11. Quality assurance

11.1 Substation quality checking document

ESKOM COPYRIGHT PROTECTED

B Morrison / February 2013 / Rev 0

Standard Group Technology

Title: QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Part 7 -Substations

Area of Applicability: Distribution Engineering

Documentation Type: Standard

Revision: 0

Total Pages: 112

Next Review Date: February 2018

Disclosure Classification: Controlled Disclosure

Compiled by Approved by

……………………………………………………… ………………………………………………..…….

Abre Le Roux

Chief Engineer Substations

Elli Lechtman

Substations SC Chairperson

Date: ……………………………………………. Date: ………………………………………………

Approved by Authorized by

………………………………………………..……. ……………………………………

Elli Lechtman

SCOT Representative

Phineas Tlhatlhetji

Substations COE Manager

Date: ……………………………………………… Date: …………………………

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 2 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Content

Page

Foreword ........................................................................................................................................................ 3!1! Scope .................................................................................................................................................. 4!2! Normative references .......................................................................................................................... 4!3! Definitions & Abbreviations ................................................................................................................. 4!

3.1! Definitions .................................................................................................................................... 4!3.2! Abbreviations ............................................................................................................................... 5!

4! Requirements ...................................................................................................................................... 5!4.1! General Project Information ......................................................................................................... 8!4.2! Requirements applicable to Stages 1 to 13 ................................................................................. 8!4.3! Requirements applicable to Stage 14 - “Commissioning Testing” .............................................. 9!4.4! Requirements applicable to Stage 15 - “Provisional Handover” ................................................. 9!4.5! Requirements applicable to Stage 16 - “Final Handover” ......................................................... 10!

Annexure Contents ...................................................................................................................................... 11!Annexure A – General Project Information .................................................................................................. 12!Annexure B1 – Stage 1: Civil Works: Platform ............................................................................................ 16!Annexure B2 – Stage 2: Civil Works: Control Building ................................................................................ 22!Annexure B3 – Stage 3: Civil Works: Subsoil Drainage .............................................................................. 27!Annexure B4 – Stage 4: Civil Works: Earthmat Installation ........................................................................ 29!Annexure B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches ..................................... 31!Annexure B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing ................................................................ 34!Annexure B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dame and Fire Wall ............................. 36!Annexure B8 – Stage 8: Steelwork .............................................................................................................. 42!Annexure B9 – Stage 9: Fencing ................................................................................................................. 44!Annexure B10 – Stage 10: Power Transformer Delivery & Assembly ........................................................ 47!Annexure B11 – Stage 11: Primary Equipment Installation ........................................................................ 49!Annexure B12 – Stage 12: Conductor, Busbars & Clamps Installation ...................................................... 61!Annexure B13 – Stage 13: Control Plant Installation .................................................................................. 64!Annexure B14 – Stage 14: Commissioning Testing .................................................................................... 81!Annexure B15 – Stage 15: Provisional Handover ..................................................................................... 111!Annexure B16 – Stage 16: Final Handover ............................................................................................... 112!

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 3 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Foreword

This revised standard is based on the original document DISASAAQ1 Rev 5 dated September 2005.

Revision history

This revision cancels and replaces revision no 5 of document no. DISASAAQ1.

Date Rev Compiled

by Remarks

Feb 2013 01 A le Roux

Complete document revision with new stages 1 to 16 and revised handover and quality checklist documentation

Document number changed to DST 34-1238.

Sept’05 5 C Clark

Document approved.

All comments and new comments answered. Send for Voting 03/2005.

All comments answered. Send for Voting 11/2004.

Telecontrol info updated according to comments received by Western Region. Electrical Certificate info on page 9 removed.

Sept 2002 4 C Clark Document approved

June 2002 3 C Clark Page 75 EDNS added

Nov ‘99 2 C Clark

Document changed comments added

Document changed item revised – 4.6.2

Document changed comments added – 4.6.4 , 4.6.5

Comments addressed. General typographical errors rectified. Item 4.4.2 and associated forms revised. Annex H (Stage 8) – FS added as a signatory. Annex I added to include provisional handing over certificate. Annex C (Stage 3) C13 – Fire Protection Checklist added. Annex A (Stage 1) A3 – changes/additions to checklist. General changes to all other Annexes as per comments

Typographical errors rectified as per request from western region. Alignment of document to include signatories on a single sheet.

April ‘99 1 C Clark Project Flow Process taken out, entire document changed.

Aug ‘98 0 C Clark Project Flow Process added, entire document revised to allow for Stage takeovers.

Acceptance

This document has been seen and accepted by:

Name Designation

Phineas Tlhatlhetji Substations COE manager

E Lechtman SCOT Substations Representative

This standard shall apply to Eskom Distribution.

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 4 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Development team

Name Designation

A.Le Roux Chief Engineer – Substations

N. Webber Senior Advisor - Substations

J.Kriel Thabile Eastern Cape – Electrical Engineers

Keywords

Handover, Quality, Checking.

1 Scope

This standard sets out the requirements for the various Quality Control and Handover process stages for a substation project from the inception of construction to commissioning and final handover. This standard shall be used in conjunction with all standard substation documentation and scope of works documentation that will form part of the substation project Works Information.

2 Normative references

The following documents contain provisions that, through reference in the text, constitute requirements of this standard. At the time of publication, the editions indicated were valid. All standards and specifications are subject to revision, and parties to agreements based on this standard are encouraged to investigate the possibility of applying the most recent editions of the documents listed below. Information on currently valid national and international standards and specifications can be obtained from the Information Centre and Technology Standardization Department at Megawatt Park.

SANS 121, Hot-dip (galvanized) zinc coatings (other than on continuously zinc-coated sheet and wire).

DST 34-304: Distribution standard – Part 7: Generic substation design.

SANS 1200: Specification for civil engineering construction

SABS 10400: National building regulations

DST 34-1245: Substation Earthing

DISSCAAD3: Checklist for Large Transformers

DSP 34-1658: Corrosion Protection specification for new indoor and outdoor Distribution equipment, components, materials and structures manufactured from steel

DISASAAN0: Standard for the labeling of High Voltage Equipment

3 Definitions & Abbreviations

3.1 Definitions

Contractor

! As per the NEC contract represented by an Appointed Supervisor or Responsible Person in writing. The Contractor can also be an Eskom Internal Construction team.

! Manufacturers of the Power Transformers and other substation equipment.

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 5 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Clerk Of Works People responsible for physical quality inspections.

Project Manager

Person appointed as per the NEC contract. The Project Manager can be someone within the Eskom Program Management Department or an external appointment in which case it will be a Contracted Project Manager.

Contract Project Manager Person appointed as per the NEC contract. The Project Manager is appointed external to Eskom.

Standards Implementation department (Substations)

Department responsible for standards.

Control Plant Maintenance department

Responsible for the pre-commissioning and final commissioning of the substation project.

Design Engineer (Primary Plant) Person responsible for the primary design drawings, bill of quantities and approval of Design Change Requests.

Design Engineer (Control Plant) Person responsible for the control plant design (protection, metering, DC, telecommunication and telecontrol).

Contract Design Engineer Person appointed external to Eskom responsible for the design drawings, bill of quantities and approval of Design Change Requests.

Holding Point Activity for which arrangements have to be made for the Clerk of Works to be present and to witness the work procedure.

3.2 Abbreviations

COW Clerk Of Works

PM Project Manager

CPM Control Plant Maintenance department

DE Design Engineer

CDE Contract Design Engineer

AD Asset Design

4 Requirements

The document contains all possible quality check sheets and handover forms to execute a substation project. It is important to compile a Quality Handover document specific to a project by including the relevant sections and duplicating check sheets where required (eg. In the case of two transformers two separate transformer check sheets will be required or if no capacitor bank will be installed, exclude the capacitor bank quality check sheet).

The process is initiated by collating all relevant detail and documentation regarding the project and stakeholders. This is catered for in tables in the General information section as per Annexure A.

The next stage is the actual execution of activities. This is catered for in Stages 1 to 13 (Annexure B1 to B13). Each stage consists of two types of documents per category, namely a Quality Control check sheet (Quality checking of actual activities) and a Handover form (confirming that the various Quality activity checks have been executed).

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 6 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

The next stage is the Commissioning and testing stage prior to switch-on (Stage 14, Annexure B14).

Provision has been made for two stages for Handover. Firstly, a Preliminary Handover stage to ensure that all quality checks have been performed in order to switch the substation on. The final Handover ensures that all activities relating to the project have been completed and the project is closed off and handed over for Commercial operation.

The Quality Control and Assurance process consists of the following stages:

! General Project Information

! Stage 1 Civil Works: Platform

! Stage 2 Civil Works: Control Building

! Stage 3 Civil Works: Subsoil drainage

! Stage 4 Civil Works: Earthmat Installation

! Stage 5 Civil Works: Equipment Foundations & Cable trenches

! Stage 6 Civil Works: Roads, Stoning & Kerbing

! Stage 7 Civil Works: Transformer bund area, Oil dam and fire wall

! Stage 8 Steelwork

! Stage 9 Fencing

! Stage 10 Power Transformer Delivery & Assembly

! Stage 11 Primary Equipment Installation

! Stage 12 Conductors, busbars & clamps

! Stage 13 Control Plant installation

! Stage 14 Commissioning Testing

! Stage 15 Provisional Handover

! Stage 16 Final Handover

The various stages are displayed in figure 1

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 7 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Figure 1: Quality Control handover stages

Platform

Civil Works

Control Building

General Project Information

Earthmat Installation

Subsoil drainage

Equipment Foundations & Cable trenches

Roads, Stoning & Kerbing

Transformer bund area, Oil dam and fire wall

Steelwork

Fencing

Final Handover

Provisional Handover

Commissioning Testing

Conductors, busbars & clamps

Control Plant installation

Primary Equipment Installation

Power Transformer Delivery & Assembly

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 8 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

4.1 General Project Information

! The Design Engineer shall hand over the Final Design Package and Drawings to the Project Manager. It is the responsibility of the Design Engineer to ensure that the latest revisions of all documentation have been issued to the Project Manager.

! The Project Manager will ensure that both the appointed Contractor and the appointed Clerk of Works receive the necessary documents and drawings for all the construction stages. All parties are to complete the Design Package Handover Form before commencement of construction.

! Provision has been made for signatories and the recording of the relevant Drawing Numbers and Revisions at the time of issue.

! Drawing revisions due to Design Changes will be recorded in the Documentation Change Control Form. The Project Manager will ensure that the Contractor and Clerk of Work receive the latest revision of the drawings.

4.2 Requirements applicable to Stages 1 to 13

! The Quality Control Checksheet will be issued by the Project Manager as part of the quality assurance documentation and will be on site until the stage has been completed. The activities within the stage are to be completed and checked against the design drawings and specifications to ensure compliance.

! Prior to the commencement of the construction stage, the Clerk of Works will confirm with the Contractor which activities have been identified as Holding Points and which activities he would like to be photographed as proof of compliance.

! Each activity, once completed by the contractor, will be signed off by both the Contractor and Clerk of Works. The Clerk of Works will indicate whether the activity was:Witnessed (W) – present during this activity Verified (V) – not present but confirm compliance.

! Certain Checksheets include key specifications such as soil classification, layer depth and number of layers required as per the design. This is to ensure the specification is understood by both parties and complied with.

! Once all the activities for a specific stage have been completed, the Quality Control Checksheetshall be presented to the Project Manager who will confirm that all the activities have been signed off by both the Contractor and the Clerk of Works

! The Handover Checklist is then used as a high level checklist to ensure that all Quality Control activities have been executed as per the Quality Control Checksheet. The Handover Checklist is the responsibility of the Project Manager and must be updated at least once a month during the site meeting.

! The required forms must be duplicated for multiple products in a substation (e.g. for two transformers make two copies of the transformer checksheets).

4.2.1 Additional requirements applicable to Stage 5 - “Civil Works: Equipment Foundations & Cable trenches”

! The checksheet for the foundations can be done as a bulk item check or a checksheet for each foundation or group of foundations. This is to be decided between the Clerk of Works and the Contractor.

4.2.2 Additional requirements applicable to Stage 9 - “Steelwork” and “Fencing”

! The Contractor shall ensure that all manufactured steelwork is inspected at delivery and galvanizing thickness checked and verified before erection. The Contractor needs to inform the Clerk of Works once the steelwork is on site. The Clerk of Works needs to arrange an inspection date with the Standards Implementation Representative for inspection and approval of steelwork.

! The Checksheet for the steelwork can be done as a bulk item check or a checksheet for each item or group of items. This is to be decided between the Clerk of Works and the Contractor.

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 9 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

4.2.3 Additional requirements specific to Stage 10 - “Power Transformer Delivery & Assembly”

! The Project Manager must notify the Eskom Plant Department of the projected delivery date in order for them to provide a representative to witness the Transformer delivery and acceptance activity.

! During the delivery of the Power Transformer, the Clerk of Works shall verify and complete the Transformer Delivery Checksheet

! CPM department must witness the on-site transformer tests as executed by the manufacturer.

4.2.4 Additional requirements specific to Stage 11 - “Primary Equipment Installation”

! The Contractor shall inspect all deliveries from Manufacturers in order to ensure that the equipment is in good condition before off-loading on site.

! Only high level data such as equipment type and serial number is captured on the checksheets. Once the equipment is installed, the Project Manager will inform the Plant Department to commence data capturing as per the Eskom Data capturing requirements.

4.2.5 Additional requirements specific to Stage 13 - “Control Plant installation”

! This stage will mostly be executed by the Eskom CPM Department. The Project Manager willliaise with the CPM Manager to identify the Supervisor (CPM) who will be responsible for checking and completion of the Quality Control Checksheet.

! Prior to the commencement of the construction stage, the CPM Supervisor will confirm with the Contractor which activities have been identified as Holding Points and which activities he would like to be photographed as proof of compliance.

! Each activity, once completed by the contractor, will be signed off by both the Contractor and CPM Supervisor. The Supervisor will indicate whether the activity was:Witnessed (W) – present during this activity Verified (V) – not present but confirm compliance.

! Once all the activities have been completed, the Quality Control Checksheet shall be presented to the Project Manager who will ensure that all the grouped activities have been signed off by both the Contractor and the CPM Supervisor Handover Checklist.

4.3 Requirements applicable to Stage 14 - “Commissioning Testing”

! This stage consists of all the relevant pre- and final commissioning tests to be performed in order to commission the substation project.

! Each activity, once completed by the Contractor, will be signed off by the relevant CPMSupervisor to confirm compliance.

4.4 Requirements applicable to Stage 15 - “Provisional Handover”

! The Provisional Handover Document will be completed by the Project Manager and presented for acceptance to the following key persons:

1. Asset Design – Acceptance by the appointed Senior Design Engineer (acceptance for primary and Control Plant)

2. Control Plant Maintenance - Acceptance by the Control Plant Maintenance Manager3. Network Operations – acceptance by the Chief Engineer

! The final commissioning of the substation project can commence after the completion of the Provisional Handover Document.

