2008 FasTracks Update – Interim Report to DRCOG

2008 FasTracks Update Interim Report to DRCOG

January 2009

2008 FasTracks Update – Interim Report to DRCOG

Page i

Table of Contents

Executive Summary 1.0 Introduction ............................................................................................................... 1 

1.1 Program Overview ................................................................................................... 1 1.2 Summary of 2008 Program Events ......................................................................... 1 1.3 FasTracks Budget (2007 and 2008 Annual Program Evaluation) ........................... 3 1.4 Next Steps ............................................................................................................... 4 

2.0 Status of FasTracks Corridors ................................................................................. 4 2.1 East Corridor ........................................................................................................... 4 2.2 Gold Line Corridor ................................................................................................... 6 2.3 Southeast Corridor Extension .................................................................................. 8 2.4 Southwest Corridor Extension ................................................................................. 8 2.5 I-225 Corridor ........................................................................................................ 11 2.6 North Metro ............................................................................................................ 13 2.7 Denver Union Station ............................................................................................ 13 2.8 Central Corridor Extension .................................................................................... 16 2.9 West Corridor ........................................................................................................ 16 2.10 US 36 BRT—Phase 1 .......................................................................................... 19 2.11 US 36 BRT—Phase 2 .......................................................................................... 19 2.12 Northwest Rail Corridor ....................................................................................... 21 2.13 Maintenance Facilities ......................................................................................... 21 

3.0 FasTracks Changes ................................................................................................ 24 3.1 Summary of Changes ............................................................................................ 24 3.2 Changes Potentially Requiring RTP Amendment .................................................. 24 

Appendix FasTracks Options ...................................................................................................... 26 Public Involvement Efforts ........................................................................................... 27 

List of Figures

Figure 1: FasTracks Plan ............................................................................................. 2 Figure 2: East Corridor ................................................................................................ 5 Figure 3: Gold Line ...................................................................................................... 7 Figure 4: Southeast Corridor ....................................................................................... 9 Figure 5: Southwest Corridor ..................................................................................... 10 Figure 6: I-225 Corridor ............................................................................................. 12 Figure 7: North Metro Corridor ................................................................................... 14 Figure 8: Denver Union Station ................................................................................. 15 Figure 9: Central/CPV Corridor .................................................................................. 17 Figure 10: West Corridor ........................................................................................... 18 Figure 11: US 36 BRT – Phase 2 .............................................................................. 20 Figure 12: Northwest Rail Corridor ............................................................................ 22

2008 FasTracks Update – Interim Report to DRCOG

EXECUTIVE SUMMARY

In 2004, the FasTracks Plan for expanded regional transit service was approved by the voters. Since Plan approval, work on all projects has commenced and progress has been documented in annual reports prepared for DRCOG review and approval. To date, there have been four reports submitted and approved by DRCOG. This year, preparation of the annual report to DRCOG has been delayed pending a decision by the RTD Board concerning potential options for completion of the FasTracks program. These options are being considered due to a need to address challenges encountered in implementation of the FasTracks program that have occurred as a result of downward economic trends. On August 21, 2008, RTD staff presented five potential options to the RTD Board for consideration and in September and October conducted 17 public meetings to gain public and stakeholder input. Since that time, additional study, input, and deliberation has occurred to further narrow these options. An RTD Board decision is anticipated in late March. Following a decision by the RTD Board, preparation of the annual report to DRCOG will commence, with completion anticipated three months later. In the interim, this report, The 2008 Update Interim Report to DRCOG, has been prepared to convey progress made; changes necessary; and the current status of each of the FasTracks corridors and projects. Of primary importance, this report has been prepared and submitted to ascertain and list those changes to the FasTracks program that necessitate amendment to the Regional Transportation Plan (RTP). In order to meet the Cycle 1 RTP amendment schedule, it is necessary to submit the requested plan amendments prior to completion of the full annual report to DRCOG on FasTracks. As further detailed in the following report, the Plan changes that potentially require amendment to the RTP are:

• Central and East Corridors – Change in station location (terminus) from 40th/40th to 38th/Blake.

• East Corridor – Change in station location from Stapleton park-n-Ride to Central Park Boulevard Station; and change in length of corridor from 23.6 to 22.8 miles.

