63
Review of FasTracks Status and Options for Future Direction Public Meeting Presentation Regional Transportation District Fall 2008

Review of FasTracks Status and Options for Future ...rtd-fastracks.com/media/uploads/nw/2008-0923_FasTracks_Public... · and Options for Future Direction Public Meeting Presentation

  • Upload
    hahuong

  • View
    215

  • Download
    1

Embed Size (px)

Citation preview

Review of FasTracks Status and Options for Future Direction

Public Meeting Presentation

Regional Transportation DistrictFall 2008

Today’s Presentation

• Challenges for the FasTracks Program – Changes in cost escalation– Changes in revenue forecasts

• Review 5 Options for FasTracks• Give Feedback on Option Preferences • Next Steps• Interactive Public Input

– Write a comment– Use a laptop– One-on-one with a project representative

2

How your input will be used

3

• Your input will be shared with the RTD Board and local elected officials to help determine the path forward for the FasTracks program by the 1st Quarter of 2009

Overview• Like everyone in the country – RTD is feeling the

impact of these tough economic times

• The FasTracks program is struggling with the combination of– Increases in fuel and construction costs– Decreases in RTD required revenues from sales tax

• Because of these changes in economic conditions, RTD is – Modifying their long term cost escalation and revenue

assumptions – Developing options for delivering the FasTracks

program

4

Changes in Cost Escalation

5

Original Cost Escalation Assumption

• RTD assumed annual construction inflation of 3.3 % based on the 12-year historic average – 1991-2003

• 2004 FasTracks Plan assumptions were reviewed and approved by DRCOG, Metro Mayors Caucus and the Denver Metro Chamber of Commerce

6

Sources: Bureau of Labor StatisticsColorado Legislative Council

Annual Cost Escalation Since 2004

-4

-2

0

2

4

6

8

10

12

14

1988 1993 1998 2003 2008

PPI - Highway & Street Construction

PPI - Other Heavy Construction

CPI - Urban (Denver)

FasTracks Original Budget

Approved

2006 2007

3.3%

Jun08

7

New Cost Escalation Assumptions

Revised Assumptions

Materials Cost Escalation after 2007

• 2008 = 11.65% • 2009 = 10.71% • 2010 – 2012 = 6% / year• 2013 – 2017 = 5% / year• 2018 – 2035 = 3.3% / year (CPI)

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Compounded

11.65% 10.71% 6.00% 6.00% 6.00% 5.00% 5.00% 5.00% 5.00% 5.00% 87.89%

• RTD is forecasting higher escalation rates in the future due to construction market trends

8

Revenue Forecasts

9

-5%

0%

5%

10%

15%

1981 1985 1989 1993 1997 2001 2005

Actual Growth Actual Decrease Average Annual Growth - 1980-2002

6.3%

FasTracks Original Budget Approved

Original Sales Tax Revenue Assumption• RTD assumed annual revenue growth of

6.06% –more conservative than 20-year historic average of 6.3% – 1980-2002

10

-5%

0%

5%

10%

15%

2008 2012 2016 2020 2024 2028 2032

Revised Forecast Growth Average Annual Growth - 1980-2002

6.3%

New Sales Tax Revenue Assumptions

11

Assuming These New Cost Escalation and Revenue Forecasts - What is the Impact to the FasTracks

Program?

12

$11.8 $10.9

$13.7

$0.0$2.0$4.0$6.0$8.0

$10.0$12.0$14.0$16.0

2004Forecast

2007Forecast

2008Forecast

Billi

ons

Impact of Reduced Sales Tax Forecasts

13

Impact of Increased Cost Escalation

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

Cos

t (in

bill

ions

)

2004 (Original) 2007 APE 2008 APE (Completionby 2017)

Approved Budget Scope Changes Changes/Railroad Req. Escalation

$4.7 B

$6.1 B

$7.9 B

14

Summary

• Declining revenues and escalation in costs have resulted in a funding gap for FasTracks– Forecasted increases in cost escalation could

have been accommodated if revenue forecasts were not also declining

– Forecasted declines in revenue could have been accommodated if costs were not also increasing

• RTD must determine options for delivering the FasTracks program

15

Options for Delivering FasTracks

16

FasTracks Map

17

Basic Assumptions by 2017All FasTracks options include completion of the

following activities by 2017:

18

• Complete all environmental documentation, basic engineering and purchase railroad right-of- way

19

• Complete all environmental documentation, basic engineering and purchase railroad right-of-way

• Complete projects under construction (West, US 36 BRT Phase 1)

20

• Complete all environmental documentation, basic engineering and purchase railroad right-of-way

• Complete projects in construction: West, US 36 BRT Phase 1

• Complete Denver Union Station and all Maintenance Facilities

21

• Complete Gold Line and East Corridor to retain eligibility for $1 billion in federal funds and $1 billion in private funds

–This does not affect the extent to which remaining corridors are impacted

22

Why West, Gold Line and East Corridors Qualify for FTA Funding

• All FasTracks projects meet regional needs, but do not meet requirements to receive Federal money

• Only projects that could qualify under the FTA New Starts criteria, a nationwide competitive grant process – Projects must meet a Cost Effectiveness Index,

which considers cost and ridership, to be eligible for FTA funds

• Part of original 2004 FasTracks finance plan assumptions

• Eligible for $1.3 billion (West, East, Gold)

23

5 Options

Note: All Options Are Initial Concepts and Subject To Change Based on Stakeholder

Input and Further Refined Engineering

24

Option #1Basic Assumptions

-PLUS-

25

Basic Assumptions

-PLUS-

Segments of other corridors by 2017 – End the Program

Option #1

Preliminary Concept – Subject to Change Based on Public Input 26

Option #1 – Pros and ConsBasic Assumptions + Segments of all other

corridors by 2017 – End the Program

Pros• Does not require additional

funding

• Longer segments could be built if economic conditions improve

Cons• Does not build out entire

program

• All corridors not completed

27

Basic Assumptions

-PLUS-

Option #2

28

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 29

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 30

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 31

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 32

Option #2 – Pros and ConsBasic Assumptions + One additional complete corridor

by 2017 – End the Program

Pros• Does not require additional

funding

• Provides full build-out of one additional corridor

Cons• Does not build out entire

program

• Prioritization of corridors will require regional consensus

33

Basic Assumptions

-PLUS-

Option #3

34

Option #3Basic Assumptions

-PLUS-

Segments of other corridors by 2017 – Build the Rest Over Time as Revenues Allow

Preliminary Concept – Subject to Change Based on Public Input 35

Option #3Basic Assumptions

-PLUS-

Segments of other corridors by 2017 – Build the Rest Over Time as Revenues Allow

Preliminary Concept – Subject to Change Based on Public Input 36

Option #3 – Pros and ConsBasic Assumptions + Segments of all other

corridors by 2017 – Build the Rest Over Time as Revenues Allow

Pros• Does not require new

revenue sources

• Builds out the entire program

• Build out could be accelerated before 2034 if economic conditions improve

Cons• Some corridor schedules

would be delayed

• Overall program budget increases

37

Basic Assumptions

-PLUS-

Option #4

38

Basic Assumptions

-PLUS-

Longer Segments of other corridors with limited service by 2017 –

Option #4

Service Frequencies:• North Metro – 30 min• I-225 – 30 min• Northwest Rail – 30

min (peak only-bus all day) Preliminary Concept – Subject to

Change Based on Public Input 39

Basic Assumptions

-PLUS-

Longer Segments of other corridors with limited service by 2017 – Build Rest Over Time as Revenues Allow

Option #4

Preliminary Concept – Subject to Change Based on Public Input 40

Option #4 – Pros and ConsBasic Assumptions + Longer Segments of all other corridors with limited service by 2017 – Build Rest

Over Time as Revenues Allow

Pros• Does not require new

revenue streams

• Builds out the entire program

• Provides longer sections of each corridor by 2017

• Build out could be accelerated before 2034 if economic conditions improve

Cons• Does not build out entire

program

• Service levels are reduced as compared to original FasTracks plan

• Overall program budget increases

41

Option #5

Build Complete FasTracks Program by 2017 – Seek Additional Revenue Sources

42

Potential New Revenue Sources• New revenue sources will be needed to implement the entire FasTracks

program by 2017. Total cost of program is estimated at $7.9 B. Approaches for new revenue sources include:

– Partner with CDOT for state-wide transportation initiative (Blue Ribbon Panel)

– Monitor and participate in any Regional Transportation Authority that might be formed in the metro area

– Pursue additional Public-Private Partnership funding opportunities

– Optimize RTD’s operating revenues (parking fees, fares, advertising)

– Pursue additional RTD regional revenues– Pursue all available federal transportation grant

revenues 43

Option #5 – Pros and ConsBuild complete FasTracks program by 2017 and

Seek Additional Revenue Sources

Pros• Builds out the entire

program by 2017

• Consistent with the original FasTracks plan

Cons• Would require additional

revenue streams

• Could require legislative approval for revenue measure and public vote

44

What Do You Think?

45

We Want to Know:• Your feedback on each of the options RTD

has presented tonight

• Your input and suggestions on other ideas for RTD to explore

46

Automatic Response System

47

Basic Assumptions

-PLUS-

Segments of other corridors by 2017 – End the Program

Option #1

Preliminary Concept – Subject to Change Based on Public Input 48

Option #1 Input• How supportive would you be of RTD continuing

to analyze this type of option?

• Option #1: Basic Assumptions + Segments of all Other Corridors by 2017 – End the Program

1. Very Supportive2. Somewhat Supportive3. Somewhat Unsupportive4. Very Unsupportive5. Don’t Know

49

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 50

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 51

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 52

Basic Assumptions

-PLUS-

One additional complete corridor by 2017 – End the Program

Option #2

Preliminary Concept – Subject to Change Based on Public Input 53

Option #2 Input• How supportive would you be of RTD continuing

to analyze this type of option?

• Option #2: Basic Assumptions + One Additional Complete Corridor by 2017 – End the Program

1. Very Supportive2. Somewhat Supportive3. Somewhat Unsupportive4. Very Unsupportive5. Don’t Know

54

Option #3Basic Assumptions

-PLUS-

Segments of other corridors by 2017 – Build the Rest Over Time as Revenues Allow

Preliminary Concept – Subject to Change Based on Public Input 55

Option #3 Input• How supportive would you be of RTD continuing

to analyze this type of option?

• Option #3: Basic Assumptions + Sections of Other Corridors by 2017 – Build the Rest Over Time as Revenues Allow

1. Very Supportive2. Somewhat Supportive3. Somewhat Unsupportive4. Very Unsupportive5. Don’t Know

56

Basic Assumptions

-PLUS-

Longer Segments of other corridors with limited service by 2017 – Build Rest Over Time as Revenues Allow

Option #4

Preliminary Concept – Subject to Change Based on Public Input 57

Option #4 Input• How supportive would you be of RTD continuing

to analyze this type of option?

• Option #4: Basic Assumptions + Longer Sections of Other Corridors with Limited Service by 2017 – Build the Rest Over Time as Revenues Allow

1. Very Supportive2. Somewhat Supportive3. Somewhat Unsupportive4. Very Unsupportive5. Don’t Know

58

Option #5

Build Complete FasTracks Program by 2017 – Seek Additional Revenue Sources

59

Option #5 Input• How supportive would you be of RTD continuing

to analyze this type of option?

• Option #5: Build Complete FasTracks Program by 2017 – Seek Additional Revenue Sources

1. Very Supportive2. Somewhat Supportive3. Somewhat Unsupportive4. Very Unsupportive5. Don’t Know

60

Thank You!

Thank you for taking time to help us find solutions for FasTracks.

As it took a regional effort to gain approval for the program, it will take regional cooperation to find solutions for these challenges.

61

Next Steps• September/October – Collect input/opinions from all

Districts • Late October-Q1 2009 – Ongoing meetings with

city/county officials and local government teams • November 6th – Provide summary of input to date to

RTD Board • Mid-November – Conduct public opinion phone

survey, based on input to date • December – Refinement by RTD Board on option(s)

for future implementation of the FasTracks program• Q1 2009 – Collaboration/recommendation from

regional agencies to RTD Board on preferred option for future implementation of the FasTracks program

• End of Q1 2009 – RTD Board adoption of preferred FasTracks implementation plan

62

Next Steps

• NOW – Provide additional feedback and ideas to our FasTracks staff

63