Upload
aztec-mayan
View
5
Download
0
Embed Size (px)
DESCRIPTION
Resources Management
Citation preview
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 1/29
CRITICAL PATH METHOD 3
KAEA 4165Construction Management and Technology
Dr. Tan Chee Ghuan
1
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 2/29
Resource Management
• The most important resources: people, machines,
materials and money.
• If these resources are available in abundance, then the
project could be accelerated to achieve shorter projectduration.
• If these resources are severely limited, then the result
more likely will be a delay in the project completion
time.
• In general, from a scheduling perspective, projects
can be classified as either time constrained or
resource constrained.2
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 3/29
Resource Leveling
• Time constrained project - project completion time cannot be delayed even if additional resources are required.
However, the additional resource usage should be no
more than what is absolutely necessary.
•The primary focus purposes of scheduling in timeconstrained projects is to improve resource utilization.
This process is called resource leveling.
• It applies when it is desired to reduce the hiring and firing
of resources and to smooth the fluctuation in the dailydemand of a resource.
3
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 4/29
Resource Leveling
• In this case, resources are not limited and project duration
is not allowed to be delayed.
• The objective in this case is to shift non-critical activities
of the original schedule, within their float times so that a
better resource profile is achieved.
4
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 5/29
Resource Scheduling
• Resource constrained project - the level ofresource availability cannot be exceeded.
• In those situations where resources are
inadequate, project delay is acceptable, but the
delay should be minimal.
• The focus of scheduling in these situations is to
prioritize and allocate resources in such a manner
that there is minimal project delay.• However, it is also important to ensure that the
resource limit is not exceeded and the technical
relationships in the project network are respected.5
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 6/29
Resource Scheduling
6
Shortage of resources is a major challenge for construction projects. i.e.
number of skilled labor is limited, a related equipment has to be returned
as soon as possible, a limited require our special consideration.Scheduling under these resource constraints becomes a complex
problem, particularly when more than one resource is limited.
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 7/29
Resource Scheduling
7
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 8/29
Example 1: Resource Leveling
Critical path:A-C-F-H-K
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 9/29
Critical path:A-C-F-H-K
Example 1: Resource Leveling
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 10/29
Activity Duration Total Float/Slack Resource HoursNeeded Per Week
Total Resources Required
A 5 0 6 30
B 4 1 2 8
C 5 0 4 20
D 6 3 3 18
E 6 1 3 18
F 6 0 2 12
G 4 3 4 16
H 7 0 3 21
I 5 3 4 20
J 3 5 2 6
K 5 0 5 25 Total 194
Example 1: Resource Leveling
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 11/29
Example 1: Resource Leveling
• On day 10 the required resource hours is 10
• If project is budgetted for up to 10 resource units per day, then it is
acceptable.
Day 10
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 12/29
Example 1: Resource Leveling
• How if the project is limit to 9 resources hour?
• Activity C, D, and E are all scheduled on this day and have require 4, 3, and
3 hours respectively.
6
2
4
3
4
4
2
3
3
2
5
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 13/29
Which activity should be adjusted?
• C is on the critical path
• E has 1 day slack
• D has 3 days of slack (we can split the activity)
Example 1: Resource Leveling
6
2
4
3
2
3
3
4
3
Critical path:A-C-F-H-K
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 14/29
Example 2: Resource LevelingQuestion:
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 15/29
Solution:
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 16/29
Activity M has a free float of 7 weeks.
Shifting activity M by 7 weeks will reduce
the peak usage of the resource on weeks
10 and 11 and increase the usage onweeks 17 and 18. Also, shifting activity M
will give chance for preceding activities to
be shifted.
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 17/29
Activity J can be shifted by 6, however it
has 8 weeks free float. By shifting activity
J, the free float of both activities E and F
are changed.
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 18/29
Shift activity L by 2 weeks to optimize the
resource usage. The free float of activity
will be changed to 2 weeks.
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 19/29
• Next, shift activity E by 10 weeks to
improve the resource usage.
• Shift activity H by 2 weeks.
• Finally, shift activity F by 1 week.
Resource histogram after leveling
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 20/29
Question:
• Resource limit is set at 8 hourly units per day. Display the
amount of resources required as a function of time.
A
B D E
CF
Example 3: Resource Scheduling
Activity Resource Duration ES Slack LF
A 6 4 0 0 4B 2 1 4 0 5
C 2 3 4 4 11
D 7 4 5 0 9
E 3 2 9 0 11
F 6 1 11 0 12
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 21/29
A
B D E
C F
Activity Resource Duration ES Slack LF
A 6 4 0 0 4
B 2 1 4 0 5
C 2 3 4 4 11
D 7 4 5 0 9
E 3 2 9 0 11
F 6 1 11 0 12
Project delay 2
days due to
resource limitation
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 22/29
Rearrange activities
within their slack tocreate a more level
profile. Splitting C
creates a more level
project.
Project delay 2days due to
resource limitation
E l 4 R S h d li
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 23/29
Example 4: Resource SchedulingQuestion:• A construction project is presented using an AOA as shown with the
duration and number of workers required to complete each activity.Determine the critical path and the project duration. If only 11workers are available for this project, workout the minimum durationrequired to complete the project using the serial method forallocating the workers. Make use of the table below.
1
4
2 5
7
3
8
6
2
6
3
5
4
5
3
4
4
5
4
6
4
6
4
4
workers
weeks
Solution:
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 24/29
Solution:
1
4
2 5
7
3
8
6
2 34
3
4
4
4
40 2
2 6
6 10
2 6
6 9
0 3
3 7
7 11
ET EF
LS LF
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 25/29
Priority Rules:
1. Critical Paths (zero
float)
2. Earliest Start
3. Least Float
4. Largest No. of
Resource - week
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 26/29
Priority Rules:
1. Critical Paths (zero float)
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 27/29
Priority Rules:
1. Critical Paths (zero float)
2. Earliest Start
3. Least Float
4. Largest No. of Resource
- week
CHECK DEPENDENCY PATH!!
Example 5 Resource Scheduling
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 28/29
Example 5: Resource SchedulingQuestion:• Resource M limited to 5, resource L limited to 8.
• Calculate the activity times and identify the critical path.
• Produce a scheduled start date for each activity based on the resourcesloading diagrams for both M and L which do not exceed the resourceslimitations. Use the priority sorting of early start – total float inpreparing the resource loading diagrams
Activity Duration
(Weeks)
Resource requirement
M L
A 8 2 2
B 7 4 2
C 6 3 2
D 8 4 2
E 6 4 -
F 8 - 5
G 6 3 -
H 7 - 4
I 9 4 -
J 3 - 4
E l 5 R S h d li
7/21/2019 Resources Management
http://slidepdf.com/reader/full/resources-management-56d9a34011d21 29/29
Example 5: Resource Scheduling
Given:
A
C
B D
E G
I
F
H
J