The footbridge should be enclosed to prevent users interacting with the vehicles on the A120.

Source: Mott MacDonald

Page 115: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

20

Design Team Response

Agreed – However, this proposal was withdrawn due to structural interface issues and this level crossing

removed from the project.

2.43.2 Problem

Location: A120 southern verge.

Summary: Risk of vehicle to pedestrian collisions.

The proposed diversion will run along the southern side of the A120 and it is not clear if this will be on the

A120 side of the embankment or along the agricultural side at the top of the embankment. Pedestrians

walking along the verge are at serious risk of injury in the event of loss of control collisions.

Recommendation

A suitable footway width should be provided behind the barrier and be clear of any obstructions.

Design Team Response

Disagree – Pedestrians would have been routed along the agricultural side and therefore not exposed to

errant vehicles. However, this proposal was withdrawn and this level crossing removed from the project.

2.44 E38 - Battlesbridge (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

Figure 2.12: A120 westbound verge.

Source: Mott MacDonald

Page 116: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

21

2.45 E40 – Creaksea Place 1 (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.46 E40 – Creaksea Place 1 (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.47 E41 – Padget (GRIP 1 – December 2015/ GRIP2 September 2017)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.48 E42 – Sand Pit (GRIP 1 – December 2015)

2.48.1 Problem

Location: Alresford Road.

Summary: Risk of pedestrian trip accidents.

The proposed diversion will run along the north eastern verge of the Arlesford Road and where the wide

verge narrows the surface of the existing narrow verge is uneven with a lower worn area and a raised

unworn area presenting a level difference. The worn area also features numerous pot holes. There is a

risk of pedestrians tripping on the uneven surface and falling into the carriageway, at risk of collisions with

vehicles.

Figure 2.13: Alresford Road north eastern verge.

Page 117: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

22

Recommendation

A suitable level hardstanding should be provided to reduce the risk of pedestrians tripping.

Design Team Response

Agreed – Suitable surfacing will be provided as part of the proposed measures on Alresford Road.

2.49 E43 – High Elm (GRIP 1 – December 2015)

2.49.1 Problem

Location: B1027 Ten Penny Hill.

Summary: Risk of vehicle to pedestrian collisions.

The proposed diversion will guide pedestrians along Ten Penny Hill. Currently there is a footway on the

north east side of Ten Penny Hill which terminates at Wivenhoe Road and a footway is provided on the

south west side of Ten Penny Hill which continues as far as Coach Road, opposite where the proposed

diversion will join Ten Penny Hill. Ten Penny Hill is a high speed road with a posted 50mph speed limit

and is also quite wide. Pedestrians will be vulnerable to collisions with vehicles if required to cross the

road twice to continue their journey.

Source: Mott MacDonald

Page 118: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

23

Recommend

It is recommended that a suitable compacted footpath is provided on the north east side of Ten Penny Hill

to avoid pedestrians having to cross the wide busy road twice.

Design Team Response

Disagree – It is considered that there is a suitable footway on the opposite side of the carriageway.

However, to mitigate the problem of pedestrians crossing Ten Penny Hill, as noted on the Road Safety

Audit, it is proposed to install a suitable pedestrian refuge island at either end of the pedestrian route.

2.50 E44 – Frating Abbey (Red Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.51 E44 – Frating Abbey (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.52 E45 – Great Bentley Station (September 2017)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.53 E47 - Bluehouse (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

Figure 2.14: Ten Penny Hill at the western interface looking south east.

Source: Mott MacDonald

Page 119: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

24

2.54 E48 – Wheatsheaf (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.55 E49 – Maria Street (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.56 E51 – Thornfield Wood (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.57 E51 – Thornfield Wood (Red Route – August 2016)

2.57.1 Problem

Location: Jupe’s Hill Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Jupe’s Hill between Oldhouse Farm and Willow

Cottage where no footway or notable verge is present; this will result in pedestrians walking in the

carriageway. Whilst traffic flows were observed to be low, speeds were excessive with visibility restricted

by a road bridge. These factors may result in collisions between pedestrians and vehicles.

Figure 2.15: Lack of verge or footway on Jupe’s Hill.

Source: Mott MacDonald

Page 120: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

25

Recommendation

It is recommended that a suitable footway is provided or that the Blue Route Option is utilised.

Design Team Response

Agreed – The blue route has been taken forward.

2.58 E52 – Golden Square (GRIP 1 – December 2015)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.59 E53 – Josselyns (Blue Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.60 E54 – Bures (September 2017)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.61 E55 – Lamarsh Kings Farm (Green Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.62 E56 – Abbotts (Blue Route – August 2016)

2.62.1 Problem

Location: Harwich Road / Little Bromley Road junction.

Summary: Lack of crossing facility my result in trips and falls.

It is proposed that diverted pedestrians will utilise the footway on the northern side of Harwich Road and

the carriageway on Little Bromley Road. This will require pedestrians to cross Harwich Road in the vicinity

of its junction with Little Bromley Road. No crossing facilities are provided at this location and crossing

pedestrians may either cross at inappropriate locations or trip on the full height kerb.

Page 121: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

26

Recommendation

It is recommended that an appropriately positioned crossing point is installed on Harwich Road.

Design Team Response

Agreed – To mitigate this problem the route was amended to provide an off-road footpath parallel to the

railway.

2.63 E56 – Abbotts (Orange Route – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.64 E57 – Wivenhoe Park (August 2016)

2.64.1 Problem

Location: Lightship Way / River Colne waterfront.

Summary: Inappropriate interaction between agricultural vehicles and non-motorised users.

Figure 2.16: Lack of crossing point on Harwich Road at its junction with Little Bromley Road.

Source: Mott MacDonald

Page 122: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

27

It is proposed that diverted agricultural vehicles will access land to the west of the railway via Lightship

Way and the River Colne waterfront path. There was a notable presence of vulnerable road users in the

vicinity of Lightship Way whilst the River Colne path is for cyclists and pedestrians. Diverting agricultural

vehicles through this residential area and onto the recreational riverside path may increase the risk of

collisions between large vehicles and vulnerable road users.

Recommendation

It is recommended that agricultural vehicles are not diverted along this route.

Design Team Response

The diversion route may not be suitable for very large machinery and therefore further discussions with the

landowner are being undertaken to ascertain the exact type and frequency of agricultural machinery

movements.

2.65 HA3 – Manor Farm (August 2016)

2.65.1 Problem

Location: Ockendon Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Ockendon Road where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on Ockendon Road travelling at high speeds despite the 40mph speed limit and visibility is

restricted by the highway geometry and the railway road bridge. These factors may result in collisions

between pedestrians and vehicles.

Figure 2.17: Lack of verge or footway on Ockendon Road.

Page 123: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

28

Recommendation

It is recommended that a suitable footway is provided. This should extend to Pea Lane with a dropped

kerb provided at a suitable position to allow pedestrians to join the carriageway on Pea Lane.

Design Team Response

Disagree – The level crossing and public right of way are not present on site and therefore there are no

users to undertake the diversion. However, as the route forms part of the diversion for Eve’s crossing,

provision of a field walking route adjacent to Ockendon Road to avoid as much road walking as possible

will be considered.

2.66 HA4 – Eve’s (Blue Route – August 2016)

2.66.1 Problem

Location: Ockendon Road Bridge.

Summary: Narrow road width may lead to conflict between pedestrians and vehicles.

It is proposed that pedestrians will walk along a section of Ockendon Road where no footway or notable

verge is present; this will result in pedestrians walking in the carriageway. A high volume of traffic was

observed on Ockendon Road travelling at high speeds despite the 40mph speed limit and visibility is

restricted by the highway geometry and the railway road bridge. These factors may result in collisions

between pedestrians and vehicles.

Source: Mott MacDonald

Figure 2.18: Lack of verge or footway on Ockendon Road.

Page 124: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

29

Recommendation

It is recommended that a suitable footway is provided. This should extend to Pea Lane with a dropped

kerb provided at a suitable position to allow pedestrians to join the carriageway on Pea Lane.

Design Team Response

The level crossing has very low or no usage and therefore it would be disproportionate to construct the

footway measure given the road and verge width available. However, provision of a field walking route

adjacent to Ockendon Road to avoid as much road walking as possible will be considered.

2.66.2 Problem

Location: Pea Lane.

Summary: Pedestrians walking for extended period of time in verge.

It is proposed that pedestrians will walk along the length of Pea Lane where no footway or notable verge is

present; a high volume of traffic was observed travelling at high speeds and visibility is restricted by the

highway geometry and vegetation. These factors may result in collisions between pedestrians and

vehicles.

Source: Mott MacDonald

Figure 2.19: Lack of footway on Pea Lane.

Page 125: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

30

Recommendation

It is recommended that a suitable footway is provided along Pea Lane or that the Red Route is utilised

taking into consideration issues raised in Section 2.65.

Design Team Response

The level crossing has very low or no users and therefore it would be disproportionate to construct the

footway measure given the road and verge width available. There is available verge width for the

occasional pedestrian to step out of the carriageway into a position of safety as and when a vehicle

passes.

2.67 HA4 – Eve’s (Red Route – August 2016)

2.67.1 Problem

Location: Dennis Road and West Road.

Summary: Pedestrians walking for extended period of time in verge.

It is proposed that pedestrians will walk along a section of Dennis Road and West Road where no footway

is present; pedestrians walking in the verge for extended periods of time may be vulnerable to trips and

falls or choose to walk in the carriageway. A high volume of traffic was observed travelling at high speeds

Source: Mott MacDonald

Page 126: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

31

and visibility is restricted by the highway geometry and vegetation. These factors may result in collisions

between pedestrians and vehicles.

Recommendation

It is recommended that a suitable footway is provided on Dennis Road and West Road.

