ESKOM COPYRIGHT PROTECTED
B Morrison / February 2013 / Rev 0
Standard Group Technology
Title: QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Part 7 -Substations
Area of Applicability: Distribution Engineering
Documentation Type: Standard
Revision: 0
Total Pages: 112
Next Review Date: February 2018
Disclosure Classification: Controlled Disclosure
Compiled by Approved by
……………………………………………………… ………………………………………………..…….
Abre Le Roux
Chief Engineer Substations
Elli Lechtman
Substations SC Chairperson
Date: ……………………………………………. Date: ………………………………………………
Approved by Authorized by
………………………………………………..……. ……………………………………
Elli Lechtman
SCOT Representative
Phineas Tlhatlhetji
Substations COE Manager
Date: ……………………………………………… Date: …………………………
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 2 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Content
Page
Foreword ........................................................................................................................................................ 3!1! Scope .................................................................................................................................................. 4!2! Normative references .......................................................................................................................... 4!3! Definitions & Abbreviations ................................................................................................................. 4!
3.1! Definitions .................................................................................................................................... 4!3.2! Abbreviations ............................................................................................................................... 5!
4! Requirements ...................................................................................................................................... 5!4.1! General Project Information ......................................................................................................... 8!4.2! Requirements applicable to Stages 1 to 13 ................................................................................. 8!4.3! Requirements applicable to Stage 14 - “Commissioning Testing” .............................................. 9!4.4! Requirements applicable to Stage 15 - “Provisional Handover” ................................................. 9!4.5! Requirements applicable to Stage 16 - “Final Handover” ......................................................... 10!
Annexure Contents ...................................................................................................................................... 11!Annexure A – General Project Information .................................................................................................. 12!Annexure B1 – Stage 1: Civil Works: Platform ............................................................................................ 16!Annexure B2 – Stage 2: Civil Works: Control Building ................................................................................ 22!Annexure B3 – Stage 3: Civil Works: Subsoil Drainage .............................................................................. 27!Annexure B4 – Stage 4: Civil Works: Earthmat Installation ........................................................................ 29!Annexure B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches ..................................... 31!Annexure B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing ................................................................ 34!Annexure B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dame and Fire Wall ............................. 36!Annexure B8 – Stage 8: Steelwork .............................................................................................................. 42!Annexure B9 – Stage 9: Fencing ................................................................................................................. 44!Annexure B10 – Stage 10: Power Transformer Delivery & Assembly ........................................................ 47!Annexure B11 – Stage 11: Primary Equipment Installation ........................................................................ 49!Annexure B12 – Stage 12: Conductor, Busbars & Clamps Installation ...................................................... 61!Annexure B13 – Stage 13: Control Plant Installation .................................................................................. 64!Annexure B14 – Stage 14: Commissioning Testing .................................................................................... 81!Annexure B15 – Stage 15: Provisional Handover ..................................................................................... 111!Annexure B16 – Stage 16: Final Handover ............................................................................................... 112!
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 3 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Foreword
This revised standard is based on the original document DISASAAQ1 Rev 5 dated September 2005.
Revision history
This revision cancels and replaces revision no 5 of document no. DISASAAQ1.
Date Rev Compiled
by Remarks
Feb 2013 01 A le Roux
Complete document revision with new stages 1 to 16 and revised handover and quality checklist documentation
Document number changed to DST 34-1238.
Sept’05 5 C Clark
Document approved.
All comments and new comments answered. Send for Voting 03/2005.
All comments answered. Send for Voting 11/2004.
Telecontrol info updated according to comments received by Western Region. Electrical Certificate info on page 9 removed.
Sept 2002 4 C Clark Document approved
June 2002 3 C Clark Page 75 EDNS added
Nov ‘99 2 C Clark
Document changed comments added
Document changed item revised – 4.6.2
Document changed comments added – 4.6.4 , 4.6.5
Comments addressed. General typographical errors rectified. Item 4.4.2 and associated forms revised. Annex H (Stage 8) – FS added as a signatory. Annex I added to include provisional handing over certificate. Annex C (Stage 3) C13 – Fire Protection Checklist added. Annex A (Stage 1) A3 – changes/additions to checklist. General changes to all other Annexes as per comments
Typographical errors rectified as per request from western region. Alignment of document to include signatories on a single sheet.
April ‘99 1 C Clark Project Flow Process taken out, entire document changed.
Aug ‘98 0 C Clark Project Flow Process added, entire document revised to allow for Stage takeovers.
Acceptance
This document has been seen and accepted by:
Name Designation
Phineas Tlhatlhetji Substations COE manager
E Lechtman SCOT Substations Representative
This standard shall apply to Eskom Distribution.
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 4 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Development team
Name Designation
A.Le Roux Chief Engineer – Substations
N. Webber Senior Advisor - Substations
J.Kriel Thabile Eastern Cape – Electrical Engineers
Keywords
Handover, Quality, Checking.
1 Scope
This standard sets out the requirements for the various Quality Control and Handover process stages for a substation project from the inception of construction to commissioning and final handover. This standard shall be used in conjunction with all standard substation documentation and scope of works documentation that will form part of the substation project Works Information.
2 Normative references
The following documents contain provisions that, through reference in the text, constitute requirements of this standard. At the time of publication, the editions indicated were valid. All standards and specifications are subject to revision, and parties to agreements based on this standard are encouraged to investigate the possibility of applying the most recent editions of the documents listed below. Information on currently valid national and international standards and specifications can be obtained from the Information Centre and Technology Standardization Department at Megawatt Park.
SANS 121, Hot-dip (galvanized) zinc coatings (other than on continuously zinc-coated sheet and wire).
DST 34-304: Distribution standard – Part 7: Generic substation design.
SANS 1200: Specification for civil engineering construction
SABS 10400: National building regulations
DST 34-1245: Substation Earthing
DISSCAAD3: Checklist for Large Transformers
DSP 34-1658: Corrosion Protection specification for new indoor and outdoor Distribution equipment, components, materials and structures manufactured from steel
DISASAAN0: Standard for the labeling of High Voltage Equipment
3 Definitions & Abbreviations
3.1 Definitions
Contractor
! As per the NEC contract represented by an Appointed Supervisor or Responsible Person in writing. The Contractor can also be an Eskom Internal Construction team.
! Manufacturers of the Power Transformers and other substation equipment.
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 5 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Clerk Of Works People responsible for physical quality inspections.
Project Manager
Person appointed as per the NEC contract. The Project Manager can be someone within the Eskom Program Management Department or an external appointment in which case it will be a Contracted Project Manager.
Contract Project Manager Person appointed as per the NEC contract. The Project Manager is appointed external to Eskom.
Standards Implementation department (Substations)
Department responsible for standards.
Control Plant Maintenance department
Responsible for the pre-commissioning and final commissioning of the substation project.
Design Engineer (Primary Plant) Person responsible for the primary design drawings, bill of quantities and approval of Design Change Requests.
Design Engineer (Control Plant) Person responsible for the control plant design (protection, metering, DC, telecommunication and telecontrol).
Contract Design Engineer Person appointed external to Eskom responsible for the design drawings, bill of quantities and approval of Design Change Requests.
Holding Point Activity for which arrangements have to be made for the Clerk of Works to be present and to witness the work procedure.
3.2 Abbreviations
COW Clerk Of Works
PM Project Manager
CPM Control Plant Maintenance department
DE Design Engineer
CDE Contract Design Engineer
AD Asset Design
4 Requirements
The document contains all possible quality check sheets and handover forms to execute a substation project. It is important to compile a Quality Handover document specific to a project by including the relevant sections and duplicating check sheets where required (eg. In the case of two transformers two separate transformer check sheets will be required or if no capacitor bank will be installed, exclude the capacitor bank quality check sheet).
The process is initiated by collating all relevant detail and documentation regarding the project and stakeholders. This is catered for in tables in the General information section as per Annexure A.
The next stage is the actual execution of activities. This is catered for in Stages 1 to 13 (Annexure B1 to B13). Each stage consists of two types of documents per category, namely a Quality Control check sheet (Quality checking of actual activities) and a Handover form (confirming that the various Quality activity checks have been executed).
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 6 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
The next stage is the Commissioning and testing stage prior to switch-on (Stage 14, Annexure B14).
Provision has been made for two stages for Handover. Firstly, a Preliminary Handover stage to ensure that all quality checks have been performed in order to switch the substation on. The final Handover ensures that all activities relating to the project have been completed and the project is closed off and handed over for Commercial operation.
The Quality Control and Assurance process consists of the following stages:
! General Project Information
! Stage 1 Civil Works: Platform
! Stage 2 Civil Works: Control Building
! Stage 3 Civil Works: Subsoil drainage
! Stage 4 Civil Works: Earthmat Installation
! Stage 5 Civil Works: Equipment Foundations & Cable trenches
! Stage 6 Civil Works: Roads, Stoning & Kerbing
! Stage 7 Civil Works: Transformer bund area, Oil dam and fire wall
! Stage 8 Steelwork
! Stage 9 Fencing
! Stage 10 Power Transformer Delivery & Assembly
! Stage 11 Primary Equipment Installation
! Stage 12 Conductors, busbars & clamps
! Stage 13 Control Plant installation
! Stage 14 Commissioning Testing
! Stage 15 Provisional Handover
! Stage 16 Final Handover
The various stages are displayed in figure 1
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 7 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Figure 1: Quality Control handover stages
Platform
Civil Works
Control Building
General Project Information
Earthmat Installation
Subsoil drainage
Equipment Foundations & Cable trenches
Roads, Stoning & Kerbing
Transformer bund area, Oil dam and fire wall
Steelwork
Fencing
Final Handover
Provisional Handover
Commissioning Testing
Conductors, busbars & clamps
Control Plant installation
Primary Equipment Installation
Power Transformer Delivery & Assembly
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 8 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
4.1 General Project Information
! The Design Engineer shall hand over the Final Design Package and Drawings to the Project Manager. It is the responsibility of the Design Engineer to ensure that the latest revisions of all documentation have been issued to the Project Manager.
! The Project Manager will ensure that both the appointed Contractor and the appointed Clerk of Works receive the necessary documents and drawings for all the construction stages. All parties are to complete the Design Package Handover Form before commencement of construction.
! Provision has been made for signatories and the recording of the relevant Drawing Numbers and Revisions at the time of issue.
! Drawing revisions due to Design Changes will be recorded in the Documentation Change Control Form. The Project Manager will ensure that the Contractor and Clerk of Work receive the latest revision of the drawings.
4.2 Requirements applicable to Stages 1 to 13
! The Quality Control Checksheet will be issued by the Project Manager as part of the quality assurance documentation and will be on site until the stage has been completed. The activities within the stage are to be completed and checked against the design drawings and specifications to ensure compliance.
! Prior to the commencement of the construction stage, the Clerk of Works will confirm with the Contractor which activities have been identified as Holding Points and which activities he would like to be photographed as proof of compliance.
! Each activity, once completed by the contractor, will be signed off by both the Contractor and Clerk of Works. The Clerk of Works will indicate whether the activity was:Witnessed (W) – present during this activity Verified (V) – not present but confirm compliance.
! Certain Checksheets include key specifications such as soil classification, layer depth and number of layers required as per the design. This is to ensure the specification is understood by both parties and complied with.
! Once all the activities for a specific stage have been completed, the Quality Control Checksheetshall be presented to the Project Manager who will confirm that all the activities have been signed off by both the Contractor and the Clerk of Works
! The Handover Checklist is then used as a high level checklist to ensure that all Quality Control activities have been executed as per the Quality Control Checksheet. The Handover Checklist is the responsibility of the Project Manager and must be updated at least once a month during the site meeting.
! The required forms must be duplicated for multiple products in a substation (e.g. for two transformers make two copies of the transformer checksheets).
4.2.1 Additional requirements applicable to Stage 5 - “Civil Works: Equipment Foundations & Cable trenches”
! The checksheet for the foundations can be done as a bulk item check or a checksheet for each foundation or group of foundations. This is to be decided between the Clerk of Works and the Contractor.
4.2.2 Additional requirements applicable to Stage 9 - “Steelwork” and “Fencing”
! The Contractor shall ensure that all manufactured steelwork is inspected at delivery and galvanizing thickness checked and verified before erection. The Contractor needs to inform the Clerk of Works once the steelwork is on site. The Clerk of Works needs to arrange an inspection date with the Standards Implementation Representative for inspection and approval of steelwork.
! The Checksheet for the steelwork can be done as a bulk item check or a checksheet for each item or group of items. This is to be decided between the Clerk of Works and the Contractor.
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 9 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
4.2.3 Additional requirements specific to Stage 10 - “Power Transformer Delivery & Assembly”
! The Project Manager must notify the Eskom Plant Department of the projected delivery date in order for them to provide a representative to witness the Transformer delivery and acceptance activity.
! During the delivery of the Power Transformer, the Clerk of Works shall verify and complete the Transformer Delivery Checksheet
! CPM department must witness the on-site transformer tests as executed by the manufacturer.
4.2.4 Additional requirements specific to Stage 11 - “Primary Equipment Installation”
! The Contractor shall inspect all deliveries from Manufacturers in order to ensure that the equipment is in good condition before off-loading on site.
! Only high level data such as equipment type and serial number is captured on the checksheets. Once the equipment is installed, the Project Manager will inform the Plant Department to commence data capturing as per the Eskom Data capturing requirements.
4.2.5 Additional requirements specific to Stage 13 - “Control Plant installation”
! This stage will mostly be executed by the Eskom CPM Department. The Project Manager willliaise with the CPM Manager to identify the Supervisor (CPM) who will be responsible for checking and completion of the Quality Control Checksheet.
! Prior to the commencement of the construction stage, the CPM Supervisor will confirm with the Contractor which activities have been identified as Holding Points and which activities he would like to be photographed as proof of compliance.
! Each activity, once completed by the contractor, will be signed off by both the Contractor and CPM Supervisor. The Supervisor will indicate whether the activity was:Witnessed (W) – present during this activity Verified (V) – not present but confirm compliance.
! Once all the activities have been completed, the Quality Control Checksheet shall be presented to the Project Manager who will ensure that all the grouped activities have been signed off by both the Contractor and the CPM Supervisor Handover Checklist.
4.3 Requirements applicable to Stage 14 - “Commissioning Testing”
! This stage consists of all the relevant pre- and final commissioning tests to be performed in order to commission the substation project.
! Each activity, once completed by the Contractor, will be signed off by the relevant CPMSupervisor to confirm compliance.
4.4 Requirements applicable to Stage 15 - “Provisional Handover”
! The Provisional Handover Document will be completed by the Project Manager and presented for acceptance to the following key persons:
1. Asset Design – Acceptance by the appointed Senior Design Engineer (acceptance for primary and Control Plant)
2. Control Plant Maintenance - Acceptance by the Control Plant Maintenance Manager3. Network Operations – acceptance by the Chief Engineer
! The final commissioning of the substation project can commence after the completion of the Provisional Handover Document.