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 10 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

4.5 Requirements applicable to Stage 16 - “Final Handover”

! The Final Handover Document will be will be completed by the Project Manager and presented for acceptance to the following key persons:

1. Asset Design – Acceptance by the appointed Senior Design Engineer (acceptance for primary and Control Plant)

2. Control Plant Maintenance - acceptance by the CPM Manager 3. Zone – final acceptance by Sector Manager.

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 11 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure Contents

Quality Control & Handover Check-sheets

Annexure A

General Project information

! Project Detail

! Tracking Page

! Design Package Handover

! Documentation Change Control

Annexure B1 Stage 1 Civil Works: Platform

Annexure B2 Stage 2 Civil Works: Control Building

Annexure B3 Stage 3 Civil Works: Subsoil drainage

Annexure B4 Stage 4 Civil Works: Earthmat Installation

Annexure B5 Stage 5 Civil Works: Equipment Foundations & Cable trenches

Annexure B6 Stage 6 Civil Works: Roads, Stoning & Kerbing

Annexure B7 Stage 7 Civil Works: Transformer bund wall, oil dam and fire wall

Annexure B8 Stage 8 Steelwork

Annexure B9 Stage 9 Fencing

Annexure B10 Stage 10 Power Transformer Delivery & Assembly

Annexure B11 Stage 11 Primary Equipment Installation

Annexure B12 Stage 12 Conductors, busbars & clamps

Annexure B13 Stage 13 Control Plant installation

Annexure B14 Stage 14 Commissioning Testing

Annexure B15 Stage 15 Provisional Handover

Annexure B16 Stage 16 Final Handover

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 12 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure A – General Project Information

Substation Project Name:

Project No:

COW name:

Design Engineer:

Project Manager:

Contractor Civil Platform Works: Contractor Secondary Works:

Contract No: Contract No:

Contractor Supervisor: Contractor Supervisor:

Contractor Civil Buildings: Contractor :

Contract No: Contract No:

Contractor Supervisor: Contractor Supervisor:

Contractor Primary Works: Contractor:

Contract No: Contract No:

Contractor Supervisor: Contractor Supervisor:

Project Detail

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 13 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Quality Control Checklist

Completion Date

Handover Checklist

Completion DateNotes

Stage 1 Civil Works: Platform

Stage 2 Civil Works: Control Building

Stage 3 Civil Works: Subsoil drainage

Stage 4 Civil Works: Earthmat Installation

Stage 5 Civil Works: Equipment Foundations & Cable trenches

Stage 6 Civil Works: Roads, Stoning & Kerbing

Stage 7 Transformer bund wall, oil dam and fire wall

Stage 8 Steelwork

Stage 9 Fencing

Stage 10 Power Transformer Delivery & Assemble

Stage 11 Equipment Installation

Stage 12 Conductors, busbars & clamps

Stage 13 Control Plant Installation

Stage 14 Commissioning Testing

Stage 15 Provisional Handover Document

Stage 16 Final Handover Document

The purpose of this page is to track the relevant stages and to record progress.

Project Tracking

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 14 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

Stage Construction Activity Drawing Title & ReferenceRev

No:

Issued by (Project

Manager Name)Date

Received by (Clerk of

Works Name)Date

Received by

(Contractor Name)Date

Access to site documentation completed as per

the NEC contract

Health & Safety Plan and File presented and

approved before start of construction.

1 Civil Works: Platform

2 Civil Works: Control Building

3 Civil Works: Subsoil drainage

4 Civil Works: Earthmat Installation

5Civil Works: Equipment Foundations &

Cable trenches

6 Civil Works: Roads, Stoning & Kerbing

7Civil Works: Transformer bund wall, oil dam and

fire wall

8 Steelwork

9 Fencing

10 Power Transformer Delivery & Assembly

11 Primary Equipment Installation

12 Conductors, busbars & clamps

13 Control Plant installation

Design Package Handover

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 15 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

Item Drawing No: Change Rev No:Issued by Project

Manager NameDate

Received by Clerk of

Works NameDate

Received by Contractor

NameDate

Documentation Change Control

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 16 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B1 – Stage 1: Civil Works: Platform

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

1 Benchmark Installation Name of Surveyor:__________________

Depth:__________________mm

Quantity:__________________m³

Stockpile

position:

Stockpile height:__________________m

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Quality Control Checksheet for Civil Works: Platform

2 Platform: Clear & grub

3Platform: Road bed

preparation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 17 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Soil classification :__________________

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Soil classification :__________________

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Depth:__________________mm

Quantity:__________________m³

Stockpile

position:Stockpile

height: m

6Platform: Wearing coarse /

Final layer preparation

7 Access Road: Clear & grub

4 Platform: Cut to Fill Operation

5Platform: Importation of

materials

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 18 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Soil classification :__________________

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

Soil classification :__________________

Layer Depth:__________________mm

No of layers:__________________

No of Compaction & Density

tests:No of Compaction & Density tests

witnessed by COW:

10Access Road: Importation of

materials

11

Access Road: Wearing

coarse / Final layer

preparation

8Access Road: Road bed

preparation

9Access Road: Cut to Fill

Operation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 19 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Drainage & Channelling required:

Bell mouth: Size and bending

radius:Signage:___________________________

Entry from Road:

Type of

drain:

Drain Positions:______________________

Drain

sizes:Concrete

specification:

Concrete supplied: __________________

Finishes:___________________________

Run-offs / Channelling:

Embankment angles and preparation:

Seeding:

Soil Blankets:

Retaining walls - Type & size:

14Embankments & Soil

Detainment

12 Access Road: Finishes

13 Storm water drainage

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 20 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Type & Position:

Corner Posts:

Intermediate posts:

Fencing:

Gates:

16 Levelling of spoiled materials. Levelling of spoiled materials.

Position:

Size:

Position:

Seeding:

17 Earth berm installation.

18 Rehabilitation

15 Boundary Fence

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 21 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Benchmark Installation

2 Platform: Clear & grub

3 Platform: Road bed preparation

4 Platform: Cut to Fill Operation

5Platform: Importation of

materials

6Platform: Wearing coarse /

Final layer preparation

7 Access Road: Clear & grub

8Access Road: Road bed

preparation

9Access Road: Cut to Fill

Operation

10Access Road: Importation of

materials

11Access Road: Wearing coarse

/ Final layer preparation

12 Access Road: Finishes

13 Storm water drainage

14Embankments & Soil

Detainment

15 Boundary Fence

16 Levelling of spoiled materials.

17 Earth berm installation.

18 Rehabilitation

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Platform

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 22 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B2 – Stage 2: Civil Works: Control Building

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

1Setting out of building

foundations & levels.Building set out according to XY

Foundation correctly excavated - width &

depth

Levels/height correct

Reinforcing installed correctly

Compaction acceptable

Local Municipality approval

3 Concrete - Foundations Concrete - mixture at correct MPa

Quality Control Checksheet for Civil Works: Control Building

2 Foundations - excavation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 23 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Concrete - mixture at correct Mpa

Waterproofing:

Shuttering:

Floating / Power floating:

Brick type & colour

Cement mixture correct

Waterproofing

Jointing

Correct heights & levels

Plastering

Trusses delivery - visual inspection

Trusses designed correctly

Trusses positioned & lined up correctly

Roof sheeting type & colour

Roof installation

Roof waterproofing installation

Gutters & down pipes

4 Concrete - Floor

5 Brickwork

6 Roof Installation - Sheeting

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 24 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Concrete - mixture at correct MPa

Reinforcing installation

Shuttering.

Waterproofing installation

Gutters & down pipes

Ceiling type & colour

Ceiling height & level

Plumbing installation

Plumbing Installation approval by an

accredited person

Electrical installation

Certificate of Compliance issued

Electrical installation

Electrical Installation approval a Master

Electrician.

7 Roof Installation - Concrete

8 Ceilings

9 Plumbing Installation

10Control Building - Electrical

Installation

11Battery room - Electrical

Installation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 25 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Painting

Steps, Ramps & hand rails

Doors, Security gates

Trench covers

Cable rack installations

Key cabinet

Operating Diagram board installation

Fire extinguishers

Furniture

Operating earths

Barricading nets & stands

12 Finishing

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 26 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1Setting out of building

foundations & levels.

2 Foundations

3 Concrete - Foundations

4 Concrete - Floor

5 Brickwork

6 Roof Installation - Sheeting

7 Roof Installation - Concrete

8 Ceilings

9 Plumbing Installation

10Control Building - Electrical

Installation

11Battery room - Electrical

Installation

12 Finishing

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Control Building

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 27 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B3 – Stage 3: Civil Works: Subsoil Drainage

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Grid lengths measured out with correct

distances

Grid levels to be determined to ensure

enough fall is created during excavation &

installation of the drainage pipes.

Drainage pipes - size & type

Bidum material

Stone - size & type

Trenching - width & depth

Backfilling of materials

Compaction

4 Drainage outlets Number of outlets

Quality Control Checksheet for Civil Works: Subsoil drainage

3Subsoil drainage backfill and

compaction

1Subsoil drainage & piping

setting out

2Installation of subsoil drainage

pipes, bidum and stone

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 28 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1Subsoil drainage setting

out.

2

Installation of subsoil

drainage pipes, bidum

and stone

3Subsoil drainage backfill

and compaction

4 Drainage outlets

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Subsoil drainage

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 29 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B4 – Stage 4: Civil Works: Earthmat Installation

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

1 Earth Grid setting out Earthmat - setting out

Excavations

Backfill of materials

Compaction

Earth Conductor - type & size

Earth Conductor installation

Earth Conductor connections

Sacrificial earth installation

4 Earth Continuity test Earth Continuity test

2 Earth Grid Excavations

3Earth Conductor Installation &

Connections

Quality Control Checksheet for Civil Works: Earthmat Installation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 30 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Earth Grid setting out

2 Earth Grid Excavations

3Earth Conductor Installation &

Connections

4 Earth Continuity test

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Earthmat Installation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 31 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Equipment Foundation - setting out

Foundation dimensions - length, width &

depth

Foundation side walls - stable & vertical

Foundation compaction

Reinforcing

Steel Shuttering

Control cabling uPVC pipe

Steel Templates - installed & positioned

HD Bolts

Earthing - installed HD bolt earthing

Concrete - mixture at correct Mpa

1Equipment Foundation

No:___________________

Quality Control Checksheet for Civil Works: Foundations

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 32 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Cable trenches - setting out

Cable trench excavations &

installation

Cable trench bedding preparation.

Cable trench cover support brackets

Cable trench (pipe) road crossings

Cable trench covers.

Cable trench entry into Control

Building.

2 Cable trenches

Quality Control Checksheet for Civil Works: Cable Trenches

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 33 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Foundations

2 Cable trenches

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Foundations & Cable Trenches

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 34 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Road kerbing installation

Stone kerbing installation

Road stoning - size & depth.

Paving - preparation

Paving - installation

Gate ramp installation

3 Stoning Yard stoning - size & depth.

4 Weed killer Spraying of weed killer.

1 Kerbing

2 Roads

Quality Control Checksheet for Civil Works: Roads, Stoning & Kerbing

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 35 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Kerbing

2 Roads

3 Stoning

4 Weed killer

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Roads, Stoning & Kerbing

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 36 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dame and Fire Wall

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Foundation - depth & size

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Walls - Height & Level

Sump - depth & size

Floor - levels (direction of flow)

Floor - sealing correct

Valve chamber - level & size

Drizit bags - installed

Outlet Valve - level

Drizit bag - level

Drainage pipe - outlet level

Valve Chamber cover - size

Flow stop - invert level

Oil drainage pipes levels - 300mm concrete

Oil drainage pipes joints sealed - 300mm

concreteOil drainage pipes direction of flow -

300mm concrete

Quality Control Checksheet for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall

Transformer Oil Containment Area1

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 37 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Foundation - position depth & size

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Walls - Height & Level

Oil drainage pipes joints sealed - 300mm

concrete

Manhole cover - installed

Foundation - position depth & size

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Chamber 1 - size

Chamber 2 - size

Inlet - level

Outlet - level

Level separation wall - position

Oil drainage pipes joints sealed - 300mm

concrete

Manhole cover - installed

2 Manholes

3 Firetrap

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 38 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Foundation - position depth & size

Oil Dam dimensions - length, width, depth

Waterproofing - installed

Shuttering - install

Oil Dam floor - concrete & reinforcing.

Oil Dam walls - concrete & reinforcing.

Inlet - level

Outlet - level

Ladder - istalled

Cover - installed

Earthing

4 Oil dam - Type A Concrete

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 39 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Foundation - position depth & size

Oil Dam dimensions - length, width, depth

Waterproofing - installed

Oil Dam floor - sand bedding

Concrete & Reinforcing - installed.

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Inlet - level

Outlet - level

Oil drainage pipes joints sealed - 300mm

concrete

Manhole cover - installed

Sealing

Side wall - river sand bedding

Sump - depth & size

Valve chamber - level & size

Valve chamber - Quality and facebrick

Drizit bags - installed

Outlet Valve - level

Drizit bag - level

Drainage pipe - outlet level

Valve Chamber cover - size

Flow stop installed - invert level

Side wall - river sand bedding installed

Water Pump - installed

Water Pump probes - installed

Water Pump controls & JB - installed

Earthing - Installed

5Oil dam - Type

B Brick

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 40 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Foundation - position, depth & size

Support - correct height

Module 'A' - correct position

Module 'B' - correct position

6Stainless Steel

Fire Walls

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 41 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1Transformer Oil Containment

Area

2 Manholes

3 Firetrap

4 Oil dam

5 Stainless Steel Fire Wall

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 42 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B8 – Stage 8: Steelwork

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

1 Steelwork DeliverySteelwork delivery inspection - verification

of material condition & galvanising.

Assembling.

Installed, plumbed & levelled.

Bolts torqued.

Grouting

2

Steelwork :

______________________

Quality Control Checksheet for Steelwork

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 43 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Steelwork Delivery

2 Steelwork Installation

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Steelwork

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 44 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B9 – Stage 9: Fencing

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

1 Fencing DeliveryFencing delivery inspection - verification of

material condition & galvanising.

Assembling

Installed, plumbed & levelled

Bolts sheared

Earthing

Labelling

Assembling

Installed, plumbed & levelled

Earthing

Labelling

Quality Control Checksheet for Fencing

2 Palisade Fence

3 Diamond Mesh Fence

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 45 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Installation

Labelling

Installed, plumbed & levelled

Locks

Earthing

Labelling

6 Boundary Fence & Gate Installation

5 Gates

4 Precast Walls

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 46 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1 Fencing Delivery

2 Palisade Fence

3 Diamond Mesh Fence

4 Precast Walls

5 Gates

6 Boundary Fence & Gate

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Fencing

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 47 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B10 – Stage 10: Power Transformer Delivery & Assembly

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Transformer Delivery from supplier - Health

& Safety Plan approvedSupplier accept that site is accessible for

the delivery of the transformer.Transformer plinth & slipway - concrete

works completed and cured.Transformer position indicated on the

plinth.Supplier tests conducted and witnessed by

Control Plant Maintenance.

Transformer Delivery Checklist completed.

Refer to Document: DFM 34-1901

1Transformers - Delivery &

Installation by Supplier

Quality Control Checksheet for Primary Equipment: Power Transformer Delivery & Assembly

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 48 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1Transformers - Delivery &

Installation by Supplier

Accepted by Control Plant Maintenance Manager:

Name Signature Date

Accepted by Eskom Plant Department:

Name Signature Date

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Primary Equipment: Power Transformer Delivery & Assembly

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 49 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B11 – Stage 11: Primary Equipment Installation

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Transformer Oil levels – conservator – tap-changer

Ensure no oil leaks. Check at sampling

points, bushings and radiator couplings.

Bushings - Check for broken/chipped.

Check for acrylic covers on MV bushings

(Covers to have drain holes to prevent

moisture build-up)

Silica Gel Breather - correctly installed and

correct colour.

Labelling

Earthing installation correct.

Oil sample tests & results

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Power Transformer

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 50 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Auxiliary Transformer Delivery from supplier - general condition.

Installation

Orientation

Oil levels – conservator

Ensure no oil leaks. Check at sampling points,

bushings and radiator couplings.

Bushings - Check for broken/chipped.

Check for acrylic covers on MV bushings (Covers to

have drain holes to prevent moisture build-up)

Silica Gel breather - correctly installed and correct

colour.

Labelling

Earthing installation correct.

Oil sample tests & results

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Auxiliary Transformer

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 51 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

NECRT Delivery from supplier - general condition.

Installation

Orientation

Oil levels – conservator

Ensure no oil leaks. Check at sampling

points, bushings and radiator couplings.

Bushings - Check for broken/chipped.

Check for acrylic covers on MV bushings

(Covers to have drain holes to prevent

moisture build-up)

Silica Gel breather - correctly installed and

correct colour.

Labelling

Earthing installation correct.

Oil sample tests & results

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - NECRT's

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 52 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Capacitor Bank Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped.

Earthing correct.

Labelling

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Capacitor Bank

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 53 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Circuit Breaker Delivery from supplier - general condition.

Installation

Orientation correct.

Bushings - Check for broken/chipped.

Earthing correct.

