Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Promoting choice and value for all gas and electricity customers
Dear Colleague,
Transmission Investment Incentives (TII): decision on requests for funding in
2012-13
The Transmission Investment Incentives (TII)1 framework is designed to provide project-
specific, interim funding2 for critical, large-scale investments that the electricity
Transmission Owners (TOs) identify and justify to be required to support achievement of
the Government‟s 2020 renewable energy targets. Our TII work seeks to ensure value for
money for consumers in the short term while keeping a range of investment options open
in the long term. The TOs are National Grid Electricity Transmission plc (NGET), SP
Transmission Ltd (SPTL) and Scottish Hydro Electric Transmission Ltd (SHETL).
The TII framework3 was introduced in April 2010 to provide funding within the current price
control period (TPCR4, which runs to 31 March 2012). It is being extended into 2012-13
under the one-year adapted rollover of TPCR4 (TPCR4 Rollover) in line with the approach
set out in our decision letter of 30 November 20114 (our November 2011 policy
decision). For all projects considered under TII, funding arrangements beyond March 2013
will be addressed as part of our work on the next full transmission price control review,
RIIO-T1, which will take effect on 1 April 2013.
Our work to extend the TII framework includes extending existing TII funding to include the
rollover year, 2012-13. Our default approach is to use the same baseline assumptions on
which the relevant past TII funding decisions were based. By this approach, we will have
funded £545m (2009-10 prices) of additional investment prior to RIIO-T1, over and above
that included in the TPCR4 baseline.
We published a consultation on 15 November 20115 (our November 2011 consultation)
in relation to five further requests under TII for funding in 2012-13. The purpose of this
letter is to set out our decision to fund a further £72m of additional investment
under TII. This increases the total level of investment funded under TII to £617m.
1 For further information on TII, see: http://www.ofgem.gov.uk/Networks/Trans/ElecTransPolicy/CriticalInvestments/InvestmentIncentives/Pages/InvestmentIncentives.aspx 2 By “funding under TII”, we mean efficient cost recovery allowed via a revenue stream calculated under the relevant provisions of the TII framework. These provisions are set out in Special Condition D11 of NGET‟s licence and in Special Condition J12 of the licences of SPTL and SHETL. 3 For more detail, see: Enhanced Transmission Investment Incentives: Final Proposals (Ref 04/10), Jan‟10: http://www.ofgem.gov.uk/Networks/Trans/ElecTransPolicy/TAR/Pages/Traccrw.aspx 4 TII: decisions on extending the policy framework into 2012-13, 30 Nov‟11: http://www.ofgem.gov.uk/Pages/MoreInformation.aspx?docid=29&refer=Networks/Trans/ElecTransPolicy/CriticalInvestments/InvestmentIncentives 5 Transmission Investment Incentives: Update and consultation on requests for funding in 2012-13, 15 Nov‟11:
http://www.ofgem.gov.uk/Pages/MoreInformation.aspx?docid=24&refer=Networks/Trans/ElecTransPolicy/CriticalInvestments/InvestmentIncentives
Direct Dial: 020 7901 7165
Email: [email protected]
Date: 31 January 2012
2 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
To reflect this decision, it will be necessary make appropriate changes to the transmission
licence to specify project-specific funding allowances and associated deliverables. We will
take this forward as part of our licence changes to extend the TII framework to 2012-13.
We published an informal consultation on our initial drafting of those licence changes on 30
November 20116. We are continuing to work with the TOs in developing our final drafting
ahead of issue of the statutory consultation currently planned for February 2012.
We are separately continuing work towards a decision on NGET‟s and SPTL‟s requests for
construction funding under TII for the High Voltage Direct Current (HVDC) component of
the Western HVDC link7. As set out in our November 2011 policy decision letter, any further
requests for funding of works planned to be undertaken before the end of the rollover year
will be considered in the context of RIIO-T1.