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 10 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
4.5 Requirements applicable to Stage 16 - “Final Handover”
! The Final Handover Document will be will be completed by the Project Manager and presented for acceptance to the following key persons:
1. Asset Design – Acceptance by the appointed Senior Design Engineer (acceptance for primary and Control Plant)
2. Control Plant Maintenance - acceptance by the CPM Manager 3. Zone – final acceptance by Sector Manager.
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 11 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure Contents
Quality Control & Handover Check-sheets
Annexure A
General Project information
! Project Detail
! Tracking Page
! Design Package Handover
! Documentation Change Control
Annexure B1 Stage 1 Civil Works: Platform
Annexure B2 Stage 2 Civil Works: Control Building
Annexure B3 Stage 3 Civil Works: Subsoil drainage
Annexure B4 Stage 4 Civil Works: Earthmat Installation
Annexure B5 Stage 5 Civil Works: Equipment Foundations & Cable trenches
Annexure B6 Stage 6 Civil Works: Roads, Stoning & Kerbing
Annexure B7 Stage 7 Civil Works: Transformer bund wall, oil dam and fire wall
Annexure B8 Stage 8 Steelwork
Annexure B9 Stage 9 Fencing
Annexure B10 Stage 10 Power Transformer Delivery & Assembly
Annexure B11 Stage 11 Primary Equipment Installation
Annexure B12 Stage 12 Conductors, busbars & clamps
Annexure B13 Stage 13 Control Plant installation
Annexure B14 Stage 14 Commissioning Testing
Annexure B15 Stage 15 Provisional Handover
Annexure B16 Stage 16 Final Handover
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 12 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure A – General Project Information
Substation Project Name:
Project No:
COW name:
Design Engineer:
Project Manager:
Contractor Civil Platform Works: Contractor Secondary Works:
Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:
Contractor Civil Buildings: Contractor :
Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:
Contractor Primary Works: Contractor:
Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:
Project Detail
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 13 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Quality Control Checklist
Completion Date
Handover Checklist
Completion DateNotes
Stage 1 Civil Works: Platform
Stage 2 Civil Works: Control Building
Stage 3 Civil Works: Subsoil drainage
Stage 4 Civil Works: Earthmat Installation
Stage 5 Civil Works: Equipment Foundations & Cable trenches
Stage 6 Civil Works: Roads, Stoning & Kerbing
Stage 7 Transformer bund wall, oil dam and fire wall
Stage 8 Steelwork
Stage 9 Fencing
Stage 10 Power Transformer Delivery & Assemble
Stage 11 Equipment Installation
Stage 12 Conductors, busbars & clamps
Stage 13 Control Plant Installation
Stage 14 Commissioning Testing
Stage 15 Provisional Handover Document
Stage 16 Final Handover Document
The purpose of this page is to track the relevant stages and to record progress.
Project Tracking
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 14 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
Stage Construction Activity Drawing Title & ReferenceRev
No:
Issued by (Project
Manager Name)Date
Received by (Clerk of
Works Name)Date
Received by
(Contractor Name)Date
Access to site documentation completed as per
the NEC contract
Health & Safety Plan and File presented and
approved before start of construction.
1 Civil Works: Platform
2 Civil Works: Control Building
3 Civil Works: Subsoil drainage
4 Civil Works: Earthmat Installation
5Civil Works: Equipment Foundations &
Cable trenches
6 Civil Works: Roads, Stoning & Kerbing
7Civil Works: Transformer bund wall, oil dam and
fire wall
8 Steelwork
9 Fencing
10 Power Transformer Delivery & Assembly
11 Primary Equipment Installation
12 Conductors, busbars & clamps
13 Control Plant installation
Design Package Handover
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 15 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
Item Drawing No: Change Rev No:Issued by Project
Manager NameDate
Received by Clerk of
Works NameDate
Received by Contractor
NameDate
Documentation Change Control
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 16 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B1 – Stage 1: Civil Works: Platform
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
1 Benchmark Installation Name of Surveyor:__________________
Depth:__________________mm
Quantity:__________________m³
Stockpile
position:
Stockpile height:__________________m
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Quality Control Checksheet for Civil Works: Platform
2 Platform: Clear & grub
3Platform: Road bed
preparation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 17 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Soil classification :__________________
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Soil classification :__________________
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Depth:__________________mm
Quantity:__________________m³
Stockpile
position:Stockpile
height: m
6Platform: Wearing coarse /
Final layer preparation
7 Access Road: Clear & grub
4 Platform: Cut to Fill Operation
5Platform: Importation of
materials
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 18 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Soil classification :__________________
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
Soil classification :__________________
Layer Depth:__________________mm
No of layers:__________________
No of Compaction & Density
tests:No of Compaction & Density tests
witnessed by COW:
10Access Road: Importation of
materials
11
Access Road: Wearing
coarse / Final layer
preparation
8Access Road: Road bed
preparation
9Access Road: Cut to Fill
Operation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 19 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Drainage & Channelling required:
Bell mouth: Size and bending
radius:Signage:___________________________
Entry from Road:
Type of
drain:
Drain Positions:______________________
Drain
sizes:Concrete
specification:
Concrete supplied: __________________
Finishes:___________________________
Run-offs / Channelling:
Embankment angles and preparation:
Seeding:
Soil Blankets:
Retaining walls - Type & size:
14Embankments & Soil
Detainment
12 Access Road: Finishes
13 Storm water drainage
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 20 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Type & Position:
Corner Posts:
Intermediate posts:
Fencing:
Gates:
16 Levelling of spoiled materials. Levelling of spoiled materials.
Position:
Size:
Position:
Seeding:
17 Earth berm installation.
18 Rehabilitation
15 Boundary Fence
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 21 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Benchmark Installation
2 Platform: Clear & grub
3 Platform: Road bed preparation
4 Platform: Cut to Fill Operation
5Platform: Importation of
materials
6Platform: Wearing coarse /
Final layer preparation
7 Access Road: Clear & grub
8Access Road: Road bed
preparation
9Access Road: Cut to Fill
Operation
10Access Road: Importation of
materials
11Access Road: Wearing coarse
/ Final layer preparation
12 Access Road: Finishes
13 Storm water drainage
14Embankments & Soil
Detainment
15 Boundary Fence
16 Levelling of spoiled materials.
17 Earth berm installation.
18 Rehabilitation
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Platform
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 22 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B2 – Stage 2: Civil Works: Control Building
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
1Setting out of building
foundations & levels.Building set out according to XY
Foundation correctly excavated - width &
depth
Levels/height correct
Reinforcing installed correctly
Compaction acceptable
Local Municipality approval
3 Concrete - Foundations Concrete - mixture at correct MPa
Quality Control Checksheet for Civil Works: Control Building
2 Foundations - excavation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 23 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Concrete - mixture at correct Mpa
Waterproofing:
Shuttering:
Floating / Power floating:
Brick type & colour
Cement mixture correct
Waterproofing
Jointing
Correct heights & levels
Plastering
Trusses delivery - visual inspection
Trusses designed correctly
Trusses positioned & lined up correctly
Roof sheeting type & colour
Roof installation
Roof waterproofing installation
Gutters & down pipes
4 Concrete - Floor
5 Brickwork
6 Roof Installation - Sheeting
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 24 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Concrete - mixture at correct MPa
Reinforcing installation
Shuttering.
Waterproofing installation
Gutters & down pipes
Ceiling type & colour
Ceiling height & level
Plumbing installation
Plumbing Installation approval by an
accredited person
Electrical installation
Certificate of Compliance issued
Electrical installation
Electrical Installation approval a Master
Electrician.
7 Roof Installation - Concrete
8 Ceilings
9 Plumbing Installation
10Control Building - Electrical
Installation
11Battery room - Electrical
Installation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 25 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Painting
Steps, Ramps & hand rails
Doors, Security gates
Trench covers
Cable rack installations
Key cabinet
Operating Diagram board installation
Fire extinguishers
Furniture
Operating earths
Barricading nets & stands
12 Finishing
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 26 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1Setting out of building
foundations & levels.
2 Foundations
3 Concrete - Foundations
4 Concrete - Floor
5 Brickwork
6 Roof Installation - Sheeting
7 Roof Installation - Concrete
8 Ceilings
9 Plumbing Installation
10Control Building - Electrical
Installation
11Battery room - Electrical
Installation
12 Finishing
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Control Building
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 27 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B3 – Stage 3: Civil Works: Subsoil Drainage
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Grid lengths measured out with correct
distances
Grid levels to be determined to ensure
enough fall is created during excavation &
installation of the drainage pipes.
Drainage pipes - size & type
Bidum material
Stone - size & type
Trenching - width & depth
Backfilling of materials
Compaction
4 Drainage outlets Number of outlets
Quality Control Checksheet for Civil Works: Subsoil drainage
3Subsoil drainage backfill and
compaction
1Subsoil drainage & piping
setting out
2Installation of subsoil drainage
pipes, bidum and stone
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 28 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1Subsoil drainage setting
out.
2
Installation of subsoil
drainage pipes, bidum
and stone
3Subsoil drainage backfill
and compaction
4 Drainage outlets
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Subsoil drainage
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 29 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B4 – Stage 4: Civil Works: Earthmat Installation
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
1 Earth Grid setting out Earthmat - setting out
Excavations
Backfill of materials
Compaction
Earth Conductor - type & size
Earth Conductor installation
Earth Conductor connections
Sacrificial earth installation
4 Earth Continuity test Earth Continuity test
2 Earth Grid Excavations
3Earth Conductor Installation &
Connections
Quality Control Checksheet for Civil Works: Earthmat Installation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 30 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Earth Grid setting out
2 Earth Grid Excavations
3Earth Conductor Installation &
Connections
4 Earth Continuity test
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Earthmat Installation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 31 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Equipment Foundation - setting out
Foundation dimensions - length, width &
depth
Foundation side walls - stable & vertical
Foundation compaction
Reinforcing
Steel Shuttering
Control cabling uPVC pipe
Steel Templates - installed & positioned
HD Bolts
Earthing - installed HD bolt earthing
Concrete - mixture at correct Mpa
1Equipment Foundation
No:___________________
Quality Control Checksheet for Civil Works: Foundations
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 32 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Cable trenches - setting out
Cable trench excavations &
installation
Cable trench bedding preparation.
Cable trench cover support brackets
Cable trench (pipe) road crossings
Cable trench covers.
Cable trench entry into Control
Building.
2 Cable trenches
Quality Control Checksheet for Civil Works: Cable Trenches
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 33 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Foundations
2 Cable trenches
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Foundations & Cable Trenches
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 34 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Road kerbing installation
Stone kerbing installation
Road stoning - size & depth.
Paving - preparation
Paving - installation
Gate ramp installation
3 Stoning Yard stoning - size & depth.
4 Weed killer Spraying of weed killer.
1 Kerbing
2 Roads
Quality Control Checksheet for Civil Works: Roads, Stoning & Kerbing
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 35 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Kerbing
2 Roads
3 Stoning
4 Weed killer
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Roads, Stoning & Kerbing
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 36 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dame and Fire Wall
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Foundation - depth & size
Face Bricks - correct make
Walls - Quality of finish
Walls - Facebrick jointing
Walls - Height & Level
Sump - depth & size
Floor - levels (direction of flow)
Floor - sealing correct
Valve chamber - level & size
Drizit bags - installed
Outlet Valve - level
Drizit bag - level
Drainage pipe - outlet level
Valve Chamber cover - size
Flow stop - invert level
Oil drainage pipes levels - 300mm concrete
Oil drainage pipes joints sealed - 300mm
concreteOil drainage pipes direction of flow -
300mm concrete
Quality Control Checksheet for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall
Transformer Oil Containment Area1
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 37 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Foundation - position depth & size
Face Bricks - correct make
Walls - Quality of finish
Walls - Facebrick jointing
Walls - Height & Level
Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed
Foundation - position depth & size
Face Bricks - correct make
Walls - Quality of finish
Walls - Facebrick jointing
Chamber 1 - size
Chamber 2 - size
Inlet - level
Outlet - level
Level separation wall - position
Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed
2 Manholes
3 Firetrap
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 38 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Foundation - position depth & size
Oil Dam dimensions - length, width, depth
Waterproofing - installed
Shuttering - install
Oil Dam floor - concrete & reinforcing.
Oil Dam walls - concrete & reinforcing.
Inlet - level
Outlet - level
Ladder - istalled
Cover - installed
Earthing
4 Oil dam - Type A Concrete
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 39 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Foundation - position depth & size
Oil Dam dimensions - length, width, depth
Waterproofing - installed
Oil Dam floor - sand bedding
Concrete & Reinforcing - installed.
Face Bricks - correct make
Walls - Quality of finish
Walls - Facebrick jointing
Inlet - level
Outlet - level
Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed
Sealing
Side wall - river sand bedding
Sump - depth & size
Valve chamber - level & size
Valve chamber - Quality and facebrick
Drizit bags - installed
Outlet Valve - level
Drizit bag - level
Drainage pipe - outlet level
Valve Chamber cover - size
Flow stop installed - invert level
Side wall - river sand bedding installed
Water Pump - installed
Water Pump probes - installed
Water Pump controls & JB - installed
Earthing - Installed
5Oil dam - Type
B Brick
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 40 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Foundation - position, depth & size
Support - correct height
Module 'A' - correct position
Module 'B' - correct position
6Stainless Steel
Fire Walls
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 41 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1Transformer Oil Containment
Area
2 Manholes
3 Firetrap
4 Oil dam
5 Stainless Steel Fire Wall
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 42 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B8 – Stage 8: Steelwork
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
1 Steelwork DeliverySteelwork delivery inspection - verification
of material condition & galvanising.
Assembling.
Installed, plumbed & levelled.
Bolts torqued.
Grouting
2
Steelwork :
______________________
Quality Control Checksheet for Steelwork
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 43 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Steelwork Delivery
2 Steelwork Installation
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Steelwork
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 44 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B9 – Stage 9: Fencing
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
1 Fencing DeliveryFencing delivery inspection - verification of
material condition & galvanising.
Assembling
Installed, plumbed & levelled
Bolts sheared
Earthing
Labelling
Assembling
Installed, plumbed & levelled
Earthing
Labelling
Quality Control Checksheet for Fencing
2 Palisade Fence
3 Diamond Mesh Fence
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 45 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Installation
Labelling
Installed, plumbed & levelled
Locks
Earthing
Labelling
6 Boundary Fence & Gate Installation
5 Gates
4 Precast Walls
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 46 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1 Fencing Delivery
2 Palisade Fence
3 Diamond Mesh Fence
4 Precast Walls
5 Gates
6 Boundary Fence & Gate
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Fencing
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 47 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B10 – Stage 10: Power Transformer Delivery & Assembly
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Transformer Delivery from supplier - Health
& Safety Plan approvedSupplier accept that site is accessible for
the delivery of the transformer.Transformer plinth & slipway - concrete
works completed and cured.Transformer position indicated on the
plinth.Supplier tests conducted and witnessed by
Control Plant Maintenance.
Transformer Delivery Checklist completed.
Refer to Document: DFM 34-1901
1Transformers - Delivery &
Installation by Supplier
Quality Control Checksheet for Primary Equipment: Power Transformer Delivery & Assembly
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 48 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1Transformers - Delivery &
Installation by Supplier
Accepted by Control Plant Maintenance Manager:
Name Signature Date
Accepted by Eskom Plant Department:
Name Signature Date
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Primary Equipment: Power Transformer Delivery & Assembly
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 49 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B11 – Stage 11: Primary Equipment Installation
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Transformer Oil levels – conservator – tap-changer
Ensure no oil leaks. Check at sampling
points, bushings and radiator couplings.
Bushings - Check for broken/chipped.
Check for acrylic covers on MV bushings
(Covers to have drain holes to prevent
moisture build-up)
Silica Gel Breather - correctly installed and
correct colour.
Labelling
Earthing installation correct.
Oil sample tests & results
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Power Transformer
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 50 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Auxiliary Transformer Delivery from supplier - general condition.
Installation
Orientation
Oil levels – conservator
Ensure no oil leaks. Check at sampling points,
bushings and radiator couplings.
Bushings - Check for broken/chipped.
Check for acrylic covers on MV bushings (Covers to
have drain holes to prevent moisture build-up)
Silica Gel breather - correctly installed and correct
colour.
Labelling
Earthing installation correct.
Oil sample tests & results
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Auxiliary Transformer
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 51 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
NECRT Delivery from supplier - general condition.
Installation
Orientation
Oil levels – conservator
Ensure no oil leaks. Check at sampling
points, bushings and radiator couplings.
Bushings - Check for broken/chipped.
Check for acrylic covers on MV bushings
(Covers to have drain holes to prevent
moisture build-up)
Silica Gel breather - correctly installed and
correct colour.
Labelling
Earthing installation correct.
Oil sample tests & results
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - NECRT's
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 52 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Capacitor Bank Delivery from supplier - general condition.
Installation
Bushings - Check for broken/chipped.
Earthing correct.
Labelling
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Capacitor Bank
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 53 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Circuit Breaker Delivery from supplier - general condition.
Installation
Orientation correct.
Bushings - Check for broken/chipped.
Earthing correct.