Function / Pre-commissioning testing

Labelling

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Circuit Breaker

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 54 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Current Transformer Delivery from supplier - general condition.

Installation

Orientation

Oil levels - no leaks.

Bushings - Check for broken/chipped.

Earthing correct.

Labelling

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Current Transformer

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 55 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Voltage Transformer Delivery from supplier - general condition.

Installation

Oil levels - no leaks.

Bushings - Check for broken/chipped.

Earthing correct.

Labelling

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Voltage Transformer

1

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 56 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Isolator Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped

porcelain.

Earthing correct.

Function / Pre-commissioning testing

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Isolators

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 57 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Earth Switch Delivery from supplier - general condition.

Installation

Orientation

Earthing correct.

Function / Pre-commissioning testing

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Earth Switch

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 58 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Surge Arrestor Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped.

Earthing correct.

Labelling

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Surge Arrestors

Drawing No:__________

Type:_________________

Make:________________

Serial No:_____________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 59 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)COW Signature

Post Insulator Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped.

Overall Condition

Quality Control Checksheet for Primary Equipment Installation - Post Insulators

Type:_________________

Make:________________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 60 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist Sub Section

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

8 Post Insulators Installation

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Installation

Function testing

Data Captured

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Equipment Installation

Auxiliary Transformer1

Capacitor Banks2

9 Power Transformer

3 Circuit-breakers

11 Voltage transformers

10 Surge arresters

7 Necrt's

Current transformers4

5 Earth Switch

6 Isolators

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 61 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B12 – Stage 12: Conductor, Busbars & Clamps Installation

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Delivery inspection - compliance to

specification

Installation

Correct strain/suspension insulators

Sag & Tension

Delivery inspection - compliance to

specification

Installation

Correct support insulators

Correct size & lengths

Quality Control Checksheet for Conductor, Busbars & Clamps Installation

1

Busbars/Stringers - Conductor

No:___________________

Type:__________________

2

Busbars - Tubular

No:___________________

Type:__________________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 62 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Delivery inspection - compliance to

specification

Installation

Conductor jumper size

Correct clamp

Correctly torqued/crimp

Clearances correct

Delivery inspection - compliance to

specification

Installation

Sag & Tension

4

Shieldwire

No:___________________

Type:__________________

3Jumpers, Clamps & Spacers

Position:_______________

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 63 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

COW - Quality

Assurance

Check : Name

Signature

1Busbars/Stringers -

Conductor

2 Busbars - Tubular

3 Jumpers, Clamps & Spacers

4 Shieldwire

5 Data Captured

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Civil Works: Conductor, Busbars & Clamps Installation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 64 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B13 – Stage 13: Control Plant Installation

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

1 Drawings Drawing checks

Protection panel acceptance tests

Transformer acceptance tests

Current transformers acceptance tests

Voltage transformers acceptance tests

Circuit-breakers acceptance tests

Wiring and cabling checks

Transformer commissioning tests

Current transformer commissioning tests

Circuit-breaker commissioning tests.

Protection functional tests

Auxiliary transformer/commissioning test

Setting sheet handed over

Sheet No:

4 Setting sheet

Quality Control Checksheet - Protection

2 Acceptance Tests

3 Commissioning Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 65 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Ensure that the panel layout and equipment

installed are in accordance with the

specification drawings.

Verify cable and wire numbering.

Install meters and verify that they have

been tested by an approved SANAS

laboratory.

Install modem and communication cabling

to meters.Obtain all test certificates for hand over -

meters, CTs and VTsEnsure that CT test blocks have shorting

strips connectedEnsure that VT test blocks do not have

shorting strips

Ensure that proper labels are fitted

Verify Insulation test results for

acceptance?Verify Magnetizing test results for

acceptance?Verify Accuracy test results for

acceptance?Verify cabling connections onto the correct

CT ratio?Verify Injection test results to determine

correct CT connected ratio.

Verify Polarity test results for acceptance.

Quality Control Checksheet - Metering

1 Pre-Commissioning

2Pre-Commissioning

CT's

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 66 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Verify Insulation test results for

acceptance.

Verify VT ratio test results for acceptance.

Verify cabling connections onto the correct

VT winding.

Verify Polarity test results for acceptance.

4

Pre-Commissioning

Meter panel functional

tests

Verify Injection test results for acceptance.

Verify correct voltage registered onto

meter.

Verify VT burden measurements test

results for acceptance.

Verify CT burden measurements test

results for acceptance.

Verify Voltage drop test results for

acceptance.

Verify customer pulsing (where

applicable).

Verify VT fail alarms through to

supervisory (if applicable)

Verify correct meter configuration and load

profile channel allocation

Verify correct time and date on all meters

Verify correct phasor diagram results on

all meters

Verify on-load accuracy of all meters for

both kWh and kVArh

5Commissioning of

Metering equipment

3Pre-Commissioning

VT's

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 67 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Verify correct channel allocation on

MV90.

Verify correct CT and VT factors on MV90

Verify correct channel mapping on MV90

Verify communication through to all

meters.

7Post Commissioning

Data verification

Verify results from a metering verification

procedure for acceptance.

8Billing

Customer services

Verify Customer Services acceptance and

sign-off .

6Commissioning of the

MV90 master station

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 68 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Temporary incoming AC supply

commissionedPermanent incoming AC supply

commissioned.

Yard AC distribution commissioning test

Day-Night switch fitted

2Control Building AC

distributionCOC for building issued.

Hazardous area COC obtained

Zoning done

Ventilation checked

Fire walls built up

Basin outlet correct

Safety signs on entrances

Appropriate safety equipment available

Water available

Quality Control Checksheet for AC/DC Auxiliary systems

1Yard AC distribution

commissioning test

3 Battery Room acceptance

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 69 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Battery cable ducting entry in battery room

sealedDucting end correct height above floor

level

Battery charger commissioning test

Panel labels and boost labels installed

Battery commissioning test

Pilot cell label and cell numbering

Emergency lights commissioning test

Correct fittings and bulbs used.

8 Wiring Panel wiring and cable checks

9Incoming AC selection and

commissioning

Incoming AC selection and commissioning

test

4Battery cable ducting entry in

battery room

5 Battery charger

6 Battery commissioning test

7 Emergency lights

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 70 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

AC/DC onsite commissioning test

Temporary incoming AC supply

commissionedPermanent incoming AC supply

commissioned

Inverter commissioning tests

Converter commissioning tests

Yard box tested to control

Charger tested to control

Power electronic tested to control

13 LabellingCorrect safety signs on self-contained

battery enclosures

12 Alarms

10 AC/DC panel

11 Power electronic equipment

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 71 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

1 Drawings & preparationLatest cable block diagram and control room

layout issued.

Cable drums unrolled in the correct direction.

All cables indicated on cable blocks installed.

Correct cable sizes installed: core numbers and

cross-sectional area.

Cables terminated using correct glands for cable

size.

All cables numbered on both ends.

Cable routing is neat and orderly.

Correct hole size for applicable gland.

Cable gland & shroud

Ensure that the insulation of the wiring is not

cut/damaged. Pay particular attention to the area

just above the gland.

Open gland holes to be plugged.

3 Glanding of cables

Quality Control Checksheet - Control Wiring

2 Cabling

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 72 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

All wiring checked and tested with an insulation

voltage tester (megger)

All wires numbered at both ends

All wiring neatly strapped/fitted in trunking

380 V supplies, phase sequence and colour

indication correctSpare cores earthed at location closest to power

plant equipment (or in junction box)

Check that the correct panel type has been

installed (scheme designation matches drawings)

Confirm rated DC voltage of scheme matches

substation DC supply: 110V vs 220V

Confirm presence of transducers (where

applicable)

Panels securely fastened to the floor/walls to

prevent tipping when the door is opened.

Panel/junction box appropriately connected to

substation earth mat.

All bolted plates to be connected to the panel

earth bar using green/yellow 2.5sqmm earhting

wire using the earthing studs provided.

Ensure that schemes are fitted such that all

controls and indications on panels are at a

reasonable working height from the ground.

All apertures in panel closed (vermin proof)

Panels free of lose bolts, offcuts, clippings and

shavings

All trunking covers fitted

Terminal screws secure

No exposed bare wires within panels

Wiring & Numbering

Panels and junction boxes

House keeping

4

5

6

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 73 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

P1 side of Current Transformers faces circuit-

breaker

Kiosk circuit-breakers installed in the correct

orientation with respect to phasing.

Appropriate neutral surge arrester fitted to

unearthed power transformer windings with

partially graded insulation.

Current transformers (all cores)

Voltage transformers

Disconnectors (aux contacts)

Power transformers

Neutral Electromagnetic couplers

Circuit-breakers

Earth switches

Drawings marked-up with on-site changes

Settings documentation marked-up with on-site

changes.

7

8

9

Power plant check sheet

Test sheets provided for

Documentation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 74 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Telecomms equipment

Telecomms equipment installed

ID/NAMEF installation cross connections:

Cables numbered and drawings updatedEarthing of equipment Station earth

resistivity checked and notedRepeater buildings, cable trays and

feeders in place

Security equipment

2 SecurityPerimeter electrified fence:

Commissioned

3 TransformerTransformer enclosure electrified:

Commissioned

4 MicrowaveMicrowave security system and control

box, etc.: CommissionedAll records updated in system book and

Network Diagram, etc.

General comments:

1 Equipment

5 Records & General

Quality Control Checksheet - Telecommunication Equipment

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 75 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Create RTU Configuration.

Create Master Station Database

Verify Communications link to Master.

Test and record AR Field Strength.

Verify correct cable termination on IDF.

Verify cable and IDF numbering.

Assemble RTU and test Configuration.

Verify all RTU-to-IDF cabling.

Simulate all Digital Inputs from IDF to

Master.Inject all Analog Inputs from IDF to

Master.Measure Control Output Voltages on IDF

when sent from Master.

Quality Control Checksheet - Telecontrol Equipment

1 Configuration

2Pre-Commissioning

[Phase 1]

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 76 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Install cross connection wiring on IDF.

Test all Digitals, Analogs and Controls

from/to Control plant Panels from RTU.Verify all Digitals and Analogs form

Equipment Panels to Master.Verify all Controls from Master to

Equipment Panels by visual confirmation of

Relay operation.

Functional testing to be done in

accordance with Commissioning

Schedule/Screed as supplied by Regional

Control.

Ensure that all system records are updated

and modifications returned to ED Project

Engineering.

Ensure that latest version Configuration

and Station Records remain on site after

completion of commissioning.

4 Commissioning

3Pre-Commissioning

[Phase 2]

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 77 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

1 EquipmentVisual check of mechanical installation and

Earthing

Wiring: (Internal and External)

Check for dry joints and loose

connections. Visual check on ID/NAMEF

3 Line-MatchingTest carried out according to Telecomms

Standards

4 Line-upLine-up: System line-up Test Sheet

completed and signed

5 AlarmsAlarms: All alarms checked from initiating

panel through to Regional Control Centre

6 Intertripping Intertripping: End-to-end intertripping

7 RecordsAll records updated in System Book and

Network Diagram, etc.

2 Wiring

Quality Control Checksheet - Telecommunication Carrier

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 78 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W)

Head of Telecomms Dept

Signature

1 Equipment InstallationVisual check of mechanical installation and

earthing

Wiring: (Internal and External)

Check for dry joints and loose

connections. Visual check on ID/NAMEF

3 Tower and Accessories Check feeder, antenna, brackets and

tower earthing

4 Earth resistivity Station earth resistivity check and noted

5 Line-up Installation and line-up sheets completed

and signed

6 Alarms Check alarms to Regional Control Centre

7 RecordsAll record updated in System Book and

Network Diagram, etc.

2 Wiring

Quality Control Checksheet - Telecommunications Broadband/Radio

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 79 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 Eskom EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

1 Switchgear operation Switchgear operates freely

2 Tools Special tools supplied where applicable

3 DrawingsDrawings and manuals on site (scheme

drawings and applicable manuals)

4 Labelling All feeders correctly labelled

5 General Excess material removed and site cleaned

Applicable certificates received from Plant

SpecialistsApplicable certificates received from Cable

Construction/ContractorApplicable certificates received from

Contractor

7 InstructionInstruction given to PT&M section to

proceed with Dead Testing.

6 Certificates

Quality Control Checksheet - Labelling & Documentation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 80 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Appointed Contractor:

4 Appointed COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

EDFS - Quality

Assurance

Check : Name

Signature

1Quality Control Checksheet for

AC/DC Auxiliary systems

2Quality Control Checksheet -

Control Wiring

3Quality Control Checksheet -

Labelling & Documentation

4Quality Control Checksheet -

Protection

5Quality Control Checksheet -

Metering

6Quality Control Checksheet -

Telecommunication Equipment

7Quality Control Checksheet -

Telecontrol Equipment

8Quality Control Checksheet -

Telecommunication Carrier

9

Quality Control Checksheet -

Telecommunications

Broadband/Radio

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Control Plant Installation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 81 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B14 – Stage 14: Commissioning Testing

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and Equipment Intact and Visually

Sound

Panel not Damaged

Panel Wired according to application drawings

supplied.

Scheme version on equipment and drawings

correspond

Panel equipment corresponds in make, model

and function to the application drawings

provided.

The panel and associated equipment is

correctly earthed.

Protection Data Capture Form Complete

All Applicable TI's and TB's implemented (detail

on PDC)

All IED Settings Correctly Applied

Relay Characteristic Tests and Logic Functions

Completed (Omicron Results Required)

DC and functional Checks as per drawing

Transducer Outputs Correct

Telecontrol: Supervisory controls operate

correctly. Alarms, indications and analogue

outputs are correct to the control centre

Test Blocks and shorting strips operate

correctly.

1

Data Capture 2

Secondary Injection Tests3

Quality Control Checksheet - Transformer Commissioning Testing

Panel Checks and Visual

Inspection

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 82 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Breaker Speed Checks – HV and MV

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current Transformer

test procedure”. These include all: HV and MV

post type CT's, HV, MV and Neutral bushing

type CT's and NEC/R CT's.

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio Tests – All Cores

Secondary Loop Tests – All Cores (Specify

Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests on 132kV CT's

Oil Level Checks on All CT's

Application of Specified CT Ratio (All Cores)

VT Tests in compliance with Distribution

Standard DISPVAEB6R0 “Voltage transformer

test procedure”

VT Polarity Tests – All Cores

VT Ratio Tests – All Cores

VT Insulation Resistance Tests

VT Checking of Oil Levels

Tan Delta Tests on all Trfr Capacitive Bushings

Transformer and Earthing transformer Tests

according to the Distribution Standard

SCSPVADJ2R0 “Procedure for the testing of

power transformers”.

Primary Injection Tests4

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 83 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Vector Group Tests

Ratio Tests

Positive Sequence Impedance Tests on all tap

positions

Zero Sequence Impedance Tests: Transformer

HV and MV and NEC/R

Insulation Resistance Tests

Frequency Response Test FRA

Winding Resistance

NER Resistance

Calibration and setting of winding and oil

temperature gauges and tripping functions

(both electromechanical and electronic). Both

Power Transformer and NEC/R

Calibration and function of Bucholtz and

pressure relief devices on both Power

Transformer and NEC/R

Tap change and tap change load diverter tests

Transformer, NECR, and attached bushings.

CT oil level checks.

Confirmation of fin valves

Operation of fans and pumps

Primary Injection Tests for Protection Circuits

Verification of applied CT Ratios;

Overcurrent and Earth Fault Tests;

Metering equipment verification tests;

Differential protection sensitivity check;

Differential stability check;

Restricted earth fault sensitivity check;

Restricted earth fault stability check

Negative phase sequence primary test;

Zero sequence elimination stability check for

differential relays

Primary Injection Tests

Primary Injection Tests

5

6

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 84 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All tripping circuits normalised and proven to

trip the circuit breakers. Main and Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and addressed

according to defect list

The transformer bay is ready to be energised.

Arrangements have been made with the

authorised person in terms of the ORHVS to

clear all outstanding work permits on this bay.

Panel Test Sheet has been completed – record

Panel Test Sheet Number in the Remarks

column

7 Primary Injection Tests

Consolidation of Test Results8

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 85 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

VT Voltage Ratio Check

Auxiliary Voltage Check

VT Phasing Check – Correct Phase Rotation

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with Control

Centre – Cross Check with values given by

IED or panel meters

On-load stability check for differential relay.

Confirm zero spill current

Directional Checks for Impedance and

directional overcurrent relays.

On load operation of tap changer.

Record power factor and loading measured by

the tap change control relay

Completion of certificate as equipment fully

commissioned

Marked Up drawings. Copy in substation, copy

to Design Office, copy to the area EDFS

office.

Handover Certificate Completed and submitted

by Head of Commissioning Team

Commissioning Test Results Complete and

Compiled

On load check results with analogue results

must be attached to commissioning results.

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings downloaded

and forwarded to EDNS Configuration and Co-

ordination

Protection Data Capture Sheet (PDCS)

On load Energisation Checks9

Final Documentation and

documentation consolidation10

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 86 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Panel and Equipment Intact and Visually

Sound

Panel not Damaged

Panel Wired according to application

drawings supplied.

Scheme version on equipment and

drawings correspond

Panel equipment corresponds in make,

model and function to the application

drawings provided.

The panel and associated equipment is

correctly earthed,

Protection Data Capture Form Complete

All Applicable TI's and TB's implemented

(detail on PDC)

All IED Settings Correctly Applied

Relay Characteristic Tests and Logic

Functions Completed (Omicron Results

Required)

DC and functional Checks as per drawing

Transducer Outputs Correct

Telecontrol: Supervisory supervisory

controls operate correctly. Alarms,

indications and analogue outputs are

correct to the control centre

Test Blocks and shorting strips operate

correctly.

Data Capture

3 Secondary Injection Tests

Quality Control Checksheet - HV Feeder Commissioning Testing

1Panel Checks and Visual

Inspection

2

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 87 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

Circuit Breaker Speed Checks

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current

Transformer test procedure”

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio Tests – All Cores

Secondary Loop Resistance Tests – All

Cores (Specify Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests

Oil Level Checks on All CT's

Application of Specified CT Ratio (All

Cores)

VT Tests in compliance with Distribution

Standard DISPVAEB6R0 “Voltage

transformer test procedure”

VT Polarity Tests – All Cores

VT Ratio Tests – All Cores

VT Insulation Resistance Tests

VT Checking of Oil Levels

Primary Injection Tests for Protection

Circuits

Verification of applied CT Ratios;

Overcurrent and Earth Fault Tests;

End to End checks to confirm Auto

Reclose, communications and

teleprotection systems operational

Primary Injection Tests4

Primary Injection Tests5

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 88 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

All tripping circuits normalised and proven

to trip the circuit breakers. Main and

Backup trip coils

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and

addressed according to defect list

The HV feeder bay is ready to be

energised.

Arrangements have been made with the

authorised person in terms of the ORHVS

to clear all outstanding work permits on this

bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

6 Normalisation of Circuits

7 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 89 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) COW Signature

New feeders – perform end to end phasing

checks.

VT Voltage Ratio Check

Auxiliary Voltage Check

VT Phasing Check – Correct Phase

Rotation

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with

Control Centre – Cross Check with values

given by IED or panel meters

Directional Checks - Impedance and

directional overcurrent relays.

Record power factor and loading

measured by numerical impedance IED

Completion of certificate: Equipment fully

commissioned

Marked Up drawings. Copy in substation,

copy to EDNS Design Office, copy to the

area EDFS office.

Handover Certificate Completed and

submitted by Head of Commissiong Team

Commissioning Test Results Complete and

Compiled

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet Completed

(PDCS)

8 On load Energisation Checks

9Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 90 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and equipment intact and visually sound

Panel not damaged

Panel wired according to application drawings

supplied.

Scheme version on equipment and drawings

correspond

Panel equipment corresponds in make, model

and function to the application drawings

provided.

The panel and associated equipment is

correctly earthed according to TQAKS008

Protection data capture form complete

All applicable TI's and TB's implemented

(detail on PDC)

All IED settings correctly applied

Relay characteristic tests and logic functions

completed (Omicron Results Required)

DC and functional checks as per drawing

Transducer outputs correct

Telecontrol: Supervisory controls operate

correctly. Alarms, indications and analogue

outputs are correct to the control centre

Test blocks and shorting strips operate

correctly.

3 Secondary Injection Tests

Quality Control Checksheet - Rural Feeder Commissioning Testing

1Panel Checks and Visual

Inspection

2 Data Capture

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 91 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Breaker Speed Checks – HV and MV

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current

Transformer test procedure”. These include

all: dog box CT’s; indoor switch gear CT’s or

post

CT’s.

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio tests – All Cores

Secondary loop tests – All Cores (Specify

Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests on 132kV CT's

Oil Level Checks on All CT's

Application of Specified CT Ratio (All Cores)

VT Tests in compliance with Distribution

Standard DISPVAEB6R0 “Voltage transformer

test procedure”. This is applicable for indoor

switchgear switching station or busbar VT’s.

VT Polarity Tests – All Cores

VT Ratio Tests – All Cores

VT Insulation Resistance Tests

VT Checking of Oil Levels

4 Primary Injection Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 92 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All tripping circuits normalised and proven to

trip the circuit breakers. Main and Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and addressed

according to defect list

The rural feeder is ready to be energised.

Arrangements have been made with the

authorised person in terms of the ORHVS to

clear all outstanding work permits on this bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

5 Normalisation of Circuits

6 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 93 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

VT Voltage Ratio Check

Auxiliary Voltage Check

VT Phasing Check – Correct Phase Rotation

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with

Control Centre – Cross Check with values

given by IED or panel meters

On-load stability check for differential relay.

Confirm zero spill current

Directional Checks for directional over current

relays.

Completion of certificate as equipment fully

commissioned

Marked Up drawings. Copy in substation,

copy to Design Office, copy to the area EDFS

office.

Handover Certificate Completed and submitted

by Head of Commissioning Team

Commissioning Test Results Complete and

Compiled

On load check results with analogue results

must be attached to commissioning results.

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet (PDCS)

7 On load Energisation Checks

8Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 94 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and Equipment Intact and Visually

Sound

Panel not Damaged

Panel Wired according to application

drawings supplied.

Scheme version on equipment and

drawings correspond

Panel equipment corresponds in make,

model and function to the application

drawings provided.

The panel and associated equipment is

correctly earthed according to TQAKS008

Protection Data Capture Form Complete

All Applicable TI's and TB's implemented

(detail on PDC)

Quality Control Checksheet - Cable Feeder Commissioning Testing

1Panel Checks and Visual

Inspection

2 Data Capture

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 95 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All IED Settings Correctly Applied

Relay Characteristic Tests and Logic

Functions Completed (Omicron Results

Required)

DC and functional Checks as per drawing

Transducer Outputs Correct

Telecontrol: Supervisory controls operate

correctly. Alarms, indications and

analogue outputs are correct to the control

centre

Test Blocks and shorting strips operate

correctly.

Breaker Speed Checks – HV and MV

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current

Transformer test procedure”. These

include all : indoor CT’s; post CT’s; dog

box CT’s.

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio Tests – All Cores

Secondary Loop Tests – All Cores

(Specify Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests on 132kV CT's

Oil Level Checks on All CT's

Application of Specified CT Ratio (All

Cores)

VT Tests in compliance with Distribution

Standard DISPVAEB6R0 “Voltage

transformer test procedure”

VT Polarity Tests – All Cores

VT Ratio Tests – All Cores

VT Insulation Resistance Tests

VT Checking of Oil Levels

3 Secondary Injection Tests

4 Primary Injection Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 96 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All tripping circuits normalised and proven

to trip the circuit breakers. Main and

Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and

addressed according to defect list

The cable feeder is ready to be energised.

Arrangements have been made with the

authorised person in terms of the ORHVS

to clear all outstanding work permits on this

bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

5 Normalisation of Circuits

6 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 97 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

VT Voltage Ratio Check

Auxiliary Voltage Check

VT Phasing Check – Correct Phase

Rotation

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with

Control Centre – Cross Check with values

given by IED or panel meters

On-load stability check for differential

relay. Confirm zero spill current

Directional Checks for overcurrent relays.

Completion of certificate as equipment fully

commissioned

Marked Up drawings. Copy in substation,

copy to Design Office, copy to the area

EDFS office.

Handover Certificate Completed and

submitted by Head of Commissioning

Team

Commissioning Test Results Complete and

Compiled

On load check results with analogue results

must be attached to commissioning results.

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet (PDCS)

7On load Energisation Checks

and result capture

8Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 98 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and Equipment Intact and Visually

Sound

Panel not Damaged

Panel Wired according to application

drawings supplied.

Scheme version on equipment and

drawings correspond

Panel equipment corresponds in make,

model and function to the application

drawings provided.

The panel and associated equipment is

correctly earthed according to TQAKS008

Protection Data Capture Form Complete

All Applicable TI's and TB's implemented

(detail on PDC)

Quality Control Checksheet - Bus Coupler Commissioning Testing

1Panel Checks and Visual

Inspection

2 Data Capture

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 99 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All IED Settings Correctly Applied

Relay Characteristic Tests and Logic

Functions Completed (Omicron Results

Required)

DC and functional Checks as per drawing

Transducer Outputs Correct

Telecontrol: Supervisory controls operate

correctly. Alarms, indications and

analogue outputs are correct to the control

centre

Test Blocks and shorting strips operate

correctly.

Breaker Speed Checks – HV and MV

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current

Transformer test procedure”. These

include all post CT’s; indoor or dogbox

CT’s.

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio Tests – All Cores

Secondary Loop Tests – All Cores

(Specify Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests on 132kV CT's

Oil Level Checks on All CT's

Application of Specified CT Ratio (All

Cores)

3 Secondary Injection Tests

4 Primary Injection Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 100 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All tripping circuits normalised and proven

to trip the circuit breakers. Main and

Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and

addressed according to defect list

The bus coupler is ready to be energised.

Arrangements have been made with the

authorised person in terms of the ORHVS

to clear all outstanding work permits on this

bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

5 Normalisation of Circuits

6 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 101 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Auxiliary Voltage Check

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with

Control Centre – Cross Check with values

given by IED or panel meters

On-load stability check for differential

relay. Confirm zero spill current

On load operation of tap changer.

Record power factor and loading

measured by the tap change control relay

Completion of certificate as equipment fully

commissioned

Final Documentation and documentation

consolidation

Marked Up drawings. Copy in substation,

copy to Design Office, copy to the area

EDFS office.

Handover Certificate Completed and

submitted by Head of Commissioning

Team

Commissioning Test Results Complete and

Compiled

On load check results with analogue results

must be attached to commissioning results.

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet (PDCS)

7On load Energisation Checks

– All results to be recorded

8Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 102 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and equipment intact and visually

sound

Panel not damaged

Panel wired according to application

drawings supplied.

Scheme version on equipment and

drawings correspond

Panel equipment corresponds in make,

model and function to the application

drawings provided.

The panel and associated equipment is

correctly earthed according to TQAKS008

Protection data capture form complete

All applicable TI's and TB's implemented

(detail on PDC)

Quality Control Checksheet - ARC Detection Scheme Commissioning Testing

1Panel Checks and Visual

Inspection

2 Data Capture

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 103 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All IED settings correctly applied

Relay characteristic tests and logic

functions completed (Omicron Results

Required)

DC and functional checks as per drawing

and to the matrix that is attached to the

panel.

Telecontrol: supervisory controls operate

correctly. Alarms, indications and

analogue outputs are correct to the control

centre

Test Blocks and shorting strips operate

correctly.

Ratio Tests – from incomer/transformer for

all master relays.

Secondary Loop Tests – All Cores

(Specify Circuits)

All tripping circuits normalised and proven

to trip the circuit breakers. Main and

Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

3 Secondary Injection Tests

4 Primary Injection Tests

5 Normalisation of Circuits

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 104 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All test that have been planned have been

completed

All test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and

addressed according to defect list

The substation switchgear is ready to be

energised.

Arrangements have been made with the

authorised person in terms of the ORHVS

to clear all outstanding work permits on this

bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

Current Measurement Check – on load

confirmation of CT Ratios

If ARC detection is added and unused CT

core is used, then mag curve of the core

only needs to be done.

Completion of certificate as equipment fully

commissioned

7 On load Energisation Checks

6 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 105 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Marked Up drawings. Copy in substation,

copy to Design Office, copy to the area

EDFS office.

Handover certificate completed and

submitted by Head of Commissioning

Team

Commissioning test results completed and

compiled

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

On load check results with analogue results

must be attached to commissioning results.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet (PDCS)

Confirmation of laminated matrix is

properly attached to the ARC detecting

panel.

P-touch information i.e. CT ratio, plug

setting, time multiplier, etc. to be marked

on panel – right hand side of relay.

8Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 106 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 EDFS:

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Panel and Equipment Intact and Visually

Sound

Panel not Damaged

Panel Wired according to application

drawings supplied.

Scheme version on equipment and

drawings correspond

Panel equipment corresponds in make,

model and function to the application

drawings provided.

The panel and associated equipment is

correctly earthed according to TQAKS008

Protection Data Capture Form Complete

All Applicable TI's and TB's implemented

(detail on PDC)

All IED Settings Correctly Applied

Relay Characteristic Tests and Logic

Functions Completed (Omicron Results

Required)

DC and functional Checks as per drawing

Transducer Outputs Correct

Telecontrol: Supervisory controls operate

correctly. Alarms, indications and

analogue outputs are correct to the control

centre

Test Blocks and shorting strips operate

correctly.

Quality Control Checksheet - Capacitor Bank Commissioning Testing

1Panel Checks and Visual

Inspection

2 Data Capture

3 Secondary Injection Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 107 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Breaker Speed Checks – HV and MV

CT Tests in compliance with Distribution

Standard DISPVAEC6R0 “Current

Transformer test procedure”. These

include all: post type CT's and imbalance

CT’s.

Polarity Test – All Cores

Magnetisation Curve Test – All Cores

Ratio Tests – All Cores

Secondary Loop Tests – All Cores

(Specify Circuits)

Insulation Resistance Tests – All Cores

Tan Delta Tests on 132kV CT's

Oil Level Checks on All CT's

Application of Specified CT Ratio (All

Cores)

VT Tests in compliance with Distribution

Standard DISPVAEB6R0 “Voltage

transformer test procedure”

VT Polarity Tests – All Cores

VT Ratio Tests – All Cores

VT Insulation Resistance Tests

VT Checking of Oil Levels

4 Primary Injection Tests

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 108 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

All tripping circuits normalised and proven

to trip the circuit breakers. Main and

Backup

All alarm circuits normalised and proven.

All IED settings normalised as per

documentation provided by EDNS

Configuration and Co-ordination.

All IED configuration logic and protections

function normalised as per documentation

provided by EDNS Configuration and Co-

ordination

All Test that have been planned have been

completed

All Test results obtained are consistent with

reasonable engineering expectations

All defects have been itemised and

addressed according to defect list

The capacitor bank is ready to be

energised.

Arrangements have been made with the

authorised person in terms of the ORHVS

to clear all outstanding work permits on this

bay.

Panel Test Sheet has been completed –

record Panel Test Sheet Number in the

Remarks column

5 Normalisation of Circuits

6 Consolidation of Test Results

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 109 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Item Checklist QC items to check or supplyHolding Point

Required (Y/N)

Photo Required

(Y/N)Contractor Signature

Verified (V)

Witnessed (W) EDFS Signature

Neutral Spill must be recorded before

adjustment and after adjustment.

Relay adjusted

Record capacitance of each Cap with

serial number

Record Imbalance

VT Voltage Ratio Check

Auxiliary Voltage Check

VT Phasing Check – Correct Phase

Rotation

Current Measurement Check – on load

confirmation of CT Ratios

Verification of Analogue quantities with

Control Centre – Cross Check with values

given by IED or panel meters

Record Harmonic readings

Completion of certificate as equipment fully

commissioned

Marked Up drawings. Copy in substation,

copy to Design Office, copy to the area

EDFS office.

Handover Certificate Completed and

submitted by Head of Commissioning

Team

Commissioning Test Results Complete and

Compiled

On load check results with analogue results

must be attached to commissioning results.

Proof of implementation of Technical

Instructions and Bulletins – document

completed.

Proof of applied settings – settings

downloaded and forwarded to EDNS

Configuration and Co-ordination

Protection Data Capture Sheet (PDCS)

7 On load Energisation Checks

8Final Documentation and

documentation consolidation

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 110 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

1 Project name:

2 Contract/Order No:

3 Contractor:

4 COW:

Item Checklist

Contractor -

Quality

Assurance

Check : Name

Signature

EDFS - Quality

Assurance

Check : Name

Signature

1

Quality Control Checksheet -

Transformer Commissioning

Testing

2Quality Control Checksheet - HV

Feeder Commissioning Testing

3

Quality Control Checksheet -

Rural Feeder Commissioning

Testing

4

Quality Control Checksheet -

Cable Feeder Commissioning

Testing

5Quality Control Checksheet - Bus

Coupler Commissioning Testing

6

Quality Control Checksheet -

ARC Detection Scheme

Commissioning Testing

7

Quality Control Checksheet -

Capacitor Bank Commissioning

Testing

Accepted by Project Manager:

Name Signature Date

Handover Checklist for Commissioning Testing

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 111 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B15 – Stage 15: Provisional Handover

1 Project name:

2 Contract/Order No:

3 Project Manager:

Stage ActivityHandover per stage

completed (Y/N)

Received by Project

ManagerDate

1 Civil Works: Platform

2 Civil Works: Control Building

3 Civil Works: Subsoil drainage

4 Civil Works: Earthmat Installation

5Civil Works: Equipment Foundations &

Cable trenches

6 Civil Works: Roads, Stoning & Kerbing

7Transformer bund wall, oil dam and fire

wall

8 Steelwork Erection

9 Fencing

10Power Transformer Delivery &

Assembly

11 Primary Equipment Installation

12 Conductors, busbars & clamps

13 Control Plant installation

13 Commissioning Testing

Accepted by: Project Manager (Name & Signature) Date

Accepted by: Senior Design Engineer (Name & Signature) Date

Accepted by: Control Plant Maintenance Manager (Name & Signature) Date

StageConfirmed by Project

ManagerDate

1

2

Accepted by: Project Manager (Name & Signature) Date

Accepted by: Network Operations Manager (Name & Signature) Date

Station Electric Diagram updated and SCADA updated at Control

Operating procedure for commissioning complete

(Project Provisionally handed over for final Commissioning)

Plant and Equipment provisionally handed over and pre-commission testing completed in order to arrange final

commissioning

Activity

Document Classification: Controlled Disclosure

QUALITY CONTROL PROCESS FOR THE CHECKING OF DISTRIBUTION SUBSTATION CONSTRUCTION BEFORE HANDING OVER FOR COMMERCIAL OPERATION

Unique Identifier: 34-1238

Revision: 0

Page: 112 of 112

ESKOM COPYRIGHT PROTECTED

When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.

Annexure B16 – Stage 16: Final Handover

1 Project name:

2 Contract/Order No:

3 Name of Project Manager:

Stage ActivityHandover per stage completed

(Y/N)

Received by Project

ManagerDate

1 Civil Works: Platform

2 Civil Works: Control Building

3 Civil Works: Subsoil drainage

4 Civil Works: Earthmat Installation

5Civil Works: Equipment Foundations

& Cable trenches

6Civil Works: Roads, Stoning &

Kerbing

7 Steelwork Erection

8 Fencing

9Power Transformer Delivery &

Assembly

10 Primary Equipment Installation

11 Conductors, busbars & clamps

12 Control Plant installation

13 Commissioning Testing

14 Final Commissioning Complete

Accepted by: Project Manager (Name & Signature) Date

Accepted by: Senior Design Engineer (Name & Signature) Date

Accepted by: Asset Design Manager (Name & Signature) Date

Accepted by: Control Plant Maintenance Manager (Name & Signature) Date

Accepted by: Zone Manager (Name & Signature) Date

11.2 Environmental checklist

POWERLINE / SUBSTATION HAND-OVER ENVIRONMENTAL CHECKLIST

Name of Powerline/Substation :________________ Project I. D:______________________

Contractor:_________________________________ Clerk of Works:___________________

QUESTION Y / N / NA

ACTION TAKEN REQUIREMENTS / SPECIFICATIONS

Restriction of working areas

1. Have construction activities remained within the designated working areas?

EMP

Vegetation Management

2. If required, were the relevant permits obtained for the cutting of protected trees and fynbos? i.e. milkwood

EMP

3. Has bush clearing been done according to the Standard for Bush Clearance and maintenance within Overhead Powerline Servitudes (ESKASABG3)

ESKASABG3 / EMP

4. Have all the bush cuttings been removed from the servitude and substation?

EMP

5. Has all herbicide spraying been undertaken under the supervision of a registered Pest Control Officer.

EMP

6. Was all herbicide usage undertaken according to Eskom’s guidelines and the Standard for the Safe Use of

Pesticides and Herbicides (ESKASAAL0)?

ESKASAAL0 / EMP

7. Are there any signs of damage by herbicides to the owner’s property?

EMP

8. If yes, have measures been implemented to rehabilitate the damage caused?

EMP

Oil Spill Management

9. Have any oil or diesel spills occurred on site?

10. If yes, was a flash report issued within 24 hrs to the Environmental Management Department?

Flash Report

11. Have oil spills been managed according to the Standard for Oil Spill Clean-Up and Rehabilitation – ESKASABT0 (i.e. spills are cleared up on site)

ESKASABT0 / EMP

12. Was there stock of oil remediation chemicals on site?

EMP

13. Have bund walls been constructed, where appropriate?

EMP

Soil Erosion

14. Have any complaints been received from property owners regarding occurrence of erosion on their properties as a result of construction activities?

Complaints record / letters

15. Were any signs of erosion visible before site handover?

EMP

16. If yes, have measures been implemented to rehabilitate eroded areas?

EMP / Audit / Inspection Reports

Topsoil Management

17. Has all the topsoil been backfilled or levelled on site?

EMP

Fire Management

18. Were the emergency numbers available on site?

Emergency numbers / EMP

19. Have any incidents of veld fires occurred? Flash Report / EMP

20. Was there sufficient fire fighting equipment on site?

EMP

Disturbance to the Natural Heritage Resources

21. Were tribal graves or archaeological sites identified during the construction activities?

EMP (if relevant)

22. If yes, were recommendations/mitigation measures implemented, where appropriate?

EMP (if relevant)

Access

23. Has the existing single access route been used? (No multiple tracks allowed)

EMP

24. Have additional access routes been developed?

EMP

25. If yes, have existing / additional access routes been rehabilitated to the owners satisfaction?

EMP

26. Were entrance gates and walls rehabilitated to the property owners satisfaction?

EMP / Owners letter (if possible)

Water Management

27. Had any incidents of water pollution occurred?

EMP

28. If yes, was a flash report issued within 24hrs to the Environmental Management

Flash Report

Department?

29. Was the incident investigated and recommendations implemented?

Incident Report (if applicable)

Social Issues

30. Were any complaints registered and actioned?

Complaints / Incident register / Letters

Waste Management

31. Were there sufficient waste bins on site? EMP

32. Was litter noted during site handover? EMP

33. Has all waste material been removed and suitably disposed of at a licensed landfill site?

EMP / Waste disposal certificate

Use of cement and/or concrete

34. Was any excess cement of concrete noted during the site inspection?

EMP

35. If yes, has this been removed and disposed of, prior to site handover?

EMP

Environmental Records

36. Have the conditions of the Record of Decision (“ROD”), relevant to the construction phase of the project, been implemented?

Record of Decision (or signed copy of the Distribution Screening Document)

37. Are there special mitigatory conditions in the EMP?

EMP

38. If yes, have all the conditions in the EMP, relevant to construction been implemented?

EMP

39. Have all the recommendations from the environmental audits (e.g. by COW, PC, Environmental Practitioner) been undertaken?

Audit Reports

Site Rehabilitation

40. Have measures been implemented for site / vegetation rehabilitation, where required?

EMP / Inspection / Audit reports

To be completed by the Clerk of Works (COW) and Contractor:

Taken over by: ……………………………………………… Date: ……………………………………. (C.O.W) (NAME IN BLOCK LETTERS)

Signature: ……………………………………………………… Date: ……………………………………. (C.O.W)

Handed over by: ……………………………………………… Date: ……………………………………. (Contractor) (NAME IN BLOCK LETTERS)

Signature: ……………………………………………………….. Date: ……………………………………..

11.3 SHE report

1

SHE SPECIFICATION

Document Classification: Controlled Disclosure/Confidential Title:

SAFETY HEALTH AND ENVIRONMENTAL SPECIFICATION FOR VYEVLEI S/S

Reference: 32-524

Document Type: DSP

Revision: 0

Effective date: 20.11.2012 Total pages: 31 Revision date: 20.11.2013

COMPILED BY FUNCTIONAL RESP AUTHORISED BY

_ _ _ _ _ _ _

P Rilityane

_ _ _ _ _ _ _

S Ralarala

_ _ _ _ _ _ _

S. POTELWA

SHE OFFICER PROJECT CO-ORDINATOR RISK MANAGER

2

Table of Contents:

Item Contents Page #

1 Introduction 3

1.1 Purpose and Scope of Specification 3

1.2 Project works information, Scope of work and other detail 3

1.2.1 Location 3

1.2.2 Scope of Work 3

1.3 Normative and Informative references 4

2 Definitions and Abbreviations 4-5

3 Documentation required – Tender submittal 6

4 Administrative Requirements 7

5 Construction Requirements 15

Annexure 1 19

Annexure 2 20

Annexure 3 21 -28

Annexure 4 29

Annexure 5 30

3

1. INTRODUCTION

Eskom’s responsibility and commitment to ensure a safe working environment are in line with our Safety, Health, and Environmental Policy, along with legislative obligations. The objective of this Specification is to outline the requirements appropriate to the Occupational Health and Safety Act 85/1993 and Regulations and to ensure that a common approach is adopted when engaging in construction work.

1.1 Purpose and Scope Purpose of Specification: To provide a framework for Health, Safety and Environmental Requirements relevant to the work to be done so as to ensure the Health and Safety of persons. These specifications shall act as the basis for the drafting of the principal contractors’ and contractors’ construction phase Health & Safety plans

Scope:To ensure compliance with the Occupational Health and Safety Act (85/1993) and Regulations associated therewith so as to protect persons at work, persons working with plant and machinery and persons other than those persons at work from health and safety hazards arising out of or in connection with activities of persons at work.

1.2 Project works information, scope of work, and other details 1.2.1 Location:

1.2.2 Scope of Work:

Karoo substation is located near the town of Carnarvon. Geographical coordinates - 22°9’7.2” E 30°52’24” S

Primary Plant Replace all old 66kV and 22kV equipment with new equipment. Normalise transformer bays by equipping each bay with a 66kV circuit breaker. Standardise transformer 1 & 2 plinth and bund areas. Replace section of perimeter fence with new diamond mesh fence and modify with chicken wire and electrify as existing fence. Install new section of internal diamond mesh fence. Install new substation lights fitted on 8m masts. Lay new section of control cable trench. Normalise existing 22kV Loxton feeder by relocating the feeder position to “bottom” of 22kV busbar. Create an extra new 22kV feeder bay. Install 22kV reclosers for feeder breakers.Install a 33kV recloser with 33kV VTs and surge arrestors in transformer 3 & 4 earth path.TSG transformer workshop to refurbish existing transformer 1 & 2 on site. Control Plant Use existing building. Install new 4TM7100 and 4TC5200 schemes for transformer 1 & 2. Install recloser control box in relay room for the two MV feeders. Install statistical metering on the transformers and MV feeders. Install new modules in AC/DC panel. Install new lead acid battery bank in existing battery room.

4

1.3 Normative and Informative references:

Parties using this specification shall apply the most recent edition of the documents listed below:

! Occupational Health and Safety Act 85 of 1993 and Regulations

! 32-136: Construction Safety, Health and Environment Management

! 34-333: OHS Act Requirements to be met by Principal Contractors Employed by Eskom Distribution.

! ESKPVAEY6: Operating Regulations for High Voltage Systems

! 32-93: Eskom Vehicle and Driver Safety Management procedure

! 32-95: Eskom Incident/ Accident management procedure

! National Environmental Management Act 107/1998

! Compensation for Occupational Injuries and Diseases Act

! Basic Conditions of Employment Act 75/1997

! Labour Relations Act 66/1995

! National Road Traffic Act 93/1996

2. DEFINITIONS AND ABBREVIATIONS (To be read in conjunction with definitions contained in OHS Act 85/1993 and Regulations)

2.1 Definitions

Client: means the Eskom 16.2 appointed person directly involved and for whom construction work is performed on the basis of a contractual agreement formally entered into with either an agent or a principal contractor (external to Eskom).

Competent Person: means any person having the knowledge, training and experience specific to the work or task being performed: provided that where appropriate qualifications and training are registered in terms of the South African Qualifications Authority Act, 1995 (act 58 of 1995), these qualifications and training shall be deemed to be the required qualifications and training.

Contractor: means an employer, as defined in section 1 of the OHSA, who performs construction work for the client either directly or through an agent and includes principal contractors and the subcontractor.

Employer: means any person who employs or provides work for any person and remunerates that person or expressly or tacitly undertakes to remunerate him/her.

Eskom requirements: Eskom requirements flowing out of directives, policies, standards, procedures, specifications, work instructions, guidelines, or manuals.

Fall arrest system: a system used to arrest an employee in a fall from an elevated working level. It consists of an anchor point, connectors, and a body harness and may include a lanyard, deceleration device, lifeline, or suitable combinations of these, BUT excludes body belts. The entire system must be capable of withstanding the tremendous impact forces involved in stopping or arresting the fall.

Fall prevention equipment: means equipment used to prevent persons from falling from an elevated position, including personal equipment, body harnesses, body belts, lanyards, lifelines or physical equipment, guardrails, screens, barricades, anchorages, or similar equipment.

Fall protection plan: means a documented plan of all risks relating to working from an elevated position, considering the nature of work undertaken and setting out the procedures and methods to be applied in order to eliminate the risk.

Method statement or safe working procedure means a written document detailing the key activities to be performed in order to reduce the hazards identified in any risk assessment.

5

On site/site: any workplace where the contractor or his/her employees perform contract-related work.

Pre-job brief meetings: a meeting that is held prior to the commencement of the day’s work with all relevant personnel associated with the work task in attendance. The job, relevant procedures, associated hazards, and safety measures, that is, the task risk assessments, shall be discussed. Each employee who attends the briefing shall sign an attendance register. The toolbox topics will be based on SHE issues pertaining to the construction site.The topic contents shall be in writing.

Principal contractor (PC): means an employer, as defined in section 1 of the Act, who performs construction work and is appointed by the client or the client’s agent to be in overall control and management of a part of, or the whole of, a construction site.

Project manager: means the person who has the responsibility for the successful planning and execution of a project. The project manager must satisfy the certification requirements set by the South African Council for the Project and Construction Management Professions.

Risk assessment: means a programme to determine any hazard at a construction site and to identify the steps needed to remove, reduce, or control such hazard.

Safety, health, and environmental (SHE) specification: means a documented specification of significant residual SHE requirements for a construction site, which a competent and resourced principal contractor or subcontractor would not have been aware of. This is to ensure the health and safety of persons, both workers and the public, and duty of care for the environment. The client/agent compiles the SHE specification, which shall be specific to each construction project.

Safety, health, and environmental file: means a permanent record, containing the information on the SHE management system during construction and all information relating to the post-construction phase after the handover to client, so that the client can maintain the works in a healthy and safe way.

Safety, health, and environmental plan: means a written plan that addresses hazards identified during a risk assessment as well as the identified impacts in the SHE specification. This would include safe work procedures to mitigate, reduce, or control the hazards identified. It is specific to each construction project undertaken, is compiled by a principal contractor or subcontractor, and must be approved by the client or agent. Both the principal contractor and the client (or agent where applicable) shall be signatories to the SHE plan once acceptable.

