Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
RGMO/MVAR Meeting – 26.09.2018 Page 1
Minutes of the RGMO/MVAR Meeting held on 26.09.2018 at SRPC, Bengaluru
1. Introduction
A Meeting on RGMO/MVAR was held at SRPC, Bengaluru on 26th September 2018.
The list of Participants is given at Annexure-I.
It was noted with concern that there was no representation from APSLDC, TNSLDC
(had informed that they would not be attending the meeting), NTPC-Talcher, MAPS,
KGS, KKNPP, JSWEL, IL&FS & HNPCL.
Shri S R Bhat, Member Secretary, SRPC welcomed all the participants and noted that
the 9th
meeting on RGMO/MVAR was being held after a gap of around one & half years
since 8th
meeting was held in April 2017. Around 10 incidents since April 2017 of
RGMO were to be analysed during the course of this meeting. Role of generators in
voltage management was also essential to maintain the voltage profile within the
permissible limits, with reactive interchange within the capability curves. From 1st April
2017 to 31st August 2018, the MVAR analysis would be discussed so as to identify steps
to improve the performance.
2. RGMO/FGMO WITH MI
Hydro Thermal TOTAL
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
26.04.2017 (10:01 hrs) frequency rose from 50.02 Hz to 50.21 Hz (+0.19 Hz) -
Tripping of Karad & Kolhapur ICT's occurred, resulting Load loss of 900 MW
-78 -18 23% -965 -307 32% -1043 -325 31%
09.05.2017 (16:41 hrs) frequency fell from 49.99 Hz to 49.86 Hz (-0.13 Hz) – 400 kV
J.P.Nigri-Satna line - 1&2 tripped at 16:19 and 16:41 Hrs due to which Unit- 1&2 at
J.P.Nigri tripped due to loss of evacuation lines. Generation Loss of 1180 MW
32 15 47% 1041 250 24% 1073 265 25%
18.05.2017 (08:01 hrs) frequency fell from 50.10 Hz to 49.83 Hz (-0.27 Hz) - Rihand
TPS Unit 1, 2 & 4 tripped and at 08:03 Hrs Rihand TPS Unit 3, 5 & 6 got tripped.
Generation Loss around 2750 MW.
39 114 292% 1021 333 33% 1060 447 42%
20.05.2017 (20:06 hrs) frequency fell from 50.08 Hz to 49.86 Hz (-0.22 Hz) -2000
MW generation loss at Chavra/Anta generation complex at Rajasthan due to fault at
765 Kv Anta - Phagi- II
40 -46 -
215% 1088 276 25% 1127 229 20%
23.05.2017 (17:43 hrs) frequency fell from 49.93 Hz to 49.72 Hz (-0.21 Hz) -
Vindhyachal Stage-III tripped reportedly due to fire in Generator Transformer.
Vindhyachal Unit 8, 9 & 10(capacity 500 MW each) tripped.
24 28 117% 1127 266 24% 1151 294 26%
16.08.2017 (12:18 hrs) frequency fell from 49.93 Hz to 49.84 Hz (-0.09 Hz) - 979 MW
Generation loss at Teesta and Dikchu due to 400kV Rangpo-Teesta
RGMO/MVAR Meeting – 26.09.2018 Page 2
44 45 104% 939 235 25% 983 280 29%
12.11.2017 (07:14 hrs) frequency fell from 50.00 Hz to 49.89 Hz (-0.11 Hz) -
Generation loss of 1097 MW due evacuation lines tripping of Taleandi Sabo
64 2 3% 1091 340 31% 1155 342 30%
09.12.2017 (12:58 hrs) frequency rose from 50.04 Hz to 50.16 Hz (+0.12 Hz) – 1400
MW Load loss Padghe S/S TBC blast, all feeders tripped
-74 -48 65% 894 342 38% 968 390 40%
30.01.2018 (10:46 hrs) frequency fell from 49.89 Hz to 49.82 Hz (-0.07 Hz) -
Generation of loss of 1250 MW at Koderma and Load loss of 300 MW
41 53 130% 669 159 24% 710 211 30%
23.04.2018 (10:42 hrs) frequency fell from 50.02 Hz to 49.71 Hz (-0.31 Hz) - 3090
MW generation loss at DB Power, KSK, SKS, RKM, TRN and NSPCL generating
stations
81 109 135% 1282 380 30% 1363 489 36%
Deliberations
The incident of 30.01.2018 was agreed to not to be considered for RGMO/FGMO
with MI analysis since fall in frequency was only 0.07 Hz (reportedly in steps).
