Second Avenue Subway

Community Board 8 Second Avenue Subway

Task Force Update

September 24, 2015

Anil Parikh, P.E.

Senior Vice President & Program Executive

Second Avenue Subway Project

Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

1 1

96th Street Station

(Cut-and-Cover)

86th Street Station

2 Entrances

72nd Street Station

3 Entrances

63rd Street /

Lexington Ave Station

Phase 1: Target Cost-$4.451B--- Ridership 200,000 --- Target Completion Date-December 2016

• Scope:

Q train service

Tunnels from 92nd St to 63rd St

New Stations at 96th St, 86th St, and 72nd St

63rd St Station Connection

Track & Systems from 105th St to 63rd St

Service between 96th St & Brooklyn via Broadway Line

Phase 1 Overview

96th Street Station

3 Entrances

63rd Street Station

4 New Entrances

Page 3: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

2 2

• The Second Avenue Subway Project is on time and on budget for a December 2016 completion.

• Overall Construction Progress is 86.35% complete as of September 1st.

• All 10 SAS Contracts have been awarded for Phase 1

• 5 Construction Contracts Completed:

− Tunnel Boring Machine Tunneling

− 86th St Excavation, Utility Relocation, and Road Decking

− 96th St Site Work and Heavy Civil

− 72nd St Cavern Mining, Tunnels and Heavy Civil

− 86th St Cavern Mining & Heavy Civil

Current Project Status

Page 4: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

3

5 Active Contracts

96thSt. Station Finishes, Systems, Ancillary 76%

Buildings and Entrances

86thSt. Station Finishes, Systems, Ancillary 51.9%

Buildings and Entrances

72nd St. Station Finishes, Systems, Ancillary 70.15%

Buildings and Entrances

63rd St. Station Upgrade 92.13%

All Stations Track, Power, Signals & Communications 63.32%

Systems

Page 5: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

4

63rd Street

3rd

Ave

Ancillary 1

124 E 63rd St

Top of

Hahn Garage

Entrance 4

(Outside) Entrance 1

(Inside)

Entrance 3

(Outside)

New Elevator Entrance 2

Ancillary 2

Lexin

gto

n A

ve

Existing Elevator Entrance

Existing Entrance

Existing Entrance

Plaza

Station Upgrade Contract

Percent Complete: 92.13%

Contract Value incl. AWOs: $190.8 M

Award Date: January 13, 2011

Forecast Completion: Winter 2015/2016

Rehabilitation of Existing 63rd Street

Station Plaza

Page 6: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

5 5 MTA Capital Construction

Milestones

• Escalator installation at new Entrance 1 (southeast

corner of 63rd Street and 3rd Avenue) is underway.

• Construction for Entrance 3 (northeast corner of 63rd

Street and Third Avenue) and Entrance 4 (southwest

corner of 63rd and 3rd Avenue) continuing below

sidewalk level. Entrance canopies have been installed.

Page 7: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

6 6

Current Work Zones (SE corner of 63rd Street & Third Avenue)

Escalator installation at Entrance 1

Page 8: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

7 7 MTA Capital Construction

Current Work Zones (NW corner of 63rd Street & Third Avenue)

Entrance 2 Elevator Kiosk

Page 9: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

8 8

Current Progress

Granite flooring at lower level elevator lobby

Elevators

Page 10: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

9 9

Current Progress

Installation of artwork at 63rd Street station area

Page 11: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

10

Three-Month Look Ahead

10 MTA Capital Construction

STATION

• Installation of service carrier, ductwork and electrical

conduit at the upper platform level

• Installation of platform finishes, including ceilings, track

wall tile framing, column covers, platform paving, and

lighting fixtures

• Masonry wall, ceiling panel, and door installation

throughout station

• Mechanical, electrical and plumbing systems installation in

new station area

Page 12: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

11

Three-Month Look Ahead

11

ENTRANCE 1

(200 East 63rd Street)

• Escalator installation

• Installation of finishes and tiles

ANCILLARY 2

(Northwest corner of 63rd Street and Third Avenue)

• Construction of elevator shaft within plaza work zone

area

• Receive materials via sidewalk access hatch on the

north side of 63rd Street west of the existing work zone

MTA Capital Construction

Page 13: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

12 12

Three-Month Look Ahead

OTHER SURFACE WORK

• Installation of interior finishes at Entrance 4 (southwest

corner of 63rd Street and Third Avenue).

THIRD AVENUE STORAGE/WORK ZONE

(Third Avenue between 63rd and 64th Streets)

• Work zone will remain until Summer 2016 for materials

storage and small office trailer for systems contractor.