• Gold Line – Change in length of corridor from 11.2 to 10.8 miles. • I-225 – Change in alignment; addition of eighth station (station to be funded either by

the City of Aurora or private development); change in station location from 4th/Abilene to 2nd/Abilene; the Exposition Station has been moved to Florida; and parking at the Iliff Station has increased from 450 to 600 spaces (opening day); 910 spaces (2035).

• North Metro – Change in alignment as a result of RR negotiations; Globeville-Swansea Station replaced by a station located either at the Stock Show Complex or at the Denver Coliseum (RTP amendment not requested in Cycle 1).

None of the changes cited above materially impact corridor costs or the FasTracks Financial Plan. Determining theses changes now will allow DRCOG to process the RTP amendments, which assures consistency with RTD’s plans for the Corridors and allows DRCOG to award Station Area Planning grants to local governments where appropriate.

2008 FasTracks Update – Interim Report to DRCOG

Page 1

1.0 INTRODUCTION

In 2004, the FasTracks Plan (Figure 1) for expanded regional transit service was approved by the voters. Since Plan approval, work on all projects has commenced and progress has been documented in annual reports prepared for DRCOG review and approval. To date, there have been four reports submitted and approved by DRCOG. These include the original 2004 approval and subsequent reports for 2005, 2006, and 2007. This report is intended to serve as an interim report conveying progress made, changes necessary, and the current status of each of the FasTracks corridors and projects. Below is a summary of the program, project changes and status; public involvement efforts; and a description of next steps.

1.1 Program Overview The FasTracks Plan consists of nine rail corridors (new or extended): one bus rapid transit (BRT) corridor; redevelopment of Denver Union Station; and new or expanded bus, commuter rail, and light rail maintenance facilities. At completion the Plan will add 93.3 miles of commuter rail (East, Gold Line, North Metro, and Northwest Rail Corridors); 28.2 miles of light rail (Southeast and Southwest Corridor Extensions, I-225, and West Corridor); and 18 miles of bus rapid transit (BRT).

1.2 Summary of 2008 Program Events By mid-2008, all FasTracks projects were underway. Even in challenging economic times, it has been a productive year. Following is a summary status of each of the FasTracks projects.

• West Corridor Began early construction and reached Guaranteed Maximum Price with contractor: Denver Transit Construction Group

• DUS Received Record of Decision from the Federal Transit Administration

• Gold Line Released Draft Environmental Impact Statement (DEIS)

• East Corridor Ready to release DEIS

• North Metro Determined Preferred Alternative for major corridor elements

• I-225 Determined Preferred Alternative for major corridor elements

• Northwest Rail Completed railroad crossing analysis for quiet zones

2008 FasTracks Update – Interim Report to DRCOG

Page 2

Figure 1: FasTracks Plan

2008 FasTracks Update – Interim Report to DRCOG

Page 3

• US 36 Determined Combined Alternative Identified buildout of HOT/BRT lane in each direction as preferred first construction phase

• Southeast and Southwest Extensions Began environmental processes and held initial public meetings

• Commuter Rail Maintenance Facility Nearing completion of Environmental Assessment

• Bus Maintenance Facility Site selection narrowed to three locations

• Light Rail Maintenance Facility Completed design for expansion of existing facility

• Eagle P3 Project Released Request For Qualifications and received Statements of Qualifications from three strong concessionaire teams pursuing the Public-Private Partnership contract

• Railroad negotiations Reached a preliminary agreement with Union Pacific and have made major progress with BNSF Railway

• Railroad refinements Completed refinements of commuter rail corridors

• FasTracks Implementation Options Public Process Completed 17 public meetings and three regional Local Governments Team meetings to get feedback on future direction for FasTracks

1.3 FasTracks Budget (2007 and 2008 Annual Program Evaluation) In 2007, RTD conducted an Annual Program Evaluation (APE) that indicated an increase in material and labor costs, with a loss in revenue that was reflective of economic trends observed in the Denver metropolitan region, nationally, and internationally. RTD addressed these challenges by instituting changes on both a program and project level, which included changes in technology, delivery options, and financing mechanisms. The results of the 2007 APE and the changes made to the FasTracks program are documented in the RTD 2007 Annual Report to DRCOG on FasTracks that was approved by the DRCOG Board on May 21, 2008. RTD conducted a similar annual evaluation in 2008 that indicated a continued rise in costs, particularly in materials costs, and further decline in sales tax revenue. In response, RTD staff developed several options for completing the FasTracks Plan, which were presented to the RTD Board of Directors for consideration and, ultimately, to

2008 FasTracks Update – Interim Report to DRCOG

Page 4

the public for comment. The options considered; the public involvement process; and the status of these options is detailed in the attached appendix.

