Second Avenue Subway Newsletter Issue XLVII – March 2016 86th Street Station Area Announcements Subscribe! Want to stay most informed? Send your email address to [email protected] to sign up for our e-news distribution list. Be sure to specify “86th St Station Area.” SAS Community News Escalators for Entrance 1 were delivered to 83rd Street for installation. The contractor has installed ten of the thirteen escalators in the station and the final parts will arrive this month. Ancillary 2 (northwest corner of 86th Street and Second Avenue) has reached street level and will reach full height in the coming weeks. West side sidewalk restoration is ongoing and expected to be completed in the spring. Construction of the elevator on the southeast corner of 86th Street and Second Avenue progresses. CIC HOURS of OPERATION Monday, Wednesday, Friday: 10 a.m. – 6 p.m. Tuesday, Thursday: 11 a.m. – 7 p.m. Saturday: 11 a.m. – 3 p.m. (second Saturday of the month) Come visit our current exhibit, The People Behind the Project which tells the story of the funding, planning and building of the Second Avenue Subway through the voices of its key players. The People Behind the Project: Bringing the Second Avenue Subway to Life, the exhibit is a series of short documentary style videos that tell the story of the first major expansion of the New York City Subway in decades. In addition to the wall installation, the center also features an interactive exhibit, presented at four stations with iPads and high-definition monitors. The interactive exhibit features 17 videos - a six-minute feature film, six “Digging Deeper” videos that focus on specific topics including leadership and construction, and 10 short films in which individuals share personal stories. Construction Update Photo

Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 86th-March2016.pdfAncillary 2 (northwest corner of 86th Street and Second Avenue) has reached street level and

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 86th-March2016.pdfAncillary 2 (northwest corner of 86th Street and Second Avenue) has reached street level and

Second Avenue SubwayNewsletter

Issue XLVII – March 2016

86th Street Station Area Announcements

Subscribe!

Want to stay most informed? Send your email address to [email protected] to sign up for our e-news distribution list. Be sure to specify “86th St Station Area.”

SAS Community News

Escalators for Entrance 1 were delivered to 83rd Street for installation. The contractor has installed ten of the thirteen escalators in the station and the final parts will arrive this month. Ancillary 2 (northwest corner of 86th Street and Second Avenue) has reached street level and will reach full height in the coming weeks.

West side sidewalk restoration is ongoing and expected to be completed in the spring.

Construction of the elevator on the southeast corner of 86th Street and Second Avenue progresses.

CIC HOURS of OPERATION

Monday, Wednesday, Friday: 10 a.m. – 6 p.m.

Tuesday, Thursday: 11 a.m. – 7 p.m.

Saturday: 11 a.m. – 3 p.m. (second Saturday of the month)

Come visit our current exhibit, The People Behind the Project which tells the story of the funding, planning and building of the Second Avenue Subway through the voices of its key players.

The People Behind the Project: Bringing the Second Avenue Subway to Life, the exhibit is a series of short documentary style videos that tell the story of the first major expansion of the New York City Subway in decades. In addition to the wall installation, the center also features an interactive exhibit, presented at four stations with iPads and high-definition monitors. The interactive exhibit features 17 videos - a six-minute feature film, six “Digging Deeper” videos that focus on specific topics including leadership and construction, and 10 short films in which individuals share personal stories.

Construction Update Photo

Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 86th-March2016.pdfAncillary 2 (northwest corner of 86th Street and Second Avenue) has reached street level and

Project Overview

86th Street Station Area – March 2016Second Avenue Subway Newsletter

Follow the SAS project on the MTA website at http://mta.info/sas

SURFACE UndergroundLEVEL

Construction Update

• The center work zone on Second Avenue between 78th and 79th Streets will be maintained to pour concrete for tracks in the underground tunnels

• Replacement of the 12” water main on the west side of Second Avenue between 83rd and 84th Streets is completed. Replacement of the larger 48” water main is ongoing

• Sidewalk restoration on the west side of Second Avenue between 82nd and 84th Streets is ongoing

• Construction of the Ancillary 1 building (northwest corner of 83rd Street) has reached full height. Above ground work will continue, including installation of building finishes

• There will be intermittent sidewalk closures on the east side of Second Avenue between 83rd and 84th Street to facilitate deliveries of the final few pieces of the escalators for the station entrance. The deliveries, approved by DOT, will only occur during off-peak hours (10 a.m. – 4 p.m. and 7 p.m. – 10 p.m.). Pedestrians will be directed by flaggers to the west side of Second Avenue

• Construction of the ADA elevator on the southeast corner of 86th Street and Second Avenue will continue

• The contractor continues to receive deliveries of equipment at the Ancillary 2 access shaft (northwest corner of 86th Street)

• Delivery of station and traction power equipment, escalators, elevators, signal, and communication systems will continue.

• Installation of HVAC duct work and electrical conduit continues at all levels in the station

• Installation of wall and ceiling cladding at the platform level and the wall cladding framing at the mezzanine level is underway

• Platform service carrier installation is now complete

• Mezzanine service carrier installation is ongoing

Work HoursMonday – Friday 7:00 a.m. to 10:00 p.m. Saturday 10:00 a.m. to 7:00 p.m. Work is permitted underground 24/7 For questions and concerns regarding the 86th Street Station, please contact Claudia Wilson at [email protected] or (646)-448-8884 ext 102 (new phone number). After business hours or on weekends please use the SAS 24/7 hotline # (212)792 9716.

Future Mezzanine level of 86th Street Station Entrance.

The future 86th Street Station will have two new entrances including 10 escalators, and one street-level ADA accessible elevator at the southeast corner of 86th Street and Second Avenue. Work in this area is to construct the station cavern, entrances and ancillary spaces for the future station.

The follow-on contractor 86th Street Constructers, Joint Venture (86STCJV) took over the finishes portion of the contract in December 2014. 86STCJV is responsible for the construction of the station facilities and architectural finishes, mechanical, electrical and plumbing systems, and entrances above street level; construction of the ancillary facilities up to and above street level; and restoration of the street and sidewalks in the station area. Estimated completion of this station is Fall of 2016.

Follow on Finishes Contract

Contractor:86th Street Contractors, JV

Budget:$209 Million

Award Date: June 2013 Contract Forecast Completion:Fall 2016

For community related concerns, please contact Claudia Wilson at [email protected] or (646)-448-8884 ext 102.

Construction progress statistics as of March 1, 2016:

• The Finishes, Entrances, Ancillaries, and Mechanical, Electrical and Plumbing Systems Contract (86th St. Constructors JV) is: 75.37% complete.

• The 86th Street Station is 90.35% complete.

• The Second Avenue Subway project construction is 91.9% complete.