  • PUBLIC WORKS AGENCY WATERSHED PROTECTION DISTRICT

    FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    (FUNDING SOURCE AND AMOUNT)

    FISCAL YEAR

    2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 Total

    Zone: 1

    WPD $ 3,251,000 $ 5,957,000 $ 180,000 $ 90,000 $ 30,000 $ 9,508,000

    Zone: 2

    WPD $ 9,148,087 $ 19,177,240 $ 13,284,029 $ 20,000 $ - $ 41,629,356

    Zone: 3

    WPD $ 2,779,100 $ 2,525,000 $ 1,307,000 $ 695,000 $ 7,000 $ 8,008,100

    Zone: 4

    WPD $ 1,359,218 $ 225,604 $ - $ - $ - $ 1,584,822

    Annual Total $ 16,537,405 $ 27,884,844 $ 14,771,029 $ 805,000 $ 37,000 $ 60,730,278

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 1 FISCAL YEAR (2016/2017)

    Project Location Estimated Costs1 Fresno Canyon Diversion Community of Casitas Springs $ 390,0002 Matilija Dam ERP - Preliminary Engineering

    Design (PED)North of the City of Ojai $ 30,000

    3 Ventura River Levee (VR-1) City of Ventura $ 2,173,0004 Ventura River Levee at Casitas Springs (VR-2)

    Preliminary DesignCommunity of Casitas Springs $ 658,000

    Grand Total: $ 3,251,000

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 1 FISCAL YEARS (2017/2018 to 2020/2021)

    Project Location Estimated Costs1 Fresno Canyon Diversion Community of Casitas Springs $ 5,915,0002 Matilija Dam ERP - Preliminary Engineering

    Design (PED)North of the City of Ojai $ 120,000

    3 Ventura River Levee (VR-1) City of Ventura $ 182,0004 Ventura River Levee at Casitas Springs (VR-2)

    Preliminary DesignCommunity of Casitas Springs $ 40,000

    Grand Total: $ 6,257,000

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Fresno Canyon Diversion Project No.: 81181

    Supervisorial District: 1 Zone: 1 Unincorporated Area: X City of: N/A

    Location: Community of Casitas Springs

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEConstruct a reinforced concrete pipe diversion from upstream of Highwy 33 to Ventura River. The purpose of this project isto provide 100-year flood protection from Fresno Canyon to the community of Casitas Springs.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 880,324 $ 215,000 $ 162,000 $ - $ - $ -

    Right of Way: $ 523,359 $ 120,000 $ 80,000 $ - $ - $ -

    Con. Eng./Insp.: $ 855 $ - $ 495,000 $ - $ 60,000 $ -

    Construction: $ 2,220 $ - $ 4,613,000 $ - $ - $ -

    *Miscellaneous: $ 1,502 $ 55,000 $ 445,000 $ 60,000 $ - $ -

    Fiscal Year Total: $ 1,408,261 $ 390,000 $ 5,795,000 $ 60,000 $ 60,000 $ -

    Total Estimated Costs: $ 7,713,261

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: 05/13/2014 Date Filed: 05/13/2014

    REMARKSAdditional annual operations and maintenance costs = $20,000. Mitigation monitoring and maintenance costs = $100,000(funded annually over five years from construction completion). FEMA will reimburse 75% of costs, up to a maximum of$3,000,000.

    Prepared By: Masood Jilani Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Matilija Dam ERP - Preliminary Engineering Design (PED) Project No.: 81915

    Supervisorial District: 1 Zone: 1 Unincorporated Area: X City of: N/A

    Location: North of the City of Ojai

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe primary project objectives are to remove the dam to provide fish passage to upstream steelhead trout habitat, andimprove sediment transport of sand to the beach.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 1,263,184 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ 30,000

    Right of Way: $ 21,599 $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ 10,751 $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ 591 $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 1,296,125 $ 30,000 $ 30,000 $ 30,000 $ 30,000 $ 30,000

    Total Estimated Costs: $ 1,446,125

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: 12/14/2004 Date Filed: 12/17/2004

    REMARKSProject schedule is based on Federal appropriations to the US Army Corps of Engineers. Local sponsor responsible for 25%of Corps $8M budget. Planned costs are for staff time to coordinate with Corps and project stakeholders due to lack ofCorps funding.