Funding requests in scope of November 2011 consultation
This document focuses on five funding requests8 (referred to in our November 2011
consultation and in this document as the current funding requests) received from the
TOs under TII up to the end of August 2011:
Three requests relating to construction works planned to commence in 2012-13:
o Western HVDC link: Hunterston East substation
o Anglo-Scottish Incremental Works: Reconductor Harker-Hutton-
Quernmore
o North Wales: Reconductor Trawsfynydd-Treuddyn
Two requests relating to works with existing TII funding (to end 2011-12) in line
with funding decisions reached in January 2010:
o Western HVDC link: Deeside/ Connah’s Quay substation
o Eastern HVDC link: Pre-construction (excl. onshore works)
Our November 2011 consultation outlined these requests and set out our assessment
process. We sought views on the issues relevant to our assessment of the requests, the
initial views of our consultants (Pöyry) taking into account information provided by the TOs
up to early November 2011, and our process and timescales towards reaching a decision.
Responses to November 2011 consultation
We received three responses to our November 2011 consultation, all of which are non-
confidential. The responses are summarised in Appendix 1.
Assessment of funding requests and funding decisions
We set out below our assessment of each funding request taking into account responses to
our November 2011 consultation, Pöyry‟s recommendations and any relevant past
assessment. We then set out the funding decisions which we have reached in light of our
assessment. In relation to Pöyry‟s recommendations, Appendix 2 of this letter sets out the
criteria against which we asked Pöyry to assess each request, taking relevant past
assessment into account. It also sets out Pöyry‟s views in these areas taking into account
further information provided by the TOs up to the end of November 2011. Where relevant,
Pöyry‟s recommendations also take into account interactions with any funding previously
provided.
6 TII: informal consultation on licence changes to extend the policy framework into 2012-13 (Ref 164/11), Nov‟11 http://www.ofgem.gov.uk/Networks/Trans/ElecTransPolicy/CriticalInvestments/InvestmentIncentives/Pages/InvestmentIncentives.aspx 7 Transmission Investment Incentives (TII): update on Western HVDC Link (“Western Bootstrap”), Nov‟11: http://www.ofgem.gov.uk/Pages/MoreInformation.aspx?docid=20&refer=Networks/Trans/ElecTransPolicy/CriticalInvestments/InvestmentIncentives 8 For more detail on these requests see Appendix 2 of our November 2011 consultation.
3 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Summary of funding decisions
Table 1 below summarises the 2012-13 allowances9 we have determined under TII in
relation to each cost item for which funding was requested, as compared to the allowances
requested by the TO. The default allowances, based on extension of funding decisions
reached in January 2010, are also shown.
Table 1: Funding decisions in relation to current funding requests TO Cost item Default
2012-13
allowance (Jan 2010 decision)10 (£m)
2012-13 allowance
requested by the TO11 (£m)
2012-13 allowance
determined under TII (£m)
Comment
Works planned to commence in 2012-13
SPTL Western HVDC link: Hunterston East substation
N/A 2.6 2.6 Funding provided
NGET Anglo-Scottish Incremental Works: Harker-Hutton-
Quernmore reconductoring
N/A 25.0 25.0 Funding provided
North Wales: Trawsfynydd-Treuddyn reconductoring
N/A 20.2 2.6
Funding provided
(adjusted for TPCR4 funding)
Works with existing TII funding via January 2010 decisions
NGET Western HVDC link: Deeside/ Connah‟s Quay substation
24.5 65.7
65.7
Default superseded
Eastern HVDC link: Pre-construction (excl. onshore works)
0.2 3.4 0.2
Default maintained
Overall, in relation to the above cost items we have determined 2012-13 funding
allowances under TII totalling12 £96.2m, comprising £24.6m of default allowances and
£71.6m in addition to this. The funding allowances we have determined are consistent with
Pöyry‟s recommendations.
Our assessment and funding decisions (our January 2012 funding decisions) are set out
in more detail below. These funding decisions will be reflected in ex ante funding
allowances and associated deliverables within the existing TII framework as extended to
2012-13. We do not consider it necessary to vary any aspects of our TII framework13 for
these cost items. In the majority of cases, the deliverables14 to be set out in the TII funding
provisions15 will reflect the TO plans as of December 2011. The only exception to this is the
Eastern HVDC link pre-construction works, where the deliverables will continue to reflect
the TO plans as of January 2010, given that the default allowance has been maintained.
9 Note: all numbers are specified in 2009-10 price base and have been converted from their source values using
the RPI indexation method set out in http://www.ofgem.gov.uk/Pages/MoreInformation.aspx?docid=117&refer=Networks/Trans/PriceControls/RIIO-T1/ConRes 10 Default 2012-13 allowance, where applicable, is based on extension of existing TII funding using the same assumptions underpinning the original funding decision. 11 Some monetary values have been updated since the November 2011 consultation in line with basing the relevant calculations on data converted from their original source to 2009-10 price base. 12 Aggregate numbers may differ from similar values derived using values in Table 1 - this is due to rounding. 13 As set out in our November 2011 policy decision letter, we retained flexibility to vary aspects of our TII framework when funding individual cost items where we see good reasons to do so. 14 Key project milestones for each year and (where applicable) forecast output measures on completion of planned construction works 15 Project-specific information set out in Annex A of Special Condition D11/J12 of the relevant licence.
4 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Works planned to commence in 2012-13:
SPTL: Hunterston East substation:
We consider that our work on need, scope and timing of the Western HVDC link is
also valid for this project.
Having reviewed the specific plans for this project, we agree that this project should
go ahead at this stage.
Funding decision – We have determined a TII funding allowance for 2012-13 in
line with SPTL‟s latest cost forecast for that year (allowance of £2.6m).
NGET: Harker-Hutton-Quernmore reconductoring:
We consider that the needs case, scope and timing of the overarching Anglo-
Scottish Incremental scheme has been established from previous assessments.
Having reviewed the specific plans for this project, we agree that this project should
go ahead at this stage.
Funding decision - We have determined a TII funding allowance for 2012-13 in
line with NGET‟s latest cost forecast for that year (allowance of £25.0m).
NGET: Trawsfynydd-Treuddyn reconductoring:
Although there is doubt surrounding the needs case and timing of the overarching
North Wales scheme, we note that this sub-project provides incremental capacity in
its own right and that there is further merit in considering it separately because of
asset condition and the imminent need for refurbishment. We agree with our
consultants‟ view that carrying out reconductoring at the same time as
refurbishment represents the „least-regret‟ option.
Having reviewed the specific plans for this project, we agree that this project should
go ahead at this stage.
However, we note that funding for the refurbishment that would otherwise be
required has been previously provided under TPCR4 (£17.5m in 2009-10 prices16),
but that these works did not go ahead. Further, TII is only intended to provide
funding for works not already funded as part of the main price control settlement.
Funding decision - We have determined a TII funding allowance for 2012-13 in
line with NGET‟s latest cost forecast for that year less an adjustment to net off the
allowance previously included in the TPCR4 settlement (£20.2m less £17.5m gives
an allowance of £2.6m)17. We have made this adjustment to protect consumers
from paying twice for a single set of works.
Works with existing TII funding via January 2010 decisions:
NGET: Deeside / Connah’s Quay:
We consider that the changes in design and programme and associated cost
changes are reasonable; and relate to factors not taken into account in the original
decision.
Funding decision - We have determined a TII funding allowance for 2012-13 in
line with NGET‟s request to reflect increased costs over the period from 2010-11 to
2012-13 relative to the cost forecasts on which the January 2010 decisions were
based (allowance of £65.7m in place of default allowance of £24.5m).
NGET: Eastern HVDC link pre-construction:
We share our consultants‟ concerns about the lack of detail and rationale for the
potential changes in scope and timing of the overall Eastern HVDC link scheme, and
the apparent lack of coordination between NGET, SHETL and SPTL in taking this
work forward. It is therefore difficult at this stage to reach a view on the case for
taking forward a multi-terminal design for potential delivery one year earlier than
previously proposed for a point-to-point link.
16 Converted from source data in 2004-05 prices. 17 This is derived using more accurate values - any inconsistencies to one decimal place are due to rounding.
5 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Noting the under-spend against existing TII funding allowances, and in the absence
of more detailed cost information and associated activities, we also have concerns
that some of the cost increases relate to aspects of works already in scope of the
original funding decision.
Overall, we consider that insufficient evidence has been provided in the timescales
for our assessment to enable us to determine any additional funding under TII.
However, this is not to say that the proposed works and associated costs cannot be
justified in light of new evidence and we expect to review this matter further in the
context of RIIO-T1 to the extent that we receive such evidence. We expect this
evidence to include a qualitative and quantitative Cost Benefit Analysis (CBA)
comparing the respective merits of a point-to-point solution (as originally proposed)
versus alternative options including a multi-terminal solution, for a range of
potential delivery dates. We also expect this to include a detailed breakdown of the
works and associated costs that are necessary to finalise the design.
We note that the revenue determined for 2012-13 under the rollover baseline takes
account of aggregate provisional TII allowances (see below) which, for both NGET
and SHETL, incorporate the TOs‟ latest cost forecasts for the Eastern HVDC link.
Therefore both TOs will have sufficient revenue to progress any necessary works in
2012-13 to develop their plans in more detail, in line with their licence obligations,
pending further review in the context of RIIO-T1.
Funding decision - We have determined a 2012-13 funding allowance under TII in
line with the cost forecasts on which the January 2010 decisions were based
(maintaining the default allowance of £0.2m), i.e. no additional TII funding has
been provided over and above the default allowance.
Impact on allowed revenues
As outlined in our November 2011 policy decision, there are interactions between TII and
our TPCR4 Rollover Final Proposals18. We have incorporated an aggregate provisional TII
allowance (based on the TO‟s latest business plan forecasts) as part of setting the baseline
allowances for 2012-13 under the TPCR4 Rollover Final Proposals, and these will form the
basis for revenues in 2012-13.
Any resulting difference in revenue provided via the aggregate provisional TII allowance
compared to final TII allowances across all projects will be „trued-up‟ in RIIO-T1. The
funding allowances set out above under our January 2012 funding decisions will not feed
directly into the revenue calculation for 2012-13, and instead will be reflected in the
adjustment made in RIIO-T1. A further revenue adjustment will be made at a later stage to
reflect the outcome of our capex efficiency review of TII funding.
Any works not funded under TII or the TPCR4 Rollover will be considered in the context of
RIIO-T1. In the meantime we expect the TOs to proceed with the work they consider
appropriate during the rollover year, 2012-13, in line with their general licence obligation19
to develop their networks in an efficient manner. Provided the TOs are able to justify this
work, we will allow efficient cost recovery under RIIO-T1, via funding allowances to be
specified from 2013-14 onwards.
Given the interim nature of TII funding, any differences between the specified deliverables
set out in the TII funding provisions and the actual work undertaken by the TO will be
taken into account alongside any associated differences between funding allowances and
actual spend under TII both within our capex efficiency review of TII funding and in our
consideration of further funding requirements under RIIO-T1. Provided the TO is able, in
18 Transmission Price Control Review 4 (TPCR4) Rollover: Final Proposals - (Ref: 162/11) 28/11/11: http://www.ofgem.gov.uk/Pages/MoreInformation.aspx?docid=75&refer=NETWORKS/TRANS/PRICECONTROLS/TPCR4ROLL-OVER 19 Under the Electricity Act 1989 (“the Act”) the general duties of transmission licensees include the duty, set out in Section 9 of the Act, to “develop and maintain an efficient, co-ordinated and economical system of electricity transmission”.
6 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
that context, to justify any changes in its plans, the TO is not bound to delivering a given
project in the exact manner specified in the relevant TII funding provisions.
We therefore do not think that the context or timing of our funding decision on works
proposed by the TOs should impact on the timely delivery of efficient investment.
Next steps
To reflect this decision, it will be necessary make appropriate changes to the transmission
licence. As discussed above, we will take this forward as part of our licence changes to
extend the TII framework to 2012-13 for which our statutory consultation is currently
planned for February 2012.
