Upload
yurisdal-bowie-azwan
View
213
Download
0
Embed Size (px)
Citation preview
8/18/2019 Project Tembus Sholeh
1/4
ID Task Name Duration Start Finish
1 PEMBANGUNAN JALAN TEMBUS SHOLEH 120 days Thu 24/07/14 Thu 20/11/14
2 DIVISI 1. UMUM 42 days Mon 18/08/14 Sun 28/09/14
3 Pek. Mobilisasi dan Demobilisasi 7 days Mon 18/08/14 Sun 24/08/14
4 Pek. Direksi keet 14 days Mon 18/08/14 Sun 31/08/14
5 Pek. Papan Nama Proyek 7 days Mon 18/08/14 Sun 24/08/14
6 Pek. Pengaturan lalu lintas dan Pagar Pengaman 7 days Fri 22/08/14 Thu 28/08/14
7 Pek. Pengukuran Site 7 days Mon 18/08/14 Sun 24/08/14
8 Pek. Bouplank 21 days Mon 25/08/14 Sun 14/09/14
9 Pek. Los Kerja / Bahan 14 days Mon 25/08/14 Sun 07/09/14
10 Pek. Pembersihan Damija 7 days Mon 08/09/14 Sun 14/09/14
11 Pek. Pengujian Lapangan 14 days Mon 15/09/14 Sun 28/09/14
12 Pek. Normalisasi Saluran 7 days Mon 15/09/14 Sun 21/09/14
13 DIVISI 2. DRAINASE 40 days Mon 15/09/14 Fri 24/10/14
14 Pek. Pasangan batu dengan mortar 28 days Mon 15/09/14 Sun 12/10/14
15 Pek. Buis Beton Bulat Dia 30 28 days Fri 19/09/14 Thu 16/10/14
16 Pek. Drainase U-Ditch (U-800) 28 days Tue 23/09/14 Mon 20/10/14
17 Pek. Cover Drainase U-Ditch (U-800) 28 days Sat 27/09/14 Fri 24/10/14
18 Pek. Box Culvert HD BC 800x800 14 days Wed 01/10/14 Tue 14/10/14
19 Pek. Box Culvert HD BC 800x800 BM 14 days Sun 05/10/14 Sat 18/10/14
20 DIVISI 3. PEKERJAAN TANAH 42 days Mon 01/09/14 Sun 12/10/14
21 Pek. Galian Tanah 21 days Mon 01/09/14 Sun 21/09/14
22 Pek. Galian Tanah Keras Oprit 7 days Mon 15/09/14 Sun 21/09/14
23 Pek. Urugan Tanah Kembali Bekas Galian (dipadatkan) 7 days Mon 06/10/14 Sun 12/10/14
24 Pek. Penyiapan badan jalan 14 days Mon 15/09/14 Sun 28/09/14
25 Pek. Buangan tanah bekas galian 21 days Mon 08/09/14 Sun 28/09/14
26 DIVISI 4. Peke rjaan Aspal 25 days Mon 29/09/14 Thu 23/10/14
27 Pek. Pondasi Agregat Kelas A 7 days Mon 29/09/14 Sun 05/10/14
28 Pek. Lapis Resap Pengikat 7 days Mon 06/10/14 Sun 12/10/14
29 Pek. Laston Lapis Pondasi (AC-Base) levelling (crossing) 14 days Mon 06/10/14 Sun 19/10/14
30 Pek. Laston Lapis Pondasi (AC-Base) levelling (oprit) 14 days Fri 10/10/14 Thu 23/10/14
31 DIVISI 5. PERKERASAN BERBUTIR 21 days Tue 14/10/14 Mon 03/11/14
32 Pek. Limestone tebal 30 cm 21 days Tue 14/10/14 Mon 03/11/14
33 DIVISI 7. STRUKTUR 53 days Mon 29/09/14 Thu 20/11/14
34 Pek. Beton K-250 (ready mix) Block Beton 54 cm x 60 cm 7 days Tue 28/10/14 Mon 03/11/14
35 Pek. Beton K-250 (ready mix) Block Beton 56 cm x 60 cm 7 days Tue 04/11/14 Mon 10/11/14
36 Pek. Beton Jepit Ready Mix K-250 7 days Tue 11/11/14 Mon 17/11/14
37 Pek. Lantai kerja Ready mix K-125 (Box Utilitas, U-Ditch, Box Culvert) 14 days Mon 29/09/14 Sun 12/10/14
38 Pek. Bekisting (2x pakai) 21 days Fri 03/10/14 Thu 23/10/14
39 Pek. Beton K-225 (site mix, exclude formwork) + pipa pvc dia.2" 7 days Tue 07/10/14 Mon 13/10/14
40 Pek. Beton K-250 (ready mix) Blox Utilitas + Bak Kontrol 38 days Tue 14/10/14 Thu 20/11/14
41 Pek. Besi tulangan polos U24 38 days Tue 07/10/14 Thu 13/11/14
F T S W S T M F T S W
ug '14 01 Sep '14 29 Sep '14 27 Oct '14 24 Nov '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Project Tembus Sholeh
Date: Thu 24/07/14
8/18/2019 Project Tembus Sholeh
2/4
8/18/2019 Project Tembus Sholeh
3/4
W S T M F T S W S T M F T S W S T M F T S W
Nov '14 22 Dec '14 19 Jan '15 16 Feb '15 16 Mar '15 13 Apr '15 11 May '15 08 Jun '15 06 Jul '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Project Tembus Sholeh
Date: Thu 24/07/14
8/18/2019 Project Tembus Sholeh
4/4
W S T M F T S W S T M F T S W S T M F T S W
Nov '14 22 Dec '14 19 Jan '15 16 Feb '15 16 Mar '15 13 Apr '15 11 May '15 08 Jun '15 06 Jul '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Project Tembus Sholeh
Date: Thu 24/07/14