MS, SRPC emphasised the importance of RGMO / FGMO with MI and reminded
that ED, SRLDC in the AGC meeting held on 19.09.2018 had stated that non-
implementation of primary response, AGC and grid requirements for RE
(including LVRT) was a certain recipe for grid disturbance and all the stake
holders needed to take definite action in this regard.
Krishnapattnam (APGENCO-JV) informed that they had modified the logic in
July 2018 and the performance would be monitored.
NLC informed that they constituted an internal team to review the RGMO
performance and the performance would be reviewed.
NTPL informed that the RGMO logic was modified in December 2017 and the
performance was under review.
Ramagundam, NTPC informed that Unit-I, II & III controllers along with turbines
were planned to be replaced during 2019-20 and then the response can be
expected.
Simhadri, NTPC informed that the logic of disabling the RGMO at technical
minimum has been disabled from April 2018 for Stage-II and August 2018 for
Stage-I.
It was noted that the response of Talcher Stage-II was poor and there was no
representation by Talcher Stage-II.NTPC, SRHQ was requested to kindly take up
the issue with Talcher Stage-II.
SEIL informed that TPCIL units RGMO logic has been modified during 1st week
of November 2017 and for SGPL units in June 2018. The performance was under
review.
It was noted NTECL had put an alarm during triggering of RGMO requirement
and during such incidents; the operators suspend the normal scheduling
RGMO/MVAR Meeting – 26.09.2018 Page 3
requirements for few minutes. The generators were requested to consider the
option if found feasible.
KPCL informed that BTPS Unit-I & II RGMO logic has been modified during
December 2017. Unit-III logic modification would be carried out during the
shutdown (which is undergoing).
KPCL informed that the RGMO had some issue at Raichur Unit-IV, the
rectification would be considered during major overhaul.
UPCL informed that they had implemented the same logic deployed at Tiroda and
fine tuning was being carried out. As recommended in the 8th
meeting, the dead
band was removed soon after that meeting.
TANGEDCO informed that the DCS was to be replaced for Unit-I & II at Mettur.
PO would be placed and by December 2018, the commissioning was expected. In
some instances of rise in frequency since the machines were on FGMO with MI,
the operator had given a command on the alarm for increasing the generation.
TANGEDCO informed that at Mettur stage-III, the logic had been modified in
July 2018 and the response would be monitored. TANGEDCO confirmed that the
dead band in the operating frequency range had been disabled.
TANGEDCO informed that for NCTPS stage-I Unit-I the PO for DCS would be
placed within a week and it would take 2-3 months to complete the work. The
logic would be implemented and response would be monitored.
TANGEDCO informed that for NCTPS stage-II the revised logic had been
implemented from 04.10.2018 and the performance was under review.
TANGEDCO was requested to assess the settings of RGMO at Tuticorin
(Hydraulic Governor) as there was no response during rise in frequency incidents.
TSTRANSCO informed that Singareni Unit-I, the revised RGMO logic had been
implemented from June 2018 and the response would be monitored.
KPCL informed that at load less than 50%, the RGMO was disabled.
It was pointed out that the RGMO/FGMO with MI was to be in place at all
loadings.
NTPC informed that at Kudgi Unit-I & II, the revised logic had been implemented
two months back and fine tuning was being undertaken.
KPCL agreed to look into the non-response at Kadra. The data recording facility
at Nagjheri was being undertaken. At Supa, the RGMO / FGMO with MI was not
possible due to head and balancing reservoir (for Nagjheri) constraints. It was
pointed out that the exemption can be sought from Hon’ble Commission until that
time, the performance would be measured.
