25
Recycled Asphalt Program & Environmental Stewardship Program (Post Consumer Content) Robert C. Rea Nebraska Department of Roads WASHTO – Omaha, Nebraska April 2014

Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

  • Upload
    italia

  • View
    27

  • Download
    0

Embed Size (px)

DESCRIPTION

Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content). Robert C. Rea Nebraska Department of Roads WASHTO – Omaha, Nebraska April 2014. Average RAP Contents (Overall). 39.2%. 37.3%. 34.4%. 28.6%. 27.3%. 6.9%. RAP Savings ($ millions). 43.6M. 41.7M. - PowerPoint PPT Presentation

Citation preview

Page 1: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Recycled Asphalt Program&

Environmental Stewardship Program(Post Consumer Content)

Robert C. ReaNebraska Department of RoadsWASHTO – Omaha, Nebraska

April 2014

Page 2: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Average RAP Contents (Overall)

2007 2009 2010 2011 2012 201305

10152025303540

6.9%

27.3% 28.6%

34.4%37.3% 39.2%

Page 3: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

RAP Savings ($ millions)

2007 2009 2010 2011 2012 201305

1015202530354045

3.6M

23.3M19.8M

41.7M

35.3M

43.6M

Page 4: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

How did we get to 39.2% average RAP ?

Design and Specifications to optimize RAP

RAP Incentive for binder savings

Page 5: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

RAP Incentive for binder savings

1. Binder Cost Subsidiary to Mix (36 States)

• Not Needed -- Incentive is already there to use less contractor purchased ‘new’ binder• SPECIFICATIONS2. Binder Paid Separately as Bid Item

(14 States)• Needed -- No incentive for the Contractor

to underrun an established item, so we must place incentive on the net binder savings• SPECIFICATIONS and INCENTIVE

Page 6: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)
Page 7: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

15% of Binder SavingsFor Contractor

35% of Binder SavingsFor Contractor

50% of Binder SavingsFor Contractor

DOT Millings from ‘ON’ project DOT Millings from ‘OFF’ project

Contractor ‘Owned’ Millings

90% of our projects are this 8% of our projects are this 2% of our projects are this

85/15 Incentive Split 65/35 Incentive Split 50/50 Incentive Split

Page 8: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Example 40,000 Ton Project( 5 M ESAL Design – Typical SPR mix )

MILLINGS FROM ON PROJECT85/15 Incentive Split

• Mill 2” – Fill 3”• Hot Mix = $ 30 per ton• Binder PG 64-34 = $650 per liquid ton• Design is for 5.4% Binder Content

Page 9: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Total Cost = $2,604,000Recycle Savings to DOT = $0.00Recycle Incentive to the Contractor = $0.00

Total final Cost Realized by DOT $2,604,000

Virgin Mix (No RAP)• Hot Mix = 1,200,000• Virgin Binder = $1,404,000• Binder from RAP = $0 Total Cost = $2,604,000

Pre-incentive 2008 (6.9% RAP)• Hot Mix = 1,200,000• Virgin Binder = $1,307,124• Binder from RAP = $96,876

Total Cost = $2,507,124

Current w/Incentive (45% RAP)• Hot Mix = 1,200,000• Virgin Binder = $772,200• Binder from RAP = $631,800

Total Cost = $1,972,200

Total Cost = $2,604,000Recycle Savings to DOT = $96,876Recycle Incentive to the Contractor = $0.00

Total final Cost Realized by DOT $2,507,124

Total Cost = $2,604,000Recycle Savings to DOT = $537,030Recycle Incentive to the Contractor = $94,770

Total final Cost Realized by DOT $2,066,970

Page 10: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Virgin Mix (No RAP)

Total final Cost Realized by DOT $2,604,000

Pre-incentive 2008 (6.9% RAP)

Current w/Incentive (45% RAP)

Savings from optimizing RAP

$440,000 to $550,000Total final Cost Realized by DOT

$2,507,124

Total final Cost Realized by DOT $2,066,970 On one 40,000 ton hot mix project

Page 11: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

REASONS RAP USE MAY BE LIMITED

1. Agency limits use of RAP or says ‘I want the new stuff, not the used stuff ’

2. Stigma of lesser quality, Engineered Design a must 3. Plant Superintendant says ‘The plant won’t run that much’4. Design must optimize mill and fill strategies or ‘Road

Mining’5. Requires binder grade bumps/dumps when higher amounts

are used6. Restrictive in the specification, i.e. dust/asphalt maximum7. Limits the RAP #200 amounts and therefor rejects the RAP8. Voids and VMA and other properties restrict the amount of

RAP

Page 12: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

SPR – Mix Design• CAA

o 83 Allows for RAP Variation, typically 90+

• FAAo Allows for RAP Variation, typically 44+o FAA Sp. Gravity slightly lowers true FAAo Binder Grade and Volumetrics provide added

Rutting Resistanceo Overshoot FAA – Increased Cracking

• Voidso Allow more dust & binder, better field density

• Min. Bindero Used as Factor for VMA

• #200o Typically around 4-6%, D/B around 1.0-1.2

Page 13: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

APA Testing of SPR Mixes

• 8000 Cycles• 100 PSI Pressure Load• 64 degrees C• Max of 12 mm Rutting

Page 14: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

APA Testing of SPR Mixes

Page 15: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

02468

101214

APA Testing of SPR vs SP-4SP-4 SPR

Rutt

ing

(mm

)

44.7%

Page 16: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Approach to a 50% RAP Project1. Pick a 20,000 to 40,000 Ton Project 2. Use a ‘tried and true’ mix that you know works and has been a

workhorse for your state 3. Specify the quality and type of virgin aggregate that you want to use,

in other words, the ones that you like and are of good quality4. Use softest base oil you can get either -34 or -28 if you can 5. Specify a minimum Binder Content if you don’t pay ac separately6. Specify minimum 40 % RAP7. Have the RAP come from the road…….fresh processed millings8. Be flexible with the #200 material9. Lower voids and no VMA spec, effects of burnoff oven – another all

day presentation to discuss this control by voids and binder content10. Place it in all lifts, especially surface, we want to monitor this material

Page 17: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Robert C. Rea402 479 3839 office

402 326 9934 [email protected]

Page 18: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

(No RAP) (20% RAP) (50% RAP)05

101520253035404550

BinderAggregate

$ 12

Type ‘R’ Asphalt

$ 36

$ 24

$ 12 - $ 20$ 44

Page 19: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

RAP Savings Potential $ 12 to $20 per Ton x ?? Million Tons $ 10 to 40 Million

Annual Savings realized every year, over and over and over again .

Not to mention, Better on the environment, Green Technology, Recycling, Less Raw Materials, Less Hauling, Less Transportation and consumption of fuels ……..

Page 20: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Post Consumer Content

Page 21: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

On Project Plan Sets in 2014

Page 22: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)
Page 23: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)
Page 24: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)
Page 25: Recycled Asphalt Program & Environmental Stewardship Program ( Post Consumer Content)

Thank You!