1.4 Next Steps It is anticipated that the RTD Board of Directors will select an option to direct staff in completing the FasTracks Plan late in the first quarter of 2009. Prior to that time, the Board will receive recommendations from the Metro Mayor’s Caucus and the results of a public opinion survey (first quarter 2009) to consider in making their decision.

2.0 STATUS OF FASTRACKS CORRIDORS

The corridor descriptions below highlight changes in scope to the corridor projects. Included in each is an overview of the corridor, with a listing of characteristics, areas served, and notable changes.

2.1 East Corridor The East Corridor consists of 22.8 miles of double-track commuter rail from Denver Union Station (DUS) to Denver International Airport (DIA). It serves the Denver communities of Five Points, Cole, Elyria/Swansea, Northeast Park Hill, Stapleton, Gateway, and DIA, as well as northwest Aurora. It also serves to transport passengers arriving and departing from DIA (Figure 2). Significant this year are changes made to the alignment as a result of the railroad negotiation process and the progress made in the Public-Private Partnership procurement. The alignment was refined in early 2008, and the refined alignment was presented to the public in corridor-wide meetings in July. In 2007, the East Corridor was selected for the Federal Transit Administration’s (FTA) Public-Private Partnership Pilot Program (Penta-P). Public-private partnerships are a procurement delivery mechanism that allocates risks and rewards of project development among public agencies and private companies. The Penta-P project offers the opportunity for a streamlined and expedited project development process under the federal New Starts capital funding program. In 2008, the “Eagle P3” project was initiated and on July 30th an Industry Forum was held to provide information to potential concessionaires. Following this, RTD received notice of interest from three industry groups representing potential private sector concessionaire teams. A request for proposal is scheduled to be completed and provided to interested parties in May 2009.

2008 FasTracks Update – Interim Report to DRCOG

Page 5

Figure 2: East Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 6

East Corridor Summary Length: 22.8 miles Mode: Commuter Rail/EMU Method of Delivery: Design-Build-Finance-Operate-Maintain (DBFOM); P3 Status: Draft EIS scheduled for release early 2009 Tasks Remaining: Final EIS; Record of Decision (ROD); P3 procurement; Design, Construction, Operation, and Maintenance Scheduled Completion: 2015 Notable Changes:

• The alignment has been refined, as a result of railroad negotiations that necessitated this change. In particular, the alignment was refined from Denver Union Station to Kearney Street.

• The East Corridor no longer shares any portion of the alignment with the North Metro Corridor.

• The 40th/40th Station has been moved to 38th/Blake. • The Central Park Boulevard Station replaces the existing Stapleton park-n-Ride.

2.2 Gold Line Corridor The Gold Line is 10.8 miles of mostly double-track commuter rail from DUS to Ward Road, which will link downtown Denver with the growing western areas of the region and terminate at Ward Road in Wheat Ridge. It will serve the City and County of Denver, Adams County, the City of Arvada, and the City of Wheat Ridge (Figure 3). In 2007, the Gold Line was selected for the Federal Transit Administration’s (FTA) Public-Private Partnership Pilot Program (Penta-P). Public-private partnerships are a procurement delivery mechanism that allocates risks and rewards of project development among public agencies and private companies. The Penta-P project offers the opportunity for a streamlined and expedited project development process under the federal New Starts capital funding program. In 2008, the “Eagle P3” project was initiated and on July 30th an Industry Forum was held to provide information to potential concessionaires. Following this, RTD received notice of interest from three industry groups representing potential private sector concessionaire teams. A request for proposal is scheduled to be completed and provided to interested parties in May 2009.