Design Team Response

Agreed - However, the red route has been discounted and therefore the Road Safety Audit issues have

been removed.

2.68 H04 – Tednambury (Blue and Red Routes – August 2016)

2.68.1 Problem

Location: A1184 Layby adjacent to The Gates.

Summary: Excessively overgrown verge.

It is proposed that pedestrians will walk along an existing footway on the eastern side of the A1184. At a

point where the footway follows the back of the layby adjacent to The Gates, excessive vegetation

encroachment prevents the footway from being used. Pedestrians stepping into the carriageway to pass

the vegetation may be struck by passing vehicles increasing the risk of personal injury.

Figure 2.20: Lack of footway on Dennis Road.

Source: Mott MacDonald

Page 127: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

32

Recommendation

It is recommended that suitable vegetation clearance is undertaken at this location.

Design Team Response

Agreed – Hertfordshire County Council is to be informed of maintenance issues on their footways.

2.69 H05 – Pattens (December 2015 – August 2016 – September 2017)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.70 H06 – Gilston (December 2015 – August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.71 H07 – Twyford Road (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

Figure 2.21: Overgrown footway along back of layby.

Source: Mott MacDonald

Page 128: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

33

2.72 H09 – Fowlers (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.73 T01 – No 131 (August 2016)

The Audit Team did not identify any road safety related issues associated with the scheme.

2.74 T04 – Jefferies (GRIP 1 – December 2015)

2.74.1 Problem

Location: Manorway.

Summary: Risk of vehicle to pedestrian collisions.

The proposed diversion will run along the south eastbound A1014. The footway was inaccessible at the

time of the site visit as it was located behind a large safety barrier and it was therefore difficult to determine

the existing width. If there is insufficient width, there is a risk that pedestrians will be forced to travel within

the carriageway to cross the railway at risk of collisions with vehicles, which were observed to travel at high

speed.

Recommendation

A suitable footway width should be provided behind the barrier and be clear of any obstructions.

Figure 2.22: Proposed footway behind safety barrier.

Source: Mott MacDonald

Page 129: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

34

Design Team Response

Agreed – A suitable footpath will be provided behind the barrier.

2.75 T05 – Howells Farm (December 2015 / August 2016)

2.75.1 Problem

Location: Southend Road / High Road roundabouts.

Summary: Increase in conflict points between pedestrians and vehicles.

The proposed diversion directs pedestrians across a residential service road junction on High Road before

guiding them across another access on Southend Road which provides access to a garage and petrol

station directly from the roundabout. The route then directs pedestrians onto a grassed island. Each of

these crossings increases the potential for conflict between pedestrians and vehicles particularly at the

roundabout where vehicles can exit from different angles.

Recommendation

It is recommended that the diversion utilises the existing footway that runs between High Road service

road and Southend Road away from the two roundabouts. This removes the need for pedestrians to cross

the carriageway, and the potential for conflict between pedestrians and vehicles.

Design Team Response

Agreed – It is the intention that users would be routed along the existing footway that runs between High

Road service road and Southend Road on this section of the diversion route.

2.75.2 Problem

Location: Southend Road.

Summary: Lack of footway potentially resulting in conflict between pedestrians and vehicles.

The available verge width on Southend Road appeared restricted which could force pedestrians into the

carriageway where they are at risk of collisions with vehicles. A cycleway is also present on Southend

Road and cyclists may swerve to avoid pedestrians in the carriageway potentially resulting in conflict either

between pedestrians and cyclists or between cyclists and vehicles.

Figure 2.23: Restricted verge width.

Page 130: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

35

Recommendation

It is recommended that a suitable footway is provided along Southend Road.

Design Team Response

Disagree – Pedestrians currently use the verge to walk along this section of Southend Road and we are

not proposing to change this part of their current journey. However, a new route running west from the

crossing to B1420 on the south side of the railway provides an off road walking route between the footways

on each road to the east and west of the crossing.

2.75.3 Problem

Location: High Road.

Summary: Incomplete footway provision.

The footway along the western side of High Road is incomplete in the vicinity of Fobbing Level Crossing.

As such, pedestrian will either continue along the verge or cross unnecessarily to the eastern side before

crossing back again. Both scenarios increase the risk of trips and falls or collisions with passing vehicles.

Source: Mott MacDonald

Page 131: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

36

Recommendation

It is recommended that an additional section of footway is provided on the western side of High Road to

the north of the railway, to remove the incomplete section of footway.

Design Team Response

Disagree – Pedestrians currently use the footpath walk along this section of Southend Road and we are

not proposing to change this part of their current journey.

2.76 T05 – Howells Farm (September 2017)

The Audit Team did not identify any road safety related issues associated with the scheme.

Figure 2.24: Incomplete footway.

Source: Mott MacDonald

Page 132: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

37

Appendices

Appendix A. Key Plans ________________________________________________________________________ 38

Page 133: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

38

A.1 MMD-367516-E04-GEN-002

A.2 MMD-367516-E09-GEN-002

A.3 MMD-354763-E11-GEN-001 GRIP 1

A.4 MMD-367516-E13-GEN-002

A.5 MMD-354763-E17-GEN-001 GRIP 1

A.6 MMD-354763-E27-GEN-001 GRIP 1

A.7 MMD-367516-E27-GEN-002

A.8 MMD-367516-E28-GEN-002

A.9 MMD-354763-E29-GEN-001 GRIP 1

A.10 MMD-367516-E29-GEN-002

A.11 MMD-367516-E33-GEN-002

A.12 MMD-354763-E34-GEN-001 GRIP 1

A.13 MMD-354763-E42-GEN-001

A.14 MMD-354763-E43-GEN-001 GRIP 1

A.15 MMD-367516-E51-GEN-002

A.16 MMD-367516-E56-GEN-002

A.17 MMD-367516-E57-GEN-002

A.18 MMD-367516-HA3-GEN-002

A.19 MMD-367516-HA4-GEN-002

A.20 MMD-367516-H04-GEN-002

A.21 MMD-354763-T04-GEN-001 GRIP 1

Appendix A. Key Plans

Page 134: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Transport & Works Act Order (TWAO) Anglia Route Essex Stage 1 Road Safety Audit Response Report

367516/EST/YHE/021/A 17 November 2016 C:\Users\til23119\AppData\Roaming\OpenText\OTEdit\EC_EUNAPiMS\c2100822543\R021B Essex ST1 RSA Response Report Rev B.docx

39

A.22 MMD-354763-T05-GEN-002 GRIP 1

A.23 MMD-367516-T05-GEN-002

Page 135: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For In form a tion

GG

GG

G

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

U se of existin g un derpa ss

E04-Parndon Mill

EX|185|72

EX|185|73

EX|185|112

EX|185|69

EX|185|68

EX|185|127

EX|185|71

EX|185|122

EX|185|77

EX|185|119

EX|185|70EX|185|128

EX|185|129

1:3,500Sc a le a t A3 Dra win g No.

Ch'k'd App'dDesc ription DwnDateRev

JASSJPW CP1 16/10/2015

P:\L eeds\Eastern \367516 - GRIP 2-4 - An glia L evel Crossin gs.JAS\GIS\C2 Pla n s\04 MXDs\367516 C2 Proposa ls - Con sultation Style_ New Key.m xd

MMD-367516-E04-GEN-002© Mott Ma c Don a ld L td.T his doc um en t is issued for the pa rty whic h c om m ission ed it a n d for spec ific purposes con n ec ted with the c a ption ed projec t on ly. It should n ot b e relied upon b y a n y other party or used for a n y other purpose.W e a c c ept n o respon sib ility for the con sequen c es of this doc um en t b ein g relied upon b y a n y other party, or b ein g used for a n y other purpose, or con ta in in g a n y error or om ission whic h is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

An glia L X Con sultation Sta ge 1

E Chk

-

¯

© Crown copyright a n d da ta b a se rights 2015 Ordn a n c e Survey 0100040692.T his da ta m ust n ot b e passed on to a n y con tra c tor/s or third pa rties without perm ission from Network Ra il’s OS Ma p T ea ma n d/or without your con tra c tor/s duly sign ed-up to the OS FCDC Con tra c tor L ic en c e (see a tta c hm en t). Sen din g a n d/orsharin g of OS da ta to/with extern a l third-pa rties suc h a s Network Ra il’s Con tra c tors, their delegated a gen ts a n d/orrepresen tatives, without proper govern a n c e will put the Con tra c tor (a n d Network Ra il b y exten sion ) in b rea c h of the OS

2 Brewery W ha rfKen dell StreetL eedsL S10 1JRU n ited Kin gdom +44 (0)113 3946700

0 25 50 75 100Metres

NR Com m en ts JASSJPW CP2 20/01/2016 -

E04 - Parn don MillEssex

Revised Form a t JASSJPW CP3 20/06/2016 -

#Ñ L evel crossin g b ein g disc ussed

Alternative OptionsRed RouteA solid lin e in dic a tes a proposed n ew Pub lic Right of W a y(type to b e deterem in ed).Other lin e types usin g the a b ove route option c oloursin dic a te use of existn g Pub lic Rights of W a y.Right of wa y extin guishm en ts a re still to b e determ in ed a n da re n ot shown for c larity given m ultiple option s.

Existing Public Rights of WayFootpathBridlewa yRestric ted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this lin e is in a c olour, this den otes use b y a route option(see a b ove).

Page 136: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform a tion

GG

G G G GG G G

GGGGGGGGGGGGGG

GG

GG

GGG

GG

G

GG

GG

GG

G

GG

GG

GG

GG

GG

GGGGGGGGGGGGGG

GGG

GG

GGGGGGGGGGGGGGGGGGGGGGGGG

GG

GGGGGGGGGGGGGG

GGG

GG

GG

GG

GGGGGGGGGGG

GG

GG

GGG

GG

GG

GG

GG

G

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GGG

G

GGGGGGGG

GG

GG

G

GG

GG

GG

GG

GGGG

GG

GGGG

GGGGGGGGGGGGGG

GG

G

GG

GG

GGGGGGGG

G

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GGGG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

G

G

G

GGGG

GG

GG

GG

GG

GG

GG

G G

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

GG

G

GG

GG

G

G

GG

GG

G

U se of existing underpa ss

U se of existing roa d b ridge

U se of existing sta tion footb ridge

E09-Elephant

EX|41|23

EX|41|15

EX|41|18

EX|41|14

EX|41|22

EX|41|2

EX|41|4

EX|41|21

EX|41|24

EX|41|17

EX|41|12

EX|41|1

EX|41|20

EX|41|13#1

EX|41|16

EX|41|11

EX|41|13#2

EX|41|29

1:4,000S ca le a t A3 Dra wing No.

Ch'k'd App'dDescription DwnDa teRev

JASS JPWCP1 16/10/2015

P:\Leeds\Ea stern\367516 - GRIP 2-4 - Anglia Level Crossings.JAS \GIS \C2 Pla ns\04 MXDs\367516 C2 Proposa ls - Consulta tion S tyle_ N ew K ey.m xd

MMD-367516-E09-GEN-002© Mott Ma cDona ld Ltd.T his docum ent is issued for the pa rty which com m issioned it a nd for specific purposes connected with the ca ptioned project only. It should not b e relied upon b y a ny other pa rty or used for a ny other purpose.We a ccept no responsib ility for the consequences of this docum ent b eing relied upon b y a ny other pa rty, or b eing used for a ny other purpose, or conta ining a ny error or om ission which is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

Anglia LX Consulta tion S ta ge 1

E Chk

-

¯

© Crown copyright a nd da ta b a se rights 2015 Ordna nce S urvey 0100040692.T his da ta m ust not b e pa ssed onto a ny contra ctor/s or third pa rties without perm ission from N etwork Ra il’s OS Ma p Tea ma nd/or without your contra ctor/s duly signed-up to the OS FCDC Contra ctor Licence (see a tta chm ent). S ending a nd/orsha ring of OS da ta to/with externa l third-pa rties such a s N etwork Ra il’s Contra ctors, their delega ted a gents a nd/orrepresenta tives, without proper governa nce will put the Contra ctor (a nd N etwork Ra il b y extension) in b rea ch of the OS

2 Brewery Wha rfK endell S treetLeedsLS 10 1JRU nited K ingdom +44 (0)113 3946700

0 25 50 75 100Metres

NR Com m ents JASS JPWCP2 20/01/2016 -

E09 - Elepha ntEssex

Newport CPRevised Form a t JASS JPWCP3 16/06/2016 -

#Ñ Level crossing b eing discussed

Alternative OptionsRed RouteBlue RouteGreen RouteA solid line indica tes a proposed new Pub lic Right of Wa y(type to b e deterem ined).Other line types using the a b ove route option coloursindica te use of existng Pub lic Rights of Wa y.Right of wa y extinguishm ents a re still to b e determ ined a nda re not shown for cla rity given m ultiple options.

Existing Public Rights of WayFootpa thBridlewa yRestricted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this line is in a colour, this denotes use b y a route option(see a b ove).

Page 137: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Information

Scale at A3 Drawing No.

Ch'k'd App'dDescription DwnDateRev

JASSJPWCP1 16/10/2015

P:\Leeds\Eastern\354763 - Anglia CP5 Level Crossings\GIS\Plans\Appendix C\Proposals\P1\MMD-354763-LX-GEN Plans - Appendix C1.mxd

MMD-354763-E11-GEN-001© Mott MacDonald Ltd.

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to use by other parties.

Overview

GRIP 1 Proposals

Ordnance Survey data © Crown

copyright and database right 2014

E Chk

-

2 Brewery WharfKendell StreetLeedsLS10 1JRUnited Kingdom

+44 (0)113 3946700

NR Comments JASSJPWCP2 20/01/2016 -

E11 - Windmills

EssexNewport CP

Trees

E11-Windmills

18

28

19

17

4

12

8

Contains OS data © Crown Copyright and database right 2015

#Ñ Current level crossing

#Ñ Other level crossing

Right of way/highway symbology by type

Footpath

Bridleway

Restricted byway

G G GByway open to all traffic

Highway (only shown where a change of use is proposed)

Right of way/highway symbology by proposed status

Creation

Extinguishment

Use of existing

Change of status

No change to existing status

0 25 50 75 100

Metres

¯

1:3,000

© Crown copyright and database rights 2015 Ordnance Survey 0100040692.This data must not be passed onto any contractor/s or third parties without permission from Network Rail’s OS Map Team

and/or without your contractor/s duly signed-up to the OS FCDC Contractor Licence (see attachment). Sending and/or

sharing of OS data to/with external third-parties such as Network Rail’s Contractors, their delegated agents and/or

representatives, without proper governance will put the Contractor (and Network Rail by extension) in breach of the OS

Page 138: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For In form a tion

GG

GG

GG

GG

GG

GG

GG

GG

GG

#ÑE13-Littlebury Gate House

EX|31|3

EX|31|7

EX|31|28

EX|31|29

1:3,500Sc a le a t A3 Dra win g No.

Ch'k'd App'dDesc ription DwnDateRev

JASSJPW CP1 16/10/2015

P:\L eeds\Eastern \367516 - GRIP 2-4 - An glia L evel Crossin gs.JAS\GIS\C2 Pla n s\04 MXDs\367516 C2 Proposa ls - Con sultation Style_ New Key.m xd

MMD-367516-E13-GEN-002© Mott Ma c Don a ld L td.T his doc um en t is issued for the pa rty whic h c om m ission ed it a n d for spec ific purposes con n ec ted with the c a ption ed projec t on ly. It should n ot b e relied upon b y a n y other party or used for a n y other purpose.W e a c c ept n o respon sib ility for the con sequen c es of this doc um en t b ein g relied upon b y a n y other party, or b ein g used for a n y other purpose, or con ta in in g a n y error or om ission whic h is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

An glia L X Con sultation Sta ge 1

E Chk

-

¯

© Crown copyright a n d da ta b a se rights 2015 Ordn a n c e Survey 0100040692.T his da ta m ust n ot b e passed on to a n y con tra c tor/s or third pa rties without perm ission from Network Ra il’s OS Ma p T ea ma n d/or without your con tra c tor/s duly sign ed-up to the OS FCDC Con tra c tor L ic en c e (see a tta c hm en t). Sen din g a n d/orsharin g of OS da ta to/with extern a l third-pa rties suc h a s Network Ra il’s Con tra c tors, their delegated a gen ts a n d/orrepresen tatives, without proper govern a n c e will put the Con tra c tor (a n d Network Ra il b y exten sion ) in b rea c h of the OS

2 Brewery W ha rfKen dell StreetL eedsL S10 1JRU n ited Kin gdom +44 (0)113 3946700

0 25 50 75 100Metres

NR Com m en ts JASSJPW CP2 20/01/2016 -

E13 - L ittleb ury Gate HouseEssex

L ittleb ury CPRevised Form a t JASSJPW CP3 16/06/2016 -

#Ñ L evel crossin g b ein g disc ussed

Alternative OptionsRed RouteA solid lin e in dic a tes a proposed n ew Pub lic Right of W a y(type to b e deterem in ed).Other lin e types usin g the a b ove route option c oloursin dic a te use of existn g Pub lic Rights of W a y.Right of wa y extin guishm en ts a re still to b e determ in ed a n da re n ot shown for c larity given m ultiple option s.

Existing Public Rights of WayFootpathBridlewa yRestric ted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this lin e is in a c olour, this den otes use b y a route option(see a b ove).

Page 139: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform ation

Scale at A3 Drawing No.Ch'k'd Ap p 'dDe scrip tion DwnDateRe v

JASSJPW CP1 16/10/2015

P:\Le e d s\Easte rn\354763 - Anglia CP5 Le ve l Crossings\GIS\Plans\Prop osals\P1\M M D-354763-LX -GEN Plans - Ap p e nd ix C1.m xd

M M D-354763-E17-GEN-001© M ott M acDonald Ltd .This d ocum e nt is issue d for the p arty whic h c om m issione d it and for sp e c ific p urp ose s conne cte d with the cap tione d p roje c t only. It should not b e re lie d up on b y any othe r p arty or use d for any othe r p urp ose .W e ac c e p t no re sp onsib ility for the c onse que nc e s of this d ocum e nt b e ing re lie d up on b y any othe r p arty, or b e ing use d for any othe r p urp ose , or containing any e rror or om ission whic h is d ue to an e rror or om ission in d ata sup p lie d to use b y othe r p artie s.

Ove rvie w

GRIP 1 Prop osals

Ord nanc e Surve y d ata © Crowncop yright and d atab ase right 2014

E Chk

-

2 Bre we ry W harfKe nd e ll Stre e tLe e d sLS10 1JRU nite d Kingd om +44 (0)113 3946700

NR Com m e nts JASSJPW CP2 07/12/2015 -

E17 - Bore hamEsse x

Bore ham CPEX /213/23

E17-Boreham

E18-Noakes

Contains OS d ata © Crown Cop yright and d atab ase right 2015

#Ñ Curre nt le ve l crossing

#Ñ Othe r le ve l crossing in stud y

Type_2Brid le wayFootp ath

Right of way/highway sym b ology b y typ eFootp athBrid le wayRe stricte d b yway

G G GByway op e n to all trafficHighway (only shown whe re a c hange of use is p rop ose d )

Right of way/highway sym b ology b y p rop ose d statusCre ationExtinguishm e ntU se of e xisting Change of statusNo c hange to e xisting status

0 25 50 75 100M e tre s

¯

1:4,000

© Crown cop yright and d atab ase rights 2015 Ord nanc e Surve y 0100040692.This d ata m ust not b e p asse d onto any contractor/s or third p artie s without p e rm ission from Ne twork Rail’s OS M ap Te amand /or without your contractor/s d uly signe d -up to the OS FCDC Contractor Lic e nc e (se e attac hm e nt). Se nd ing and /orsharing of OS d ata to/with e xte rnal third -p artie s suc h as Ne twork Rail’s Contractors, the ir d e le gate d age nts and /orre p re se ntative s, without p rop e r gove rnanc e will p ut the Contractor (and Ne twork Rail b y e xte nsion) in b re ac h of the OS

Page 140: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Fo r Info rm a tio n

Sc a le a t A3 Dra wing No .Ch'k'd App'dDesc riptio n DwnDa teRev

JASSJPW CP1 16/10/2015

P:\L eed s\Ea stern\354763 - Anglia CP5 L evel Cro ssings\GIS\Pla ns\Pro po sa ls\P1\MMD-354763-L X-GEN Pla ns - Append ix C1.m xd

MMD-354763-E27-GEN-001© Mo tt Ma c Do na ld L td .T his d o c um ent is issued fo r the pa rty whic h c o m m issio ned it a nd fo r spec ific purpo ses c o nnec ted with the c a ptio ned pro jec t o nly. It sho uld no t b e relied upo n b y a ny o ther pa rty o r used fo r a ny o ther purpo se.W e a c c ept no respo nsib ility fo r the c o nsequenc es o f this d o c um ent b eing relied upo n b y a ny o ther pa rty, o r b eing used fo r a ny o ther purpo se, o r c o nta ining a ny erro r o r o m issio n whic h is d ue to a n erro r o r o m issio n in d a ta supplied to use b y o ther pa rties.

Overview

GRIP 1 Pro po sa ls

Ord na nc e Survey d a ta © Cro wnc o pyright a nd d a ta b a se right 2014

E Chk

-

2 Brewery W ha rfKend ell StreetL eed sL S10 1JRU nited Kingd o m +44 (0)113 3946700

NR Co m m ents JASSJPW CP2 07/12/2015 -

E27 - Pud d le Do c kEssex

Brentwo o d Distric t (B)EX/272/180

E27-Puddle Dock

E28-Whipps Farmers

Co nta ins OS d a ta © Cro wn Co pyright a nd d a ta b a se right 2015

#Ñ Current level c ro ssing

#Ñ Other level c ro ssing in stud y

Type_2Brid lewa yFo o tpa th

Right o f wa y/highwa y sym b o lo gy b y typeFo o tpa thBrid lewa yRestricted b ywa y

G G GBywa y o pen to a ll tra fficHighwa y (o nly sho wn where a c ha nge o f use is pro po sed )

Right o f wa y/highwa y sym b o lo gy b y pro po sed sta tusCrea tio nExtinguishm entU se o f existing Cha nge o f sta tusNo c ha nge to existing sta tus

0 255075100Metres

¯

1:5,000

© Cro wn c o pyright a nd d a ta b a se rights 2015 Ord na nc e Survey 0100040692.T his d a ta m ust no t b e pa ssed o nto a ny c o ntra c to r/s o r third pa rties witho ut perm issio n fro m Netwo rk Ra il’s OS Ma p T ea ma nd /o r witho ut yo ur c o ntra c to r/s d uly signed -up to the OS FCDC Co ntra c to r L ic enc e (see a tta c hm ent). Send ing a nd /o rsha ring o f OS d a ta to /with externa l third -pa rties suc h a s Netwo rk Ra il’s Co ntra c to rs, their d elega ted a gents a nd /o rrepresenta tives, witho ut pro per go verna nc e will put the Co ntra c to r (a nd Netwo rk Ra il b y extensio n) in b rea c h o f the OS

Page 141: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform a tion

#Ñ#Ñ

Existing B186 roa db ridgelikely to b e unsuita b le for pedestria ndiversion due to width, tra fficvolum es a nd speeds

U se of existing roa d b ridge.S uita b ility for pedestria ns potentia l

rem edia l m ea sures a nd tra ffic m a na gem ent to b e further considered

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

E28-Whipps FarmersE27-Puddle Dock

Brickfields

EX|272|183

EX|272|178

EX|272|179

EX|272|119

EX|272|180

EX|313|119

EX|272|177#2

1:10,000S ca le a t A3 Dra wing No.

Ch'k'd App'dDescription DwnDa teRev

JASS JPWCP1 16/10/2015

\\U K LEEDDC01\Projects\Leeds\Ea stern\367516 - GRIP 2-4 - Anglia Level Crossings.JAS \GIS \C2 Pla ns\04 MXDs\367516 C2 Proposa ls - Consulta tion S tyle_ N ew K ey.m xd

MMD-367516-E27-GEN-002© Mott Ma cDona ld Ltd.T his docum ent is issued for the pa rty which com m issioned it a nd for specific purposes connected with the ca ptioned project only. It should not b e relied upon b y a ny other pa rty or used for a ny other purpose.We a ccept no responsib ility for the consequences of this docum ent b eing relied upon b y a ny other pa rty, or b eing used for a ny other purpose, or conta ining a ny error or om ission which is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

Anglia LX Consulta tion S ta ge 1

E Chk

-

¯

© Crown copyright a nd da ta b a se rights 2015 Ordna nce S urvey 0100040692.T his da ta m ust not b e pa ssed onto a ny contra ctor/s or third pa rties without perm ission from Network Ra il’s OS Ma p Tea ma nd/or without your contra ctor/s duly signed-up to the OS FCDC Contra ctor Licence (see a tta chm ent). S ending a nd/orsha ring of OS da ta to/with externa l third-pa rties such a s Network Ra il’s Contra ctors, their delega ted a gents a nd/orrepresenta tives, without proper governa nce will put the Contra ctor (a nd Network Ra il b y extension) in b rea ch of the OS

2 Brewery Wha rfK endell S treetLeedsLS 10 1JRU nited K ingdom +44 (0)113 3946700

0255075100Metres

NR Com m ents JASS JPWCP2 20/01/2016 -

E27 - Puddle DockEssex

Brentwood District (B)Revised Form a t JASS JPWCP3 21/06/2016 -

#Ñ Level crossing b eing discussed

#Ñ Other level crossing in the project

#Ñ Other level crossings

Alternative OptionsRed RouteBlue RouteGreen RouteA solid line indica tes a proposed new Pub lic Right of Wa y(type to b e deterem ined).Other line types using the a b ove route option coloursindica te use of existng Pub lic Rights of Wa y.Right of wa y extinguishm ents a re still to b e determ ined a nda re not shown for cla rity given m ultiple options.

Existing Public Rights of WayFootpa thBridlewa yRestricted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this line is in a colour, this denotes use b y a route option(see a b ove).

Page 142: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform a tion

#Ñ#Ñ

Existing B186 roa db ridgelikely to b e unsuita b le for pedestria ndiversion due to width, tra fficvolum es a nd speeds

U se of existing roa d b ridge.S uita b ility for pedestria ns potentia l

rem edia l m ea sures a nd tra ffic m a na gem ent to b e further considered

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

##

E27-Puddle DockE28-Whipps Farmers

Brickfields

EX|272|183

EX|272|178

EX|272|179

EX|272|119

EX|272|180

EX|313|119

EX|272|177#2

1:10,000S ca le a t A3 Dra wing No.

Ch'k'd App'dDescription DwnDa teRev

JASS JPWCP1 16/10/2015

\\U K LEEDDC01\Projects\Leeds\Ea stern\367516 - GRIP 2-4 - Anglia Level Crossings.JAS \GIS \C2 Pla ns\04 MXDs\367516 C2 Proposa ls - Consulta tion S tyle_ N ew K ey.m xd

MMD-367516-E28-GEN-002© Mott Ma cDona ld Ltd.T his docum ent is issued for the pa rty which com m issioned it a nd for specific purposes connected with the ca ptioned project only. It should not b e relied upon b y a ny other pa rty or used for a ny other purpose.We a ccept no responsib ility for the consequences of this docum ent b eing relied upon b y a ny other pa rty, or b eing used for a ny other purpose, or conta ining a ny error or om ission which is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

Anglia LX Consulta tion S ta ge 1

E Chk

-

¯

© Crown copyright a nd da ta b a se rights 2015 Ordna nce S urvey 0100040692.T his da ta m ust not b e pa ssed onto a ny contra ctor/s or third pa rties without perm ission from Network Ra il’s OS Ma p Tea ma nd/or without your contra ctor/s duly signed-up to the OS FCDC Contra ctor Licence (see a tta chm ent). S ending a nd/orsha ring of OS da ta to/with externa l third-pa rties such a s Network Ra il’s Contra ctors, their delega ted a gents a nd/orrepresenta tives, without proper governa nce will put the Contra ctor (a nd Network Ra il b y extension) in b rea ch of the OS

2 Brewery Wha rfK endell S treetLeedsLS 10 1JRU nited K ingdom +44 (0)113 3946700

0255075100Metres

NR Com m ents JASS JPWCP2 20/01/2016 -

E28 - Whipps Fa rm ersEssex

Brentwood District (B)Revised Form a t JASS JPWCP3 21/06/2016 -

#Ñ Level crossing b eing discussed

#Ñ Other level crossing in the project

#Ñ Other level crossings

Alternative OptionsRed RouteBlue RouteGreen RouteA solid line indica tes a proposed new Pub lic Right of Wa y(type to b e deterem ined).Other line types using the a b ove route option coloursindica te use of existng Pub lic Rights of Wa y.Right of wa y extinguishm ents a re still to b e determ ined a nda re not shown for cla rity given m ultiple options.

Existing Public Rights of WayFootpa thBridlewa yRestricted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this line is in a colour, this denotes use b y a route option(see a b ove).

Page 143: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Fo r Info rma tio n

Sc a le a t A3 Dra wing No .Ch'k'd App'dDesc riptio n DwnDa teRev

JASSJPW CP1 16/10/2015

P:\L eed s\Ea stern\354763 - Anglia CP5 L evel Cro ssings\GIS\Pla ns\Pro po sa ls\P1\MMD-354763-L X-GEN Pla ns - Append ix C1.mxd

MMD-354763-E29-GEN-001© Mo tt Ma c Do na ld L td .T his d o c ument is issued fo r the pa rty whic h c o mmissio ned it a nd fo r spec ific purpo ses c o nnec ted with the c a ptio ned pro jec t o nly. It sho uld no t b e relied upo n b y a ny o ther pa rty o r used fo r a ny o ther purpo se.W e a c c ept no respo nsib ility fo r the c o nsequenc es o f this d o c ument b eing relied upo n b y a ny o ther pa rty, o r b eing used fo r a ny o ther purpo se, o r c o nta ining a ny erro r o r o missio n whic h is d ue to a n erro r o r o missio n in d a ta supplied to use b y o ther pa rties.

Overview

GRIP 1 Pro po sa ls

Ord na nc e Survey d a ta © Cro wnc o pyright a nd d a ta b a se right 2014

E Chk

-

2 Brewery W ha rfKend ell StreetL eed sL S10 1JRU nited Kingd o m +44 (0)113 3946700

NR Co mments JASSJPW CP2 07/12/2015 -

E29 - Bro wn & T a wseEssex

W est Ho rnd o n CPEX/313/39

!

!!!

!

!

! !

!

!!

!

!!

! !

E29-Brown & Tawse

Co nta ins OS d a ta © Cro wn Co pyright a nd d a ta b a se right 2015

#Ñ Current level c ro ssing

RoW_ThurrockType

Fo o tpa thType_2

Fo o tpa thRight o f wa y/highwa y symb o lo gy b y type

Fo o tpa thBrid lewa yRestricted b ywa y

G G GBywa y o pen to a ll tra fficHighwa y (o nly sho wn where a c ha nge o f use is pro po sed )

Right o f wa y/highwa y symb o lo gy b y pro po sed sta tusCrea tio nExtinguishmentU se o f existing Cha nge o f sta tusNo c ha nge to existing sta tus

0 255075100Metres

¯

1:5,000

© Cro wn c o pyright a nd d a ta b a se rights 2015 Ord na nc e Survey 0100040692.T his d a ta must no t b e pa ssed o nto a ny c o ntra c to r/s o r third pa rties witho ut permissio n fro m Netwo rk Ra il’s OS Ma p T ea ma nd /o r witho ut yo ur c o ntra c to r/s d uly signed -up to the OS FCDC Co ntra c to r L ic enc e (see a tta c hment). Send ing a nd /o rsha ring o f OS d a ta to /with externa l third -pa rties suc h a s Netwo rk Ra il’s Co ntra c to rs, their d elega ted a gents a nd /o rrepresenta tives, witho ut pro per go verna nc e will put the Co ntra c to r (a nd Netwo rk Ra il b y extensio n) in b rea c h o f the OS

Page 144: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform a tion

U se of existing roa d b ridgeBlue route use ofexisting roa d b ridge

E29-Brown & Tawse

EX|313|39

Footpa th 4

Footpa th 142

Footpa th 7

EX|313|41#1

EX|313|41#2

1:5,000S ca le a t A3 Dra wing No.

Ch'k'd App'dDescription DwnDa teRev

JASS JPWCP1 16/10/2015

P:\Leeds\Ea stern\367516 - GRIP 2-4 - Anglia Level Crossings.JAS \GIS \C2 Pla ns\04 MXDs\367516 C2 Proposa ls - Consulta tion S tyle_ N ew K ey.m xd

MMD-367516-E29-GEN-002© Mott Ma cDona ld Ltd.T his docum ent is issued for the pa rty which com m issioned it a nd for specific purposes connected with the ca ptioned project only. It should not b e relied upon b y a ny other pa rty or used for a ny other purpose.We a ccept no responsib ility for the consequences of this docum ent b eing relied upon b y a ny other pa rty, or b eing used for a ny other purpose, or conta ining a ny error or om ission which is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

Anglia LX Consulta tion S ta ge 1

E Chk

-

¯

© Crown copyright a nd da ta b a se rights 2015 Ordna nce S urvey 0100040692.T his da ta m ust not b e pa ssed onto a ny contra ctor/s or third pa rties without perm ission from N etwork Ra il’s OS Ma p Tea ma nd/or without your contra ctor/s duly signed-up to the OS FCDC Contra ctor Licence (see a tta chm ent). S ending a nd/orsha ring of OS da ta to/with externa l third-pa rties such a s N etwork Ra il’s Contra ctors, their delega ted a gents a nd/orrepresenta tives, without proper governa nce will put the Contra ctor (a nd N etwork Ra il b y extension) in b rea ch of the OS

2 Brewery Wha rfK endell S treetLeedsLS 10 1JRU nited K ingdom +44 (0)113 3946700

0 255075100Metres

NR Com m ents JASS JPWCP2 20/01/2016 -

E29 - Brown & T a wseEssex

West Horndon CPRevised Form a t JASS JPWCP3 16/06/2016 -

#Ñ Level crossing b eing discussed

Alternative OptionsRed RouteBlue RouteA solid line indica tes a proposed new Pub lic Right of Wa y(type to b e deterem ined).Other line types using the a b ove route option coloursindica te use of existng Pub lic Rights of Wa y.Right of wa y extinguishm ents a re still to b e determ ined a nda re not shown for cla rity given m ultiple options.

Existing Public Rights of WayFootpa thBridlewa yRestricted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this line is in a colour, this denotes use b y a route option(see a b ove).

Page 145: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Fo r Info rma tio n

#ÑE33-Motorbike

Vange Wharf

Pitsea HallEX |279|136

EX |279|156

EX |279|153

EX|279|154

EX|279|222

1:5,000Sc a le a t A3 Dra wing No .

Ch'k'd App'dDesc riptio n DwnDa teRev

JASSJPW CP1 16/10/2015

P:\Leed s\Ea stern\367516 - GRIP 2-4 - Anglia Level Cro ssings.JAS\GIS\C2 Pla ns\04 M X Ds\367516 C2 Pro po sa ls - Co nsulta tio n Style_New Key.mxd

M M D-367516-E33-GEN-002© M o tt M a c Do na ld Ltd .This d o c ument is issued fo r the pa rty whic h c o mmissio ned it a nd fo r spec ific purpo ses c o nnec ted with the c a ptio ned pro jec t o nly. It sho uld no t b e relied upo n b y a ny o ther pa rty o r used fo r a ny o ther purpo se.W e a c c ept no respo nsib ility fo r the c o nsequenc es o f this d o c ument b eing relied upo n b y a ny o ther pa rty, o r b eing used fo r a ny o ther purpo se, o r c o nta ining a ny erro r o r o missio n whic h is d ue to a n erro r o r o missio n in d a ta supplied to use b y o ther pa rties.

Overview

Anglia LX Co nsulta tio n Sta ge 1

E Chk

-

¯

© Cro wn c o pyright a nd d a ta b a se rights 2015 Ord na nc e Survey 0100040692.This d a ta must no t b e pa ssed o nto a ny c o ntra c to r/s o r third pa rties witho ut permissio n fro m Netwo rk Ra il’s OS M a p Tea ma nd /o r witho ut yo ur c o ntra c to r/s d uly signed -up to the OS FCDC Co ntra c to r Lic enc e (see a tta c hment). Send ing a nd /o rsha ring o f OS d a ta to /with externa l third -pa rties suc h a s Netwo rk Ra il’s Co ntra c to rs, their d elega ted a gents a nd /o rrepresenta tives, witho ut pro per go verna nc e will put the Co ntra c to r (a nd Netwo rk Ra il b y extensio n) in b rea c h o f the OS

2 Brewery W ha rfKend ell StreetLeed sLS10 1JRU nited Kingd o m +44 (0)113 3946700

0 255075100M etres

NR Co mments JASSJPW CP2 20/01/2016 -

E33 - M o to rb ikeEssex

Ba sild o n DistrictRevised Fo rma t JASSJPW CP3 16/06/2016 -

#Ñ Level cro ssing b eing d iscussed

#Ñ Other level cro ssings

Alternative OptionsRed Ro uteA so lid line ind ic a tes a pro po sed new Pub lic Right o f W a y(type to b e d eteremined ).Other line types using the a b o ve ro ute o ptio n c o lo ursind ic a te use o f existng Pub lic Rights o f W a y.Right o f wa y extinguishments a re still to b e d etermined a nda re no t sho wn fo r c la rity given multiple o ptio ns.

Existing Public Rights of WayFo o tpa thBrid lewa yRestric ted b ywa y

G G G Bywa y o pen to a ll tra fficHighwa y (where used )If this line is in a c o lo ur, this d eno tes use b y a ro ute o ptio n(see a b o ve).

Page 146: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Information

Scale at A3 Drawing No.

Ch'k'd App'dDescription DwnDateRev

JASSJPWCP1 16/10/2015

P:\Leeds\Eastern\354763 - Anglia CP5 Level Crossings\GIS\Plans\Appendix C\Proposals\P1\MMD-354763-LX-GEN Plans - Appendix C1.mxd

MMD-354763-E34-GEN-001© Mott MacDonald Ltd.

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to use by other parties.

Overview

GRIP 1 Proposals

Ordnance Survey data © Crown

copyright and database right 2014

E Chk

-

2 Brewery WharfKendell StreetLeeds

LS10 1JRUnited Kingdom

+44 (0)113 3946700

NR Comments JASSJPWCP2 20/01/2016 -

E34 - Cousins Number 1

EssexCressing CP

Cousins

Number 2

E34-Cousins Number 1

4

3120

90

22

16

86

34

21

35

Contains OS data © Crown Copyright and database right 2015

#Ñ Current level crossing

#Ñ Other level crossing

Right of way/highway symbology by type

Footpath

Bridleway

Restricted byway

G G GByway open to all traffic

Highway (only shown where a change of use is proposed)

Right of way/highway symbology by proposed status

Creation

Extinguishment

Use of existing

Change of status

No change to existing status

0 25 50 75 100

Metres

¯

1:5,000

© Crown copyright and database rights 2015 Ordnance Survey 0100040692.This data must not be passed onto any contractor/s or third parties without permission from Network Rail’s OS Map Team

and/or without your contractor/s duly signed-up to the OS FCDC Contractor Licence (see attachment). Sending and/or

sharing of OS data to/with external third-parties such as Network Rail’s Contractors, their delegated agents and/or

representatives, without proper governance will put the Contractor (and Network Rail by extension) in breach of the OS

Page 147: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Information

Scale at A3 Drawing No.

Ch'k'd App'dDescription DwnDateRev

JASSJPWCP1 16/10/2015

P:\Leeds\Eastern\354763 - Anglia CP5 Level Crossings\GIS\Plans\Appendix C\Proposals\P1\MMD-354763-LX-GEN Plans - Appendix C1.mxd

MMD-354763-E42-GEN-001© Mott MacDonald Ltd.

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to use by other parties.

Overview

GRIP 1 Proposals

Ordnance Survey data © Crown

copyright and database right 2014

E Chk

-

2 Brewery WharfKendell StreetLeedsLS10 1JRUnited Kingdom

+44 (0)113 3946700

NR Comments JASSJPWCP2 20/01/2016 -

E42 - Sand Pit

EssexElmstead CP

E42-Sand Pit

12

24

7

15

2

13

16

19

Contains OS data © Crown Copyright and database right 2015

#Ñ Current level crossing

Right of way/highway symbology by type

Footpath

Bridleway

Restricted byway

G G GByway open to all traffic

Highway (only shown where a change of use is proposed)

Right of way/highway symbology by proposed status

Creation

Extinguishment

Use of existing

Change of status

No change to existing status

0 25 50 75 100

Metres

¯

1:4,000

© Crown copyright and database rights 2015 Ordnance Survey 0100040692.This data must not be passed onto any contractor/s or third parties without permission from Network Rail’s OS Map Team

and/or without your contractor/s duly signed-up to the OS FCDC Contractor Licence (see attachment). Sending and/or

sharing of OS data to/with external third-parties such as Network Rail’s Contractors, their delegated agents and/or

representatives, without proper governance will put the Contractor (and Network Rail by extension) in breach of the OS

Page 148: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform ation

Scale at A3 Drawing No.Ch'k'd Ap p 'dDe scrip tion DwnDateRe v

JASSJPW CP1 16/10/2015

P:\Le e d s\Easte rn\354763 - Anglia CP5 Le ve l Crossings\GIS\Plans\Prop osals\P1\M M D-354763-LX -GEN Plans - Ap p e nd ix C1.m xd

M M D-354763-E43-GEN-001© M ott M acDonald Ltd .This d ocum e nt is issue d for the p arty whic h c om m issione d it and for sp e c ific p urp ose s conne cte d with the cap tione d p roje c t only. It should not b e re lie d up on b y any othe r p arty or use d for any othe r p urp ose .W e ac c e p t no re sp onsib ility for the c onse que nc e s of this d ocum e nt b e ing re lie d up on b y any othe r p arty, or b e ing use d for any othe r p urp ose , or containing any e rror or om ission whic h is d ue to an e rror or om ission in d ata sup p lie d to use b y othe r p artie s.

Ove rvie w

GRIP 1 Prop osals

Ord nanc e Surve y d ata © Crowncop yright and d atab ase right 2014

E Chk

-

2 Bre we ry W harfKe nd e ll Stre e tLe e d sLS10 1JRU nite d Kingd om +44 (0)113 3946700

NR Com m e nts JASSJPW CP2 07/12/2015 -

E43 - High ElmEsse x

Alre sford CPEX /157/4

E43-High Elm

Contains OS d ata © Crown Cop yright and d atab ase right 2015

#Ñ Curre nt le ve l crossing

Type_2Footp ath

Right of way/highway sym b ology b y typ eFootp athBrid le wayRe stricte d b yway

G G GByway op e n to all trafficHighway (only shown whe re a c hange of use is p rop ose d )

Right of way/highway sym b ology b y p rop ose d statusCre ationExtinguishm e ntU se of e xisting Change of statusNo c hange to e xisting status

0 25 50 75 100M e tre s

¯

1:2,000

© Crown cop yright and d atab ase rights 2015 Ord nanc e Surve y 0100040692.This d ata m ust not b e p asse d onto any contractor/s or third p artie s without p e rm ission from Ne twork Rail’s OS M ap Te amand /or without your contractor/s d uly signe d -up to the OS FCDC Contractor Lic e nc e (se e attac hm e nt). Se nd ing and /orsharing of OS d ata to/with e xte rnal third -p artie s suc h as Ne twork Rail’s Contractors, the ir d e le gate d age nts and /orre p re se ntative s, without p rop e r gove rnanc e will p ut the Contractor (and Ne twork Rail b y e xte nsion) in b re ac h of the OS

Page 149: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For In form a tion

#ÑE51-Thornfield Wood

EX|152|13

EX|152|10

EX|152|14#3

EX|146|24

EX|152|11

EX|146|23

EX|152|12

EX|152|20#1

EX|152|14#2

1:4,000Sc a le a t A3 Dra win g No.

Ch'k'd App'dDesc ription DwnDateRev

JASSJPW CP1 16/10/2015

P:\L eeds\Eastern \367516 - GRIP 2-4 - An glia L evel Crossin gs.JAS\GIS\C2 Pla n s\04 MXDs\367516 C2 Proposals - Con sultation Style_ New Key.m xd

MMD-367516-E51-GEN-002© Mott Ma c Don ald L td.T his doc um en t is issued for the pa rty whic h c om m ission ed it a n d for spec ific purposes con n ec ted with the c a ption ed projec t on ly. It should n ot b e relied upon b y a n y other party or used for a n y other purpose.W e a c c ept n o respon sib ility for the con sequen c es of this doc um en t b ein g relied upon b y a n y other party, or b ein g used for a n y other purpose, or con ta in in g a n y error or om ission whic h is due to a n error or om ission in da ta supplied to use b y other pa rties.

O verview

An glia L X Con sultation Sta ge 1

E Chk

-

¯

© Crown copyright a n d da ta b a se rights 2015 Ordn a n c e Survey 0100040692.T his da ta m ust n ot b e passed on to a n y con tra c tor/s or third pa rties without perm ission from Network Ra il’s OS Ma p T ea ma n d/or without your con tra c tor/s duly sign ed-up to the OS FCDC Con tra c tor L ic en c e (see a tta c hm en t). Sen din g a n d/orsharin g of O S da ta to/with extern al third-pa rties suc h a s Network Ra il’s Con tra c tors, their delegated a gen ts a n d/orrepresen tatives, without proper govern a n c e will put the Con tra c tor (a n d Network Ra il b y exten sion ) in b rea c h of the O S

2 Brewery W ha rfKen dell StreetL eedsL S10 1JRU n ited Kin gdom +44 (0)113 3946700

0 25 50 75 100Metres

NR Com m en ts JASSJPW CP2 20/01/2016 -

E51 - T horn field W oodEssex

W a kes Coln e CPRevised Form a t JASSJPW CP3 15/06/2016 -

#Ñ L evel crossin g b ein g disc ussed

Alternative OptionsRed RouteBlue RouteA solid lin e in dic a tes a proposed n ew Pub lic Right of W a y(type to b e deterem in ed).Other lin e types usin g the a b ove route option c oloursin dic a te use of existn g Pub lic Rights of W a y.Right of wa y extin guishm en ts a re still to b e determ in ed a n da re n ot shown for clarity given m ultiple option s.

Existing Public Rights of WayFootpathBridlewa yRestric ted b ywa y

G G G Bywa y open to all tra fficHighwa y (where used)If this lin e is in a c olour, this den otes use b y a route option(see a b ove).

Page 150: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For In form a tion

U se of existin g roa d b ridge

E56-Abbotts

Norwith

Ardleigh

7

5

4

28

42

10

3

8

22

39

2

11

49

27

29

50

31

1:5,500Sc a le a t A3 Dra win g No.

Ch'k'd App'dDesc ription DwnDateRev

JASSJPW CP1 16/10/2015

P:\L eeds\Eastern \367516 - GRIP 2-4 - An glia L evel Crossin gs.JAS\GIS\C2 Pla n s\04 MXDs\367516 C2 Proposa ls - Con sultation Style_ New Key.m xd

MMD-367516-E56-GEN-002© Mott Ma c Don a ld L td.T his doc um en t is issued for the pa rty whic h c om m ission ed it a n d for spec ific purposes con n ec ted with the c a ption ed projec t on ly. It should n ot b e relied upon b y a n y other party or used for a n y other purpose.W e a c c ept n o respon sib ility for the con sequen c es of this doc um en t b ein g relied upon b y a n y other party, or b ein g used for a n y other purpose, or con ta in in g a n y error or om ission whic h is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

An glia L X Con sultation Sta ge 1

E Chk

-

¯

© Crown copyright a n d da ta b a se rights 2015 Ordn a n c e Survey 0100040692.T his da ta m ust n ot b e passed on to a n y con tra c tor/s or third pa rties without perm ission from Network Ra il’s OS Ma p T ea ma n d/or without your con tra c tor/s duly sign ed-up to the OS FCDC Con tra c tor L ic en c e (see a tta c hm en t). Sen din g a n d/orsharin g of OS da ta to/with extern a l third-pa rties suc h a s Network Ra il’s Con tra c tors, their delegated a gen ts a n d/orrepresen tatives, without proper govern a n c e will put the Con tra c tor (a n d Network Ra il b y exten sion ) in b rea c h of the OS

2 Brewery W ha rfKen dell StreetL eedsL S10 1JRU n ited Kin gdom +44 (0)113 3946700

0 255075100Metres

NR Com m en ts JASSJPW CP2 20/01/2016 -

E56 - Ab b otsEssex

FP27/ FP28 ArdleighRevised Form a t JASSJPW CP3 15/06/2016 -

#Ñ L evel crossin g b ein g disc ussed

#Ñ Other level crossin gs

Alternative OptionsRed RouteBlue RouteGreen RouteOra n ge RouteA solid lin e in dic a tes a proposed n ew Pub lic Right of W a y(type to b e deterem in ed).Other lin e types usin g the a b ove route option c oloursin dic a te use of existn g Pub lic Rights of W a y.Right of wa y extin guishm en ts a re still to b e determ in ed a n da re n ot shown for c larity given m ultiple option s.

Existing Public Rights of WayFootpathBridlewa yRestric ted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this lin e is in a c olour, this den otes use b y a route option(see a b ove).

Page 151: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For In form a tion

GG G G G G

GG G G G G G G G G G

GG

GG

GG

GG

G G G G G G G G G

G

G GG

GG G G G

G G GG

G

#Ñ Close priva te vehic le c rossin gReta in pub lic footpath crossin g

E57-Wivenhoe Park

EX|127|139EX|155|8

EX|127|236

EX|155|7

EX|155|3

EX|127|162

EX|127|130

EX|127|129

EX|127|16

4

EX|162|26

EX|127|234EX|127|138

EX|155|2

EX|127|142

EX|130|3

EX|127|220

EX|130|2

EX|127|140

EX|155|22

EX|127|163

EX|127|143EX|127|144

EX|155|19

EX|127|146

EX|155|4

EX|155|20

1:10,000Sc a le at A3 Dra win g No.

Ch'k'd App'dDescription DwnDateRev

JASSJPW CP1 16/10/2015

\\U KL EEDDC01\Projec ts\L eeds\Eastern \367516 - GRIP 2-4 - An glia L evel Crossin gs.JAS\GIS\C2 Pla n s\04 MXDs\367516 C2 Proposa ls - Con sultation Style_ New Key.m xd

MMD-367516-E57-GEN-002© Mott Ma c Don a ld L td.T his doc um en t is issued for the party whic h com m ission ed it a n d for spec ific purposes c on n ec ted with the c a ption ed projec t on ly. It should n ot b e relied upon b y a n y other party or used for a n y other purpose.W e a c c ept n o respon sib ility for the con sequen c es of this doc um en t b ein g relied upon b y a n y other party, or b ein g used for a n y other purpose, or con ta in in g a n y error or om ission whic h is due to a n error or om ission in da ta supplied to use b y other parties.

Overview

An glia L X Con sultation Sta ge 1

E Chk

-

¯

© Crown copyright a n d da ta b a se rights 2015 Ordn a n c e Survey 0100040692.T his data m ust n ot b e passed on to a n y c on tra c tor/s or third parties without perm ission from Network Ra il’s OS Map T ea ma n d/or without your c on tra c tor/s duly sign ed-up to the OS FCDC Con tra c tor L ic en c e (see a tta c hm en t). Sen din g a n d/orsha rin g of OS da ta to/with extern a l third-parties suc h as Network Ra il’s Con tra c tors, their delega ted a gen ts a n d/orrepresen ta tives, without proper govern a n c e will put the Con tra c tor (a n d Network Ra il b y exten sion ) in b rea c h of the OS

2 Brewery W ha rfKen dell StreetL eedsL S10 1JRU n ited Kin gdom +44 (0)113 3946700

0255075100Metres

NR Com m en ts JASSJPW CP2 20/01/2016 -

E57 - W iven hoe ParkEssex

W iven hoe CPRevised Form at JASSJPW CP3 14/06/2016 -

#Ñ L evel crossin g b ein g disc ussed

Alternative OptionsRed RouteA solid lin e in dic a tes a proposed n ew Pub lic Right of W a y(type to b e deterem in ed).Other lin e types usin g the a b ove route option c oloursin dic a te use of existn g Pub lic Rights of W a y.Right of wa y extin guishm en ts are still to b e determ in ed a n da re n ot shown for c la rity given m ultiple option s.

Existing Public Rights of WayFootpathBridlewa yRestric ted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this lin e is in a c olour, this den otes use b y a route option(see a b ove).

Page 152: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Fo r Info rma tio n

#ÑHA3-Manor Farm

1:3,000Sc a le a t A3 Dra wing No .

Ch'k'd App'dDesc riptio n DwnDa teRev

JASSJPW CP1 16/10/2015

P:\Leed s\Ea stern\367516 - GRIP 2-4 - Anglia Level Cro ssings.JAS\GIS\C2 Pla ns\04 M X Ds\367516 C2 Pro po sa ls - Co nsulta tio n Style_New Key.mxd

M M D-367516-HA3-GEN-002© M o tt M a c Do na ld Ltd .This d o c ument is issued fo r the pa rty whic h c o mmissio ned it a nd fo r spec ific purpo ses c o nnec ted with the c a ptio ned pro jec t o nly. It sho uld no t b e relied upo n b y a ny o ther pa rty o r used fo r a ny o ther purpo se.W e a c c ept no respo nsib ility fo r the c o nsequenc es o f this d o c ument b eing relied upo n b y a ny o ther pa rty, o r b eing used fo r a ny o ther purpo se, o r c o nta ining a ny erro r o r o missio n whic h is d ue to a n erro r o r o missio n in d a ta supplied to use b y o ther pa rties.

Overview

Anglia LX Co nsulta tio n Sta ge 1

E Chk

-

¯

© Cro wn c o pyright a nd d a ta b a se rights 2015 Ord na nc e Survey 0100040692.This d a ta must no t b e pa ssed o nto a ny c o ntra c to r/s o r third pa rties witho ut permissio n fro m Netwo rk Ra il’s OS M a p Tea ma nd /o r witho ut yo ur c o ntra c to r/s d uly signed -up to the OS FCDC Co ntra c to r Lic enc e (see a tta c hment). Send ing a nd /o rsha ring o f OS d a ta to /with externa l third -pa rties suc h a s Netwo rk Ra il’s Co ntra c to rs, their d elega ted a gents a nd /o rrepresenta tives, witho ut pro per go verna nc e will put the Co ntra c to r (a nd Netwo rk Ra il b y extensio n) in b rea c h o f the OS

2 Brewery W ha rfKend ell StreetLeed sLS10 1JRU nited Kingd o m +44 (0)113 3946700

0 25 50 75 100M etres

NR Co mments JASSJPW CP2 20/01/2016 -

HA3 - M a no r Fa rmEssex

FP251 Ha veringRevised Fo rma t JASSJPW CP3 17/06/2016 -

#Ñ Level cro ssing b eing d iscussed

Alternative OptionsRed Ro uteA so lid line ind ic a tes a pro po sed new Pub lic Right o f W a y(type to b e d eteremined ).Other line types using the a b o ve ro ute o ptio n c o lo ursind ic a te use o f existng Pub lic Rights o f W a y.Right o f wa y extinguishments a re still to b e d etermined a nda re no t sho wn fo r c la rity given multiple o ptio ns.

Existing Public Rights of WayFo o tpa thBrid lewa yRestric ted b ywa y

G G G Bywa y o pen to a ll tra fficHighwa y (where used )If this line is in a c o lo ur, this d eno tes use b y a ro ute o ptio n(see a b o ve).

Page 153: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

Fo r Info rma tio n

HA3-Manor Farm

HA4-Eve's

Foo tpa th 1

Fo o tpa th 136

Fo o tpa th 135

Fo o tpa th 254

Fo o tpa th 139

Fo o tpa th 259

Fo o tpa th 210

1:12,000Sc a le a t A3 Dra wing No .

Ch'k'd App'dDesc riptio n DwnDa teRev

JASSJPW CP1 16/10/2015

P:\Leed s\Ea stern\367516 - GRIP 2-4 - Anglia Level Cro ssings.JAS\GIS\C2 Pla ns\04 M X Ds\367516 C2 Pro po sa ls - Co nsulta tio n Style_New Key.mxd

M M D-367516-HA4-GEN-002© M o tt M a c Do na ld Ltd .This d o c ument is issued fo r the pa rty whic h c o mmissio ned it a nd fo r spec ific purpo ses c o nnec ted with the c a ptio ned pro jec t o nly. It sho uld no t b e relied upo n b y a ny o ther pa rty o r used fo r a ny o ther purpo se.W e a c c ept no respo nsib ility fo r the c o nsequenc es o f this d o c ument b eing relied upo n b y a ny o ther pa rty, o r b eing used fo r a ny o ther purpo se, o r c o nta ining a ny erro r o r o missio n whic h is d ue to a n erro r o r o missio n in d a ta supplied to use b y o ther pa rties.

Overview

Anglia LX Co nsulta tio n Sta ge 1

E Chk

-

¯

© Cro wn c o pyright a nd d a ta b a se rights 2015 Ord na nc e Survey 0100040692.This d a ta must no t b e pa ssed o nto a ny c o ntra c to r/s o r third pa rties witho ut permissio n fro m Netwo rk Ra il’s OS M a p Tea ma nd /o r witho ut yo ur c o ntra c to r/s d uly signed -up to the OS FCDC Co ntra c to r Lic enc e (see a tta c hment). Send ing a nd /o rsha ring o f OS d a ta to /with externa l third -pa rties suc h a s Netwo rk Ra il’s Co ntra c to rs, their d elega ted a gents a nd /o rrepresenta tives, witho ut pro per go verna nc e will put the Co ntra c to r (a nd Netwo rk Ra il b y extensio n) in b rea c h o f the OS

2 Brewery W ha rfKend ell StreetLeed sLS10 1JRU nited Kingd o m +44 (0)113 3946700

0255075100M etres

NR Co mments JASSJPW CP2 20/01/2016 -

HA4 - Eve'sEssex

FP252 Ha veringRevised Fo rma t JASSJPW CP3 17/06/2016 -

#Ñ Level cro ssing b eing d iscussed

#Ñ Other level cro ssing in the pro jec t

Alternative OptionsRed Ro uteBlue Ro uteA so lid line ind ic a tes a pro po sed new Pub lic Right o f W a y(type to b e d eteremined ).Other line types using the a b o ve ro ute o ptio n c o lo ursind ic a te use o f existng Pub lic Rights o f W a y.Right o f wa y extinguishments a re still to b e d etermined a nda re no t sho wn fo r c la rity given multiple o ptio ns.

Existing Public Rights of WayFo o tpa thBrid lewa yRestric ted b ywa y

G G G Bywa y o pen to a ll tra fficHighwa y (where used )If this line is in a c o lo ur, this d eno tes use b y a ro ute o ptio n(see a b o ve).

Page 154: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform a tion

#ÑH04-Tednambury

EX|37|38#2

EX|37|41

EX|37|21#1

EX|37|22

S AWBRIDGEWORT H 003

SAWBRIDGEWORT H 004

S AWBRIDGEWORT H 003

1:3,000S ca le a t A3 Dra wing No.

Ch'k'd App'dDescription DwnDa teRev

JASS JPWCP1 16/10/2015

P:\Leeds\Ea stern\367516 - GRIP 2-4 - Anglia Level Crossings.JAS \GIS \C2 Pla ns\04 MXDs\367516 C2 Proposa ls - Consulta tion S tyle_ N ew K ey.m xd

MMD-367516-H04-GEN-002© Mott Ma cDona ld Ltd.T his docum ent is issued for the pa rty which com m issioned it a nd for specific purposes connected with the ca ptioned project only. It should not b e relied upon b y a ny other pa rty or used for a ny other purpose.We a ccept no responsib ility for the consequences of this docum ent b eing relied upon b y a ny other pa rty, or b eing used for a ny other purpose, or conta ining a ny error or om ission which is due to a n error or om ission in da ta supplied to use b y other pa rties.

Overview

Anglia LX Consulta tion S ta ge 1

E Chk

-

¯

© Crown copyright a nd da ta b a se rights 2015 Ordna nce S urvey 0100040692.T his da ta m ust not b e pa ssed onto a ny contra ctor/s or third pa rties without perm ission from N etwork Ra il’s OS Ma p Tea ma nd/or without your contra ctor/s duly signed-up to the OS FCDC Contra ctor Licence (see a tta chm ent). S ending a nd/orsha ring of OS da ta to/with externa l third-pa rties such a s N etwork Ra il’s Contra ctors, their delega ted a gents a nd/orrepresenta tives, without proper governa nce will put the Contra ctor (a nd N etwork Ra il b y extension) in b rea ch of the OS

2 Brewery Wha rfK endell S treetLeedsLS 10 1JRU nited K ingdom +44 (0)113 3946700

0 25 50 75 100Metres

NR Com m ents JASS JPWCP2 20/01/2016 -

H04 - Tedna m b uryHertfordshire

S a wb ridgeworth CPRevised Form a t JASS JPWCP3 20/06/2016 -

#Ñ Level crossing b eing discussed

Alternative OptionsRed RouteBlue RouteGreen RouteOra nge RouteA solid line indica tes a proposed new Pub lic Right of Wa y(type to b e deterem ined).Other line types using the a b ove route option coloursindica te use of existng Pub lic Rights of Wa y.Right of wa y extinguishm ents a re still to b e determ ined a nda re not shown for cla rity given m ultiple options.

Existing Public Rights of WayFootpa thBridlewa yRestricted b ywa y

G G G Bywa y open to a ll tra fficHighwa y (where used)If this line is in a colour, this denotes use b y a route option(see a b ove).

Page 155: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Information

Scale at A3 Drawing No.

Ch'k'd App'dDescription DwnDateRev

JASSJPWCP1 16/10/2015

P:\Leeds\Eastern\354763 - Anglia CP5 Level Crossings\GIS\Plans\Proposals\P1\MMD-354763-LX-GEN Plans - Appendix C1.mxd

MMD-354763-T04-GEN-001© Mott MacDonald Ltd.

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to use by other parties.

Overview

GRIP 1 Proposals

Ordnance Survey data © Crown

copyright and database right 2014

E Chk

-

2 Brewery WharfKendell StreetLeedsLS10 1JRUnited Kingdom

+44 (0)113 3946700

NR Comments JASSJPWCP2 07/12/2015 -

T04 - Jefferies

Thurrock Unitary AuthorityThurrock (B)

T04-Jefferies

Contains OS data © Crown Copyright and database right 2015

#Ñ Current level crossing

RoW_Thurrock

Type

Footpath

Right of way/highway symbology by type

Footpath

Bridleway

Restricted byway

G G GByway open to all traffic

Highway (only shown where a change of use is proposed)

Right of way/highway symbology by proposed status

Creation

Extinguishment

Use of existing

Change of status

No change to existing status

0 25 50 75 100

Metres

¯

1:5,000

© Crown copyright and database rights 2015 Ordnance Survey 0100040692.This data must not be passed onto any contractor/s or third parties without permission from Network Rail’s OS Map Team

and/or without your contractor/s duly signed-up to the OS FCDC Contractor Licence (see attachment). Sending and/or

sharing of OS data to/with external third-parties such as Network Rail’s Contractors, their delegated agents and/or

representatives, without proper governance will put the Contractor (and Network Rail by extension) in breach of the OS

Page 156: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted
Page 157: TRANSPORT AND WORKS ACT 1992 TRANSPORT AND …bailey.persona-pi.com/Public-Inquiries/Essex/NR Dox/nr32-5.pdf · appended to my rebuttal document ref NR32/4/2, which was submitted

For Inform ation

#ÑT05-Howells Farm

Fobbing

1:5,000Scale at A3 Drawing No.

Ch'k'd Ap p 'dDe scrip tion DwnDateRe v

JASSJPW CP1 16/10/2015

P:\Le e d s\Easte rn\367516 - GRIP 2-4 - Anglia Le ve l Crossings.JAS\GIS\C2 Plans\04 M X Ds\367516 C2 Prop osals - Consultation Style .m xd

M M D-354763-T05-GEN-002© M ott M acDonald Ltd .This d ocum e nt is issue d for the p arty whic h c om m issione d it and for sp e c ific p urp ose s conne cte d with the cap tione d p roje c t only. It should not b e re lie d up on b y any othe r p arty or use d for any othe r p urp ose .W e ac c e p t no re sp onsib ility for the c onse que nc e s of this d ocum e nt b e ing re lie d up on b y any othe r p arty, or b e ing use d for any othe r p urp ose , or containing any e rror or om ission whic h is d ue to an e rror or om ission in d ata sup p lie d to use b y othe r p artie s.

Ove rvie w

Anglia LX Consultation Stage 1

E Chk

-

¯

© Crown cop yright and d atab ase rights 2015 Ord nanc e Surve y 0100040692.This d ata m ust not b e p asse d onto any contractor/s or third p artie s without p e rm ission from Ne twork Rail’s OS M ap Te amand /or without your contractor/s d uly signe d -up to the OS FCDC Contractor Lic e nc e (se e attac hm e nt). Se nd ing and /orsharing of OS d ata to/with e xte rnal third -p artie s suc h as Ne twork Rail’s Contractors, the ir d e le gate d age nts and /orre p re se ntative s, without p rop e r gove rnanc e will p ut the Contractor (and Ne twork Rail b y e xte nsion) in b re ac h of the OS

2 Bre we ry W harfKe nd e ll Stre e tLe e d sLS10 1JRU nite d Kingd om +44 (0)113 3946700

0 255075100M e tre s

NR Com m e nts JASSJPW CP2 20/01/2016 -

T05 - Howe lls FarmThurroc k U nitary Authority

Thurroc k (B)

#Ñ Le ve l crossing b e ing d iscusse d

#Ñ Othe r le ve l crossings

Alternative OptionsRe d RouteBlue RouteGre e n Route

A solid line ind ic ate s a p rop ose d ne w Pub lic Right ofW ay (typ e to b e d e te re m ine d ).Othe r line typ e s using the ab ove route op tion c oloursind ic ate use of e xistng Pub lic Rights of W ay.

Existing Public Rights of WayFootp athBrid le wayRe stricte d b yway

G G G Byway op e n to all trafficHighway (whe re use d )

If this line is in a c olour, this d e note s use b y a routeop tion (se e ab ove ).

Re vise d Form at JASSJPW CP3 27/05/2016 -