Function / Pre-commissioning testing
Labelling
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Circuit Breaker
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 54 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Current Transformer Delivery from supplier - general condition.
Installation
Orientation
Oil levels - no leaks.
Bushings - Check for broken/chipped.
Earthing correct.
Labelling
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Current Transformer
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 55 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Voltage Transformer Delivery from supplier - general condition.
Installation
Oil levels - no leaks.
Bushings - Check for broken/chipped.
Earthing correct.
Labelling
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Voltage Transformer
1
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 56 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Isolator Delivery from supplier - general condition.
Installation
Bushings - Check for broken/chipped
porcelain.
Earthing correct.
Function / Pre-commissioning testing
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Isolators
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 57 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Earth Switch Delivery from supplier - general condition.
Installation
Orientation
Earthing correct.
Function / Pre-commissioning testing
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Earth Switch
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 58 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Surge Arrestor Delivery from supplier - general condition.
Installation
Bushings - Check for broken/chipped.
Earthing correct.
Labelling
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Surge Arrestors
Drawing No:__________
Type:_________________
Make:________________
Serial No:_____________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 59 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)COW Signature
Post Insulator Delivery from supplier - general condition.
Installation
Bushings - Check for broken/chipped.
Overall Condition
Quality Control Checksheet for Primary Equipment Installation - Post Insulators
Type:_________________
Make:________________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 60 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist Sub Section
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
8 Post Insulators Installation
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Installation
Function testing
Data Captured
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Equipment Installation
Auxiliary Transformer1
Capacitor Banks2
9 Power Transformer
3 Circuit-breakers
11 Voltage transformers
10 Surge arresters
7 Necrt's
Current transformers4
5 Earth Switch
6 Isolators
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 61 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B12 – Stage 12: Conductor, Busbars & Clamps Installation
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Delivery inspection - compliance to
specification
Installation
Correct strain/suspension insulators
Sag & Tension
Delivery inspection - compliance to
specification
Installation
Correct support insulators
Correct size & lengths
Quality Control Checksheet for Conductor, Busbars & Clamps Installation
1
Busbars/Stringers - Conductor
No:___________________
Type:__________________
2
Busbars - Tubular
No:___________________
Type:__________________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 62 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Delivery inspection - compliance to
specification
Installation
Conductor jumper size
Correct clamp
Correctly torqued/crimp
Clearances correct
Delivery inspection - compliance to
specification
Installation
Sag & Tension
4
Shieldwire
No:___________________
Type:__________________
3Jumpers, Clamps & Spacers
Position:_______________
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 63 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
COW - Quality
Assurance
Check : Name
Signature
1Busbars/Stringers -
Conductor
2 Busbars - Tubular
3 Jumpers, Clamps & Spacers
4 Shieldwire
5 Data Captured
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Civil Works: Conductor, Busbars & Clamps Installation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 64 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B13 – Stage 13: Control Plant Installation
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
1 Drawings Drawing checks
Protection panel acceptance tests
Transformer acceptance tests
Current transformers acceptance tests
Voltage transformers acceptance tests
Circuit-breakers acceptance tests
Wiring and cabling checks
Transformer commissioning tests
Current transformer commissioning tests
Circuit-breaker commissioning tests.
Protection functional tests
Auxiliary transformer/commissioning test
Setting sheet handed over
Sheet No:
4 Setting sheet
Quality Control Checksheet - Protection
2 Acceptance Tests
3 Commissioning Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 65 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Ensure that the panel layout and equipment
installed are in accordance with the
specification drawings.
Verify cable and wire numbering.
Install meters and verify that they have
been tested by an approved SANAS
laboratory.
Install modem and communication cabling
to meters.Obtain all test certificates for hand over -
meters, CTs and VTsEnsure that CT test blocks have shorting
strips connectedEnsure that VT test blocks do not have
shorting strips
Ensure that proper labels are fitted
Verify Insulation test results for
acceptance?Verify Magnetizing test results for
acceptance?Verify Accuracy test results for
acceptance?Verify cabling connections onto the correct
CT ratio?Verify Injection test results to determine
correct CT connected ratio.
Verify Polarity test results for acceptance.
Quality Control Checksheet - Metering
1 Pre-Commissioning
2Pre-Commissioning
CT's
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 66 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Verify Insulation test results for
acceptance.
Verify VT ratio test results for acceptance.
Verify cabling connections onto the correct
VT winding.
Verify Polarity test results for acceptance.
4
Pre-Commissioning
Meter panel functional
tests
Verify Injection test results for acceptance.
Verify correct voltage registered onto
meter.
Verify VT burden measurements test
results for acceptance.
Verify CT burden measurements test
results for acceptance.
Verify Voltage drop test results for
acceptance.
Verify customer pulsing (where
applicable).
Verify VT fail alarms through to
supervisory (if applicable)
Verify correct meter configuration and load
profile channel allocation
Verify correct time and date on all meters
Verify correct phasor diagram results on
all meters
Verify on-load accuracy of all meters for
both kWh and kVArh
5Commissioning of
Metering equipment
3Pre-Commissioning
VT's
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 67 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Verify correct channel allocation on
MV90.
Verify correct CT and VT factors on MV90
Verify correct channel mapping on MV90
Verify communication through to all
meters.
7Post Commissioning
Data verification
Verify results from a metering verification
procedure for acceptance.
8Billing
Customer services
Verify Customer Services acceptance and
sign-off .
6Commissioning of the
MV90 master station
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 68 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Temporary incoming AC supply
commissionedPermanent incoming AC supply
commissioned.
Yard AC distribution commissioning test
Day-Night switch fitted
2Control Building AC
distributionCOC for building issued.
Hazardous area COC obtained
Zoning done
Ventilation checked
Fire walls built up
Basin outlet correct
Safety signs on entrances
Appropriate safety equipment available
Water available
Quality Control Checksheet for AC/DC Auxiliary systems
1Yard AC distribution
commissioning test
3 Battery Room acceptance
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 69 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Battery cable ducting entry in battery room
sealedDucting end correct height above floor
level
Battery charger commissioning test
Panel labels and boost labels installed
Battery commissioning test
Pilot cell label and cell numbering
Emergency lights commissioning test
Correct fittings and bulbs used.
8 Wiring Panel wiring and cable checks
9Incoming AC selection and
commissioning
Incoming AC selection and commissioning
test
4Battery cable ducting entry in
battery room
5 Battery charger
6 Battery commissioning test
7 Emergency lights
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 70 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
AC/DC onsite commissioning test
Temporary incoming AC supply
commissionedPermanent incoming AC supply
commissioned
Inverter commissioning tests
Converter commissioning tests
Yard box tested to control
Charger tested to control
Power electronic tested to control
13 LabellingCorrect safety signs on self-contained
battery enclosures
12 Alarms
10 AC/DC panel
11 Power electronic equipment
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 71 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
1 Drawings & preparationLatest cable block diagram and control room
layout issued.
Cable drums unrolled in the correct direction.
All cables indicated on cable blocks installed.
Correct cable sizes installed: core numbers and
cross-sectional area.
Cables terminated using correct glands for cable
size.
All cables numbered on both ends.
Cable routing is neat and orderly.
Correct hole size for applicable gland.
Cable gland & shroud
Ensure that the insulation of the wiring is not
cut/damaged. Pay particular attention to the area
just above the gland.
Open gland holes to be plugged.
3 Glanding of cables
Quality Control Checksheet - Control Wiring
2 Cabling
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 72 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
All wiring checked and tested with an insulation
voltage tester (megger)
All wires numbered at both ends
All wiring neatly strapped/fitted in trunking
380 V supplies, phase sequence and colour
indication correctSpare cores earthed at location closest to power
plant equipment (or in junction box)
Check that the correct panel type has been
installed (scheme designation matches drawings)
Confirm rated DC voltage of scheme matches
substation DC supply: 110V vs 220V
Confirm presence of transducers (where
applicable)
Panels securely fastened to the floor/walls to
prevent tipping when the door is opened.
Panel/junction box appropriately connected to
substation earth mat.
All bolted plates to be connected to the panel
earth bar using green/yellow 2.5sqmm earhting
wire using the earthing studs provided.
Ensure that schemes are fitted such that all
controls and indications on panels are at a
reasonable working height from the ground.
All apertures in panel closed (vermin proof)
Panels free of lose bolts, offcuts, clippings and
shavings
All trunking covers fitted
Terminal screws secure
No exposed bare wires within panels
Wiring & Numbering
Panels and junction boxes
House keeping
4
5
6
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 73 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
P1 side of Current Transformers faces circuit-
breaker
Kiosk circuit-breakers installed in the correct
orientation with respect to phasing.
Appropriate neutral surge arrester fitted to
unearthed power transformer windings with
partially graded insulation.
Current transformers (all cores)
Voltage transformers
Disconnectors (aux contacts)
Power transformers
Neutral Electromagnetic couplers
Circuit-breakers
Earth switches
Drawings marked-up with on-site changes
Settings documentation marked-up with on-site
changes.
7
8
9
Power plant check sheet
Test sheets provided for
Documentation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 74 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Telecomms equipment
Telecomms equipment installed
ID/NAMEF installation cross connections:
Cables numbered and drawings updatedEarthing of equipment Station earth
resistivity checked and notedRepeater buildings, cable trays and
feeders in place
Security equipment
2 SecurityPerimeter electrified fence:
Commissioned
3 TransformerTransformer enclosure electrified:
Commissioned
4 MicrowaveMicrowave security system and control
box, etc.: CommissionedAll records updated in system book and
Network Diagram, etc.
General comments:
1 Equipment
5 Records & General
Quality Control Checksheet - Telecommunication Equipment
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 75 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Create RTU Configuration.
Create Master Station Database
Verify Communications link to Master.
Test and record AR Field Strength.
Verify correct cable termination on IDF.
Verify cable and IDF numbering.
Assemble RTU and test Configuration.
Verify all RTU-to-IDF cabling.
Simulate all Digital Inputs from IDF to
Master.Inject all Analog Inputs from IDF to
Master.Measure Control Output Voltages on IDF
when sent from Master.
Quality Control Checksheet - Telecontrol Equipment
1 Configuration
2Pre-Commissioning
[Phase 1]
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 76 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Install cross connection wiring on IDF.
Test all Digitals, Analogs and Controls
from/to Control plant Panels from RTU.Verify all Digitals and Analogs form
Equipment Panels to Master.Verify all Controls from Master to
Equipment Panels by visual confirmation of
Relay operation.
Functional testing to be done in
accordance with Commissioning
Schedule/Screed as supplied by Regional
Control.
Ensure that all system records are updated
and modifications returned to ED Project
Engineering.
Ensure that latest version Configuration
and Station Records remain on site after
completion of commissioning.
4 Commissioning
3Pre-Commissioning
[Phase 2]
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 77 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
1 EquipmentVisual check of mechanical installation and
Earthing
Wiring: (Internal and External)
Check for dry joints and loose
connections. Visual check on ID/NAMEF
3 Line-MatchingTest carried out according to Telecomms
Standards
4 Line-upLine-up: System line-up Test Sheet
completed and signed
5 AlarmsAlarms: All alarms checked from initiating
panel through to Regional Control Centre
6 Intertripping Intertripping: End-to-end intertripping
7 RecordsAll records updated in System Book and
Network Diagram, etc.
2 Wiring
Quality Control Checksheet - Telecommunication Carrier
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 78 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W)
Head of Telecomms Dept
Signature
1 Equipment InstallationVisual check of mechanical installation and
earthing
Wiring: (Internal and External)
Check for dry joints and loose
connections. Visual check on ID/NAMEF
3 Tower and Accessories Check feeder, antenna, brackets and
tower earthing
4 Earth resistivity Station earth resistivity check and noted
5 Line-up Installation and line-up sheets completed
and signed
6 Alarms Check alarms to Regional Control Centre
7 RecordsAll record updated in System Book and
Network Diagram, etc.
2 Wiring
Quality Control Checksheet - Telecommunications Broadband/Radio
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 79 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 Eskom EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
1 Switchgear operation Switchgear operates freely
2 Tools Special tools supplied where applicable
3 DrawingsDrawings and manuals on site (scheme
drawings and applicable manuals)
4 Labelling All feeders correctly labelled
5 General Excess material removed and site cleaned
Applicable certificates received from Plant
SpecialistsApplicable certificates received from Cable
Construction/ContractorApplicable certificates received from
Contractor
7 InstructionInstruction given to PT&M section to
proceed with Dead Testing.
6 Certificates
Quality Control Checksheet - Labelling & Documentation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 80 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Appointed Contractor:
4 Appointed COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
EDFS - Quality
Assurance
Check : Name
Signature
1Quality Control Checksheet for
AC/DC Auxiliary systems
2Quality Control Checksheet -
Control Wiring
3Quality Control Checksheet -
Labelling & Documentation
4Quality Control Checksheet -
Protection
5Quality Control Checksheet -
Metering
6Quality Control Checksheet -
Telecommunication Equipment
7Quality Control Checksheet -
Telecontrol Equipment
8Quality Control Checksheet -
Telecommunication Carrier
9
Quality Control Checksheet -
Telecommunications
Broadband/Radio
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Control Plant Installation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 81 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B14 – Stage 14: Commissioning Testing
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and Equipment Intact and Visually
Sound
Panel not Damaged
Panel Wired according to application drawings
supplied.
Scheme version on equipment and drawings
correspond
Panel equipment corresponds in make, model
and function to the application drawings
provided.
The panel and associated equipment is
correctly earthed.
Protection Data Capture Form Complete
All Applicable TI's and TB's implemented (detail
on PDC)
All IED Settings Correctly Applied
Relay Characteristic Tests and Logic Functions
Completed (Omicron Results Required)
DC and functional Checks as per drawing
Transducer Outputs Correct
Telecontrol: Supervisory controls operate
correctly. Alarms, indications and analogue
outputs are correct to the control centre
Test Blocks and shorting strips operate
correctly.
1
Data Capture 2
Secondary Injection Tests3
Quality Control Checksheet - Transformer Commissioning Testing
Panel Checks and Visual
Inspection
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 82 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Breaker Speed Checks – HV and MV
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current Transformer
test procedure”. These include all: HV and MV
post type CT's, HV, MV and Neutral bushing
type CT's and NEC/R CT's.
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio Tests – All Cores
Secondary Loop Tests – All Cores (Specify
Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests on 132kV CT's
Oil Level Checks on All CT's
Application of Specified CT Ratio (All Cores)
VT Tests in compliance with Distribution
Standard DISPVAEB6R0 “Voltage transformer
test procedure”
VT Polarity Tests – All Cores
VT Ratio Tests – All Cores
VT Insulation Resistance Tests
VT Checking of Oil Levels
Tan Delta Tests on all Trfr Capacitive Bushings
Transformer and Earthing transformer Tests
according to the Distribution Standard
SCSPVADJ2R0 “Procedure for the testing of
power transformers”.
Primary Injection Tests4
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 83 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Vector Group Tests
Ratio Tests
Positive Sequence Impedance Tests on all tap
positions
Zero Sequence Impedance Tests: Transformer
HV and MV and NEC/R
Insulation Resistance Tests
Frequency Response Test FRA
Winding Resistance
NER Resistance
Calibration and setting of winding and oil
temperature gauges and tripping functions
(both electromechanical and electronic). Both
Power Transformer and NEC/R
Calibration and function of Bucholtz and
pressure relief devices on both Power
Transformer and NEC/R
Tap change and tap change load diverter tests
Transformer, NECR, and attached bushings.
CT oil level checks.
Confirmation of fin valves
Operation of fans and pumps
Primary Injection Tests for Protection Circuits
Verification of applied CT Ratios;
Overcurrent and Earth Fault Tests;
Metering equipment verification tests;
Differential protection sensitivity check;
Differential stability check;
Restricted earth fault sensitivity check;
Restricted earth fault stability check
Negative phase sequence primary test;
Zero sequence elimination stability check for
differential relays
Primary Injection Tests
Primary Injection Tests
5
6
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 84 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All tripping circuits normalised and proven to
trip the circuit breakers. Main and Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and addressed
according to defect list
The transformer bay is ready to be energised.