2008 FasTracks Update – Interim Report to DRCOG

Page 7

Figure 3: Gold Line

2008 FasTracks Update – Interim Report to DRCOG

Page 8

Gold Line Summary Length: 10.8 miles (3 miles from DUS to Pecos are shared with the Northwest Rail Corridor) Mode: Commuter Rail/EMU Method of Delivery: Design-Build-Finance-Operate-Maintain (DBFOM); P3 Status: Draft EIS in final review Tasks Remaining: Final EIS; Record of Decision (ROD); P3 procurement; Design, Construction, Operation, and Maintenance Scheduled Completion: 2015 Notable Changes:

• The alignment has been refined, as a result of railroad negotiations that necessitated this change.

• The length of the corridor has changed from 11.2 to 10.8 miles due to the change in alignment.

2.3 Southeast Corridor Extension The Southeast Corridor Extension is 2.3 miles in length and extends from the existing Lincoln Station south to RidgeGate Parkway (under construction). This extension will serve the South Denver Metropolitan area including Lone Tree, Highlands Ranch, and northern Douglas County (Figure 4). Southeast Corridor Extension Summary Length: 2.3 miles Mode: Light Rail Method of Delivery: Design-Build (DB) Status: Environmental Evaluation (EE) and Basic Engineering (BE) began Summer 2008 with initial public meetings held in October 2008 Tasks Remaining: Completion of EE/BE; Design and Construction; Operation and Maintenance Scheduled Completion: 2015 Notable Changes:

• Early procurement of light rail vehicles. • No other notable changes.

2.4 Southwest Corridor Extension The Southwest Corridor Extension is 2.5 miles in length and extends from the existing Mineral Station south and east to Lucent Boulevard. The extension will serve Littleton, Highlands Ranch, and Douglas County (Figure 5).

2008 FasTracks Update – Interim Report to DRCOG

Page 9

Figure 4: Southeast Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 10

Figure 5: Southwest Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 11

Southwest Corridor Extension Summary Length: 2.5 miles Mode: Light Rail Method of Delivery: Design-Build (DB) Status: Environmental Evaluation (EE) and Basic Engineering (BE) began Summer 2008 with initial public meetings held in October 2008 Tasks Remaining: Completion of EE/BE; Design and Construction; Operation and Maintenance Scheduled Completion: 2015 Notable Changes:

• Early procurement of light rail vehicles. • No other notable changes.

2.5 I-225 Corridor The FasTracks I-225 Corridor is a 10.5 mile light rail extension from the existing Nine Mile Station through the Aurora City Center and the Anschutz Medical Campus and Fitzsimons Life Sciences District to a transfer station with the East Corridor at Peoria/Smith (Figure 6). I-225 Corridor Summary Length: 10.5 miles Mode: Light Rail Method of Delivery: Design-Build (DB) Status: Environmental Evaluation (EE) and Preliminary Engineering (PE) in process Tasks Remaining: Completion of EE; Design and Construction; Operation and Maintenance Scheduled Completion: 2015 Notable Changes:

• The alignment has been refined with the preferred alternative located along the east side of I-225 from Nine Mile to Exposition rather than in the I-225 median; a flyover at Colfax has been eliminated; and the existing I-225 13th Avenue underpass will be utilized for the alignment.

• An eighth, new station, with 250 parking spaces has been added at 13th Avenue. Parking at this station is not additional parking, but rather, it replaces a portion of the parking spaces originally planned for the Colfax Station. The remainder of that parking has been redistributed among the 2nd and Abilene and Iliff Avenue Stations with no net change in number of spaces provided. Funding for the 13th Avenue Station will be through the City of Aurora or private development.

• Several station locations have changed. See below. - The Exposition Station (no parking) has been moved to Florida (no parking). - The 4th/Abilene Station (200 spaces) has been moved to 2nd/Abilene (200

spaces). - The Fitzsimons South Station (no parking) has been renamed and is now the

Colfax Station (no parking). - The Fitzsimons Commons Station (no parking) is now named the Montview

Station (no parking).

2008 FasTracks Update – Interim Report to DRCOG

Page 12

Figure 6: I-225 Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 13

2.6 North Metro The North Metro Corridor begins at DUS and extends north 18.7 miles to 162nd Avenue traversing the jurisdictions of Denver, Commerce City, Adams County, Northglenn, and Thornton. The alignment follows the BNSF rail alignment to near 54th Avenue, then further north it joins the UPRR Boulder Branch right-of-way (Figure 7). The RTD Board approved commuter rail DMU technology in late 2007, but recent fuel price increases have caused the corridor project team to reinvestigate electric multiple units (EMU). North Metro Corridor Summary Length: 18.7 miles Mode: Commuter Rail/DMU Method of Delivery: Design-Bid-Build Status: The Draft EIS is in process and is scheduled for release in early March 2009. Tasks Remaining: Completion of Draft EIS; Final EIS; obtaining a ROD; Final Design; Construction; Operation and Maintenance Scheduled Completion: 2015 Notable Changes:

• The alignment has been refined, as a result of railroad negotiations that necessitated this change.

