Typical construction process: Jefferson Ave. phase I, Napoleon Ave. - phase 2, Claiborne Ave. - phase 1 and 2. 1. Existing sewer and water mains are relocated, if necessary 2. Timber pile supported box: timber and sheet piles are installed 3. Excavation of Material Southeast Louisiana Urban Flood Control Project (SELA) Board 1 of 2 1 2a 3b 2b 3a

Southeast Louisiana Urban Flood Control Project (SELA ... · 1. Existing sewer and water mains are relocated if necessary. 2. Jet grout supported box: sheet piles are installed and

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Southeast Louisiana Urban Flood Control Project (SELA ... · 1. Existing sewer and water mains are relocated if necessary. 2. Jet grout supported box: sheet piles are installed and

Typical construction process: Jefferson Ave. – phase I, Napoleon Ave. - phase 2, Claiborne Ave. - phase 1 and 2.

1. Existing sewer and water mains are relocated, if necessary

2. Timber pile supported box: timber and sheet piles are installed

3. Excavation of Material

Southeast Louisiana Urban Flood Control Project (SELA) Board 1 of 2

1 2a

3b

2b

3a

Page 2: Southeast Louisiana Urban Flood Control Project (SELA ... · 1. Existing sewer and water mains are relocated if necessary. 2. Jet grout supported box: sheet piles are installed and

4. Box culvert construction takes place

5. Materials are backfilled into the ground

Typical construction process: Jefferson Ave. – phase I, Napoleon Ave. - phase 2, Claiborne Ave. - phase 1 and 2.

Southeast Louisiana Urban Flood Control Project (SELA) Board 2 of 2

6. Roadway is restored

Page 3: Southeast Louisiana Urban Flood Control Project (SELA ... · 1. Existing sewer and water mains are relocated if necessary. 2. Jet grout supported box: sheet piles are installed and

1. Existing sewer and water mains are relocated if necessary.

2. Jet grout supported box: sheet piles are installed and jet grout operations take place.

3. Materials are excavated.

Typical construction process: Jefferson Ave. – Phase 2, Napoleon Ave. – phase 3 and Louisiana Ave.

Southeast Louisiana Urban Flood Control Project (SELA) Board 1 of 2

1 2a 2b

3a

3b

Page 4: Southeast Louisiana Urban Flood Control Project (SELA ... · 1. Existing sewer and water mains are relocated if necessary. 2. Jet grout supported box: sheet piles are installed and

4. Box culvert construction takes place

5. Materials are backfilled into the ground

Southeast Louisiana Urban Flood Control Project (SELA) Board 2 of 2

6. Roadway is restored

Typical construction process: Jefferson Ave. – Phase 2, Napoleon Ave. – phase 3 and Louisiana Ave.