Subcontractor: means a contractor who is employed by a principal contractor and has no direct formal agreement of employment with the client/agent.

2.2 Abbreviations

AIA: approved inspection authority CE: Chief Executive COID Act: Compensation for Occupational Injuries and Diseases Act CR: Construction Regulations DMR: Driven Machinery Regulations EAP: Employee Assistance Programme EDC: Eskom Documentation Centre EMR: Electrical Machinery Regulations EMP: Environmental Management Plan EIA: Environmental Impact Assessment GAR: General Administrative Regulations GMR: General Machinery Regulations GSR: General Safety Regulations HCS: Hazardous Chemical Substances ICAS: International Counselling and Advisory Services MD: Managing Director

6

MSDS: Material Safety Data Sheet PPE: Personal Protective Equipment ROD: Record of Decision SHE: Safety, Health and Environment OHS Act: Occupational Health and Safety Act 85/1993 ORHVS: Operating Regulations for High-voltage Systems SANS: South African National Standards PER: Pressure Equipment Regulations

3. Documentation Required – Tender Submittal

The following documentation must be provided with the tender submittal in order to assist with the evaluation in terms of SHE performance, which in turn will assist with the selection of contractors. Should the requested information not be provided then it would be assumed that it does not exist.

! Letter of good standing for workmen’s compensation from insurance body (e.g. WCC).

! An organogram stipulating the positions of all the persons proposed by the Contractor who would hold legal appointments on the project in terms of the prescribed legislation. (SHE Rep, First Aider & Construction Supervisor etc.)

! The expected roles and responsibilities of those who are proposed to receive legal appointments.

! Based on the SHE Specifications / requirements reflected within this document including the intended scope of work, submit a SHE Plan in terms of regulation 5(4) of the Construction Regulations, 2003. (OHS Act, 1993)

! Provide an overview of your risk assessment process (methodology i.e. how, when, who, what, where, why) as well as examples of completed assessments (baseline risk assessments and issue based risk assessments).

! Competency and training records (SHE Rep, First Aider, Risk Assessor, Supervisor)

! Safety Stats for the past two years

The above information to be compiled as per Tender Evaluation Questionnaire – Annex 1- attached. Information must be contained in a folder with a contents page and dividers between various documents. The same numbering system as is reflected within this document, to be adopted. The folder must then be submitted as an annexure to the tender document.

7

4. Administrative Requirements

4.1. Notification of Construction Work The Contractor must notify the Provincial Director (D.O.L) in writing prior to construction work commencing as per CR 3. Copy of the notification and proof thereof to be kept in site safety file

4.2. Appointment of Contractor – CR 4(1) (c) Copy of above appointment by client to be kept in site safety file. Appointment shall only be done after Client has satisfied him / herself that the potential contractor has the necessary competencies required to do the work as per Tender Evaluation Questionnaire.

4.3. Compensation for Occupational Injuries and Diseases The contractor must submit proof of registration (Letter of Goodstanding) with the compensation fund or with a licensed compensation insurer for his/her company and each of his/her subcontractors. This must remain valid for the duration of the contract. The Letter of Goodstanding must reflect the name of the contractor and/or subcontractor company.

4.4. Cost of Health and Safety All contractors tendering to do work on this project must ensure that they have made provision for the Cost of Health and Safety so as to comply with this specification, OHSA 85/1993 and Regulations. Items to be considered: Training; PPE; Site laydown incl. fencing, access control, Signage; Medical surveillance; Welfare facilities; demarcation etc. The above is extracts of items that should be considered but is not exhaustive.

4.5. Mandatory Agreement In terms of section 37(2) of the OHS Act, it shall be required of every contractor to sign such an agreement with Eskom. Where a contractor appoints a sub-contractor the same shall apply. Where a Contractor appoints a sub-contractor the sub- contractor must also be on the Eskom database.

4.6. Organisational Structure The contractor’s organisational SHE structure shall be provided in the form of an Organogram. The organogram shall reflect intended appointments in cases where such appointments have not been made yet. Organogram to be updated when changes in SHE structure and dated accordingly.

4.7. Competency All persons deemed competent should have the necessary training, experience and qualifications specific to the task being performed. Proof of competency to be attached to relevant appointments.

4.8. Appointments The contractor, as defined in the contract, shall ensure that all site-related appointments are in place prior to work commencing and that it is specific and indicate for which areas within the OHS Act individuals are responsible.

The contractor shall ensure that all his/her appointees are made aware of their accountabilities and responsibilities in terms of their appointment and that he/she advises and assists these appointees in the execution of their duties.

Copies of any appointments made by the contractor shall be included in the health and safety plan and be provided to the client. Appointments to be accompanied by relevant training / competency. Typical examples of statutory appointments: see Annexure 2 attached

8

4.9. Training and Competence

The aim of this section is to outline Eskom’s expectations in respect of the scope of the training that the contractor and subcontractor employees receive. The scope of the training includes, but is not limited to, the type of work being performed and the relevant procedures. Additional to the requirements will be that the contractors and subcontractors will have the appropriate qualifications, certificates, and tickets and will be under competent supervision. Records of all training and qualifications of all contractor employees must be kept. The contractor shall for the duration of the contract, maintain comprehensive records of all employees under his/her control (including all employees of the subcontractor) attending induction training. Acknowledgement of receiving and understanding the induction must be signed by all persons receiving the induction. All training needs shall be identified and considered in SHE plan. See training needs attached – Annex 4

When there is an amendment to the Acts and/or to the regulations, SHE specification, and SHE plan, all affected staff shall undergo the relevant retraining as soon as reasonably practicable

General construction site induction carried out by the contractor - Induction

The contractor shall ensure that all his/her employees and subcontractor employees undergo general work induction with regard to the approved SHE plan, general hazards prevalent on the construction site, construction risk assessment, rules and regulations, and other related aspects prior to commencing work on site. Proof of such training will be kept in site safety file. The induction should also include identification of sensitive features such as wetlands/vlei areas, red data species, graves, etc.

Job-specific induction carried out by the contractor/subcontractor supervisor on the site - Daily Safety Task Analysis

The contractor is required to ensure, before an employee commences work on the project, that the supervisor in control with responsibility for the employee has informed the employee of his/her scope of authority, any hazards associated with the work to be performed, as well as the control measures to be taken. This will include man-task specifications and the discussion of any standard task procedures or hazardous operational procedures to be performed by the employee. The contractor is to ensure that the supervisor has satisfied himself/herself that the employee understands the hazards associated with any work to be performed by conducting task/job observations.

Proof of job-specific induction signed by inductor and trainee must be kept in the health & safety file.

Awareness – the Contractor shall conduct weekly on site toolbox talks, display posters and contract statistics regularly and before any hazardous work takes place. Records of attendance must be kept in the health and safety file. Safe Work Procedures shall be discussed with workers and signed attendance registers kept of communication thereof.

Site Visitor Induction Training Visitors to the site shall be required to undergo and comply with site-specific safety induction requirements prior to being allowed access to the site. All visitors must remain in the care and custody of a person (host) who has been properly inducted. No visitors are permitted to undertake any construction work of any nature.

4.10. SHE COMMUNICATION

Occupational Health and Safety Act - Sections 17, 18, 19, and 20

9

The contractor shall provide a communication strategy outlining how he/she intends to communicate SHE issues to his/her staff and, where appropriate, his/her subcontractors and their staff, the mediums he/she will employ, and how he/she will measure the effectiveness of his/her SHE communication. The contractor shall ensure that safety representatives are trained and appointed and SHE committee formed and shall perform all statutory functions. Monthly SHE Meetings shall be held on site and records of these meetings shall be kept in site safety file as well as signed attendance registers of such meetings. Matters to be discussed shall include, but are not limited to the following:

! Accident/safety incidents

! Accident investigations (including near misses) and close-out of recommendations

! Audit findings and close-out

! Hazardous materials/substances

! Work procedures

! Protective clothing/equipment

! Housekeeping

! Work permits

! Non-conformances

! Emergency preparedness

! Medicals

! Training

! Forthcoming high risk activities

! General SHE issues

! Matters arising from contractors’ SHE meetings

4.11. Access Control To The Construction Site

The contractor in collaboration with the Client’ Representative and Protective Services will ensure that proper access control is in place and functional at all times for all persons working on site. All contractor employees shall be identifiable as Eskom contractor employees and be issued with contractor identification cards. Contractor identification cards shall be carried on person at all times. Emergency contact numbers to be on back of access cards for workers and visitors. All visitors to site shall sign in on Visitor Access Control Register. Where there is construction vehicles and mobile plant on site then the contractor shall draft a site traffic plan, communicate this to all and demarcate such traffic routes. This plan shall be reviewed at the monthly safety meeting to ensure its applicability. All security requirements shall be highlighted at the general construction site induction. All contractors shall adhere to site security requirements

4.12. Incident Management

The contractor shall have an incident reporting system that is compatible and complies with Eskom’s Incident Management Procedure: 32-95, Section 24 of OHS Act 85/1993, GAR 8 & 9 and all other applicable legislation. Any incident or near miss involving the clients, contractors, or third-party’s personnel, property, plant, or equipment shall be reported as soon as reasonably practicable, but not later than 24 hours, to the client representative, irrespective of whether injury to personnel or damage to property or equipment resulted. Notification to be done as per Annexure 5 – Flash Report. The contractor shall investigate the causes of all incidents and shall within seven working days, provide the client with the results of the investigation and recommendations on how to prevent a recurrence. The client reserves the right to designate a representative to participate in the investigation at the client sole discretion. The principal contractor shall keep on site/at the workplace a record of all accidents and incidents reported as per Annexure 1 – Recording and Investigating of Incidents - of General Administrative Regulations (GAR 9).

10

The principal contractor shall provide SHE-related statistics to the client at the end of each month. Eskom reserves the right to conduct an independent investigation in any incident.

4.13. Hazard Identification and Risk Management, Safe Work Procedures, Fall Protection

The contractor shall cause hazards and potentially hazardous work operations to be identified by a competent person appointed in writing before commencement of construction work. The intent being to: (a) Highlight construction site SHE risks and hazards, (b) Ensuring that the site hazards and activity risks and the mitigating measure has been considered in Contractors risk assessments, (c) Method statements or written Safe Work Procedures are drafted for all the contractor activities and (d) Emerging risks and hazards are managed during construction work. For each work operation identified, the contractor shall supply a risk assessment, which shall:

! describe the operation to be performed in the sequence of the basic job steps;

! identify and rank the hazard or potential hazard;

! describe how the hazard will be managed; and

! identify the responsible person for each mitigation action.

The contractors risk assessments shall be reviewed on a monthly basis, when designing new job or task, change in job or task or introduction of new equipment and updated accordingly. Updated risk assessments shall be communicated with all employees and proof of such communication kept in the site safety file. The site and project specific hazards are attached in Annexure 3 in this SHE specification in order to make potential Contractors aware of the hazards. The list is by no means exhaustive and should not be limited to these activities, but must cover all activities that form part of the said construction work. A Fall Protection Plan shall be drafted by a competent Fall Protection Plan Developer. Appointment and Proof of competency of Fall Protection Plan Developer shall be kept in site safety file. Fall Protection Plan shall consider all fall hazards from elevated position (falls from, on and into). The Fall Protection Plan shall include: (1) Risk assessment of all work performed from elevated position including procedures and methods used to address risks, (2) Process for evaluating employees physical and psychological fitness to work in elevated positions and records, (3) Programme for maintaining, testing of Fall protection equipment. Fall protection Plan shall be updated on a monthly basis and proof kept in site safety file. Fall Protection Plan shall be drafted in accordance with CR 8. Contingency Plan in the event of a fall from elevated position shall also be considered.

4.14. Occupational Health, Hygiene, Rehabilitation and Welfare

The aim of this section is to stipulate Eskom’s requirements with regard to occupational health and hygiene practices and welfare facilities expected from the contractors and their subcontractors.

4.14.1. Workers’ Compensation The contractor must submit proof of registration and a letter of good standing with the compensation fund or with a licensed compensation insurer for his/her company and each of his/her subcontractors. This must remain valid for the duration of the contract. The letter of good standing must reflect the name of the contractor and/or subcontractor company.

4.14.2. Protection from adverse weather conditions Hot and humid conditions Contractors shall take into consideration and mitigate dehydration and exhaustion of employees. Wet, Windy and cold conditions Contractors shall take into consideration and mitigate inclement and extreme weather conditions.

11

4.14.3. Medical surveillance programme Contractors shall submit details of their employee health and wellness programme as part of their health and safety plan The contractor must ensure that his/her employees and subcontractor employees shall be registered on a medical surveillance programme and shall be in possession of a valid medical health certificate. A certificate of fitness is also required that is relevant to the type of work (risk-based) that the employee will be carrying out.

4.15. Emergency Procedures The contractor shall draft emergency procedures for the site and ensure that such emergency procedures are communicated to all. Proof of communication to be kept in site safety file. A list of emergency numbers must be posted at phones and in every office. The contractor must ensure that his/her employees, visitors and subcontractor employees are familiar with the emergency procedures and numbers. Emergency contact numbers shall be provided to all employees, sub contractor employees and visitors to site. The emergency contact numbers shall be provided on back of site access cards.

Eskom has established a contract with Euro Assistance for all employees and its contractor employees for emergency medical assistance needed while on duty anywhere in South Africa. The telephone number is 0861 2ESKOM or 0861 237566.

4.16. Welfare Facilities and First aid4.16.1 First aid Contractor shall outline first aid arrangements in SHE Plan. Contractors shall have a first-aid box on site at all times and ensure that a certified first aider is on site at all times. Contractors shall have one first-aid box for the first five persons and, thereafter, one for every 50 or team of workers on site or part thereof. More first-aid boxes shall be provided if the risks, distance between work teams, or workplace requirements require it (it should be available and accessible for the treatment of injured persons at that workplace). Minimum contents of a first-aid box (GSR 3): Item 1: wound cleaner/antiseptic (100 ml) Item 2: swabs for cleaning wounds Item 3: cotton wool for padding (100 g) Item 4: sterile gauze (minimum quantity 10)Item 5: one pair of forceps (for splinters) Item 6: one pair of scissors (minimum size 100 mm) Item 7: one set of safety pins Item 8: four triangular bandages Item 9: four roller bandages (75 mm x 5 m)Item 10: four roller bandages (100 mm x 5 m)Item 11: one roll of elastic adhesive (25 mm x 3 m)

Item 12: one non-allergenic adhesive strip (25 mm x 3 m) Item 13: one packet of adhesive dressing strips (minimum quantity 10 assorted sizes) Item 14: four first-aid dressings (75 mm x 100 mm) Item 15: four first-aid dressings (150 mm x 200 mm) Item 16: two straight splints Item 17: two pairs large and two pairs medium disposable latex gloves Item 18: two CPR mouth pieces or similar devices

A prominent notice or sign shall be displayed at the work place in a conspicuous place, indicating where the first-aid box or boxes are kept as well as the name and contact details of the first-aider. The contractor and subcontractor shall ensure that alternative arrangements shall be made for possible incidents occurring after normal working hours. A first aid register shall be kept in the first aid box and contents of first aid box inspected on a monthly basis

4.16.2 Welfare facilities – CR 28 The following welfare facilities shall be provided in a clean and suitable condition, unless an agreement is reached with the client representative regarding the use of existing facilities:

12

Sanitary facilities for male and female staff – 1 for every 15 Sheltered Changing facilities for male and female Sheltered Eating areas Potable Drinking water at strategic locations on site

4.17 Signage The contractor(s) shall use all symbolic safety signage that conforms to the requirements of SANS and/or applicable legislative requirements. The display of the following signs is mandatory: For contractors with site establishment: the contractor company sign must be posted at their site offices to reflect the name and contact details of the construction supervisor, first-aider, health and safety representative. Site office location, Visitors to report to site office, location of every first-aid box, fire extinguisher, and emergency exit and assembly points to be clearly indicated by means of a sign. When in use, an explosive-powered tool shall have a sign warning people of its use. The contractors shall provide signage where work is conducted and where unauthorised entry is prohibited and/or where alerting and cautioning passers-by to be aware of potential dangers.

4.18 Personal Protective Equipment (PPE) In terms of Section 8 of the OHS Act, the duty of the employer is to take steps to eliminate or mitigate (hierarchy of control measures) any hazard or potential hazard to the safety or health of employees before resorting to PPE. PPE matrix shall be drawn up and reviewed as required. Training regarding issue, use, maintenance and care of PPE shall be provided to all workers and signed attendance registers of such interventions kept in site safety file. Relevant notices and signs shall be displayed where required. Detailed PPE program shall be outlined in Safety Plan. Refer to General Safety Regulation 2 of the OHS Act. Strict non-compliance measures must be administered for any employee not complying with the use of PPE.

4.19 SHE Plan

The SHE plan is a detailed document comprising of specific plans and programmes for implementing the health, safety, and environmental requirements of the contract i.e. Site Safety Management System and shall be supported by relevant documentation. SHE Plan will be drafted by Contractor after receiving Clients specification for the project. The SHE plan shall meet requirements of OHS Act 85/1993 and Regulations, other Legislative Requirements and be aligned to Client Site Specification. SHE Plan must then be submitted by Contractor to Client for Client approval, 10 days before implementation on site. SHE Plan must be reviewed so as to determine applicability.

Following find a guide for contents of SHE Plan. This list is not exhaustive and other items might be added or some might be omitted due to scope of work. Each Safety Plan must be site specific.

! Introduction, Purpose, Scope, Contact details

! Organisational Structure (Organogram) and Appointments

! Exemptions and / or Notifications (D.O.L)

! SHE Policy ( Policy statement)

! Compensation Insurance

! HIRA Process, Fall Protection Plan, Safe Work Procedures

! PPE (Issue, management and control)

! Inspection Registers (Type, Frequency, Non compliance / deviation management)

! Training and Awareness (Types, Proof of training, Frequency, Non-compliance management etc)

! Site lay down area

! First aid and Welfare ( Requirements, Management etc)

13

! Emergency and Evacuation procedure (Management,Notification, Implementation, Drills, Responsibilities, Communication etc)

! Incident Management Process ( Incident types, Management of incident types – Reporting, Recording, Investigation, Analysis,Communication and Non-compliance management)

! Medical Surveillance Plan

! HCS (Types, Management, communication etc)

! Site statistics (Data collection, Analysis, Client feedback etc)

! Inspections and Audits ( Work area, Plant and Machinery, Contractors etc)

! Site and Statutory Meetings (Frequency, Agenda etc)

! Contractor Management ( Contractor assessment, Compliance management, SHE Plans etc)

! SHE Plan Review

4.20 Legal Compliance Contractors on the project site shall comply, as a minimum, with all relevant legislation, South African National Standards, or international standards and with the client’s policies and procedures, which include, but are not limited to the following:

The Constitution of the Republic of South Africa (particularly section 24 of the Bill of Rights) Occupational Health and Safety Act 1993 (Act 85 of 1993) and its Regulations National Environmental Management Act 1998 (Act 107 of 1998) Environment Conservation Act 1989 (Act 73 of 1989) National Water Act 1998 (Act 36 of 1998) Conservation of Agricultural Resources Act 1983 (Act 43 of 1983) COID Act Any other applicable South African legislation Applicable South African National Standards (SANS) Applicable international standards Operating Regulations for High-voltage Systems Plant Safety Regulations (Low-voltage Regulations) Construction SHE Management Procedures Work-at-height Procedures Incident Management Procedures Eskom SHE Policy Eskom Cardinal Rules

It is the duty of the contractor(s) and their subcontractor(s) to ensure that they are familiar with all the necessary SHE legislation required for implementation on this project.

Eskom has implemented five rules that apply to all Eskom employees and contractors. These are as follows:

Rule 1 – Open, isolate, test, earth, bond, and/or insulate before touch Rule 2 – Hook up at heights Rule 3 – Buckle up Rule 4 – Be sober Rule 5 – Ensure that you have a permit to work

These Cardinal Rules are non-negotiable health and safety rules that must not be broken under any circumstances. Eskom takes a ZERO TOLERANCE stance to violation of these rules. Cardinal Rules to be communicated as part of Site Induction to all workers and visitors to site.

The contractor shall compile a legal register listing all applicable legislation and standards that may have an impact on the scope of work that he/she is performing on this project. The register shall be updated on a regular basis.

The client is entitled to stop work and issue non-conformance reports whenever health, safety, or environmental violations are observed for both contractors and/or their

14

subcontractors. Any costs incurred as a result of such work stoppage and standing time shall be for the contractor’s account. Any non-conformances/findings/observations found during audits/inspections on subcontractors shall be raised, discussed, and resolved with the relevant contractor (with whom the subcontractor is contracted).

4.21 Overtime Work (before and after hours)

Any work that is to be performed outside of normal working hours shall be regarded as overtime work. The contractor shall ensure that adequate provision is made for over time work in regards to first aider availability, emergency preparedness etc. The contractor shall also ensure that where a sub contractor is working overtime a responsible contractor supervisor is on site. Where required provision must be made for adequate artificial lighting so as to allow work to be carried out safely at all times.

4.22 Monthly/Weekly Statistical Reports Contractors shall report all incidents to Eskom as per the Eskom Incident Management Procedure and shall include the following as a minimum:

! Incidents: lost time, medical, first aid, near misses reported

! Manpower numbers per principal contractor and subcontractor company

! Actual man-hours worked

! Status on incidents investigated and recommendations closed out

! Status on audits conducted and findings closed out

4.23 Transport for Workers

The Principal Contractor shall refer and comply with the requirements of the National Road Transport Regulations, 2000 as well as CR 21(2). The Principal Contractor shall ensure no persons are transported at the back of LDV’S / bakkies unless the vehicle: Is provided with a canopy with proper seating and safety belts; Is driven on site at a low speed of less than 40km/h and proper seating and handrails have been provided; And:An assessment has been carried out indicating a very low risk; Mitigating factors have been identified to control the risk; It has been discussed and agreed upon at a health and safety committee meeting; All vehicles are provided with a serviced portable fire extinguisher and a vehicle first aid kit at all times.

4.24 Monitoring and Evaluation

Inspections - The Principal Contractor shall carry out inspections as prescribed by legislation, the site SHE plan and Client SHE specification. The Principal Contractor shall keep records of all inspections.

Internal Audits – the Principal Contractor shall conduct regular SHE audits at least once a month to ensure compliance to OHSA and SHE specification. Records of audits shall be kept on site and non-conformances reported.

Eskom reserves the right to conduct unannounced audits on contractors

Non-compliance and Penalties Eskom will view the following at-risk behaviour in a very serious light: Disregarding any requirements contained in OHSA, this document, site specific health and safety requirements and plan. Performing an unsafe act or creating an unsafe condition that could pose a danger to themselves or to others. A Principal Contractor allowing any of their employees or sub-contractors employees (including casual labourers, or labour broker employees) to work on any site without ensuring that each employee has received proper training. If any of the above are noted, it may result in cancellation of the contract

15

4.25 Omissions from this SHE Specification By drawing up this SHE specification, Eskom has endeavoured to address the most critical aspects relating to SHE issues in order to assist the contractor in adequately providing for the health and safety of employees on site.

Should Eskom not have addressed all SHE aspects pertaining to the work that is tendered for, the contractor needs to include them in the SHE plan and inform Eskom of such issues when submitting the tender.

4.26 SHE File The contractor must have a SHE file in which records of this specification, SHE plan and supporting documents are kept.

All information required in the specification and plan, for the duration of the contract of the principal contractor and subcontractors, is to be recorded in the file.

The SHE file shall be maintained by the contractor(s) at the construction site. Consolidated SHE file shall be handed to Client at end of project – CR 5(8).

5. Construction Requirements

5.1 Excavations and Trenches Requirements in Construction Regulation 11 of the OHS Act, shall apply.

All excavations must be on register and inspected daily before work commences and after inclement weather by the contractor’s appointed competent person, declared safe and his findings noted in the said register. Client shall review the said register on a pre-determined frequency not exceeding seven (7) days. Any ground operations which may include digging, excavation, or driving a peg, pile or spike into the ground by the Contractor and their sub-contractors may not commence without the written authorisation from the Engineer. Prior to excavation underground services to be identified by appropriate service providers. Contractor to ensure workers made aware of location of underground services and records of such communication kept in site safety file. All excavations done by the Contractor are to be clearly demarcated and barricaded to prevent accidental access. Only solid barricading will be used at areas where a fall hazard is present. Solid barricading and / or hole covers shall be provided around all holes or openings to prevent any person being injured as a result of a fall. Barricade to be at least 1m high. Danger tape may only be used as a pre-warning to make the solid barricading more visible and to prevent persons from coming close to the danger area. Where excavations are to be left open overnight in public areas adequate warning measures are to be implemented, visibility ensured and signage shall be displayed.

Danger tape has to be used in conjunction with proper barricading methods.

5.2 Working in elevated positions / at heights:

Working at height is a high-risk activity, and as such, all precautions including but not limited to Eskom and legislative requirements must be taken to prevent incidents while working at height.

Persons may only work from a fall risk position if:

! a working at heights risk assessment has been completed for the work to be conducted;

! a safe work procedure/task analysis and work instruction, approved by a competent person, are in place;

! a fall rescue plan, along with necessary equipment and trained rescuers, is in place;

! appropriate training, as determined by the risk assessment, has been provided; and

16

! Appropriate height safety equipment and personal protective equipment have been issued to the individual.

Where work in an elevated position is necessary, preference shall be given to fall prevention measures such as, but not limited to, effective barricading and the use of work platforms.

5.3 Plant, Machinery and equipment

The Principal Contractor shall comply with the requirements of the Driven Machinery Regulations and General machinery regulations promulgated under the OHSA 85/1993. The regulations include inspecting machinery regularly, designating a competent person to inspect and ensure maintenance, issuing PPE or clothing and training those that use machinery and enforce compliance. Contractor shall ensure that Schedule D of General Machinery Regulations is communicated to operators, Proof of communication kept in site safety file and displayed.

All employees shall: (1) Be competent when operating or using machines and tools, (2) Be in possession of valid medical (issued by Occupational Health Practitioner) and training certificate (issued by approved training institution), (3) Have proof of any form of task related training.

5.3.1 Construction vehicles and mobile plant

All construction vehicles and mobile plant shall comply with the Road Traffic Ordinance and Road Traffic Act, CR 21, GMR ,DMR as well as Eskom requirements. Designated drivers shall be in possession of a national driver’s licence, valid for the class of vehicle. The driver’s licence shall be kept by the person so authorised, and he/she shall produce such card on request. All drivers of construction vehicles and mobile plant shall have valid medical certificates of fitness to determine physical and psychological fitness. Each project site shall have a system/process to manage vehicle access to the site. Vehicle management process shall be included in SHE Plan. Operators and drivers shall comply to site speed limit of 30 km p/h. Site speed limit shall be communicated to all operators and drivers on site. Operators and drivers shall not talk on cell phone or radio while driving / operating. Contractor shall ensure that drivers and operators comply with following:

! All passengers wear seat belts while the vehicle is in motion;

! Operators / drivers complies with all safety, direction, and speed signs;

! Loads are properly secured and loaded onto vehicles; and

! Vehicles / Plant not overloaded. Daily inspections done on construction Vehicles and Mobile Plant and records kept in site safety file. Contractors shall ensure that adequate measures are put in place when refuelling, servicing and repairing on site and that such measure are communicated to operators.

5.3.2 Lifting machine and tackle A risk assessment shall be conducted prior to commencing with the task to identify the risk involved and appropriate mitigation measures must be put in place. If it is the Principal Contractor’s intention is to use lifting machines on site, it should be indicated in the Principal Contractor’s SHE plan as well as the inspection so that the Eskom Project/Site Manager can conduct an inspection when equipment is brought onto site. If his/her intention is to use a sub-contractor he must enter the name of the sub-contractor into the notification letter to the Department of Labour. All lifting machine operators shall be competent to operate a lifting machine. They must be in possession of a valid training certificate and medical certificate. When ever making use of an external contractor to do lifting work the Principal Contractor must ensure that the operator is competent and if the Principal Contractor is satisfied with the operator's competency after looking at his portfolio he/she should issue a temporary permit to the operator. The Principal Contractor should verify if the lifting machines and tackle have been examined and a performance test done by registered Lifting Machine Inspector. Proof of performance test and last inspection to be on site at all times. Performance tests shall be done at intervals

17

not exceeding 12 months, Lifting machines shall be inspected every 6 months and Lifting tackle every 3 months. No work to commence without valid Performance test certificate. Operator training shall be done according to relevant Code of practice by a provider registered with the Department of Labour. Before using any lifting machines or tackle the operator should inspect it. Refer to the requirements of the Driven Machinery Regulation 18 and Construction Regulation 20 of the OHS Act.

5.3.3 Portable electrical tools

The Principal Contractor shall ensure that portable electrical tools: Are inspected regularly by a competent person Are on register Are maintained in good working order

5.4 High Voltage Electrical Equipment

Where work is carried under, on or near high voltage equipment, work is performed by a person authorised to do so in terms of the Client’s ORHVS or under supervision of a responsible person in possession of a working permit.

5.5 Housekeeping

The contractor and subcontractor shall maintain a high standard of housekeeping within the site. Prompt disposal of waste materials, scrap, and rubbish is essential. Adequate care must be taken by the contractor to ensure that storage and stacking are correctly and safely carried out. Before stacking any material, the contractor, subcontractor, or their employees must consult the Eskom project/site manager for allocation of a stacking area. Materials/objects shall not be left unsecured in elevated areas; falling objects may cause serious injuries/fatalities. Nails protruding through timber shall be bent over or removed so as not to cause injury. All packaging material, including boxes, pallets, crates, etc. to be removed from the work area immediately. Eating facilities shall be kept in a clean and tidy manner. On completion of his/her work, the contractor is responsible for clearing his/her work area of all materials, scrap, temporary buildings, and building bases to the satisfaction of the client. In cases where an inadequate standard of housekeeping has developed, compromising safety and cleanliness, everyone has the responsibility to bring it to the attention of the Eskom project/site manager. The Eskom project/site manager has the right to instruct the contractor and his/her subcontractor to cease work until the area has been tidied up and made safe. Neither additional costs nor extension of time to the contract shall be allowed as a result of such a stoppage. Failure to comply will result in site cleaning by another cleaning contractor company at the cost of the contractor. The contractor shall carry out regular safety/housekeeping inspections (at least weekly) to ensure maintenance of satisfactory standards.

5.6 Stacking & Storage

Contractor shall ensure compliance to CR 26

5.7 Hand tools

Contractor shall ensure that hand tools are : Inspected monthly on a register Maintained in a good condition Properly stored Contrators shall ensure that awareness training re hand tools are provided to workers and proof of such training kept on record.

18

5.8 Fire Precautions

Contractor shall ensure: Fire Risk assessment done Suitable fire extinguishers available and accessible Fire extinguishers inspected monthly by a person designated thereto Fire extinguishers inspected by a competent person on a yearly basis Smoking and open flames prohibited where deemed fire risk and signage displayed to indicate Combustible materials regularly removed from site Hot work done after necessary pre-cautions taken Workers trained in use of fire extinguishers Escape routes clearly indicated Siren sounded in the event of a fire Compliance to CR 27

5.9 Scaffolding

Contractor shall ensure: Compliance to CR 14 and SANS 10085:2004. A competent scaffold supervisor shall be appointed in writing. Ensure that inspections are carried out weekly, after inclement weather, after erection and before dismantling. Adequate and relevant signage displayed. Scaffold materials used for erection are inspected prior to use so as to ensure it is constructed of sound material. All scaffold erectors, team leaders, inspectors are in possession of valid training certificate and medical certificate of fitness. Safe Work Procedures for Erection and Dismantling of scaffold is drafted and communicated to all workers and proof thereof kept in site safety file. Scaffold material is stored in such a manner so as to prevent obstruction of walkways and work areas. Fall protection equipment worn at all times. Adequate measures taken to prevent tools and material from falling from scaffold. Signage placed re overhead work

5.10 Ladders

Contractor shall ensure that ladders are: Inspected monthly, Proof of such inspection kept in site safety file, correct ladder used for type of work to be performed, Workers trained on use of ladders and training records kept in site safety file, Constructed of sound material, Fitted with non-skid devices, Secured against displacement. Prevent tools from falling from ladders. Ladders are stored out of walkways.Contractor shall ensure that all requirements of GSR 13 A are met.