• The Globeville-Swansea Station, which was located on the UPRR alignment, will be replaced by a station adjacent to the BNSF rail alignment. This station will be located either at the Stock Show Complex or at the Denver Coliseum.

• The North Metro Corridor no longer shares any portion of the alignment with the East Corridor.

2.7 Denver Union Station Development of Denver Union Station (DUS) is proceeding as a public-private partnership (P3), following selection of a Master Developer, Union Station Neighborhood Company (USNC), in late 2006. Contract negotiations with the Master Developer are ongoing. They will be responsible for private development of the DUS site and for oversight of the design and construction of public spaces (Figure 8). In 2008, the City and County of Denver created, by ordinance, the Denver Union Station Project Authority (DUSPA). It includes eleven voting members and two non-voting members. Voting members are comprised of six members appointed by the Mayor of Denver, two members from RTD, one from CDOT, one from DRCOG, and one from the Denver Union Station Metropolitan District. The DUSPA is responsible for receipt and distribution of project funding and for contracting with the design-builder for all transit infrastructure. Also in 2008, the Downtown Development Authority was created to assess sales tax within their boundary and the Denver Union Station Metropolitan District was created to levy property taxes.

2008 FasTracks Update – Interim Report to DRCOG

Page 14

Figure 7: North Metro Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 15

Figure 8: Denver Union Station

2008 FasTracks Update – Interim Report to DRCOG

Page 16

Denver Union Station Summary Length: NA Mode: NA Method of Delivery: Design-Build (DB); P3 Status: A ROD was issued on October 17, 2008. Tasks Remaining: Final Design; Construction; Operation and Maintenance Scheduled Completion: 2009 (for Final Design of LRT, CRT, and Bus Facilities, and LRT Systems Design): 2010 (for construction of LRT); 2012 (for construction of CRT) Notable Changes:

• Creation of DUSPA • Creation of Downtown Development Authority • Creation of Denver Union Station Metropolitan District • Completed 30% design to begin negotiating a design-build contract

2.8 Central Corridor Extension The Central Corridor Extension begins at the 30th and Downing Station and extends north approximately 0.8 miles to the 38th/Blake Station. This station will serve as the terminus for the Central Corridor, as well as a transfer hub to the East Corridor (Figure 9). Central Corridor Extension Summary Length: 0.8 miles (approximate) Mode: Light Rail Method of Delivery: Design-Bid-Build Status: Preliminary Engineering underway Tasks Remaining: Final Design and Construction; Operation and Maintenance Scheduled Completion: 2015 Notable Changes:

• Change in terminus from 40th/40th to 38th/Blake. • No other notable changes.

2.9 West Corridor The West Corridor originates at DUS and extends west for 12.1-miles ending at the Jefferson County Government Center. The areas served include the Auraria Campus, Pepsi Center/Elitch Gardens, Invesco field at Mile High, west Denver; the Lakewood, Lakewood Industrial Park, Denver Federal Center, Red Rocks Community College, Jefferson County Government Center, and the City of Golden. This corridor is furthest along in the development and construction process, with completion of construction scheduled for 2012 and opening day in 2013 (Figure 10).

2008 FasTracks Update – Interim Report to DRCOG

Page 17

Figure 9: Central /CPV Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 18

Figure 10: West Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 19

West Corridor Summary Length: 12.1 miles Mode: Light Rail Method of Delivery: Design-Bid-Build Status: Transitional Period Construction based on Letter of No Prejudice (LONP) and FTA guidelines. A Full Funding Grant Agreement (FFGA) is scheduled for execution on January 16, 2009, and full notice to proceed in expected in April 2009. Tasks Remaining: Receipt of FFGA and Construction; Operation and Maintenance Scheduled Completion: 2012 (construction complete); 2013 (opening day) Notable Changes:

• Release of FFGA in January 2009. • Construction began in April 2008.