Page 14: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

13 13

Rendering of 63rd Street Plaza SW corner of 63rd Street and Third Avenue

Page 15: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

14

Rendering of 63rd Street Station Art Installation, Mezzanine Level (Area 5) Artist – Jean Shin, MTA Arts and Design commissioned work 14

Page 16: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

15

72nd Street Station

Finishes, MEP Systems, Ancillary Buildings

and Entrances Contract

Percent Complete : 70.15%

Contract Value incl. AWOs: $283.7 M

Award Date: February 14, 2013

Forecast Completion: October 2016

Page 17: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

16 16 MTA Capital Construction

Milestones

• Exterior and interior excavation is complete at Entrance 1

(northeast corner of 69th Street and Second Avenue)

• Structural work is complete at Ancillary 2 (northwest corner of

72nd Street and Second Avenue)

• Entrance 3 (southeast corner of 72nd Street and Second Avenue)

structural work is at street level

• Ancillary 1 (northwest corner of 69th Street and Second Avenue)

structural work has reached the third floor level

• Systems contractor has begun installation of communications

and signaling equipment

Page 18: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

17 17

Current Progress

Main Cavern Service Carrier Steel Framing Installation

MTA Capital Construction

Page 19: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

18 MTA Capital Construction

18

Current Progress

Main Cavern (platform level) – Track wall tile installation near completion

Page 20: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

19

Current Progress

19

Ancillary#2 NW corner 72nd Street

MTA Capital Construction

Page 21: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

20 20

Current Progress

Ancillary#1 NW corner 69th Street

MTA Capital Construction

Page 22: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

21

Current Progress

21

Entrance 3 (southeast corner of 72nd Street and Second Avenue) at street level

MTA Capital Construction

Page 23: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

22 22 MTA Capital Construction

Three-Month Look Ahead Main Station Cavern:

• Installation of wall tiles, ceiling panels, conduits and duct work

at the mezzanine level

• Mechanical, electrical and plumbing systems installation at

mezzanine level

• Installation of service carrier and ceiling panels at the platform

level

• Cable pulling through finished conduits

• Resumption of track work in station area in September

Page 24: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

23 23

Three-Month Look Ahead Entrance 1:

• Installation of the underground incline lining

• Concrete pours continuing

• Street work hours: 7 a.m. – 10 p.m.

Ancillary 1, Ancillary 2, Entrance 3

• Installation of waterproofing and construction of Ancillary 1 and

Entrance 3 structures

• Concrete pumping at Ancillary 1 and Entrance 3

• Equipment delivery and installation at Ancillary 1, Ancillary 2

and Entrance 3

• Façade Installation at Ancillary 2

• Installation of elevator steel at Entrance 3 shaft

Page 25: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

24 24

Three-Month Look Ahead

Miscellaneous

• Concrete truck staging as needed between 74th and 75th

Streets

• Use of access hatch at Ancillary 1 and Ancillary 2 to deliver

materials to the station

• Upcoming Verizon work on 72nd Street from 1st to 3rd Avenues

• Upcoming Con Edison Work at 69th Street and 2nd Avenue for

permanent power to the station

• Removal of water treatment plant between 73-74 Street

• Plans to start street restoration between 65-68 Streets and 74-75

Street

MTA Capital Construction

Page 26: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

25

Page 27: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

26 26

Page 28: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

27 27

Page 29: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

28 28

Page 30: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

29

Ancillary 2 Ancillary 1

Entrance 1

(Inside)

Ancillary 2

86th Street Station

2nd Avenue

Finishes, Entrances, Ancillaries, and MEP Systems Contract

Percent Complete : 51.9%

Contract Value: $223,000,000

Award Date: June 12, 2013

Forecast Completion: October 2016

84th 85th 86th 87th

Entrance 2

(outside)

83rd

Page 31: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

30 30

• Three of the four escalators at Entrance 2 (E.

86th Street) have been installed.

• Traffic has been switched to the east side of

Second Avenue, between 82nd – 85th Streets, so

that work can begin on the west side there.

86th Street Station Milestones

Page 32: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

31 31

Installation of wall panels and support

brackets for wall tile.

Page 33: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

32 32

Fan is for temporary

ventilation purposes.

Rail stored for future installation

Installation of escalators from the

mezzanine level to the platform level

Page 34: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

33 33

Three Month Look Ahead 86th Street Station Area

E. 78th to E. 79th Streets – (Center of Second Avenue)

Maintain center work zone on Second Avenue between 78th

and 79th Streets for concrete placement for track work in the

underground tunnels.

E. 82nd to E. 85th Streets

Construction of the Ancillary 1 building on the northwest corner

of 83rd Street will reach street level in September.

E.86th Street to E. 87th Streets

Construction of the Ancillary 2 building on the northwest corner

of 86th Street will reach street level in October.

Crane will be removed from the work zone on the east side and

utility relocation will begin.

Page 35: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

34 34

E. 86th Street between 1st and 2nd Avenues

Work will begin at the elevator shaft late-

September. Traffic lanes will be reduced to

two eastbound lanes and one westbound

bound lane.