Arrangements have been made with the
authorised person in terms of the ORHVS to
clear all outstanding work permits on this bay.
Panel Test Sheet has been completed – record
Panel Test Sheet Number in the Remarks
column
7 Primary Injection Tests
Consolidation of Test Results8
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 85 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
VT Voltage Ratio Check
Auxiliary Voltage Check
VT Phasing Check – Correct Phase Rotation
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with Control
Centre – Cross Check with values given by
IED or panel meters
On-load stability check for differential relay.
Confirm zero spill current
Directional Checks for Impedance and
directional overcurrent relays.
On load operation of tap changer.
Record power factor and loading measured by
the tap change control relay
Completion of certificate as equipment fully
commissioned
Marked Up drawings. Copy in substation, copy
to Design Office, copy to the area EDFS
office.
Handover Certificate Completed and submitted
by Head of Commissioning Team
Commissioning Test Results Complete and
Compiled
On load check results with analogue results
must be attached to commissioning results.
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings downloaded
and forwarded to EDNS Configuration and Co-
ordination
Protection Data Capture Sheet (PDCS)
On load Energisation Checks9
Final Documentation and
documentation consolidation10
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 86 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Panel and Equipment Intact and Visually
Sound
Panel not Damaged
Panel Wired according to application
drawings supplied.
Scheme version on equipment and
drawings correspond
Panel equipment corresponds in make,
model and function to the application
drawings provided.
The panel and associated equipment is
correctly earthed,
Protection Data Capture Form Complete
All Applicable TI's and TB's implemented
(detail on PDC)
All IED Settings Correctly Applied
Relay Characteristic Tests and Logic
Functions Completed (Omicron Results
Required)
DC and functional Checks as per drawing
Transducer Outputs Correct
Telecontrol: Supervisory supervisory
controls operate correctly. Alarms,
indications and analogue outputs are
correct to the control centre
Test Blocks and shorting strips operate
correctly.
Data Capture
3 Secondary Injection Tests
Quality Control Checksheet - HV Feeder Commissioning Testing
1Panel Checks and Visual
Inspection
2
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 87 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
Circuit Breaker Speed Checks
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current
Transformer test procedure”
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio Tests – All Cores
Secondary Loop Resistance Tests – All
Cores (Specify Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests
Oil Level Checks on All CT's
Application of Specified CT Ratio (All
Cores)
VT Tests in compliance with Distribution
Standard DISPVAEB6R0 “Voltage
transformer test procedure”
VT Polarity Tests – All Cores
VT Ratio Tests – All Cores
VT Insulation Resistance Tests
VT Checking of Oil Levels
Primary Injection Tests for Protection
Circuits
Verification of applied CT Ratios;
Overcurrent and Earth Fault Tests;
End to End checks to confirm Auto
Reclose, communications and
teleprotection systems operational
Primary Injection Tests4
Primary Injection Tests5
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 88 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
All tripping circuits normalised and proven
to trip the circuit breakers. Main and
Backup trip coils
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and
addressed according to defect list
The HV feeder bay is ready to be
energised.
Arrangements have been made with the
authorised person in terms of the ORHVS
to clear all outstanding work permits on this
bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
6 Normalisation of Circuits
7 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 89 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) COW Signature
New feeders – perform end to end phasing
checks.
VT Voltage Ratio Check
Auxiliary Voltage Check
VT Phasing Check – Correct Phase
Rotation
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with
Control Centre – Cross Check with values
given by IED or panel meters
Directional Checks - Impedance and
directional overcurrent relays.
Record power factor and loading
measured by numerical impedance IED
Completion of certificate: Equipment fully
commissioned
Marked Up drawings. Copy in substation,
copy to EDNS Design Office, copy to the
area EDFS office.
Handover Certificate Completed and
submitted by Head of Commissiong Team
Commissioning Test Results Complete and
Compiled
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet Completed
(PDCS)
8 On load Energisation Checks
9Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 90 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and equipment intact and visually sound
Panel not damaged
Panel wired according to application drawings
supplied.
Scheme version on equipment and drawings
correspond
Panel equipment corresponds in make, model
and function to the application drawings
provided.
The panel and associated equipment is
correctly earthed according to TQAKS008
Protection data capture form complete
All applicable TI's and TB's implemented
(detail on PDC)
All IED settings correctly applied
Relay characteristic tests and logic functions
completed (Omicron Results Required)
DC and functional checks as per drawing
Transducer outputs correct
Telecontrol: Supervisory controls operate
correctly. Alarms, indications and analogue
outputs are correct to the control centre
Test blocks and shorting strips operate
correctly.
3 Secondary Injection Tests
Quality Control Checksheet - Rural Feeder Commissioning Testing
1Panel Checks and Visual
Inspection
2 Data Capture
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 91 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Breaker Speed Checks – HV and MV
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current
Transformer test procedure”. These include
all: dog box CT’s; indoor switch gear CT’s or
post
CT’s.
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio tests – All Cores
Secondary loop tests – All Cores (Specify
Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests on 132kV CT's
Oil Level Checks on All CT's
Application of Specified CT Ratio (All Cores)
VT Tests in compliance with Distribution
Standard DISPVAEB6R0 “Voltage transformer
test procedure”. This is applicable for indoor
switchgear switching station or busbar VT’s.
VT Polarity Tests – All Cores
VT Ratio Tests – All Cores
VT Insulation Resistance Tests
VT Checking of Oil Levels
4 Primary Injection Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 92 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All tripping circuits normalised and proven to
trip the circuit breakers. Main and Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and addressed
according to defect list
The rural feeder is ready to be energised.
Arrangements have been made with the
authorised person in terms of the ORHVS to
clear all outstanding work permits on this bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
5 Normalisation of Circuits
6 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 93 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
VT Voltage Ratio Check
Auxiliary Voltage Check
VT Phasing Check – Correct Phase Rotation
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with
Control Centre – Cross Check with values
given by IED or panel meters
On-load stability check for differential relay.
Confirm zero spill current
Directional Checks for directional over current
relays.
Completion of certificate as equipment fully
commissioned
Marked Up drawings. Copy in substation,
copy to Design Office, copy to the area EDFS
office.
Handover Certificate Completed and submitted
by Head of Commissioning Team
Commissioning Test Results Complete and
Compiled
On load check results with analogue results
must be attached to commissioning results.
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet (PDCS)
7 On load Energisation Checks
8Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 94 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and Equipment Intact and Visually
Sound
Panel not Damaged
Panel Wired according to application
drawings supplied.
Scheme version on equipment and
drawings correspond
Panel equipment corresponds in make,
model and function to the application
drawings provided.
The panel and associated equipment is
correctly earthed according to TQAKS008
Protection Data Capture Form Complete
All Applicable TI's and TB's implemented
(detail on PDC)
Quality Control Checksheet - Cable Feeder Commissioning Testing
1Panel Checks and Visual
Inspection
2 Data Capture
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 95 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All IED Settings Correctly Applied
Relay Characteristic Tests and Logic
Functions Completed (Omicron Results
Required)
DC and functional Checks as per drawing
Transducer Outputs Correct
Telecontrol: Supervisory controls operate
correctly. Alarms, indications and
analogue outputs are correct to the control
centre
Test Blocks and shorting strips operate
correctly.
Breaker Speed Checks – HV and MV
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current
Transformer test procedure”. These
include all : indoor CT’s; post CT’s; dog
box CT’s.
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio Tests – All Cores
Secondary Loop Tests – All Cores
(Specify Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests on 132kV CT's
Oil Level Checks on All CT's
Application of Specified CT Ratio (All
Cores)
VT Tests in compliance with Distribution
Standard DISPVAEB6R0 “Voltage
transformer test procedure”
VT Polarity Tests – All Cores
VT Ratio Tests – All Cores
VT Insulation Resistance Tests
VT Checking of Oil Levels
3 Secondary Injection Tests
4 Primary Injection Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 96 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All tripping circuits normalised and proven
to trip the circuit breakers. Main and
Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and
addressed according to defect list
The cable feeder is ready to be energised.
Arrangements have been made with the
authorised person in terms of the ORHVS
to clear all outstanding work permits on this
bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
5 Normalisation of Circuits
6 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 97 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
VT Voltage Ratio Check
Auxiliary Voltage Check
VT Phasing Check – Correct Phase
Rotation
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with
Control Centre – Cross Check with values
given by IED or panel meters
On-load stability check for differential
relay. Confirm zero spill current
Directional Checks for overcurrent relays.
Completion of certificate as equipment fully
commissioned
Marked Up drawings. Copy in substation,
copy to Design Office, copy to the area
EDFS office.
Handover Certificate Completed and
submitted by Head of Commissioning
Team
Commissioning Test Results Complete and
Compiled
On load check results with analogue results
must be attached to commissioning results.
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet (PDCS)
7On load Energisation Checks
and result capture
8Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 98 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and Equipment Intact and Visually
Sound
Panel not Damaged
Panel Wired according to application
drawings supplied.
Scheme version on equipment and
drawings correspond
Panel equipment corresponds in make,
model and function to the application
drawings provided.
The panel and associated equipment is
correctly earthed according to TQAKS008
Protection Data Capture Form Complete
All Applicable TI's and TB's implemented
(detail on PDC)
Quality Control Checksheet - Bus Coupler Commissioning Testing
1Panel Checks and Visual
Inspection
2 Data Capture
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 99 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All IED Settings Correctly Applied
Relay Characteristic Tests and Logic
Functions Completed (Omicron Results
Required)
DC and functional Checks as per drawing
Transducer Outputs Correct
Telecontrol: Supervisory controls operate
correctly. Alarms, indications and
analogue outputs are correct to the control
centre
Test Blocks and shorting strips operate
correctly.
Breaker Speed Checks – HV and MV
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current
Transformer test procedure”. These
include all post CT’s; indoor or dogbox
CT’s.
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio Tests – All Cores
Secondary Loop Tests – All Cores
(Specify Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests on 132kV CT's
Oil Level Checks on All CT's
Application of Specified CT Ratio (All
Cores)
3 Secondary Injection Tests
4 Primary Injection Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 100 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All tripping circuits normalised and proven
to trip the circuit breakers. Main and
Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and
addressed according to defect list
The bus coupler is ready to be energised.
Arrangements have been made with the
authorised person in terms of the ORHVS
to clear all outstanding work permits on this
bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
5 Normalisation of Circuits
6 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 101 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Auxiliary Voltage Check
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with
Control Centre – Cross Check with values
given by IED or panel meters
On-load stability check for differential
relay. Confirm zero spill current
On load operation of tap changer.
Record power factor and loading
measured by the tap change control relay
Completion of certificate as equipment fully
commissioned
Final Documentation and documentation
consolidation
Marked Up drawings. Copy in substation,
copy to Design Office, copy to the area
EDFS office.
Handover Certificate Completed and
submitted by Head of Commissioning
Team
Commissioning Test Results Complete and
Compiled
On load check results with analogue results
must be attached to commissioning results.
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet (PDCS)
7On load Energisation Checks
– All results to be recorded
8Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 102 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and equipment intact and visually
sound
Panel not damaged
Panel wired according to application
drawings supplied.
Scheme version on equipment and
drawings correspond
Panel equipment corresponds in make,
model and function to the application
drawings provided.
The panel and associated equipment is
correctly earthed according to TQAKS008
Protection data capture form complete
All applicable TI's and TB's implemented
(detail on PDC)
Quality Control Checksheet - ARC Detection Scheme Commissioning Testing
1Panel Checks and Visual
Inspection
2 Data Capture
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 103 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All IED settings correctly applied
Relay characteristic tests and logic
functions completed (Omicron Results
Required)
DC and functional checks as per drawing
and to the matrix that is attached to the
panel.
Telecontrol: supervisory controls operate
correctly. Alarms, indications and
analogue outputs are correct to the control
centre
Test Blocks and shorting strips operate
correctly.
Ratio Tests – from incomer/transformer for
all master relays.
Secondary Loop Tests – All Cores
(Specify Circuits)
All tripping circuits normalised and proven
to trip the circuit breakers. Main and
Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
3 Secondary Injection Tests
4 Primary Injection Tests
5 Normalisation of Circuits
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 104 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All test that have been planned have been
completed
All test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and
addressed according to defect list
The substation switchgear is ready to be
energised.
Arrangements have been made with the
authorised person in terms of the ORHVS
to clear all outstanding work permits on this
bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
Current Measurement Check – on load
confirmation of CT Ratios
If ARC detection is added and unused CT
core is used, then mag curve of the core
only needs to be done.
Completion of certificate as equipment fully
commissioned
7 On load Energisation Checks
6 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 105 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Marked Up drawings. Copy in substation,
copy to Design Office, copy to the area
EDFS office.
Handover certificate completed and
submitted by Head of Commissioning
Team
Commissioning test results completed and
compiled
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
On load check results with analogue results
must be attached to commissioning results.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet (PDCS)
Confirmation of laminated matrix is
properly attached to the ARC detecting
panel.
P-touch information i.e. CT ratio, plug
setting, time multiplier, etc. to be marked
on panel – right hand side of relay.
8Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 106 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 EDFS:
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Panel and Equipment Intact and Visually
Sound
Panel not Damaged
Panel Wired according to application
drawings supplied.
Scheme version on equipment and
drawings correspond
Panel equipment corresponds in make,
model and function to the application
drawings provided.
The panel and associated equipment is
correctly earthed according to TQAKS008
Protection Data Capture Form Complete
All Applicable TI's and TB's implemented
(detail on PDC)
All IED Settings Correctly Applied
Relay Characteristic Tests and Logic
Functions Completed (Omicron Results
Required)
DC and functional Checks as per drawing
Transducer Outputs Correct
Telecontrol: Supervisory controls operate
correctly. Alarms, indications and
analogue outputs are correct to the control
centre
Test Blocks and shorting strips operate
correctly.
Quality Control Checksheet - Capacitor Bank Commissioning Testing
1Panel Checks and Visual
Inspection
2 Data Capture
3 Secondary Injection Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 107 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Breaker Speed Checks – HV and MV
CT Tests in compliance with Distribution
Standard DISPVAEC6R0 “Current
Transformer test procedure”. These
include all: post type CT's and imbalance
CT’s.
Polarity Test – All Cores
Magnetisation Curve Test – All Cores
Ratio Tests – All Cores
Secondary Loop Tests – All Cores
(Specify Circuits)
Insulation Resistance Tests – All Cores
Tan Delta Tests on 132kV CT's
Oil Level Checks on All CT's
Application of Specified CT Ratio (All
Cores)
VT Tests in compliance with Distribution
Standard DISPVAEB6R0 “Voltage
transformer test procedure”
VT Polarity Tests – All Cores
VT Ratio Tests – All Cores
VT Insulation Resistance Tests
VT Checking of Oil Levels
4 Primary Injection Tests
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 108 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
All tripping circuits normalised and proven
to trip the circuit breakers. Main and
Backup
All alarm circuits normalised and proven.
All IED settings normalised as per
documentation provided by EDNS
Configuration and Co-ordination.
All IED configuration logic and protections
function normalised as per documentation
provided by EDNS Configuration and Co-
ordination
All Test that have been planned have been
completed
All Test results obtained are consistent with
reasonable engineering expectations
All defects have been itemised and
addressed according to defect list
The capacitor bank is ready to be
energised.
Arrangements have been made with the
authorised person in terms of the ORHVS
to clear all outstanding work permits on this
bay.
Panel Test Sheet has been completed –
record Panel Test Sheet Number in the
Remarks column
5 Normalisation of Circuits
6 Consolidation of Test Results
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 109 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Item Checklist QC items to check or supplyHolding Point
Required (Y/N)
Photo Required
(Y/N)Contractor Signature
Verified (V)
Witnessed (W) EDFS Signature
Neutral Spill must be recorded before
adjustment and after adjustment.
Relay adjusted
Record capacitance of each Cap with
serial number
Record Imbalance
VT Voltage Ratio Check
Auxiliary Voltage Check
VT Phasing Check – Correct Phase
Rotation
Current Measurement Check – on load
confirmation of CT Ratios
Verification of Analogue quantities with
Control Centre – Cross Check with values
given by IED or panel meters
Record Harmonic readings
Completion of certificate as equipment fully
commissioned
Marked Up drawings. Copy in substation,
copy to Design Office, copy to the area
EDFS office.
