29
7/21/2019 Resources Management http://slidepdf.com/reader/full/resources-management-56d9a34011d21 1/29 CRITICAL PATH METHOD 3 KAEA 4165 Construction Management and Technology Dr. Tan Chee Ghuan 1

Resources Management

Embed Size (px)

DESCRIPTION

Resources Management

Citation preview

Page 1: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 1/29

CRITICAL PATH METHOD 3

KAEA 4165Construction Management and Technology

Dr. Tan Chee Ghuan

1

Page 2: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 2/29

Resource Management

• The most important resources: people, machines,

materials and money.

• If these resources are available in abundance, then the

project could be accelerated to achieve shorter projectduration.

• If these resources are severely limited, then the result

more likely will be a delay in the project completion

time.

• In general, from a scheduling perspective, projects

can be classified as either time constrained  or

resource constrained.2

Page 3: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 3/29

Resource Leveling

• Time constrained project - project completion time cannot be delayed even if additional resources are required.

However, the additional  resource usage  should be no

more than what is absolutely necessary. 

•The primary focus purposes of scheduling in timeconstrained projects is to improve resource utilization.

This process is called resource leveling. 

• It applies when it is desired to reduce the hiring and firing

of resources and to smooth the fluctuation  in the dailydemand of a resource.

3

Page 4: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 4/29

Resource Leveling

• In this case, resources are not limited and project duration

is not allowed to be delayed.

• The objective in this case is to shift non-critical activities

of the original schedule, within their float times so that a

better resource profile is achieved.

4

Page 5: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 5/29

Resource Scheduling

• Resource constrained project  - the level ofresource availability cannot be exceeded.

• In those situations where resources are

inadequate, project delay is acceptable, but the

delay should be minimal.

• The focus of scheduling in these situations is to

prioritize and allocate resources in such a manner

that there is minimal project delay.• However, it is also important to ensure that the

resource limit is not exceeded and the technical

relationships in the project network are respected.5

Page 6: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 6/29

Resource Scheduling

6

Shortage of resources is a major challenge for construction projects. i.e.

number of skilled labor is limited, a related equipment has to be returned

as soon as possible, a limited require our special consideration.Scheduling under these resource constraints becomes a complex

problem, particularly when more than one resource is limited.

Page 7: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 7/29

Resource Scheduling

7

Page 8: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 8/29

Example 1: Resource Leveling

Critical path:A-C-F-H-K

Page 9: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 9/29

Critical path:A-C-F-H-K

Example 1: Resource Leveling

Page 10: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 10/29

Activity  Duration  Total Float/Slack   Resource HoursNeeded Per Week  

Total Resources Required 

A  5  0  6  30 

B  4  1  2  8 

C  5  0  4  20 

D  6  3  3  18 

E  6  1  3  18 

F  6  0  2  12 

G  4  3  4  16 

H  7  0  3  21 

I  5  3  4  20 

J  3  5  2  6 

K   5  0  5  25 Total  194 

Example 1: Resource Leveling

Page 11: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 11/29

Example 1: Resource Leveling

• On day 10 the required resource hours is 10

• If project is budgetted for up to 10 resource units per day, then it is

acceptable.

Day 10

Page 12: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 12/29

Example 1: Resource Leveling

• How if the project is limit to 9 resources hour?

•  Activity C, D, and E are all scheduled on this day and have require 4, 3, and

3 hours respectively.

2

4

Page 13: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 13/29

Which activity should be adjusted?

• C is on the critical path

• E has 1 day slack

• D has 3 days of slack (we can split the activity)

Example 1: Resource Leveling

2

4

Critical path:A-C-F-H-K

Page 14: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 14/29

Example 2: Resource LevelingQuestion:

Page 15: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 15/29

Solution:

Page 16: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 16/29

 Activity M has a free float of 7 weeks.

Shifting activity M by 7 weeks will reduce

the peak usage of the resource on weeks

10 and 11 and increase the usage onweeks 17 and 18. Also, shifting activity M

will give chance for preceding activities to

be shifted.

Page 17: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 17/29

 Activity J can be shifted by 6, however it

has 8 weeks free float. By shifting activity

J, the free float of both activities E and F

are changed.

Page 18: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 18/29

Shift activity L by 2 weeks to optimize the

resource usage. The free float of activity

will be changed to 2 weeks.

Page 19: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 19/29

• Next, shift activity E by 10 weeks to

improve the resource usage.

• Shift activity H by 2 weeks.

• Finally, shift activity F by 1 week.

Resource histogram after leveling

Page 20: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 20/29

Question:

• Resource limit is set at 8 hourly units per day. Display the

amount of resources required as a function of time.

 A

B D E

CF

Example 3: Resource Scheduling

Activity Resource Duration ES Slack LF

 A 6 4 0 0 4B 2 1 4 0 5

C 2 3 4 4 11

D 7 4 5 0 9

E 3 2 9 0 11

F 6 1 11 0 12

Page 21: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 21/29

 A

B D E

C F

Activity Resource Duration ES Slack LF

 A 6 4 0 0 4

B 2 1 4 0 5

C 2 3 4 4 11

D 7 4 5 0 9

E 3 2 9 0 11

F 6 1 11 0 12

Project delay 2

days due to

resource limitation

Page 22: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 22/29

Rearrange activities

within their slack tocreate a more level

profile. Splitting C

creates a more level

project.

Project delay 2days due to

resource limitation

E l 4 R S h d li

Page 23: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 23/29

Example 4: Resource SchedulingQuestion:• A construction project is presented using an AOA as shown with the

duration and number of workers required to complete each activity.Determine the critical path and the project duration. If only 11workers are available for this project, workout the minimum durationrequired  to complete the project using the serial method forallocating the workers. Make use of the table below.

1

4

2 5

7

3

8

6

2

6

3

5

4

5

3

4

4

5

4

6

4

6

4

4

workers

weeks

Solution:

Page 24: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 24/29

Solution:

1

4

2 5

7

3

8

6

2 34

3

4

4

4

40 2

2 6

6 10

2 6

6 9

0 3

3 7

7 11

ET EF

LS LF

Page 25: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 25/29

Priority Rules:

1. Critical Paths (zero

float)

2. Earliest Start

3. Least Float

4. Largest No. of

Resource - week

Page 26: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 26/29

Priority Rules:

1. Critical Paths (zero float)

Page 27: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 27/29

Priority Rules:

1. Critical Paths (zero float)

2. Earliest Start

3. Least Float

4. Largest No. of Resource

- week

CHECK DEPENDENCY PATH!!

Example 5 Resource Scheduling

Page 28: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 28/29

Example 5: Resource SchedulingQuestion:• Resource M limited to 5, resource L limited to 8.

•  Calculate the activity times and identify the critical path.

• Produce a scheduled start date for each activity based on the resourcesloading diagrams for both M and L which do not exceed the resourceslimitations. Use the priority sorting of early start  –  total float  inpreparing the resource loading diagrams

Activity Duration

(Weeks)

Resource requirement

M L

A 8 2 2

B 7 4 2

C 6 3 2

D 8 4 2

E 6 4 -

F 8 - 5

G 6 3 -

H 7 - 4

I 9 4 -

J 3 - 4

E l 5 R S h d li

Page 29: Resources Management

7/21/2019 Resources Management

http://slidepdf.com/reader/full/resources-management-56d9a34011d21 29/29

Example 5: Resource Scheduling

Given:

A

C

B D

E G

I

F

H

J