KSEBL informed that logic at Idukki Units-I to III would be modified and tuned
after the R&M.
Summary / Recommendations
The generators pointed out that in some cases; there was discrepancy in the output at
the generator vs the results in the report. The observations with actual performance
had been communicated to the SLDCs but had not reflected in the report.
RGMO/MVAR Meeting – 26.09.2018 Page 4
SRLDC & SRPC pointed out that the analysis was being discussed in the respective
OCC meetings and any anomaly needed to be rectified at that time. The state
generators needed to coordinate with the SLDCs to address the mismatch between
the SCADA and the response at the generator terminals.
In view of the above, it was agreed that the spreadsheet with the response would
be communicated by SRLDC (by 28.09.2018) and the state generators needed to
interact with the SLDCs to ensure that the response observed at the generator
terminal is reflected in the reports after thorough validation by the SLDCs by
05.10.2018.
The unit-wise / station-wise response / analysis would be communicated after
incorporating the comments / feedback.
In Petition No. 302/MP/2013 ( Date of Order : 23.10.2015), Hon’ble CERC had
directed in the Order, ‘However, SLDCs are not reporting the performance of the
generators on regular basis. Accordingly, SLDCs/RLDCs are directed to keep watch
on the response of generators during major frequency excursions and submit report
on quarterly basis to SERCs and POSOCO. SLDCs, through their respective
SERCs, may also initiate action against defaulting State`s generators in
accordance with the provisions of the Grid Code.’
In Petition No. 84/MP/2015 (Date of Order: 31.07.2017) Hon’ble CERC had directed
the following :
‘(a) Considering the fact that further measures have been put in place to facilitate
desirable primary response, the Commission, starting from the month of
September, 2017 shall be closely watching the primary response of ISGSs as
reported by POSOCO/NLDCs. At the State level, SLDCs shall report the
frequency response of intra-State generators to the concerned SERCs.
(b) NLDCs and SLDCs through the assistance of POSOCO shall start the process
of selecting independent third parties capable of undertaking periodic checkups to
monitor the RGMO/FGMO response. To start with selected independent third
parties shall be sent to the generating stations which are not providing the desired
RGMO/FGMO response. Independent Third Parties shall ensure that the
generator has not, in any way, prevented/disabled the governor from providing
the desired response. In case, even after enabling the governors, units are not able
to provide the desired response as per the provisions of the Grid Code, third
parties, based on the submissions of the generators, shall bring out the technical
constraints, if any, which limit the primary response of the units.
c). All ISGSs are directed to provide primary response compulsorily in terms of
Regulation 5.2 (f), (g), (h) and (i) of the Grid Code failing which we would not
hesitate in initiating action under Section 142 of Electricity Act, 2003 for not
providing desired RGMO/FGMO response without any valid reasons’.
It was noted that number of units were not giving desired performance in number of
incidents. It was also felt that adequate monitoring / follow-up was not being carried
out by SLDCs for the non-performance of the units. The generators needed to
interact with the SLDCs for non-performance on the applicable incidents (generators
sought one month time to complete the activity). Therefore, it was agreed that a
VC held with the SLDCs (one at a time) after one month with participation by
RGMO/MVAR Meeting – 26.09.2018 Page 5
SRLDC& SRPC to review the performance. Inadequate response was needed to
be taken up by SLDCs with respective SERC’s in line with Hon’ble CERC
Orders in respect of Petition No. 84/MP/2015 and 302/MP/2013.
The non-performance of the generators under SRLDC control would be taken
up by SRLDC with the respective generators.
Logic implemented at few generators where RGMO response is satisfactory is
enclosed at Annexure-II (SRLDC letter dated 12.06.2017). All the Generators to
note that this was only for understanding but each generator had to ensure RGMO
compliance as per IEGC and as per their machines make, vintage, DCS etc.
It was noted that some of the generators were disabling RGMO without informing /
concurrence from SLDC/SRLDC. The IEGC provision states ‘5.2(f)(ii)(c) if any of
the generating units is required to be operated without its governor in operation as
specified above, the RLDC shall be immediately advised about the reason and
duration of such operation.’ The IEGC provision needed to be complied.
The following Regulation had been added in the 5th
Amendment to IEGC
‘For the purpose of ensuring primary response, RLDCs/SLDCs shall not schedule
the generating station or unit(s) thereof beyond exbus generation corresponding to
100% of the Installed capacity of the generating station or unit(s) thereof. The
generating station shall not resort to Valve Wide Open (VWO) operation of units
whether running on full load or part load, and shall ensure that there is margin
available for providing Governor action as primary response. In case of gas/liquid
fuel based units, suitable adjustment in Installed Capacity should be made by
RLDCs/SLDCs for scheduling in due consideration of prevailing ambient conditions
of temperature and pressure vis-à-vis site ambient conditions on which installed
capacity of the generating station or unit(s) thereof have been specified’.
SLDCs were suggested to ensure that the schedules are restricted to normative exbus
generation. The generators were suggested not to resort to VWO and maintain
generation as per the coal quality/ system/machine parameters and keep the margins
for RGMO / FGMO with MI at all instances.
SRLDC informed that any incident from now would be analysed in detail and if there
was no significant improvement, they may be constrained to approach Hon’ble
CERC through petition.
It was suggested that wherever FGMO with MI is implemented, a discernible alarm
for rise in frequency / fall in frequency needs to be implemented to avoid such
adverse operations.
RGMO status points to be configured to SLDC / SRLDC SCADA would be discussed
in the VC with individual states.
As there was no representation by some of the SLDCs, it was noted that the FRC
computation would be discussed in the VC with individual states.
As per 5th
Amendment to IEGC, gas stations above 50 MW Installed Capacity were
also to come under RGMO/FGMO operation w.e.f. 1st October 2017. Status update
in this regard would be discussed in the VC with individual states.
RGMO/MVAR Meeting – 26.09.2018 Page 6
The need for testing of RGMO response at the field emerged as the response was not
forthcoming. In this regard, para under Regulation 5.2(h) as per 5th
Amendment of
IEGC was noted, ‘Provided that periodic checkups by third party should be
conducted at regular interval once in two years through independent agencies
selected by RLDCs or SLDCs as the case may be. The cost of such tests shall be
recovered by the RLDCs or SLDCs from the Generators. If deemed necessary by
RLDCs/SLDCs, the test may be conducted more than once in two years’.
SRLDC stated that they would revert back on this after discussing with NLDC.
SLDCs are requested to ensure compliance of the above Regulation.
3. MVAR Issues
The data for MVAR interchange was sought for the period from April 2017 to August
2018.
Stations not submitted the data:
APGENCO: VTPS, RYTPS, U_Sileru & L_Sileru
TS: Singareni
KAR: YTPS (KPCL), UPCL
TANGEDCO: MTPS-III, NCTPS & Kadamparai
NPCIL: KGS & MAPS
NTPC: RSTPS, Talcher-II & Kudgi
NLC: NLC-I, I Exp, II, II Exp
ISGS: SEL & SEIL
Station submitted data but not in format/consolidated: All stations data received
from KSEBL (for one month), NTPL, SDSTPS and all hydro data received from
KPCL
Station submitted consolidated data in format: Simhadri, NTECL, IL&FS, NTPL,
KKNPP, MEPL, JSWEL, BTPS, TTPS, MTPS1, HNPCL, COASTAL, SGPL,
KTPP, N’SAGAR, SSLM LB, SSLM RB
SRLDC made a presentation on MVAR interchange (Annexure-III) for the
period from April 2017 to August 2018.
