Upload
sophie-powell
View
215
Download
1
Embed Size (px)
Citation preview
SITR April 2009; Page 1
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
GREAT
GREAT: German REceiver for Astronomy at Terahertz frequencies
PI-Instrument funded and developed by
MPIfR (2.7THz channel)
R. Güsten (PI)S. Heyminck (system engineer)B. KIein (FFT spectrometer)MPIfR Engineers (electronics, LO-mechanics)
KOSMA (1.4/1.9THz channels)
J. Stutzki (Co-PI)U.U. Graf et al. (1.4 &1.9THz LO, Optics)K. Jacobs et al. (mixers @1.9THz & 2.7THz)R. Schieder et al. (array-AOS)
DLR-Berlin (4.7THz channel)
H-W Hübers et al. (IF, cold-Load, …)
MPSP. Hartogh et al. (CO-PI; CTS)
Lab-picture of GREAT equipped with theL#1 and
L#2 channel
SITR April 2009; Page 2
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Early-Science Configurations
GREAT flight configurations: baseline: simultaneous observations with 2 low-frequency channels goal: fly mid-frequency channel at the earliest possible (altitude) upgrade: operate 4.7 THz channel (not in short and basic science)
Short science configuration: baseline configuration (2 low-frequency channels)
Basic science configuration: goal configurations (combinations of the mid and low-frequency channels)
request pending for schedule adjustment with envelope expansion prior to GREAT SS flights
Channel Frequencies [THz] Astronomical lines of interest low-frequency #1 1.25 – 1.50 [NII], CO(12-11), (13)CO(13-12), HCN(17-16), H2D
+
low-frequency #2 1.82 – 1.92 [CII], CO(16-15) mid-frequency 2.4 – 2.7 HD, OH(23/2), CO(22-21), (13)CO(23-22) high-frequency 4.7 [OI]
SITR April 2009; Page 3
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Stoplight-chart
ongoing project schedule delays pose incalculable risk on integrity of GREAT project
funding at risk, more than everloosing support of interested G communitiesscience return of “investment” unpredictable for consortiumplanning of instrument developments vs. other projects is impossiblehow to restore confidence in stability of project schedule ?
not communicated welldelay of almost one year came by surprise
(old schedule was confirmed at PSR in Dec. 2008)
Item Technical ScheduleBudget RemarkStructure Finally assembledCryostat 6 units Delivered, hold-time >24hOptics works fine at 1.9THzDetectors (HEBs) 1.9THz ready, development ongoingControl-Electronics final integration ongoingIF-Processor Pre-processor ready, IF readyBackends AOS and CTS delivered/ work fineBWO-LO Works fine at 1.9THzSolid-State LO 1.4THz was operated at the APEX-telescopeSolid-State LO 1.9THz First testsresults @ 1.9THz Solid-State LO 2.7THz Design readyLaser-LO Not first flight, final assembly startedSoftware In use at KOSMA 3mAirworthiness got positive first airworthiness reportICP submitted (document package)
Comments: M-Band Solid-State-LO technical risk (not short science)
GREAT L-L configuration passed its PSR in Dec. 2008 and is ready for shipment
SOFIA schedule
SITR April 2009; Page 4
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
GREAT in L-L configuration
Power distributor
Monitor drawler
Ethernet-HUB
Obs-computer
IF-Power-supply
IF Pre-processor
IF LO-supply
IF-processor
Chopper control
SOFIA PI-rack
AOS-system
CTS #1 and #2
FFTS (see talk W4D)
Oscilloscope
LO-synthesizer #1
Optics control
Instrument computer
Mixer-BIAS #1 & #2
Power-supply
LO-synthesizer #2
1.9 THz Solid-state LO
1.4 THz Solid-state LO
Cryostats
SI mounting flange
Cold-load
Picture taken by DLR
SITR April 2009; Page 5
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Software
frontend software allows fully remote hardware access offers
a debugging GUI monitoring all software tasks an online database storing all available house-
keeping data a user GUI for easy instrument handling a KOSMA file I/O interface a Perl interface for individual hardware
programming a hardware simulation mode for development
and debugging
well tested during the PSR-tests
Obs-Software “KOSMA-control” in use at KOSMA and Nanten II well tested and understood
SITR April 2009; Page 6
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Cart
GREAT Cartfulfills all ICDs
SITR April 2009; Page 7
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Ready for Shipment
GREAT was ready for shipment by end of February as required to meet the last project schedule
customized shipping boxes availablemain-structure + cart + LOsfour boxes for cryostats aluminum boxes for electronics/ tools
Picture: GREAT main structure shipping box waiting to be stored
SITR April 2009; Page 8
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
L#2: performance goody
Best noise-performance we measured so far !
uncorrected receiver noise performance measured at 1821GHz LO frequency
SITR April 2009; Page 9
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Ongoing developments
increase usable RF-bandwidthnew HEB-mixernew cold amplifier with better matching to the mixer
no isolator required (isolator is limiting bandwidth so far)
first tests are currently ongoing in Cologne
build-up of the M-band channel (2.7THz)optics and cryostat are readyLO under development
SITR April 2009; Page 10
MPIfRKOSMAMPSDLR-Berlin
S. Heyminck, MPIfR
Schedule towards S/S flights
Schedule counts backwards from first science flight date:
start of GREAT short science period (end of May 2010)
-4 weeks schedule reserve to solve unexpected problems
-2 weeks install GREAT, EMI-test, line-Obs
-4 weeks schedule reserve to solve unexpected problems
-2 weeks re-integration and post shipment inspection
-1 weeks schedule reserve for delays during shipment
-2 weeks shipping the instrument to Palmdale
-1 weeks de-integration and packing
-8 weeks pre-shipment testing (e.g. test new mixers)
(in total 24 weeks)