Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Typical construction process: Jefferson Ave. – phase I, Napoleon Ave. - phase 2, Claiborne Ave. - phase 1 and 2.
1. Existing sewer and water mains are relocated, if necessary
2. Timber pile supported box: timber and sheet piles are installed
3. Excavation of Material
Southeast Louisiana Urban Flood Control Project (SELA) Board 1 of 2
1 2a
3b
2b
3a
4. Box culvert construction takes place
5. Materials are backfilled into the ground
Typical construction process: Jefferson Ave. – phase I, Napoleon Ave. - phase 2, Claiborne Ave. - phase 1 and 2.
Southeast Louisiana Urban Flood Control Project (SELA) Board 2 of 2
6. Roadway is restored
1. Existing sewer and water mains are relocated if necessary.
2. Jet grout supported box: sheet piles are installed and jet grout operations take place.
3. Materials are excavated.
Typical construction process: Jefferson Ave. – Phase 2, Napoleon Ave. – phase 3 and Louisiana Ave.
Southeast Louisiana Urban Flood Control Project (SELA) Board 1 of 2
1 2a 2b
3a
3b
4. Box culvert construction takes place
5. Materials are backfilled into the ground
Southeast Louisiana Urban Flood Control Project (SELA) Board 2 of 2
6. Roadway is restored
Typical construction process: Jefferson Ave. – Phase 2, Napoleon Ave. – phase 3 and Louisiana Ave.