MVAR Inter-change analysis:
AP
Station Unit No. Comments/Remarks
HNPCL
Station Both the units injecting at the voltages below
410 kV and absorbing up to 170 MVAR above
410 kV
SSLM RB Station All the units were absorbing as per capability
TS
Station Unit No. Comments/Remarks
KTPP Station Data not submitted in proper format
RGMO/MVAR Meeting – 26.09.2018 Page 7
KTPS Station Data submitted partially
N’SAGAR Station
All the units absorbing up to 20-30 MVAR
over 215 kV-235 kV range. Tap position data
not given.
SSLM LB
Station All the units were absorbing as per capability.
And, absorbing around 60-70 MVAR in
condenser mode
Karnataka
Station Unit No. Comments/Remarks
BTPS-KPCL Station Both the units injecting at the voltages below
405 kV and absorbing upto120 MVAR above
405 kV
JSWEL Station All the units were found to be absorbing upto
75 MVAR and injecting up to 100 MVAR
Kerala
Station Unit No. Comments/Remarks
All hydro (>50 MW) Station Only one month data submitted
Tamil Nadu
Station Unit No. Comments/Remarks
TTPS-TANGEDCO Station Injecting at the voltages below 237 kV. All the
units were found to be absorbing upto 30-50
MVAR
MTPS1-TANGEDCO Station All the units were injecting as per requirement
and found satisfactory
NPCIL
Station Unit No. Comments/Remarks
KKNPP Station
Both the units were found to be absorbing up
to 170-190 MVAR, and injecting upto 300
MVAR
NLC/NTPL
Station Unit No. Comments/Remarks
NTPL Station
Unit1: Found to be absorbing upto 150
MVAR
Unit2:Data not submitted properly
NTPC/NTECL
Station Unit No. Comments/Remarks
Simhadri Station All the units were found to be satisfactory.
NTECL Station All units were found to be injecting when
voltages were less than 400 kV. Units were
injecting/absorbing up to 180 MVAR between
RGMO/MVAR Meeting – 26.09.2018 Page 8
400-410 kV. Above 410 kV, units are
absorbing and were found to be satisfactory.
IPPs
Station Unit No. Comments/Remarks
COASTAL
1
Absorbing up to 130 MVAR (Capability
around 200 MVAR) above 410 kV. Desired
absorption above 400 kV.
2 Absorbing up to 120 MVAR (capability
around 200 MVAR) above 410 kV. Desired
absorption above 400 kV.
IL&FS Station
Both the units absorbing upto 110-125 MVAR
(Capability around 170 MVAR) above 405
kV. Desired absorption above 400 kV.
MEPL Station Both the units were found to be absorbing as
per the agreed quantum.
SGPL Station
Both the units were found to be absorbing
130-140 MVAR, (Capability around 170
MVAR@ 600 MW, 280 MVAR @ 500 MW)
Seems limiter at 140 MVAR, more MVAR can
be absorbed at lower MW Generation.
Summary / Recommendations
It was noted that many of the stations had not furnished the MVAR interchange
details and therefore, a comprehensive exercise could not be carried out. Therefore, it
was agreed that SRLDC would communicate the format (along with the guidelines to
fill the format). The data for the period from April 2018 to September 2018 needs
to be furnished. The SRLDC controlled stations response would be analysed in
the OCC meeting. The state embedded generators need to furnish their
response to the SLDCs (with a copy to SRLDC/SRPC) and unit-wise / station-
wise analysis would be carried out after through VC with individual SLDCs
(after the RGMO VCs).
It was noted that there were still some margins available as per Capability Curve
and generators could consider improving the MVAR interchange.
It was noted that few units were not keeping the Vref to nominal and were changing it
manually to control / restrict the MVAR interchange. This was to be discontinued.
SLDCs would discuss the MVAR issues for embedded generators along with
RGMO/FGMO issues.
SRLDC would take up the status point availability to SRLDC of the GT taps for ISG
stations, wherever not extended.
RGMO/MVAR Meeting – 26.09.2018 Page 9
4. Conclusion
Member Secretary, SRPC thanked the participants for their active inputs and valued
contributions and hoped that the generators would take steps to improve the
RGMO/MVAR performance.
*******************