    Prepared By: Peter Sheydayi Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Ventura River Levee (VR-1) Project No.: 81020

    Supervisorial District: 1 Zone: 1 Unincorporated Area: City of: Ventura

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEComplete design of improvements required to certify the existing U.S. Army Corps of Engineers built Ventura River Levee(VR-1). The objective is to provide 100-yr level of flood protection and certify the levee.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 428,897 $ 2,166,000 $ 92,000 $ 90,000 $ - $ -

    Right of Way: $ 18,879 $ 7,000 $ - $ - $ - $ -

    Con. Eng./Insp.: $ 3,215 $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 450,991 $ 2,173,000 $ 92,000 $ 90,000 $ - $ -

    Total Estimated Costs: $ 2,805,991

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: --- Date Filed: ---

    REMARKSUSACE has rated VR-1 as "minimally acceptable" and therefore no federal funding is anticipated. 55% of current scope ofwork, including final design, CEQA, and permitting, will be funded by a Department of Water Resources 2015 LLAP grant.

    Prepared By: Salvador Diaz-Rubin Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Ventura River Levee at Casitas Springs (VR-2) Preliminary Design Project No.: 81025

    Supervisorial District: 1 Zone: 1 Unincorporated Area: X City of: N/A

    Location: Community of Casitas Springs

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEEvaluate the Casitas Spring Levee for certification and prepare a deficiency study for rehabilitation of the levee to meet 44CFR 65.10 certification criteria.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ - $ 658,000 $ 40,000 $ - $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ - $ 658,000 $ 40,000 $ - $ - $ -

    Total Estimated Costs: $ 698,000

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: X EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKS55% of current scope of work, including preliminary design and geotechnical investigations, will be funded by a Departmentof Water Resources 2015 LLAP grant.

    Prepared By: Masood Jilani Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 2 FISCAL YEAR (2016/2017)

    Project Location Estimated Costs1 Arundell Barranca Hydraulic Deficiency

    ImprovementsCity of Ventura $ 230,000

    2 Cavin Road Debris Basin Retrofits West of the Community of Piru $ 85,0003 Rice Road Drain at Terrace Avenue RCB Repair City of Oxnard $ 544,000

    4 Santa Clara River Levee D/S of Hwy 101(SCR-3)

    City of Oxnard $ 2,202,087

    5 Santa Clara River Levee U/S of Hwy 101(SCR-1)

    City of Oxnard $ 2,152,000

    6 Sespe Creek Levee - Hwy 126 to Old TelegraphRd (SC-2)

    City of Fillmore $ 3,770,000

    7 tšumaš creek - Hueneme Road to PleasantValley Road

    City of Oxnard $ 165,000

    Grand Total: $ 9,148,087

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 2 FISCAL YEARS (2017/2018 to 2020/2021)

    Project Location Estimated Costs1 Arundell Barranca Hydraulic Deficiency

    ImprovementsCity of Ventura $ 740,000

    2 Cavin Road Debris Basin Retrofits West of the Community of Piru $ 660,0003 Rice Road Drain at Terrace Avenue RCB Repair City of Oxnard $ 93,500

    4 Santa Clara River Levee D/S of Hwy 101(SCR-3)

    City of Oxnard $ 12,257,769

    5 Santa Clara River Levee U/S of Hwy 101(SCR-1)

    City of Oxnard $ 135,000

    6 Sespe Creek Levee - Hwy 126 to Old TelegraphRd (SC-2)

    City of Fillmore $ -

    7 tšumaš creek - Hueneme Road to PleasantValley Road

    City of Oxnard $ 18,595,000

    Grand Total: $ 32,481,269

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Arundell Barranca Hydraulic Deficiency Improvements Project No.: TBD

    Supervisorial District: 1 Zone: 2 Unincorporated Area: City of: Ventura

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe purpose of this project is to complete improvements to two hydraulic deficiencies downstream of Mills Road drain, 1)the unnamed road crossing downstream of Arundell Circle, and 2) the upstream bridge underneath Harbor Boulevard.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ - $ 225,000 $ - $ - $ - $ -

    Right of Way: $ - $ 5,000 $ 5,000 $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ 135,000 $ - $ - $ -

    Construction: $ - $ - $ 600,000 $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ - $ 230,000 $ 740,000 $ - $ - $ -

    Total Estimated Costs: $ 970,000

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: X Neg. Dec: EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSWork expected to fit within the Routine O&M Program regulatory permit authorization requirements.

    Prepared By: Kirk Norman Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Cavin Road Debris Basin Retrofits Project No.: TBD

    Supervisorial District: 3 Zone: 2 Unincorporated Area: X City of: N/A

    Location: West of the Community of Piru

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe purpose of this project is to modify the primary outlet to pass more sediment during annual storms, and improve theemergency spillway to meet District freeboard criteria.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ - $ 85,000 $ - $ - $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ 110,000 $ - $ - $ -

    Construction: $ - $ - $ 550,000 $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ - $ 85,000 $ 660,000 $ - $ - $ -

    Total Estimated Costs: $ 745,000

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: X Neg. Dec: EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSWork expected to fit within the Routine O&M Program regulatory permit authorization requirements.