Handover Certificate Completed and
submitted by Head of Commissioning
Team
Commissioning Test Results Complete and
Compiled
On load check results with analogue results
must be attached to commissioning results.
Proof of implementation of Technical
Instructions and Bulletins – document
completed.
Proof of applied settings – settings
downloaded and forwarded to EDNS
Configuration and Co-ordination
Protection Data Capture Sheet (PDCS)
7 On load Energisation Checks
8Final Documentation and
documentation consolidation
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 110 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:
Item Checklist
Contractor -
Quality
Assurance
Check : Name
Signature
EDFS - Quality
Assurance
Check : Name
Signature
1
Quality Control Checksheet -
Transformer Commissioning
Testing
2Quality Control Checksheet - HV
Feeder Commissioning Testing
3
Quality Control Checksheet -
Rural Feeder Commissioning
Testing
4
Quality Control Checksheet -
Cable Feeder Commissioning
Testing
5Quality Control Checksheet - Bus
Coupler Commissioning Testing
6
Quality Control Checksheet -
ARC Detection Scheme
Commissioning Testing
7
Quality Control Checksheet -
Capacitor Bank Commissioning
Testing
Accepted by Project Manager:
Name Signature Date
Handover Checklist for Commissioning Testing
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 111 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B15 – Stage 15: Provisional Handover
1 Project name:
2 Contract/Order No:
3 Project Manager:
Stage ActivityHandover per stage
completed (Y/N)
Received by Project
ManagerDate
1 Civil Works: Platform
2 Civil Works: Control Building
3 Civil Works: Subsoil drainage
4 Civil Works: Earthmat Installation
5Civil Works: Equipment Foundations &
Cable trenches
6 Civil Works: Roads, Stoning & Kerbing
7Transformer bund wall, oil dam and fire
wall
8 Steelwork Erection
9 Fencing
10Power Transformer Delivery &
Assembly
11 Primary Equipment Installation
12 Conductors, busbars & clamps
13 Control Plant installation
13 Commissioning Testing
Accepted by: Project Manager (Name & Signature) Date
Accepted by: Senior Design Engineer (Name & Signature) Date
Accepted by: Control Plant Maintenance Manager (Name & Signature) Date
StageConfirmed by Project
ManagerDate
1
2
Accepted by: Project Manager (Name & Signature) Date
Accepted by: Network Operations Manager (Name & Signature) Date
Station Electric Diagram updated and SCADA updated at Control
Operating procedure for commissioning complete
(Project Provisionally handed over for final Commissioning)
Plant and Equipment provisionally handed over and pre-commission testing completed in order to arrange final
commissioning
Activity
Document Classification: Controlled Disclosure
QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION
Unique Identifier: 34-1238
Revision: 0
Page: 112 of 112
ESKOM COPYRIGHT PROTECTED
When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
Annexure B16 – Stage 16: Final Handover
1 Project name:
2 Contract/Order No:
3 Name of Project Manager:
Stage ActivityHandover per stage completed
(Y/N)
Received by Project
ManagerDate
1 Civil Works: Platform
2 Civil Works: Control Building
3 Civil Works: Subsoil drainage
4 Civil Works: Earthmat Installation
5Civil Works: Equipment Foundations
& Cable trenches
6Civil Works: Roads, Stoning &
Kerbing
7 Steelwork Erection
8 Fencing
9Power Transformer Delivery &
Assembly
10 Primary Equipment Installation
11 Conductors, busbars & clamps
12 Control Plant installation
13 Commissioning Testing
14 Final Commissioning Complete
Accepted by: Project Manager (Name & Signature) Date
Accepted by: Senior Design Engineer (Name & Signature) Date
Accepted by: Asset Design Manager (Name & Signature) Date
Accepted by: Control Plant Maintenance Manager (Name & Signature) Date
Accepted by: Zone Manager (Name & Signature) Date
POWERLINE / SUBSTATION HAND-OVER ENVIRONMENTAL CHECKLIST
Name of Powerline/Substation :________________ Project I. D:______________________
Contractor:_________________________________ Clerk of Works:___________________
QUESTION Y / N / NA
ACTION TAKEN REQUIREMENTS / SPECIFICATIONS
Restriction of working areas
1. Have construction activities remained within the designated working areas?
EMP
Vegetation Management
2. If required, were the relevant permits obtained for the cutting of protected trees and fynbos? i.e. milkwood
EMP
3. Has bush clearing been done according to the Standard for Bush Clearance and maintenance within Overhead Powerline Servitudes (ESKASABG3)
ESKASABG3 / EMP
4. Have all the bush cuttings been removed from the servitude and substation?
EMP
5. Has all herbicide spraying been undertaken under the supervision of a registered Pest Control Officer.
EMP
6. Was all herbicide usage undertaken according to Eskom’s guidelines and the Standard for the Safe Use of
Pesticides and Herbicides (ESKASAAL0)?
ESKASAAL0 / EMP
7. Are there any signs of damage by herbicides to the owner’s property?
EMP
8. If yes, have measures been implemented to rehabilitate the damage caused?
EMP
Oil Spill Management
9. Have any oil or diesel spills occurred on site?
10. If yes, was a flash report issued within 24 hrs to the Environmental Management Department?
Flash Report
11. Have oil spills been managed according to the Standard for Oil Spill Clean-Up and Rehabilitation – ESKASABT0 (i.e. spills are cleared up on site)
ESKASABT0 / EMP
12. Was there stock of oil remediation chemicals on site?
EMP
13. Have bund walls been constructed, where appropriate?
EMP
Soil Erosion
14. Have any complaints been received from property owners regarding occurrence of erosion on their properties as a result of construction activities?
Complaints record / letters
15. Were any signs of erosion visible before site handover?
EMP
16. If yes, have measures been implemented to rehabilitate eroded areas?
EMP / Audit / Inspection Reports
Topsoil Management
17. Has all the topsoil been backfilled or levelled on site?
EMP
Fire Management
18. Were the emergency numbers available on site?
Emergency numbers / EMP
19. Have any incidents of veld fires occurred? Flash Report / EMP
20. Was there sufficient fire fighting equipment on site?
EMP
Disturbance to the Natural Heritage Resources
21. Were tribal graves or archaeological sites identified during the construction activities?
EMP (if relevant)
22. If yes, were recommendations/mitigation measures implemented, where appropriate?
EMP (if relevant)
Access
23. Has the existing single access route been used? (No multiple tracks allowed)
EMP
24. Have additional access routes been developed?
EMP
25. If yes, have existing / additional access routes been rehabilitated to the owners satisfaction?
EMP
26. Were entrance gates and walls rehabilitated to the property owners satisfaction?
EMP / Owners letter (if possible)
Water Management
27. Had any incidents of water pollution occurred?
EMP
28. If yes, was a flash report issued within 24hrs to the Environmental Management
Flash Report
Department?
29. Was the incident investigated and recommendations implemented?
Incident Report (if applicable)
Social Issues
30. Were any complaints registered and actioned?
Complaints / Incident register / Letters
Waste Management
31. Were there sufficient waste bins on site? EMP
32. Was litter noted during site handover? EMP
33. Has all waste material been removed and suitably disposed of at a licensed landfill site?
EMP / Waste disposal certificate
Use of cement and/or concrete
34. Was any excess cement of concrete noted during the site inspection?
EMP
35. If yes, has this been removed and disposed of, prior to site handover?
EMP
Environmental Records
36. Have the conditions of the Record of Decision (“ROD”), relevant to the construction phase of the project, been implemented?
Record of Decision (or signed copy of the Distribution Screening Document)
37. Are there special mitigatory conditions in the EMP?
EMP
38. If yes, have all the conditions in the EMP, relevant to construction been implemented?
EMP
39. Have all the recommendations from the environmental audits (e.g. by COW, PC, Environmental Practitioner) been undertaken?
Audit Reports
Site Rehabilitation
40. Have measures been implemented for site / vegetation rehabilitation, where required?
EMP / Inspection / Audit reports
To be completed by the Clerk of Works (COW) and Contractor:
Taken over by: ……………………………………………… Date: ……………………………………. (C.O.W) (NAME IN BLOCK LETTERS)
Signature: ……………………………………………………… Date: ……………………………………. (C.O.W)
Handed over by: ……………………………………………… Date: ……………………………………. (Contractor) (NAME IN BLOCK LETTERS)
Signature: ……………………………………………………….. Date: ……………………………………..
1
SHE SPECIFICATION
Document Classification: Controlled Disclosure/Confidential Title:
SAFETY HEALTH AND ENVIRONMENTAL SPECIFICATION FOR VYEVLEI S/S
Reference: 32-524
Document Type: DSP
Revision: 0
Effective date: 20.11.2012 Total pages: 31 Revision date: 20.11.2013
COMPILED BY FUNCTIONAL RESP AUTHORISED BY
_ _ _ _ _ _ _
P Rilityane
_ _ _ _ _ _ _
S Ralarala
_ _ _ _ _ _ _
S. POTELWA
SHE OFFICER PROJECT CO-ORDINATOR RISK MANAGER
2
Table of Contents:
Item Contents Page #
1 Introduction 3
1.1 Purpose and Scope of Specification 3
1.2 Project works information, Scope of work and other detail 3
1.2.1 Location 3
1.2.2 Scope of Work 3
1.3 Normative and Informative references 4
2 Definitions and Abbreviations 4-5
3 Documentation required – Tender submittal 6
4 Administrative Requirements 7
5 Construction Requirements 15
Annexure 1 19
Annexure 2 20
Annexure 3 21 -28
Annexure 4 29
Annexure 5 30
3
1. INTRODUCTION
Eskom’s responsibility and commitment to ensure a safe working environment are in line with our Safety, Health, and Environmental Policy, along with legislative obligations. The objective of this Specification is to outline the requirements appropriate to the Occupational Health and Safety Act 85/1993 and Regulations and to ensure that a common approach is adopted when engaging in construction work.
1.1 Purpose and Scope Purpose of Specification: To provide a framework for Health, Safety and Environmental Requirements relevant to the work to be done so as to ensure the Health and Safety of persons. These specifications shall act as the basis for the drafting of the principal contractors’ and contractors’ construction phase Health & Safety plans
Scope:To ensure compliance with the Occupational Health and Safety Act (85/1993) and Regulations associated therewith so as to protect persons at work, persons working with plant and machinery and persons other than those persons at work from health and safety hazards arising out of or in connection with activities of persons at work.
1.2 Project works information, scope of work, and other details 1.2.1 Location:
1.2.2 Scope of Work:
Karoo substation is located near the town of Carnarvon. Geographical coordinates - 22°9’7.2” E 30°52’24” S
Primary Plant Replace all old 66kV and 22kV equipment with new equipment. Normalise transformer bays by equipping each bay with a 66kV circuit breaker. Standardise transformer 1 & 2 plinth and bund areas. Replace section of perimeter fence with new diamond mesh fence and modify with chicken wire and electrify as existing fence. Install new section of internal diamond mesh fence. Install new substation lights fitted on 8m masts. Lay new section of control cable trench. Normalise existing 22kV Loxton feeder by relocating the feeder position to “bottom” of 22kV busbar. Create an extra new 22kV feeder bay. Install 22kV reclosers for feeder breakers.Install a 33kV recloser with 33kV VTs and surge arrestors in transformer 3 & 4 earth path.TSG transformer workshop to refurbish existing transformer 1 & 2 on site. Control Plant Use existing building. Install new 4TM7100 and 4TC5200 schemes for transformer 1 & 2. Install recloser control box in relay room for the two MV feeders. Install statistical metering on the transformers and MV feeders. Install new modules in AC/DC panel. Install new lead acid battery bank in existing battery room.
4
1.3 Normative and Informative references:
Parties using this specification shall apply the most recent edition of the documents listed below:
! Occupational Health and Safety Act 85 of 1993 and Regulations
! 32-136: Construction Safety, Health and Environment Management
! 34-333: OHS Act Requirements to be met by Principal Contractors Employed by Eskom Distribution.
! ESKPVAEY6: Operating Regulations for High Voltage Systems
! 32-93: Eskom Vehicle and Driver Safety Management procedure
! 32-95: Eskom Incident/ Accident management procedure
! National Environmental Management Act 107/1998
! Compensation for Occupational Injuries and Diseases Act
! Basic Conditions of Employment Act 75/1997
! Labour Relations Act 66/1995
! National Road Traffic Act 93/1996
2. DEFINITIONS AND ABBREVIATIONS (To be read in conjunction with definitions contained in OHS Act 85/1993 and Regulations)
2.1 Definitions
Client: means the Eskom 16.2 appointed person directly involved and for whom construction work is performed on the basis of a contractual agreement formally entered into with either an agent or a principal contractor (external to Eskom).
Competent Person: means any person having the knowledge, training and experience specific to the work or task being performed: provided that where appropriate qualifications and training are registered in terms of the South African Qualifications Authority Act, 1995 (act 58 of 1995), these qualifications and training shall be deemed to be the required qualifications and training.
Contractor: means an employer, as defined in section 1 of the OHSA, who performs construction work for the client either directly or through an agent and includes principal contractors and the subcontractor.
Employer: means any person who employs or provides work for any person and remunerates that person or expressly or tacitly undertakes to remunerate him/her.
Eskom requirements: Eskom requirements flowing out of directives, policies, standards, procedures, specifications, work instructions, guidelines, or manuals.
Fall arrest system: a system used to arrest an employee in a fall from an elevated working level. It consists of an anchor point, connectors, and a body harness and may include a lanyard, deceleration device, lifeline, or suitable combinations of these, BUT excludes body belts. The entire system must be capable of withstanding the tremendous impact forces involved in stopping or arresting the fall.
Fall prevention equipment: means equipment used to prevent persons from falling from an elevated position, including personal equipment, body harnesses, body belts, lanyards, lifelines or physical equipment, guardrails, screens, barricades, anchorages, or similar equipment.
Fall protection plan: means a documented plan of all risks relating to working from an elevated position, considering the nature of work undertaken and setting out the procedures and methods to be applied in order to eliminate the risk.
Method statement or safe working procedure means a written document detailing the key activities to be performed in order to reduce the hazards identified in any risk assessment.
5
On site/site: any workplace where the contractor or his/her employees perform contract-related work.
Pre-job brief meetings: a meeting that is held prior to the commencement of the day’s work with all relevant personnel associated with the work task in attendance. The job, relevant procedures, associated hazards, and safety measures, that is, the task risk assessments, shall be discussed. Each employee who attends the briefing shall sign an attendance register. The toolbox topics will be based on SHE issues pertaining to the construction site.The topic contents shall be in writing.
Principal contractor (PC): means an employer, as defined in section 1 of the Act, who performs construction work and is appointed by the client or the client’s agent to be in overall control and management of a part of, or the whole of, a construction site.
Project manager: means the person who has the responsibility for the successful planning and execution of a project. The project manager must satisfy the certification requirements set by the South African Council for the Project and Construction Management Professions.
Risk assessment: means a programme to determine any hazard at a construction site and to identify the steps needed to remove, reduce, or control such hazard.
Safety, health, and environmental (SHE) specification: means a documented specification of significant residual SHE requirements for a construction site, which a competent and resourced principal contractor or subcontractor would not have been aware of. This is to ensure the health and safety of persons, both workers and the public, and duty of care for the environment. The client/agent compiles the SHE specification, which shall be specific to each construction project.
Safety, health, and environmental file: means a permanent record, containing the information on the SHE management system during construction and all information relating to the post-construction phase after the handover to client, so that the client can maintain the works in a healthy and safe way.
Safety, health, and environmental plan: means a written plan that addresses hazards identified during a risk assessment as well as the identified impacts in the SHE specification. This would include safe work procedures to mitigate, reduce, or control the hazards identified. It is specific to each construction project undertaken, is compiled by a principal contractor or subcontractor, and must be approved by the client or agent. Both the principal contractor and the client (or agent where applicable) shall be signatories to the SHE plan once acceptable.
