PRE FEASIBILITY REPORT
For
Proposed 700 TPD Municipal Solid Waste Management
(Waste To Energy Plant) Project
By
PUNE MUNICIPAL CORPORATION
700 TPD Municipal Waste Management Facility Project
At
Gut no. 493, Pimpri Sandas Village,
Talulka Haveli, Dist Pune, Maharashtra
Prepared By
ABC Techno Labs India Pvt. Ltd.
QCI NABET Accredited (Certificate No. NABET / EIA / 1316 / RA001)
Corporate Office:
No.2, 2nd
Street, Thangam Colony, Anna Nagar West, Chennai 600040.
Tamil Nadu, India.
Tel: 044 26161123 / 24 / 25
Mumbai Office:
A/355, Balaji Bhavan, Plot No. 42 A, Sector 11, CBD Belapur,
Navi Mumbai 400614, Maharashtra. India
Tel: 022 27580055 / 44
www.abctechnolab.com
mumbai@abctechnolab.com
http://www.abctechnolab.com/mailto:mumbai@abctechnolab.com
Pre Feasibility Report 700 TPD Municipal Waste Management Facility Project
2
ABC TECHNO LABS INDIA PVT. LTD.
Table of Content
CHAPTER 1 ...................................................................................................................................................................................... 6
EXECUTIVE SUMMARY .............................................................................................................................................................. 6
CHAPTER 2 ...................................................................................................................................................................................... 8
IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ......................................................................................... 8
2.1 IDENTIFICATION OF PROJECT: ................................................................................................................................................ 8
2.1.1 Details of the Proponent ............................................................................................................................................. 8
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT .................................................................................................................. 9
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY OR REGION ...................................................................... 10
2.4 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT ........................................................................ 11
CHAPTER 3 .................................................................................................................................................................................... 12
PROJECT DESCRIPTION ........................................................................................................................................................... 12
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY ....................................................... 12
3.2 LOCATION ........................................................................................................................................................................... 12
3.3 ENVIRONMENTAL SETTINGS .................................................................................................................................................... 16
3.4 DETAILS OF ALTERNATIVE SITE ............................................................................................................................................... 17
3.5 SIZE AND MAGNITUDE OF PROJECT .......................................................................................................................................... 17
3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS ....................................................................................................................... 17
3.7 RAW MATERIAL REQUIREMENT: .............................................................................................................................................. 19
3.8 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE PROJECT, IF ANY: ....................................................... 19
3.9 AVAILABILITY OF WATER ITS SOURCE, ENERGY/ POWER REQUIREMENT AND SOURCE ............................................................. 19
3.9.1 Water requirement .......................................................................................................................................................... 19
3.9.2 Power Requirement ........................................................................................................................................................ 19
CHAPTER 4 .................................................................................................................................................................................... 21
SITE ANALYSIS ............................................................................................................................................................................ 21
4.1 SITE CONNECTIVITY ............................................................................................................................................................ 21
4.2 LANDFORM, LAND USE AND LAND OWNERSHIP ..................................................................................................................... 23
4.3 TOPOGRAPHY .......................................................................................................................................................................... 23
4.4 EXISTING LAND USE PATTERN ................................................................................................................................................ 23
4.5 CLIMATE AND RAINFALL ........................................................................................................................................................ 23
4.6 SOCIAL INFRASTRUCTURE AVAILABLE ................................................................................................................................... 23
CHAPTER 5 .................................................................................................................................................................................... 24
PLANNING BRIEF ........................................................................................................................................................................ 24
Pre Feasibility Report 700 TPD Municipal Waste Management Facility Project
3
ABC TECHNO LABS INDIA PVT. LTD.
5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, AND TRANSPORTATION ETC.) TOWN AND COUNTRY
PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION ............................................................................................................. 24
5.2 POPULATION PROJECTION ....................................................................................................................................................... 24
5.3 LAND USE PLANNING .............................................................................................................................................................. 24
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) ..................................................................................... 24
CHAPTER 6 .................................................................................................................................................................................... 25
PROPOSED INFRASTRUCTURE ............................................................................................................................................... 25
6.1 PLANNING BRIEF ..................................................................................................................................................................... 25
6.2 GREEN BELT ........................................................................................................................................................................... 25
6.3 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO / WATER WAYS ETC.) ............................................ 25
6.4 DRINKING WATER MANAGEMENT .......................................................................................................................................... 25
6.5 SEWERAGE SYSTEM ................................................................................................................................................................ 25
6.6 INDUSTRIAL WASTE MANAGEMENT........................................................................................................................................ 25
6.7 SOLID WASTE MANAGEMENT ................................................................................................................................................. 25
6.8 POWER REQUIREMENT & SUPPLY/SOURCE ............................................................................................................................. 26
CHAPTER 7 ......................................................................................................................