    Prepared By: Masood Jilani Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Rice Road Drain at Terrace Avenue RCB Repair Project No.: TBD

    Supervisorial District: 5 Zone: 2 Unincorporated Area: City of: Oxnard

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe purpose of this project is to repair the damaged reinforced concrete box culvert under Terrace Avenue.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ - $ 135,000 $ 5,000 $ - $ - $ -

    Right of Way: $ - $ 5,000 $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ 34,000 $ 5,000 $ - $ - $ -

    Construction: $ - $ 370,000 $ 83,500 $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ - $ 544,000 $ 93,500 $ - $ - $ -

    Total Estimated Costs: $ 637,500

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: X Neg. Dec: EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSWork expected to fit within the Routine O&M Program regulatory permit authorization requirements.

    Prepared By: Kirk Norman Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Santa Clara River Levee D/S of Hwy 101 (SCR-3) Project No.: 82045

    Supervisorial District: 1, 5 Zone: 2 Unincorporated Area: City of: Oxnard

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEDesign and construct upgrades to the existing levee improvements on the south bank of the Santa Clara River from theclosed Bailard Landfill to the UPRR bridge crossing. The objective is to protect adjacent properties from the 100-yr flood.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 2,450,288 $ 200,000 $ 150,000 $ - $ - $ -

    Right of Way: $ 32,550 $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ 3,342 $ 160,000 $ 303,740 $ 920,000 $ - $ -

    Construction: $ - $ 1,832,087 $ - $ 10,204,029 $ - $ -

    *Miscellaneous: $ - $ 10,000 $ - $ 680,000 $ - $ -

    Fiscal Year Total: $ 2,486,180 $ 2,202,087 $ 453,740 $ 11,804,029 $ - $ -

    Total Estimated Costs: $ 16,946,036

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: --- Date Filed: ---

    REMARKSCity of Oxnard and District have conceptually agreed to share project costs. Mitigation monitoring and maintenance costs =$400K (over 5yrs). 55% of design, CEQA and Phase 1 construction will be funded by a Department of Water Resources2011 LLAP grant.

    Prepared By: Masood Jilani Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Santa Clara River Levee U/S of Hwy 101 (SCR-1) Project No.: 82035

    Supervisorial District: 1, 3, 5 Zone: 2 Unincorporated Area: City of: Oxnard

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEUpgrade existing U.S. Army Corps of Engineers built levee improvements on the south bank of the Santa Clara River fromHwy 101 to upstream of Hwy 118 to protect adjacent properties from the 100-yr flood and certify the levee.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 752,162 $ 2,152,000 $ 90,000 $ 45,000 $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ 157 $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 752,318 $ 2,152,000 $ 90,000 $ 45,000 $ - $ -

    Total Estimated Costs: $ 3,039,318

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: --- Date Filed: ---

    REMARKSCurrent scope of work includes final design, CEQA, and permitting. 55% of budgeted work will be funded by Department ofWater Resources 2015 LLAP grant.

    Prepared By: Peter Sheydayi Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Sespe Creek Levee - Hwy 126 to Old Telegraph Rd (SC-2) Project No.: 83309

    Supervisorial District: 3 Zone: 2 Unincorporated Area: X City of: Fillmore

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEConstruct upgrades to the existing U.S. Army Corps of Engineers built levee improvements on the east bank of the SespeCreek from Hwy 126 to Old Telegraph Road. The objective is to protect adjacent properties from the 100-yr flood and certifythe levee.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 2,030,800 $ 60,000 $ - $ - $ - $ -

    Right of Way: $ 45,192 $ 50,000 $ - $ - $ - $ -

    Con. Eng./Insp.: $ 6,408 $ 360,000 $ - $ - $ - $ -

    Construction: $ - $ 3,300,000 $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 2,082,400 $ 3,770,000 $ - $ - $ - $ -

    Total Estimated Costs: $ 5,852,400

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: X EIR/EIS: Date Completed: 08/06/2013 Date Filed: 08/06/2013

    REMARKSAdditional annual operations and maintenance costs = $0.00 No environmental mitigation anticipated. 55% of budgetedwork will be funded by a Department of Water Resources 2011 LLAP grant.

    Prepared By: Kirk Norman Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: tšumaš creek - Hueneme Road to Pleasant Valley Road Project No.: 82323

    Supervisorial District: 3, 5 Zone: 2 Unincorporated Area: City of: Oxnard

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEConstruct channel improvements from downstream of Hueneme Road to Pleasant Valley Road to increase capacity ofexisting inadequate facility. Objective is to provide 100-yr flow protection to adjacent residential properties.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 310,664 $ 160,000 $ 105,000 $ - $ - $ -

    Right of Way: $ 576 $ 5,000 $ 5,000 $ 5,000 $ - $ -

    Con. Eng./Insp.: $ 9,880 $ - $ 170,000 $ 585,000 $ 20,000 $ -

    Construction: $ - $ - $ 16,860,000 $ 845,000 $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 321,120 $ 165,000 $ 17,140,000 $ 1,435,000 $ 20,000 $ -

    Total Estimated Costs: $ 19,081,120

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: 03/27/2012 Date Filed: 03/28/2012

    REMARKSThe project includes a $4.4M grant to construct the reinforced concrete box alternative so the City can implement a linearpark. The City and District need to enter into an agreement to share project costs and outline future maintenanceresponsibilities.

    Prepared By: Kirk Norman Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 3 FISCAL YEAR (2016/2017)

    Project Location Estimated Costs1 Arroyo Simi Grade Stabilization - Hitch Blvd to

    UPRRCity of Moorpark $ 1,795,100

    2 Calleguas Creek Levee - Hwy 101 to Adolfo Rd(CC-2)

    City of Camarillo $ 15,000

    3 Conejo Mountain Creek Detention Basins 2-5 atDos Vientos

    City of Thousand Oaks $ 310,000

    4 Santa Rosa Road #2 Debris BasinDecommissioning

    Between Thousand Oaks and Moorpark $ 302,000

    5 Sycamore Canyon Dam Spillway and BasinModifications

    City of Simi Valley $ 357,000

    Grand Total: $ 2,779,100

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 3 FISCAL YEARS (2017/2018 to 2020/2021)

    Project Location Estimated Costs1 Arroyo Simi Grade Stabilization - Hitch Blvd to

    UPRRCity of Moorpark $ 2,635,000

    2 Calleguas Creek Levee - Hwy 101 to Adolfo Rd(CC-2)

    City of Camarillo $ -

    3 Conejo Mountain Creek Detention Basins 2-5 atDos Vientos

    City of Thousand Oaks $ 2,594,000

    4 Santa Rosa Road #2 Debris BasinDecommissioning

    Between Thousand Oaks and Moorpark $ -

    5 Sycamore Canyon Dam Spillway and BasinModifications

    City of Simi Valley $ -

    Grand Total: $ 5,229,000

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Arroyo Simi Grade Stabilization - Hitch Blvd to UPRR Project No.: 87006

    Supervisorial District: 4 Zone: 3 Unincorporated Area: City of: Moorpark

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEProject scope includes invert stabilization to eliminate scour and degradation within the project reach. A preliminary designstudy will be completed to properly site which stabilizers need to be improved and which may be removed.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 111,978 $ 460,100 $ 90,000 $ 90,000 $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ 235,000 $ 210,000 $ 210,000 $ 35,000 $ -

    Construction: $ - $ 1,100,000 $ 1,000,000 $ 1,000,000 $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 111,978 $ 1,795,100 $ 1,300,000 $ 1,300,000 $ 35,000 $ -

    Total Estimated Costs: $ 4,542,078

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: X EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSAdditional annual operations and maintenance costs = $0.00 Environmental mitigation will be required for newrock/concrete. Scope assumes that six stabilizers will be repaired or constructed to complete project.

    Prepared By: Peter Sheydayi Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Calleguas Creek Levee - Hwy 101 to Adolfo Rd (CC-2) Project No.: 015049

    Supervisorial District: 3 Zone: 3 Unincorporated Area: City of: Camarillo

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEPreliminary design of improvements to the existing Calleguas Creek Levee (CC-2) between Hwy 101 and Adolfo Road, andSomis Drain upstream to correct deficiencies in order to certify the exsting levee with FEMA.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 333,571 $ 15,000 $ - $ - $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 333,571 $ 15,000 $ - $ - $ - $ -

    Total Estimated Costs: $ 348,571

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: EIR/EIS: X Date Completed: --- Date Filed: ---

    REMARKSMitigation monitoring and maintenance costs are unknown at this time. 55% of current scope of work, including preliminarydesign and geotechnical investigations, will be funded by a Departmemt of Water Resources 2015 LLAP grant.

    Prepared By: Zia Hosseinipour Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Conejo Mountain Creek Detention Basins 2-5 at Dos Vientos Project No.: 86910

    Supervisorial District: 2 Zone: 3 Unincorporated Area: City of: Thousand Oaks

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVERehabilitate existing debris and detention basins to meet District design standards. Focus is on developing a solution tosolve detention and debris volume deficiencies.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 19,010 $ 310,000 $ 340,000 $ 7,000 $ 5,000 $ 7,000

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ 185,000 $ - $ 185,000 $ -

    Construction: $ - $ - $ 700,000 $ - $ 470,000 $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 19,010 $ 310,000 $ 1,225,000 $ 7,000 $ 660,000 $ 7,000

    Total Estimated Costs: $ 2,228,010

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: X EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSFunding for this project is from a negotiated settlement from the developer that initially constructed these facilities.

    Prepared By: Robin Jester Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Santa Rosa Road #2 Debris Basin Decommissioning Project No.: TBD

    Supervisorial District: 2 Zone: 3 Unincorporated Area: X City of: N/A

    Location: Between Thousand Oaks and Moorpark

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe purpose of this project is to remove the Santa Rosa Road #2 Debris Basin and restore the impacted area.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ - $ 302,000 $ - $ - $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ - $ - $ - $ - $ -

    Construction: $ - $ - $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ - $ 302,000 $ - $ - $ - $ -

    Total Estimated Costs: $ 302,000

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: Neg. Dec: X EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSCurrent scope of work is only for design and permitting. It is anticipated that grants will become available to pay for theconstruction of this restoration project. No compensatory habitat mitigation is anticipated.

    Prepared By: Salvador Diaz-Rubin Date: 03/23/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Sycamore Canyon Dam Spillway and Basin Modifications Project No.: 87903

    Supervisorial District: 4 Zone: 3 Unincorporated Area: City of: Simi Valley

    Location: N/A

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVEThe project includes the modification of the existing emergency spillway and access to the dam. Objective is to improve damsafety and flood protection of the existing detention basin.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 259,194 $ - $ - $ - $ - $ -

    Right of Way: $ - $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ - $ 332,000 $ - $ - $ - $ -

    Construction: $ 1,200,000 $ - $ - $ - $ - $ -

    *Miscellaneous: $ - $ 25,000 $ - $ - $ - $ -

    Fiscal Year Total: $ 1,459,194 $ 357,000 $ - $ - $ - $ -

    Total Estimated Costs: $ 1,816,194

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: X Neg. Dec: EIR/EIS: Date Completed: --- Date Filed: ---

    REMARKSAdditional Annual Operations and Maintenance Costs = $0 Work expected to fit within the Routine O&M Programregulatory permit authorization requirements.

    Prepared By: Salvador Diaz-Rubin Date: 03/24/2016

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 4 FISCAL YEAR (2016/2017)

    Project Location Estimated Costs1 Oak Park Green Streets Urban Retrofit Community of Oak Park $ 1,359,218

    Grand Total: $ 1,359,218

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    FIVE YEAR PLANNED CAPITAL PROJECTS

    ZONE: 4 FISCAL YEARS (2017/2018 to 2020/2021)

    Project Location Estimated Costs1 Oak Park Green Streets Urban Retrofit Community of Oak Park $ 225,604

    Grand Total: $ 225,604

  • VENTURA COUNTY PUBLIC WORKS AGENCY

    WATERSHED PROTECTION DISTRICT

    Project Name: Oak Park Green Streets Urban Retrofit Project No.: 40540

    Supervisorial District: 2 Zone: 4 Unincorporated Area: X City of: N/A

    Location: Community of Oak Park

    LOCATION MAP

    SCOPE OF WORK AND OBJECTIVERetrofit existing medians on Kanan Rd as biofiltration stormwater BMPs and install 10 modular wetland proprietarytreatment devices in various locations throughout Oak Park community.

    ESTIMATED COSTS PER FISCAL YEAR

    Category Prev Years 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021

    Design: $ 194,438 $ - $ - $ - $ - $ -

    Right of Way: $ 4,818 $ - $ - $ - $ - $ -

    Con. Eng./Insp.: $ 39,887 $ 129,218 $ 225,604 $ - $ - $ -

    Construction: $ - $ 1,230,000 $ - $ - $ - $ -

    *Miscellaneous: $ - $ - $ - $ - $ - $ -

    Fiscal Year Total: $ 239,143 $ 1,359,218 $ 225,604 $ - $ - $ -

    Total Estimated Costs: $ 1,823,965

    ENVIRONMENTAL REQUIREMENTS

    Cat. Ex: X Neg. Dec: EIR/EIS: Date Completed: --- Date Filed: 10/08/2014

    REMARKSThis project will be reimbursed by a State Water Resources Control Board (SWRCB) grant under the Proposition 84 in theamount of $1,397,990.

    Prepared By: David Kirby Date: 03/24/2016