Subcontractor: means a contractor who is employed by a principal contractor and has no direct formal agreement of employment with the client/agent.
2.2 Abbreviations
AIA: approved inspection authority CE: Chief Executive COID Act: Compensation for Occupational Injuries and Diseases Act CR: Construction Regulations DMR: Driven Machinery Regulations EAP: Employee Assistance Programme EDC: Eskom Documentation Centre EMR: Electrical Machinery Regulations EMP: Environmental Management Plan EIA: Environmental Impact Assessment GAR: General Administrative Regulations GMR: General Machinery Regulations GSR: General Safety Regulations HCS: Hazardous Chemical Substances ICAS: International Counselling and Advisory Services MD: Managing Director
6
MSDS: Material Safety Data Sheet PPE: Personal Protective Equipment ROD: Record of Decision SHE: Safety, Health and Environment OHS Act: Occupational Health and Safety Act 85/1993 ORHVS: Operating Regulations for High-voltage Systems SANS: South African National Standards PER: Pressure Equipment Regulations
3. Documentation Required – Tender Submittal
The following documentation must be provided with the tender submittal in order to assist with the evaluation in terms of SHE performance, which in turn will assist with the selection of contractors. Should the requested information not be provided then it would be assumed that it does not exist.
! Letter of good standing for workmen’s compensation from insurance body (e.g. WCC).
! An organogram stipulating the positions of all the persons proposed by the Contractor who would hold legal appointments on the project in terms of the prescribed legislation. (SHE Rep, First Aider & Construction Supervisor etc.)
! The expected roles and responsibilities of those who are proposed to receive legal appointments.
! Based on the SHE Specifications / requirements reflected within this document including the intended scope of work, submit a SHE Plan in terms of regulation 5(4) of the Construction Regulations, 2003. (OHS Act, 1993)
! Provide an overview of your risk assessment process (methodology i.e. how, when, who, what, where, why) as well as examples of completed assessments (baseline risk assessments and issue based risk assessments).
! Competency and training records (SHE Rep, First Aider, Risk Assessor, Supervisor)
! Safety Stats for the past two years
The above information to be compiled as per Tender Evaluation Questionnaire – Annex 1- attached. Information must be contained in a folder with a contents page and dividers between various documents. The same numbering system as is reflected within this document, to be adopted. The folder must then be submitted as an annexure to the tender document.
7
4. Administrative Requirements
4.1. Notification of Construction Work The Contractor must notify the Provincial Director (D.O.L) in writing prior to construction work commencing as per CR 3. Copy of the notification and proof thereof to be kept in site safety file
4.2. Appointment of Contractor – CR 4(1) (c) Copy of above appointment by client to be kept in site safety file. Appointment shall only be done after Client has satisfied him / herself that the potential contractor has the necessary competencies required to do the work as per Tender Evaluation Questionnaire.
4.3. Compensation for Occupational Injuries and Diseases The contractor must submit proof of registration (Letter of Goodstanding) with the compensation fund or with a licensed compensation insurer for his/her company and each of his/her subcontractors. This must remain valid for the duration of the contract. The Letter of Goodstanding must reflect the name of the contractor and/or subcontractor company.
4.4. Cost of Health and Safety All contractors tendering to do work on this project must ensure that they have made provision for the Cost of Health and Safety so as to comply with this specification, OHSA 85/1993 and Regulations. Items to be considered: Training; PPE; Site laydown incl. fencing, access control, Signage; Medical surveillance; Welfare facilities; demarcation etc. The above is extracts of items that should be considered but is not exhaustive.
4.5. Mandatory Agreement In terms of section 37(2) of the OHS Act, it shall be required of every contractor to sign such an agreement with Eskom. Where a contractor appoints a sub-contractor the same shall apply. Where a Contractor appoints a sub-contractor the sub- contractor must also be on the Eskom database.
4.6. Organisational Structure The contractor’s organisational SHE structure shall be provided in the form of an Organogram. The organogram shall reflect intended appointments in cases where such appointments have not been made yet. Organogram to be updated when changes in SHE structure and dated accordingly.
4.7. Competency All persons deemed competent should have the necessary training, experience and qualifications specific to the task being performed. Proof of competency to be attached to relevant appointments.
4.8. Appointments The contractor, as defined in the contract, shall ensure that all site-related appointments are in place prior to work commencing and that it is specific and indicate for which areas within the OHS Act individuals are responsible.
The contractor shall ensure that all his/her appointees are made aware of their accountabilities and responsibilities in terms of their appointment and that he/she advises and assists these appointees in the execution of their duties.
Copies of any appointments made by the contractor shall be included in the health and safety plan and be provided to the client. Appointments to be accompanied by relevant training / competency. Typical examples of statutory appointments: see Annexure 2 attached
8
4.9. Training and Competence
The aim of this section is to outline Eskom’s expectations in respect of the scope of the training that the contractor and subcontractor employees receive. The scope of the training includes, but is not limited to, the type of work being performed and the relevant procedures. Additional to the requirements will be that the contractors and subcontractors will have the appropriate qualifications, certificates, and tickets and will be under competent supervision. Records of all training and qualifications of all contractor employees must be kept. The contractor shall for the duration of the contract, maintain comprehensive records of all employees under his/her control (including all employees of the subcontractor) attending induction training. Acknowledgement of receiving and understanding the induction must be signed by all persons receiving the induction. All training needs shall be identified and considered in SHE plan. See training needs attached – Annex 4
When there is an amendment to the Acts and/or to the regulations, SHE specification, and SHE plan, all affected staff shall undergo the relevant retraining as soon as reasonably practicable
General construction site induction carried out by the contractor - Induction
The contractor shall ensure that all his/her employees and subcontractor employees undergo general work induction with regard to the approved SHE plan, general hazards prevalent on the construction site, construction risk assessment, rules and regulations, and other related aspects prior to commencing work on site. Proof of such training will be kept in site safety file. The induction should also include identification of sensitive features such as wetlands/vlei areas, red data species, graves, etc.
Job-specific induction carried out by the contractor/subcontractor supervisor on the site - Daily Safety Task Analysis
The contractor is required to ensure, before an employee commences work on the project, that the supervisor in control with responsibility for the employee has informed the employee of his/her scope of authority, any hazards associated with the work to be performed, as well as the control measures to be taken. This will include man-task specifications and the discussion of any standard task procedures or hazardous operational procedures to be performed by the employee. The contractor is to ensure that the supervisor has satisfied himself/herself that the employee understands the hazards associated with any work to be performed by conducting task/job observations.
Proof of job-specific induction signed by inductor and trainee must be kept in the health & safety file.
Awareness – the Contractor shall conduct weekly on site toolbox talks, display posters and contract statistics regularly and before any hazardous work takes place. Records of attendance must be kept in the health and safety file. Safe Work Procedures shall be discussed with workers and signed attendance registers kept of communication thereof.
Site Visitor Induction Training Visitors to the site shall be required to undergo and comply with site-specific safety induction requirements prior to being allowed access to the site. All visitors must remain in the care and custody of a person (host) who has been properly inducted. No visitors are permitted to undertake any construction work of any nature.
4.10. SHE COMMUNICATION
Occupational Health and Safety Act - Sections 17, 18, 19, and 20
9
The contractor shall provide a communication strategy outlining how he/she intends to communicate SHE issues to his/her staff and, where appropriate, his/her subcontractors and their staff, the mediums he/she will employ, and how he/she will measure the effectiveness of his/her SHE communication. The contractor shall ensure that safety representatives are trained and appointed and SHE committee formed and shall perform all statutory functions. Monthly SHE Meetings shall be held on site and records of these meetings shall be kept in site safety file as well as signed attendance registers of such meetings. Matters to be discussed shall include, but are not limited to the following:
! Accident/safety incidents
! Accident investigations (including near misses) and close-out of recommendations
! Audit findings and close-out
! Hazardous materials/substances
! Work procedures
! Protective clothing/equipment
! Housekeeping
! Work permits
! Non-conformances
! Emergency preparedness
! Medicals
! Training
! Forthcoming high risk activities
! General SHE issues
! Matters arising from contractors’ SHE meetings
4.11. Access Control To The Construction Site
The contractor in collaboration with the Client’ Representative and Protective Services will ensure that proper access control is in place and functional at all times for all persons working on site. All contractor employees shall be identifiable as Eskom contractor employees and be issued with contractor identification cards. Contractor identification cards shall be carried on person at all times. Emergency contact numbers to be on back of access cards for workers and visitors. All visitors to site shall sign in on Visitor Access Control Register. Where there is construction vehicles and mobile plant on site then the contractor shall draft a site traffic plan, communicate this to all and demarcate such traffic routes. This plan shall be reviewed at the monthly safety meeting to ensure its applicability. All security requirements shall be highlighted at the general construction site induction. All contractors shall adhere to site security requirements
4.12. Incident Management
The contractor shall have an incident reporting system that is compatible and complies with Eskom’s Incident Management Procedure: 32-95, Section 24 of OHS Act 85/1993, GAR 8 & 9 and all other applicable legislation. Any incident or near miss involving the clients, contractors, or third-party’s personnel, property, plant, or equipment shall be reported as soon as reasonably practicable, but not later than 24 hours, to the client representative, irrespective of whether injury to personnel or damage to property or equipment resulted. Notification to be done as per Annexure 5 – Flash Report. The contractor shall investigate the causes of all incidents and shall within seven working days, provide the client with the results of the investigation and recommendations on how to prevent a recurrence. The client reserves the right to designate a representative to participate in the investigation at the client sole discretion. The principal contractor shall keep on site/at the workplace a record of all accidents and incidents reported as per Annexure 1 – Recording and Investigating of Incidents - of General Administrative Regulations (GAR 9).
10
The principal contractor shall provide SHE-related statistics to the client at the end of each month. Eskom reserves the right to conduct an independent investigation in any incident.
4.13. Hazard Identification and Risk Management, Safe Work Procedures, Fall Protection
The contractor shall cause hazards and potentially hazardous work operations to be identified by a competent person appointed in writing before commencement of construction work. The intent being to: (a) Highlight construction site SHE risks and hazards, (b) Ensuring that the site hazards and activity risks and the mitigating measure has been considered in Contractors risk assessments, (c) Method statements or written Safe Work Procedures are drafted for all the contractor activities and (d) Emerging risks and hazards are managed during construction work. For each work operation identified, the contractor shall supply a risk assessment, which shall:
! describe the operation to be performed in the sequence of the basic job steps;
! identify and rank the hazard or potential hazard;
! describe how the hazard will be managed; and
! identify the responsible person for each mitigation action.
The contractors risk assessments shall be reviewed on a monthly basis, when designing new job or task, change in job or task or introduction of new equipment and updated accordingly. Updated risk assessments shall be communicated with all employees and proof of such communication kept in the site safety file. The site and project specific hazards are attached in Annexure 3 in this SHE specification in order to make potential Contractors aware of the hazards. The list is by no means exhaustive and should not be limited to these activities, but must cover all activities that form part of the said construction work. A Fall Protection Plan shall be drafted by a competent Fall Protection Plan Developer. Appointment and Proof of competency of Fall Protection Plan Developer shall be kept in site safety file. Fall Protection Plan shall consider all fall hazards from elevated position (falls from, on and into). The Fall Protection Plan shall include: (1) Risk assessment of all work performed from elevated position including procedures and methods used to address risks, (2) Process for evaluating employees physical and psychological fitness to work in elevated positions and records, (3) Programme for maintaining, testing of Fall protection equipment. Fall protection Plan shall be updated on a monthly basis and proof kept in site safety file. Fall Protection Plan shall be drafted in accordance with CR 8. Contingency Plan in the event of a fall from elevated position shall also be considered.
4.14. Occupational Health, Hygiene, Rehabilitation and Welfare
The aim of this section is to stipulate Eskom’s requirements with regard to occupational health and hygiene practices and welfare facilities expected from the contractors and their subcontractors.
4.14.1. Workers’ Compensation The contractor must submit proof of registration and a letter of good standing with the compensation fund or with a licensed compensation insurer for his/her company and each of his/her subcontractors. This must remain valid for the duration of the contract. The letter of good standing must reflect the name of the contractor and/or subcontractor company.
4.14.2. Protection from adverse weather conditions Hot and humid conditions Contractors shall take into consideration and mitigate dehydration and exhaustion of employees. Wet, Windy and cold conditions Contractors shall take into consideration and mitigate inclement and extreme weather conditions.
11
4.14.3. Medical surveillance programme Contractors shall submit details of their employee health and wellness programme as part of their health and safety plan The contractor must ensure that his/her employees and subcontractor employees shall be registered on a medical surveillance programme and shall be in possession of a valid medical health certificate. A certificate of fitness is also required that is relevant to the type of work (risk-based) that the employee will be carrying out.
4.15. Emergency Procedures The contractor shall draft emergency procedures for the site and ensure that such emergency procedures are communicated to all. Proof of communication to be kept in site safety file. A list of emergency numbers must be posted at phones and in every office. The contractor must ensure that his/her employees, visitors and subcontractor employees are familiar with the emergency procedures and numbers. Emergency contact numbers shall be provided to all employees, sub contractor employees and visitors to site. The emergency contact numbers shall be provided on back of site access cards.
Eskom has established a contract with Euro Assistance for all employees and its contractor employees for emergency medical assistance needed while on duty anywhere in South Africa. The telephone number is 0861 2ESKOM or 0861 237566.
4.16. Welfare Facilities and First aid4.16.1 First aid Contractor shall outline first aid arrangements in SHE Plan. Contractors shall have a first-aid box on site at all times and ensure that a certified first aider is on site at all times. Contractors shall have one first-aid box for the first five persons and, thereafter, one for every 50 or team of workers on site or part thereof. More first-aid boxes shall be provided if the risks, distance between work teams, or workplace requirements require it (it should be available and accessible for the treatment of injured persons at that workplace). Minimum contents of a first-aid box (GSR 3): Item 1: wound cleaner/antiseptic (100 ml) Item 2: swabs for cleaning wounds Item 3: cotton wool for padding (100 g) Item 4: sterile gauze (minimum quantity 10)Item 5: one pair of forceps (for splinters) Item 6: one pair of scissors (minimum size 100 mm) Item 7: one set of safety pins Item 8: four triangular bandages Item 9: four roller bandages (75 mm x 5 m)Item 10: four roller bandages (100 mm x 5 m)Item 11: one roll of elastic adhesive (25 mm x 3 m)
Item 12: one non-allergenic adhesive strip (25 mm x 3 m) Item 13: one packet of adhesive dressing strips (minimum quantity 10 assorted sizes) Item 14: four first-aid dressings (75 mm x 100 mm) Item 15: four first-aid dressings (150 mm x 200 mm) Item 16: two straight splints Item 17: two pairs large and two pairs medium disposable latex gloves Item 18: two CPR mouth pieces or similar devices
A prominent notice or sign shall be displayed at the work place in a conspicuous place, indicating where the first-aid box or boxes are kept as well as the name and contact details of the first-aider. The contractor and subcontractor shall ensure that alternative arrangements shall be made for possible incidents occurring after normal working hours. A first aid register shall be kept in the first aid box and contents of first aid box inspected on a monthly basis
4.16.2 Welfare facilities – CR 28 The following welfare facilities shall be provided in a clean and suitable condition, unless an agreement is reached with the client representative regarding the use of existing facilities:
12
Sanitary facilities for male and female staff – 1 for every 15 Sheltered Changing facilities for male and female Sheltered Eating areas Potable Drinking water at strategic locations on site
4.17 Signage The contractor(s) shall use all symbolic safety signage that conforms to the requirements of SANS and/or applicable legislative requirements. The display of the following signs is mandatory: For contractors with site establishment: the contractor company sign must be posted at their site offices to reflect the name and contact details of the construction supervisor, first-aider, health and safety representative. Site office location, Visitors to report to site office, location of every first-aid box, fire extinguisher, and emergency exit and assembly points to be clearly indicated by means of a sign. When in use, an explosive-powered tool shall have a sign warning people of its use. The contractors shall provide signage where work is conducted and where unauthorised entry is prohibited and/or where alerting and cautioning passers-by to be aware of potential dangers.
4.18 Personal Protective Equipment (PPE) In terms of Section 8 of the OHS Act, the duty of the employer is to take steps to eliminate or mitigate (hierarchy of control measures) any hazard or potential hazard to the safety or health of employees before resorting to PPE. PPE matrix shall be drawn up and reviewed as required. Training regarding issue, use, maintenance and care of PPE shall be provided to all workers and signed attendance registers of such interventions kept in site safety file. Relevant notices and signs shall be displayed where required. Detailed PPE program shall be outlined in Safety Plan. Refer to General Safety Regulation 2 of the OHS Act. Strict non-compliance measures must be administered for any employee not complying with the use of PPE.
4.19 SHE Plan
The SHE plan is a detailed document comprising of specific plans and programmes for implementing the health, safety, and environmental requirements of the contract i.e. Site Safety Management System and shall be supported by relevant documentation. SHE Plan will be drafted by Contractor after receiving Clients specification for the project. The SHE plan shall meet requirements of OHS Act 85/1993 and Regulations, other Legislative Requirements and be aligned to Client Site Specification. SHE Plan must then be submitted by Contractor to Client for Client approval, 10 days before implementation on site. SHE Plan must be reviewed so as to determine applicability.
Following find a guide for contents of SHE Plan. This list is not exhaustive and other items might be added or some might be omitted due to scope of work. Each Safety Plan must be site specific.
! Introduction, Purpose, Scope, Contact details
! Organisational Structure (Organogram) and Appointments
! Exemptions and / or Notifications (D.O.L)
! SHE Policy ( Policy statement)
! Compensation Insurance
! HIRA Process, Fall Protection Plan, Safe Work Procedures
! PPE (Issue, management and control)
! Inspection Registers (Type, Frequency, Non compliance / deviation management)
! Training and Awareness (Types, Proof of training, Frequency, Non-compliance management etc)
! Site lay down area
! First aid and Welfare ( Requirements, Management etc)
13
! Emergency and Evacuation procedure (Management,Notification, Implementation, Drills, Responsibilities, Communication etc)
! Incident Management Process ( Incident types, Management of incident types – Reporting, Recording, Investigation, Analysis,Communication and Non-compliance management)
! Medical Surveillance Plan
! HCS (Types, Management, communication etc)
! Site statistics (Data collection, Analysis, Client feedback etc)
! Inspections and Audits ( Work area, Plant and Machinery, Contractors etc)
! Site and Statutory Meetings (Frequency, Agenda etc)
! Contractor Management ( Contractor assessment, Compliance management, SHE Plans etc)
! SHE Plan Review
4.20 Legal Compliance Contractors on the project site shall comply, as a minimum, with all relevant legislation, South African National Standards, or international standards and with the client’s policies and procedures, which include, but are not limited to the following:
The Constitution of the Republic of South Africa (particularly section 24 of the Bill of Rights) Occupational Health and Safety Act 1993 (Act 85 of 1993) and its Regulations National Environmental Management Act 1998 (Act 107 of 1998) Environment Conservation Act 1989 (Act 73 of 1989) National Water Act 1998 (Act 36 of 1998) Conservation of Agricultural Resources Act 1983 (Act 43 of 1983) COID Act Any other applicable South African legislation Applicable South African National Standards (SANS) Applicable international standards Operating Regulations for High-voltage Systems Plant Safety Regulations (Low-voltage Regulations) Construction SHE Management Procedures Work-at-height Procedures Incident Management Procedures Eskom SHE Policy Eskom Cardinal Rules
It is the duty of the contractor(s) and their subcontractor(s) to ensure that they are familiar with all the necessary SHE legislation required for implementation on this project.
Eskom has implemented five rules that apply to all Eskom employees and contractors. These are as follows:
Rule 1 – Open, isolate, test, earth, bond, and/or insulate before touch Rule 2 – Hook up at heights Rule 3 – Buckle up Rule 4 – Be sober Rule 5 – Ensure that you have a permit to work
These Cardinal Rules are non-negotiable health and safety rules that must not be broken under any circumstances. Eskom takes a ZERO TOLERANCE stance to violation of these rules. Cardinal Rules to be communicated as part of Site Induction to all workers and visitors to site.
The contractor shall compile a legal register listing all applicable legislation and standards that may have an impact on the scope of work that he/she is performing on this project. The register shall be updated on a regular basis.
The client is entitled to stop work and issue non-conformance reports whenever health, safety, or environmental violations are observed for both contractors and/or their
14
subcontractors. Any costs incurred as a result of such work stoppage and standing time shall be for the contractor’s account. Any non-conformances/findings/observations found during audits/inspections on subcontractors shall be raised, discussed, and resolved with the relevant contractor (with whom the subcontractor is contracted).
4.21 Overtime Work (before and after hours)
Any work that is to be performed outside of normal working hours shall be regarded as overtime work. The contractor shall ensure that adequate provision is made for over time work in regards to first aider availability, emergency preparedness etc. The contractor shall also ensure that where a sub contractor is working overtime a responsible contractor supervisor is on site. Where required provision must be made for adequate artificial lighting so as to allow work to be carried out safely at all times.
4.22 Monthly/Weekly Statistical Reports Contractors shall report all incidents to Eskom as per the Eskom Incident Management Procedure and shall include the following as a minimum:
! Incidents: lost time, medical, first aid, near misses reported
! Manpower numbers per principal contractor and subcontractor company
! Actual man-hours worked
! Status on incidents investigated and recommendations closed out
! Status on audits conducted and findings closed out
4.23 Transport for Workers
The Principal Contractor shall refer and comply with the requirements of the National Road Transport Regulations, 2000 as well as CR 21(2). The Principal Contractor shall ensure no persons are transported at the back of LDV’S / bakkies unless the vehicle: Is provided with a canopy with proper seating and safety belts; Is driven on site at a low speed of less than 40km/h and proper seating and handrails have been provided; And:An assessment has been carried out indicating a very low risk; Mitigating factors have been identified to control the risk; It has been discussed and agreed upon at a health and safety committee meeting; All vehicles are provided with a serviced portable fire extinguisher and a vehicle first aid kit at all times.
4.24 Monitoring and Evaluation
Inspections - The Principal Contractor shall carry out inspections as prescribed by legislation, the site SHE plan and Client SHE specification. The Principal Contractor shall keep records of all inspections.
Internal Audits – the Principal Contractor shall conduct regular SHE audits at least once a month to ensure compliance to OHSA and SHE specification. Records of audits shall be kept on site and non-conformances reported.
Eskom reserves the right to conduct unannounced audits on contractors
Non-compliance and Penalties Eskom will view the following at-risk behaviour in a very serious light: Disregarding any requirements contained in OHSA, this document, site specific health and safety requirements and plan. Performing an unsafe act or creating an unsafe condition that could pose a danger to themselves or to others. A Principal Contractor allowing any of their employees or sub-contractors employees (including casual labourers, or labour broker employees) to work on any site without ensuring that each employee has received proper training. If any of the above are noted, it may result in cancellation of the contract
15
4.25 Omissions from this SHE Specification By drawing up this SHE specification, Eskom has endeavoured to address the most critical aspects relating to SHE issues in order to assist the contractor in adequately providing for the health and safety of employees on site.
Should Eskom not have addressed all SHE aspects pertaining to the work that is tendered for, the contractor needs to include them in the SHE plan and inform Eskom of such issues when submitting the tender.
4.26 SHE File The contractor must have a SHE file in which records of this specification, SHE plan and supporting documents are kept.
All information required in the specification and plan, for the duration of the contract of the principal contractor and subcontractors, is to be recorded in the file.
The SHE file shall be maintained by the contractor(s) at the construction site. Consolidated SHE file shall be handed to Client at end of project – CR 5(8).
5. Construction Requirements
5.1 Excavations and Trenches Requirements in Construction Regulation 11 of the OHS Act, shall apply.
All excavations must be on register and inspected daily before work commences and after inclement weather by the contractor’s appointed competent person, declared safe and his findings noted in the said register. Client shall review the said register on a pre-determined frequency not exceeding seven (7) days. Any ground operations which may include digging, excavation, or driving a peg, pile or spike into the ground by the Contractor and their sub-contractors may not commence without the written authorisation from the Engineer. Prior to excavation underground services to be identified by appropriate service providers. Contractor to ensure workers made aware of location of underground services and records of such communication kept in site safety file. All excavations done by the Contractor are to be clearly demarcated and barricaded to prevent accidental access. Only solid barricading will be used at areas where a fall hazard is present. Solid barricading and / or hole covers shall be provided around all holes or openings to prevent any person being injured as a result of a fall. Barricade to be at least 1m high. Danger tape may only be used as a pre-warning to make the solid barricading more visible and to prevent persons from coming close to the danger area. Where excavations are to be left open overnight in public areas adequate warning measures are to be implemented, visibility ensured and signage shall be displayed.
Danger tape has to be used in conjunction with proper barricading methods.
5.2 Working in elevated positions / at heights:
Working at height is a high-risk activity, and as such, all precautions including but not limited to Eskom and legislative requirements must be taken to prevent incidents while working at height.
Persons may only work from a fall risk position if:
! a working at heights risk assessment has been completed for the work to be conducted;
! a safe work procedure/task analysis and work instruction, approved by a competent person, are in place;
! a fall rescue plan, along with necessary equipment and trained rescuers, is in place;
! appropriate training, as determined by the risk assessment, has been provided; and
16
! Appropriate height safety equipment and personal protective equipment have been issued to the individual.
Where work in an elevated position is necessary, preference shall be given to fall prevention measures such as, but not limited to, effective barricading and the use of work platforms.
5.3 Plant, Machinery and equipment
The Principal Contractor shall comply with the requirements of the Driven Machinery Regulations and General machinery regulations promulgated under the OHSA 85/1993. The regulations include inspecting machinery regularly, designating a competent person to inspect and ensure maintenance, issuing PPE or clothing and training those that use machinery and enforce compliance. Contractor shall ensure that Schedule D of General Machinery Regulations is communicated to operators, Proof of communication kept in site safety file and displayed.
All employees shall: (1) Be competent when operating or using machines and tools, (2) Be in possession of valid medical (issued by Occupational Health Practitioner) and training certificate (issued by approved training institution), (3) Have proof of any form of task related training.
5.3.1 Construction vehicles and mobile plant
All construction vehicles and mobile plant shall comply with the Road Traffic Ordinance and Road Traffic Act, CR 21, GMR ,DMR as well as Eskom requirements. Designated drivers shall be in possession of a national driver’s licence, valid for the class of vehicle. The driver’s licence shall be kept by the person so authorised, and he/she shall produce such card on request. All drivers of construction vehicles and mobile plant shall have valid medical certificates of fitness to determine physical and psychological fitness. Each project site shall have a system/process to manage vehicle access to the site. Vehicle management process shall be included in SHE Plan. Operators and drivers shall comply to site speed limit of 30 km p/h. Site speed limit shall be communicated to all operators and drivers on site. Operators and drivers shall not talk on cell phone or radio while driving / operating. Contractor shall ensure that drivers and operators comply with following:
! All passengers wear seat belts while the vehicle is in motion;
! Operators / drivers complies with all safety, direction, and speed signs;
! Loads are properly secured and loaded onto vehicles; and
! Vehicles / Plant not overloaded. Daily inspections done on construction Vehicles and Mobile Plant and records kept in site safety file. Contractors shall ensure that adequate measures are put in place when refuelling, servicing and repairing on site and that such measure are communicated to operators.
5.3.2 Lifting machine and tackle A risk assessment shall be conducted prior to commencing with the task to identify the risk involved and appropriate mitigation measures must be put in place. If it is the Principal Contractor’s intention is to use lifting machines on site, it should be indicated in the Principal Contractor’s SHE plan as well as the inspection so that the Eskom Project/Site Manager can conduct an inspection when equipment is brought onto site. If his/her intention is to use a sub-contractor he must enter the name of the sub-contractor into the notification letter to the Department of Labour. All lifting machine operators shall be competent to operate a lifting machine. They must be in possession of a valid training certificate and medical certificate. When ever making use of an external contractor to do lifting work the Principal Contractor must ensure that the operator is competent and if the Principal Contractor is satisfied with the operator's competency after looking at his portfolio he/she should issue a temporary permit to the operator. The Principal Contractor should verify if the lifting machines and tackle have been examined and a performance test done by registered Lifting Machine Inspector. Proof of performance test and last inspection to be on site at all times. Performance tests shall be done at intervals
17
not exceeding 12 months, Lifting machines shall be inspected every 6 months and Lifting tackle every 3 months. No work to commence without valid Performance test certificate. Operator training shall be done according to relevant Code of practice by a provider registered with the Department of Labour. Before using any lifting machines or tackle the operator should inspect it. Refer to the requirements of the Driven Machinery Regulation 18 and Construction Regulation 20 of the OHS Act.
5.3.3 Portable electrical tools
The Principal Contractor shall ensure that portable electrical tools: Are inspected regularly by a competent person Are on register Are maintained in good working order
5.4 High Voltage Electrical Equipment
Where work is carried under, on or near high voltage equipment, work is performed by a person authorised to do so in terms of the Client’s ORHVS or under supervision of a responsible person in possession of a working permit.
5.5 Housekeeping
The contractor and subcontractor shall maintain a high standard of housekeeping within the site. Prompt disposal of waste materials, scrap, and rubbish is essential. Adequate care must be taken by the contractor to ensure that storage and stacking are correctly and safely carried out. Before stacking any material, the contractor, subcontractor, or their employees must consult the Eskom project/site manager for allocation of a stacking area. Materials/objects shall not be left unsecured in elevated areas; falling objects may cause serious injuries/fatalities. Nails protruding through timber shall be bent over or removed so as not to cause injury. All packaging material, including boxes, pallets, crates, etc. to be removed from the work area immediately. Eating facilities shall be kept in a clean and tidy manner. On completion of his/her work, the contractor is responsible for clearing his/her work area of all materials, scrap, temporary buildings, and building bases to the satisfaction of the client. In cases where an inadequate standard of housekeeping has developed, compromising safety and cleanliness, everyone has the responsibility to bring it to the attention of the Eskom project/site manager. The Eskom project/site manager has the right to instruct the contractor and his/her subcontractor to cease work until the area has been tidied up and made safe. Neither additional costs nor extension of time to the contract shall be allowed as a result of such a stoppage. Failure to comply will result in site cleaning by another cleaning contractor company at the cost of the contractor. The contractor shall carry out regular safety/housekeeping inspections (at least weekly) to ensure maintenance of satisfactory standards.
5.6 Stacking & Storage
Contractor shall ensure compliance to CR 26
5.7 Hand tools
Contractor shall ensure that hand tools are : Inspected monthly on a register Maintained in a good condition Properly stored Contrators shall ensure that awareness training re hand tools are provided to workers and proof of such training kept on record.
18
5.8 Fire Precautions
Contractor shall ensure: Fire Risk assessment done Suitable fire extinguishers available and accessible Fire extinguishers inspected monthly by a person designated thereto Fire extinguishers inspected by a competent person on a yearly basis Smoking and open flames prohibited where deemed fire risk and signage displayed to indicate Combustible materials regularly removed from site Hot work done after necessary pre-cautions taken Workers trained in use of fire extinguishers Escape routes clearly indicated Siren sounded in the event of a fire Compliance to CR 27
5.9 Scaffolding
Contractor shall ensure: Compliance to CR 14 and SANS 10085:2004. A competent scaffold supervisor shall be appointed in writing. Ensure that inspections are carried out weekly, after inclement weather, after erection and before dismantling. Adequate and relevant signage displayed. Scaffold materials used for erection are inspected prior to use so as to ensure it is constructed of sound material. All scaffold erectors, team leaders, inspectors are in possession of valid training certificate and medical certificate of fitness. Safe Work Procedures for Erection and Dismantling of scaffold is drafted and communicated to all workers and proof thereof kept in site safety file. Scaffold material is stored in such a manner so as to prevent obstruction of walkways and work areas. Fall protection equipment worn at all times. Adequate measures taken to prevent tools and material from falling from scaffold. Signage placed re overhead work
5.10 Ladders
Contractor shall ensure that ladders are: Inspected monthly, Proof of such inspection kept in site safety file, correct ladder used for type of work to be performed, Workers trained on use of ladders and training records kept in site safety file, Constructed of sound material, Fitted with non-skid devices, Secured against displacement. Prevent tools from falling from ladders. Ladders are stored out of walkways.Contractor shall ensure that all requirements of GSR 13 A are met.
5.12 Form and Support work
A competent person shall be appointed in writing to supervise all form and support work. Design drawings (updated) shall be available on site at all times. All form and support work shall be inspected on a daily basis until removal thereof and records shall be kept in the site safety file. All equipment and material used shall be inspected prior to use by a competent person and defective material shall be removed. All employees (Form and support work erectors) shall be trained re type of formwork and support work being used and have valid medical certificates of fitness. Compliance to provisions of CR 10 to be ensured.
5.13 Explosive Power Tools
Contractor shall ensure competent person appointed in writing to clean and inspect. Issue and return of cartridges to be controlled by person appointed in writing. Signage displayed wherever such tools are used. Operator trained re use and maintenance of tool and issued with appropriate PPE. Compliance to CR 19 to be ensured.
19
Annex 1 – Tender Evaluation Questionnaire
DetailsContact Person: _____________________________________________________________________________________________
Telephone: _____________________________________________________ Cell phone: _____________________________________________________ Fax no.: _______________________________________________________ E-mail: ________________________________________________________ Contract duration: _______________________________________________ Commencing date: _______________________________________________ Completion date: ________________________________________________ Expected number of employees on site: ______________________________
1. Is company registered with Compensation Commissioner? Provide CC Fund number. If yes, attach proof. _____________________________________________________________________________________________
2. Does company have an Organogram? If yes, attach proof. _____________________________________________________________________________________________
3. Has a Person charged with the responsibilities of the Act been appointed? (Reference Section 16.1 OHS Act) If yes, attach proof. ______________________________________________________________
4. Does the company have a written SHE (Safety, Health and Environmental) Policy in place? If yes, attach proof. Reference Section 7 - OHSA 85/1993 ______________________________________________________________
5. Does the company have a SHE Management System in place? If yes, provide details. (How do you manage H&S at work?) ______________________________________________________________
6. Does the company provide training for workers and appointees? If yes state training in relation to appointee / workers using below format. Attach proof of Competency
Appointee / Workers Training
e.g. First Aider First Aid Training
7. Does the company have a SHE Plan? If yes, attach. Reference CR 5(4)
8. Provide details of Hazard Identification and Risk Assessment process with risk matrix. Attach examples of baseline risk assessment and issue based risk assessment. Reference CR 7
9. How does the company ensure legislative, contractor and client requirement compliance of sub-contractors? Provide details. Reference CR 5
10. Provide incident statistics for current year and previous two years using below format.
Year Medicals Lost Time Injuries Fatalities Lost Time Injury Rate
11. Has the company made provision for the cost of Health, Safety and Environment? Provide details. Reference CR 4(h)
Principal Contractor / Service Provider Name: _______________________________________________________________________________
_______________________________________
Scope of Work:
_______________________________________________________________________________
______________________________________________________________________________
20
Annexure 2 – Legal appointments
ITEM Legal reference Appointment
1. Sect. 16.1 CEO
2. Sect 16.2 Assistant to CEO
3. Sect. 17 Health and Safety Representative
4. Sect. 19 Health and Safety Committee Member
5. CR 4(1)(c) Principal Contractor for each phase or project
6. CR 5(3)(b) Contractor
7. CR 6(1) Construction Work Supervisor
8. CR 6(2) Construction Work Supervisor - subordinates
9. CR 6(6) Health and Safety Officer
10. CR 7(1) Risk Assessor
11. CR 8(1)(a) Fall Protection Plan Developer
12. CR 10 (a) Formwork and Support Work Supervisor
13. CR 11(1) Excavation Work Supervisor
14. CR 12(1) Demolition Work Supervisor
15. CR 14(2) Scaffold Supervisor
16. CR 15(1) Suspended Platform Supervisor
17. CR17(8)(a) Material Hoist Inspector
18. CR 18(1) Batch Plant Supervisor
19. CR 19(2)(g)(i) Explosive Power Tool Supervisor
20. CR 21(1)(j) Construction Vehicle and Mobile Plant Inspector
21. CR 22(e) Temporary Electrical Installations Controller
22. CR 26(a) Stacking and Storage Supervisor
23. CR 27(h) Fire Equipment Inspector
24. DMR18 (11) Lifting Machine Operator
25. DMR18 (5) Lifting Machine Inspector
26. DMR 18(10)(e) Lifting Tackle Inspector
27. GMR 2(1) Supervisor of Machinery
28. GMR 2(7) Supervisor of Machinery Assistant
29 GSR 3 First Aider
30. GAR 9(2) Incident/ Accident Investigator
31. Emergency Planning Co-coordinator
32. Fire official
21
Annexure 3 RISK/ HAZARDS
Activity / Task Hazard Risk
Driving Different types of road condition i.e tar , gravel, sandy etcSpeeding
Vehicle accident due to driver not observing different types of road conditions and adapting thereto Vehicle incident involving member of public
Transporting material, equipment and people on the same vehicle
Vehicle involved in accident Injury to persons due to loose material and equipment falling about Damage to material or equipment
Work areas / environment Animals (bees, dogs, ticks etc) present Adverse weather conditions ( Too hot or too cold) Loose gravel and stone leading to slips, trips and falls Rubbish , off cuts thrown around & oil leaks /spills Material theft Traffic accident involving member of public, children
Ill health due to insect / animal bites Ill health of workers
Injury to workers
Environmental pollution
Asset loss Vehicle incident
Fire prevention Uncontrolled fires Injury to workers, Damage to property
Working directly underneath or in proximity to over head power lines /
Contact with live overhead power lines Flash overs – Mobile plant and workers
Injury to workers
22
Close proximity work to live equipment
Static Electricity Induction
Injury to workers, Damage to property
Use of plant and machinery – generators, concrete vibrator etc
Exposed moving parts of machinery Use of untrained operators Operators not medically fit Spills while refuelling Use of defective PPE
Injury to workers Injury to workers, Damage to property Injury to workers, Damage to property Environmental pollution Injury to workers
Manual handling Overexertion, sprains and strains Incorrect lifting and handling procedures
Injury to workers Injury to workers
Overhead work Foreign object entering eye Overexertion, sprains, strains, awkward position
Injury to workers Injury to workers
Use of hand tools Defective hand tools Incorrect tool for the job
Injury to workers Injury to workers
Use of Portable electrical tools Defective electrical tool, Exposed cables and leads Trailing cables leading to trips and falls
Injury to workers, damage to property
Injury to workers
Working in elevated positions / at heights
Untrained workers, Falls from heights Failure to use FAS Defective / Ineffective PPE Workers unfit to perform work at heights Lack of / inadequate emergency planning
Injury to workers Injury to workers Injury to workers Injury to workers Injury to workers
23
Lifting machine and tackle Incompetent operator; Expired or lack of valid training or medical certificate Expired or lack of Load test certificate or 6 monthly inspection records of lifting machineExpired or lack of 3 monthly inspection record of lifting tackle Lack of / inadequate emergency planningFailure of lifting machine or tackle Incorrect lifting and rigging practise, Safe working load not displayed
Injury to workers, Damage to property
Stacking and Storage Incorrect procedure followed, Stacks collapsing Overexertion, Sprains and Strains Walkways obstructed Unauthorised entry, Lack of demarcation, Theft
Injury to workers, Damage to property Injury to workers
Injury to workers, Damage to property
Earthworks – Backfilling and compacting trenches
Defective / ineffective hand tools Exposed moving parts of machinery Use of defective PPE
Mechanical compacting
Bodily injury, Hand injury Bodily injury, Hand injury Bodily injury, Hand injury, Dust and noise exposureHand injury, Noise and vibration exposure
Wet trades – Brick work and Plastering
Inadequate stacking and storage
Environmental pollution due to mixing of cement / mortar Use of defective / ineffective hand tools Uncontrolled water loss
Injury to workers, damage to property / materialEnvironmental damage
Bodily injury, Hand injury Water wastage, Work area soggy and
24
Tools, material, equipment, workers falling from heights / elevated position Exposure to Hazardous chemical substance (HCS) - cement dust inhalationExposure to HCS – skin Exposure to HCS – entering eye Ineffective / incorrect PPE used Overexertion
slippery leading to slips and trips Damage to tools, material and equipment; Bodily injury to workers resulting in medical or lost time or fatality Inhalation of cement dust DermatitisEye irritation Bodily injury Sprains and Strains
Use, Erection, Dismantling of scaffolding
Scaffolds not erected / dismantled / designed as per SANS 10085 Incorrect signage displayed
Tools, material, equipment, workers falling from heights / elevated position
Incompetent, medically unfit supervisor, erectorsScaffolds not inspected on register
Lack of pre-task planning
Overexertion
Scaffold collapse, Injury to workers / Fatality, damage to property Injury to workers / Fatality, damage to propertyDamage to tools, material and equipment; Bodily injury to workers resulting in medical or lost time or fatality Injury to workers / Fatality, damage to propertyScaffold collapse, Injury to workers / Fatality, damage to property Scaffold collapse, Injury to workers / Fatality, damage to property Sprains and Strains
Concrete works Spillage of concrete, Incorrect area used to wash outIneffective / incorrect PPE used OverexertionExposure to HCS – skin Exposure to HCS – entering eye
Environmental pollution
Hand and foot injuries Sprains and Strains DermatitisEye irritation
25
Reinforcement / Steel fixing Incorrect / Ineffective PPE Hand injuries – cuts and abrasions
Use of ladders Falls of workers and tools Defective / inadequate ladder used
Injury to workers Injury to workers
Painting Exposure to hazardous chemical substanceIneffective / defective PPE Painting equipment cleaned on site OverexertionFalls from elevated position – workers / equipment
Inhalation of HCS
Exposure to HCS Environmental pollution Sprains and strains Bodily injury
Roof work Falls from heights – tools / equipment / workersFailure to use Fall prevention equipment Workers not trained / medically fit Lack of pre task planning
Bodily injury, fatality, damage to property
Bodily injury, fatality Bodily injury, fatality Bodily injury, fatality
Excavations by hand Falls into excavation - workers and members of publicExcavation walls collapsing resulting in injury to staff Existing underground services Use of defective hand tools
Bodily injury
Bodily injury
Injury to workers, Damage to property Bodily injury
Excavations using plant and machinery
Falls into excavation– workers and members of publicExcavation walls collapsing resulting in injury to staff Existing underground services Untrained and medically unfit operators Plant and workers in same excavation Plant failure due to plant and machinery
Bodily injury
Bodily injury, suffocation
Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers Injury to workers, Damage to property
26
not regularly serviced and inspected
Plumbing work Incorrect / defective tools used Incorrect / defective PPE used Use of Hazardous chemical substances
Bodily injury Bodily injury Exposure to HCS
Site establishment and de establishment
Use of lifting equipment and tackle Off loading containers Erecting temporary site offices, amenities and stores, site boundary fenceErecting / Dismantling roof sheeting Provision of potable water and ablution facilities Use of hand tools Manual Handling
Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers, Damage to property
Injury to workers, Damage to property
Ill health of workers Injury to workers Injury to workers
Electrical work Incorrect / defective tools used Incorrect / defective PPE used Work performed by person not competent / authorised to perform such work
Bodily injury Bodily injury Electrical shock, electrocution
Form and Support work Collapse of structure Defective material / equipment used Erectors not trained to perform work Inadequate inspection and supervision Premature stripping of support work Inadequate means of access and egressOverexertionWorking at heights
Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers Injury to workers, Damage to property Injury to workers, Damage to property
Injury to workers, Damage to property Sprains and strains Injury to workers
27
Use of hazardous chemical substances
Incorrect PPE used First aid facilities unavailable MSDS not on site
Bodily injury Injury to workers Injury to workers
Explosive Power tools Users not trained No signage displayed No control over issue and return of cartridges
Injury to workers Injury to workers Injury to workers
Erecting steel structure Tools, material, equipment, workers falling from heights Ineffective, defective or lack of FAS Lifting equipment failure
Injury to workers
Injury to workers Injury to workers, Property damage
Fencing Overexertion, Sprains, Strains Defective portable electrical equipment usedDefective plant and machinery used Incorrect / defective PPE used Fire risk
Injury to workers
Injury to workers Injury to workers, damage to property Injury to workers Environmental damage
Hot work (Soldering, Brazing, Flame cutting etc)
Inadequate fire precautions Incorrect / ineffective PPE Exposure to hazardous fumes Burns to body Untrained person performing task Other workers in area exposed
Environmental damage, injury to workers Injury to workers Ill health of workers Injury to workers Injury to workers Injury to workers
Deliveries , Access to site Driving (gravel road) Traffic accident
Storage of fuel, diesel, petrol Spillages Fire
Environmental damage Environmental damage, Injury to workers, Damage to private property
28
Putting down yard stone Incorrect manual handling Defective, incorrect hand tools used Weather conditions
Injury to workers Injury to workers Ill health of workers
Private property Theft Unauthorised access
Injury to workers Injury to workers
Installing heavy equipment Load swinging out of control Lifting tackle failure Unbalanced load Works area beneath slew area to be kept clear Incorrect PPE worn by workers
Damage to property, Injury to workers Damage to property, Injury to workers Damage to property, Injury to workers Damage to property, Injury to workers
In jury to workers
29
Annexure 4 - Training Needs Matrix
CR
EA
TE
3 D
AY
SE
MIN
AR
CO
NS
TR
UC
TIO
N
RE
GS
OH
S A
CT
& R
EG
S
FIR
ST
AID
L
2
CO
ID A
CT
OR
HV
S
INC
IDE
NT
INV
ES
TIG
AT
IN
ES
KO
M S
AF
ET
Y
IND
UC
TIO
N
FIR
E F
IGH
TIT
ING
HIR
A/J
SA
VE
HIC
LE
AN
D
MO
BIL
E
EQ
UIP
ME
NT
OP
ER
AT
OR
H &
S R
EP
TR
AIN
ING
BA
SIC
H &
S
TR
AIN
ING
OHS Act 16 (1) MD * * * * * *
OHS Act 16 (2) PM * * * * * *
Construction Supervisor
CR 6 (1)
* * * * *
Assistant Construction
Supervisor CR 6 (2)
* * * * *
Safety Officer CR 6 (6) * * * * * * * * * *
Site Risk Assessor * * *
Fire officer * * *
H&S Rep * * * *
Scaffolding Supervisor * *
Excavation Supervisor * *
Construction vehicles and
mobile plant inspector /
operator
* *
First Aider *
Fall Prevention plan
developer
* * *
Stacking supervisor * * *
Site personnel *
30
Annexure 5 - Flash Report
ESKOM EMPLOYEE / EXTERNAL PERSON INCIDENT
INCIDENT NOTIFICATION FLASH REPORT TO BE SENT TO RISK MANAGER WITHIN 24 HOURS OF INCIDENT.
__________________________________________________________________________________ INCIDENT NUMBER: 0000000000000000#####PERSONS INVOLVED TYPE:
PERSONS NAME PERSON TYPE UNIQUE NUMBER
Note number ranges for Person Type External Person:
! Contractor 1000000001 – 2999999999
! Member of Public 3000000000 – 4999999999
! Third Party 5000000000 – 6999999999
SHORT DESCRIPTION OF ACCIDENT:
INCIDENT DETAILS:
IMMEDIATE RECOMMENDATIONS:
PERSONS INVOLVED:
Name Accident Category
Involved Role
Involved Type
Body part Injury
ACCIDENT TYPE:
REPORTED BY:
DATE:
PLANT:
WORK AREA DESCRIPTION:
ACCIDENT LOCATION:
MANAGER/ SUPERVISOR:
TELEPHONE NUMBER:
FAX NUMBER:
DATE OF INCIDENT:
TIME OF INCIDENT: