26
On the cleaning system incident at the Paks NPP Presented by Dr. Lajos Voross Hungarian Atomic Energy Authority

Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

On the cleaning systemincident at the Paks NPP

Presented

by

Dr. Lajos VorossHungarian Atomic Energy

Authority

Page 2: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Contents

REvent sequence (early phase)HLayout of the deviceRReleasesHEvent sequence (later phase)HMeasured 1-131 activitiesMA possible explanationHNext stepsHReport by the NPPHHAEA investigation

2

Page 3: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

I'

Event sequence (early phase)

#Crud deposition on fuel assemblies in three unitsdue to earlier decontamination procedures

H 15,03. - installation of fuel assembly cleaningdevice (Framatom ANP)

HCleaning of two loads (30 assemblies each)H29.03. - shutdown of unit 2MCleaning of three loads from unit 2H09.04 - start of cleaning the fourth load from unit 2H 10.04. 16:30 - end of cleaningNOpening of cleaning tank postponed for other

activities on the critical path3

Page 4: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

f

Event sequence (early phase)R 10.04, 22:00 - increase fK-85-dose rat6i de-tected311.04. 02.15 - Lid lock opened, bubble outburstM11.04. 04:20 - unsuccessful attempt to open the

vessel-lid (rope rupture), vessel semi-open" Elevated release of noble gases and iodine through

the NPP stack" Elevated, but <500 nSv/h dose rate at one of the

9 near-station monitors for a short period(background value: 100 nSv/h)

HNo other off-site effect detectedH Classified to INES level .239 Extensive field exploration and monitoring initiated

Page 5: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Structure of the tank

z- • .- __• .,.• •,Guide plateo

-•4- •- - utleO

~Lower holder plat~ !5

Sa Ise99a

.- j4.-r -11

L ..v

3rd figure

Page 6: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Functional layout of the system- - - *•- • -• .. ....... . . ... n... -..... . . . - - -... . ... ..

6

Page 7: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

-I"

Layout of the B operating mode- ~ ~ ~ ~ ~ ~ ~ ~ ~ . t ., .- .I-T rr -r~w

7

Page 8: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Events during the incident

-14.5013-07

4.O00-E--07

3,50E-+07

II__________________ ________

3 ~ 24 lp.'0 00

1 ,50r--407.

1 .001--#07

5,00I1-.--06

0.0010-apr-2003 15:00

End of cleaning 16:00

I, I-apr 22:01I I-apr-2001 02:-0 [I I apt-2003 10:00l [ ]~T Cover lifting unsuccesful

Surroundings of spent f. p. 12 mSv/h 02:45Start of submersible pump 16:40Discharge wash.c. 16:56

Elevated water-level of spent fuel pool 19:20The lock is opened, big bubble outbursts 02:15 I

Venting fans started 23:45

KR-85 activity increased in cleaning system 21:50 IIDE ordered the leaving of rect. hall 23:308

Page 9: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

lJ

Noble-gas release

180

160

140

120

100TBq 80 6

60

40

20

0 4.5*AtAI 2fjofe)H21

9

Page 10: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

131 I-equivalent release.... .. ,• :• • .....:....: .................. _::• •.. ' '=.;::••. _•_•• •• • :I:•:,_. : _.. . .. -.

200

180

160140

120GBq 100

80

60

40

20

0

?04

143

7.76 1.35 1.61 0.98 0.35 0.43I I i

.4~L.L........4......L............L I * ' I I - I ______ I II I I I I ! I

10

Page 11: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Aerosol release

Radioaeroszol kibocsit~is

CL

rn

3000

2500

2000

1500

1000

500

03.29'~ b.f'.5 11.33! 11.07ý O.63ý 0.07 0.53ý '0.211 '.04,' ý0.02ý '00.0.3;4O02

~x. \ -,C)

II

Page 12: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

.11

Event sequence (later phase)H 16.04 - successful attempt. to remove lid# remote camera-snapshot taken#fuel assemblies highly damaged but not meltedc NPP Emergency Preparedness Organisation alerted,

HAEA notifiedH HAEA NERO alerted, IAEA and neighbouring

countries notifiedH"Communication emergency"U Reclassification to INES 3MAnalysis of possible scenarios, no change in plant

status nor in radiation circumstances12

Page 13: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

,4 I

Event sequence (later phase)

" Framatom and Russian experts invited" Radiation evaluation three times a day - continuos

decrease (c.f. figures above)" Noble gas overestimation for deposition in deviceMAnalysis of possible criticality - keff is below 0.95 if

CBoron is about 16 g/kg (actual value was 15.3 g/kg)HAddition of boron acid, installation of neutron and

thermal measurementsP20.04. 09:00 - emergency state called off, EPO

alert is terminatedHIntensive media, professional and political interest

13

Page 14: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

+It

Wind-trajectories

Sogo@o

0o 0o

A A A0

*0A

00

A*

AAv

1 0 0 0

(000

0 00

* @ 0

0

0

0

0

/7

18 h (11. April 2003)15 h (11. April 2003)12 h (11. April 2003)09 h (11. April 2003)06 h (11. April 2003)03 h (11. April 2003)00 h (11. April 2003)21 h (10. April 2003)18 h (10. April 2003)

Trajectories

)0 0

0

014

Page 15: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Specific activity of 1-131 inplants

N

E

S

1-131 a, Bq/kg® <0.5® 0.5-1.5® 1.5-5* 5-15* 15-100/ <500

N Trajectol

fresh weight

15ries

Page 16: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Specific activity - near Paks-------------.

~.--~-..--.-----

w E

S

1-131

00

0

a, Bq/kg fresh<0.50.5-1.51.5-55-1515- 100< 500

Page 17: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

A possible explanation

9 Post-cleaning cooling insufficient for coolant by-pass

N Evolution of a steam-cushion3 Gap release due to assembly dry-outHThermal shock or steam explosion after lid opening

crushes the assembliesInvestigation and verification is still underway

17

Page 18: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

0

Next steps

RDedicated team of NPP for consequencemanagement

HKeeping stabilised the assemblyHIsolation and safe deposition of wasteM Decontamination of the poolsHRestart of Unit 2HLessons learned, drawing conclusionsHReporting

18

Page 19: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Report submitted by the NPP

1FlSubmission: 11. May 2003. to HAEAZIMain chapters:

FShort summary of the incidentEHEvaluation of the incident covering radiation

protection, technological circumstances, activity of thestaff, documentation, efficiency of self-inspections,causes of fuel damage

ElNon-conformities detected during the investigation,ElConsequences and safety impacts of the incidentFNecessary countermeasures

19

Page 20: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Main conclusions of the NPP

HImmediate cause: insufficient coolingHPlans have not secured sufficient cooling for

every possible caseHSafety analysis has not covered in-vessel

flow-patterns for B-mode coolingHPlans for. system-parameter control have not

garanteed recognition of insufficient cooling

20

Page 21: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

ii• k .I •

Independent HAEA investigation

HData collection phase (interviews, minutes,op. data, records) closed

P.Report to be ready by end of MayHShall also include the regulatory assessment

of the NPP reportsHAccounts also for the activity of the

regulatory body

21

Page 22: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

'3. 6 4

Contents of the HAEA report

rJCharacteristic data of the incidentEr-Preceding events and their evaluationIllEvent sequence of the incidentFl-Process followed by the HAEAFlCauses of the incident

iDeviations (malfunctions) leading to the incidentI[Evaluation of related operator's actionsIlNuclear and environmental safety assessmentsIFlNecessary countermeasures

22

Page 23: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

Summary

of the serious incident on the unit 2 of Paks NPP, set in on the 10 th April 2003

The Unit 2 of Paks NPP was shut down for yearly refuelling and maintenance works on 2 9th

March. In addition to the routine operations, maintenance works included chemical cleaning

of the fuel assemblies unloaded from that unit. This operation has been performed in a

dedicated tank housing 30 assemblies, about one tenth of the full load of the reactor. The

same cleaning system has previously been used without any troubles for cleaning 5 charges of

assemblies. Cleaning of fuel assemblies has been carried out at the plant for two years

because of excessive deposition of corrosion-type material in the assemblies. The cleaning

process applied is not a routine process and it is not part of the regular activities of the outage.

The cleaning of the sixth charge was started on 9 th April 2003 and was terminated in the

afternoon of 10th April 2003. On the same day, late in the evening, the radiation monitoring

system indicated the presence of radioactive gases. Leakage in one or a few fuel assemblies

was assumed. Consecutively the removal of the lid of the cleaner tank was decided. The

removing operation was unsuccessful due to the break of the lifting rope, and the lid remained

in a partially lifted position on the cleaning tank.

Paks NPP issued a press release about the event and notified also the Hungarian Atomic

Energy Authority (HAEA). The event has been rated Level 2 on the International Nuclear

Event Scale (INES). The HAEA notified the International Atomic Energy Agency and issued

a press release with its own evaluation of the situation.

The Paks NPP and the Hungarian Atomic Energy Authority have started independent

investigation of the incident. Contrary to its routine practice the Nuclear Safety Directorate of

the HAEA established a Special Event Investigating Team.

After several attempts, on 16 th April the lid of the fuel-cleaning tank was successfully

removed. Thereafter, following a predefined programme, they performed visual inspection in

the cleaning tank using a video camera. In spite of the original suppositions, the visual

inspection gave evidence of all of the 30 assemblies being damaged and a number of heavily

damaged assemblies. were observed. Having studied the pictures, the NPP declared the site

emergency state and the severity of the incident was increased to Level 3.

Page 24: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

The radioactive materials released from the plant have been measured continuously.

Furthermore a concise sample collecting field activity has been initiated soon after the release

in order to scan the near and broader vicinity of the plant.

According to the plant measurements the release of airborne radioactivity can be character-

ised by the following values:

Period Noble gases [TBq] Iodine ("'"I) equivalent [GBq]

10th April 12 143

11 t"April 160 204

12t" April 25 7.0

13-19 April 179* 5.7*

20-26 April 38* 0.8*(*Attention: The figures stand for 7 days. For getting the daily average, it should be divided

by 7).

The monitoring stations located within the 1.5 km vicinity of the plant (consisting 9 stations

measuring gamma-dose-rates) have not shown any increase above the daily fluctuations

related to the circa 100 nSv/h average value, except for one station showing a marked increase

up to 260 nSv/h, for a short time on I 11t April. However, the value remained much lower than

the warning limit of 500 nSv/h. Such values often occur in the environment after a heavy rain

because of the natural radioactivity. As a matter of fact this is negligible from the point of

view of possible human exposure.

Field measurements in the plant and in the surrounding area yield as typical values of 1 13i

surface contamination between a few Bq/m2 and a few hundred Bq/m2 . The highest level

detected in the close vicinity of the plant was less than one thousandth of the average

contamination in Hungary following the Chernobyl accident. No activity due to the event has

been found in milk samples.

Correspondingly no countermeasures whatsoever have been introduced or are foreseen on-site

or out of the site.

Page 25: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

a

On 2 0 th April 9:00 a.m. in view of the stabilised and safe condition of the cleaning system the

NPP has declared the end of the emergency state and terminated the activity of its emergency

preparedness organisation.

The power plant continues elaborating measures for decreasing the radioactivity release as

well as for reinforcing the safety of the damaged fuel assemblies in the cleaning tank.

Calculations and measurements prove that at the present level of boric acid concentration

(16g/kg) in the tank and the surrounding water pool the fuel-coolant system in the cleaning

tank is safely sub-critical and its cooling is sufficient. Redundant measurements and pumps

have been installed. The power plant formed a working group for mitigation of the

consequences of the incident (removal, management and storage of damaged fuel assemblies

and possible other fragments arising from the incident and transportation of the cleaning

tank).

As part of its independent investigation of the incident the HAEA carried out several site

inspections at the Paks NPP. During the inspections the authority asked for additional written

and video documents from the NPP and interviews were made with the employees taking part

in the activities related to the incident. The investigation focused on the following issues:

* event sequence of the incident, activities after the incident and measures for

mitigating the consequences

* cleaning technology applied, condition of the equipment and devices, processes

" decisions, persons making the decisions and their competencies

A resolution issued by the HAEA requires the Paks NPP to revise its plans of the outage of

the second unit in the light of the present situation and also requires the NPP to submit the

modification to the HAEA for approval.

On 11 May 2003 the Paks NPP submitted its report to the HAEA in accordance with its

legally stipulated obligations.

The report of the NPP consists of the following main chapters:

" Short summary of the incident" Evaluation of the incident covering radiation protection, technological circumstances,

activity of the staff, documentation, efficiency of self-inspections, causes of fuel damage

Page 26: Slides: On the cleaning system incident at the Paks NPP. · 10th April 12 143 11 t"April 160 204 12t" April 25 7.0 13-19 April 179* 5.7* 20-26 April 38* 0.8* (*Attention: The figures

" Non-conformities detected during the investigation,* Consequences and safety impacts of the incident* Necessary countermeasures

In order to thoroughly evaluate the report the HAEA started studying it without any delay.

The data collection phase of the HAEA's independent investigation has been completed. The

results will be summarised in a report and it is due by the end of May. It will also include the

regulatory evaluation on the operator's report. Other main topics of the HAEA's report will be

the following:

" Characteristic data of the incident

" Preceding events of the incident and their evaluation

" Event sequence of the incident

" Process followed by the HAEA

" Causes of the incident

" Deviations (malfunctions) leading to the incident

" Evaluation of the operator's actions in connection with the incident

" Nuclear and environmental safety assessments in connection with the incident

" Necessary countermeasures

On the basis of the HAEA's preliminary evaluation of the event the incident can be attributed

to several independent, however, interfering causes. Further investigations are needed to

reveal the fundamental technical reasons of the incident.

Budapest, 14 May 2003.