2.10 US 36 BRT—Phase 1 This project includes construction of the US 36/McCaslin park-n-Ride and pedestrian bridge (completed in 2006); the US 36/Church Ranch park-n-Ride and north and southbound bus slip ramps (completed in 2007); a shared parking structure at the Arista Development in Broomfield (completed in fall 2007); and construction of a relocated Broomfield park-n-Ride (scheduled for completion in spring 2010). US 36 BRT – Phase I Summary Length: Not Applicable Mode: Bus Rapid Transit Method of Delivery: Design-Bid-Build Status: Construction underway (to be completed late 2009) Tasks Remaining: Completion of Construction; Operation and Maintenance Scheduled Completion: Spring 2010 Notable Changes:

• This phase will be completed with the conclusion of design and construction of the Broomfield pedestrian bridge and slip ramps in 2010.

2.11 US 36 BRT—Phase 2 This project consists of 18 miles of dedicated BRT lanes in US 36 that extend from DUS to the Table Mesa park-n-Ride. It also includes construction of a pedestrian bridge at the Table Mesa park-n-Ride and a new eastbound bus slip ramp on the south side of US 36. Senate Bill 1 funds that will be used to assist in funding construction of the pedestrian bridge have been received by RTD on behalf of the US 36 Mayors and Commissioners Coalition (MCC). RTD, the US 36 MCC, and CDOT are exploring funding options for the BRT lanes as part of the ongoing EIS process. The Preferred Alternative for US 36 includes adding one lane each direction between Federal and Table Mesa. The new lane each direction will be used as a HOT lane, to include buses, carpools and vanpools and single occupant vehicles if they pay a toll (Figure 11).

2008 FasTracks Update – Interim Report to DRCOG

Page 20

Figure 11: US 36 BRT – Phase 2

2008 FasTracks Update – Interim Report to DRCOG

Page 21

US 36 BRT – Phase 2 Summary Length: 18 miles Mode: Bus Rapid Transit (BRT) Method of Delivery: Design-Bid-Build Status: Final EIS effort in process (to be phased with the ROD for the first phase issued in at the end of 2009) Tasks Remaining: Completion of EIS/PE; Final Design and Construction (to be implemented in phases); Operation and Maintenance Scheduled Completion: To be determined based on CDOT, RTD, and US 36 MCC agreement on final US 36 phased alternatives. Notable Changes:

• RTD, CDOT, and a Preferred Alternative Committee (PAC) identified a Combined Alternative and a phased process for completing the FEIS and ROD.

• No other notable changes.

2.12 Northwest Rail Corridor The Northwest Rail Corridor consists of 41 miles of commuter rail (DMU) that originates at DUS and extends northwest to downtown Longmont (1st and Terry). Areas served include Northwest Denver, Adams County, Westminster, Broomfield, Louisville, Boulder, Boulder County, and Longmont. Most significant in 2008, is the BNSF determination to construct the corridor within their ROW (Figure 12). Northwest Rail Corridor Summary Length: 41 miles (3 miles from DUS to Pecos are shared with the Gold Line) Mode: Commuter Rail/DMU Method of Delivery: The BNSF Railway will construct the corridor; Design-Bid-Build will be used to construct the park-n-Rides. Status: EE and PE underway Tasks Remaining: Final Design and Construction; Operation and Maintenance Scheduled Completion: 2014 Notable Changes:

• Determination that BNSF will construct the corridor. • No other notable changes.

2.13 Maintenance Facilities This includes facilities for light rail, bus, and commuter rail. Light rail maintenance will be accommodated by an expansion of the existing Elati and Mariposa Facilities; and the commuter rail facility will accommodate both EMU and DMU. Two sites are currently being considered. An evaluation of the need for expansion of bus maintenance capacity indicated that it was not needed until 2020. Therefore, the planning process for this facility will be initiated in 2013, with completion scheduled for 2020.

