REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 11.06.22 Presentation by: Mitja Kosec Project Manager Zagreb , 9 th November 2009 CHALLENGES OF THE AGENCY OF REPUBLIC OF SLOVENIA FOR THE MANAGEMENT OF PUBLIC RAILWAY INFRASTRUCTURE INVESTMENT

REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

Embed Size (px)

Citation preview

Page 1: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

118.04.23

Presentation by: Mitja Kosec – Project Manager

Zagreb , 9th November 2009

CHALLENGES OF THE

AGENCY OF REPUBLIC OF SLOVENIA FOR THE MANAGEMENT OF PUBLIC RAILWAY

INFRASTRUCTURE INVESTMENT

Page 2: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

218.04.23

DEVELOPMENT OF SLOVENIAN RAILWAY INFRASTRUCTURE

CORRIDORSV.th and X.th corridor

Lenght of railway lines

total: 1228 km single track lines: 330 km duble track lines: 898 km

Page 3: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

318.04.23

THE GOALS WE WANT TO ACHIEVE • Abandoning of bottle-necks, completing of the missing sections and the construction of main lines;

• Connecting of the railway transport with air and maritime transport;

• Improvement of transport safety;

• Acceleration of the national economic development;

• Reduction of the negative impact on environment;

• Assuring of the allowed axle load min. D3 (225 kN/axle and 72 kN/m);

• Increasing of the maximal allowed line speed on main lines, which coincide with corridors V and X on 160 km/h or more and

• Assuring of the renovation of safety signalling devices and the up-to date remote control of traffic on main lines of public railway infrastructure.

Page 4: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

418.04.23

ESTABLISHED: 1.8.2007

No. of Employees: 30

BUDGET IN 2009: 300 mio EUR

ADDRESS:Kopitarjeva ulica 52000 MARIBORSLOVENIJA

PHONE: +386 2 234 14 21

E-MAIL: [email protected]

Page 5: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

518.04.23

RUNNING PROJECTS

•International projects (co-financed from European funds)The Republic of Slovenia is entitled to co-financing of projects by means of the European Union, namely with the aid of:

• Financial TEN-T funds, within this at present nine projects are implemented;

• ISPA 2000-2004, within this at present two projects are still implemented;• Cohesion fund 2004-2006, within this two projects are still implemented;

•Cohesion fund 2007-2013, within this four projects are running in the moment.  

•Domestic projects (financed by the means of the Republic of Slovenia)

Page 6: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

618.04.23

TEN-T PROJECTS• Technical studies for the construction of the second track of the railway line Divača-Koper;• Plan for obtaining the building permit for the reconstruction and electrification of the existing railway line Pragersko – Hodoš;• Preparing of legal expertise and the feasibility study for the development of the railway infrastructure on the area of the Ljubljana junction; • Main solution of the airport Ljubljana including the railway line connection with Ljubljana and Kranj (new railway line connection Ljubljana-Jesenice); • Implementation of system GSM-R on Slovenian railway network; • Cross-border railway line Trieste-Divača: Study and the plan of the cross-border railway line Trieste-Divača-Ljubljana-Budapest-border with Ukraine; • Implementation of ERTMS system on the Vth railway corridor (Valencia-Budapest);• Preparing of the preliminary study for the construction of the new high capacity line / high speed line Divača-Ljubljana;• Preparing of the preliminary study for the construction of the new high capacity line / high speed line Ljubljana - Zidni Most.

Page 7: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

718.04.23

Within the period of the Cohesion fund 2004-2006 two projects are implemented, namely:

1-Modernization of the railway line Pragersko-Ormož (A);

2-Remote control of electrical traction

Within the period of the Cohesion 2007-2013 the next projects are implemented:

1-New railway line connection Divača-Koper;

2-Reconstruction, electrification and upgrading of the line Pragersko-Hodoš;

3-Modernization of the existing railway line Divača-Koper;

4-Modernization of level crossings

Within the period of ISPA 2000-2004 two projects are in implementation, namely:

1-Modernisation of SS devices on the line Divača-Koper;

2-Modernisation of SS devices in the line Pragersko – Ormož

Page 8: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

818.04.23

DOMESTIC PROJECTS

1-Preparing and management of projects;

2-Modernization of the railway line Grosuplje-Kočevje;

3-Abandoning of slow drives on the section of the line Košana-Gornja Ležeče;

4-Environment protection and noise barriers;

5-Protection of railway level crossings;

6-Updating of SS protection on the railway station Kamnik;

7-Modernization of SS and TC devices on the railway line Ormož-Murska Sobota

Page 9: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

REPUBLIKA SLOVENIJA

MINISTRSTVO ZA PROMET

DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V

JAVNO ŽELEZNIŠKO INFRASTRUKTURO

918.04.23

WE ARE DELIGHTED ABOUT THE CHALLENGES

Page 10: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

10

MINISTRSTVO ZA PROMETDIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE

INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO

18.04.23

THANK YOU FOR YOUR ATTENTION!

Presentation by: Mitja Kosec – Project Manager

Zagreb , 9th November 2009

Page 11: REPUBLIKA SLOVENIJA MINISTRSTVO ZA PROMET DIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO 1 14.4.2015 Presentation

11

MINISTRSTVO ZA PROMETDIREKCIJA REPUBLIKE SLOVENIJE ZA VODENJE

INVESTICIJ V JAVNO ŽELEZNIŠKO INFRASTRUKTURO

18.04.23

QUESTIONS?

Presentation by: Mitja Kosec – Project Manager

Zagreb , 9th November 2009