Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Digby Wells and Associates
(South Africa) (Pty) Ltd
Company Registration: 2010/008577/07
Turnberry Office Park,
Digby Wells House.
48 Grosvenor Road,
Bryanston,2191
Phone: +27 (0) 11 789 9495
Fax: +27 (0) 11 789 9495
E-mail: [email protected]
Website: www.digbywells.com
Directors: J Leaver (Chairman)*,
NA Mehlomakulu*, DJ Otto, M Rafundisani
*Non-Executive
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
Audit Report
Prepared for:
Sigma Mooikraal Colliery
Project Number:
SAS5921
29 January 2020
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com ii
This document has been prepared by Digby Wells Environmental.
Report Type: Audit Report
Project Name: Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
Project Code: SAS5921
Name Responsibility Signature Date
Puleng Chabeli Report Compiler
November 2019
Barbara Wessels Reviewer
November 2019
Mia Smith Reviewer
January 2020
This report is provided solely for the purposes set out in it and may not, in whole or in part, be used for any other purpose
without Digby Wells Environmental prior written consent.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com iii
EXECUTIVE SUMMARY
Digby Wells Environmental (hereafter “Digby Wells”) was appointed by Sasol Mining (Pty) Ltd
to undertake an Environmental Audit for the Sigma Colliery: Mooikraal and the 3 Shaft
Operations (hereafter “Mooikraal”).
The audit was done in fulfilment of the performance assessment and environmental auditing
requirements specified in Regulation 55 of the Mineral and Petroleum Resources
Development Act, 2002 (Act No. 28 of 2002) (MRPDA) and associated MPRDA Regulations
(GN R527 of 23 April 2004); and Regulation 34 of the Environmental Impact Assessment (EIA)
Regulations, 2014 (GN R326 of 7 April 2017), as amended (EIA Regulations, 2014)
promulgated under the National Environmental Management Act, 1998 (Act No. 107 of 1998)
(NEMA), respectively.
Compliance with the conditions of the Environmental Authorisation (EA) and commitments of
the Environmental Management Programme (EMPR) was rated using the evaluation criteria
described in the evaluation criteria table below.
Evaluation Criteria
Non-Compliance
(NC)
These are areas were found non-compliant as observed during the site visit
to stated commitments of EMPR conditions.
Compliance (C)
These are areas which were found compliant as observed during the site
visit, and evidence provided, to the stated commitments of the EMPR
conditions.
Not Applicable
(N/A)
These are areas which were found not relevant to the operations at this
phase of the activity, i.e. construction and/or decommissioning phase
commitments.
Based on the evaluation criteria above, Mooikraal scored the following for compliance against
the EA and EMPR.
Compliance Calculations
Criteria EA
Conditions %
EMPR
Commitments %
Non-Compliance (NC) 7 11 12 19
Compliance (C) 55 89 52 81
Not Applicable (N/A) 14 - 16 -
Total Applicable 62 100 64 100
Based on site observations and the findings of the audit, the following recommendations were
made:
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com iv
● The eradication of invasive species is required in terms of the Alien and Invasive
Species Regulations (GN R 598 of 1 August 2014) promulgated under the National
Environmental Management Biodiversity Act, 2004 (Act No. 10 of 2004) (NEM:BA) and
any plan drafted in compliance with the legal requirements must be implemented.
Invasive species must be removed to prevent spreading to other areas around the site.
Mechanical methods should be used to remove the invasive species specifically at the
time of the year when the plants are not producing seeds which can result in the spread
of these species to other areas. The disposal of these species must be removed in a
controlled manner to prevent further spreading. Proof of training specific to the invasive
species identified on site must be provided either to the appointed contractor or the
person made responsible for the removal of alien invasive species;
● It is recommended that vehicles stored at the redundant storage area below the silo be
removed from site, ensure that they are fully drained of oils and stored within a
designated dirty water area; and
● Used tyres need to be removed and disposed of in accordance with the Waste Tyre
Regulations, 2017 (GN 1064 of 29 September 2017) (Waste Tyre Regulations)
promulgated under the National Environmental Management: Waste Act, 2008 (Act No.
59 of 2008).
The pressure of the fogger cannons installed at 3 Shaft needs to be checked to ensure that
the intended purpose of the fogger cannons is being achieved (i.e. dust suppression on the
coal stockpile area).
Mooikraal has appointed an Environmental Assessment Practitioner (EAP) to undertake a
Regulation 31 EMPR Amendment Process in terms of the EIA Regulations, 2014 and to apply
for a Water Use Licence (WUL) in terms of Section 21 of the National Water Act, 1998 (Act
No. 36 of 1998) (NWA). The authorisation of the Regulation 31 EMPR Amendment application
and WUL application will allow for most conditions identified as non-compliant in the audit to
be addressed.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com v
TABLE OF CONTENTS
1 Introduction .................................................................................................................. 1
1.1 Project Description .................................................................................................. 1
1.1.1 Current Mining Activities ................................................................................... 1
1.2 Objectives of the Audit............................................................................................. 3
2 Methodology ................................................................................................................. 3
3 Assumptions and Limitation .......................................................................................... 4
4 Auditor Details .............................................................................................................. 4
5 Auditor Declaration ....................................................................................................... 5
6 Site Observations ......................................................................................................... 7
6.1 Water Management ................................................................................................. 7
6.2 Waste Management ................................................................................................ 9
6.3 Fuel, Oil and Workshop Areas ................................................................................. 9
6.3.1 Fuel and Hydraulic Oil Areas ............................................................................ 9
6.3.2 Engineering Workshop ................................................................................... 11
6.4 Pollution Control Dams .......................................................................................... 11
6.5 Dust Suppression at 3 Shaft .................................................................................. 12
6.6 Sewage Treatment Plant ....................................................................................... 13
6.7 Laydown Area and Overburden Stockpile.............................................................. 14
6.8 3 Shaft ................................................................................................................... 16
6.9 Conveyor Belt between Mooikraal and 3 Shaft ...................................................... 18
7 Compliance Ratings ................................................................................................... 19
8 Financial Provision and Rehabilitation ......................................................................... 19
9 Recommendations & Conclusion ................................................................................ 20
LIST OF FIGURES
Figure 6-1: Concreted overflowing sump ............................................................................... 7
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com vi
Figure 6-2: Fenced overflowing sump ................................................................................... 7
Figure 6-3: Ponding near the sump near the workshop ......................................................... 8
Figure 6-4: Ponding near the hydraulic oil storage area ........................................................ 8
Figure 6-5: Sump with the oil skimmer .................................................................................. 8
Figure 6-6: Wood collection area........................................................................................... 9
Figure 6-7: Scrap metal collection area ................................................................................. 9
Figure 6-8:Bunded wall capacity ......................................................................................... 10
Figure 6-9: No oil spills ........................................................................................................ 10
Figure 6-10: Oil spill kit available at the hydraulic oil area ................................................... 10
Figure 6-11: The cleaned bunded area for the hydraulic oil ................................................. 10
Figure 6-12: Front of workshop area ................................................................................... 11
Figure 6-13: Machinery maintained at the workshop area ................................................... 11
Figure 6-14: North PCD ...................................................................................................... 12
Figure 6-15: Newly renovated PCD spill way ...................................................................... 12
Figure 6-16: Dust Suppression fogger cannon .................................................................... 12
Figure 6-17: Dust Suppression fogger cannons along the haul road ................................... 12
Figure 6-18: Aerator tank for the aeration process .............................................................. 13
Figure 6-19: Drying bed ...................................................................................................... 13
Figure 6-20: Bricks at the laydown area .............................................................................. 15
Figure 6-21: Redundant cars near the silo .......................................................................... 15
Figure 6-22: Used tyres ....................................................................................................... 15
Figure 6-23: Steel pipes ...................................................................................................... 15
Figure 6-24: Overburden stockpile ...................................................................................... 16
Figure 6-25: Unsuccessful vegetation on the overburden stockpile ..................................... 16
Figure 6-26: Stormwater management at 3 Shaft ................................................................ 17
Figure 6-27: Coal being stockpiled ...................................................................................... 18
Figure 6-28: Biomonitoring along the conveyor belt ............................................................ 19
Figure 6-29: Conveyor belt and water pipeline from Mooikraal ............................................ 19
LIST OF TABLES
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com vii
Table 2-1: Evaluation Criteria ................................................................................................ 4
Table 4-1: Senior Auditor ...................................................................................................... 4
Table 4-2: Assistant Auditor .................................................................................................. 5
Table 7-1: Summary Compliance for Mooikraal ................................................................... 19
Table 8-1: Financial Provision for Mooikraal Colliery (Jones and Wagener, 2019) .............. 20
LIST OF APPENDICES
Appendix A: EA Checklist
Appendix B: EMPR Checklist
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 1
1 Introduction
Digby Wells Environmental (hereafter “Digby Wells”) was appointed by Sasol Mining (Pty) Ltd
to undertake an Environmental Audit for the Sigma Colliery: Mooikraal and the 3 Shaft
Operations (hereafter “Mooikraal”).
The audit was done in fulfilment of the performance assessment and environmental auditing
requirements specified in Regulation 55 of the Mineral and Petroleum Resources
Development Act, 2002 (Act No. 28 of 2002) (MRPDA) and associated MPRDA Regulations
(GN R527 of 23 April 2004); and Regulation 34 of the Environmental Impact Assessment (EIA)
Regulations, 2014 (GN R326 of 7 April 2017), as amended (EIA Regulations, 2014)
promulgated under the National Environmental Management Act, 1998 (Act No. 107 of 1998)
(NEMA), respectively.
1.1 Project Description
Sasol Mining commenced with its mining operations at Sasol Sigma Colliery in the 1950s with
the aim to supply coal to Sasol Chemical Industries, now referred to as Sasolburg Operations
(SO) from both its underground and strip-mining operations. The Wonderwater and Mohlolo
shafts ceased operations in 2006.
In 2005, Mooikraal became the operational shaft to supply coal to the SO. Mooikraal is located
approximately 17.7 km southwest of Sasolburg in the Fezile Dabi District Municipality, Free
State Province. Mooikraal has a Life of Mine (LoM) of 34 years and will be operational until
2039.
The Mooikraal operations include the incidental 3 Shaft coal handling complex (3 Shaft)
located within the town of Sasolburg.
The Environmental Audit was undertaken to determine compliance with the EMPR and EA for
Mooikraal, inclusive of 3 Shaft.
1.1.1 Current Mining Activities
Mooikraal is an underground mine that is currently mining five underground sections.
Underground workings are accessed via an incline shaft which was constructed utilising a box
cut method. The soil extracted from the incline shaft was stockpiled and allowed to be
vegetated naturally along the outside of the incline shaft. This soil will be utilised once LoM is
reached and rehabilitation commences.
The incline shaft is utilised to allow vehicles, machinery and personnel to both enter and exit
the underground workings. Mooikraal is extracting coal utilising the underground bord and
pillar mining method, however in some areas high extraction mining is taking place. The coal
is transported via conveyor belt underground and brought to surface via the same incline shaft
which is used to enter the mine. The coal is brought to surface and stored in a silo that has
capacity to store one day’s volume of coal, should supply issues be identified such as the
need to undertake maintenance activities. The coal is then conveyed from Mooikraal to 3 Shaft
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 2
via an overland conveyer belt, where it is crushed and screened prior to being sent to SO for
further use.
The following infrastructure is present at Mooikraal:
● Incline Shaft;
● Pollution Control Dams (PCDs);
● Three sumps (Wash bay, fuel storage, shaft complex);
● Clean water channels;
● Soil stockpiles;
● Material laydown areas;
● One waste rock dump;
● Sewage Treatment Plant (STP);
● One waste storage area;
● Workshops;
● Bulk fuel and oil storage area;
● Conveyor belt;
● 10 ML Pipeline from Sigma Colliery: Mooikraal to SO;
● 7 ML Pipeline from Kleinvlei Shaft to SO; and
● Office Blocks.
The following infrastructure is present at 3 Shaft:
● Primary processing plant;
● Run of Mine (RoM) stockpile area;
● Stacker/ reclaimer;
● Chutes;
● Workshops;
● Waste storage area;
● Cement water transfer dam;
● Old Dams currently not in use and proposed to be demolished;
● Water reservoir for the fogger cannons;
● Conveyor belts; and
● Material storage yard.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 3
1.2 Objectives of the Audit
The objectives of the environmental audit are:
● To determine Mooikraal’ s level of compliance with the commitments contained in the
EA and approved EMPR; and
● To assess the appropriateness and suitability of the EA and EMPR to provide for the
mitigation of impacts associated with activities and future developments at Mooikraal.
2 Methodology
The methodology used in the undertaking of the environmental audit was as follows:
● A checklist of the EA conditions and EMPR commitments for Mooikraal;
● A site assessment was undertaken to assess compliance on 13 November 2019;
● Discussions took place prior, during and after the site assessment with Ms Lisa Grobler;
and
● Review of all documentation that was provided to Digby Wells during the site
assessment and via email thereafter was completed.
This audit report is compiled in accordance with the requirements of Regulations 34 and
Appendix 7 of the EIA Regulations, 2014 and will contain the following:
● Details and expertise of the independent person(s) who prepared the report;
● A declaration that the auditor is independent in a form as may be specified by the DMR;
● The scope of, and the purpose for which, the audit report was prepared;
● A description of the methodology adopted in preparing the audit report;
● An evaluation of compliance with the requirements of the EA and EMPR;
● A determination of whether the EA, EMPR and Closure Plan, if applicable, sufficiently
provide for the avoidance, management and mitigation of environmental impacts and
risks;
● An identification of potential shortcomings of the EA, EMPR and Closure Plan, if
applicable;
● A description of any assumptions made, and any uncertainties or gaps in knowledge;
and
● Recommendations on how identified deficiencies of and non-compliance to the EA and
EMPR EA requirements should be rectified.
Compliance with the commitments of the EA and EMPR were rated using the evaluation
criteria described in Table 2-1 below.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 4
Table 2-1: Evaluation Criteria
Non-Compliance
(NC)
These are areas were found non-compliant as observed during the site visit
to stated commitments of the EA and EMPR.
Compliance (C)
These are areas which were found compliant as observed during the site
visit, and evidence provided, to the stated EA conditions and commitments
of the EMPR.
Not Applicable
(N/A)
These are areas which were found not relevant to the operations at this
phase of the activity, i.e. construction, decommissioning phase
commitments.
3 Assumptions and Limitation
This report is subject to the following assumptions and limitations:
● The findings recorded in this report are limited to the site observations made and areas
visited during the site assessment undertaken on 13 November 2019;
● The auditors did not visit all areas of the operation and as a result, only areas identified
by the audit team in conjunction with the operation were visited and are referred to in
this audit report;
● The scope of work specifically excludes an audit referred to in the Regulations on Use
of Water for Mining and Related Activities aimed at the Protection of Water Resources
(GN 704 of 4 June 1999) (GN 704);1 and
● Although care was taken to audit as comprehensively as possible, auditing is done on
a sample basis and based on the conditions as they were found on the day of the audit.
4 Auditor Details
Table 4-1 and Table 4-2 below sets out the auditors’ details.
Table 4-1: Senior Auditor
Name and
qualifications
Ms Barbara Wessels
Barbara completed her B. Sc. in Geography and Environmental Management at the
University of Johannesburg in 2005. She manages the Environmental Services and
Ecology & Atmospheric Sciences Divisions, which include Environmental
Management, Compliance, GIS, Air Quality, Aquatics, Fauna and Flora, and
Wetlands.
She has over 10 years’ experience and is responsible for the management of
integrated projects both locally (South Africa) and internationally and is occasionally
involved in the undertaking of closure and rehabilitation studies, due diligences and
environmental auditing.
1 GN 704 in GG 20119 of 4 June 1999.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 5
Company Digby Wells and Associates (South Africa) (Pty) Ltd
Telephone: 011 789 9495 Email: [email protected]
Table 4-2: Assistant Auditor
Name and
qualifications
Ms Puleng Chabeli
BSc Environmental Science and Bachelor of Laws (LLB)
Puleng is an assistant auditor. She has experience within the public sector working
as an International Climate Change Relations and Negotiations Intern in the
Climate Change Division of the National Department of Environmental Affairs
(DEA). Puleng has experience working with international legislation, in particular,
the United Nations Framework Convention on Climate Change (UNFCCC) where
she provided assistance in the International Negotiation space writing opinions and
developing recommendations on policies on climate change; Article 6 of the Paris
Agreement and bi-lateral agreements between developing countries.
Company Digby Wells and Associates (South Africa) (Pty) Ltd
Telephone: 011 789 9495 Email: [email protected]
5 Auditor Declaration
The auditors declare that they acted independently and compiled this audit report using the
information furnished by the client.
I, Barbara Wessels, herewith declare that:
● I act as the independent environmental practitioner in this Audit;
● I will perform the work relating to the Audit in an objective manner, even if this results
in views and findings that are not favourable to the Holder;
● I declare that there are no circumstances that may compromise my objectivity in
performing such work;
● I have expertise in conducting environmental audits, including knowledge of the
standards, legislation and any guidelines that have relevance to the activity;
● I have no, and will not engage in, conflicting interests in the undertaking of the audit;
and
I declare that all the information furnished by me for this Audit is true and correct.
Signature of the Lead Auditor:
Date: January 2020
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 6
I, Puleng Chabeli, herewith declare that:
● I act as the independent environmental practitioner in this Audit;
● I will perform the work relating to the Audit in an objective manner, even if this results
in views and findings that are not favourable to the Holder;
● I declare that there are no circumstances that may compromise my objectivity in
performing such work;
● I have expertise in conducting environmental audits, including knowledge of the
standards, legislation and any guidelines that have relevance to the activity;
● I have no, and will not engage in, conflicting interests in the undertaking of the audit;
and
I declare that all the information furnished by me for this Audit is true and correct.
Signature of the Lead Auditor:
Date: January 2020
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 7
6 Site Observations
The observations that were made on site are discussed in the below sections.
6.1 Water Management
Mooikraal obtains potable water from the Metsimaholo Local Municipality for the office blocks
and for drinking water underground.
Three sumps are located at the Mooikraal operation to collect water generated around the
shaft complex. Two sumps are located near the wash bay and at the fuel and oil storage area
while the third sump is located at the incline shaft. The sumps separate hydrocarbons and
sludge from water. The water drains to the South Dam PCD which then flows to the North
Dam PCD.
It was observed on site, as seen in Figure 6-1 and Figure 6-2, that the stormwater
management sumps used for dirty water runoff prior to the water entering the PCDs were at
full capacity and overflowing and this is due to heavy rains the day before the site visit.
Maintenance and good housekeeping practices to be implemented to ensure these sumps
operate at optimal capacity.
Figure 6-1: Concreted overflowing sump
Figure 6-2: Fenced overflowing sump
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 8
Ponding of water, due to rains the day before, was observed around the sump area near the
workshop and hydraulic oil area as shown in Figure 6-3 and Figure 6-4 below. The sump with
the oil skimmer is also at full capacity as seen in Figure 6-5 and should either be emptied or
the capacity increased.
Figure 6-3: Ponding near the sump near
the workshop
Figure 6-4: Ponding near the hydraulic
oil storage area
Figure 6-5: Sump with the oil skimmer
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 9
6.2 Waste Management
Waste generated at Mooikraal is stored in a designated storage area which is separated into
various waste streams namely wood waste, scrap metal and hazardous waste as seen in
Figure 6-6 and Figure 6-7.
Figure 6-6: Wood collection area
Figure 6-7: Scrap metal collection area
Mooikraal considers general waste to be hazardous as all general waste is obtained from the
underground workings and anticipated to be contaminated with hydrocarbons. It was
communicated that hazardous waste is removed by EnviroServ and disposed at Holfontein
Landfill. Safe disposal certificates, purchase orders and invoices were provided as proof of
the safe disposal of waste. Oil drums were being removed on site at the time of the audit.
6.3 Fuel, Oil and Workshop Areas
6.3.1 Fuel and Hydraulic Oil Areas
Fuel and hydraulic oil are stored on site in bulk storage tanks. These tanks are stored within
a bunded area and on a concrete standing. The oil storage area contains a total of 73 000 litres
and has a bund wall capacity to store 150% of the total capacity of the bundwall which amounts
to 113 500 litres.
During the site visit, no oil spillages were identified, and this can be due to wet conditions due
to the rain the day before the site visit. The hydraulic oil bunded area was cleaned and an oil
spill kit was placed outside the bunded area.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 10
Figure 6-8:Bunded wall capacity
Figure 6-9: No oil spills
Figure 6-10: Oil spill kit available at the
hydraulic oil area
Figure 6-11: The cleaned bunded area
for the hydraulic oil
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 11
6.3.2 Engineering Workshop
The workshop area was well maintained and clean.
Figure 6-12: Front of workshop area
Figure 6-13: Machinery maintained at the
workshop area
6.4 Pollution Control Dams
Two PCDs are located at the Mooikraal operation namely South Dam and North Dam. South
Dam is utilised as a settlement dam. The water, once settled, is then allowed to flow naturally
to North Dam.
Water is pumped to 3 Shaft where it is used for dust suppression at the stockpiles as well as
to the SO for disposal through their systems. Prior to the installation of the water pipeline the
North PCD overflowed regularly into the Kromelmboogspruit due to a lack of capacity in the
PCD.
In 2013 it was, determined that the both the South and North PCDs, which are clay lined, were
unable to contain the amount of water being pumped from the underground workings to the
dams which resulted in multiple overflows over the past few years. However, the PCDs have
had no overflows in recent years.
According to the Mooikraal water monitoring by IGS, the report indicated monitoring of various
boreholes and exceedances were identified and the quality of the groundwater was discussed
to be affected by either the geology of the area, tailings at the Waste Ash Site at Sasol 1, 3
Shaft coal stockpile, fertiliser on cultivated land and the borehole assessed being near it and
the proximity of boreholes to explosives used for blasting underground.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 12
Figure 6-14: North PCD
Figure 6-15: Newly renovated PCD spill
way
6.5 Dust Suppression at 3 Shaft
Dust suppression is being undertaken at 3 Shaft using fogger cannons installed along the haul
road.
Figure 6-16: Dust Suppression fogger
cannon
Figure 6-17: Dust Suppression fogger
cannons along the haul road
The dust suppression mechanisms employed at 3 Shaft as shown in Figure 6-16 and Figure
6-17 above were observed to not have the required pressure as the water was not reaching
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 13
the stockpile area, this was due to the fogger cannons still being in testing phase and not fully
operational.
6.6 Sewage Treatment Plant
The STP located on site is utilised to treat all sewage from Mooikraal. The sewage water
collected from the office blocks and change houses via a sewage network is collected and
pumped into a bioreactor. The sewage is then pumped into an aeration tank shown in Figure
6-18. Aeration is utilised to assist in the promotion of microbial growth which helps in the
breakdown of wastewater. The sewage is then transferred to a surge tank where the sludge
is allowed to settle. The water is transferred to a baffle tank where the water is treated with
chemicals and dosed with chlorine and then discharged into the nearby watercourse namely
the Kromelmboogspruit in accordance with the approved Integrated Water Use Licence
(IWUL). The sludge that is removed from the aeration tanks is allowed to dry in drying beds
as shown in Figure 6-19, after which it is removed by EnviroServ. No incineration of sludge is
being undertaken on site. The STP is managed and monitored by Proxa.
Figure 6-18: Aerator tank for the aeration
process
Figure 6-19: Drying bed
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 14
6.7 Laydown Area and Overburden Stockpile
The laydown area is well organised with material placed in batches. It is evident from Figure
6-20 and Figure 6-23 that the material will be used for continuous maintenance. Figure 6-21
and Figure 6-22 however show used tyres and redundant cars which can be classified as a
waste.
The used tyres need to be removed and disposed of in accordance with the Waste Tyre
Regulations, 2017 (GN 1064 of 29 September 2017) (Waste Tyre Regulations) promulgated
under the National Environmental Management: Waste Act, 2008 (Act No. 59 of 2008).
The National Norms and Standards for Storage of Waste (GN R 926 of 2013) also apply to
the laydown area for any redundant material which would need to be disposed of. Best
environmental practice, as per the Norms and Standards, is defined as performing a particular
activity or activities in the most suitable, appropriate, advantageous or best advised manner
in order to achieve the highest standards while performing or exercising such activity or
activities.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 15
Figure 6-20: Bricks at the laydown area
Figure 6-21: Redundant cars near the
silo
Figure 6-22: Used tyres
Figure 6-23: Steel pipes
This overburden stockpile which is located near the silo will be used for rehabilitation purposes
when Mooikraal reaches its LoM. The overburden stockpile is located in a clean water area
and has a berm constructed around it. The vegetation of the overburden stockpile was not
successful, and erosion can be observed and this is due to the gradient of the slope being too
steep (Digby Wells Environmental Mooikraal Audit, 2018).
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 16
Figure 6-24: Overburden stockpile
Figure 6-25: Unsuccessful vegetation on
the overburden stockpile
6.8 3 Shaft
The coal stockpile area at 3 Shaft is well maintained. The only concern at the area is the
stormwater management particularly the dirty water management. Dirty water generated from
the primary processing plant has a high probability of flowing to the Leeuspruit and cause
water contamination.
As identified in the 2019 WUL Audit for Mooikraal, stormwater management was flagged as
an issue. It was noted that the stormwater management measures as shown in Figure 6-26
below were insufficient to contain the potential runoff water from the primary plant is entering
into the Leeuspruit.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 17
Figure 6-26: Stormwater management at 3 Shaft
The proposed measure to address this concern is to upgrade the stormwater management at
the stockpile area by constructing silt traps and the possible re-use of water back into the dust
suppression system.
This upgrade was assessed in the Regulation 31 EMPR Amendment application that was
submitted to the DMR on 15 May 2019 and the WUL Application that was submitted to the
Department of Water and Sanitation (DWS) in November 2018.
Decisions are still pending by both authorities. Without granting the authorisation to undertake
these upgrades, the possibility of surface water contamination remains.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 18
Figure 6-27: Coal being stockpiled
6.9 Conveyor Belt between Mooikraal and 3 Shaft
A conveyer belt has been constructed between Mooikraal and 3 Shaft to convey the coal to
the primary processing plant at 3 Shaft. The conveyer belt is covered and utilises water
sprayers to reduce dust generation. A maintenance road (dirt road) has been constructed
along the conveyer belt.
Biomonitoring along the conveyor belt is conducted by Digby Wells Environmental on a bi-
annual basis as per authorised WUL requirements (WUL number 08/C22K/CIGJFAE/6981,
dated 10/01/2018).
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 19
Figure 6-28: Biomonitoring along the
conveyor belt
Figure 6-29: Conveyor belt and water
pipeline from Mooikraal
7 Compliance Ratings
As shown in Table 7-1, Mooikraal was found 89% compliant with the EA conditions and 81%
compliant with the EMPR commitments.
Table 7-1: Summary Compliance for Mooikraal
Criteria EA
Conditions %
EMPR
Commitments %
Non-Compliance (NC) 7 11 12 19
Compliance (C) 55 89 52 81
Not Applicable (N/A) 14 - 16 -
Total Applicable 62 100 64 100
8 Financial Provision and Rehabilitation
Mooikraal is an underground operation therefore very limited concurrent rehabilitation is
undertaken during the operational phase of the mine. Once the shaft has reached its LoM,
rehabilitation will be undertaken to remove all infrastructure from the site and seal the box-
cut/adit.
After decommissioning, the box-cut and adit will be filled with rubble from the overburden
stockpiles and concrete generated from demolition of infrastructures. Jones and Wagener (Ref
No. JW047/15/E473 - Rev 4) updated the calculation of the financial provision for the various
Sasol operational areas in March 2019 and this included the Mooikraal Operations.
Audit Report
Sigma Colliery: Mooikraal and 3 Shaft Environmental Audit
SAS5921
DIGBY WELLS ENVIRONMENTAL
www.digbywells.com 20
Table 8-1: Financial Provision for Mooikraal Colliery (Jones and Wagener, 2019)
Shaft Operational Status Financial Provision
MKR1 – Sigma No 3 Shaft Operational R 11 016 424.36
MKR2 – Mooikraal Operational R 74 063 714.64
MKR3 – Old Sigma Coal
Handling Operational R 35 213 788.19
Total R 120 293 927.19
9 Recommendations & Conclusion
Based on site observations and the findings of the audit, the following recommendations were
made:
● The eradication of invasive species is required in terms of the Alien and Invasive
Species Regulations (GN R 598 of 1 August 2014) promulgated under the National
Environmental Management Biodiversity Act, 2004 (Act No. 10 of 2004) (NEM:BA) and
any plan drafted in compliance with the legal requirements must be implemented.
Invasive species must be removed to prevent spreading to other areas around the site.
Mechanical methods should be used to remove the invasive species specifically at the
time of the year when the plants are not producing seeds which can result in the spread
of these species to other areas. The disposal of these species must be removed in a
controlled manner to prevent further spreading. Proof of training specific to the invasive
species identified on site must be provided either to the appointed contractor or the
person made responsible for the removal of alien invasive species;
● It is recommended that vehicles stored at the redundant storage area below the silo be
removed from site, ensure that they are fully drained of oils and stored within a
designated dirty water area; and
● Used tyres need to be removed and disposed of in accordance with the Waste Tyre
Regulations, 2017 (GN 1064 of 29 September 2017) (Waste Tyre Regulations)
promulgated under the National Environmental Management: Waste Act, 2008 (Act No.
59 of 2008).
The pressure of the fogger cannons installed at 3 Shaft needs to be checked to ensure that
the intended purpose of the fogger cannons is being achieved (i.e. dust suppression on the
coal stockpile area).
Mooikraal has appointed an Environmental Assessment Practitioner (EAP) to undertake a
Regulation 31 EMPR Amendment Process in terms of the EIA Regulations, 2014 and to apply
for a Water Use Licence (WUL) in terms of Section 21 of the National Water Act, 1998 (Act
No. 36 of 1998) (NWA). The authorisation of the Regulation 31 EMPR Amendment application
and WUL application will allow for most conditions identified as non-compliant in the audit to
be addressed.
Appendix A: EA Checklist
Compliance
2018Compliance 2019
C /NC/NA C /NC/NA
1.1
Sasol Mining (Pty) Ltd (herein referred to as
the holder) shall be responsible for ensuring
compliance with the conditions of this
approval letter and the environmental
management commitments/measures
contained in the EMPr. This includes any
person acting on the holder's behalf,
including but not limited to an agent, servant,
contractor, subcontractor, employee,
consultant or any person rendering a service
to mining area in which this EMPr relates to.
C No further action required
Mooikraal remains an entity of Sasol Mining and therefore still the relevant
holder in relation to the EA condition.
No changes since the previous audit. Therefore, no further action is
required.
C
The principles set out in section 2 of the
National Environmental Management Act,
1998 (Act 107 of 1998) (NEMA) applies to
your mining operation as stipulated 1n
section 37(1)(a) of the MPRDA.
C
The Mooikraal operation aims to ensure that Section 2 of the
NEMA is adhered to. This is undertaken through the various
environmental procedures which aim to prevent degradation to
the environment as well as to promote sustainable development.
These procedures include:
■ Emergency Preparedness and Response (Ref No. SIG IMS
447000);
■ Procedure for the Handling of Oil Spills and Oil Recycling
(Ref No. SIG (EM) IMS SOP/ 008);
■ Standard operating procedure for the handling of sewage at
Sigma Mooikraal mine (Ref No. SOP 4.4.6/07); and
■ Site Specific Standard Operating Procedure Waste
Management (Ref No. IMS(EM) 4.4.6 / SOP 001).
Additionally management of various aspects which include
water, waste, air quality, aquatic environments and heritage is
undertaken to prevent deterioration of the environment and aims
to minimise the impact of the mine.
No further action required
Audit Comments
DMR - Authorisation for the consolidation of EMP FS 221 MR and FS 224 MR, dated 12 April 2016, reference: FS 30/5/1/2/3/2/2 (221) ER
1) SCOPE OF AUTHORISATION
Activity Proposed Mitigation Measure Comments 2018Action Plan - Measures to be Implemented to
Achieve Compliance
Mooikraal is an entity of Sasol Mining which takes responsibility
to ensure the Environmental Authorisation (EA) and EMPr
conditions are adhered to while the mine is operational.
Environmental audits are undertaken by Mooikraal on an annual
basis as well as Water Use Licence (WUL) audits which
indicates Sasol’s compliance to their EA as well as the EMPr.
Digby Wells has been contracted by Sasol Mining to undertake
the 2018 external audit as the Independent Environmental
Assessment Practitioner (EAP). Additionally Mooikraal ensures
that the contractors undertaking work at the mine are informed of
the conditions of the EMPr and the requirement to abide by
these conditions.
1.2
All mining activities must adhere to the
provisions of regulations 56, 64, 66, 68, 69,
70, 71 and 73 of the Regulations of the
MPRDA.
C
The Mooikraal operation aims to abide by the following
provisions:
■ Regulation 56 (Principles for mine closure);
■ Regulation 64 (Air quality management and control);
■ Regulation 66 (Noise management and control);
■ Regulation 68 (Water management and pollution control);
■ Regulation 69 (Disposal of waste material);
■ Regulation 70 (Soil pollution and erosion control);
■ Regulation 71 (.Sanitation of surface); and
■ Regulation 73 (Management of residue stockpiles and
deposits).
This is undertaken through compliance with the conditions of the
EMPr as the EMPr has been compiled with consideration of the
MPRDA. Additionally management and monitoring plans are
undertaken with the aim to ensure aspects are kept within
acceptable standards. Internal legal compliance audits are
undertaken by head office. During the site assessment a legal
audit was being undertaken.
No further action required
1.3
Mooikraal operates uth the parameteres of the MPRDA Regulations as per
the EA condition. Management and monitoring plans are still undertaken
with the aim to ensure aspects are kept within acceptable standards.
Internal legal compliance audits are undertaken by head office.
No changes since the previous audit. Therefore, no further action is
required.
C
Mooikraal has management plans in place that aim to ensure adhearance
to Section 2 of NEMA. The management plans ar
No changes since the previous audit.
Therefore, no further action is required.
C
1.4
The holder must at all times give effect to the
general objectives of the integrated
environmental management laid down in
Chapter 5 of NEMA as stipulated in section
38(1)(a) of the MPRDA.
NC
Based on the review of the EMP and correlated with
the legislative requirements of the EIA Regulations,
2014 (as amended) it is concluded that 3 Shaft which
includes the operation of the primary processing plant
is not sufficiently described, the impacts assessed
and mitigation measures provided in the EMPr to
confirm an environmental authorisation for the
activities or the area on which the activities are taking
place. The lack of detail in the EMPr with regard to 3
Shaft can be rectified by means of a Regulation 31
amendment application process. Mooikraal have
appointed Digby Wells to undertake the required
Regulation 31 amendment process to rectify the
issues identified by this audit report. This process has
however not commenced yet.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
1.5
Any changes to, or deviation from the mining
project description set out in the EMPr and
the mining right must be approved in writing
by the Department before such changes or
deviation may be effected. In assessing
whether to grant such approval or not, the
Department may request any information as
is deems necessary to evaluate the
significance and impacts of such changes or
deviation and it may be necessary for the
holder to apply for further authorization in
terms of the applicable legislation of the
time.
C No further action required
Changes to the mining project description has been reflected into the
Regulation 31 Amendment Process. Until that is granted, the current
mining project description is that which is included in the current EMPR.
No changes since the previous audit. Therefore, no further action is
required.
C
1.6
Mining activities may only be carried out at
the properties covered by the mining right
indicate in which this EMPr is approved for.
C No further action required
Changes to the mining project description has been reflected into the
Regulation 31 Amendment Process. Until that is granted, the current
mining project description is that which is included in the current EMPR.
No changes since the previous audit. Therefore, no further action is
required.
C
1.7
Where any of the holder's contact details
change; including name of the responsible
person, physical or postal address/ or
telephonic details, the holder must notify the
Department as soon as the new details
become known to the holder.
NA No further action required
No changes with regards to the holder's contact details including name of
the responsible person, physical or postal address/ or telephonic details
have occurred.
If the change takes place, the DMR is to be informed.
NA
1.8
This approval and the approved EMPr do not
negate the responsibility of the holder to
comply with any other statutory requirements
that may be applicable to the undertaking of
mining and any mining related activities.
C No further action required
Mooikraal is held to approved EA conditions, EMPR commitments, NEMA,
NEM:WA, NEM:AQA, NEM:BA, NWA and all consequential laws and
regulations.
This has not changed since the previous audit and Moiikraal is
undertskaing a legal compliance audit to ensure complaince with all laws.
C
As per our evaluation of the EMPr it is noted that the project
description must be updated to reflect certain aspects which are
currently being undertaken at the Mooikraal Colliery and 3 Shaft.
Additionally Mooikraal are proposing to relocate the conveyer
belt as the underground mining operation is proposing to mine in
this area. The water management system is also proposed to be
upgraded to avoid further accidently discharges of contaminated
water into the Leeuspruit. A basic assessment and 31
amendment process is currently being undertaken to assess the
impacts associated with the proposed project and obtain the
required authorisation.
The mining activities undertaken for the Mooikraal operation
were confirmed to be undertaken within the mining right area.
The properties included in the mining right area are listed in the
mining right (FS 30/5/1/2/3/2/2 (221) MR). A mine plan was
provided during the site assessment which indicated where
mining had been undertaken and where mining would occur in
the future. It is however noted that 3 Shaft is currently not
incorporated within the Mooikraal Mining Right. It is as per a
number of legal options that the definition of Mining Operations
is “any operation relating to the act of mining and matters directly
incidental thereto”
It was communicated that no changes with regards to the
holder's contact details including name of the responsible
person, physical or postal address/ or telephonic details have
occurred. It was noted that should changes to the mining right
holder occur these changes will be communicated to the DMR.
Mooikraal are committed to ensuring the operation not only
abides by the MPRDA but by also complies with other
legislations with specific reference to the National Environmental
Management Act (Act 107 of 1998 (NEMA), National
Environmental Management: Waste Act (Act 59 of 2008)
(NEM:WA), National Environment Management: Air Quality Act
(Act 39 of 2004) (NEM:AQA), National Water Act (Act 36 of
1998) (NWA), National Heritage Resources Act (No. 25 of
1999) (NHRA) and National Environmental Management:
Biodiversity Act (Act No. 10 of 2004) (NEM:BA) as well as other
provincial and local legislation. A legal audit is undertaken every
second year to determine the compliance of the Mooikraal
Operations with the relevant legislation. At the time of the site
assessment an internal legal audit was being completed
The Mooikraal operation aims to ensure that Chapter 5 of NEMA
is complied with to ensure all environmental management is
undertaken correctly and all impacts that the mine may have on
the environment is assessed and mitigated. It is however note
that the Mooikraal EMPr has failed to assess and provide
mitigation measures for all aspect specific to 3 Shaft. A non-
compliance has been identified against Section 24N with
regards to the effectiveness of the EMPr. Please refer to
Section 8 of the audit report for further details regarding the non-
compliance. It can be concluded however that in accordance
with the NEMA and EIA Regulations 2014 (as amended), the
Mooikraal EMPr is substantively lacking with regard to 3 Shaft in
the following respects:
■ 3 Shaft and its associated activities are not included in Section
1.1 or 1.2 of the EMPr, the sections which give the project
background and description respectively;
■ The Mooikraal EMPr does not adequately incorporate the
activities, aspects, impacts and associated mitigation steps at 3
Shaft into Section 4 – Environmental Impact Assessment,
Section 5.3 Environmental Management Programme, or Section
7 Environmental Monitoring.
■ Infrastructure (figure 2) and locality plans (figure 1) do not
indicate the infrastructure at 3 Shaft, nor the physical location of
3 Shaft, the mining right boundary does not correlate with the
Plan of Land Amendment of a Mining Right (dated 05/02/2016).
1.9
The holder must ensure that all areas where
the authorized mining activities occur have
controlled access to ensure safety of people
and animals.
C No further action required
Mooikraal is fenced to minimise any potential threats between animals and
mine personnel.
No changes since the previous audit. Therefore, no further action is
required.
C
1.1
Mine waste will not be allowed to be
deposited in natural drainage lines or erosion
gullies
C No further action required
Mooikraal and 3 Shaft still stores waste in the ISO yards which has
designated waste storage areas, one at Mooikraal and one at 3 Shaft,
which is separated into various waste streams namely wood waste, scrap
metal and hazardous waste. The hazardous waste is stored in waste skips
and signage indicating the waste stream is placed above the waste skip.
Mooikraal considers general waste to be hazardous as general waste is
obtained from the underground workings and anticipated to be
contaminated with hydrocarbons. It was communicated that hazardous
waste is removed by EnviroServ and disposed at Holfontein. Safe disposal
certificates were provided for the safe disposal of this waste.
No changes since the previous audit. Therefore, no further action is
required.
C
1.11
Dump structures must not be left on the
surface, this includes topsoil stockpiles,
overburden stockpiles, waste rock
stockpiles, tailing dumps and slimes dams.
NA
It is recommended as part of the NEMA EIA
Regulations, 2014 Regulation 31 amendment
process that Condition 1.11 of the EA is removed or
amended.
This commitment is not applicable at the present phase. NA
1.12
All excavations must be backfilled to the
natural surface levels if a bulk factor exists it
must be accommodated on the total area of
disturbance.
NC
Although full rehabilitation will not be undertaken until
LoM is reached it is recommended that rehabilitation
of the borrow pits should be undertaken to prevent
ponding of water and the spread of alien invasive
species. The area should be ploughed to make the
surface level. Additionally alien invasive management
measures must be implemented
Full rehabilitation will not be undertaken until end of LoM for the mine.
The borrow pit has been made free draining, it is well vegetated and
stable.
Additionally alien invasive management measures will be implemented in
the new year.
C
A surveyed plan must be submitted every
year to the Regional Manager that indicates:
■ The positions, footprints and volumes of
all topsoil stockpiles, overburden dumps,
waste rock dumps and slimes dams (Any
structure that is above the natural surface);
■ The positions, surface areas and depths
of all open pits; and
■ The positions and surface areas of all
rehabilitated areas (please indicate the status
of rehabilitation-backfilled,
profiled/landscaped, top soiled, vegetated or
monitoring and managing.
During the operation of the mine stockpiles including an
overburden damp, soil stockpiles and PCDs are located within
the mining right area. The overburden and soil stockpile will be
utilised once the mine reaches closure which will assist with the
rehabilitation of the mine. Additionally the PCDs are required for
the operation of the mine and water management. This condition
is considered not applicable as these structures will only be
removed once LoM is reached and rehabilitation of the mine will
be undertaken.
All excavations that have been formed as a result of the
operating of the mine will be rehabilitated once LoM is reached.
Borrow pits were observed during the site assessment. It was
noted that rehabilitation efforts had been undertaken however
further effort is required to ensure the borrow pits are free
draining. Ponding of water was observed and alien invasive
species were noted within the disturbed area.
1.13 C
Evidence was provided that indicated that the surveyed plan was
submitted to the Reginal Manager at the DMR on 17 April 2018.
It was communicated that an updated plan is submitted on an
annual basis every September. These plans indicate the
progression of the mine and position of all surface infrastructure.
All excavations that have been formed as a result of the
operating of the mine will be rehabilitated once LoM is reached.
Borrow pits were observed during the site assessment. It was
noted that rehabilitation efforts had been undertaken however
further effort is required to ensure the borrow pits are free
draining, and alien invasive species are controlled.
Consideration should be taken to rehabilitate these borrow pits
during the operational life of the mine.
No further action required
The mine is access controlled to ensure no unauthorised
personnel are permitted into the mine. During the site
assessment the auditors were required to provide identification
documentation as well as permission from the Environmental
Practitioner was required to gain access to the mine. The
access to the Mooikraal Colliery is permitted through the main
gate which is access controlled. Access to 3 Shaft is also only
permitted by one gate. To gain entry, access cards as well as a
biometric systems have been implemented. Fencing has been
constructed around the entire Mooikraal Colliery and 3 Shaft and
no entry signage has been erected. Fencing has also been
erected around the PCDs (both Mooikraal and 3 Shaft) which are
required to prevent the possibility of drowning and restrict
access. Signage has also been erected to discourage people
from entering the restricted area. Additionally entry to the
underground workings is also restricted by means of a shaft
guard which requires proof that the individual is fit to work prior
to that individual proceeding.
During the site assessment it was observed that waste
generated at Mooikraal and 3 Shaft is stored in the ISO yards
which has designated waste storage areas, one at Mooikraal
and one at 3 Shaft, which is separated into various waste
streams namely wood waste, scrap metal and hazardous waste.
The hazardous waste is stored in waste skips and signage
indicating the waste stream is placed above the waste skip.
Mooikraal considers general waste to be hazardous as general
waste is obtained from the underground workings and
anticipated to be contaminated with hydrocarbons. It was
communicated that hazardous waste is removed by EnviroServ
and disposed at Holfontein. Safe disposal certificates are
provided for the safe disposal of this waste. During the audit a
safe disposal certificate for the disposal of hazardous waste
was provided (Ref No.GP-SP240100). Good housekeeping
measures are in place. All waste is stored and handled in
accordance with the National Environmental Management:
Waste Act, 2008 (Act 59 of 2008) (NEM:WA) Norms and
standards for the Storage of Waste, 2013 as well as the Site
Specific Standard Operating Procedure Waste Management
(Ref No. IMS (EM) 4.4.6 / SOP 001).
Updated surveyed plans are submitted on an annual basis and
rehabilitation of excavations (i.e. the borrow pit) will be rehabilitated at the
mine's end of LoM. For now, the borrow pit is made free draining and alien
invasives controlled.
No changes since the previous audit. Therefore, no further action is
required.
C
2.1
In order to ensure safety, all employees must
be given the necessary personnel protective
equipment (PPE).
C No further action required
PPE was worn by individuals on site during the time of the audit. The mine
still supplies the PPE to the workers as per Section 6 of the Mine Health
and Safety Act, 1996 (Act 29 of 1996). The auditors were required to wear
appropriate PPE while walking around the mine.
No changes since the previous audit. Therefore, no further action is
required.
C
2.2
This approval letter and the approved EMPr
must be provided to the site operator(s) and
the requirements thereof must be made fully
known to him or her.
C No further action required
Lisa Grobler remians the appointed Environmental Manager at Mooikraal
and she ensures that the conditions of the EA and EMPr are complied with.
Lisa undertakes regular internal assessments to ensure compliance to
these conditions, where non-compliances are identified these issues are
raised and measures are taken to rectify the issue. Continuous
environmental awareness is undertaken at the mine to ensure all individuals
are aware of the EA and the EMPr conditions.
No changes since the previous audit. Therefore, no further action is
required.
C
2.3
Hauling routes for construction vehicles and
machinery must be clearly marked and
appropriate signaling must be posted to that
effect. Furthermore, movement of
construction vehicles and machinery must be
restricted to areas outside of the drainage
line or wet areas.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
2.4
Appropriate notification sign must be erected
at the construction site, warning the public
(residents, visitors etc.) about the hazard
around the mining area and presence of
heavy vehicles and machinery.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
2.5
Construction must include design measures
that allow surface and subsurface movement
of water along the drainage lines so as not to
impede natural surface and subsurface water
flow, and drainage measures must promote
the dissipation of storm water runoff.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
2.6
Vegetation clearance must be limited on
areas where the individual activities will
occur, and mitigation measures must be
implemented to reduce the risk of erosion
and alien species invasion.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
2.7
The holder must note that in terms of the
National Forest Act, 1998 (Act No. 84 of
1998) protected plant species, also listed in
must not be cut, disturbed, damaged,
destroyed and their products must not be
possessed, collected, removed, transported,
exported, donated, purchased or sold unless
permission is granted by the Department of
Agriculture, Forestry and fisheries.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
2.8
Construction areas (e.g. material lay down
areas), topsoil and subsoil must be protected
from contamination or pollution. Stockpiling
must not take place in drainage lines or areas
where it will impede surface water runoff.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable.
NA
3) COMMENCEMENT/ CONTINUATION OF MINING ACTIVITIES
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
No clearance of vegetation is currently being undertaken
therefore this condition is considered to be not applicable.
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
During the site assessment it was observed that individuals
working at the mine are required to have their own PPE. The
type of PPE required is dependent on the tasks which needs to
be conducted. The mine supplies the PPE to the workers as per
Section 6 of the Mine Health and Safety Act, 1996 (Act 29 of
1996). The auditors were required to wear appropriate PPE
while walking around the mine.
Lisa Grobler has been appointed by the mine to ensure the
conditions of the EA and EMPr are complied with. All operational
managers and contractors are aware of and must comply with
these conditions. Lisa undertakes regular internal assessments
to ensure compliance to these conditions, where non-
compliances are identified these issues are raised and
measures are taken to rectify the issue. Continuous
environmental awareness is undertaken at the mine to ensure all
individuals are aware of the EA and the EMPr conditions
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
2.9
If any soil contamination is noted at any
phase of mining, the contaminated soil must
be removed to a licensed waste disposal
facility and the site must be rehabilitated to
the satisfaction of this Department and the
Department of Water and Sanitation. The
opportunity for the onsite remediation and re-
use of contaminated soil must be
investigated prior to the disposal and this
Department must be informed in this regard.
C No further action required
A Contaminated Land Assessment was conducted in by Geo Pollution
Technologies - Gauteng (Pty) Ltd and the report compiled for August
2019.
The report held for the Mooikraal Operations that none of the compounds
measured in the samples exceeded the SSV2 and Anion screening levels
for these two areas. In the samples from Mooikraal and 3 Shaft copper,
manganese and lead exceeded SSV1 values, but when considering the
background soil quality from South Africa and manganese in a World
Health Organisation report, none of the values that are exceeding are
regarded as significant. The arsenic value in sample Mooikraal discard
dump should be assessed in groundwater and surface water. Should there
be groundwater or surface water monitoring data around the two sites
close to Sasolburg, it would be prudent to check the levels of these
compounds in the sampling data.
C
2.1
An integrated waste management approach
must be implemented that is based on waste
minimization and must incorporate
avoidance, reduction, recycling, treatment,
reuse and disposal where appropriate.
Uncontaminated rubble generated on the
premises can be re-used as backfilling
material on any relevant site (if this
requirement exist). Ensure that no refuse or
rubble generated on the premises is placed,
dumped or deposited on the adjacent
properties or public places and open space.
NC
It is recommended that the vehicles stored in the
designated clean water area below the silo and
conveyer belt at Mooikraal Colliery should be
removed from site or stored within a designated dirty
water area. Rehabilitation of the area where the
vehicles were discarded must also be undertaken to
remove any potential contamination as this area is
considered to be clean in accordance with GNR 704
of the National Water Act, 1998 (Act 36 of 1998)
(NWA) . Should Mooikraal wish to construct a new
designated waste storage area for additional waste
stored at Mooikraal Colliery, a review must be
undertaken to determine whether any listed activities
in terms of NEM:WA such as Category C are
triggered. Should no waste activities be triggered, a
31 amendment process must be undertaken and
appropriate mitigation measures implemented to
prevent further contamination.
A waste management procedure has been compiled to deal with the
handling and disposal of waste (Ref No. IMS(EM) 4.4.6 / SOP 001). The
procedures indicated that all waste must be recycled where possible and
the remaining waste must be disposed at permitted or licensed landfill
sites. During the site assessment it was observed that waste generated at
Mooikraal is stored in a designated waste storage area which is separated
into various waste streams namely wood waste, scrap metal and
hazardous waste. All waste is appropriately disposed off.
During the site visit, the waste material was being removed for disposal -
the oil drums to be specific.
C
2.11
In terms of sections 28 and 30 of NEMA, and
sections 19 and 20 of the National Water
Act, 1998 (Act 36 of 1998) as amended
(NWA), any costs incurred to remedy
environmental damage must be borne by the
person responsible for the damage. It is
therefore imperative that the holder reads
through and understand the legislative
requirements pertaining to mining. It is the
holder's responsibility to take reasonable
measures which include informing and
educating contractors and employees about
environmental risks of their work and training
them to operate in an environmentally
acceptable manner.
C No further action required
The mine aims to avoid impacts to the environment. Environmental
awareness is provided to all employees and contractors so as to avoid
potential environmental incidents. It is underst that should environmental
deterioration be identified it is the mines responsibility to rectify the impact.
The financial provision is for this purpose, the mine must ensure sufficient
funds are available for rehabilitation once LoM is reached (Jones and
Wagener (Ref No. JW047/15/E473 - Rev 4).
The lastest financial provisioning is March 2019.
C
2.12
Construction vehicle must be serviced and
maintained in the manner whereby no
excessive smokes are produced and noise
production is reduced to acceptable levels,
and to prevent oil leaks. Contaminated soil
must be remediated on site or removed to an
authorised landfill site.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable
NA
The mine aims to avoid impacts to the environment.
Environmental awareness is provided to all employees and
contractors so as to avoid potential environmental incidents. It is
understood however that should environmental deterioration be
identified it is the mines responsibility to rectify the impact.
Financial provision is updated on an annual basis and submitted
to the DMR to ensure sufficient funds are available for
rehabilitation once LoM is reached (Jones and Wagener (Ref
No. JW047/15/E473 - Rev 3).
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
Certain areas around the mine have been identified to be high
risk areas where soil contamination may have occurred during
the operational phase. These areas are specifically around the
STP, below the PCDs, around the ROM coal stockpile area and
the shafts. Soil samples taken by Digby Wels have been taken
and sent for analysis to determine the baseline soil condition
around Mooikraal and 3 Shaft. It is however noted unless
severe contamination is identified which will result in
contamination to the water courses, the soil will remain until the
mine has reached LoM where rehabilitation will occur and these
soils will be rehabilitated. To date no results from the soil survey
has been provided.
A waste management procedure has been compiled to deal with
the handling and disposal of waste (Ref No. IMS(EM) 4.4.6 /
SOP 001). The procedures indicated that all waste must be
recycled where possible and the remaining waste must be
disposed at permitted or licensed landfill sites. During the site
assessment it was observed that waste generated at Mooikraal
is stored in a designated waste storage area which is separated
into various waste streams namely wood waste, scrap metal and
hazardous waste. All waste is appropriately disposed off.
However, during the site assessment decommissioned
equipment which is no longer in use was observed to be
dumped within a designated clean water area located below the
silo and conveyer belt area. It was communicated that the
equipment had been drained of oil however the equipment is still
considered to be dirty and contained evidence of coal. Although
discussions regarding making this area the new waste
management area are being undertaken, decommissioned
equipment may not be permitted to be dumped in this area until
relevant mitigation measures have been implemented.
2.13
Residents (if any) on the property (ies) and
surrounding the mining areas must be
informed if any unusual noisy activities are
planned.
C No further action required
It was noted that the Mooikraal Colliery is not considered to be noisy as
only underground mining is being undertaken. Additionally the nearest
receptor is considered to be far away from the mining operation and would
not be considered to be impacted upon by noise.
No changes since the previous audit. Therefore, no further action is
required.
C
2.14
Dust suppression measures must be
implemented on all exposed surface to
minimize and control airborne dust.
NC
As the dust mitigation measures implemented at the
mine were found to be inadequate. An air quality
specialist study is currently being undertaken to
assess the impact of dust fall-out on the surrounding
community and to recommend measures to reduce
the impacts around 3 Shaft and the Mooikraal Colliery.
The mitigation measures proposed from this
specialist study must be implemented to ensure dust
levels are reduced and are brought in compliance with
air quality legislation.
Dust suppression measures have been put into place at Sigma Colliery: 3
Shaft in the form of fogger cannons. This was put in place to address dust
fall-out impacts to the surrounding community.
The dust monitoring report compiled by Godnwana Environmental
Solutions in October 2019 states that during the period of monitoring,
2019-09-30/2019-10-31 there were no exceedances for non-residential
standards.
The Mooikraal Opertaions are classified as non-residential. Therefore,
based on the lastes report provided to Digby Wells, this condition is met.
C
2.15
Should any heritage remains be exposed
during operation or any actions on the site,
these must immediately be reported to South
African Heritage Resources Agency
(SAHRA) and in accordance with the
applicable legislation. Heritage remains
uncovered or disturbed during earthworks
must not be further disturbed until the
necessary approval has been obtained from
SAHRA. This Department must also be
informed about such exposure in writing.
C No further action required
According to the EMPr approved by DMR on 12 April 2016, no
archaeological and/or cultural historical sites are found in the mining right
area. It is understood that should any additional activities be undertaken the
mine will notify the South African Heritage Resources Agency (SAHRA) in
terms of the National Heritage Resources Act, 1999 (No. 25 of 1999).
No archaeological and/or cultural historical sites have been found on site
and the sitautions remains unchanged since the previous audit.
C
2.16
Care must be taken to ensure that the
material and excavated soil required for
backfilling are free of contamination from
hydrocarbons.
C No further action required
Soil and overburden stockpiles are located at the Mooikraal Colliery and
will be utilised for rehabilitation once LoM is reached. The stockpiles were
located in designated clean areas and no contamination was observed. It
was observed that a berm has been constructed around the overburden
stockpile to prevent the loss of soil. Additionally the soil stockpile has been
vegetated and utilised as clean water berms.
No changes since the previous audit. Therefore, no further action is
required.
C
According to the EMPr approved by DMR on 12 April 2016, no
archaeological and/or cultural historical sites are found in the
mining right area. It is understood that should any additional
activities be undertaken the mine will notify the South African
Heritage Resources Agency (SAHRA) in terms of the National
Heritage Resources Act, 1999 (No. 25 of 1999). A heritage
study is currently being undertaken for the 31 amendment
process to ensure no heritage resources are impacted.
Soil and overburden stockpiles are located at the Mooikraal
Colliery and will be utilised for rehabilitation once LoM is
reached. The stockpiles were located in designated clean areas
and no contamination was observed. It was observed that a
berm has been constructed around the overburden stockpile to
prevent the loss of soil. Additionally the soil stockpile has been
vegetated and utilised as clean water berms. As the Mooikraal
Mine is an underground coal mine, limited rehabilitation is
undertaken on areas where mining or related activities have
been undertaken. It was reported that to date only minimal
rehabilitation activities had been undertaken. Once LoM is
reached, all infrastructure will be removed from site and
rehabilitation will commence in line with the rehabilitation
measures proposed in the approved EMPr, a rehabilitation
management plan will also be compiled at the time of closure.
Should rehabilitation be undertaken, the soil utilised to
rehabilitate the area will be free of contaminates from
hydrocarbons.
It was noted that the Mooikraal Colliery is not considered to be
noisy as only underground mining is being undertaken.
Additionally the nearest receptor is considered to be far away
from the mining operation and would not be considered to be
impacted upon by noise. Additionally although the ventilation
shaft is quiet noisy their are no close receptors to the ventilation
shaft. It is noted however that should a noisy activities be
planned to be undertaken at the mine, adjacent land owners will
be notified. No noise complaints for Mooikraal have been
received for 2017 and 2018 (Sasol Mining External Complaints
Register April 2018). It was however noted that issues regarding
noise generated by the crushing and screening plant has been
received. A noise specialist study is currently being undertaken
to address the issue of noise and implement measures to
reduce these impacts to the surrounding community
A dust monitoring programme has been implemented at
Mooikraal and 3 Shaft where dust buckets have been positioned
in all major and secondary wind directions. These dust buckets
are monitored on a monthly basis by Gondwana. Dust results
were provided for the months of August 2012 to May 2018. The
results indicated that the levels of dust did exceed the specified
limits associated with residential levels and in some month’s
industrial levels as per the National Dust Fallout Regulations.
Dust is considered to be an issue at 3 Shaft due to the handling
of coal. A number of complaints have also been raised
regarding the generation of dust around the conveyer belt and 3
Shaft (Refer to Complaints register, 2018).
2.17
Hydraulic fluid or chemicals required during
construction must be stored in a concrete
lined surface with bund walls and shall be
designed in such a manner that any spillage
can be contained and reclaimed without any
impact on the surrounding environment.
Should any spills occur it should be cleaned
immediately by removing spillage together
with the polluted solids and dispose it in the
authorised disposal site permitted of such
waste. The relevant regional office of the
Department of Water and Sanitation must be
notified within 24 hours of an incident that
may pollute surface and underground water
resources.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable. Therefore, no further action is
required.
NA
2.18
Chemical sanitation facilities or system such
as toilets that do not rely on the seepage of
liquids must be provided with a ratio of 1 for
every 15 workers. These must be placed
such that they prevent spills or leaks to the
environment and must be maintained
according to the operating instructions and
the content thereof must be disposed at an
authorised waste water treatment works.
NC
It is recommended that an investigation be
undertaken to determine the reason for the high
concentrations of NO3 and E Coli in the treated
effluent that is discharged from the STP. Measures
must be implemented to ensure that these non-
compliances are addressed and aim to comply with
the specified qualities of the IWUL.
The high concentrations of NO3 and E Coli found in the STP results in the
previous were investigated and addressed. C
Once the 7ML and 10ML pipeline is constructed water
will be transferred between Mooikraal PCDs to SO
PCDs which will prevent further discharge of dirty
water to the environment at Mooikraal. A Dam Safety
Inspection by a professional Registered Engineer on
the PCDs at Mooikraal must be undertaken to ensure
the PCDs are able to contain the required amount of
water without the potential of dam failure. Additionally
the incident is required to be reported to water affairs
if the reason for the overflow was due to the integrity
of the PCDs.
During the site assessment it was observed that the
PCD at 3 Shaft was at full capacity and above the 0.8
m recommended freeboard level. The water level
within the PCD at 3 Shaft must be reduced to be
within the recommended level.
■ The disposal of the effluent from the STP to the
Kromelmboogspruit triggers a Section 21 (f) water use:
Discharging waste or water containing waste into a water
resource,;
■ Disposal of water found underground to the North and the
South PCDs triggers a Section 21 (g) which is defined as the
disposing of waste in a manner which may detrimentally impact
on a water resource; and
■ Construction and operation of a pipeline over various water
courses (Section 21 c and i).
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
Toilets are located within office buildings as well as in the
change houses. A portable toilet is also located at the STP. It
was noted that the toilets are regularly cleaned and maintained.
Should an issue be detected such as a leak this will be reported
on and repaired. The sewage generated from the use of the
toilet is transported via pipeline to the STP. The STP is
authorized under the IWUL (Licence No
08/C22K/CIGJFAE/6981) approved on 16 January 2018. The
sewage is treated to an acceptable standard in accordance with
the IWUL and discharged to the Kromelmboogspruit. The water
qualities reported on from the STP are however not complying
with the water quality standards in the IWUL. High levels of
Nitrates and E-coli were detected in the monitoring data (STP
Water Quality, 2018). It was however observed during the site
assessment that maintenance of the STP was being undertaken
in an attempt to clean out the system and ensure the STP
operates efficiently.
2.19
The holder must ensure that any water uses
listed in terms of section 21 of NWA must
get authorization from Department of Water
and Sanitation prior to the commencement of
such activity (ies).
NC
Mooikraal has an approved WUL (Licence No
08/C22K/CIGJFAE/6981) which permits the following water
uses:
■ Abstraction of water from underground triggers a Section 21
(a) water use which is the taking of water from a water resource;
■ The removal of water found underground for the safe
continuation of mining triggers a Section 21 (j) water use.Pipelines transferring water from Mooikraal to other Sasol Operations are
installed, functional and operational.
All water uses are accounted for in the WUL.
C
2.2
This approval letter does not purport to
absolve the holder from its common law
obligations towards the owner of the surface
of land affected.
C No further action required
Mooikraal understands its responsibility to landowners. An external
complaints register is maintained which documents all complaints raised
by I&APs, landowners as well as adjacent landowners. On the day of the
audit, the Environmental Manager was dealing with an I&AP compliant
about a borehole on his land.
Mooikraal still has a working compliants register and issues are still logged
to be addressed.
C
2.21
The holder must ensure that rehabilitation of
the disturbed areas caused by mining and
mining related activities at all times comply
with the approved EMPr.
C No further action required
As the Mooikraal Mine is an underground coal mine, limited rehabilitation is
undertaken on areas where mining or related activities have been
undertaken. It was reported that to date only minimal rehabilitation activities
had been undertaken. Once LoM is reached, all infrastructure will be
removed from site and rehabilitation will commence in line with the
rehabilitation measures proposed in the approved EMPr, a rehabilitation
management plan will also be compiled at the time of closure.
This remains the way the mine will undertake rehabilitation, thus nothing
has changed since the previous audit.
C
2.22
This approval letter may be amended or
withdrawn at any stage for non compliance
and provides no relief from the provisions of
any other relevant statutory or contractual
obligations.
C No further action required
Mooikraal acknowledges the importance of ensuring all conditions of this
authorisation and EMPR are adhered to. Should a non-compliance be
identified an action plan is compiled to provide measures to address the
non-compliance.
The non-compliances identified during this audit are dependent on the
approval of the Regulation 31 Amendment application that is still to be
approved by the DMR.
C
2.23
The holder must note that residue deposit
and residue deposit must be deposited and
managed in a prescribed manner on any site
demarcated for that purpose in the EMPr. No
person may temporary or permanently
deposits residue stockpile or residue deposit
on any area or site other than on site
indicated on the EMPr.
C No further action required
A number of soil and overburden stockpiles are located onsite. The
stockpiles are located at the Adit, PCD and silo and conveyer belt area.
The soil stockpiles are utilised for clean stormwater management. These
stockpiles will be utilised for rehabilitation once LoM is reached.
No changes since the previous audit. Therefore, no further action is
required.
C
Once the 7ML and 10ML pipeline is constructed water
will be transferred between Mooikraal PCDs to SO
PCDs which will prevent further discharge of dirty
water to the environment at Mooikraal. A Dam Safety
Inspection by a professional Registered Engineer on
the PCDs at Mooikraal must be undertaken to ensure
the PCDs are able to contain the required amount of
water without the potential of dam failure. Additionally
the incident is required to be reported to water affairs
if the reason for the overflow was due to the integrity
of the PCDs.
During the site assessment it was observed that the
PCD at 3 Shaft was at full capacity and above the 0.8
m recommended freeboard level. The water level
within the PCD at 3 Shaft must be reduced to be
within the recommended level.
Mooikraal understands its responsibility to landowners. An
external complaints register is maintained which documents all
complaints raised by I&APs, landowners as well as adjacent
landowners. These complaints are reposted to the Sasol Mineral
Rights Departments. All issues raised are investigated and
specific actions are implemented to ensure the issue is
resolved (Mooikraal Complaints Register April 2018).
As the Mooikraal Mine is an underground coal mine, limited
rehabilitation is undertaken on areas where mining or related
activities have been undertaken. It was reported that to date only
minimal rehabilitation activities had been undertaken. Once LoM
is reached, all infrastructure will be removed from site and
rehabilitation will commence in line with the rehabilitation
measures proposed in the approved EMPr, a rehabilitation
management plan will also be compiled at the time of closure.
All excavations that have been formed as a result of the
operating of the mine will be rehabilitated once LoM is reached.
Borrow pits were observed during the site assessment. It was
noted that rehabilitation efforts had been undertaken however
further effort is required to ensure the borrow pits are free
draining, has ponding was observed and alien invasive species
are controlled. Consideration should be taken to rehabilitate
these borrow pits during the operational life of the mine.
Mooikraal acknowledges the importance of ensuring all
conditions of this authorisation and EMPR are adhered to.
Should a non-compliance be identified an action plan is
compiled to provide measures to address the non-compliance.
Additionally Mooikraal ensures both internal and external audits
are undertaken to ensure its compliance to the various
authorisation and EMPr conditions.
During the site assessment it was observed that a number of
soil and overburden stockpiles are located onsite. The
stockpiles are located at the Adit, PCD and silo and conveyer
belt area. The soil stockpiles are utilised for clean stormwater
management. These stockpiles will be utilised for rehabilitation
once LoM is reached.
During the site assessment it was observed that water was
overflowing uncontrolled from the PCD into the
Kromelmboogspruit. It was observed that the water was
overflowing beneath the spill way which may indicate issues
relating to structural integrity of the dam wall of the PCD. The
overflow of water from the PCDs to the environment is not
authorised in terms of the NWA and under the IWUL. Measures
have been put in place to manage the excess water. This
includes the construction of a 7 ML and 10 ML pipeline which will
direct the water from the PCDs to the Sasolburg Operations and
prevent the unauthorised discharge. The construction of the
pipeline received environmental authorisation in 2015 with the
IWUL being authorised in January 2018. The pipeline has been
constructed except in the areas where the pipeline will cross
watercourses. It is proposed that the pipeline will be fully
constructed by the end of 2018. It was observed that the PCD at
3 Shaft was also quiet full and above the 0.8 m recommended
level.
2.19
The holder must ensure that any water uses
listed in terms of section 21 of NWA must
get authorization from Department of Water
and Sanitation prior to the commencement of
such activity (ies).
NC
Pipelines transferring water from Mooikraal to other Sasol Operations are
installed, functional and operational.
All water uses are accounted for in the WUL.
C
2.24
The holder must note that no person may
commence, undertake or conduct a waste
management activity, except in accordance,
with the requirements of norms and
standards determined for that activity or a
waste management licence is issued in
respect of that activity if licence is required.
NC
It is recommended that the vehicles stored in the
designated clean water area below the silo and
conveyer belt at Mooikraal Colliery should be
removed from site or stored within a designated dirty
water area. Rehabilitation of the area where the
vehicles were discarded must also be undertaken to
remove any potential contamination as this area is
considered to be clean in accordance with GNR 704
of the National Water Act, 1998 (Act 36 of 1998)
(NWA) . Should Mooikraal wish to construct a new
designated waste storage area for additional waste
stored at Mooikraal Colliery, a review must be
undertaken to determine whether any listed activities
in terms of NEM:WA such as Category C are
triggered. Should no waste activities be triggered, a
31 amendment process must be undertaken and
appropriate mitigation measures implemented to
prevent further contamination.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
2.25
The Department reserves the right to audit
and/or inspect the activity (ies) without prior
notification at any reasonable time and at
such frequency as may be determined by the
Regional Manager.
C No further action required
The mine permits any authority who wishes to conduct the audit provided
that previous arrangements have been made with the mine to ensure
appropriate health and safety procedures are followed.
No changes since the previous audit.
C
2.26
The waste storage site must have a firm,
impermeable, chemical resistant floors and a
roof to prevent direct sunlight and rain water
from getting in contact with the waste.
NC
As per the condition of the authorisation, it is a
requirement to ensure that the hazardous waste
storage area has a roof in order to prevent direct
sunlight and rainwater having direct contact with the
waste. It was communicated that it would be
impractical to construct a roof over the waste storage
area as it would create difficulties when contractors
come to remove the waste as the roof will hinder the
waste vehicles from accessing the skip. It is therefore
recommended that an application for an amendment
of the condition be included in the Regulation 31
amendment process.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
2.27
The storage of hydrocarbons must have
bund walls with adequate capacity to contain
the maximum volume that is stored in the
area. Uncontaminated storm water must be
prevented from coming into contact with the
waste and must be diverted away from the
storage site.
C
Further maintenance and good housekeeping
practices must be implemented at the sump located
at the fuel and hydraulic oil storage area to ensure the
sump operates at optimal capacity.
Maintenance and good housekeeping practices have been implemented at
the fuel and hydraulic oil storage area. The hydraulic oil and diesel storage
area have bunded areas that can carry capacity of potential spills. C
2.28
Should there be any conflicting conditions
between this approval letter and other
approval granted by other authorities, it is
upon the holder to bring it to the attention of
this Department for resolution.
C No further action required
Mooikraal has confirmed that no conditions within this authorisation
contradict the conditions in the EMPr and any other authorisation Mooikraal
currently has been granted.
No changes since the previous audit. Therefore, no further action is
required.
C
Fuel and Hydraulic Oil is stored onsite at the Mooikraal operation
in bulk storage tanks. These tanks are stored within a bunded
area and on a concreted standing. It was noted that the bunded
area would be able to contain 1.5 times the amount of fuel
stored within these areas. The bunded areas have been
designed as per the South African National Standards (SANS)
10089 (for oils and transportation fuel) and SANS 310 (for
hazardous chemicals). The fuel storage area is located within a
dirty water area and therefore all water contained in this area is
diverted to the sump and discharged to the South PCD. It must
be noted that a new sump has being constructed and is
operational. It was however noted that an oil separator has not
yet been installed and water is being manually pumped out of
the sump. Ponding of water was observed around the sump
area and further maintenance and good housekeeping practices
is still required to ensure the sump operates at optimal capacity.
Mooikraal has confirmed that no conditions within this
authorisation contradict the conditions in the EMPr and any other
authorisation Mooikraal currently has been granted.
Mooikraal has one waste storage area. It was confirmed that this
waste area does not exceed 100 m3
for general waste and 80
m3
for hazardous waste. Therefore no listed activities in
accordance with the NEM:WA are triggered and no waste
licence is required. However, as best practice the NEM:WA
Norms and standards for the Storage of Waste, 2013 are
utilised as a guideline to ensure the storage area is
management in accordance with applicable legislation. It is
noted that no waste activity may commence without a waste
management licence should it trigger the listed activities in
accordance with Government Notice 921 in Government
Gazette 37083 dated 29 November 2013 of NEM:WA.
However, during the site assessment decommissioned
equipment which is no longer in use was observed to be
dumped within a designated clean water area located below the
silo and conveyer belt area. It was communicated that the
equipment had been drained of oil however the equipment is still
considered to be dirty and contained evidence of coal. Although
discussions regarding making this area the new waste
management area are being undertaken, decommissioned
equipment may not be permitted to be dumped in this area until
relevant mitigation measures have been implemented. It should
be noted that although the area was not measured it may
exceed 80 m3 which may result in the triggering of listed
activities in terms of the NEM:WA.
It was communicated during the site assessment that the DMR
makes regular visits to the mine to ensure it is compliant with its
various licences. The mine permits any authority who wishes to
conduct the audit provided that previous arrangements have
been made with the mine to ensure appropriate health and
safety procedures are followed.
During the site assessment it was observed that the waste
storage area is positioned on a concrete surface to prevent
potential contamination. Additionally the waste is placed within
skips to ensure all waste contained within the skips is treated as
contaminated and disposed at an appropriate licensed landfill
site. However it was observed that no roof is located over the
area where the waste is stored to prevent direct sunlight and rain
water from entering the waste container.
3.1
A copy of this approval letter and EMPR
must be kept at the property or on site office
where the mining activities will be
undertaken/are being conducted. This
approval letter and EMPr must be produced
to any authorised officials of the Department
who request to see it and must be made
available for inspection by any employee or
agent of the holder who works or undertakes
work at the mining area.
C No further action required
A copy of the authorisation as well as the EMPr is retained at the mine with
the appointed environmental offices Lisa Grobler. Additionally the
documents are saved on Sasol’s internal server. Should authorities or
employees wish to access the information Sasol will ensure the
documents are provided.
No changes since the previous audit. Therefore, no further action is
required.
C
3.2
The content of the EMPr and its objectives
must be made known to all contractors,
subcontractors, agent and any other people
working on the site, and any updates or
amendments to the EMPr must be submitted
to the Department for approval.
C No further action required
During the induction undertaken at Mooikraal contractors, subcontractors
and employees of the mine are educated on the requirements and
objectives of the EMPr and EA and environmental management measures
to be implemented. Contractors are required to abide by Sasol’s internal
policy on environmental management.
No changes since the previous audit. Therefore, no further action is
required.
C
3.3
Regular monitoring and maintenance of
storm water drainage facilities must be
conducted at all times, if damaged as
directed by the Department or any other
relevant authority.
NC
Effective stormwater management measures needs
to be implemented at both Mooikraal (soil / conveyer
belt area) as well as at 3 Shaft. Dirty water generated
from the mine should not be permitted to be
discharged as it can result in contamination. It is
however noted that stormwater management
measures are proposed to be implemented at 3 Shaft
as part of the 31 Amendment process.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
3.4
A buffer zone of 100 metres between the
activity (ies) and the residential areas,
cemeteries or burial grounds, Eskom power
lines and the fuel pipe line must be clearly
demarcated and maintained.
C No further action required
No residential areas and archaeological and/or cultural historical sites are
located within 100 meters of the operational structures of the mine. A
statutory plan is updated on an annual basis which demonstrates this buffer
zone.
No changes since the previous audit. Therefore, no further action is
required.
C
3.5
The holder must prevent nuisance conditions
or health hazards, or the potential creation of
nuisance conditions or health hazards.
NC
Mooikraal is in the process applying for environmental
authorization for the upgrade of the stormwater
management measures at 3 Shaft. The proposed
upgrade involves the construction of silt traps and the
re-use of water back into its primary processing plant
as dust suppression. Should authorisation be
received, rehabilitation specifically where the coal has
built up beneath the culvert at 3 shaft should be
desilted to allow continuous flow of water.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
5) MANAGEMENT OF MINING ACTIVITIES
Clean water is diverted around the mine and permitted to be
discharged directly to the environment. Berms are created
around the mining areas so as to assist with the diversion of
clean water away from the dirty water areas and the containment
of dirty water to prevent accidental discharge to the environment.
It was noted that the clean water berms are well maintained.
Maintenance activities are undertaken regularly and inspections
are undertaken before and after many major storms. However a
lack of effective storm water management to prevent dirty water
being discharged to the environment was observed at both
Mooikraal (soil / conveyer belt area) as well as at 3 Shaft. It was
observed that at both these locations dirty water was being
discharged to the environment.
No residential areas and archaeological and/or cultural historical
sites are located within 100 meters of the operational structures
of the mine. A statutory plan is updated on an annual basis which
demonstrates this buffer zone. This plan is submitted to the
DMR every September on an annual basis.
Mooikraal aims to ensure that its operation is well managed and
abides by the conditions in the authorisation and EMPr.
Additional best practice procedures are also considered to
prevent the possibility of a nuisance or health hazard occurring.
Continuous monitoring is being undertaken to ensure the mine is
not resulting in contamination of the environment. When
elevated levels of contaminates are identified, mitigation
measures are implemented to rectify the issue. Additionally a
complaints register is maintained to ensure that all issue raised
by I&APs are recorded and an investigation is undertaken to
address the issue prior to it becoming a potential nuisance
conditions or health hazards. However, it was observed that dirty
water generated at 3 Shaft from the coal stockpile area is being
discharged directly into the Leeuspruit. The results indicate that
over the past year and a half increased levels of sulphate are
noted which has resulted in pH values exceeding 8 which can
result in health hazards. It is however noted that the deteriorating
water quality is not only from 3 Shaft and has other contributing
factors. At a regional scale, the Vaal River, which the Leeuspruit
joins, is considered to be heavily contaminated as a result of
accidental discharges from the municipal STP which has
resulted in the significant losses of aquatic life. Although the
STP has a more significant impact on the environment and the
people utilising the river, additional contamination to the river
generated from 3 Shaft should be avoided.
A copy of the authorisation as well as the EMPr is retained at the
mine with the appointed environmental offices Lisa Grobler.
Additionally the documents are saved on Sasol’s internal server.
Should authorities or employees wish to access the information
Sasol will ensure the documents are provided.
During the induction undertaken at Mooikraal contractors,
subcontractors and employees of the mine are educated on the
requirements and objectives of the EMPr and EA and
environmental management measures to be implemented.
Contractors are required to abide by Sasol’s internal policy on
environmental management. During the site assessment sub-
contractors where located onsite which were in the process of
constructing new office buildings.
3.6
Mining activities must be managed and
operated in accordance with the
Environmental Management Systems (EMS)
that inter alia identifies and minimises risks of
pollution, including those arising from
operations, maintenance, accidents,
incidents and non-conformances and those
drawn to the attention of the holder as a
result of complaints.
C No further action required
Mooikraal Mine is ISO 14001 certified. The latest ISO 14001 audit was
undertaken in May 2018 by DQS . An EMS system has been set up to
ensure compliance with the ISO 14001:2015 system to ensure that all
monitoring is recorded as well as incidents are reported on.
No changes since the previous audit. Therefore, no further action is
required.
C
3.7
The holder must ensure that all non-
recyclable waste are disposed at waste
management facilities licenced to handle
such wastes and all recyclable waste are
collected by licenced waste management
facilities for recycling, reuse or treatment.
NC
Waste should not be permitted to be dump in any
other place besides the waste storage facilities. The
area where the coal waste was dumped at Sigma
Defunct Colliery should be cleaned up as the land had
been recently rehabilitated as part of the closure
process for the Sigma Defunct Colliery.
It is noted that waste generated at Mooikraal and 3 Shaft is stored in
designated waste storage areas, one at Mooikraal and one at 3 Shaft,
which is separated into various waste streams. Waste contractors have
been appointed to remove the waste and dispose of it at a licence waste
facility.
However, it was observed at the laydown area that there were redundant
cars and used tyres. Redundant cars become classfied as waste and
should be removed from site accordingly as either scrap metal or another
type of waste. The used tyres need to be handled in accordance with the
Waste Tyres Regulations under the National Environmental Management:
Waste Act No. 59 of 2008.
NC
3.8
The holder must ensure that all liquid wastes,
whose emissions to water or land could
cause pollution are diverted to sewer, after
testing water quality and receiving written
approval from the relevant local authority.
NC
It is recommended that an investigation be
undertaken to determine the reason for the high
concentrations of NO3 and E Coli in the treated
effluent that is discharged from the STP. Measures
must be implemented to ensure that these non-
compliances are addressed and aim to comply with
the specified qualities of the IWUL.
The Mooikraal STP must be registered with the DWS
and have a registration certificate displayed on site
which includes the classification of the STP. In
addition, the Process Controller (PC) must be
registered and have the relevant qualifications and
training to operate the specified class of STP. This is
contained in Regulation 2834 of WA (1956) and Draft
Regulation 813 of the Water Services Act, 1997 (Act
108 of 1997).
An investigation was conducted as per the 2018 recommendation and the
Nitrate and E.coli was treated by adding fresh innoculent into the STP.
A registration of the "Mooikraal Wastewater Works" under section 26 of
the National Water Acr with the Department of Water Affairs was avaliable
and issued 13 December 2012.
The operators are approporiately qualified to operate the STP.
C
3.9
Non-compliance with any condition of this
approval letter or EMPr may result in the
issuing of statutory orders or instruction as
per section 93 and 47 of the MPRDA.
C No further action required
External audits are undertaken to determine the level of compliance the
mine has towards its authorisation and EMPR. The audit reports aim to
document the non-conformities and propose mitigation measures to
address the issues that were identified. These reports are submitted to the
DMR by Sasol on an annual basis to notify them of the non-conformities
that may have been identified.
This audit serves as the external audit to check compliance status. Non-
compliances idnetified during thia audit will be addressed accordingly
through an action plan.
C
External audits are undertaken to determine the level of
compliance the mine has towards its authorisation and EMPR.
The audit reports aim to document the non-conformities and
propose mitigation measures to address the issues that were
identified. These reports are submitted to the DMR by Sasol on
an annual basis to notify them of the non-conformities that may
have been identified. The lasted audit report was submitted in 8
December 2017. Once a non-compliance is noted Sasol
compile action lists of how to address the non-compliance and
specify a deadline to implement the measures.
In accordance with Mooikraal IWUL (Licence No.
08/C22K/CIGJFAE/6981), the STP is authorised to discharge
treated effluent to the environment. The STPs are operated in
accordance with the Site Specific Standard Operating
Procedure (SOP): The handling of sewage at Mooikraal (Ref No.
SOP 4.4.6/07). The STP treats the sewage originating from the
office blocks and change houses using a package plant
consisting of an aeration reactor and chorine tank. Chlorine is
added to the final treated effluent to ensure the quality of water
is suitable for discharge to the catchment. Monthly samples are
taken and submitted to a SANNAS accredited laboratory. The
final treated effluent from the STP at Mooikraal is discharged to
an open channel which is then released into the
Kromelmboogspruit. The results for the water that is being
discharged from the STP indicated that the volume and quality
of treated effluent exceeds the authorised volume and qualities
specified in the IWUL specifically for nitrate and E.coli.
Mooikraal Mine is ISO 14001 certified. The latest ISO 14001
audit was undertaken in May 2018 by DQS . An EMS system
has been set up to ensure compliance with the ISO 14001:2015
system to ensure that all monitoring is recorded as well as
incidents are reported on. Additionally operational procedures
have also been compiled which deal with specific actions to be
undertaken at the mine as well as procedures to address an
emergency situation such as the Emergency Preparedness and
Response Procedure (Ref No. SIG IMS 447000) and
Procedure for the Handling of Oil Spills and Oil Recycling (Ref
No. SIG (EM) IMS SOP/ 008). Additionally complaints are
recorded on an external complaints register which is managed
by Sasol Mining Rights and Properties Department. All issues
are investigated and resolved (Mooikraal Complaints Register
April 2018).
It is noted that waste generated at Mooikraal and 3 Shaft is
stored in designated waste storage areas, one at Mooikraal and
one at 3 Shaft, which is separated into various waste streams.
Waste contractors have been appointed to remove the waste
and dispose of it at a licence waste facility. However, during the
site assessment it was observed that the clean-up crew, which
cleans up coal along the conveyer belt was collecting all the coal
and dumping it on previously rehabilitated land for the local
people in the surrounding communicates to use. The area where
the coal is being dumped is not considered to be a dirty water
area as it has recently been rehabilitated and coal dumped in the
area should not be permitted. It is however noted that when the
EAP became aware of the issue immediate measure where
undertaken to stop the coal being dumped.
3.10
Only mining activities that are expressly
specified in the EMPr that forms part of this
approval letter may be conducted, and
additional or new activities not specified
herein must be applied for by the holder and
authorised in the form of an amendment to
the aforesaid EMPr before such activities
may be commenced with. This condition is
also applicable in the case of the
amendment, addition, substitution,
correction, and removal or updating of any
detail in the aforesaid EMPr.
NC
Based on the review of the EMP and correlated with
the legislative requirements of the EIA Regulations,
2014 (as amended) it is concluded that 3 Shaft which
includes the operation of the primary processing plant
is not sufficiently described, the impacts assessed
and mitigation measures provided in the EMPr to
confirm an environmental authorisation for the
activities or the area on which the activities are taking
place. The lack of detail in the EMPr with regard to 3
Shaft can be rectified by means of a Regulation 31
amendment application process. Mooikraal have
appointed Digby Wells to undertake the required
Regulation 31 amendment process to rectify the
issues identified by this audit report. This process has
however not commenced yet.
Mooikraal has appointed an Environmental Assessment Practitioner (EAP)
to undertake a Regulation 31 EMPR Amendment Process in terms of the
EIA Regulations, 2014 and to apply for a Water Use Licence (WUL) in
terms of Section 21 of the National Water Act, 1998 (Act No. 36 of 1998)
(NWA). The authorisation of the Regulation 31 EMPR Amendment
application and WUL application will allow for most conditions identified as
non-compliant in the audit to be addressed.
The authorisation has not been granted as yet and thus this EA
commitment remains non-compliant until such a time that the changes are
authorised.
NC
3.11
Rehabilitation of the disturbed surface
caused by mining operation at all times must
comply with the approved EMPr
C No further action required
As the Mooikraal Mine is an underground coal mine, limited rehabilitation is
undertaken on areas where mining or related activities have been
undertaken. It was reported that to date only minimal rehabilitation activities
had been undertaken. Once LoM is reached, all infrastructure will be
removed from site and rehabilitation will commence in line with the
rehabilitation measures proposed in the approved EMPR.
This is still the way the mine will operate. No changes to the
implementation of rehabilitation measures isnce the previous audit.
Therefore, continual management of areas should take place, however, no
immediate action is required.
C
3.12
The holder must ensure that the name and
contact details of the person responsible for
environmental management is made
available to the Regional Manager within 30
days from the date of this approval
(consolidation of mining rights and approved
EMPrs).The holder must also ensure that a
person responsible for environmental
management is always available on site to
ensure that mining activities at all times
comply with the conditions of approval letter
and approved EMPr (consolidated).
C No further action required
Since the mine began operating in 2005, no changes to the contact details
of the holder of the authorisation have occurred therefore no notification of
the regional manager is required.
Lisa Grobler has been appointed by Sasol to ensure that all conditions are
adhered to on the mine and ensure mining activities are undertaken in
accordance with relevant legislation.
No changes since the previous audit, therefore no further action is
required.
C
3.13
3.13 a
Keep and maintain a detailed incidents
register (including any spillages of fuels,
chemicals or any other material
C No further action required
An incident register is retained onsite and maintained by the Environmental
Practitioner at the mine. Any incidences or non-conformities that occur are
reported on and an investigation is undertaken to resolve the issue.
The . SIG IMS 10.2 Incident Register is still operational and the only
actions required are the mitigation measures for each incident logged.
C
The Mooikraal operation aims to ensure that Chapter 5 of NEMA
is complied with to ensure all environmental management is
undertaken correctly and all impacts that the mine may have on
the environment is assessed and mitigated. It is however note
that the Mooikraal EMPr has failed to assess and provide
mitigation measures for all aspect specific to 3 Shaft. A non-
compliance as been identified against Section 24N with regards
to the effectiveness of the EMPr. Please refer to Section 8 of
the audit report for further details regarding the non-compliance.
It can be concluded however that in accordance with the NEMA
and EIA Regulations 2014 (as amended), the Mooikraal EMPr is
substantively lacking with regard to 3 Shaft in the following
respects:
■ 3 Shaft and its associated activities are not included in Section
1.1 or 1.2 of the EMPr, the sections which give the project
background and description respectively;
■ The Mooikraal EMPr does not adequately incorporate the
activities, aspects, impacts and associated mitigation steps at 3
Shaft into Section 4 – Environmental Impact Assessment,
Section 5.3 Environmental Management Programme, or Section
7 Environmental Monitoring.
■ Infrastructure (figure 2) and locality plans (figure 1) do not
indicate the infrastructure at 3 Shaft, nor the physical location of
3 Shaft, the mining right boundary does not correlate with the
Plan of Land Amendment of a Mining Right (dated 05/02/2016).
As the Mooikraal Mine is an underground coal mine, limited
rehabilitation is undertaken on areas where mining or related
activities have been undertaken. It was reported that to date only
minimal rehabilitation activities had been undertaken. Once LoM
is reached, all infrastructure will be removed from site and
rehabilitation will commence in line with the rehabilitation
measures proposed in the approved EMPr, a rehabilitation
management plan will be compiled once closure is reached
which will include all mitigation measures to prevent
unnecessary environmental impact. It was observed that all soil
stockpiles as well as the areas around the mine was vegetated
Since the mine began operating in 2005, no changes to the
contact details of the holder of the authorisation have occurred
therefore no notification of the regional manager is required. An
Environmental Practitioner, Lisa Grobler has been appointed by
Sasol to ensure that all conditions are adhered to on the mine
and ensure mining activities are undertaken in accordance with
relevant legislation.
The person responsible for environmental management must:
An incident register is retained onsite and maintained by the
Environmental Practitioner at the mine. Any incidences or non-
conformities that occur are reported on and an investigation is
undertaken to resolve the issue. Additionally internal weekly
audits are undertaken by the Environmental Practitioner to
ensure that any incidents are recorded and reported on. The
most recent incident that was reported occurred in July 2018
due to a contractor damaging a water line (Ref No. SIG IMS
10.2 Incident Register 2018). The incident was reported to be
investigated and resolved. Additionally Mooikraal is an ISO
14001 certified mine and as per part 4.5.3 an incident register is
required.
3.13 b
Keep a complaint register on site indicating
the complaint and how the issues were
addressed, what measures were taken and
what the preventative measures were
implemented to avoid re-occurrence of
complaints
C No further action required
A complaints register is maintained which documents all complaints raised
by I&APs, landowners as well as adjacent landowners.
It is recommended that the complaints be addressed expediantly.
C
3.13 c
Keep records relating to monitoring and
auditing on site and avail them for inspection
to any relevant authorised officials.
3.13 dKeep copies of all environmental reports
submitted to the Department.
3.13 eKeep the records of all permits, licences and
authorisations required by the operation.
3.13 f
Compile a monthly monitoring report and
make it available to the Department if
requested.
C No further action required
Monitoring is undertaken to monitor groundwater, surface water, air quality
and aquatics / wetlands. Additionally regular reports are compiled which
consolidate these results and indicate its compliance to various
authorisations obtained by the mine. Should the DMR wish a monthly
monitoring report to be submitted this will be undertaken by the mine.
If the DMR requests monthly reports from Mooikraal, reports will be
furnished. For now, no further action is required outside the periodic
monitoring already taking place.
C
3.14
The duties and responsibility of the person
responsible of environmental management
should not be seen as exempting the holder
from the legal obligations in terms of the
MPRDA and it subordinate Regulations.
C No further action requiredLisa Grobler aims to ensure the mine is compliant with is authorisations
and does not contribute to increasing environmental pollution. C
3.15
The footprint of the mining activities must be
limited on the areas authorised for the actual
construction works and operational
activities and all areas outside of the
footprint must be regarded as a "no go"
areas.
C No further action required
Surface activities is located within the shaft area and the underground
mining activities are being undertaken within the mining right area. No
mining activities are being undertaken outside of the authorised areas.
There are no changes to this since the previous audit.
C
3.16
Erosion and soil loss must be prevented by
minimizing the construction site exposed to
surface water run-off. Where necessary
erosion stabilizing action such as gabions or
re-vegetation must be implemented to
prevent further habitat deterioration.
NA No further action required
The Mooikraal Mine has been operational since 2005. No construction
activities are currently being undertaken at the mine. Therefore, this
condition is considered to be not applicable. Therefore, no further action is
required.
NA
3.17
The holder must ensure that all personnel
who work with hazardous waste are trained to
deal with these potential hazardous situations
so as to minimise the risk involved. Records
of training and verification of competence
must be kept by the holder.
C No further action required
Waste is managed in accordance with the waste management procedure
for Mooikraal Colliery (Ref No. IMS(EM) 4.4.6 / SOP 001). This procedure
stipulated the appropriate measures which must be undertaken to ensure
waste is handled correctly. These procedures are then communicated to
all employees and internal training is undertaken.
External training is still not undertaken as EnviroServ has been contracted
to remove and deal with hazardous waste. It was noted that EnviroServ has
the relevant licences and training certificates for the handling of hazardous
waste.
Therefore, no further action is required.
C
3.18
In order to prevent nuisance conditions, the
holder must ensure that all storage skips and
bins are not overfilled
C No further action required
Waste skips are emptied by EnviroServ on a weekly basis. All waste is
handled in accordance with the waste management procedure for
Mooikraal Colliery (Ref No. IMS(EM) 4.4.6 / SOP 001). During the site visit,
the oil drums were being collected and the skips not overflowing.
C
The Environmental Practitioner aims to ensure the mine is
compliant with is authorisations and does not contribute to
increasing environmental pollution.
During the site assessment and based on the maps provided it
can be confirmed that the surface activities is located within the
shaft area and the underground mining activities are being
undertaken within the mining right area. No mining activities are
being undertaken outside of the authorised areas.
The Mooikraal Mine has been operational since 2005. No
construction activities are currently being undertaken at the mine.
Therefore, this condition is considered to be not applicable.
Waste is managed in accordance with the waste management
procedure for Mooikraal Colliery (Ref No. IMS(EM) 4.4.6 / SOP
001). This procedure stipulated the appropriate measures which
must be undertaken to ensure waste is handled correctly. These
procedures are then communicated to all employees and
internal training is undertaken. External training is not undertaken
as EnviroServ has been contracted to remove and deal with
hazardous waste. It was noted that EnviroServ has the relevant
licences and training certificates for the handling of hazardous
waste.
It was communicated that waste skips are emptied by
EnviroServ on a weekly basis. All waste is handled in
accordance with the waste management procedure for
Mooikraal Colliery (Ref No. IMS(EM) 4.4.6 / SOP 001). During
the site assessment it was observed that none of the waste
skips were overfilled.
7) REPORTING TO THE DEPARTMENT
Monitoring is undertaken to monitor groundwater, surface water,
air quality and aquatics / wetlands. Additionally regular reports
are compiled which consolidate these results and indicate its
compliance to various authorisations obtained by the mine.
Should the DMR wish a monthly monitoring report to be
submitted this will be undertaken by the mine.
All documents regarding monitoring and auditioning is kept at
the Mooikraal Mine with the Environmental Practitioner as well as
saved on the Sasol internal server. All monitoring and auditing
reports were made available to the auditors during the site
assessment and compilation of this audit report for 2018. A list
of documents that were reviewed during this audit has been
listed in Section 2.1 of the audit report.
C No further action required
An external complaints register (Mooikraal Complaints Register
April 2018) is maintained which documents all complaints raised
by I&APs, landowners as well as adjacent landowners. These
complaints are directed to the Sasol Mineral Rights
Departments. All issues raised are investigated and specific
actions are implemented to ensure the issue is resolved. The
complaints register provided has captured complaints raised
between 2016 and 2018.
All documents regarding monitoring and auditioning is kept at the Mooikraal
Mine with the Environmental Practitioner as well as saved on the Sasol
internal server. All monitoring and auditing reports were made available to
the auditors during the site assessment.
No changes since the previous audit. Therefore, no further action is
required.
C
4.1
The holder must submit an Environmental
Performance Assessment Report to this
Department annually as per regulation 55 of
the MPRDA Regulations. The report should
be submitted manually in a form of two (2)
copies which specify whether the conditions
of this approval letter and an approved EMPr
are adhered to. This Environmental
Performance Assessment Report must
include the information referred to in
condition 4.2 below.
C No further action required
This audit is in line with Regulation 55 of the Mineral and Petroleum
Resources Development Act, 2002 (Act No. 28 of 2002) (MRPDA) and
associated MPRDA Regulations (GN R527 of 23 April 2004); and
Regulation 34 of the Environmental Impact Assessment (EIA)
Regulations, 2014 (GN R326 of 7 April 2017), as amended (EIA
Regulations, 2014) promulgated under the National Environmental
Management Act, 1998 (Act No. 107 of 1998) (NEMA), respectively.
C
4.2
The holder must annually assess the
environmental liabilities of the operation as
contemplated in the Financial Provisioning
Regulations, 2015 and address the shortfall
on the financial provision submitted in terms
of section 24P of NEMA.
C No further action required
Jones and Wagener (Ref No. JW047/15/E473 - Rev 4) updated the
calculation of the financial provision for the various Sasol operational areas
in March 2019 and this included the Mooikraal Operations and the MKR1 -
Sigma No 3 Shaft at R 11 016 424.36; MKR2 - Mooikraal at R 74 063
714.64 and MKR3 - Old Sigma coal handling at R 35 213 788.19 and all
amounting to a total of R 120 293 927.19.
C
4.3
The holder must, within 24 hours of incidents
occurring, notify this department any other
relevant department of the occurrence or
detection of any incident on the site, or
incidental to the operation of the site, which
has the potential to cause, or has caused
pollution of the environment, health risks,
nuisance conditions or water pollution.
C No further action required
In 2013 it was, determined that the both the South and North PCDs, which
are clay lined, were unable to contain the amount of water being pumped
from the underground workings to the dams which resulted in multiple
overflows over the past few years.
These incidents were reported to the DMR and DWS. No incidents have
happened since then.
C
5.1
The holder must ensure effective access
control on the site to reasonably prevent
unauthorised entry. Signs indicating the risks
involved in unauthorised entry must be
displayed at each entrance.
C No further action required
The mine is access controlled to ensure no unauthorised personnel are
permitted into the mine. During the site visit he auditors were required to
provide identification documentation as well as permission from the
Environmental Practitioner was required to gain access to the mine. C
5.2
Weather proof, durable and legible notices in
at least three official languages applicable in
the area must be displayed at each entrance
to the Site. These notices must prohibit
unauthorised entry and state the hours of
operation, the name, address and telephone
number of the holder and the person
responsible for the operation of the site.
C No further action required
Appropriate signage is placed at the entrance to Mooikraal and 3 Shaft
which is weather proof and provides the correct information regarding the
operation and the holder of the authorisation. The necessary signage were
also provided at the entrance to the STP and the PCDs.
C
The holder must maintain and implement an
emergency preparedness plan and review it
biennially when conducting environmental
monitoring and assessment or audit and after
each emergency and or major accident. The
plan must, amongst others, include:
o Site fire
o Spillage
It is recommended that the Emergency Preparedness
and Response Procedure must be updated / revised
in 2018 and continue to be updated every two years
going forward and after any emergency incident that
would have a significant impact on the receiving
environment.
Appropriate signage is placed at the entrance to Mooikraal and 3
Shaft which is weather proof and provides the correct
information regarding the operation and the holder of the
authorisation. The necessary signage were also provided at the
entrance to the STP and the PCDs
11) EMERGENCY PREPAREDNESS PLAN
6.1 C
An Emergency Preparedness and Response Procedure has
been compiled for the Mooikraal Colliery (Ref No. SIG IMS
447000). The procedure deals with various environmental
emergencies which include:
■ Fire outbreak / surface or veld fires
■ Flooding (underground)
The first overflow of the PCD was reported through formal
communication however since then continuous email
communication between the mine and the DWS is undertaken
which aims to communicate when the PCD overflows.
The overflow of the PCDs is reported to DWS on a regular
basis. It is noted that when the PCDs overflows, weekly
monitoring is undertaken at the Kromelmboogspruit to determine
the level of impact this water has on the water quality. These
results are reported to the DWS, the latest results were
submitted on 8 February 2017. Weekly monitoring will again be
undertaken with the reporting of this overflow incident.
9) SITE SECURITY AND ACCESS CONTROL
The mine is access controlled to ensure no unauthorised
personnel are permitted into the mine. During the site
assessment the auditors were required to provide identification
documentation as well as permission from the Environmental
Practitioner was required to gain access to the mine. The
access to the Mooikraal Colliery is permitted through the main
gate which is access controlled. Access to 3 Shaft is also only
permitted by one gate. To gain entry, access cards as well as a
biometric systems have been implemented. Fencing has been
constructed around the entire Mooikraal Colliery and 3 Shaft and
no entry signage has been erected. Fencing has also been
erected around the PCDs (both Mooikraal and 3 Shaft) which are
required to prevent the possibility of drowning and restrict
access. Signage has also been erected to discourage people
from entering the restricted area. Additionally entry to the
underground workings is also restricted by means of a shaft
guard which requires proof that the individual is fit to work prior
to that individual proceeding.
External audits are undertaken to determine the level of
compliance the mine has towards its authorisation and EMPr.
The audit reports aim to document the non-conformities and
propose mitigation measures to address the issues that were
identified. These reports are submitted to the DMR by Sasol on
an annual basis to notify them of the non-conformities that may
have been identified. The lasted audit report was submitted in
December 2017.
Sasol Mining calculated the financial provision for the various
Sasol mines in 2018 which was completed by Jones and
Wagener (Ref No. JW047/15/E473 - Rev 3). Financial provision
for Mooikraal for 2018 was estimated to be R 70,209,540.00.
Financial provision for Old Sigma Coal Handling for 2018 was
estimated to be R 33,314,672.00. Financial provision for 3 Shaft
for 2018 was estimated to be R 11,088,759.00
.
the Emergency Preparedness and Response Procedure is available and
due for a revision in 2021.
No emergency incident has trigger the need for an update.
C
o Natural disasters such
as floodso Industrial actiono Contact details of
police, ambulances and
any emergency centre
closer to the site
6.2
The holder must ensure that an up to date
emergency register is kept during all phases
of the mining operation. This register must
be made available upon request by the
department.
C No further action required
An incident register is retained onsite which records any incidents that may
occur during all phases of the mining operation. All incidents that occur at
Mooikraal are dealt with in accordance with the Emergency Preparedness
and Response Procedure.
There are no chnages to the way emergencies are addressed on site.
C
7.1
If, in the opinion of this department,
nuisances or health risks may be or is
occurring on the site, the holder must initiate
an investigation into the cause of the problem
or suspected problem.
C No further action required
The department has not raised specific issues with regards to health risks
or nuisances. It is noted however that all non-compliance identified during
the audit is reported to the department on an annual basis.
Therefore, no further action required
C
7.2
If, in the opinion of this department, pollution
may be or is occurring, the holder must
initiate an investigation into the cause of the
problem or suspected problem. Such
investigation must include the monitoring of
the water quality variables, at those
monitoring points and such frequency as may
be specified by the Department of Water and
Sanitation.
C No further action required
The department have not raised specific issues with regards to pollution or
contamination. It is noted however that all non-compliance identified during
the audit is reported to the department on an annual basis.
Therefore, no further action required
C
7.3
Investigations carried out in terms of
conditions 7.1 and 7.2 above must include
the monitoring of the relevant environmental
pollution, nuisance and health risk variables,
at those monitoring points and such
frequency to be determined in consultation
with the relevant Departments.
C No further action required
The department has not raised specific issues with regards to health risks,
nuisances, pollution or contamination. It is noted however that all non-
compliance identified during the audit is reported to the department on an
annual basis.
Therefore, no further action required
C
7.4
Should the investigation carried out as per
conditions 7.1 and 7.2 above reveal any
unacceptable levels of pollution, the holder
must submit mitigation measures to the
satisfaction of this and any other relevant
Department.
C No further action required
The department has not raised specific issues with regards to pollution. It
is noted however that all non-compliance identified during the audit is
reported to the department on an annual basis.
Therefore, no further action required
C
8.1
The holder must apply for a closure
certificate as prescribed in the MPRDA
and any other applicable legislation
NA No further action required
The Mooikraal Colliery has been operational since 2005 and has a LoM of
34 years. A closure certificate will only be applied for once LoM is
reached.
NA
8.2
The application for closure indicated above
must be submitted together with all relevant
documents as prescribed in the MPRDA and
any other applicable legislation.
NA No further action required
The Mooikraal Colliery has been operational since 2005 and has a LoM of
34 years. A closure certificate will only be applied for once LoM is
reached. The mine will submit all relevant documentation at this time.
NA
The Mooikraal Colliery has been operational since 2005 and has
a LoM of 34 years. A closure certificate will only be applied for
once LoM is reached.
The Mooikraal Colliery has been operational since 2005 and has
a LoM of 34 years. A closure certificate will only be applied for
once LoM is reached. The mine will submit all relevant
documentation at this time.
The department have not raised specific issues with regards to
pollution or contamination. It is noted however that all non-
compliance identified during the audit is reported to the
department on an annual basis.
The department have not raised specific issues with regards to
pollution or contamination. It is noted however that all non-
compliance identified during the audit is reported to the
department on an annual basis.
The department have not raised specific issues with regards to
pollution or contamination. It is noted however that all non-
compliance identified during the audit is reported to the
department on an annual basis.
The department have not raised specific issues with regards to
pollution or contamination. It is noted however that all non-
compliance identified during the audit is reported to the
department on an annual basis.
It is recommended that the Emergency Preparedness
and Response Procedure must be updated / revised
in 2018 and continue to be updated every two years
going forward and after any emergency incident that
would have a significant impact on the receiving
environment.
An incident register (Ref No. Ref No. SIG IMS 10.2 Incident
Register 2018) is retained onsite which records any incidents
that may occur during all phases of the mining operation. All
incidents that occur at Mooikraal are dealt with in accordance
with the Emergency Preparedness and Response Procedure
(Ref No. SIG IMS 447000). The DWS is also notified of the
incident such as the overflow of the water from the PCD into the
Kromelmboogspruit. This register is available should the
department wish to review it.
13) INVESTIGATIONS
■ Multiple casualty accidents
■ Entrapment
■ Total mine power failure
■ Fan/ventilation failure
■ Gas explosion (surface storage areas)
■ Employees missing underground
6.1 C
■ Spillages of potentially contaminated water (mine water
■ Diesel tank ruptures (Mooikraal) / petrol pump failure 3#
The Emergency Preparedness and Response Procedure was
last revised in 2013 and should have been reviewed on a
biennial basis in 2015 and again in 2017.
15) SITE CLOSURE
the Emergency Preparedness and Response Procedure is available and
due for a revision in 2021.
No emergency incident has trigger the need for an update.
C
8.3
The holder remains responsible for any
environmental liability, pollution or ecological
degradation, the pumping and treatment of
extraneous water, compliance with the
conditions of this approval letter, the
approved EMPr, management and
sustainable closure thereof until the Minister
has issued a closure certificate in terms of
section 43 of the MPRDA. Where necessary
the Minister may retain certain portion of
financial provision for residual, health or
environmental impacts that might be known in
future.
NA No further action required
The Mooikraal Colliery has been operational since 2005 and has a LoM of
34 years. A closure certificate will only be applied for once LoM is
reached. Mooikraal understands that environmental liability remains with the
mine until the closure certificate is obtained.
NA
Compliant 55 88.71
Non-compliant 7 11.29
Not Applicable 14
Total 76
Total Applicable 62
76
The Mooikraal Colliery has been operational since 2005 and has
a LoM of 34 years. A closure certificate will only be applied for
once LoM is reached. Mooikraal understands that environmental
liability remains with the mine until the closure certificate is
obtained.
Appendix B: EMPR Checklist
Compliance Compliance (2019)
C /NC/NA C /NC/NA
■ To ensure that the resource is
mined optimally.
The comprehensive monitoring of
surface subsidence is and will be
done in accordance with the
requirements of Regulation 5.3.6 and
Regulation 12.7.1 of the GN992 of
26/06/1970.
C
The Mooikraal Colliery undertakes both bord and
pillar and high extraction mining method to extract
the coal from the coal seam. It was
communicated that no high extraction mining is
undertaken beneath watercourses in accordance
with GN 704. To date no subsidence has
occurred within the Mooikraal mining right area.
However a visual surface inspection is
undertaken on a biannual basis of the elevation of
the land where high extraction has occurred.
No further action required
The Mooikraal Colliery undertakes both bord
and pillar and high extraction mining method to
extract the coal from the coal seam. It was
communicated that no high extraction mining is
undertaken beneath watercourses in
accordance with GN R 704. To date no
subsidence has occurred within the Mooikraal
mining right area. However a visual surface
inspection is undertaken on a biannual basis
of the elevation of the land where high
extraction has occurred.
C
Where the probability of an
occurrence of subsidence has been
determined and it poses a danger,
the void area underground, in that
specific area will be stabilised as far
as is practicably possible in terms of
Regulation 5.3.3 of the GN992 of
26/06/1970, after consultation with
the relevant authorities and affected
parties. The fill material used to date
consists of fine ash due to its
pozzalenic properties or fine ash and
cement mixtures.
C
It was communicated to Digby Wells that to date
no evidence of subsidence has occurred within
the Mooikraal mining right area. This was
confirmed by the biannual report which is
submitted to DWS ever year. This is based on
regular surveys that are done on the area that
has been undermined. Visual surveys are
completed on a quarterly basis with Lidar
monitoring undertaken on an annual / biennial
basis. It was confirmed that the survey will be
undertaken in 2018. However, should there be
such instances of subsidence; the areas will be
rehabilitated in order to make the area free
draining as far as practicably possible, as per
procedure: Rehabilitation of Damage to the
Surface Due to Underground Mining Operations at
Sigma Colliery (SIG IM (EM) 4.4.6 021). It should
however be noted that although the EMPr gives
permission to pump ash underground to stabilise
the underground workings, a IWUL will need to be
obtained before this is commenced with. To date
no ash backfilling has taken place at Mooikraal
Colliery.
No further action required
No evidence of subsidence has occurred
within the Mooikraal mining right area. This is
confirmed by the biannual subsidence
monitoring report which is submitted to DWS
ever year. The report documents the findings
of regular surveys that are done in the area
that has been undermined.
C
Surface water permeability in the
subsidence areas will be controlled
from entering the underground
working by means of :
■ Rehabilitating the surface of the
soils as discussed in paragraph
5.3.2,
■ By making the area as far as is
practically possible to be free
draining, and
■ Where the soil type does not
allow for natural drainage the area
may have to be shaped to emulate
more or less the natural contours so
as to provide for surface run-off.
Audit Comments
EMPr for the Operation of Sigma Mooikraal Operations
Action Plan - Measures to be Implemented to
Achieve Compliance
No further action required
■ To monitor surface subsidence
so as to determine and plan for the
long-term land use and to timeously
prevent or control a dangerous
situation which may occur from such
a subsidence.
Activity Aspect Objective Proposed Mitigation Measure Comments 2018
1 Geology
C
It was communicated to Digby Wells that to date
no evidence of subsidence has occurred within
the Mooikraal mining right area. However, should
there be such instances of subsidence; the areas
will be rehabilitated in order to make the area free
draining as far as practicably possible, as per
procedure: Procedure for Rehabilitation of
Damage to the Surface Due to Underground
Mining Operations at Sigma Colliery (SIG IM (EM)
4.4.6 021). Additionally should subsidence occur
the area will be rehabilitated, thereafter the area
will be monitored for soil erosion every month for
a year, then biannually for a year and then
annually for three years until erosion is no longer
detected.
No evidence of subsidence has occurred
within the Mooikraal mining right area. This is
confirmed by the biannual subsidence
monitoring report which is submitted to DWS
ever year. The report documents the findings
of regular surveys that are done in the area
that has been undermined.
C
■ To ensure that no soils in new
areas are disturbed.
Soils in areas not allocated to the
building of infrastructures will not be
disturbed unnecessarily.
C
During the construction of the mine soils would
have been disturbed for the establishment of the
surface infrastructure as well as the incline shaft.
Since then the Kleinvlei Ventilation Shaft was
established in 2010 which resulted in further
disturbance of the soil in that specific area.
During the site assessment no unnecessary soil
disturbance was observed however the area
where the conveyor belt is located, a borrow pit
was constructed and the soil was disturbed.
Rehabilitation efforts have been undertaken
however it is noted that further rehabilitation is
still required. It was also determined that the soil
stockpiles were well vegetated and the waste
rock dump although erosion that was observed
did not require further intervention as the discard
dump was located within a contained area and no
soil lost to soil erosion was exiting the
containment area.
Although full rehabilitation will not be undertaken
until LoM is reached it is recommended that
rehabilitation of the borrow pits should be
undertaken to prevent ponding of water and the
spread of alien invasive species. The area should
be ploughed to make the surface level. Additionally
alien invasive management measures must be
implemented.
During the construction of the mine soils would
have been disturbed for the establishment of
the surface infrastructure as well as the incline
shaft.
No unnecessary soil disturbance was
observed however the area where the
conveyor belt is located, a borrow pit was
constructed and the soil was disturbed. Some
soils were also used to renovate the PCD spill
way.
Therefore, no soils were disturbed and being
used for buidling infrastructures at the time of
the audit.
It is still recommended that alien invasive
species management and eradication be
undertaken. The borrow pit has been made
free draining and will be rehabiliated at the
mine's end of LoM.
C
■ To prevent soil erosion.
■ To ensure that topsoil stockpiles
are managed in such a way that they
can be used for rehabilitation of the
disturbed areas.
Soil amelioration will be undertaken
to enhance the arable capability of
the soils and to sustain the ability of
the soil to retain oxygen and thus
sustain vegetative material during the
storage period.
C
During the site assessment it was observed that
soil has been stockpiled around the incline shaft,
PCD and utilised to construct stormwater berms.
These soil stockpiles are vegetated and are
regular inspected and maintained.
No further action required
Soil has been stockpiled around the incline
shaft, PCD and utilised to construct
stormwater berms. These soil stockpiles are
vegetated and are regular inspected and
maintained.
C
The area undergoing rehabilitation
will be fenced and all animals
prevented from entering the area until
vegetation is sustainable.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Once LoM is reached, all
infrastructure will be removed from site and
rehabilitation will commence in line with the
rehabilitation measures proposed in the approved
EMPr, a rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact.
No further action requiredRehabilitation will be undertaken at the end of
LoM for Mooikraal. NA
During the site assessment it was observed that
soil has been stockpiled around the incline shaft,
PCD and utilised to construct stormwater
management berms. These soil stockpiles are
vegetated and are regular inspected and
maintained. No evidence of erosion was
observed on these soil stockpile areas.
A maintenance road (dirty road) has been
constructed along the conveyer belt for security
reasons and should maintenance activities need
to be undertaken. It was observed that erosion
was found along the road which needed to be
addressed.
It is recommended that good practice housekeeping
is implemented along the conveyer belt to ensure
that coal is cleaned up more regularly and the road
is maintained to address the issues of erosion
which was observed during the site visit.
2 Soils
Topsoil stockpiles will be vegetated
and the vegetation maintained to
prevent erosion throughout the life of
the mine.
C
Topsoil is used for the construction of berms
around the mine site. The berms are well
vegetated and well maintained.
C
Newly seeded/planted areas will be
protected against compaction and
erosion.
C
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Once LoM is reached, all
infrastructure will be removed from site and
rehabilitation will commence in line with the
rehabilitation measures proposed in the approved
EMPr, a rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact. It was
observed that all soil stockpiles as well as the
areas around the mine was vegetated
No further action required
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken.
No newly seeded areas were observed during
the site visit.
NA
Traffic shall be limited where possible
while the vegetation is establishing
itself.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Once LoM is reached, all
infrastructure will be removed from site and
rehabilitation will commence in line with the
rehabilitation measures proposed in the approved
EMPr, a rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact.
No further action required
As the Mooikraal Mine is an underground coal
mine, Limited vehichles move the surface.
However, there are designated roads on the
mine and traffic signs indicating speed limits.
C
A monitoring programme will be
initiated to monitor the rehabilitation
of disturbed areas.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported during the reporting
period that no rehabilitation had been undertaken
(Financial Provision J&W 2018).
It is recommended that once the borrow pits are
rehabilitated this monitoring plan must be
implemented to ensure no erosion or alien invasive
species occurs within the newly rehabilitated area.
A disturbed area that has been partially
rehabiliated by making it free draining and
naturally vegetating is the borrow pit.
The mine is maintained and monitored. Where
the free draining borrow pit begins to fail to
free drain, measures will be put in place to
address the issue until such a time that
rehabilitation of the mine commences.
C
3 Topography
■ To remove all “scars” and
emulate within ±2 m the “pre-mining“
topography so as to, as far as is
practicably possible restore the land
forms and surface drainage paths.
To reconcile the expected and actual
material swells of the overburden
removal and placement and do the
necessary adjustment to the long
term plan in order to meet the overall
objective.
NA
This condition is considered to be not applicable
at this stage. The bulk factor will be taken into
consideration once the boxcut is rehabilitated and
backfilled.
No further action required
During the construction of the mine soils would
have been disturbed for the establishment of
the surface infrastructure as well as the incline
shaft.
The borrow pit was used for the construction
of conveyor belt. Besides this topography
change, no other excavations were observed.
The levellihng of the topography will only take
place when rehabilitation commences at the
mine's end of LoM. Therefore, for now this
action is not applicable.
NA
The main objective of the
reclamation of the surface of the land
to be impacted upon by the
operations of Sigma: Mooikraal
Operation is to restore the area to its
original potential for rain fed arable
production i.e. a COM Class II, land
capability and to establish a natural
grassland to:
The procedure for rehabilitation of
subsided areas is as follows:
4 Rehabilitation
NA No further action required
2 Soils
It was communicated to Digby Wells that to date
no evidence of subsidence has occurred within
the Mooikraal mining right area. However, should
there be such instances of subsidence, the areas
will be rehabilitated to make the area free draining
as far as practicably possible, as per procedure:
Rehabilitation of Damage to the Surface Due to
Underground Mining Operations at Sigma Colliery
(SIG IM (EM) 4.4.6 021). Additionally should
subsidence occur, the area will be rehabilitated,
thereafter the area will be monitored for soil
erosion every month for a year, then biannually
for a year and then annually for three years.
No evidence of subsidence has occurred
within the Mooikraal mining right area.
However, should there be such instances of
subsidence, the areas will be rehabilitated to
make the area free draining as far as
practicably possible, as per procedure:
Rehabilitation of Damage to the Surface Due
to Underground Mining Operations at Sigma
Colliery (SIG IM (EM) 4.4.6 021).
NA
■ Provide a satisfactory cover that
will stabilise the area, reduce the
potential for wind and water erosion
and thus reduce the potential for
contamination of the surrounding
■ The area is to be fenced off in
terms of Regulation 5.2 of the GN992
of 26/06/1970, if necessary,
■ environment,
■ Coarse and fine ash due to there
pozzalenic properties is then worked
into the cracks up to a level of ± 1m
from surface (Harmse, 1991-1993)
and where necessary this is sealed
by means of ±1m of clay,
■ Reduce the visual impact of the
mining area and restore or improve
on the pre-mining appearance of the
area,
■ A topsoil layer of at least 0.5m is
placed over the ash-filling or clay-
layer,
■ Create a more continuous plant
community across the area, and
■ The affected area is fertilised and
revegetated during the first rainfall
period after “repair work” has been
done,
■ Remove undesirable stands of
weedy species (exotics) and replace
them with a more productive and
acceptable grassland community.
■ The fencing will be removed once
the area has been rehabilitated and
the vegetation has established to a
minimum of 15% basal cover
(Chamber of Mines South Africa,
1979), and
■ The subsided areas are
inspected on a regular basis to
determine whether further
subsidence has occurred and if
necessary the process is repeated
until the area has stabilised.
The topsoil and sub-soil horizons are
stripped separately since the
physical, biological and chemical
characteristics of topsoil are
generally more suitable for the
germination, survival and growth of
the vegetation.
C
The topsoil stockpiles are located around the
incline shaft, PCD and utilised for stormwater
berms. No sub-soil is located onsite. These soil
stockpiles are well managed as they are
vegetated, no significant compaction was found
and no erosion was identified.
No further action required
The topsoil stockpiles are located around the
incline shaft, PCD and utilised for stormwater
berms. No sub-soil is located onsite. These
soil stockpiles are well managed as they are
vegetated, no significant compaction was
found and no erosion was identified.
C
Soil stockpiles are avoided as far as
is practicably possible since soil
stripped at the workings is utilised
directly for rehabilitation. Vegetation
cover is mulched into the topsoil
during removal providing additional
organic nutrients to the soil.
C
Soil stockpiles are utilised as bunds and have
been vegetated. Vegetation cover will only be
mulched into the topsoil during removal providing
additional organic nutrients to the soil during
rehabilitation. Therefore this condition is
considered to be not applicable.
No further action required
Soil stockpiles are utilised as bunds and have
been vegetated. Vegetation cover will only be
mulched into the topsoil during removal
providing additional organic nutrients to the
soil during rehabilitation. Therefore this
condition is considered to be not applicable.
C
Vegetation cover is mulched into the
topsoil during removal providing
additional organic nutrients to the
soil.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. No rehabilitation was undertaken
within the reporting year as indicated in J&W
Financial provision Report, 2018. No mulching
was undertaken as no soil removal was
completed.
No further action required
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken. No rehabilitation was
undertaken within the reporting year as
indicated in J&W Financial provision Report,
2018. No mulching was undertaken as no soil
removal was completed
NA
4 Rehabilitation
NA No further action required
Soils removal placement and land preparation:
It was communicated to Digby Wells that to date
no evidence of subsidence has occurred within
the Mooikraal mining right area. However, should
there be such instances of subsidence, the areas
will be rehabilitated to make the area free draining
as far as practicably possible, as per procedure:
Rehabilitation of Damage to the Surface Due to
Underground Mining Operations at Sigma Colliery
(SIG IM (EM) 4.4.6 021). Additionally should
subsidence occur, the area will be rehabilitated,
thereafter the area will be monitored for soil
erosion every month for a year, then biannually
for a year and then annually for three years.
No evidence of subsidence has occurred
within the Mooikraal mining right area.
However, should there be such instances of
subsidence, the areas will be rehabilitated to
make the area free draining as far as
practicably possible, as per procedure:
Rehabilitation of Damage to the Surface Due
to Underground Mining Operations at Sigma
Colliery (SIG IM (EM) 4.4.6 021).
NA
A veld-burning programme will be
followed to remove
moribund/unacceptable grass
material, to contain/prevent
encroachment of undesirable plants.
C
No veld burning programme has been
implemented however, measures have been
undertaken to ensure fire breaks are still
established such as the continued maintains of
the areas and ensuring that the grass is cut to a
height of 50 mm through a maintenance
subcontractor specifically during the summer and
winter seasons within the Mooikraal Colliery.
Communication between farmers and the mine is
also undertaken to ensure firebreaks are
constructed on adjacent farms.
No further action required
No veld burning programme has been
implemented however, measures have been
undertaken to ensure fire breaks are still
established such as the continued maintains
of the areas and ensuring that the grass is cut
to a height of 50 mm through a maintenance
subcontractor specifically during the summer
and winter seasons within the Mooikraal
Colliery. Communication between farmers and
the mine is also undertaken to ensure
firebreaks are constructed on adjacent farms.
Although a formal plan is not in place, the
purpose of a veld-burning programme is being
achieved by the measures put in place with
the fire breaks.
C
In order to limit erosion of soils, prior
to the establishment of vegetation,
erosion control contours are placed
at intervals over the rehabilitated
land. This limits the effect of
uncontrolled run-off and excessive
erosion.
C
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Rehabilitation has been undertaken
at the borrow pit areas. Vegetation has been
established however further rehabilitation is
required to prevent ponding of water. Soil
stockpiles have also been vegetated and will be
utilised once the mine ceases operation.
Although full rehabilitation will not be undertaken
until LoM is reached it is recommended that
rehabilitation of the borrow pits should be
undertaken to prevent ponding of water and the
spread of alien invasive species. The area should
be ploughed to make the surface level. Additionally
alien invasive management measures must be
implemented.
Rehabilitation will be undertaken at the end of
LoM for Mooikraal.
The site is well vegetated, the topsoil is used
as berms around the area and well
maintained.
Rehabilitation has not become applicable yet
as the mine is in the operational phase.
NA
Vegetation establishment:
Grasses - Revegetation (seeding) is
programmed for the season and time
of year, which will yield the optimum
germination and growth (late
spring/early summer). Successful
germination should be achieved
within six weeks.
Maintenance of all planted
revegetated areas - The following
maintenance is required:
■ Newly seeded/planted areas must
be protected against all undue traffic
and/or other disturbances throughout
the establishment period,
■ Plants should be watered and
weeded regularly,
■ A check for pests and diseases
at least once every two weeks and
treatment, (if necessary), for six
months,
■ Replace unhealthy or moribund
specimens,
No further action required
4 Rehabilitation
No further action requiredNA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). It was observed
that vegetation has been established on soil
stockpiles and around the mining infrastructure
area.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Once LoM is
reached, all infrastructure will be removed from
site and rehabilitation will commence in line with
the rehabilitation measures proposed in the
approved EMPr, a rehabilitation management plan
will be compiled once closure is reached which
will include all mitigation measures to prevent
unnecessary environmental impact. All steps
listed must be implemented by the mine should
rehabilitation be undertaken during the operational
phase.
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken. It was reported that to date
only minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Once LoM is
reached, all infrastructure will be removed
from site and rehabilitation will commence in
line with the rehabilitation measures proposed
in the approved EMPr, a rehabilitation
management plan will be compiled once
closure is reached which will include all
mitigation measures to prevent unnecessary
environmental impact. All steps listed must be
implemented by the mine should rehabilitation
be undertaken during the operational phase.
NA
Rehabilitation will be undertaken at the end of
LoM for Mooikraal. NA
■ Fertilize the grassed areas with
150 kg/ha LAN (28), 4-6 weeks after
germination under
■ Favorable growing conditions,
■ Control alien invasive plants, and
■ Continually repair any damage
caused by erosion.
Irrigation - In the establishment of
vegetation during the rehabilitation
procedure irrigation will be necessary
where rainfall is insufficient.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). No vegetation
was planted and therefore no irrigation was
undertaken
No further action required
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken. It was reported that to date
only minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). No
vegetation was planted and therefore no
irrigation was undertaken
NA
The rehabilitated areas must be well
managed when post-mining utilisation
commences to prevent deterioration
of the grazing and degradation of the
environment.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Once LoM is
reached, all infrastructure will be removed from
site and rehabilitation will commence in line with
the rehabilitation measures proposed in the
approved EMPr, a rehabilitation management plan
will be compiled once closure is reached which
will include all mitigation measures to prevent
unnecessary environmental impact.
No further action required
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken. It was reported that to date
only minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). No
vegetation was planted and therefore no
irrigation was undertaken
NA
It is noted that environmental awareness training
is undertaken on a monthly basis through the use
of meetings/ posters/ annual induction/
Environmental monthly topics and events such as
Arbour day tree planting which occurs every
August. Environmental training is undertaken
during the 2nd level SHE meetings. Monthly
environmental awareness poster are placed
around the mine. Annual induction is attended by
all employees and service providers which
includes aspects of environmental awareness.
Additional induction training includes the following:
■ Waste handling (hazardous, general and
recycled)
■ Water conservation
■ Soil contamination with oil spills/ diesel spills
■ Basics of ISO 14001
No further action required
No further action requiredC
4 Rehabilitation
Environmental awareness training
should form part of the annual
induction training.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Once LoM is
reached, all infrastructure will be removed from
site and rehabilitation will commence in line with
the rehabilitation measures proposed in the
approved EMPr, a rehabilitation management plan
will be compiled once closure is reached which
will include all mitigation measures to prevent
unnecessary environmental impact. All steps
listed must be implemented by the mine should
rehabilitation be undertaken during the operational
phase.
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken. It was reported that to date
only minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Once LoM is
reached, all infrastructure will be removed
from site and rehabilitation will commence in
line with the rehabilitation measures proposed
in the approved EMPr, a rehabilitation
management plan will be compiled once
closure is reached which will include all
mitigation measures to prevent unnecessary
environmental impact. All steps listed must be
implemented by the mine should rehabilitation
be undertaken during the operational phase.
NA
It was noted that environmental awareness
training is undertaken on a monthly basis
through the use of meetings/ posters/ annual
induction/ Environmental monthly topics and
events. Awareness presentations were
provided, with topics such as Greenhouse
Gases, Waste Minimisation and Firebreaks.
C
In order to mitigate the impact on the
loss of habitats, and the change in
habitat composition, the following
measures will be implemented:
Any areas that are rehabilitated
during operation, as well as sensitive
areas shall be monitored for alien
species invasion. This will be
performed at least once per season
and more frequently during very wet
seasons. All alien species found will
be removed according to the alien
plant control programme (Appendix
3).
NC
An alien plant/weed eradication programme is not
implemented on an annual basis. The Mooikraal
Colliery is in the process of developing an
operational procedure for the management of
alien invasive species onsite. It was noted that
regular inspections are undertaken by the
Environmental Practitioner at Mooikraal to ensure
the invasive species are removed to prevent the
spread of species. Mooikraal currently spray
herbicides around the conveyer belt and other
problem areas previously identified. During the
site assessment it was observed that invasive
species were present such as Scottish Thistle,
Cockleburs and Pink Tamarisk. It was
communicated that most invasive species have
been established on areas that have been
disturbed and no significant spread of invasive
species have been observed.
It is recommended that the alien plant control
programme attached as Appendix 3 to the EIA
Report is implemented to manage and control the
alien invasive species which are present onsite.
The eradication of invasive species is required by
National Environmental Management Biodiversity
Act (NEMBA) (Act 10 of 2004) – Alien and Invasive
Species (AIS) regulations, 2014 and any plan
drafted in compliance with the legal requirements
must be implemented. Invasive species must be
removed to prevent spreading to other areas
around the site. Mechanical methods should be
used to remove the invasive species specifically at
the time of the year when the plants are not
producing seeds which can result in the spread of
these species to other areas. The disposal of these
species must be removed in a controlled manner to
prevent further spreading. Proof of training specific
to the invasive species identified on site must be
provided either to the appointed contractor or the
person made responsible for the removal of alien
invasive species.
Alien species identification has been
undertaken. The development of an
operational procedure for the management of
alien invasive species onsite is needed to
give effect to the alien plant control
programme already set in place by the mine.
It has been communicated that the plan for
2020 will be to implement an alien eradication
programme on site.
NC
Areas, which have been disturbed by
the mining operations and are no
longer used will to be revegetated
with vegetation indigenous to the
area (refer to paragraph 5.3.4).
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Within the reporting period no
rehabilitation activities had been undertaken
(Financial Provision J&W 2018). Areas that had
been vegetated after construction included the
soil stockpiles, berms and borrow pit areas
No further action required
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on
areas where mining or related activities have
been undertaken.
The borrow pit was used for the construction
of conveyor belt. It has been made free
draining and it is vegetated and full
rehabilitation will take place.
C
Vegetation used for rehabilitation will
be selected for its self-sustaining
properties. If natural re-vegetation
does not occur, the vegetation will be
replaced.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Once LoM is reached, all
infrastructure will be removed from site and
rehabilitation will commence in line with the
rehabilitation measures proposed in the approved
EMPr, a rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact. Additionally a
re-vegetation programme will be implemented to
ensure indigenous vegetation is utilised during
rehabilitation. Additionally alien invasive species
monitoring will be undertaken on the newly
rehabilitated areas so as to prevent the spread of
invasive species.
No further action required
Rehabilitation will only take place at
Mooikraal's end of LoM.
A rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact.
NA
5 Flora
To maintain the status quo after
construction is completed and to
conserve and protect the structure of
the vegetation community and
prevent further loss of species
diversity.
Off-road driving by mine vehicles
through the surrounding veld will be
prohibited.
C
Maintenance vehicles are used on a daily basis
around the mine to inspect the conveyor belt and
visit the Kleinvlei Vent shaft. The vehicles are
required to utilise established road networks
which may include main roads, farm roads and
maintenance roads. It was communicated that
should a vehicle need to access an area away
from the road network caution is taken to ensure
no damage or impact to the environment occurs.
No further action required
Main roads, farm roads and maintenance
roads are used when moving about the site.
Caution is taken when accessing areas that is
far from a road network.
C
C
■ Minimal rehabilitation has been undertaken for
the mine, however where rehabilitation is
undertaken this is done in accordance with the
rehabilitation mitigation measures included in the
EMPr.
■ It was noted that alien invasive species have
been identified on site and therefore measures
need to be implemented to prevent the spread of
these species.
■ No veld burning programme has been
implemented however, measures have been
undertaken to ensure fire breaks are still
established such as the continued maintain of the
areas and ensuring that the grass is cut to a
height of 50 mm through a maintenance
subcontractor specifically during the summer and
winter seasons.
No further action required
No veld burning programme has been
implemented however, measures have been
undertaken to ensure fire breaks are still
established such as the continued maintains
of the areas and ensuring that the grass is cut
to a height of 50 mm through a maintenance
subcontractor specifically during the summer
and winter seasons within the Mooikraal
Colliery. Communication between farmers and
the mine is also undertaken to ensure
firebreaks are constructed on adjacent farms.
Although a formal plan is not in place, the
purpose of a veld-burning programme is being
achieved by the measures put in place with
the fire breaks.
C
It was noted that environmental awareness
training is undertaken on a monthly basis through
the use of meetings/ posters/ annual induction/
Environmental monthly topics and events such as
Arbour day tree occur on a yearly basis. The
most recent training was undertaken via posters
which aimed to encourage better water
management.
Limited trees are located within the mining area
however it is noted that the collection of firewood
is prohibited and this is communicated through
induction training. Additionally it is noted that the
wood waste that is taken to Sasol’s reclamation
yard. The wood waste is then sold to Arc
Charcoal, who utilise the wood as fuel for the
making of charcoal
No further action required
It was noted that environmental awareness
training is undertaken on a monthly basis
through the use of meetings/ posters/ annual
induction/ Environmental monthly topics and
events such as Arbour day tree occur on a
yearly basis. Awareness presentations were
provided, with topics such as Greenhouse
Gases, Waste Minimisation and Firebreaks.
C
Any form of hunting, poaching,
snaring or trapping will be prohibited
within the mining area.
Birds
In order to further improve bird
habitat the following measures will be
taken:
■ The active planting of the tree
screens and the revegetation of the
badly disturbed areas will definitely
improve the bird habitats.
Mammals
In order to minimise the impacts on
mammals the following actions will be
taken:
■ Relocate specimens.
Reptiles and amphibians
In order to minimise the impacts on
reptiles and amphibians the following
actions will be undertaken:
■ Relocate specimens which may
be trapped in trenches, adits and
other mine related structures, and
No further action required
No form of hunting is permitted at the Mooikraal
Colliery or Sigma 3 Shaft. This is communicated
through the induction that must be undertaken by
each individual working onsite. Security guards
regularly patrol the mine to ensure no
unauthorised entry to the mine and ensure no
hunting is taking place. It was noted that should
an animal be identified onsite the individual is
required to alert the Environmental Practitioner.
Depending of the species that is identified efforts
will be undertaken to relocate the species away
from the mine. It is noted that no killing of any
animal is permitted.
5 Flora
To maintain the status quo after
construction is completed and to
conserve and protect the structure of
the vegetation community and
prevent further loss of species
diversity.
In order to limit habitat disturbance
and fragmentation, the following
programmes shall be established
■ A rehabilitation programme for
the areas disturbed during the
construction phase
■ Alien plant control programme
(Appendix 3)
■ A fire management programme
■ Education/awareness
programme for all staff regarding the
management and protection of
biodiversity
■ Collection of firewood will be
prohibited.
6
Fauna
To minimise the impact of the mine
on animal life and re-establish and
enhance animal populations that
existed pre-mining.
C
No form of hunting is permitted at the
Mooikraal Colliery or Sigma 3 Shaft. This is
communicated through the induction that must
be undertaken by each individual working
onsite. Security guards regularly patrol the
mine to ensure no unauthorised entry to the
mine and ensure no hunting is taking place. It
was noted that should an animal be identified
onsite the individual is required to alert the
Environmental Practitioner. Depending of the
species that is identified efforts will be
undertaken to relocate the species away from
the mine. It is noted that no killing of any
animal is permitted.
C
■ Where practical, slope the walls
of permanent trenches to enable
trapped animals to escape.
■ Killing of snakes prohibited - they
will be relocated
The objectives of surface water
management will be:
■ To manage the operation in such
a way as to prevent surface water
contamination that will impact on the
aquatic environment,
■ To operate within the law as
stated in the MPRDA, 2002 (Act 28
of 2002) and the National Water Act,
1998 (Act 36 of 1998) and to ensure
that all the applicable requirements of
the National Water Act, are complied
with, in particular Government Notice
704,
■ To affect catchment yield as little
as is practically possible,
■ To keep 1:50 and regional
maximum floods out of the mine,
Surface water monitoring is undertaken to
determine whether the water qualities are in
accordance with the IWUL and Resource Quality
Objectives. The report indicates that samples are
taken on a quarterly basis and reported on
biannually. The most recent biannual water
monitoring report for Mooikraal is dated February
2018 (Ref No. 2018/04/PJHL) and compiled by
IGS. The report indicated that variations in water
quality of Kromelmboogspruit North and South
have been detected and can be attributed to the
uncontrolled mine water discharge into the
Kromelmboogspruit which has been prevalent
since 2010. However the report indicated that
over the monitoring period the surface water
qualities were within the IWUL limits.
It was observed that dirty water runoff generated
at Sigma 3 Shaft from the coal stockpile area
enters the Leeuspruit. The monthly water quality
results indicated an increase of sulphate levels
over the past eighteen months. It is however
noted that the deteriorating water quality is not
only from 3 Shaft and has other contributing
factors. The most recent biannual water
monitoring report for Sigma (which includes 3
Shaft) is dated January 2018 (Ref No.
2018/03/PJHL) and compiled by IGS.
The upgrade of stormwater management
mechanisms at Sigma Colliery: 3 Shaft will
only be effected once the Regulation 31
Amendment and WUL is granted.
Water monitoring, both surface water and
groundwater, is undertaken on a quarterly
basis. The October 2019 report indicated that
calcium-bicarbonate signature for the
upstream monitoring point and sodium-
bicarbonate signature for the downstream
monitoring point of Kromelmboogspruit North
and South whcih can be attributed to the
release of mine water discharge into the
Kromelmboogspruit t since 2010.
Based on the STP results from May to
November 2019 shows that from July, the
Nitrate dropped from 16.20 in June to 1.10 in
July. This can be attributed to the fresh
innoculent that the clinet injected into the STP.
E Coli is at a 0.00 readingfrom May to
November and was thus dealt with as per the
instructions of the 2018 recommendations.
C
■ To restrict the impacts of
polluted water to the mining area
■ To operate within the standards
and operational procedures,
■ To as far as is practicably
possible have a free draining
topography over rehabilitated areas,
The STP is authorized under the Water Use
Licence (WUL) (Licence No
08/C22K/CIGJFAE/6981) approved on 16
January 2018. The sewage is treated to an
acceptable standard in accordance with the WUL
and discharged to the Kromelmboogspruit. The
water qualities reported on from the STP are
however not complying with the water quality
standards in the IWUL. High levels of Nitrates and
E-coli were detected in the monitoring data (STP
Water Quality, 2018). It was however observed
during the site assessment that maintenance of
the STP was being undertaken in an attempt to
clean out the system and ensure the STP
operates optimally.
The STP is authorized under the Water Use
Licence (WUL) (Licence No
08/C22K/CIGJFAE/6981) approved on 16
January 2018. The sewage is treated to an
acceptable standard in accordance with the
WUL and discharged to the
Kromelmboogspruit.
Fresh innoculent was injected into the STP
and the Nitrates and E.Coli have stabilised to
licenced levels. Based on the STP results
from May to November 2019 shows that from
July, the Nitrate dropped from 16.20 in June to
1.10 in July. This can be attributed to the fresh
innoculent that the clinet injected into the STP.
E Coli is at a 0.00 readingfrom May to
November and was thus dealt with as per the
instructions of the 2018 recommendations.
C
No further action required
No form of hunting is permitted at the Mooikraal
Colliery or Sigma 3 Shaft. This is communicated
through the induction that must be undertaken by
each individual working onsite. Security guards
regularly patrol the mine to ensure no
unauthorised entry to the mine and ensure no
hunting is taking place. It was noted that should
an animal be identified onsite the individual is
required to alert the Environmental Practitioner.
Depending of the species that is identified efforts
will be undertaken to relocate the species away
from the mine. It is noted that no killing of any
animal is permitted.
It is noted that once the pipeline between Mooikraal
at 3 Shaft has been constructed water will no longer
be accidently discharged to the environment this will
assist in reducing the elevated surface water quality
levels within the Kromelmboogspruit.
It is noted that monitoring of surface water is not
being undertaken monthly as required in terms of
the EMPr and IWUL, except when the PCDs at
Mooikraal Colliery overflows, which occurs
occasionally which is then undertaken on a weekly
basis. Surface water quality samples should be
undertaken in accordance with the monitoring
methodology approved in the EMPr and IWUL.
It is recommended that an investigation be
undertaken to determine the reason for the high
concentrations of NO3 and E Coli in the treated
effluent that is discharged from the STP. Measures
must be implemented to ensure that these non-
compliances are addressed and aim to comply with
the specified qualities of the IWUL.
Mooikraal has proposed that an upgrade to the
stormwater management at Sigma 3 Shaft is
required to ensure all dirty water is contained within
the operation and not discharged to the Leeuspruit.
The proposed upgrade involves the separation of
clean and dirty water. The containment of dirty
water and sending it to the SO. The existing crusher
area will also be relocated and rehabilitated. A
basic assessment and 31 amendment process is
currently being undertaken to assess the impacts
associated with the proposed project and obtain the
required authorisation. Mitigation measures
proposed as part of this process must be
implemented to make this condition compliant.
Should authorisation be received, rehabilitation of
the built up of coal will be removed from the area
the coal which has been built up beneath the
culvert. Investigation needs been be undertaken
should a IWUL be required to undertake the
rehabilitation beneath the culvert.
Surface water
(Aquatic
Systems)
Surface water will be monitored
monthly to check for deterioration of
water quality and to identify potential
seepage pathways.
NC
6
Fauna
To minimise the impact of the mine
on animal life and re-establish and
enhance animal populations that
existed pre-mining.
C
No form of hunting is permitted at the
Mooikraal Colliery or Sigma 3 Shaft. This is
communicated through the induction that must
be undertaken by each individual working
onsite. Security guards regularly patrol the
mine to ensure no unauthorised entry to the
mine and ensure no hunting is taking place. It
was noted that should an animal be identified
onsite the individual is required to alert the
Environmental Practitioner. Depending of the
species that is identified efforts will be
undertaken to relocate the species away from
the mine. It is noted that no killing of any
animal is permitted.
C
The necessary control measures will
be maintained to ensure containment
of spillages at the plant and shaft
areas, e.g. pollution control dams, the
clearing of channels, etc.
NC
During the site assessment it was observed that
water was overflowing uncontrolled from the PCD
into the Kromelmboogspruit. It was observed that
the water was overflowing beneath the spill way
which may indicate issues relating to structural
integrity of the dam wall of the PCD. The
overflow of water from the PCDs to the
environment is not authorised in terms of the
NWA and under the IWUL. Measures have been
put in place to manage the excess water. This
includes the construction of a 7 ML and 10 ML
pipeline which will direct the water from the PCDs
to the Sasolburg Operations and prevent the
unauthorised discharge. The construction of the
pipeline received environmental authorisation in
2015 with the IWUL being authorised in January
2018. The pipeline has been constructed except
in the areas where the pipeline will cross
watercourses. It is proposed that the pipeline will
be fully constructed by the end of 2018. It was
observed that the PCD at 3 Shaft was also quiet
full and above the 0.8 m recommended levela
Once the 7ML and 10ML pipeline is constructed
water will be transferred between Mooikraal PCDs
to SO PCDs which will prevent further discharge of
dirty water to the environment at Mooikraal. A Dam
Safety Inspection by a professional Registered
Engineer on the PCDs at Mooikraal must be
undertaken to ensure the PCDs are able to contain
the required amount of water without the potential of
dam failure. Additionally the incident is required to
be reported to water affairs if the reason for the
overflow was due to the integrity of the PCDs.
During the site assessment it was observed that the
PCD at 3 Shaft was at full capacity and above the
0.8 m recommended freeboard level. The water
level within the PCD at 3 Shaft must be reduced to
be within the recommended level.
The PCDs were not overflowing. Water is
being transported via the constructed
pipelines to other Sasol Operations.
C
Prevent areas of high infiltration from
developing on mined areas and
ensure free drainage
C
It was communicated to Digby Wells that to date
no evidence of subsidence has occurred within
the Mooikraal mining right area. However, should
there be such instances of subsidence, the areas
will be rehabilitated in order to make the area free
draining as far as practicably possible, as per
procedure: Procedure for Rehabilitation of
Damage to the Surface Due to Underground
Mining Operations at Sigma Colliery (SIG IM (EM)
4.4.6 021). Additionally should subsidence occur
the area will be rehabilitated and will be made free
draining.
No further action required
There was no evidence of subsidence having
occurred within the Mooikraal mining right
area. However, should there be such
instances of subsidence, the areas will be
rehabilitated in order to make the area free
draining as far as practicably possible, as per
procedure: Procedure for Rehabilitation of
Damage to the Surface Due to Underground
Mining Operations at Sigma Colliery (SIG IM
(EM) 4.4.6 021). Additionally should
subsidence occur the area will be rehabilitated
and will be made free draining.
NA
Limit containment of uncontaminated
stormwater limit interference with
natural surface water drainage
system
NC
An IWWMP has been completed (Digby Wells,
2015 (Ref No. SAS1388) which aims to identify
potential ground and surface water contamination
and implement management measures to ensure
dirty water is contained within the operation and
clean water is permitted to be discharged. It is
noted that the IWWMP is proposed to be updated
in 2018. During the site visit two incidents where
dirty water was being discharged to the natural
surface water drainage systems was observed.
At Mooikraal Colliery it was found that the water
generated around the Silo and Conveyer belt area
is not contained to the dirty water system and the
water is currently discharging to the clean water
environment. This water may contain coal and
therefore is considered to be dirty water.
Additionally stormwater from the processing plant
at 3 Shaft will enter the Leeuspruit directly during
rainstorm events which eventually ends up in the
Vaal River.
Effective stormwater management measures must
be implemented at both Mooikraal (soil / conveyer
belt area) as well as at 3 Shaft. Dirty water
generated from the mine should be contained as it
can result in the contamination of soil and surface
water. It is however noted that stormwater
management measures are proposed to be
implemented at 3 Shaft as part of the conveyor
relocation project which will be authorised as part of
the BAR / 31 Amendment process.
A Standard Operating Procedure (SOP) for
stormwater management and the maintenance
of Sigma Colliery: 3 Shaft has been put
together and due for review in 2021. It is
however noted that stormwater management
measures are proposed to be implemented at
3 Shaft as part of the conveyor relocation
project which will be authorised as part of the
Regulation 31 Amendment process.
Therefore, this commitment remains a non-
compliance as the measures necessary for a
compliance are still to be authorised by the
competent authority.
NC
Surface water
(Aquatic
Systems)
6
Surface water
(Hydrology)
To ensure that the impact from the
mining infrastructure will not increase
from that of the construction phase.
Stormwater control measures will be
maintained around the shaft and plant
area (at 3 Shaft) to ensure the
maximum return of clean water to the
natural drainage systems.
NC
Clean water canals are in place around the
Mooikraal Shaft which ensures that all clean
water from the adjacent farm lands will be diverted
away and around the shaft.
During the site visit two incidents where dirty
water was not contained to the dirty water system
and being discharged to the clean environment.
At Mooikraal Colliery it was found that the water
generated around the Silo and Conveyer belt area
was ponding and not contained to a dirty water
system. This water contains fine coal and
therefore is considered to be dirty water.
Additionally stormwater from the processing plant
at 3 Shaft is not contained to the immediate area
but left to enter into the Leeuspruit which
eventually ends up in the Vaal River.
Effective stormwater management measures needs
to be implemented at both Mooikraal (soil /
conveyer belt area) as well as at 3 Shaft. Dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination. It is however noted that stormwater
management measures are proposed to be
implemented at 3 Shaft as part of the 31
Amendment process.
A Standard Operating Procedure (SOP) for
stormwater management and the maintenance
of Sigma Colliery: 3 Shaft has been put
together and due for review in 2021. It is
however noted that stormwater management
measures are proposed to be implemented at
3 Shaft as part of the conveyor relocation
project which will be authorised as part of the
Regulation 31 Amendment process.
Therefore, this commitment remains a non-
compliance as the measures necessary for a
compliance are still to be authorised by the
competent authority.
NC
■ To prevent the deterioration of
the surface water quality during the
operational phase as a result of
sedimentation, seepage from the
stockpiles, overburden dump and
spillages.
Soil erosion measures will be
maintained at the topsoil stockpiles,
overburden dumps and shaft area,
including the vegetation of these
deposits and construction of
paddocks where applicable.
C
During the site assessment it was observed that
soil has been stockpiled around the incline shaft,
PCD and utilised to construct stormwater berms.
These soil stockpiles are vegetated and are
regularly inspected and maintained. No evidence
of erosion was observed on these soil stockpile
areas.
Erosion was noticed at the borrow pit next to the
Waste Rock Dump. This area has not been
rehabilitated. This area will only be rehabilitated
hen equipment will be available to make the area
free draining and remove the larger waste rock
boulders.
No further action required
Th overburden stockpile will be used for
rehabilitation purposes when Mooikraal
reaches its end LoM. It is located in a clean
water area and has a berm constructed
around it. The vegetation of the overburden
stockpile was not successful, and erosion can
be observed, and this is due to the gradient of
the slope being too steep (Digby Wells
Environmental Mooikraal Audit, 2018).
No other stockpiles were observed on site.
C
7
Surface water
(Water Quality)
■ To maintain all the water pollution
control measures so that they will be
able to handle a 1:50 year flood
event.
Contaminated runoff water from the
dirty areas (shaft and plant at 3
Shaft) will be contained in water
pollution control dams (North and
South dams) that will be able to retain
a 1:50 year flood event. From these
dams it will be recycled back into the
process for reuse in the mine or
pumped to SII.
NC
As per the NWA, dirty water is not permitted to be
discharged to the environment without an IWUL
and the water quality is acceptable for discharge.
It is noted that an IWWMP has been compiled for
Mooikraal and is in the process of being updated.
Water at the Mooikraal Colliery specifically
around the shaft is contained in the North and
South PCDs and transferred to the SO.
During the site assessment it was observed that
dirty water at the Silo and Conveyer belt area at
Mooikraal is not contained to a dirty water system
but left to pond in the immediate area. This may
result in groundwater contamination or potential
discharge to the clean water environment. No
dirty water system is currently in place to contain
the water.
At 3 Shaft it was observed that the dirty water
was not contained to the immediate area but left
to flow directly into the Leeuspruit. It should also
be noted that water from 3 Shaft can not be
pumped back to North and South PCD and
therefore this condition for 3 Shaft is considered
to be impractical.
It is recommended that regular housekeeping is
undertaken at the Silo and conveyer belt area at
Mooikraal Colliery to ensure the area is kept clear
of coal. Ponding of water should also not be
permitted as it can result in contamination of the
groundwater and should it leave the area it can
result in the contamination of surface water.
Effective stormwater management measures must
to be implemented at both Mooikraal (soil /
conveyer belt area) as well as at 3 Shaft. Dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination of the receiving water environment. It
is however noted that the stormwater management
measures will be upgraded at 3 Shaft as part of the
BAR /31 Amendment process.
The situation has not changed since the
previous audit in 2018. Effective stormwater
management measures for Mooikraal will be
put into effect upon the authorsation of the
Regulation 31 Amendment.
The mine should in the meantime implement
best practice measures to ensure that dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination of the receiving water
environment.
NC
It is recommended that regular housekeeping must
be undertaken at the Silo and conveyer belt area to
ensure the area is kept clear of coal and silt.
Ponding of water should also not be permitted as it
can result in environmental contamination.
Effective stormwater management measures needs
to be implemented at both Mooikraal (soil /
conveyer belt area) as well as at 3 Shaft. Dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination. It is however noted that stormwater
management measures are proposed to be
implemented at 3 Shaft as part of the BAR/ 31
Amendment process.
Further maintenance and good housekeeping
practices must be implemented at the sump located
at the fuel and hydraulic oil storage area to ensure
the sump operates at optimal capacity.
7
Surface water
(Water Quality)
NC
Measures implemented to separate
clean and dirty stormwater at the
shaft (Figure 8) and plant (at 3 Shaft)
(Figure 9) will be maintained and
upgraded where necessary to
prevent spillages to the natural
environment .
Water at the Mooikraal Colliery specifically
around the shaft is contained in the North and
South PCDs and transferred to the SO.
During the site assessment it was observed that
dirty water at the Silo and Conveyer belt area at
Mooikraal is not contained to a dirty water system
but left to pond in the immediate area. This may
result in groundwater contamination or potential
discharge to the clean water environment. No
dirty water system is currently in place to contain
the water.
At 3 Shaft it was observed that the dirty water
was not contained to the immediate area but left
to flow directly into the Leeuspruit.
It was observed that regular maintenance of the
clean and dirty water canals is undertaken. The
sumps are inspected visually weekly by surface
services for volume. Stormwater management
infrastructure are inspected in summer months on
a monthly basis and in winter months every 2
months.
A sump and oil trap has been constructed to
collect all the water being discharged from the fuel
and oil storage area. However currently there is
not oil skimmer and water is being pumped out
manually.
The situation has not changed since the
previous audit in 2018. Effective stormwater
management measures for Mooikraal will be
put into effect upon the authorsation of the
Regulation 31 Amendment.
The mine should in the meantime implement
best practice measures to ensure that dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination of the receiving water
environment.
Therefore, this commitment remains a non-
compliance as the measures necessary for a
compliance are still to be authorised by the
competent authority.
NC
The mine will implement measures to
minimise its dirty water make that
need to be handled in the water
balance e.g. dirty areas at the plant
will be kept to the minimum.
NC
Mooikraal regularly monitors their water flow
which is recorded on a flow spreadsheet and
submitted to DWS. The water is currently pumped
from underground, to the PCDs and then to SO.
It is however noted that at present Mooikraal
Colliery is generated excess water which cannot
be contained within the North and South PCD
which is resulting in overflows. A 10 ML and 7 ML
are proposed to be constructed to transfer the
water to SO for further use. It is also noted that
the Water Balance contained in the IWWMP,
2015 does not include the flow of water at 3
Shaft. The IWWMP for Mooikraal was compiled
in 2015 and is proposed to be updated in 2018 to
ensure relevance to the current operation at
Mooikraal and 3 Shaft. It was observed that water
is currently discharging from 3 Shaft into the
Leeuspruit and that stormwater mitigation
measures currently located in the area is not
considered to be effective. It is considered that
the dirty water areas are not being kept to a
minimum.
Once the 7ML and 10ML pipeline is constructed
water will be transferred between Mooikraal PCDs
to SO which will prevent further discharge of dirty
water to the environment at Mooikraal.
The IWWMP is required to be updated on an annual
basis and submitted to the DWS. However, the
IWWMP has not been updated since 2015. Digby
Wells have been appointed to update the IWWMP.
During this update process it is recommended that
the Water Balance should also be updated to reflect
accurate water quantities as well as include 3 shaft
water usages which have been omitted in the 2015
IWWMP
Effective stormwater management measures needs
to be implemented at 3 Shaft. Dirty water generated
from the mine should not be permitted to be
discharged as it can result in contamination. It is
however noted that stormwater management
measures are proposed to be implemented at 3
Shaft as part of the 31 Amendment process
The situation has not changed since the
previous audit in 2018. Effective stormwater
management measures for Mooikraal will be
put into effect upon the authorsation of the
Regulation 31 Amendment.
The mine should in the meantime implement
best practice measures to ensure that dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination of the receiving water
environment.
Therefore, this commitment remains a non-
compliance as the measures necessary for a
compliance are still to be authorised by the
competent authority.
NC
Contaminated water will be pumped
to the dirty water system for reuse in
the plant and service water
underground.
NC
Mooikraal Colliery
Groundwater flows into the underground workings
at Mooikraal Colliery. These workings must be
kept dry for health and safety as well as
continued production reasons. The water is then
pumped to the various underground dams and
then to the PCDs. The water contained in the
PCDs is then pumped away to the SO through a
5ML pipeline.
3 Shaft
Water at 3 Shaft is received from Mooikraal and
utilised for dust suppression. It is however noted
that there is currently no water containment at 3
Shaft which is resulting in contamination of soil
and surface runoff to the Leeuspruit.
Once the 7ML and 10ML pipeline is constructed
water will be transferred between Mooikraal PCDs
to SO which will prevent further discharge of dirty
water to the environment at Mooikraal.
Effective stormwater management measures needs
to be implemented at 3 Shaft. Dirty water generated
from the mine should not be permitted to be
discharged as it can result in contamination. It is
however noted that stormwater management
measures are proposed to be implemented at 3
Shaft as part of the 31 Amendment process
The water pipelines from Mooikraal to 3Shaft
and other Sasol operations is operational. The
PCDs are not overflowing into the river
system.
The stormwater management measures
proposed and the upgrades needed at 3Shaft
need the Regulation 31 Amendment to be
approved and issued so as to authorise those
changes to be able to deal effectively with the
irty water management at 3Shaft.
Therefore, the fulfilment of this condition lies in
the Regulation 31 Amendment being granted
to authorise the stormwater measures being
proposed to handle the dirty water
management.
NC
Machinery to be brought up from
underground for repairs or
maintenance will first be washed in a
demarcated area underground. This
equipment will then be cleaned,
serviced and repaired in a dedicated
workshop with the necessary
pollution control measures in place
such as dedicated wash bays with oil
separators and a facility to contain
the recycled oil.
C
Machinery is continuously being repaired as part
of preventative maintenance. It was noted that
machinery is washed in a demarcated washbay
prior to it being transferred to the workshop area
for maintenance. The workshop underground and
washbay underground has not been established
yet. A sump is being constructed around the
workshop to capture any oil and dirty water that
may be generated at the washbay and parking
area. This water is then pumped to the PCDs. It
is noted that this area around the workshop is
concreted. A sump is located near the wash bay
which captures the water. A skimmer is also
located at the sump to skim the hydrocarbon oil
off the water. The hydrocarbon is stored in used
oil tanks located on a concrete area. This oil is
then removed by EWOR for recycling.
No further action required
Machinery is continuously being repaired as
part of preventative maintenance. It was noted
that machinery is washed in a demarcated
washbay prior to it being transferred to the
workshop area for maintenance.
However, it is recommended that redundant
underground cars need to be removed.
C
7
Surface water
(Water Quality)
Clean stormwater and run-off will be
diverted around the shaft, overburden
stockpile, plant and waste storage
areas. Contaminated water will be
contained and put back into the
process water system, for reuse.
NC
It was noted that clean stormwater channels
have been constructed around Mooikraal Colliery
to divert clean water .around the shaft. Berms are
constructed around the WRD to contain any
runoff containing silt and prevent the
contamination of the surface water.
No clean and dirty stormwater management
measures are in place at the Sigma 3 Shaft area.
Effective stormwater management measures needs
to be implemented at both Mooikraal (soil /
conveyer belt area) as well as at 3 Shaft. Dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination. It is however noted that stormwater
management measures are proposed to be
implemented at 3 Shaft as part of the 31
Amendment process.
The situation has not changed since the
previous audit in 2018. Effective stormwater
management measures for Mooikraal will be
put into effect upon the authorsation of the
Regulation 31 Amendment.
The mine should in the meantime implement
best practice measures to ensure that dirty
water generated from the mine should not be
permitted to be discharged as it can result in
contamination of the receiving water
environment.
Therefore, this commitment remains a non-
compliance as the measures necessary for a
compliance are still to be authorised by the
competent authority.
NC
A spill response plan will be
implemented and employees trained
accordingly to react efficiently to
address any spillage. Large spillages
of hazardous substances such as oil
will initially be controlled by on-site
emergency response personnel, who
will be aided by professional
contractors.
C
Any oil spills that occur on site are contained and
dealt with on a weekly basis in accordance with
the Procedure for the Handling of Oil Spills and Oil
Recycling (Ref No. SIG (EM) IMS SOP/ 008). It
was noted that all oil spillage that occur are
recorded in an incident register (Ref No. Ref No.
SIGIMS/NCREG/1) which is retained at the mine.
Training is provided on effective management and
measures to be implemented in the event of a
spillage. To date no large spillages have occurred
however an Emergency Preparedness and
Response Procedure (Ref No. SIG IMS 447000)
is available should such a spillage occur. It was
noted that miner spillages are immediately
cleaned up when required. No spillages were
noted on the incident register. Training is provided
on environmental aspects during induction.
No further action required
Any oil spills that occur on site are contained
and dealt with on a weekly basis in
accordance with the Procedure for the
Handling of Oil Spills and Oil Recycling (Ref
No. SIG (EM) IMS SOP/ 008). It was noted
that all oil spillage that occur are recorded in
an incident register (Ref No. Ref No.
SIGIMS/NCREG/1) which is retained at the
mine.
A memorandum in April and May 2019 was
written to address spills on site. An incident
register was also made available that notes
incidents, actions taken and whether
investigations were needed.
C
7
Surface water
(Water Quality)
Hazardous waste will be disposed by
an approved waste contractor to
ensure the safe disposal of the
waste. The associated safe disposal
certificates will be kept in a secure
C
During the site assessment it was observed that
waste generated at Mooikraal and 3 Shaft is
stored in the ISO yards which has designated
waste storage areas, one at Mooikraal and one
at 3 Shaft, which is separated into various waste
streams namely wood waste, scrap metal and
hazardous waste. The hazardous waste is stored
in waste skips and signage indicating the waste
stream is placed above the waste skip. Mooikraal
considers general waste to be hazardous as
general waste is obtained from the underground
workings and anticipated to be contaminated with
hydrocarbons. It was communicated that
hazardous waste is removed by EnviroServ and
disposed at Holfontein. Safe disposal certificates
are provided for the safe disposal of this waste.
During the audit a safe disposal certificate for the
disposal of hazardous waste was provided (Ref
No.GP-SP240100). Good housekeeping
measures are in place. All waste is stored and
handled in accordance with the National
Environmental Management: Waste Act, 2008
(Act 59 of 200rage area. However currently there
is not oil skimmer and water is being pumped out
manually. harged to the Leeuspruit. The proposed
upgrade involves the separation of clean
No further action required
Mooikraal considers general waste to be
hazardous as all general waste is obtained
from the underground workings and anticipated
to be contaminated with hydrocarbons. It was
communicated that hazardous waste is
removed by EnviroServ and disposed at
Holfontein.
Safe disposal certificates, purchase orders
and invoices were provided.
C
General waste will be separated in
dedicated areas to facilitate the
separation of waste from where it will
be collected for disposal to a
permitted landfill site or recycling.
C
During the site assessment it was observed that
waste generated at Mooikraal and 3 Shaft is
stored at the ISO Yard in designated waste
storage areas, one at Mooikraal and one at 3
Shaft, which is separated into various waste
streams namely wood waste, scrap metal and
hazardous waste. The hazardous waste is stored
in waste skips and signage indicating the waste
stream is placed above the waste skip. Mooikraal
considers general waste to be hazardous as all
general waste is obtain from the underground
workings and anticipated to be contaminated with
hydrocarbons and is therefore handled
accordingly. The EAP at Mooikraal ensures that
all waste generated and recycled at the mine is
recorded on a spreadsheet. The spread sheet
was provided to the auditors which showed all
waste generated and recycled between 2016 and
2018. This information is also recorded and
reported on a quarterly basis in the Sasol
Sustainability Report
No further action required
Mooikraal considers general waste to be
hazardous as all general waste is obtained
from the underground workings and anticipated
to be contaminated with hydrocarbons. It was
communicated that hazardous waste is
removed by EnviroServ and disposed at
Holfontein.
Safe disposal certificates, purchase orders
and invoices were provided.
C
Waste will be separated into the
following categories which allow
recycling: glass, steel, paper,
batteries and woodchips as per
waste procedure (SIGIMS 446002).
C
During the site assessment it was observed that
waste generated at Mooikraal and 3 Shaft is
stored at the ISO yard in designated waste
storage areas, one at Mooikraal and one at 3
Shaft, which is separated into various waste
streams namely wood waste, scrap metal and
hazardous waste. The wood waste and scrap
metal is removed from site and taken to Sasol’s
reclamation yard. The wood waste is then sold to
Archorcol who burn the wood to make charcoal
while the steel is sold or auctioned off. Oil waste
is removed off site by EWOR where it is recycled
and reused. The drums that are used to store the
oil is sold to Senno Drums for recycling.
No further action required
Waste is sorted and separated into various
waste streams namely wood waste, scrap
metal and hazardous waste.
There were no designated areas for glass,
paper and batteries. However, best practice
measures have been put into place regarding
waste separation. Therefore, the intent of
commitment is acheived.
C
7
Surface water
(Water Quality)
The waste areas will contain the
necessary water pollution control
features e.g. bunded, impermeable
surfaces and sump, and separate
demarcated areas for the different
wastes.
C
The waste is stored in the ISO yard in a
designated waste storage areas. These areas
have a concrete surface and dividers have been
established between each waste stream to
ensure separation of waste. At Mooikraal all
waste is disposed in skips depending on the
waste stream. The waste storage area is sloped
to allow water to drain towards a sump area
which collects the water from both the waste
storage area and wash bay. An oil skimmer is
also used to recover the oil from the sump prior to
the water being discharged to the PCDs. It was
observed that the water management around the
waste area is considered to be effective. Clean
runoff water is diverted around the waste storage
area and dirty runoff water will be contained in the
sump.
No further action required
The waste storage area is bunded and
concreted. Each waste stream is separated
by concrete wall on either side.
C
All bulk storage of substances such
as fuel and oil must be bunded to
contain 110% of the substance
stored. These facilities must include
a sump, an oil trap and an
impermeable floor and walls.
C
Mooikraal Colliery
All fuel and oil is stored in tanks in a designated
fuel and oil storage area. The tanks are bunded to
ensure that should a failure occur it will be able to
contain 150 % of the fuel and oil stored. The
tanks and area where the vehicles are refueled
are located on a concrete floor and within
impermeable walls. Additionally the tanks are
located within a lockable and access control area
with established fencing around it. A sump and oil
trap has been constructed to collect all the water
being discharged from the fuel and oil storage
area. However currently there is not oil skimmer
and water is being pumped out manually.
3 Shaft
A diesel storage facility is located at 3 Shaft
however it is currently not in used as it is will be
decommissioned in the near future
Further maintenance and good housekeeping
practices must be implemented at the sump located
at the fuel and hydraulic oil storage area to ensure
the sump operates at optimal capacity.
It is recommended that as the diesel storage facility
is not required it should be decommissioned to
concrete level. The oil that may be stored inside the
tank should be drained and the oil contained within
the bunded removed and disposed of as hazardous
waste.
Fuel and hydraulic oil are stored on site in bulk
storage tanks. These tanks are stored within a
bunded area and on a concrete standing. The
oil storage area contains a total of 73 000
litres and has a bund wall capacity to store
150% of the total capacity of the bundwall
which amounts to 113 500 litres.
C
All hazardous substances (such as
paint, flammable substances) will be
stored in a lockable cupboard at all
times.
C
Mooikraal Colliery
All fuel and oil is stored in tanks in a designated
fuel and oil storage area. The tanks are bunded to
ensure that should a failure occur it will be able to
contain 150 % of the fuel and oil stored. The
tanks and area where the vehicles are refueled
are located on a concrete floor and within
impermeable walls. Additionally the tanks are
located within a lockable and access control area
with established fencing around it. A sump and oil
trap has been constructed to collect all the water
being discharged from the fuel and oil storage
area. However currently there is not oil skimmer
and water is being pumped out manually.
3 Shaft
A diesel storage facility is located at 3 Shaft
however it is currently not in used as it is required
to be decommissioned.
Further maintenance and good housekeeping
practices must be implemented at the sump located
at the fuel and hydraulic oil storage area to ensure
the sump operates at optimal capacity.
It is recommended that as the diesel storage facility
at 3 Shaft is not required it should be
decommissioned with the tank and bund removed.
The oil that may be stored inside the tank and
bunded area should be removed and recycled by
an approved service provider. All the contaminated
concrete or material must be removed as hazardous
waste and appropriately disposed of.
There are lockable storage areas for
hazardous flammable substances such as
Acetylene, Oxygen and LPG Gas.
C
7
Surface water
(Water Quality)
A register with all the Material Safety
Data Sheets (MSDs) of all the
hazardous substances will be
maintained on the mine at the point of
use.
C
MSDs are retained onsite for all hazardous
substances used on the mine. An example of a
Safety Date Sheet was provided for Sasol Diesel
500 which provides measures to be implemented
in the event of an incident. It was also noted that
a chemical registry has been compiled for the
mine with all the MSDS linked to each chemical
No further action required
Material Safety Data Sheets (MSDS) were
provided for the Oxygen, Acetylene and LPG
Gas.
C
No activities will be allowed within
100m of watercourses.C
Mooikraal received a GN 704 4 (b) exemption
which permits Mooikraal to undermine the
Kromelmboogspruit and feeder streams using
bord and pillar methods. It is required that a
safety factor of 2 is maintained as well as a width
to height ratio of greater than 4. However, it was
communicated that no high extraction mining is
permitted within 100 m of a watercourse or
wetlands. The wetlands around Mooikraal have
been delineated in 2014 and a 100 m buffer has
been placed around both wetlands and river on
the mine plans.
It is also noted that 3 Shaft is considered to be
located within 100 m of a water course however
the plant was constructed in 1950 before NWA
was promulgated. It is also noted that it is
proposed that the processing plant at 3 Shaft will
be relocated away from the water course to
reduce 3 Shaft impact on the river.
No further action required
Mooikraal received a GN R704 4 (b)
exemption which permits Mooikraal to
undermine the Kromelmboogspruit and feeder
streams using bord and pillar methods. It is
required that a safety factor of 2 is maintained
as well as a width to height ratio of greater
than 4. However, it was communicated that no
high extraction mining is permitted within 100
m of a watercourse or wetlands. The wetlands
around Mooikraal have been delineated in
2014 and a 100 m buffer has been placed
around both wetlands and river on the mine
plans.
It is also noted that 3 Shaft is considered to
be located within 100 m of a water course
however the plant was constructed in 1950
before NWA was promulgated. It is also noted
that it is proposed that the processing plant at
3 Shaft will be relocated away from the water
course to reduce 3 Shaft impact on the river.
C
An annual weed eradication
programme will be undertaken
utilising a registered chemical
herbicide contractor.
NC
An alien plant/weed eradication programme is not
implemented on an annual basis. The Mooikraal
Colliery is in the process of developing an
operational procedure for the management of
alien invasive species onsite. It was noted that
regular inspections are undertaken by the
Environmental Practitioner at Mooikraal to ensure
the invasive species are removed to prevent the
spread of species. Mooikraal currently spray
herbicides around the conveyer belt and other
problem areas previously identified. During the
site assessment it was observed that invasive
species were present such as Scottish Thistle,
Cockleburs and Pink Tamarisk. It was
communicated that most invasive species have
been established on areas that have been
disturbed and no significant spread of invasive
species have been observed.
It is recommended that the alien plant control
programme attached as Appendix 3 to the EIA
Report is implemented to manage and control the
alien invasive species which are present onsite.
The eradication of invasive species is required by
National Environmental Management Biodiversity
Act (NEMBA) (Act 10 of 2004) – Alien and Invasive
Species (AIS) regulations, 2014 and any plan
drafted in compliance with the legal requirements
must be implemented.
Invasive species must be removed to prevent
spreading to other areas around the site.
Mechanical methods should be used to remove the
invasive species specifically at the time of the year
when the plants are not producing seeds which can
result in the spread of these species to other areas.
The disposal of these species must be removed in
a controlled manner to prevent further spreading.
Proof of training specific to the invasive species
identified on site must be provided either to the
appointed contractor or the person made
responsible for the removal of alien invasive
species.
It has been communicated that the plan for
2020 will be to implement an alien eradication
programme on site. NC
7
Surface water
(Water Quality)
Surface water monitoring will be
implemented to ensure that the water
management systems perform
adequately as discussed in this EMP.
NC
It is noted that biannual ground and surface water
quality monitoring is undertaken to determine
whether the water qualities are in accordance
with the WUL and catchment standards. The most
recent biannual water monitoring report for
Mooikraal dated February 2018 (Ref No.
2018/04/PJHL) was compiled by IGS. This report
is submitted to the DWS on a biannual basis. 3
Shaft is monitored under the Sasol Sigma Colliery
as per their rehabilitation requirements. The most
recent report is dated January 2018 (Ref No.
2018/03/PJHL). The monthly water quality results
for 3 shaft indicated an increase of sulphate
levels over the past eighteen months. It is
however noted that the deteriorating water quality
is not only from 3 Shaft and has other contributing
factors. Additionally it is noted that the water
management system which is described in the
EMP is not a true reflection of what is occurring
onsite and therefore the EMP is required to be
updated.
Since Sasol Sigma is no longer required by law to
monitor its surface, it is anticipated that monitoring
will be reduced around 3 Shaft within the next 3
years. It is recommended that in order to continue
assessing the impact of 3 Shaft on the surface
resources that Mooikraal Colliery expand their
monitoring programme to include 3 Shaft. The
biannual water monitoring report currently being
compiled by IGS must monitor both Mooikraal
Colliery and 3 Shaft.
It was communicated that a BAR / 31 amendment
process is being undertaken to amend the
information currently contained within the EMP and
ensure its relevance to both the Mooikraal and 3
Shaft operation. The update will also include the
implementation of mitigation measure to prevent
continuous flow to the Leeuspruit from 3 Shaft and
ensure the containment of this dirty water.
A Standard Operating Procedure (SOP) for
stormwater management and the maintenance
of Sigma Colliery: 3 Shaft has been put
together and due for review in 2021.
Water monitoring, both surface water and
groundwater, is undertaken on a quarterly
basis. The October 2019 report indicated that
calcium-bicarbonate signature for the
upstream monitoring point and sodium-
bicarbonate signature for the downstream
monitoring point of Kromelmboogspruit North
and South whcih can be attributed to the
release of mine water discharge into the
Kromelmboogspruit t since 2010.
It is however noted that stormwater
management measures are proposed to be
implemented at 3 Shaft as part of the
conveyor relocation project which will be
authorised as part of the Regulation 31
Amendment process.
NC
The water balance at Sigma:
Mooikraal operation will be managed
by pumping to SII , from where it is
discharged to the Vaal River as part
of SII's final effluent.
NC
Mooikraal regularly monitors their water flow
which is recorded on a flow spreadsheet and
submitted to DWS. The water is currently pumped
from underground, to the PCDs and then to SO.
It is however noted that at present Mooikraal
Colliery is generated excess water which cannot
be contained within the North and South PCD
which is resulting in overflows. A 10 ML and 7 ML
are proposed to be constructed to transfer the
water to SO for further use. It is also noted that
the Water Balance contained in the IWWMP,
2015 does not include the flow of water at 3
Shaft. The IWWMP for Mooikraal was compiled
in 2015 and is proposed to be updated in 2018 to
ensure relevance to the current operation at
Mooikraal and 3 Shaft. It was observed that water
is currently discharging from 3 Shaft into the
Leeuspruit and that stormwater mitigation
measures currently located in the area is not
considered to be effective. It is considered that
the dirty water areas are not being kept to a
minimum.
Once the 7ML and 10ML pipeline is constructed
water will be transferred between Mooikraal PCDs
to SO which will prevent further discharge of dirty
water to the environment at Mooikraal.
The IWWMP is required to be updated on an annual
basis and submitted to the DWS. However, the
IWWMP has not been updated since 2015. Digby
Wells have been appointed to update the IWWMP.
During this update process it is recommended that
the Water Balance should also be updated to reflect
accurate water quantities as well as include 3 shaft
water usages which have been omitted in the 2015
IWWMP .
Effective stormwater management measures needs
to be implemented at 3 Shaft. Dirty water generated
from the mine should not be permitted to be
discharged as it can result in contamination. It is
however noted that stormwater management
measures are proposed to be implemented at 3
Shaft as part of the 31 Amendment process
The pipelines have been constructed and are
operational. The water is being transferred
from Mooikraal to Sasol Operations.
The upgrade of stromwater management
mechanisms at 3Shaft will only be effected
once the Regulation 31 Amendment is
granted.
C
No river diversions are planned for
the operations. Undermining of the
Kromelmboogspruit will be done in
accordance with GN 704
C
No river or streams have been diverted during
any phase of the Mooikraal operations. Mooikraal
received the IWUL, issued 2018 which permits
Mooikraal to undermine the Kromelmboogspruit
and feeder streams using bord and pillar methods.
It is required that a safety factor of 2 is
maintained as well as a width to height ratio of
greater than 4. However, it was communicated
that no high extraction mining is permitted within
100 m of a watercourse or wetlands. The
wetlands around Mooikraal have been delineated
in 2014 and a 100 m buffer has been placed
around both wetlands and river on the mine plans.
No further action required
No river or streams have been diverted during
any phase of the Mooikraal operations
Mooikraal received a GN R704 4 (b)
exemption which permits Mooikraal to
undermine the Kromelmboogspruit and feeder
streams using bord and pillar methods.
C
7
Surface water
(Water Quality)
Mitigate against any impact on
surface water users. Undermining of
watercourses will however be
conducted in accordance with GN
704 and the National Water Act,
1998 (Act 36 of 1998).
C
Mooikraal received a IWUL (c and i) which
permits Mooikraal to undermine the
Kromelmboogspruit and feeder streams using
bord and pillar methods. The was granted in 2018.
It is required that a safety factor of 2 is
maintained as well as a width to height ratio of
greater than 4. However, it was communicated
that no high extraction mining is permitted within
100 m of a watercourse or wetlands. The
wetlands around Mooikraal have been delineated
in 2014 and a 100 m buffer has been placed
around both wetlands and river on the mine plans.
No further action required
Mooikraal received a GN R704 4 (b)
exemption which permits Mooikraal to
undermine the Kromelmboogspruit and feeder
streams using bord and pillar methods.
The wetlands around Mooikraal have been
delineated in 2014 and a 100 m buffer has
been placed around both wetlands and river
on the mine plans.
C
Users of private boreholes affected
by mining operations will be provided
with an alternative supply of potable
water the same or better quality after
an investigation has been done by
Sasol Mining.
C
A complaints registered was provided which
records all complaints that have been made with
the Mooikraal Mine. The register is maintained by
The Sasol Mining Rights Department (SMRD)
(Mooikraal Complaints Register Dated April
2018). It was observed that complaints have
been received however no complaints relating to
any distribution of borehole water utilised by
farmers have been recorded. Should an instance
arise where borehole water has been disrupted or
impacted (quality or quantity), the incident would
be recorded and an investigation undertaken to
determine whether the mine was responsible for
the impact. If it is found that mining activities had
affected the surrounding landowner’s boreholes,
water of a similar quality and volume shall be
supplied to them by Mooikraal, this in accordance
with SMRD PROC 004. Mooikraal currently does
not provide farmers with water.
No further action required
On the day of the site visit, the Environmental
Manager was attending to a borehole issue
with an I&AP.
A complaints register is available at Mooikraal.
When a complaint is issued, the complaint
would be placed under investigation. The
complaint is assigned a person competen to
deal with the issue. The remedial measures to
be implemented are noted and progress is
given on the matter.
C
Excess mine water is pumped to
surface and either recycled, re-used
for dust suppression, etc. or
abstracted for treatment
C
Groundwater flows into the underground workings
at Mooikraal Colliery. These workings must be
kept dry for health and safety as well as
production reasons. The water is then pumped to
the South PCD which overflows to the North
PCDs. The water contained in the PCDs is then
pumped away from the dam through a 5ML
pipeline to SO for disposal. The water that is
contained in the PCD at 3 Shaft is also
authorised to be utilised for dust suppression
along the conveyor belt and at the processing
plant. Water is not pumped back underground.
Water stored in the dams underground is used for
dust suppression. It was also communicated that
Dust–A-Side is utilised along roads underground
to prevent the generation of dust.
No further action required
Water from underground is pumped into the
South PCD which then flows into the North
PCD. The water is then transferred to the
Sasol Operations and to 3Shaft for dust
suppression measures.
C
7
Surface water
(Water Quality)
8 Groundwater
The objective of groundwater
management will be to restrict the
impact of polluted groundwater to the
mining area and the adverse impacts
on groundwater will be further
reduced by implementing the
mitigatory measures and
management programme of the
below listed.
The groundwater boreholes should be
monitored to ensure that seepage is
detected before it becomes an issue.
NC
IGS is responsible for biannual ground and
surface water monitoring to determine whether
the water qualities and quantities are in
accordance with the WUL and catchment
standards. The most recent biannual water
monitoring report dated February 2018 (Ref No.
2018/04/PJHL) compiled by IGS. This report is
submitted to the DWS on a biannual basis. The
report indicated that Nitrate exceeded the limit for
the prescribed water quality objectives in
borehole MK004 at Mooikraal. All the other
constituents are well within the prescribed limits.
No groundwater monitoring of 3 Shaft is currently
being undertaken. The coal handling plant as well
as coal stockpiling can result in groundwater
contamination and therefore this needs to be
monitored
No groundwater monitoring of 3 Shaft is currently
being undertaken. Monitoring boreholes are
proposed to be drilled around 3 Shaft and
incorporated into the groundwater monitoring
programme for Mooikraal. Once the boreholes are
drilled Mooikraal must ensure that quarterly
monitoring is undertaken for each borehole.
Water monitoring by IGS is being conducted.
The August 2019 report indicated monitoring
of various boreholes and exceedances were
identified and the quality of the groundwater
was discussed to be affected by either the
geology of the area, tailings at the Waste Ash
Site at Sasol 1, 3 Shaft coal stockpile,
fertiliser on cultivated land and the borehole
assessed being near it and the proximity of a
borehole to explosives used for blasting
underground.
Therefore, boreholes have been drilled and
are being monitored quarterly as
recommended in the 2018 audit.
C
Applications of a chemical binder
(ligno-sulphonate,
calcium/magnesium chloride or
bituminous products) to roads to
develop a crust, coupled to watering
and sweeping to eliminate dust
mobilisation from this source.
C
The roads utilised underground are sprayed with
Dust–A-Side which is a chemical binder. The
Dust–A-Side assists with preventing the
generation of dust. The Dust–A-Side is spray on
the surface with a watering truck. Dust monitoring
on a monthly basis.
No further action required
Dust-A-Side is used for the roads underground
and at 3Shaft, there is Dust-A-Side used along
the access road near the water guns.
C
Constant watering (with water trucks)
in areas where material removal,
placement or manipulation is
occurring
NC
Dust suppression mechanisms are being
undertaken at the mine and include the spraying
of coal at the transfer stations of the conveyor
belt. Dust suppression is also undertaken at the
crushing and screening plant. This assists with
preventing spontaneous combustion as well as to
prevent the generation of coal dust. Dust-A-Side
is also utilised underground to reduce the
generation of dust.
A dust monitoring programme has been
implemented at Mooikraal and 3 shaft where dust
buckets have been positioned in all major and
secondary wind directions. These dust buckets
are monitored on a monthly basis by Gondwana.
Dust results were provided for the months of
August 2012 to May 2018. The results indicated
that the levels of dust did exceed the specified
limits associated with residential levels and in
some months industrial levels as per the National
Dust Fallout Regulations. Dust is considered to
be an issue at 3 Shaft due to the handling of coal.
A number of complaints have also been raised
regarding the generation of dust around the
conveyer belt and 3 Shaft (Refer to Complaints
register, 2018).
As the dust mitigation measures implemented at the
mine were found to be inadequate. An air quality
specialist study is currently being undertaken to
assess the impact of dust fall-out on the
surrounding community and to recommend
measures to reduce the impacts around 3 Shaft and
the Mooikraal Colliery. The mitigation measures
proposed from this specialist study must be
implemented to ensure dust levels are reduced and
are brought in compliance with air quality legislation.
Dust suppression measures have been put
into place at Sigma Colliery: 3 Shaft in the
form of fogger cannons. This was put in place
to address dust fall-out impacts to the
surrounding community.
The dust monitoring report compiled by
Godnwana Environmental Solutions in October
2019 states that during the period of
monitoring, 2019-09-30/2019-10-31 there
were no exceedances for non-residential
standards.
The Mooikraal Opertaions are classified as
non-residential. Therefore, based on the
lastes report provided to Digby Wells, this
condition is met.
C
Rehabilitating areas as soon as
practically possible,NA
The coal handling area at 3 Shaft is still being
utilised. This area will only be decommissioned
once MK is decommissioned and or closed.No further action required
Rehabilitation will only take place at
Mooikraal's end of LoM.
A rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact.
NA
9 Air Quality
To ensure that the dust impacts do
not exceed guideline levels as a
result of the mining activities.
8 Groundwater
The objective of groundwater
management will be to restrict the
impact of polluted groundwater to the
mining area and the adverse impacts
on groundwater will be further
reduced by implementing the
mitigatory measures and
management programme of the
below listed.
Applying dust control measures to
roads to achieve maximum dust
control efficiency
C
Dust along roads underground that are not paved
is controlled through the spraying of Dust–A-Side
with watering trucks . Dust suppression on the
surface is undertaken at the coal transfer stations
on the conveyor belt. No significant generation of
dust from the use of roads has been noted.
No further action required
Dust-A-Side is used for the roads underground
and at 3Shaft, there is Dust-A-Side used along
the access road near the water guns.
C
Ensuring that dust control measures
at transfer points are in place and
operate efficiently
C
Dust suppression mechanisms are being
undertaken at the mine and include the spraying
of coal at the transfer stations of the conveyor
belt.
Dust suppression is also undertaken at the
crushing and screening plant. This assists with
preventing spontaneous combustion as well as to
prevent the generation of coal dust.
Dust-A-Side is also utilised underground to reduce
the generation of dust.
No further action required
Dust-A-Side is used for the roads underground
and at 3Shaft, there is Dust-A-Side used along
the access road near the water guns.
The pressure of the water guns at 3Shaft need
to be checked.
C
Where practically possible to
construct berms, plant tree
screens/windbreaks
C
Berms have been constructed around the incline
shaft and PCD this assist in both screening and
water management. Trees are planted on an
annual basis in August during Arbour day. Only
indigenous vegetation is planted.
No further action required
Berms have been constructed around the
incline shaft and PCD this assist in both
screening and water management. Trees are
planted on an annual basis in August during
Arbour day. Only indigenous vegetation is
planted.
C
Implement specific noise prevention
measures such as disabling audible
reverse warning devices and
replacing these with visual warning
devices on all and new equipment,
the proper silencing of all diesel
equipment, the regular and
systematic maintenance of
equipment and the continuous
training of personnel in order to
promote operational procedures
NC
It was noted that the Mooikraal Colliery is not
considered to be noisy as only underground
mining is being undertaken. Additionally the
nearest receptor is considered to be far away
from the mining operation and would not be
considered to be impacted upon by noise. All
equipment is also put onto planned maintenance
to ensure that it is operated optimally.
Although the ventilation shaft is quiet noisy there
are no close receptors to the ventilation shaft. It
is noted however that should any noisy activity be
planned to be undertaken at the mine, adjacent
land owners will be notified. No noise complaints
for Mooikraal have been received for 2017 and
2018 (Sasol Mining External Complaints Register
April 2018).
It was however noted that issues regarding noise
generated at 3 Shaft by the crushing and
screening plant has been received from the
community and reported to the mine however this
has not been captured on the complaints register.
A noise specialist study is currently being
undertaken to address the issue of noise and
implement measures to reduce these impacts to
the surrounding community
It is recommended that once the ambient noise
specialist study has been completed and mitigation
measures have been proposed, these measures
must be implemented to reduce the generation of
noise at the shaft. Additionally, noise monitoring
may need to be implemented to ensure the noise
currently being generated at 3 Shaft is reduced.
As per the Complaints register, the Sigma
Complex only has complaints for subsidence,
leaks and rehabilitation.
No noise complaints were placed on record
about the machinery at the Sigma Coliery: 3
Shaft and Sigma Colliery: Mooikrall since is an
undergound mine, it is not considered noisy.
C
10 Noise
To ensure that measures are
implemented to reduce the disturbing
noise.
9 Air Quality
To ensure that the dust impacts do
not exceed guideline levels as a
result of the mining activities.
Conduct noise measurements on all
new equipment to establish a
reference data-base and follow up
with regular noise audits to ensure
the early detection of deviations
which could lead to complaints
C
Continuous maintenance on vehicles is
undertaken to ensure the machines function
optimally and do not produce excessive noise.
Additionally when vehicles are brought onto site,
the vehicles are monitored in terms of
occupational health and safety to ensure the
noise levels do no exceed noise standards. It
was communicated that no additionally silencers
are added to the vehicles to reduce noise as
these are generally standard on these types of
machines. It was also communicated that when
new infrastructure begins operating such as the
operation of a new ventilation shaft, ambient
noise monitoring is undertaken to ensure the
infrastructure does not generate excessive noise.
No further action required
No noise monitoring and audits are conducted
ar Mooikraal.
Noise monitoring and audits need to be
undertaken at Mooikraal.
NC
Conduct ambient noise monitoring at
regular intervals in order to detect
possible deviations from predicted
and accepted noise impact levels.
Analyse and take corrective action
NC
It was noted that the Mooikraal Colliery is not
considered to be noisy as only underground
mining is being undertaken. Additionally the
nearest receptor is considered to be far away
from the mining operation and would not be
considered to be impacted upon by noise.
Additionally although the ventilation shaft is quiet
noisy there are no close receptors to the
ventilation shaft. It is noted however that should a
noisy activities be planned to be undertaken at
the mine, adjacent land owners will be notified. No
noise complaints for Mooikraal have been
received for 2017 and 2018 (Sasol Mining
External Complaints Register April 2018). It was
however noted that issues regarding noise
generated by the crushing and screening plant
has been received but not documented. No
baseline noise assessment has been completed
for the Mooikraal operation and 3 Shaft in order to
provide substantial evidence that the noise levels
are below legal noise standards. A noise
specialist study is currently being undertaken to
address the of noise and implement measures to
reduce these impacts to the surrounding
community not di
It is recommended that once the ambient noise
specialist study has been completed and mitigation
measures have been proposed, these measures
must be implemented to reduce the generation of
noise at the shaft. Additionally, noise monitoring
may need to be implemented to ensure the noise
currently being generated at 3 Shaft is reduced.
It was advised by the Environmental Officer
that no noise report were available, besides
the baseline that was conducted for the
Regulaton 31 Amendment and WUL
application.
Noise complaints were not identified in the
complaints register. However, as a
commitment of the EMPR, there needs to be
monitoring conducted. Theefore, because
these are not taking place, the condition is
found non-compliant.
NC
No “high noise” operations should
take place on or above ground level
at night
C
The mine operates as a 24 hour mine however it
was noted that excessive noisy activities which is
undertaken occasionally is limited to day light
hours such as blasting. No noise complaints for
Mooikraal have been received for 2017 and 2018
(Sasol Mining External Complaints Register April
2018). It was however noted that issues
regarding noise generated by the crushing and
screening plant has been received but not
documented.
No further action required
The mine operates as a 24 hour mine
however it was noted that excessive noisy
activities which is undertaken occasionally is
limited to day light hours such as blasting.
C
10 Noise
To ensure that measures are
implemented to reduce the disturbing
noise.
If all management actions fail to
address the impact, BATNEEC-
engineering practices will have to put
in place e.g. the construction of a
noise barrier, etc.
NA
On completion of the noise specialist study,
mitigation measures will be proposed to reduce
the noise being generated from the operation.
These mitigation measures may invoice the
construction of berms where applicable.
No further action required
It was advised by the Environmental Officer
that no noise report were available, besides
the baseline that was conducted for the
Regulaton 31 Amendment and WUL
application.
Upon approval of the Regulation 31
Amendment, the noise baseline can be used
as a starting point.
C
The shaft, conveyor, overburden
dump and plant (at 3 Shaft) will be
vegetated and rehabilitated
C
During the site assessment it was observed that
the areas around the Mooikraal shaft, Kleinvlei
Ventilation Shaft, 3 Shaft, borrow pit and
overburden dump were vegetated. The
vegetation was allowed to be established
naturally and it was observed that no significant
alien invasive species occurred. It is noted that
as the mine is an underground mine, minimal
rehabilitation activities are undertaken at the
facility.
No further action required
Rehabilitation will only take place at
Mooikraal's end of LoM.
A rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact.
NA
The infrastructure will be demolished
and removed in consultation with the
authorities.
NA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. Once LoM is reached, all
infrastructure will be removed from site and
rehabilitation will commence in line with the
rehabilitation measures proposed in the approved
EMPr, a rehabilitation management plan will be
compiled once closure is reached which will
include all mitigation measures to prevent
unnecessary environmental impact. Additionally a
re-vegetation programme will be implemented to
ensure indigenous vegetation is utilised during
rehabilitation. Additionally alien invasive species
monitoring will be undertaken on the newly
rehabilitated areas so as to prevent the spread of
invasive species.
No further action required
Rehabilitation will only take place at
Mooikraal's end of LoM.
No communications have been received from
the authorities in relation to the demolision of
infrastructure.
NA
The lighting of the plant and shaft
areas will be designed in such a way
as to reduce illumination at night.
C
During the site assessment it was observed that
lighting is utilised to illuminate the operation.
These lights are pointed towards the ground to
ensure light is direct on the mine and not into the
surrounding properties.
No further action required
Lights are pointed towards the ground to
ensure light is direct on the mine and not into
the surrounding properties.
C
High mast lights will be designed in
such a way that they shine on the
plant and mine infrastructure only.
C
During the site assessment it was observed that
high mast lights are utilised to illuminate the
operation. These lights are pointed towards the
ground to ensure light is direct on the mine and
not into the surrounding properties.
No further action required
Lights are pointed towards the ground to
ensure light is direct on the mine and not into
the surrounding properties.
C
Rehabilitate all disturbed areas as
soon as is practicably possibleNA
As the Mooikraal Mine is an underground coal
mine, limited rehabilitation is undertaken on areas
where mining or related activities have been
undertaken. It was reported that to date only
minimal rehabilitation activities had been
undertaken. No visual complaints have been
received (Complaints register, 2018). Berms have
been constructed around the incline shaft and
PCD to reduce the visual impact associated with
the mine.
No further action required
Rehabilitation will only take place at
Mooikraal's end of LoM. NA
10 Noise
To ensure that measures are
implemented to reduce the disturbing
noise.
11 Aesthetics
To minimise the visual impact of
mining operations as much as
possible.
Introduce flora to soften and screen
buildings and structuresC
It was communicated that limited flora is found
onsite as it is currently a fully operational mine.
Indigenous trees have been planted around the
mine. Limited visual receptors are located in
close proximity to the mine therefore the visual
impact of the mine to the adjacent land owners is
considered to be minimal.
No further action required
Limited flora is found onsite as it is currently
a fully operational mine. Indigenous trees have
been planted around the mine. Limited visual
receptors are located in close proximity to the
mine therefore the visual impact of the mine to
the adjacent land owners is considered to be
minimal.
C
Planting of indigenous trees around
structures, buildings, etc; and
maintaining of the area around
infrastructure and keep it neat
C
During the site assessment it was communicated
that only indigenous trees were planted and it was
found that the mine was will kept.
No further action required
Limited flora is found onsite as it is currently
a fully operational mine. Indigenous trees have
been planted around the mine
C
12Interested and
Affected Parties
To minimise the negative impacts of
the closing down of the underground
operations and resulted loss of
employment.
Sasol Mining Rights and Property
Department (SMRD) gives feedback
to all I &APs on complaints received
and the implementation of corrective
actions taken as committed in the
ISO14001 EMS
C
A complaints registered was provided which
records all complaints that have been made with
the Mooikraal Mine. The register is maintained by
the SMRD (Mooikraal Complaints Register Dated
April 2018). It was noted that complaints have
been received to date such as dust compliments,
spillages, dumping of waste and veld fires. These
complaints have been investigated to determine
whether Mooikraal is responsible for the
complaint. Should the compliant be found to be
valid, measures are undertaken in accordance
with SMRD PROC 004 to resolve the issue and
close out the complaint. It was noted that only
one compliant was found to be unresolved to date
which was raised in June 2018 with regards to
damage of grazing land from cement being
deposited on it. Sasol must undertake an
investigation to determine whether Sasol were
responsible for the incident and implement
measure if found to be responsible. All incidents
and non-conformances are thoroughly
investigated as part of ISO 14001: 2015 element
4.5.3, procedure Sn of dust arou
No further action required
The Sasol Mines Complaints register was
provided which had 25 complaints logged from
February 2019 to November 2019.
Only 1 of the 25 complaints has been resoled
as per the compliants register. It is
recommended that complaints be addressed
at a more expediant manner to avoid
complaints running over the next year.
C
The main structures requiring
maintenance are:
■ Stormwater diversion
channels/berms
■ Stormwater conveyance
channels
■ Sumps
■ Trenches
■ Pollution control dams
■ Surface dams
All of the above facilities will be
maintained according to general
accepted engineering practices and
in accordance with the requirements
of the National Water Act, 1998 (Act
36 of 1998) and will be inspected
visually at least once a week.
Estimations of the costs of measures
to comply with statutory obligations
will be determined by suitably
qualified persons within ninety days
before the end of each financial year.
No further action required
No further action required13
Maintenance of
water pollution
structures
C
Weekly inspections are undertaken at the mine by
the Environmental Practitioner. It was noted that
the sump is regularly cleaned out by EnviroServe
to remove the sludge that is generated form the
operation which was noted through inspection list
completed by the responsible person for that
area. Additionally inspections of the stormwater
management specifically the trenches and berms
are undertaken in September prior to the first
heavy rainfall event. Should an issue be identified
maintenance will be undertaken to ensure the
structures are able to contain a 1:50 year flood
event. Additionally Inspections are typically
conducted after each major rainfall event, to
determine whether any damage has occurred to
the stormwater management infrastructure.
Stormwater management infrastructure are
inspected in summer months on a monthly and in
winter months every 2 months.
14Financial
ProvisionC
11 Aesthetics
To minimise the visual impact of
mining operations as much as
possible.
Sasol Mining calculated the financial provision
for the various Sasol mines in 2019 which
was completed by Jones and Wagener (Ref
No. JW047/15/E473 - Rev 4). The FP for the
Mooikraal Opertaions is at a total of R 120
293 927.19 as of March 2019.
C
As found in the 2019 WUL Audit, berms are
used to prevent clean water from entering the
incline shaft and divert the water around the
shaft area. All contaminated stormwater from
the wash bay, parking areas and bulk storage
areas at the Mooikraal Shaft is contained to
the dirty water system which comprises a
network of sumps and silt traps which
overflows into the PCD. From the North PCD
this water is pumped to the 3 Shaft for dust
suppression or the SO as part of their water
system.
C
Contribution towards the estimated
costs of measures shall be made by
Sasol Mining before the end of the
financial year.
The shortfall between the estimated
costs of measures and the credit of a
beneficiaries account shall be made
good by Sasol Mining.
The above shortfall could arise at
termination of mining operations
and/or liquidation before the required
financial provision in terms of the
above formula has been made
No further action required14Financial
ProvisionC
Sasol Mining calculated the financial provision
for the various Sasol mines in 2019 which
was completed by Jones and Wagener (Ref
No. JW047/15/E473 - Rev 4). The FP for the
Mooikraal Opertaions is at a total of R 120
293 927.19 as of March 2019.
C