    Palo Alto Library Projects

    Bi-Monthly Progress ReportJuly August 2012

    Mitchell Park Library & Community Center

    Main Library

    Attachment C

  • 7/28/2019 Snapshot 1365

    2/9

    Table of ContentsMitchell Park Library

    Status ReportManagement SummaryAction ItemsSchedule Milestones

    Main Library

    Status Report Management Summary

  • 7/28/2019 Snapshot 1365

    3/9

    Mitchell Park Library &

    Community Center

    3700 Middlefield Road, Palo AltoThe new Mitchell Park Library and Community Center is a highly

    sustainable joint-use facility that will be a vibrant destination for

    civic, cultural, social, educational, and recreational activities. The

    new center, which will replace undersized and aged facilities, is

    made possible through Measure N and the strong partnershipbetween the city and the community. During construction,

    temporary library and teen center facilities are available at the

    Cubberley Community Center.

    PROJECT CONSTRUCTION

    CONSTRUCTION BEGAN:

    September 2010

    ANTICIPATED OPENING:

    Spring 2013

    PROJECT TEAM

    OWNER:

    City of Palo Alto Public Works

    (650) 329-2295

    ARCHITECT:

    Group 4 Architecture,Research + Planning Inc.

    South San Francisco, CA

    (650) 871-0709

    GENERAL CONTRACTOR:

    Flintco Pacific, Inc.

    Roseville, CA

    (916) 757-1000CONSTRUCTION MANAGER:

    Turner Construction Company

    San Jose CA

  • 7/28/2019 Snapshot 1365

    4/9

    Window Trim Installation at Multi Purpose Solar Hot Water Panels Installed

    Clerestory Glass for Natural Lighting

  • 7/28/2019 Snapshot 1365

    5/9

    Mitchell Park Library & Community Center

    Management Summary

    July - August 2012

    Noteworthy Accomplishments

    Exterior Glass, Plaster and Metal Siding are complete

    Solar Hot Water Panels are installed

    Raised Flooring nears completion and drywall has started

    Current Project Challenges:

    Processing the high volume of change documentation and providing directionSettle tube steel and exterior wall framing changes (Ready for Council approval)

    Settle waterproofing and sheet metal changes (Estimate complete)

    Significant number of new COR to review

    Submittals impacting material delivery and inspection (In progress but nothing completed)

    Photovoltaic systems need separate permits

    Deferred submittals for glass railings, elevators and library shelving need to complete plan check

    SafetyPublic Safety is a priority outside the fence. No incidents reported to date

    School resumed smoothly without any safety issues from construction

    Quality Control

    City and Special Inspection Work:

    Work needs to be ready when inspection is requested

    Work should pass inspection the first time around

    Quality Control Observation Reports : 56 have been issued and 12 remain openCourtyard Concrete benches finishes need remedial work.

    Exposed exterior steel needs welds ground smooth and finished with a protective coating

  • 7/28/2019 Snapshot 1365

    6/9

    Mitchell Park Library & Community Center

    Schedule Milestones

    July - August 2012

    ACTIVITY ACTIVITY I.D. Bldg-A Bldg-B Bldg-C

    Pad Certification 10/27/10 10/27/10 10/27/10

    Foundation Complete 12/28/11 1/16/11 1/7/11

    Frame & Place Slab on Grade 2/11/11 5/6/11 5/3/11

    Top out Structural Stee l Frame 5/31/11 4/15/11 5/12/11

    2nd Floor Poured 4/16/11 X X

    Roof Poured 5/31/11 6/24/11 6/21/11

    Frame Ext Walls EXT 4000 9/2/11 9/26/11 9/2/11

    Building Dried In EXT 5555 6/8/12 6/8/12 6/8/12

    Frame Interior Walls INT 1130 5/24/11 6/1/11 7/1/11

    Hang Drywall Start 1 INT A1085 B1080 C2330 9/6/12 8/8/12 8/6/12

    Ceiling Start (MEP inspections pass)2 INT A.B.1220, C1270 9/25/12 9/20/12 9/25/12

    Drywall Finished INT A1080 B1080 C1090 10/4/12 10/4/12 10/3/12

    Ceiling Tile Finished FIN 1120 11/27/12 11/8/12 11/12/12

    Completion DateFlintco Monthly Schedule update 8-15-12

  • 7/28/2019 Snapshot 1365

    7/9

    Main Library

    1213 Newell Road, Palo Alto PROJECT CONSTRUCTIONCONSTRUCTION STARTS:

    Summer 2013

    ANTICIPATED OPENING:

    Fall 2014

    PROJECT TEAM

    OWNER:

    City of Palo Alto Public Works(650) 329-2295

    ARCHITECT:

    Group 4 Architecture,

    Research + Planning Inc.

    South San Francisco, CA

    (650) 871-0709

    CONSTRUCTION MANAGER:TBD

    FOR MORE INFORMATION

    The Palo Alto Main Library renovation and addition is in the

    final phase of designBetter Libraries for Palo Alto projects,

    funded by the passage of Measure N by voters in 2008. The

    project incorporates upgrades to the historic buildings structural,

    electrical and mechanical systems while preserving the integrity of

    architectEdwards Durrell Stones iconic design. The new

    addition includes a program room and additional restrooms

    to extend the services of this heavily-used branch. The

    project targets LEED certification.

  • 7/28/2019 Snapshot 1365

    8/9

    Library Closure Plan

    July - August 2012

    Downtown Library re-opened

    Mitchell Park Library and Community Center construction started,

    College Terrace Library re-opened

    2010

    2011

    2012

  • 7/28/2019 Snapshot 1365

    9/9

    printed 9/11/2012

    MEASURE

    N

    ENGINEER'S

    ESTIMATEPROJECTED RESERVES

    09010 Cubberley Temporary Library 645,000 619,687 25,313

    09005 Downtown Library 4,000,000 5,212,000 4,418,111 793,889

    09006 Mitchell Park Library & C.C. 50,000,000 49,043,000 41,411,673 7,631,327

    11000 Main Library 18,000,000 20,100,000 21,682,800 -1,582,800

    11010 Art Center Temporary Library 500,000 500,000 0

    Bonding and Financing Costs 4,000,000 500,000 500,000 0

    BONDED AMOUNT 76,000,000 76,000,000 69,132,271 6,867,729

    data 8/28/12 - - -

    July - August 2012 Update

    PALO ALTO LIBRARIES

    BOND MEASURE N PROJECTS

    FINANCIAL SUMMARY

    BUDGET COSTS

    The combined projects currently have projected cost reserves of $6,867,729. Notes on Projected Cost:Temporary Library at Cubberley finished below estimate. Balance is held for move out costs.

    Downtown Library is now finished. Final Cost will update when all contracts are closed out.Mitchell Park Library and Community Center bids were significantly below estimate.

    Pending Design and C.M. Contract amendments are not included and will affect Reserves.

    Bond costs were reforecast and the financing budget was reduced to $500,000.

    Main Library is still the June 2012 estimate

    Turner's updated estimate is under review by Public Works Engineering.

    Council increased Project Scope. Projected Cost includes current estimated cost increases.

    Projected Costs are based on contracts awarded to date with their full contingency authorization.

    Projected Costs for contracts not yet awarded are based on the current estimate.

    Reserves will adjust as future contract awards are made.