2008 FasTracks Update – Interim Report to DRCOG

Page 22

Figure 12: Northwest Rail Corridor

2008 FasTracks Update – Interim Report to DRCOG

Page 23

Light Rail Maintenance Facility Summary: This project involves expansion of the existing Elati Facility to include additional parts storage capacity; additional power supply into and for the system elements for the added light rail vehicles to be stored at the site; modifications to the drainage system; added tracks; yard lighting; walks; and access drive improvements. Associated with the expansion of the Elati Facility is the expansion of the Mariposa Facility where RTD conducts heavy maintenance on light rail vehicles. Length: NA Mode: NA Method of Delivery: Design-Bid-Build Status: Final Design underway Tasks Remaining: Final Design (to be completed early 2009) and Construction (to begin summer 2009); Operation and Maintenance Scheduled Completion: 2012 Notable Changes:

• The budget for the project was reduced with the decision to expand the existing Elati Facility rather than construct a new facility.

• No other notable changes. Commuter Rail Maintenance Facility Summary: The facility is designed to accommodate 108 vehicles, both EMU and DMU and the shop is approximately 250,000 square-feet in size. The site plan includes storage, a repair shop, a maintenance-of-way shop and laydown, and central control/dispatch. Length: NA Mode: NA Method of Delivery: Design-Build-Finance-Operate-Maintain (DBFOM; part of Penta-P) Status: EA underway (to be completed mid-2009) Tasks Remaining: Design and Construction; Operation and Maintenance Scheduled Completion: 2014 Notable Changes:

• Several sites are under consideration for the CRMF; however, the preferred site is at Platte Division Bus Maintenance Facility.

• No other notable changes at this time. Bus Maintenance Facility Summary: Current projections are that by 2020 RTD will need additional bus maintenance facility capacity. However, if the Platte Division Bus Maintenance Facility is selected for the Commuter Rail Maintenance Facility, the necessity to relocate will create the need for a new facility at an earlier date. Length: NA Mode: NA Method of Delivery: Design-Bid-Build Status: Will begin 2013 Tasks Remaining: Environmental and Preliminary Engineering process; Final Design and Construction; Operation and Maintenance Scheduled Completion: 2020 Notable Changes:

• Scheduled for completion in 2020 based on need. • No other notable changes at this time.

2008 FasTracks Update – Interim Report to DRCOG

Page 24

3.0 FASTRACKS CHANGES

The FasTracks Program had undergone several changes throughout 2008 with additional changes to follow in 2009. Changes in the FasTracks Financial Plan can be expected, as well as additional corridor changes following the selection of an option for completing the FasTracks Plan. Below is a summary of the changes noted to date followed by a listing of changes that will likely necessitate amendment to the Regional Transportation Plan (RTP).

3.1 Summary of Changes Several corridors and projects experienced no changes outside of the normal progress of project development. These included the Southeast and Southwest Corridor Extensions, the West Corridor, US 36 BRT – Phase I and Phase II, and the Light Rail Maintenance Facility. Denver Union Station underwent some organizational changes. Minor changes were made to several others including the Gold Line and Northwest Rail (to accommodate slight alignment changes as a result of RR negotiations), while others experienced greater changes such as changes in station locations and/or alignment. Those with changed station locations or the addition of new stations include the East Corridor, Central Corridor, North Metro, and I-225. Finally, locations for the Commuter Rail and Bus Maintenance Facilities remain undecided at this time.

3.2 Changes Potentially Requiring RTP Amendment Several corridors have documented changes that will likely require an amendment to the RTP. These include the following:

• Central and East Corridors – Change in station location (terminus) from 40th/40th to 38th/Blake.

• East Corridor – Change in station location from Stapleton park-n-Ride to Central Park Boulevard Station; and change in length of corridor from 23.6 to 22.8 miles.

• Gold Line – Change in length of corridor from 11.2 to 10.8 miles. • I-225 – Change in alignment; addition of eighth station (station to be funded

either by the City of Aurora or private development); change in station location from 4th/Abilene to 2nd/Abilene; the Exposition Station has been moved to Florida; and parking at the Iliff Station has increased from 450 to 600 spaces (opening day); 910 spaces (2035).

• North Metro – Change in alignment as a result of RR negotiations; Globeville-Swansea Station replaced by a station located either at the Stock Show Complex or at the Denver Coliseum (RTP amendment not requested in Cycle 1).