As discussed above, we expect the TOs to progress any necessary works in 2012-13 in line
with their general licence obligation to develop their networks in an efficient manner.
Provided the TOs are able to justify this work, we will allow efficient cost recovery via
funding allowances from 2013-14. We expect to review further the Eastern HVDC link in the
context of RIIO-T1, in light of any further evidence provided by the TOs to justify any
additional costs incurred in 2012-13 that are associated with activities beyond the scope of
the TII allowance determined above.
Any questions on this document should be directed, in the first instance, to Cheryl Mundie
(e-mail: [email protected], tel: 0141 331 6003) or to Simon Cran-McGreehin
(e-mail: [email protected], tel: 020 7901 7440).
Yours faithfully,
Hannah Nixon
Acting Senior Partner – Smarter Grids & Governance: Transmission
7 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Appendix 1 – Responses to our November 2011 consultation
We received three responses to our November 2011 consultation, all of which are non-
confidential. This appendix summarises these responses.
TII framework and current assessment process
All three responses commented on aspects of our TII framework or current assessment
process; two had favourable views. One of these commented that Ofgem‟s approach
appeared reasonable and commensurate with requests being made, whilst ensuring
projects are not delayed. Another respondent welcomed Ofgem‟s approach to funding
these decisions, by providing a provisional allowance in the TPCR4 rollover and making
adjustments in RIIO-T1 line with final TII decisions.
One respondent commented on the process for provision of information to consultants.
This respondent also requested clarity on when a final decision would be published.
Specific project assessment
Two respondents commented specifically on the current assessment. One respondent
commented that Ofgem and Pöyry were in the best position to identify whether the funding
requests are economic and efficient, and so deferred to Ofgem‟s recommendations in this
area. The other had specific comments on our assessment of four funding requests.
This respondent supported the views of our consultants on all aspects of two of the funding
requests (Harker-Hutton-Quernmore and Deeside/Connah‟s Quay). They supported Pöyry‟s
views on aspects of the two other projects on which they commented (Trawsfynydd-
Treuddyn and Eastern HVDC pre-construction). With respect to Trawsfynydd-Treuddyn,
they noted the potential overlap between TII and TPCR4 funding. They also noted Pöyry‟s
concerns in respect to Eastern HVDC pre-construction. They stated their belief that the
work proposed to be undertaken in 2012-13 is designed to resolve the uncertainty around
the scope of the overall scheme.
Other issues
One respondent commented on other issues related to TII and interactions with RIIO-T1.
These views are not directly relevant to the decisions contained in this letter. We have
noted these views, and will ensure these are considered in developing policy relevant to
these issues.
8 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Appendix 2 – Consultant views
This Appendix sets out our consultants‟ assessment of the current funding requests. We
have published Pöyry‟s report alongside this decision letter.
As discussed in our November 2011 consultation, in line with previous consultancy reviews
under TII20, we asked Pöyry to provide a detailed assessment (deliverability, design, costs)
of the specific works for which funding is requested, as well as strategic assessment (need
case, scope and timing) of the overall scheme of which those works are a component part.
For requests relating to works with existing TII funding, we also asked Pöyry to review the
justification for the material changes in scope and the associated changes in costs.
Taking into account the relevant past and current assessment set out in our November
consultation, we considered that for certain of the current funding requests some of these
criteria did not require further review by Pöyry. We therefore asked Pöyry to focus their
assessment on the following issues:
The following sections set out Pöyry’s views based on information received as of end
November 2011. Pöyry‟s views on each of the criteria are summarised by a “traffic light”
system, as in previous TII assessments. Pöyry has also introduced an additional criterion
(“value for money”) which considers issues that might sit between the other criteria and
also any interactions between the criteria. For each of the criteria, “green” represents
“high/strong” and “red” represents “low/weak”.
The following table sets out the assessment criteria for the strategic assessment of the
overall project (including all components):
20 See Appendix 3 of our March 2011 document.
9 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
The following table sets out the assessment criteria for the detailed project assessment of
specific components for which funding is requested by the TO within the next year:
Works planned to commence in 2012-13
Hunterston East Substation
We asked Pöyry to consider the appropriateness of the design, deliverability assumptions
and cost estimates for the Hunterston East project. Their findings are summarised below:
Pöyry had raised some slight issues around risks to deliverability relating to a detailed
aspect of the scheme design, which SPTL have now addressed sufficiently in response to
relevant questions Pöyry raised. Pöyry‟s view is that the scheme is deliverable. In
addition, Pöyry‟s view is that the design has progressed in a consistent and comprehensive
manner, with due consideration given for potential future expansion. In addition, the
costings are detailed and seem consistent with the scope of work.
Based on its assessment, Pöyry recommend that funding be provided under TII in line with
SPTL‟s cost forecast.
Harker-Hutton-Quernmore reconductoring
We asked Pöyry to focus their assessment on the deliverability, design and cost of this
specific project. Specifically, we asked them to consider whether the proposed solution is
optimal, the assumptions around the project plan are reasonable and the costs are
appropriate. We also asked them to consider interactions between this work and routine
refurbishment. Their findings are summarised below:
Pöyry are satisfied that the project is deliverable, and NGET have confirmed that their
delivery partner has the necessary resources to carry out the planned works. Pöyry think
the assumptions around the project plan are reasonable. The design is considered
10 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
appropriate, the proposed solution is optimal and any residual risks are being acceptably
managed by NGET. In Pöyry‟s view, the construction costs are appropriate and sufficiently
well quantified at this stage.
In terms of value for money, given that part of the route is due for refurbishment by 2014,
Pöyry had raised concerns that there may be overlap between this funding request and
funding for routine refurbishment under TPCR4 including rollover year (which should fall
outside of TII), given that NGET indicates that based on asset condition, 57km of the
115km route requires refurbishment within 0-2years. However, NGET requested no explicit
funding for refurbishment in its TPCR4 submission and have not spent any funds as yet.
Based on its assessment, Pöyry recommend that funding be provided under TII in line with
NGET‟s cost forecasts.
Trawsfynydd – Treuddyn reconductoring
We asked Pöyry to review the needs case, scope and timing of the overarching North Wales
scheme. In particular, we asked them to consider whether work is justified now given
anticipated future generation connections, and whether the scope is reasonable to meet the
need. Their findings are summarised below:
Pöyry have raised questions over the needs case and timing for the scheme as a whole,
linked to the assumptions around future generation development, and hence had concerns
about value for money. Pöyry are satisfied that the scope of the scheme represents an
entirely reasonable approach to the expansion of transfer capacity from North Wales should
the need arise. However, the Pöyry‟s view, the timing of the full scheme is too early, given
the latest views on future generation development.
However, Pöyry acknowledges that concerns around the overall scheme do not preclude
proceeding with works on the Trawsfynydd-Treuddyn Tee project which may be the “least
regret” decision in light of the need for refurbishment given the poor condition of the
existing fittings along the route and taking into account the optionality that reconductoring
would provide to accommodate potential future generation developments in North Wales
and the adjacent area.
We also asked Pöyry to assess the deliverability, design and cost of the particular
Trawsfynydd – Treuddyn works. Specifically, we asked them to consider whether the
proposed solution is optimal, the assumptions around the project plan are reasonable and
the costs are appropriate. We also asked them to consider interactions between this work
and routine refurbishment. Their findings are summarised below:
Pöyry are satisfied with the deliverability of the works, given the confirmation that NGET‟s
delivery partner has adequate resources available. Pöyry also think that the assumptions
around the project plan are reasonable. The design is considered appropriate and the
proposed solution is considered optimal. Pöyry‟s view is that the costing is appropriate
based on the programme and design details.
However, Pöyry raised strong concerns around the potential for overlap between funding
for routine refurbishment (due by 2014) under TPCR4 and this TII funding request, and
recommended that any TII funding cover incremental costs only.
11 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
Based on its assessment, Pöyry recommend that funding be provided under TII in line with
NGET‟s cost forecasts but that this should net off the funding already provided under
TPCR4.
Works with existing TII funding via January 2010 decisions
Deeside/Connah’s Quay Substation
We asked Pöyry to assess NGET‟s submission and recommend the appropriate level of
funding for 2012-13. The key focus of this assessment is identifying the material changes in
circumstances and determining the efficient costs that should be attributed to these
changes. We did not ask Pöyry to review deliverability of the scheme as the works are
already underway and the increased costs have already been incurred. Their findings are
summarised below:
Pöyry‟s assessment is that the design has progressed in a consistent manner, and should
be adequate to cope with additional generation in the region. Pöyry agrees that material
changes in circumstances have occurred since the previous funding decision, and consider
that sufficient justification has been provided for these. Based on a NGET response to a
question raised in the Q&A process, Pöyry also believe that the design is suitable to
accommodate potential future additional direct connections to the substation.
Pöyry are satisfied that the costs appear to be appropriate and reasonable, and that there
is no duplication between funding requests for Deeside/Connah‟s Quay and Western HVDC
link. They are satisfied that the cost increases are sufficiently justified by the changes in
design scope. Regarding value for money, they commented that the scope and associated
costs and funding are generally considered consistent and appropriate. They note that any
future savings from the reuse of one Super Grid Transformer (SGT) as a spare will be
immaterial and so there is no need for any adjustment to funding.
Based on its assessment, Pöyry recommend that additional funding be provided under TII,
over and above the default allowance, to take account of additional costs incurred over the
period to end 2011-12.
Eastern HVDC link
We asked Pöyry to consider the need, scope and timing of the Eastern HVDC scheme as a
whole. In particular, we asked them to focus on whether there is a case for considering a
multi-terminal option and what works are required to take this forward. We also asked
them to consider whether there is a need to commit additional expenditure now for the
additional works proposed to be undertaken in 2012-13 in order to deliver the Eastern
HVDC link by 2017-18. Their findings are summarised below:
Pöyry‟s view is that there is general uncertainty regarding the Eastern HVDC scheme,
although the proposed pre-construction work arguably aims to address this to some extent.
Assuming continuing GB commitment to delivery of renewable targets for 2020 and
beyond, Pöyry‟s view is that there is a clear underlying future need for an overarching
scheme based on an Eastern HVDC link. However, Pöyry notes there is uncertainty as to
the optimal scope (ie point-to-point or multi-terminal link) and timing, which is dependent
12 of 12 The Office of Gas and Electricity Markets
9 Millbank London SW1P 3GE Tel 020 7901 7000 Fax 020 7901 7066 www.ofgem.gov.uk
on cost-benefit analysis yet to be completed. As a result, it is unclear whether there is a
case for considering a multi-terminal option or for advancing the completion date. Given
uncertainty over timing, Pöyry also questions whether there is a need to commit additional
expenditure now.
In addition, we asked Pöyry to assess the deliverability, design and cost of the pre-
construction works captured by NGET‟s funding request, particularly whether the costs are
reasonable. We also asked them to consider review the justification for the material
changes in circumstances and associated changes in cost. Their findings are summarised
below:
Pöyry raised concerns about deliverability of the pre-construction works, given an apparent
lack of co-ordination – as evidenced by the lack of cohesive submissions, and delays to the
original programme. Pöyry also notes uncertainty around design of the pre-construction
works, as detailed work on a multi-terminal solution will be redundant if a point-to-point
connection is chosen. Pöyry also have significant concerns that the submission is not clear
on overall project scope and cost and hence division of costs between TOs, as well as
concerns around value for money given the apparent lack of co-ordination.
Overall, Pöyry‟s concerns stem from a lack of sufficient information provided within the
timescales of this assessment to enable them to identify the extent to which the additional
costs relate to additional works beyond the original scope, and in turn to reach a firm view
on the justification for those additional works and the reasonableness of the associated
costs.
Based on its assessment, Pöyry recommend that no additional funding be provided under
TII, over and above the default allowance.