5.12 Form and Support work

A competent person shall be appointed in writing to supervise all form and support work. Design drawings (updated) shall be available on site at all times. All form and support work shall be inspected on a daily basis until removal thereof and records shall be kept in the site safety file. All equipment and material used shall be inspected prior to use by a competent person and defective material shall be removed. All employees (Form and support work erectors) shall be trained re type of formwork and support work being used and have valid medical certificates of fitness. Compliance to provisions of CR 10 to be ensured.

5.13 Explosive Power Tools

Contractor shall ensure competent person appointed in writing to clean and inspect. Issue and return of cartridges to be controlled by person appointed in writing. Signage displayed wherever such tools are used. Operator trained re use and maintenance of tool and issued with appropriate PPE. Compliance to CR 19 to be ensured.

19

Annex 1 – Tender Evaluation Questionnaire

DetailsContact Person: _____________________________________________________________________________________________

Telephone: _____________________________________________________ Cell phone: _____________________________________________________ Fax no.: _______________________________________________________ E-mail: ________________________________________________________ Contract duration: _______________________________________________ Commencing date: _______________________________________________ Completion date: ________________________________________________ Expected number of employees on site: ______________________________

1. Is company registered with Compensation Commissioner? Provide CC Fund number. If yes, attach proof. _____________________________________________________________________________________________

2. Does company have an Organogram? If yes, attach proof. _____________________________________________________________________________________________

3. Has a Person charged with the responsibilities of the Act been appointed? (Reference Section 16.1 OHS Act) If yes, attach proof. ______________________________________________________________

4. Does the company have a written SHE (Safety, Health and Environmental) Policy in place? If yes, attach proof. Reference Section 7 - OHSA 85/1993 ______________________________________________________________

5. Does the company have a SHE Management System in place? If yes, provide details. (How do you manage H&S at work?) ______________________________________________________________

6. Does the company provide training for workers and appointees? If yes state training in relation to appointee / workers using below format. Attach proof of Competency

Appointee / Workers Training

e.g. First Aider First Aid Training

7. Does the company have a SHE Plan? If yes, attach. Reference CR 5(4)

8. Provide details of Hazard Identification and Risk Assessment process with risk matrix. Attach examples of baseline risk assessment and issue based risk assessment. Reference CR 7

9. How does the company ensure legislative, contractor and client requirement compliance of sub-contractors? Provide details. Reference CR 5

10. Provide incident statistics for current year and previous two years using below format.

Year Medicals Lost Time Injuries Fatalities Lost Time Injury Rate

11. Has the company made provision for the cost of Health, Safety and Environment? Provide details. Reference CR 4(h)

Principal Contractor / Service Provider Name: _______________________________________________________________________________

_______________________________________

Scope of Work:

_______________________________________________________________________________

______________________________________________________________________________

20

Annexure 2 – Legal appointments

ITEM Legal reference Appointment

1. Sect. 16.1 CEO

2. Sect 16.2 Assistant to CEO

3. Sect. 17 Health and Safety Representative

4. Sect. 19 Health and Safety Committee Member

5. CR 4(1)(c) Principal Contractor for each phase or project

6. CR 5(3)(b) Contractor

7. CR 6(1) Construction Work Supervisor

8. CR 6(2) Construction Work Supervisor - subordinates

9. CR 6(6) Health and Safety Officer

10. CR 7(1) Risk Assessor

11. CR 8(1)(a) Fall Protection Plan Developer

12. CR 10 (a) Formwork and Support Work Supervisor

13. CR 11(1) Excavation Work Supervisor

14. CR 12(1) Demolition Work Supervisor

15. CR 14(2) Scaffold Supervisor

16. CR 15(1) Suspended Platform Supervisor

17. CR17(8)(a) Material Hoist Inspector

18. CR 18(1) Batch Plant Supervisor

19. CR 19(2)(g)(i) Explosive Power Tool Supervisor

20. CR 21(1)(j) Construction Vehicle and Mobile Plant Inspector

21. CR 22(e) Temporary Electrical Installations Controller

22. CR 26(a) Stacking and Storage Supervisor

23. CR 27(h) Fire Equipment Inspector

24. DMR18 (11) Lifting Machine Operator

25. DMR18 (5) Lifting Machine Inspector

26. DMR 18(10)(e) Lifting Tackle Inspector

27. GMR 2(1) Supervisor of Machinery

28. GMR 2(7) Supervisor of Machinery Assistant

29 GSR 3 First Aider

30. GAR 9(2) Incident/ Accident Investigator

31. Emergency Planning Co-coordinator

32. Fire official

21

Annexure 3 RISK/ HAZARDS

Activity / Task Hazard Risk

Driving Different types of road condition i.e tar , gravel, sandy etcSpeeding

Vehicle accident due to driver not observing different types of road conditions and adapting thereto Vehicle incident involving member of public

Transporting material, equipment and people on the same vehicle

Vehicle involved in accident Injury to persons due to loose material and equipment falling about Damage to material or equipment

Work areas / environment Animals (bees, dogs, ticks etc) present Adverse weather conditions ( Too hot or too cold) Loose gravel and stone leading to slips, trips and falls Rubbish , off cuts thrown around & oil leaks /spills Material theft Traffic accident involving member of public, children

Ill health due to insect / animal bites Ill health of workers

Injury to workers

Environmental pollution

Asset loss Vehicle incident

Fire prevention Uncontrolled fires Injury to workers, Damage to property

Working directly underneath or in proximity to over head power lines /

Contact with live overhead power lines Flash overs – Mobile plant and workers

Injury to workers

22

Close proximity work to live equipment

Static Electricity Induction

Injury to workers, Damage to property

Use of plant and machinery – generators, concrete vibrator etc

Exposed moving parts of machinery Use of untrained operators Operators not medically fit Spills while refuelling Use of defective PPE

Injury to workers Injury to workers, Damage to property Injury to workers, Damage to property Environmental pollution Injury to workers

Manual handling Overexertion, sprains and strains Incorrect lifting and handling procedures

Injury to workers Injury to workers

Overhead work Foreign object entering eye Overexertion, sprains, strains, awkward position

Injury to workers Injury to workers

Use of hand tools Defective hand tools Incorrect tool for the job

Injury to workers Injury to workers

Use of Portable electrical tools Defective electrical tool, Exposed cables and leads Trailing cables leading to trips and falls

Injury to workers, damage to property

Injury to workers

Working in elevated positions / at heights

Untrained workers, Falls from heights Failure to use FAS Defective / Ineffective PPE Workers unfit to perform work at heights Lack of / inadequate emergency planning

Injury to workers Injury to workers Injury to workers Injury to workers Injury to workers

23

Lifting machine and tackle Incompetent operator; Expired or lack of valid training or medical certificate Expired or lack of Load test certificate or 6 monthly inspection records of lifting machineExpired or lack of 3 monthly inspection record of lifting tackle Lack of / inadequate emergency planningFailure of lifting machine or tackle Incorrect lifting and rigging practise, Safe working load not displayed

Injury to workers, Damage to property

Stacking and Storage Incorrect procedure followed, Stacks collapsing Overexertion, Sprains and Strains Walkways obstructed Unauthorised entry, Lack of demarcation, Theft

Injury to workers, Damage to property Injury to workers

Injury to workers, Damage to property

Earthworks – Backfilling and compacting trenches

Defective / ineffective hand tools Exposed moving parts of machinery Use of defective PPE

Mechanical compacting

Bodily injury, Hand injury Bodily injury, Hand injury Bodily injury, Hand injury, Dust and noise exposureHand injury, Noise and vibration exposure

Wet trades – Brick work and Plastering

Inadequate stacking and storage

Environmental pollution due to mixing of cement / mortar Use of defective / ineffective hand tools Uncontrolled water loss

Injury to workers, damage to property / materialEnvironmental damage

Bodily injury, Hand injury Water wastage, Work area soggy and

24

Tools, material, equipment, workers falling from heights / elevated position Exposure to Hazardous chemical substance (HCS) - cement dust inhalationExposure to HCS – skin Exposure to HCS – entering eye Ineffective / incorrect PPE used Overexertion

slippery leading to slips and trips Damage to tools, material and equipment; Bodily injury to workers resulting in medical or lost time or fatality Inhalation of cement dust DermatitisEye irritation Bodily injury Sprains and Strains

Use, Erection, Dismantling of scaffolding

Scaffolds not erected / dismantled / designed as per SANS 10085 Incorrect signage displayed

Tools, material, equipment, workers falling from heights / elevated position

Incompetent, medically unfit supervisor, erectorsScaffolds not inspected on register

Lack of pre-task planning

Overexertion

Scaffold collapse, Injury to workers / Fatality, damage to property Injury to workers / Fatality, damage to propertyDamage to tools, material and equipment; Bodily injury to workers resulting in medical or lost time or fatality Injury to workers / Fatality, damage to propertyScaffold collapse, Injury to workers / Fatality, damage to property Scaffold collapse, Injury to workers / Fatality, damage to property Sprains and Strains

Concrete works Spillage of concrete, Incorrect area used to wash outIneffective / incorrect PPE used OverexertionExposure to HCS – skin Exposure to HCS – entering eye

Environmental pollution

Hand and foot injuries Sprains and Strains DermatitisEye irritation

25

Reinforcement / Steel fixing Incorrect / Ineffective PPE Hand injuries – cuts and abrasions

Use of ladders Falls of workers and tools Defective / inadequate ladder used

Injury to workers Injury to workers

Painting Exposure to hazardous chemical substanceIneffective / defective PPE Painting equipment cleaned on site OverexertionFalls from elevated position – workers / equipment

Inhalation of HCS

Exposure to HCS Environmental pollution Sprains and strains Bodily injury

Roof work Falls from heights – tools / equipment / workersFailure to use Fall prevention equipment Workers not trained / medically fit Lack of pre task planning

Bodily injury, fatality, damage to property

Bodily injury, fatality Bodily injury, fatality Bodily injury, fatality

Excavations by hand Falls into excavation - workers and members of publicExcavation walls collapsing resulting in injury to staff Existing underground services Use of defective hand tools

Bodily injury

Bodily injury

Injury to workers, Damage to property Bodily injury

Excavations using plant and machinery

Falls into excavation– workers and members of publicExcavation walls collapsing resulting in injury to staff Existing underground services Untrained and medically unfit operators Plant and workers in same excavation Plant failure due to plant and machinery

Bodily injury

Bodily injury, suffocation

Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers Injury to workers, Damage to property

26

not regularly serviced and inspected

Plumbing work Incorrect / defective tools used Incorrect / defective PPE used Use of Hazardous chemical substances

Bodily injury Bodily injury Exposure to HCS

Site establishment and de establishment

Use of lifting equipment and tackle Off loading containers Erecting temporary site offices, amenities and stores, site boundary fenceErecting / Dismantling roof sheeting Provision of potable water and ablution facilities Use of hand tools Manual Handling

Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers, Damage to property

Injury to workers, Damage to property

Ill health of workers Injury to workers Injury to workers

Electrical work Incorrect / defective tools used Incorrect / defective PPE used Work performed by person not competent / authorised to perform such work

Bodily injury Bodily injury Electrical shock, electrocution

Form and Support work Collapse of structure Defective material / equipment used Erectors not trained to perform work Inadequate inspection and supervision Premature stripping of support work Inadequate means of access and egressOverexertionWorking at heights

Injury to workers, Damage to property Injury to workers, Damage to property Injury to workers Injury to workers, Damage to property Injury to workers, Damage to property

Injury to workers, Damage to property Sprains and strains Injury to workers

27

Use of hazardous chemical substances

Incorrect PPE used First aid facilities unavailable MSDS not on site

Bodily injury Injury to workers Injury to workers

Explosive Power tools Users not trained No signage displayed No control over issue and return of cartridges

Injury to workers Injury to workers Injury to workers

Erecting steel structure Tools, material, equipment, workers falling from heights Ineffective, defective or lack of FAS Lifting equipment failure

Injury to workers

Injury to workers Injury to workers, Property damage

Fencing Overexertion, Sprains, Strains Defective portable electrical equipment usedDefective plant and machinery used Incorrect / defective PPE used Fire risk

Injury to workers

Injury to workers Injury to workers, damage to property Injury to workers Environmental damage

Hot work (Soldering, Brazing, Flame cutting etc)

Inadequate fire precautions Incorrect / ineffective PPE Exposure to hazardous fumes Burns to body Untrained person performing task Other workers in area exposed

Environmental damage, injury to workers Injury to workers Ill health of workers Injury to workers Injury to workers Injury to workers

Deliveries , Access to site Driving (gravel road) Traffic accident

Storage of fuel, diesel, petrol Spillages Fire

Environmental damage Environmental damage, Injury to workers, Damage to private property

28

Putting down yard stone Incorrect manual handling Defective, incorrect hand tools used Weather conditions

Injury to workers Injury to workers Ill health of workers

Private property Theft Unauthorised access

Injury to workers Injury to workers

Installing heavy equipment Load swinging out of control Lifting tackle failure Unbalanced load Works area beneath slew area to be kept clear Incorrect PPE worn by workers

Damage to property, Injury to workers Damage to property, Injury to workers Damage to property, Injury to workers Damage to property, Injury to workers

In jury to workers

29

Annexure 4 - Training Needs Matrix

CR

EA

TE

3 D

AY

SE

MIN

AR

CO

NS

TR

UC

TIO

N

RE

GS

OH

S A

CT

& R

EG

S

FIR

ST

AID

L

2

CO

ID A

CT

OR

HV

S

INC

IDE

NT

INV

ES

TIG

AT

IN

ES

KO

M S

AF

ET

Y

IND

UC

TIO

N

FIR

E F

IGH

TIT

ING

HIR

A/J

SA

VE

HIC

LE

AN

D

MO

BIL

E

EQ

UIP

ME

NT

OP

ER

AT

OR

H &

S R

EP

TR

AIN

ING

BA

SIC

H &

S

TR

AIN

ING

OHS Act 16 (1) MD * * * * * *

OHS Act 16 (2) PM * * * * * *

Construction Supervisor

CR 6 (1)

* * * * *

Assistant Construction

Supervisor CR 6 (2)

* * * * *

Safety Officer CR 6 (6) * * * * * * * * * *

Site Risk Assessor * * *

Fire officer * * *

H&S Rep * * * *

Scaffolding Supervisor * *

Excavation Supervisor * *

Construction vehicles and

mobile plant inspector /

operator

* *

First Aider *

Fall Prevention plan

developer

* * *

Stacking supervisor * * *

Site personnel *

30

Annexure 5 - Flash Report

ESKOM EMPLOYEE / EXTERNAL PERSON INCIDENT

INCIDENT NOTIFICATION FLASH REPORT TO BE SENT TO RISK MANAGER WITHIN 24 HOURS OF INCIDENT.

__________________________________________________________________________________ INCIDENT NUMBER: 0000000000000000#####PERSONS INVOLVED TYPE:

PERSONS NAME PERSON TYPE UNIQUE NUMBER

Note number ranges for Person Type External Person:

! Contractor 1000000001 – 2999999999

! Member of Public 3000000000 – 4999999999

! Third Party 5000000000 – 6999999999

SHORT DESCRIPTION OF ACCIDENT:

INCIDENT DETAILS:

IMMEDIATE RECOMMENDATIONS:

PERSONS INVOLVED:

Name Accident Category

Involved Role

Involved Type

Body part Injury

ACCIDENT TYPE:

REPORTED BY:

DATE:

PLANT:

WORK AREA DESCRIPTION:

ACCIDENT LOCATION:

MANAGER/ SUPERVISOR:

TELEPHONE NUMBER:

FAX NUMBER:

DATE OF INCIDENT:

TIME OF INCIDENT: