3Consulting
T Three Poin
Hawthorn Park Enhancement Project
Project Manager: Eric Diehl Report Editor: Jon Keim Project Engineer: Daniel Conley Project Engineer: Andy Bolyard
Hawthorn Park Enhancement Project
Project Background Project Approach Progress to Date Current Work Project’s Future
Direction
ProjectBackground
Location of Hawthorn Park in relation to the State of
Indiana
Property Previously Owned by the Hulman Family
1982 – Land Purchased by Vigo Co. Parks and Recreation Dept.
Burns Lake
National Road Heritage Trail
Client: Mr. William K. Ruble, Superintendent of Vigo Parks and Recreation Dept.
Project Encompasses: water resources, geotechnical, transportation, and environmental
Project’s DesignRequirements
Determine if the Lowering of Burns Lake Dam Hazard Classification is Feasible
Investigate adequacy of Emergency Spillway for Burns Lake
Connect Existing National Road Heritage Trail to Tupelo Shelter
Progress to Date Site and Dam Investigation
Survey Dam & Spillway Codes and Regulations
Indiana Code for Regulation of Dams Indiana Dam Safety Inspection Manual General Guidelines for New Dams and
Improvements to Existing Dams in Indiana AASHTO Guide for the Development of
Bicycle Facilities
Progress to Date
Emergency Spillway Hydrologic Study Hydraulic StudyU.S. Army Corp EngineersHEC-HMS Computer Model
Progress to Date
Hydrologic Study Watershed Delineation SCS Curve Numbers
Land Use Hydrologic Soil Groups
Time of Concentration Design Storm: 6hr PMP Stage Storage Relationships
Progress to Date
Hydrologic Study Watershed Delineation SCS Curve Numbers
Land Use Hydrologic Soil Groups
Time of Concentration Design Storm: 6hr PMP Stage Storage Relationships
Progress to Date
Emergency Action Plan
Chain of Command Keith Ruble Local Authorities
Evacuation Plan Emergency Agencies
State Emergency Management Agency (SEMA)
Progress to Date
Site and Dam Investigation Codes and Regulations Hydrologic Data Collection Hydrologic Modeling Results Emergency Action Plan
Project’s Future Direction
Breach Analysis Using Both Wet and Dry Condition
Trail Layout and Design Riser and Barrel Design Slope Stability Analysis
Project’s FutureDirection
Breach Analysis Computer Modeling Inundation Maps Feasibility of Hazard Classification
Riser and Barrel Design Existing Structure will Degrade in
Future Have Design Ready for Client
Project’s FutureDirection
Trail Layout and Design Connect to Tupelo Shelter and Restroom
Facilities Surface Options Site Preparation
Decision Matrices Trail Option
Criteria Cost Material Layout Accessibility
Riser & Barrel Criteria Cost Materials Size