63
ADDM 5000.02 TEMPLATE Systems Engineering Plan PROGRAM NAME – ACAT LEVEL SYSTEMS ENGINEERING PLAN VERSION __ SUPPORTING MILESTONE __ AND APPROPRIATE PHASE NAME (DATE) ******************************************************* ****************************** OFFICE OF THE SECRETARY OF DEFENSE (OSD) APPROVAL _______________________________________________ _________________________ Deputy Assistant Secretary of Defense Date Systems Engineering (for MDAPs and MAIS Programs) [or designated SEP approval authority] 1 ADDM: Systems Engineering Plan, Version 2.2 Based on: System Engineering Plan Outline dated 20 Apr 2011

Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

  • Upload
    others

  • View
    13

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

PROGRAM NAME – ACAT LEVEL

SYSTEMS ENGINEERING PLAN

VERSION __

SUPPORTING MILESTONE __

AND

APPROPRIATE PHASE NAME

(DATE)

*************************************************************************************

OFFICE OF THE SECRETARY OF DEFENSE (OSD) APPROVAL

_______________________________________________ _________________________

Deputy Assistant Secretary of Defense Date

Systems Engineering

(for MDAPs and MAIS Programs)

[or designated SEP approval authority]

DISTRIBUTION STATEMENT Click here to enter distribution letter and explanation (e.g.; “Approved for public release; distribution is unlimited”). Distribution statement reference HYPERLINK

1ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 2: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

"http://www.dtic.mil/dtic/submit/guidance/distribstatement.html"http://www.dtic.mil/dtic/submit/guidance/distribstatement.html .

2ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 3: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

SUBMITTED BY

__________________________NameProgram Lead Systems Engineer

__________Date

__________________________NameProgram Manager

_________Date

concurrence

__________________________

Name Lead/Chief Systems Engineer(Program Executive Office, System Center or Command)

__________Date

__________________________

Name

Program Executive Officer or Equivalent

_________Date

component approval

__________________________

NameTitle, OfficeComponent SEP Approval Authority

__________Date

3ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 4: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Guidance: The purpose of the Systems Engineering Plan (SEP) is to help programs develop their Systems Engineering (SE) approach, providing a firm and well-documented technical foundation for the program. The SEP is a living document in which periodic updates capture the program’s current status and evolving SE implementation and its relationship with the overall program management effort.

Enter applicable verbiage in each of the blue-font “click here to enter text” fields, as specified by the accompanying guidance sections. If the document section is not applicable, label as such and provide a short rationale.

Ensure that the Systems Engineering Plan resulting from this template includes all relevant information provided by the reference documents. Particularly the Acquisition Intelligence Guide, Version 1.0, August 2010.

“All links in this document were accurate at the time of writing. Due to web site security measures, though, clicking on some links from this document may give the error message "A Security Problem has Occurred" for a given URL, or a “Page Not Found” message. If you receive these errors, copy and paste the URL into your browser's address bar to establish the link.”

FOUO Guidance: Determine whether FOUO is applicable per DoDM 5200.01, Volume 4, “DoD Information security Program: Controlled Unclassified Information (CUI),” February 24, 2012.

FOUO Guidance Source: http://dtic.mil/whs/directives/corres/pdf/523024p.pdf

Instructions: PEO-specific instruction will be added here.

References:

1. Systems Engineering Plan (SEP) Outline, Version 1.0. 20 Apr 2011. http://www.acq.osd.mil%2Fse%2Fdocs%2FPDUSD-Approved.SEP_Outline-04-20-2011.docx

2. Acquisition Intelligence Guide, Version 1.0. Aug 2010.

3. DoD Instruction (DoDI)5000.02, "Operation of the Defense Acquisition System," Enclosure 3, “Systems Engineering.” 07 Jan 2015. http://www.dtic.mil/whs/directives/corres/pdf/500002p.pdf

4ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 5: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

This page intentionally left blank.

5ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 6: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Contents1. Introduction – Purpose and Update ........................................................................................9

1.1. User of SEP.......................................................................................................................91.2. Prime Contractor’s SEMP Alignment with Program SEP................................................91.3. SEP Update Process..........................................................................................................9

1.3.1. SEP Update Timing and Rationale............................................................................91.3.2. SEP Updating Authority..........................................................................................101.3.3. SEP Update Types Approvals Authority.................................................................101.3.4. SEP Update Record Table.......................................................................................10

2. Program Technical Requirements..........................................................................................102.1. Architectures and Interface Control................................................................................10

2.1.1. DoDAF Development Approach.............................................................................102.1.2. System Physical Architecture Diagram...................................................................102.1.3. System Functional Architecture Diagram...............................................................112.1.4. Software Architecture Priorities Development Approach.......................................112.1.5. Requirements Definition Relation with Architecture Products...............................112.1.6. Linkage of Engineering and Architecture Activities...............................................112.1.7. Required Memoranda of Agreement Table.............................................................112.1.8. External Interfaces Dependencies Management Expectation..................................12

2.2. Technical Certifications..................................................................................................123. Engineering Resources and Management..............................................................................13

3.1. Technical Schedule and Schedule Risk Assessment.......................................................133.1.1. Technical Schedule Planning and Execution Responsibilities................................133.1.2. Program Task Identification and Management........................................................133.1.3. Scheduling and Planning Assumptions...................................................................133.1.4. Technical Schedule Updating Responsibilities.......................................................133.1.5. Technical Schedule..................................................................................................133.1.6. Schedule Risk Assessment (SRA)...........................................................................16

3.2. Engineering Resources and Cost/Schedule Reporting....................................................163.2.1. Work Breakdown Structure (WBS).........................................................................173.2.2. Integrated Master Plan (IMP)/Integrated Master Schedule (IMS)..........................17

3.3. Engineering and Integration Risk Management..............................................................183.3.1. Risk Management Process Diagram........................................................................183.3.2. Roles, Responsibilities, and Authorities..................................................................18

6ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 7: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.3.3. Risk Review/Management Boards..........................................................................193.3.4. Risk Management Tools Listing Guidance.............................................................193.3.5. Risk Management Tools and Information Interoperability.....................................193.3.6. Technical Risk and Mitigation Planning.................................................................203.3.7. Risk Burn-down Plan...............................................................................................20

3.4. Technical Organization...................................................................................................213.4.1. Government Program Office Organization.............................................................213.4.2. Program Office Technical Staffing Levels..............................................................233.4.3. Contractor(s) Program Office Organization............................................................243.4.4. Engineering Team Organization and Staffing.........................................................24

3.5. Relationships with External Technical Organizations....................................................293.5.1. Responsible Organization and Authority.................................................................293.5.2. Management............................................................................................................293.5.3. FoS/SoS Schedule with Dependencies....................................................................30

3.6. Technical Performance Measures and Metrics...............................................................313.6.1. Measures and Metrics Approach, Process, and Monitoring....................................313.6.2. Technical Performance Measures Table..................................................................323.6.3. Reliability Growth Curve Graphic...........................................................................32

4. Technical Activities and Products ........................................................................................354.1. Results of Previous Phase SE Activities.........................................................................354.2. Planned SE Activities for the Next Phase.......................................................................354.3. Requirements Development and Change Process...........................................................35

4.3.1. Analysis and Decomposition...................................................................................354.3.2. Requirements Management and Change Process....................................................37

4.4. Technical Reviews ........................................................................................................384.4.1. Technical Review Process.......................................................................................384.4.2. Technical Review Responsibilities..........................................................................384.4.3. Technical Reviews Details Tables...........................................................................394.4.4. TD Tailoring............................................................................................................404.4.5. EMD Tailoring.........................................................................................................414.4.6. P&D Tailoring.........................................................................................................41

4.5. Configuration and Change Management Process ..........................................................414.5.1. Technical Baseline Artifacts....................................................................................414.5.2. Configuration Management/Control (and Change) Process Description................41

7ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 8: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.5.3. Roles, Responsibilities, and Authorities..................................................................424.5.4. Configuration Change Process................................................................................424.5.5. Classification of Changes........................................................................................434.5.6. Roles, Responsibilities and Authorities...................................................................43

4.6. Design Considerations....................................................................................................434.6.1. Mapping Key Design Considerations into Contracts Table....................................434.6.2. R&M Activity Planning and Timing Table.............................................................47

4.7. Engineering Tools...........................................................................................................484.7.1. Engineering Tools Table..........................................................................................48

Annex A – Acronyms....................................................................................................................50

NOTE: All sections above are driven by Section 139B of title 10 United States Code and DoDI 5000.02 policy; additional content is optional at the discretion of the Component.

8ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 9: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Tables and Figures(Mandated are listed below)

Guidance: Provide a list of all tables used in this plan.

TablesTable 1.1-1 SEP Update RecordTable 2.1-1 Required Memoranda of AgreementTable 2.2-1 Certification RequirementsTable 3.4.4-2 IPT Team DetailsTable 3.6-2 Technical Performance Measures and MetricsTable 4.4-1-n Technical Review DetailsTable 4.6-1 Design ConsiderationsTable 4.6-2 R&M Activity Planning and TimingTable 4.7-1 Engineering Tools

Guidance: Provide a list of all tables used in this plan.

FiguresFigure 3.1-1 System Technical ScheduleFigure 3.3-1 Technical Risk CubeFigure 3.4.1-1 Program Office OrganizationFigure 3.4.2-1 Program Technical StaffingFigure 3.4.3-1 Contractor Program Office OrganizationFigure 3.4.3-2 Contractor Technical StaffingFigure 3.4.4-1 IPT/WG Team HierarchyFigure 3.6-1 Reliability Growth CurveFigure 4.3.1-1 Requirements Decomposition/Specification Tree/BaselinesFigure 4.5-1 Configuration Management Process

(Additional, non-mandatory tables and figures may be included at the Component’s direction or the PM’s discretion.)

9ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 10: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

1. Introduction – Purpose and Update

Guidance:

SEP should be a “living” “go to” technical planning document and the blueprint for the conduct, management, and control of the technical aspects of the government’s program from concept to disposal. SE planning should be kept current throughout the acquisition lifecycle.

SEP is consistent with other program documentation.

SEP defines the methods for implementing all system requirements having technical content, technical staffing, and technical management.

Milestone Decision Authority (MDA)-approved SEP provides authority and empowers the Lead SE (LSE)/Chief Engineer to execute the program’s technical planning.

SE planning is kept current throughout acquisition lifecycle. For ACAT I programs, OSD/ Directorate Systems Engineering (DSE) expects to approve SEP updates to support milestone reviews (e.g., Milestone (MS) A, B, and C) and program restructures; the PEO can approve SEP updates to support SE technical reviews and program changes that impact the technical strategy.

Tailoring for Technology Development (TD) and Engineering and Manufacturing Development (EMD) phases: SEP should be updated after contractor award to reflect winning contractor(s)’ technical strategy reflected in SEMP.

1.1. User of SEP

Click here to enter text.

Guidance: Who will use the Systems Engineering Plan (SEP)?

1.2. Prime Contractor’s SEMP Alignment with Program SEP

Click here to enter text.

Guidance: What is the plan to align Prime Contractor’s Systems Engineering Management Plan (SEMP) with the Program Management Office (PMO) SEP?

1.3. SEP Update Process

1.3.1. SEP Update Timing and Rationale

Click here to enter text.

Guidance: Summarize how the SEP will be updated including the timing of SEP updates (e.g., following a conducted technical review, prior to milestones, as a result of SE planning changes, as a result of specific contractor-provided inputs),

10ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 11: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

1.3.2. SEP Updating Authority

Click here to enter text.

Guidance: Summarize the updating authority for the SEP

1.3.3. SEP Update Types Approvals Authority

Click here to enter text.

Guidance: Summarize the approval authorities for different types of SEP updates.

1.3.4. SEP Update Record Table

Click here to enter text.

Guidance: Provide a table of SEP document changes.

Revision Number Date Log of Changes made and Description of

Reason Changes Approved By

0.7 April 2008

Addressed Lead Systems Engineer’s (LSE’s) concerns – see comments in separate file LSE

0.8 June 2008 Updated Section 1 with draft requirementsAdded Section 4, Design Verification section LSE

0.9 October 2008

Addressed SE WIPT (to include Service and OSD) comments – many changes – see Comment Resolution Matrix (CRM)

LSE

Etc.

Table 1.1-1 SEP Update Record (mandated) (sample)

2. Program Technical Requirements

2.1. Architectures and Interface Control

2.1.1. DoDAF Development Approach

Click here to enter text.

Guidance: Summarize the approach for architecture development of the program’s DODAF architecture development efforts.

2.1.2. System Physical Architecture Diagram

Click here to enter text.11

ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 12: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Guidance: Summarize the approach for architecture development of the system physical architecture diagram (delineating physical interfaces), if available.

2.1.3. System Functional Architecture Diagram

Click here to enter text.

Guidance: Summarize the approach for architecture development of the system functional architecture diagram (delineating functional interfaces), if available.

2.1.4. Software Architecture Priorities Development Approach

Click here to enter text.

Guidance: Summarize how software architecture priorities will be developed and documented.

2.1.5. Requirements Definition Relation with Architecture Products

Click here to enter text.

Guidance: Summarize how architecture products are related to requirements definition.

2.1.6. Linkage of Engineering and Architecture Activities

Click here to enter text.

Guidance: Summarize how engineering and architecture activities are linked.

2.1.7. Required Memoranda of Agreement Table

Click here to enter text.

Guidance:

REQUIRED MEMORANDA OF AGREEMENT

Interface Cooperating Agency

Interface Control

Authority

Required By Date

Impact if Not Completed

Table 2.1-1 Required Memoranda of Agreement (mandated) (sample)

12ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 13: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

2.1.8. External Interfaces Dependencies Management Expectation

Click here to enter text.

Guidance: Programs whose system has external interfaces need to have dependencies (i.e., hierarchy) clearly defined. This should include interface control specifications, which should be confirmed early on and placed under strict configuration control. Compatibility with other interfacing systems and common architectures should be maintained throughout the development/design process.

2.2. Technical Certifications

Click here to enter text.

Guidance:

Summarize in the following table format the system-level technical certifications which must be obtained during program’s life-cycle.

This entry should be specific such as a specification compliance matrix; test, inspection, or analysis, or a combination. It can also reference a document for more information such as the TEMP.

Programs plan required technical certification activities and timing into the program IMP and IMS.

Certification PMO Team/PoC

Activities to Obtain Certification1

CertificationAuthority

Expected Certification

DateAirworthiness Airframe IPT ?Q FY?Clinger Cohen Confirm compliance Component

CIO (MDAP/MAI

S also by DoD CIO)

?Q FY?

Transportability ?Q FY?Insensitive Munitions

Manufacturing WG

Reference Document: PEO IM Strategic Plan

?Q FY?

Etc. ?Q FY?

Table 2.2-1 Certification Requirements (mandated) (sample)

1 This entry should be specific such as a specification compliance matrix; test, inspection, or analysis, or a combination. It can also reference a document for more information such as the TEMP.

13ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 14: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3. Engineering Resources and Management

3.1. Technical Schedule and Schedule Risk Assessment

Guidance: Programs should properly phase activities and key events (e.g., competitive prototyping, TRA, CDRs, etc.) to ensure a strong basis for making financial commitments. Program schedules are event driven and reflect adequate time for systems engineering (SE), integration, test, corrective actions and contingencies.

3.1.1. Technical Schedule Planning and Execution Responsibilities

Click here to enter text.

Guidance: Who is responsible for technical schedule planning and execution?

3.1.2. Program Task Identification and Management

Click here to enter text.

Guidance: How are program tasks identified and managed?

3.1.3. Scheduling and Planning Assumptions

Click here to enter text.

Guidance: List scheduling/planning assumptions.

3.1.4. Technical Schedule Updating Responsibilities

Click here to enter text.

Guidance: Identify which program office position/team is responsible for keeping the schedule up-to-date.

3.1.5. Technical Schedule

Click here to enter text.

Guidance: Provide a detailed, integrated, life-cycle system schedule (see Figure 3.1-1) (with particular emphasis on the next acquisition phase) to include:

Planned milestones

Planned significant activities (viz., activities which must be performed in order to produce the system):

SE technical reviews Key developmental, operational,

14ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 15: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Technology on/off –ramps

RFP release dates

Software releases

Hardware (HW)/Software (SW) Integration events

Contract award (including bridge contracts)

Testing events/phases

System-level certifications

integrated testing

Technology Readiness Assessments (TRAs)

Logistics/sustainment events

Long-lead or advanced procurements

Technology development efforts to include competitive prototyping

Production lot/phases

15ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 16: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.1-1 System Technical Schedule (mandated) (notional sample) Note: Include an as-of date – time sensitive figure

16ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Fiscal Year 121 2 3

4Quarter

13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Acquisition Decision Points

Logistics Events

Major Contract Events

Test Events

Systems Engineering

Production

FOCIOC

Engineering and Manufacturing Development

ICD and

System Capability and Manufacturing Process DemonstrationIntegrated System Design

Technology Development

MSD Core CapabilityILA

= Progress Reviews

= Item Production

Total Production xxx

= Item Deliveries

= IBR

30

ALFT&E waiver notification

EMD Contract

AwardLRIP Lot 2

LRIP Lot 3

LRIP Lot 1 / IOT&E Support

FRP

LRIP L/Lead

OA IOT&E / OPEVAL

OTRRBeyond LRIP Report

Integrated Testing

LFT&E Report

IOCSRILA

PCASRR SFR PDR CDR TRR/FRR SVR/FCA/PRR

GTV

Production / DeploymentLRIP / IOTE FRP

= First Flight

L/Lead

FOT&E (notional)

(notional)

ILA

TECHEVAL

MS-B ODASD(SE)

CDR Assessment

Requirements

MS-C FRP Decision Review

CPD

ALFT&E (Components) ALFT&E (Systems)

= Contract Award

EDMs

MS-APost PDR

Assessment

CDDDraft CDD

Pre-MS BMDA Rvw

= RFP Release

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 41 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4

1 2 3 4 1 2 3 4

1 2 3 4

1 2 3 4

L/Lead

Fixed Avionics SILFlight Control SILPortable/Flight Test Avionics SIL

Lot 1 x 6Lot 2 x 9

Lot 3 x 14

Source Sel

Post-CDR Assessmen

t

Supplier 1Source Sel

Supplier 2

TDContractAwards

Neg’n FRP

= Technical Reviews

= Readiness Review

AOTR: Assessment of Operational Test ReadinessALFT&E: Alternative Live Fire Test & EvaluationCDR: Critical Design ReviewEDM: Engineering Development ModelEMD: Engineering & Manufacturing DevelopmentFCA: Functional Configuration AuditFOT&E: Follow-On Operational Test & EvaluationFRP: Full Rate ProductionFRR: Flight Readiness ReviewGTV: Ground Test VehicleILA: Integrated Logistics Analysis

IOCSR: Initial Operational Capability Supportability ReviewIOT&E: Initial Operation Test & EvaluationLFT&E: Live Fire Test & EvaluationLRIP: Low-Rate Initial ProductionMDA: Milestone Decision AuthorityMSD: Material Support DateOA: Operational AssessmentOASD(SE): Office of the Assistant Secretary of Defense

(Systems Engineering)OPEVAL: Operational Evaluation

OTRR: Operational Test Readiness ReviewPCA: Physical Configuration AuditPDR: Preliminary Design Review PRR: Production Readiness ReviewSFR: System Functional ReviewSIL: Systems Integration LabSRR: System Requirements ReviewSVR: System Verification ReviewTD: Technology DevelopmentTECHEVAL: Technical EvaluationTRR: Test Readiness Review

Early OA

SourceSelection

Competitive Prototyping

Contract Awards

AOTRDevelopmental Test and Evaluation

Page 17: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.1.6. Schedule Risk Assessment (SRA)

Click here to enter text.

Guidance: Summarize the program’s schedule risk assessment (SRA) process. Programs should use SRAs to inform source selection and milestones, in addition to technical reviews.

3.1.6.1. SRA Techniques

Click here to enter text.

Guidance: What SRA techniques will be used to determine program schedule risk (e.g., critical path analysis, Monte Carlo simulations, etc.).

3.1.6.2. Schedule Drivers Mitigation

Click here to enter text.

Guidance: Describe the inherent impact of schedule constraints and dependencies and actions taken or planned to mitigate schedule drivers.

3.1.6.3. Results of SRAs Accomplished

Click here to enter text.

Guidance: List the results of any SRAs accomplished.

3.1.6.4. Critical Paths and Risk Reduction

Click here to enter text.

Guidance: List significant critical path or likely critical path events/activities and any planned actions to reduce risk for each.

3.2. Engineering Resources and Cost/Schedule Reporting

Click here to enter text.

Guidance: List and summarize the program oversight and management systems that will integrate cost, schedule, and technical performance goals, metrics, and resources.

Program should have an adequate IMP and IMS and requires the same from its contractor(s). The IMP and IMS clearly communicate the expectations of the program team, and provide traceability to the management and execution of the program by IPTs. They also provide traceability to the WBS, the Contract WBS (CWBS), the Statement of Work (SOW), systems engineering, and risk management, which together define the products and key processes associated with program success.

17ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 18: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Programs should require offerors to provide a tight linkage across IMP, IMS, risk mitigation, WBS, and cost in their proposals and with EVMS when implemented.

Program events, accomplishments, and criteria defined in the government’s IMP/program schedule, when combined with offeror-proposed events, should define top-level structure of IMS for execution.

In the RFP, offerors should be directed to:

Add key tasks only to the level necessary to define and sequence work, identify dependencies, document risk mitigations and deliverables, and support cost estimation and basis of estimate (BOE) preparation.

Include cross linkage to the IMP in the offeror’s IMS, WBS/BOE, and risk mitigation steps.

Incorporate additional detailed planning as part of the program kickoff and Integrated Baseline Review (IBR) process.

3.2.1. Work Breakdown Structure (WBS)

3.2.1.1. WBS, Product Structure, and Schedule Relationships

Click here to enter text.

Guidance: Summarize the relationship among the WBS, product structure, and schedule.

3.2.1.2. WBS Development Stakeholders

Click here to enter text.

Guidance: Identify the stakeholders who will develop the WBS.

3.2.1.3. WBS and System Technical Requirements Traceability

Click here to enter text.

Guidance: Explain the traceability between the system’s technical requirements and WBS.

3.2.2. Integrated Master Plan (IMP)/Integrated Master Schedule (IMS)

3.2.2.1. Program IMP and Contractor(s) IMS Relationship

Click here to enter text.

Guidance: What is the relationship of the program’s IMP to the contractor(s) IMS; how are they linked/interfaced; and what are their primary data elements?

18ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 19: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.2.2.2. IMP Development and RFP Utilization

Click here to enter text.

Guidance: Who or what team (e.g., IPT/WG) is responsible developing the IMP; when is it required; will it be a part of the RFP?

3.2.2.3. EVM and IMS Execution Monitoring

Click here to enter text.

Guidance: If used, how will the program use EVM cost reporting to track/monitor the status of IMS execution?

3.3. Engineering and Integration Risk Management

3.3.1. Risk Management Process Diagram

Click here to enter text.

Guidance: Diagram the process for how the program plans to manage engineering and integration risk and how these processes will be integrated with the contractor(s). This should include how the PMO will identify and analyze risks; and plan for, implement (including funding), and track risk mitigation.

Programs commonly use hierarchal boards to address risks and have integrated risk systems with their contractors, and their approach to identify risks is both top-down and bottoms-up. Risks related to technology maturation, integration, and each design consideration indicated in Table 4.6-1 should be considered in risk identification process.

3.3.2. Roles, Responsibilities, and Authorities

3.3.2.1. Risk Reporting/Identifying Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Indicate roles, responsibilities, and authorities within the risk management process for reporting/identifying risks.

3.3.2.2. Criteria for Determining Risk

Click here to enter text.

Guidance: Indicate roles, responsibilities, and authorities within the risk management process for the criteria used to determine if a “risk” submitted for consideration will become a risk or not (typically, criteria for probability and consequence).

19ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 20: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.3.2.3. Risk Addition/Modification Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Indicate roles, responsibilities, and authorities within the risk management process for adding/modifying risks.

3.3.2.4. Changing Risk Likelihood/Consequence Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Indicate roles, responsibilities, and authorities within the risk management process for changing likelihood and consequence of a risk.

3.3.2.5. Risk Closeout/Retirement Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Indicate roles, responsibilities, and authorities within the risk management process for closing/retiring a risk.

3.3.3. Risk Review/Management Boards

Click here to enter text.

Guidance: Describe Risk Review Boards or Risk Management Boards, if they are part of the process, and indicate who are the chair and participants and how often they meet.

3.3.4. Risk Management Tools Listing Guidance

Click here to enter text.

Guidance: List the risk tool(s) the program (program office and contractor(s)) will use to perform risk management in Table 4.7-1.

3.3.5. Risk Management Tools and Information Interoperability

Click here to enter text.

Guidance: If program office and contractor(s) use different risk tools, how will the information be transferred across them?

NOTE: In general, the same tool should be used. If the contractor’s tool is acceptable, then this merely requires Government direct, networked access to that tool.

20ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 21: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.3.6. Technical Risk and Mitigation Planning

Click here to enter text.

Guidance: Technical Risks and Mitigation Planning – Provide a risk cube (see Figure 3.3-1).

Figure 3.3-1 Risk Cube (mandated) (sample)

Note: Include an as-of date – time sensitive figure

3.3.6.1. Current System-level Technical Risk Listing (instead of risk cube)

Click here to enter text.

Guidance: Provide a listing of the current system-level technical risks with:

As-of date

Risk rating

Description

Driver

3.3.7. Risk Burn-down Plan

Click here to enter text.

Guidance: Include a Risk Burn-down Plan for mitigation status (optional).

21ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

R2

R1

Likelihood

Consequence

O1

Likelihood

Benefit

Page 22: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.3-2 Risk Burn-down Plan (optional) (sample)

Note: Include an as-of date – time sensitive figure

3.4. Technical Organization

3.4.1. Government Program Office Organization

Click here to enter text.

Guidance: Provide planned program office organization structure (i.e., wiring diagram to illustrate hierarchy) with an as-of date and include the following elements:

Legend, as applicable (e.g., color-coding)

Organization to which the program office reports

Program Manager (PM)

Lead/Chief Systems Engineer (LSE/CSE)

Functional Leads (e.g., T&E, logistics, risk, reliability, software)

Core, matrix, and contractor support personnel

Field or additional Service representatives

22ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 23: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

PEO

PM

Business MgmtLead

Financial MgmtLead

Logistics MgmtLead

TechLead

Test MgmtLead

Office of the

Director

Program Analysts

(2)

ProcureAnalysts

(2)

CostAnalyst

CostAnalyst

CostAnalyst

ProcureAnalyst

Logistics Mgmt

Analysts(2)

Logistics Mgmt

AnalystSE Lead Platform

Lead

MissionEquip.Lead

WeaponsLead Tester

Oper’lTester

DT&EEngineer

LoadMaster

ProgramIntegratr

Schedulr

ProgramAnalysts

(3)

SE

CM

ProductionEngineer

SafetyEngineer

Certif. Engineer

(2)

Interop. &IA

Engineer

SW Engineer

WeaponsEngineer

Field Team

Gov’t Core Team

Collocated Matrix

Contractor

Non-Collocated Matrix

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.4.1-1: Program Office Organization (mandated) (sample)Note: Include an as-of date – time sensitive figure

23ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 24: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.4.2. Program Office Technical Staffing Levels

3.4.2.1. Technical Staffing Determination Process and Tools

Click here to enter text.

Guidance: Summarize the program’s technical staffing plan to include process and tools program will use to determine required technical staffing.

Programs should use a workload analysis tool to determine adequate level of staffing, appropriate skill mix, and required amount of experience to properly staff, manage, and execute successfully.

3.4.2.2. Impact of Unmet Staffing Requirement

Click here to enter text.

Guidance: Risks and increased demands on existing resources if staffing requirements are not met;

3.4.2.3. Program Technical Staffing Profile

Click here to enter text.

Guidance: Include a Figure 3.4.2-1 (e.g., sand chart) to show the number of required full-time equivalent (FTE) positions (e.g., organic, matrix support, and contractor) by key program events (e.g., milestones and technical reviews).

24ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 25: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.4.2-1 Program Technical Staffing (mandated) (sample)

3.4.3. Contractor(s) Program Office Organization

3.4.3.1. Contractor(s) Technical Staffing Profile

Click here to enter text.

Guidance: When available, provide diagrams of the contractor(s) program office organization and staffing plans in figures analogous to Figures 3.4.1-1 and 3.4.2-1.

3.4.4. Engineering Team Organization and Staffing

3.4.4.1. Integrated Product Team (IPT) Organization

Click here to enter text.

Guidance: Provide diagrams that show ALL Government and contractors (when available) IPTs and their associated Working IPTs and Working Groups interrelated vertically and horizontall and that illustrate the hierarchy and relationship among them (see Figure 3.4.4-1). Identify the Government and contractor(s)’ leadership for all teams.

25ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 26: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.4.4-1 IPT/WG Team Hierarchy (mandated) (sample)

3.4.4.2. IPT Team Details Table

Click here to enter text.

Guidance: For all Government and contractor(s) (when available) IPTs and other key teams (e.g., Level 1 and 2 IPTs and WGs), include the following details either by attaching approved charters or as a table seen below, Table 3.4.4-2:

IPT name

Chairperson position and name

Functional team membership (to include all design consideration areas from Section 4.6)

IPT roles, responsibilities, and authorities

IPT processes

IPT products (e.g., updated baselines, risks, etc.)

IPT-specific metrics

Note: Make sure that the IPTs in the figure above match the IPTs in the table below!

26ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 27: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Program personnel should integrate SE activities with all appropriate functional and stakeholder organizations. In addition, IPTs should include personnel responsible for each of the design consideration areas in Section 4.6, Table 4.6-1.

27ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 28: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Team Name Chairperson Team Membership

(by Function or Organization) Team Role, Responsibility, and Authority Products & Metrics

SE IPT Lead SE Program Officeo Platform Leado Mission Equipment Leado Weapons Leado Test Managero Logistics Managero SW Leado Production/Quality

Managero Safety Leado Interoperability Rep.o R&M Lead

PEO and PM Service Representative OSD SE Key Subcontractor or

Suppliers

Role: IPT Purpose

Responsibilities: Integrate all technical efforts Team Member Responsibilities Cost, Performance, Schedule Goals Scope, Boundaries of IPT Responsibilities

Schedule and frequency of meetings

Date of signed IPT charter and signatory

Products:SEP/SEP UpdatesIMP/IMS InputSpecifications

Metrics:-Cost-Performance-Schedule

28ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 29: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

XXX IPT

XXX Lead Program Officeo Lead SEo Mission Equipment Leado Weapons Leado Test Managero Logistics Managero SW Leado R&M Leado Production/Quality

Managero Safety Leado Interoperability Rep.Key Subcontractor or Suppliers

Role: IPT Purpose

Responsibilities: Integrate all technical efforts Team Member Responsibilities Cost, Performance, Schedule Goals Scope, Boundaries of IPT Responsibilities

Schedule and frequency of meetings

Date of signed IPT charter and signatory

Products:Specification inputSEP inputTES/TEMP inputAS input

Metrics:Technical Performance Measure (TPM) 1TPM 2

Table 3.4.4-2 IPT Team Details (mandated unless charters are submitted) (sample)

29ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 30: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

3.4.4.3. IPT Alignment

Click here to enter text.

Guidance: Briefly summarize how the Government teams relate to/interact with the Prime Contractor’s teams, if they are not the same teams. Programs should shift IPT focus depending on the acquisition phase.

3.4.4.4. Tailoring for the Production and Deployment Phase

Click here to enter text.

Guidance: Describe how the organizational structure evolves after MS C. If the program doesn’t have a Production IPT during EMD Phase, one should be established in the P&D Phase.

3.5. Relationships with External Technical Organizations

Click here to enter text.

Guidance: What processes or methods will be used to document, facilitate, and manage interaction among SE team(s), external-to-program government organizations (e.g., FoS/SoS and contractor(s)/ competing contractor(s)) on technical tasks, activities, and responsibilities (e.g., requirements, technical baselines, and technical reviews) down to and including subcontractors.

3.5.1. Responsible Organization and Authority

Click here to enter text.

Guidance: Identify the organization responsible for coordinating SE and integration efforts associated with the FoS/SoS and its authority to reallocate resources (funding and manpower).

3.5.2. Management

3.5.2.1. FoS/SoS Interfaces Issue Resolution

Click here to enter text.

Guidance: Summarize how FoS/SoS interfaces will be managed including resolution of issues that cross PM, PEO, and Component lines.

3.5.2.2. Interface Control Documents and Working Groups

Click here to enter text.

30ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 31: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Guidance: Summarize how FoS/SoS interfaces will be managed including Interface Control Documents (ICDs) and any interface control WGs (ICWGs).

3.5.2.3. Memorandums of Agreement (MOAs)

Click here to enter text.

Guidance: Summarize how FoS/SoS interfaces will be managed including

Memorandums-of-Agreement (MOAs).

Develop MOAs with interfacing organizations that include:

Tripwires and notification to FoS/SoS members of any significant (nominally > 10%) variance in cost, schedule, or performance;

Mechanisms for FoS/SoS members to comment on any proposed interface changes; and

Fast-track issue identification and resolution process.

3.5.2.4. Notice of Deviation “Triggers”

Click here to enter text.

Guidance: Summarize how FoS/SoS interfaces will be managed including “Triggers” that require a FoS/SoS member to inform the others if there is a cost, schedule, or performance deviation.

3.5.2.5. Upgrade Programs Linkage Plans

Click here to enter text.

Guidance: Summarize how FoS/SoS interfaces will be managed including planned linkage between hardware and software upgrade programs within the FoS/SoS.

3.5.2.6. GFE/GFP/GFI

Click here to enter text.

Guidance: Summarize how FoS/SoS interfaces will be managed including any required Government Furnished Equipment/Property/Government Furnished Information (GFE/GFP/GFI) (e.g., test ranges, integration laboratories, and special equipment).

3.5.3. FoS/SoS Schedule with Dependencies

Click here to enter text.

Guidance: Include a schedule (optional) which shows FoS/SoS dependencies such as alignment of technical reviews, major milestones, test phases, GFE/GFP/GFI, etc.

31ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 32: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Recognize the importance of managing both the internal program schedule while maintaining synchronization with external programs’ schedules.

Develop a synchronized program schedule with interfacing programs schedules to provide insight into the potential impact of interfacing program schedule changes to include milestones, technical reviews, test periods.

Inform Component and OSD staffs so they better understand synchronizing funding and aligning priorities with external programs.

Figure 3.5-1 System-of-Systems Schedule (optional) (sample)

Note: Include an as-of date – time sensitive figure

3.6. Technical Performance Measures and Metrics

Click here to enter text.

Guidance: What is the program’s strategy for identifying, prioritizing, and selecting the set of metrics for monitoring and tracking program SE activities and performance?

3.6.1. Measures and Metrics Approach, Process, and Monitoring

Click here to enter text.

32ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 33: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Guidance: Include an overview of the measurement planning and metrics selection process, including the approach to monitor execution to the established plan, and identification of roles, responsibilities, and authorities for this process.

3.6.2. Technical Performance Measures Table

Click here to enter text.

Guidance: Describe the minimum set of technical performance measures (TPMs) and intermediate goals and the plan to achieve them with as-of dates (to provide quantitative insight into requirements stability and specification compliance). Examples include TPMs in the areas of software, reliability, manufacturing, and integration to assess “execution to plan.”

3.6.3. Reliability Growth Curve Graphic

Click here to enter text.

Guidance: Include a Reliability Growth Curve. PMs shall use a growth curve to plan, illustrate, and report progress. Growth curves will be stated a series of intermediate goals and tracked through fully integrated, system-level test and evaluation events until the reliability threshold is achieved see Figure 3.6-1. If a single curve is not adequate to describe overall system reliability, provide curves for critical subsystems with rationale for their selection.

Note: For ACAT I programs, performance-to-plan will be checked during Program Support Reviews (PSRs).

Programs should understand the amount of testing, test schedule and resources available for achieving the specification requirement. Programs should consider the following:

Develop the growth planning curve as a function of appropriate life units (hours, cycles, etc,) to grow to the specification value.

How the starting point that represents the initial value of reliability for the system was determined.

How the rate of growth was determined. Rigorous test programs which foster the discovery of failures, coupled with management-supported analysis and timely corrective action, will result in a faster growth rate. The rate of growth should be tied to realistic management metrics governing the fraction of initial failure rate to be addressed by corrective actions along with the effectiveness of the corrective action.

Describe the growth tracking and projection methodology that will be used to monitor reliability growth during system-level test (e.g., AMSAA-Crowe Extended, AMPM).

33ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 34: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 3.6-1 Reliability Growth Curve (mandated) (sample)

34ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 35: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Name Responsible Position/IPT

KPP or KSA

Performance Spec.

PDR Status

Actual

MS B Status

Actual

CDR Status

Actual

MS C Status

Planned

FRP Status

Planned

Aerodynamic Drag (count)

SE IPT <222 225 223 220 187 187

Thermal Utilization (kW) SE IPT <60 56 59 55 51 50

Electrical Power Usage (kW)

SE IPT <201 150 185 123 123 123

Operating Weight (lb) SE IPT <99,000 97,001 101,001 97,001 85,540 85,650

Range (nm) SE IPT >1,000 1,111 1,101 1,111 1,122 1,130

Average Flyaway Unit Cost (number)

SE IPT <1.5 1.3 1.58 1.37 1.35 1.32

*Note: Margin is 10%

Table 3.6-2 TPMs (mandated) (sample)

35ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 36: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4. Technical Activities and Products

4.1. Results of Previous Phase SE Activities

Click here to enter text.

Guidance: Summarize (consider a tabular format) system-level technical reviews, trade studies, and independent reviews conducted to date; date(s) conducted; and key results or impact(s) to design and any related recommendations and status of actions taken.

4.2. Planned SE Activities for the Next Phase

Click here to enter text.

Guidance: Summarize key planned system engineering, integration, and verification processes and activities established or modified since the previous acquisition phase including updated risk reduction and mitigation strategies and technical and manufacturing maturity.

4.3. Requirements Development and Change Process

4.3.1. Analysis and Decomposition

Guidance: How will top-level requirements (i.e., from AoA, KPPs, KSAs, statutory, regulatory, certification, safety, software, hardware, etc.) be traced from the source JCIDS documents down to configuration item (CI) build-to specifications and Verification and Validation (V&V) plans?

4.3.1.1. Requirements Traceability Roles and Responsibilities

Click here to enter text.

Guidance: Identify which program office position or team (e.g., IPT/WG) is responsible for continuously ensuring the accurate traceability of requirements.

4.3.1.2. Requirements Traceability Tools

Click here to enter text.

Guidance: Identify the tool (s) the program plans to use (or continues to use) for requirements traceability in Tools Table 4.7-1.

Program should trace all requirements from JCIDS into a verification matrix.

36ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 37: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.3.1.3. Requirements Traceability Roles Information Interoperability

Click here to enter text.

Guidance: If the program office and prime contractor(s) use different tools, how will information be transferred across them?

4.3.1.4. Requirements Management Effectiveness

Click here to enter text.

Guidance: What approach will be used to ensure that there are no orphan or childless requirements?

4.3.1.5. Tailoring for TD phase

Click here to enter text.

Guidance: Describe how competitive prototyping, the TRA, the PDR, and test results will inform the program’s KPP/KSAs for the EMD phase.

4.3.1.6. Requirements Decomposition/Specification Tree/Baselines

Click here to enter text.

Guidance: Include a Requirements Decomposition/Specification Tree/Baselines figure (mandated).

37ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 38: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Figure 4.3.1-1 Requirements Decomposition/Specification Tree/Baselines (mandated) (sample)

4.3.2. Requirements Management and Change Process

Guidance: How will requirements be managed and changes made and tracked?

Programs should ensure requirements traceability from the lowest level component all the way back to the user’s capability document.

4.3.2.1. Configuration Steering Board Utilization

Click here to enter text.

Guidance: If the program is a MDAP, and if it were to have a change in requirement which could result in a cost and/or schedule breech, summarize the mechanism by which the program will involve its Configuration Steering Board.

4.3.2.2. Requirements Management Roles and Responsibilities

Click here to enter text.

Guidance: Identify which program office position or team (e.g., IPT/WG) will be responsible for continuously ensuring the accurate management of requirements and requirement changes.

38ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 39: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.4. Technical Reviews

4.4.1. Technical Review Process

Click here to enter text.

Guidance: Summarize the PMO’s plans for conducting each technical review with particular emphasis and detail on those technical reviews planned in the program’s next acquisition phase.

Programs should use a standard process for conducting technical reviews.

4.4.1.1. Technical Review Process Diagrams

Click here to enter text.

Guidance: A diagram of the process with the objective timeframes for each activity before, during, and after the technical review may prove useful.

4.4.2. Technical Review Responsibilities

4.4.2.1. Technical Review Entry Criteria Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Identify which program office position is responsible for the overall conduct of system-level and/or key subsystem-level technical reviews.

4.4.2.2. Technical Review Entry, Action Item Taskings, Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Identify who or what team has responsibility, authority, and accountability for determining:

Whether/when technical review entry criteria have been met

What action items are to be tasked

4.4.2.3. Technical Review Tasked Action Item Closeout Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Identify who or what team has responsibility, authority, and accountability for determining that tasked action items have been closed appropriately.

39ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 40: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.4.2.4. Technical Review Exit Criteria Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Identify who or what team has responsibility, authority, and accountability for determining that technical review exit criteria are met.

4.4.3. Technical Reviews Details Tables

Click here to enter text.

Guidance: For each planned system-level technical review in the next acquisition phase, include a marker on the program schedule (Figure 4.1-1-n) and a technical review table. This table, or something analogous, is mandatory.

Program shall have event-driven technical reviews.

40ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 41: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Table 4.4-1 Technical Review Details (mandated) (sample)

4.4.4. TD Tailoring

Click here to enter text.

Guidance: At a minimum, provide details for System Requirement Review (SRR)(s), System Functional Review (SFR)(s), and Preliminary Design Review (PDR) (s) as planned by the program. For MDAPs, Section 2366b certification requires an MDA-level Post-PDR Report Assessment.

41ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

XXX Details Area XXX Review Details (For this acquisition phase, fill out tailored criteria, etc.)

Chairperson Identify the Technical Review Chair (Normally the LSE)PMO Participants Identify Positions/functions/IPTs within the program offices

which are anticipated to participate. (Engineering Leads; Risk, Logistics, and Configuration Managers, Defense Contracting Management Agency (DCMA) Rep., and Contracting Officer, etc.)

Anticipated Stakeholder Participant Organizations

Representatives (stakeholders) from Service SE and Test, OSD SE and Developmental Test and Evaluation (DT&E), FoS/SoS, and the User

Anticipated Peer and Program-Independent SME Participant Orgs.

Identify Organizations which can provide a peer perspective and participants who will provide an independent assessment of how well the program is progressing but which have no stake in the program’s success.

Purpose (of the review)

Describe the main purpose of the review and any specific SE goals

Entrance Criteria Identify tailored Entrance Criteria

Exit Criteria Identify tailored Exit Criteria

Products (from the review)

List expected products from the technical Review (for example)

Established system allocated baseline Updated risk assessment for EMD Updated Cost Analysis Requirements Document (CARD) or

CARD-like document based on system allocated baseline Updated program schedule including system and SW critical

path drivers Approved LCSP updating program sustainment development

efforts and schedules Draft Post-PDR Report (MDAPS)

Page 42: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.4.5. EMD Tailoring

Click here to enter text.

Guidance: At a minimum, provide details for delta PDR (if conducted), PDR if entering acquisition at MS B, CDR, and System Verification Review (SVR)/ Functional Configuration Audit (FCA) and Production Readiness Review (PRR), as planned.

4.4.6. P&D Tailoring

Click here to enter text.

Guidance: At a minimum, provide details for SVR/FCA/PRR (if not already detailed in the EMD Phase SEP), Physical Configuration Audit, and In-Service Reviews, as planned.

4.5. Configuration and Change Management Process

4.5.1. Technical Baseline Artifacts

Click here to enter text.

Guidance: For each baseline established at a technical review, list and describe the planned or established artifacts (if not already identified in Section 4.4). Typically, at a minimum, the following apply:

SFR = Functional Baseline = System Specification and external specifications

What action items are to be tasked

What action items are to be tasked

PDR = Allocated Baseline = Item Performance Specification for each end product, internal interface specifications, and allocated external interface specifications, and preliminary drawings

CDR = Initial Product Baseline = Item Detail Specification for each end product, internal interface specifications, allocated external interface specifications, and detailed (build-to) drawings

Programs should understand which artifacts make up each technical baseline and manage changes appropriately.

4.5.2. Configuration Management/Control (and Change) Process Description

Click here to enter text.

Guidance: Identify when in the acquisition lifecycle the program will assume initial and full configuration control of its baselines.

42ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 43: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

4.5.2.1. Configuration Management Process Diagram

Click here to enter text.

Guidance: Provide a process diagram of how the program will maintain configuration control of its baselines.

Figure 4.5-1 Configuration Management Process (mandated) (sample)

4.5.3. Roles, Responsibilities, and Authorities

Click here to enter text.

Guidance: Summarize the roles, responsibilities, and authorities within the CM process. If this includes one or more configuration boards, describe the hierarchy of these boards, their frequency, who (by position) chairs them, who participates, and who (by position) has final authority in each.

4.5.4. Configuration Change Process

4.5.4.1. Technical Baseline Changes

Click here to enter text.

Guidance: Outline the process the program will use to change the technical baseline/configuration and specifically address how changes to a technical baseline are identified, evaluated, approved/disapproved, recorded, incorporated, and verified.

4.5.4.2. Product Information Management

Click here to enter text.

43ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 44: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Guidance: Outline the process the program will use to change the technical baseline/configuration and specifically address how product information is captured, maintained, and traced back to requirements.

4.5.4.3. In-Service Configuration/Design Changes

Click here to enter text.

Guidance: Outline the process the program will use to change the technical baseline/configuration and specifically address how requirements for in-service configuration/design changes are determined and managed/controlled.

4.5.4.4. Internal Interfaces

Click here to enter text.

Guidance: Outline the process the program will use to change the technical baseline/configuration and specifically address how internal interfaces are managed and controlled.

4.5.5. Classification of Changes

Click here to enter text.

Guidance: Define the classification of changes (Class 1, Class 2, etc.) applicable to the program.

4.5.6. Roles, Responsibilities and Authorities

Click here to enter text.

Guidance: Identify by position who in the CM process is responsible for determining the classification of a change and who (by position) verifies/confirms/approves it.

Programs will control their baselines.

4.6. Design Considerations

4.6.1. Mapping Key Design Considerations into Contracts Table

Click here to enter text.

Guidance: DAG Section 4.4 contains a non-exhaustive list of design considerations; not all are equally relevant or critical to a given program, but all should be examined for relevancy. In the mandated table below, identify design considerations that are critical to the achievement of the program’s technical requirements. Consider embedding or hot-linking to reference documents. The entries below are mandated by policy for inclusion.

44ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 45: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

SEP demonstrates that the mandated design considerations are an integral part of the design decision process including trade study criteria.

45ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 46: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Mapping Key Design Considerations into Contracts

Name (Reference) Cognizant PMO Org. Certification Document (hot

link)

Contractual Req’ts(CDR

L #)Description/Comments

SE Tradeoff Analysis for Affordability

(MS B) Provide the systems engineering trade-off analysis showing how cost varies as the major design parameters and time to complete are traded off against one another. The analysis will reflect attention to capability upgrades. The analysis will support MDA approval of an Affordability Requirement to be treated as a Key Performance Parameter (KPP) in the Acquisition Decision Memorandum. The analytical summary will include a graphic illustrating cost tradeoff curves or trade space around major affordability drivers (including KPPs when they are major cost drivers) to show how the program has established a cost-effective design point for those affordability drivers.

Corrosion Prevention and Control (ACAT ID only)

CPCP(MS B & C)

Describe how design will minimize impact of corrosion and material deterioration on system throughout system life cycle.

Environmental Safety and Occupational Health (ESOH)

PESHENEPA

Compliance Schedule

(MS B & C)

Describe how design will minimize ESOH by summarizing how program will integrate ESOH considerations into SE processes to include method for tracking hazards and ESOH risks and mitigation plans throughout the life cycle of system.

Human Systems Integration (HSI)

Summarize how HSI will be integrated within the SE processes, specifically addressing the human operator and maintainer requirement allocation approach that accounts for total system performance.

46ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 47: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Item Unique Identification(IUID)

IUIDImplementationPlan (MS B & C)

Describe how the program will implement IUID to identify and track applicable major end items, etc.

Manufacturing Assess the manufacturing readiness of all contributory processes and particularly those which are new or unproven in a full-rate production environment.

Open Systems Architectures Describe how open systems architectures will be incorporated into the program's design to enable affordable change, evolutionary acquisition, and interoperability.

Program Protection and Information Assurance

PPP(MS A, B & C)

Describe how design will address safeguarding Critical Program Information (CPI) and provide countermeasures against hacking.

Reliability and Maintainability3

RAM contract Language1

RAM-C Report2

(MS A, B & C)

Describe how the program will implement and contract for a comprehensive R&M engineering program to include the phased activities in Table 4.6-2 and how R&M is integrated with SE processes.

Table 4.6-1 Design Considerations (mandated) (sample)1 Relevant R&M sections of the Systems Specification, SOW/SOO, and Sections L and M2 DoD RAM-C Report Manual, June 1, 20093 Programs operating under Space Systems Acquisition Procedures shall address Mission Assurance (MA) planning in the context of reliability and provide a description of MA activities undertaken to ensure that the system will operate properly once launched into orbit. Specifically, space programs will describe how the Mission Assurance process employed meets the best practices described in the Mission Assurance Guide (reference Aerospace Corporation TOR-2007(8547)-6018). This description should include program phase-dependent processes and planning for MA in the next phase of the program and the way program MA processes adhere to applicable policies and guidance. Also describe the launch and operations readiness process.

47ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 48: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Table 4.6-1 Legend:Name – See DAG Chapter 4.4 for more comprehensive listing of design considerations; listed items are mandated by statute or policy and must be addressed. Others are at PMO’s discretion as appropriate for the system. Cognizant PMO Organization – Assigned IPT/WIPT/WG for oversightCertification – As appropriate, to include Technical Authority and timeframeDocumentation – List appropriate PMO and/or contractor documents and hot link.Contractual Requirements – List contract clauses which the PMO is using to address the named topic.Description/Comments – As needed, to inform other PMO members and stakeholders

4.6.2. R&M Activity Planning and Timing Table

Click here to enter text.

Guidance: Include a R&M Activity Planning and Timing table (see Table 4.6-2).

Programs should understand that the content of the R&M artifacts need to be consistent with the level of design knowledge that makes up each technical baseline.

R&M Allocations – R&M requirements assigned to individual items to attain desired system level performance. Preliminary allocations are expected by SFR with final allocations completed by PDR.

R&M Block Diagrams – The R&M block diagrams and math models prepared to reflect the equipment/system configuration. Preliminary block diagrams are expected by SFR with the final completed by PDR.

R&M Predictions – The R&M predictions provide an evaluation of the proposed design or for comparison of alternative designs. Preliminary predictions are expected by PDR with the final by CDR.

Failure Definition and Scoring Criteria – Failure definitions and scoring criteria to make assessments of R&M contract requirements.

FMECA – Analyses performed to assess the severity of the effects of component/subsystem failures on system performance. Preliminary analyses are expected by PDR with the final by CDR.

Maintainability and Built-In Test – Assessment of the quantitative and qualitative maintainability and Built-In test characteristics of the design.

Reliability Growth Testing at the System and Subsystem Level – Reliability testing of development systems to identify failure modes, which if uncorrected could cause the equipment to exhibit unacceptable levels of reliability performance during operational usage.

FRACAS – Engineering activity during development, production, and sustainment to provide management visibility and control for R&M improvement of hardware and associated software by timely and disciplined utilization of failure data to generate and implement effective corrective actions to prevent failure recurrence.

48ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 49: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

R&M Engineering Activity Planning and Timing

R&M AllocationsR&M Block DiagramsR&M PredictionsFailure Definitions and Scoring CriteriaFailure Mode, Effects, and Criticality Analysis (FMECA)Maintainability and Built-in Test DemonstrationsReliability Growth Testing at the System and Subsystem LevelFailure Reporting , Analysis, and Corrective Action System (FRACAS)

Table 4.6-2 R&M Activity Planning and Timing (mandated) (sample)

4.7. Engineering Tools

4.7.1. Engineering Tools Table

Click here to enter text.

Guidance: In a table (see Table 4.7-1), identify the tools the program plans to use.

Program should ensure design solutions are documented based upon sound SE practices using engineering tools to augment the technical approach. Programs should define tool interfaces when the government and contractor(s) plan to use different tools for the same purpose.

Engineering Tool Purpose Position/IPT ResponsibilityIMSIBM®Rational®DOORS®

Requirements Traceability and Verification Methodology and Completion

SE IPT/Rqmts Manager

Requirements Verification Matrix

Requirements Verification

49ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 50: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

(RVM)Computer-Aided Three-DimensionalInteractive Application (CATIA)

Design SE IPT

Risk Mgmt Information System (RMIS)

RM SE IPT/Risk Manager

SW Integration Lab (SIL)

M&S SW WG

SW Engineering Design SW WGSW cost estimating (e.g., COCOMO)

SW WG

Producibility/ThroughputAnalysis Tool

Manufacturing WG

Line of Balance Production planning Manufacturing WGEtc.

Table 4.7-1 Engineering Tools (mandated) (sample).

50ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011

Page 51: Systems Engineering Plan SEP ADDM Template v 2.2 Sponsored Documen… · Web viewADDM 5000.02 TEMPLATE Systems Engineering Plan 7 ADDM: Systems Engineering Plan, Version 2.2 Based

ADDM 5000.02 TEMPLATESystems Engineering Plan

Annex A – Acronyms

Click here to enter text.

Guidance: Provide a list of all acronyms used in the SEP

51ADDM: Systems Engineering Plan, Version 2.2Based on: System Engineering Plan Outline dated 20 Apr 2011