Three Months Construction Look Ahead

Page 36: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

35 35

Three Month Look Ahead 86th Street Station Area

Underground Construction

• Installation of concrete masonry walls at the platform, mezzanine, and

upper mezzanine levels.

• Installation of HVAC ductwork and insulation at the mezzanine and

upper mezzanine levels.

• Installation of electrical conduit at the platform and mezzanine levels

and Entrance 1and 2.

• Delivery of equipment and systems throughout the station will

continue, including equipment to power station, escalators, and

elevators

Page 37: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

36

Elevator entrance at E. 86th Street

Page 38: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

37

86th Street Entrance 1 Rendering 83rd Street and Second Avenue

Page 39: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

38 38

Rendering of 86th Street Station Art Installation Artist – Chuck Close, MTA Arts and Design commissioned work

Portraits in mosaic and tile representing NYC cultural figures & family

Page 40: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

39

96th Street Station

Finishes, MEP Systems, Ancillary Buildings

and Entrances Contract

Percent Complete: 76%

Contract Value: $324,600,000

Award Date: June 22, 2012

Forecast Completion: October 2016

Page 41: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

40 40

Construction Update

96th Street Station

• Roadway decking & decking support removal continues

along west side of 2nd Avenue.

• Utility work continues on the west side of 2nd Avenue.

Expected to be completed in December 2015.

• Installation of communication conduits continue in

Ancillary 1 (northeast corner 93rd Street & 2nd Avenue)

and Ancillary 2 (southwest corner of 97th Street & 2nd

Avenue)

• Completed installation of facility power equipment and

wires. Started testing of facility power equipment.

Page 42: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

41 41

• Installation of escalators at Entrance 1 (southwest corner

of 94th Street & 2nd Avenue) and Entrance 2 (northeast

corner 94th Street & 2nd Avenue)

• Tunnel ventilation fans are being installed at Ancillary 1

(northeast corner of 93rd Street & 2nd Avenue.)

• Entrance 3 concrete pours complete (southwest corner of

96th Street & 2nd Avenue.

Construction Update continued

96th Street Station

Page 43: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

42

Construction Progress

9/25/2015

Installing Sound Attenuators for Fans at Ancillary 2

97th Street and 2nd Avenue

Page 44: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

43

Construction Progress

9/25/2015

Pouring Concrete Cradle for the 48” Sewer main at Entrance 3

96th Street and 2nd Avenue

Page 45: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

44

Construction Progress

9/25/2015

Backfill on the west side of Second Avenue

between 92nd and 93rd Street

Page 46: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

45

Construction Progress

9/25/2015

Entrance 3 pour complete

Southwest corner of 96th Street and 2nd Avenue

Page 47: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

46

Construction Progress

9/25/2015

Service booth Installation at Entrance 3

96th Street and 2nd Avenue

Page 48: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

47 47

Three Month Look Ahead 96th Street Station Area

• Deck beam & roadway decking removal on west side of

Second Avenue.

• Continuing surface utility work on west side of Second

Avenue between 91st Street and 99th Streets.

• Sidewalk restoration to begin in northern (104th Street)

and southern (90th Street) ends of the station area.

• Installation of HVAC ducts, masonry walls, and electrical

conduit throughout the station.

Page 49: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

48

96th Street Ancillary 2 Rendering

SW corner 97th Street and Second Avenue

Page 50: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

49

96th Street Entrance 3 Rendering

NW corner 96th Street and Second Avenue

Page 51: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

50 50

Rendering of 96th Street Station Proposed Art Installation Artist – Sarah Sze, MTA Arts For Transit commissioned work

Page 52: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

51

Systems Installation

Installation of Special Work Portion at 96th St.

• Low Vibration Track (LVT) System

Being Installed

− Track to be installed: 22,000 ft.

− Track installed to date: 12,500 ft.

(11,180 ft. concreted)

− Aluminum 3rd rail installed: 8,500 ft.

− Track delivered to site: 22,000 ft.

− 96th St. Station interlocking (Special

Work Portion) scheduled for

concrete placement before the end

of September.

Page 53: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

52 52

• Traction Power work ongoing for

three substations and four circuit

breaker houses

Traction Power Substation

equipment has been delivered to

all stations.

• Signal equipment being installed in

relay rooms, central instrumentation

room and along the wayside.

Systems Installation Central instrumentation testing underway at 63rd

Street.

Page 54: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/CB8 SAS Task Force... · •Deck beam & roadway decking removal on west side of Second Avenue. •Continuing surface utility

53 53

Systems Installation

Track, Power, Signals and

Communications Systems

Contract

Percent Complete: 63.32%

Contract Value incl. AWOs: $282.8 M

Award Date: January 18, 2012

Forecast Completion: October 2016

• Contractor completed approximately 90% of the copper cable and

95% of the fiber optic cable installations at 63rd street station.

• Installation of all CCTV cabinets at 63rd, 72nd and 96th street stations.

• Installation of inter-station communication cables completed between

86th Street and 105th Street.