2008 FasTracks Update – Interim Report to DRCOG

Page 25

APPENDIX FasTracks Options and Public Involvement Efforts

2008 FasTracks Update – Interim Report to DRCOG

Page 26

FasTracks Options The Regional Transportation District is among the many public entities across the country facing challenges as it strives to keep operations and projects on track during these sluggish economic times. RTD’s FasTracks transit expansion program continues to be impacted by slumping sales tax revenues and increased construction materials costs. As a result of these ongoing circumstances, on August 21, 2008, RTD staff presented five potential options to the RTD Board for consideration with regard to FasTracks program implementation: All five of the options presented include the following: Basic Assumptions:

• Complete environmental documentation and basic engineering for all projects • Purchase all railroad rights-of-way • Complete projects that are already in construction, including West Corridor and

Phase 1 of US 36 Bus Rapid Transit • Complete Denver Union Station and all maintenance facilities to support the

system • Complete Gold Line and East Corridor to retain eligibility for $1 billion in federal

funds Options:

• Option 1 Complete the Basic Assumptions plus sections of some corridors by 2017, then end the build-out of FasTracks.

• Option 2

Complete the Basic Assumptions plus one additional complete corridor by 2017, then end the build-out of FasTracks. (The RTD Board subsequently eliminated this option from further consideration as described below.)

• Option 3 Complete the Basic Assumptions plus sections of some corridors by 2017, then implement the full program over an extended schedule by 2034 or sooner, as revenues allow.

• Option 4 Complete the Basic Assumptions plus longer sections of some corridors with limited service by 2017 and implement the rest over an extended schedule by 2034 or sooner, as revenues allow.

• Option 5 Seek additional revenue sources to build the complete FasTracks program approved by voters by 2017.

2008 FasTracks Update – Interim Report to DRCOG

Page 27

Public Involvement Efforts Since the five options were presented at the August 21, 2008, RTD Board meeting, the FasTracks Team conducted extensive public and stakeholder outreach to seek input on the best regional solution for moving the FasTracks program forward. This public involvement effort includes the following key components: Public Meetings: RTD hosted a series of 17 public meetings throughout the Regional Transportation District between September 25, and October 23, 2008. Stakeholders and the general public were encouraged to attend one or more meetings. The meetings were conducted using an electronic response system in order to get feedback on the options and to determine which options warranted further analysis. The meetings drew almost 600 attendees. Feedback on the five options indicated that respondents were generally unsupportive or very unsupportive of Options 1 and 2. Based on the overwhelming lack of support for Option 2, the RTD Board voted on November 6, to eliminate it from further analysis or consideration. Response to Options 3 and 4 approximated a 50-50 split, with 46.2% supportive and 52.6% non-supportive of Option 3; and 43.4% supportive and 55.7% non-supportive of Option 4. Option 5 garnered the most support, with 73% of respondents supportive to very supportive of seeking additional revenue sources to build the complete FasTracks program by 2017. Regional Local Governments Team Meetings In late October, RTD hosted three regionally-based Local Governments Team-style meetings for local elected officials and staff members and other key stakeholders. FasTracks corridors were combined based on region, with both elected officials and staff encouraged to go to those meetings. The meetings were an opportunity for RTD to share public feedback on options for moving forward with FasTracks, and discuss with community leaders how to best approach a regional solution for the challenges we face.

Another series of Local Governments Team meetings will be scheduled in early 2009 to coincide with progress from the Metro Mayors Caucus “FasTracks Futures” task force. Equity Workshop On November 11, the RTD Board held a workshop open to jurisdiction stakeholders to present and discuss a variety of equity scenarios illustrating different potential approaches to apportioning the FasTracks budget by corridor project. This information was also presented to the Metro Mayors and Commissioners FasTracks Task Force on Monday, November 17.

2008 FasTracks Update – Interim Report to DRCOG

Page 28

MMC Taskforce To support RTD in their efforts, the Metro Mayors Caucus (MMC) has created a short-term Task Force of elected officials, RTD Board members, and key members of the Business and Environmental communities. The Task Force is looking at all options for delivering FasTracks equitably along all corridors based on what was presented to voters in 2004. Their stated goals are to:

1. Critically examine the FasTracks program, financially and programmatically 2. Based on findings, develop and evaluate equitable alternatives and options 3. Recommend an approach that maximizes deliverables for the region

The Task Force has met bi-weekly since October 20 and has committed to providing a recommendation to the RTD Board in early 2009. In addition, RTD has hosted a series of workshops for the Task Force designed to provide thorough insight into the variety of elements that compose the FasTracks program, including the financial model, ridership, and others.