Upload
nicole-head
View
19
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Status of E-906/Drell-Yan with Fermilab and DOE and schedule going forward. Paul E. Reimer 7 January 2008 MOU and Stage II Approval Celebration—exciting meeting Financial outlook Hall Status and schedule. Final Signatures on MOU 16 Dec 2008. Stage II approval on Christmas Eve. - PowerPoint PPT Presentation
Citation preview
Status of E-906/Drell-Yan with Fermilab and DOE and schedule going forward
Paul E. Reimer
7 January 2008
1. MOU and Stage II Approval Celebration—exciting meeting
2. Financial outlook
3. Hall Status and schedule
27 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Final Signatures on MOU 16 Dec 2008
37 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Stage II approval on Christmas Eve
MOU led to Stage II approval. This means that– We are now a “real” experiment
that can use Fermilab recourses– We can now claim some “real
estate” in which to work
– We are expected to deliver an experiment, not just talk about it.
Caveat: Subject to Fermilab’s other commitments--please let me know what I need to negotiate.
47 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Budget—Big Picture
Fiscal Year
Funding Source 2007 2008 2009 2010 Total
DOE/ONP Total $375k$375k $292k$292k $370k $401k $1,438k
US NSF Total $35k $187k $207k
DOE/HEP (via Fermilab) Total
(no fiscal year breakdown) $1,182k
Japan Total $20k $300k $15k $335k
Taiwan Total $30k $200k $100k $330k
Grand TotalGrand Total $3,392k
From MOU
What are the appropriate funding agencies in Japan and Taiwan?
57 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Budget—US Picture
US Fiscal Year
FundingSource
Institution 2007 2008 2009 2010 Total
US DOE Office of Nuclear Physics
Abilene $130k$130k $ 12k $142k
Argonne $100k$100k $100k
Argonne to Fermilab $275k$275k $292k$292k $150k$150k $291k $1,008k
Colorado $90k$90k $ 98k $188k
DOE/ONP Total $375k$375k $292k$292k $370k$370k $401k $1,438k
US NSF
Illinois $20k $20k $40k
Maryland $50k $50k
Michigan $117k $117k
Rutgers $15k
NSP Total $35k $187k $207k
67 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Budget—Continuing Resolution (flat funding)
Brad Tippens (DOE/Office of Nuclear Physics) specifically requested our response to three possible scenarios for FY09 funding:
$370k in FY09: This scenario is outlined in the MOU. Basically we would proceed with all due speed to get the spectrometer on the floor and taking data at Fermilab.
$150k in FY09: – The first priority would be to start the design and construction of the
Station 1 MWPC at Colorado. $90k is needed for this. – Next, is the purchase the Station 4a hodoscopes at Abilene Christian for
$30k. – The remaining $30k would be used either for the Station 4b hodoscopes
at Abilene, or if the Japanese obtain the extra funding they have requested (approx. $100k for Station 3x, 4b and 4c hodoscopes) this $30k could be used to fund help spectrometer installation at Fermilab. The priority would be the assembly of the magnet. Not having the remaining $220k until FY2010 would result in a significant, but manageable delay in the installation and start of the experiment.
77 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
TimelineTimeline Constraints Funding cycle Ability for Fermilab to prepare hall and beam line Our ability to construct and install spectrometer elements Tevatron schedule
– Collider run is scheduled to end at the end of FY10 (31 Sept 2010)
– High intensity protons to E-906/Drell-Yan unlikely while Collider is running
– Low intensity protons are possible—excellent opportunity to “shake down” spectrometer/DAQ/Analysis
2009
2008
2011 Publications
Expt. Funded
2010
Magnet Design ExperimentAnd construction Construction
ExperimentRuns
2012
Tevatron/Collider constraints make it unreasonable to push for the experiment to be ready in Jan 2010; however some low intensity running is desirable.
Proposed spectrometer completion date of June 2010Proposed spectrometer completion date of June 2010
87 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Hall layout and space—current
Current status of NM4 (KTeV Hall)
Scaffolding/supports everywhere
Left over ruins of a previous grand experiment
Tourists visit it occasionally
Site has been scavenged for valuable material, waste bins to through the rest away
97 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Current NM4 Hall Status (from Chuck’s talk)
Areas that will definitely be cleaned out this spring
KMAG
End of loading dock
107 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
KTeV Hall progress
See talk by Chuck Brown We now have possession of
– the counting room to use as office/work space.
– Gas shed to begin work on chamber gas mixing/circulation system
Complications:
– Liquid Argon (21 t) purification test is planned for 1 month (realistically 3 months) on floor of hall.
• Test was to have been completed by now, but not yet started• Discussing other locations for test. (We now have Stage II approval, which we
didn’t have when this test was sited.)
– Loading dock/Mezzanine level may be used for MICE solenoid test this summer
– Fermilab labor to assemble FMag will not be available until Spring 2010!
117 January 2009Paul E. Reimer. E906 Status, Funding and Schedule
Conclusions and Questions
We did it—now we need to change this from a virtual experiment into reality!!!
Budget Questions—DOE:
– By when do Abilene Christian, Colorado and Fermilab need the money?
– What cannot wait until March 2009?
– How will this impact Summer 2009 work?
Space is being opened up for us to use
– What do we need by Spring 2009?
– What do we need by Summer 2009?
– Lodging onsite?
Experiment can be ready in June 2010, but time is tight Please think in advance of the resources needed and coordinate it with myself and
Chuck. Also, don’t forget to do everything safely—and this requires coordination with Fermilab ES&H.