Upload
douglas-butler
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
Project Steering Committee
Meeting No. 411th June 2013
Intrasoft International Presentation
Project Steering Committee Meeting No. 4 (11 June 2013) 1
Support to the Establishment of Single Window for Export, Import and Transit Procedures in the
Republic of Tajikistan
Project Objectives
• The improvement of the business climate in Tajikistan.• The trade facilitation through the establishment of a Single
Window for export, import and transit procedures. • Optimization and reduction of the time and costs involved in
import, export, and transit transactions, based on international standards, recommendations, and good practices.
• Achieve greater efficiency and transparency in the management of foreign trade operations , improve interoperability between the participating government agencies.
Project Steering Committee Meeting No. 4 (11 June 2013) 2
Overall Expected Project Results
1. SWIS Development and Testing • Project Management Plan (PQP, project plan)• Detailed specification (SRS,DTD ,IRD) • System software.• Documentation (User manuals, training plan etc.)• Business Process Analysis and Optimisation
2. SWIS Pilot Implementation • At SUE SW office and two SW agencies (Chamber of commerce , Pharmaceutical)• Including the same two SW agencies in two regional centres (Khujand and Kurgan Tube)
3. Replication of SWIS • Roll out to all planned regional centres • All involved SW agencies at all those regional centres
4. Warranty and Support Services• Support, training and correction of faults and bugs in the SWIS• 6 months after system goes live
Project Steering Committee Meeting No. 4 (11 June 2013) 3
Project Phases
• Inception 12 Jun 12 11 July 12• Elaboration 16 July 12 9 Jan 13• Construction 2 Jan 13 1 Aug 13• Transition 15Aug 13 11 Apr 14
– Pilot 15 Aug 13 15 Oct 13– Installation 10 Sep 13 15 Oct 13– Replication 16 Oct 13 20 Dec 13– Warranty 23 Dec 13 11 Apr 14
Project Steering Committee Meeting No. 4 (11 June 2013) 4
Progress to date• Inception Phase – completed• Elaboration (Design) Phase – completed• Construction Phase – development at an
advanced stage• Business Process Analysis – completed• ICT equipment tender evaluated
Project Steering Committee Meeting No. 4 (11 June 2013) 5
Activities since Meeting #3
• Approved six month “Interim Report No. 1” circulated to SC members
• Next Interim Report (No. 2) to 11th June currently in draft • Business Process Analysis and Optimisation work completed
at 3 agencies and report submitted to EU Delegation• SLA Resolution and SLA Template completed (English and
Russian) and submission to MEDT next week (Tajik version)• Project website “live”• Press release ready for after this meeting
Project Steering Committee Meeting No. 4 (11 June 2013) 6
Activities since Meeting #3 (cont.)
• Advanced discussions in defining/formalizing interfaces with the Treasury and Commercial bank
• Pilot server-side infrastructure operational in Athens• Live demonstration of SWIS software made available to
selected users for evaluation and feedback purposes (system access and credentials are currently being distributed)
• ICT tender responses received and evaluations completed• Athens visit for SUE SW staff and Mr. Roziev now organised
Project Steering Committee Meeting No. 4 (11 June 2013) 7
Service Level Agreement (SLA)
• SLA Resolution being finalised• SLA template being finalised• Many meetings with the Project Team, Mr. Roziev, EU
Delegation’s Technical Assistance, GIZ’s TA to the SUE SW• Tajik version being drafted now• Submission to MEDT next week for circulation to the
Coordination Committee
Project Steering Committee Meeting No. 4 (11 June 2013) 8
Documentation Deliverables Update
1. Service Desk and Fallback Procedures (Submitted)2. Acceptance Testing Plan (Submitted)3. Development of Training Strategy, Methodology and
Environment (Submitted)4. Pilot Implementation Plan (Submitted)5. Maintenance and Support Implementation Plan (Submitted)6. System Replication (Submitted)7. Acceptance Tests (ATS) was re-submitted for acceptance8. Training Plan (Submitted)
Project Steering Committee Meeting No. 4 (11 June 2013) 9
The Construction Phase• Development of the SWIS Application Software
– Core System Development– System User Interface development
• UAIS • Business Registration System (Tax Committee)• Commercial bank and Treasury• GIZ (SIMBASE)
• Documentation of SWIS application software and all delivery activities
• Business Process Optimisation activities
Project Steering Committee Meeting No. 4 (11 June 2013) 10
Construction Phase Documentation Deliverables Due
• Installation Procedures (IPR) Tues 25/6/13• Training Material Fri 26/7/13• User Manual (UMN) Mon 29/7/13• Administrator Manual (AMN) Mon 29/7/13• External Interfaces Tue 30/7/13
Project Steering Committee Meeting No. 4 (11 June 2013) 11
Construction Phase (151 Days) 2 January 2012 - 1 August 2013
• Development 7 Jan 13 22 June 13• Test SWIS (FAT) 18 Jun 13 25 Jul 13• Package/Deliver 30 Jul 13 31 Jul 13• Documentation 2 Jan 12 1 Aug 13
• BPA/BPO 4 Feb 13 10 Jun 13
Project Steering Committee Meeting No.4 (11 June 2013) 12
The Development Activities
• Application software development• Factory Acceptance Tests and deliver report• Produce test data• Deliver deployable package
Project Steering Committee Meeting No. 4 (11 June 2013) 13
The Development Activities (Cont.)
• Progress Infrastructure (Completed)• User Interface Prototype (Completed)• Database Design (Completed)• Workflow (Completed)• Web applications (In progress)
(with User Interface)• Service Implementation (In progress)• Integration (In progress)
Project Steering Committee Meeting No. 4 (11 June 2013) 14
The Development Activities (Cont.)
• Integration with Bank/Treasury– Initial discussions about the technical solution.– Technical proposal was submitted in March.– There is an agreement in the basic issues– Some minor details still under dicsussion
Project Steering Committee Meeting No. 4 (11 June 2013) 15
The Development Activities (Cont.)
• Integration with GIZ/SIMBASE system– Initial discussions about the technical solution.– Technical proposal was submitted in March.– There is no progress, we received no written reply
to our technical proposal .
Project Steering Committee Meeting No. 4 (11 June 2013) 16
Business Process Analysis and Optimization
SW Agencies selected for BPA and BPO •State Assay Supervision•Service of the State Supervision of Pharmaceutical Activities•Service of the State Sanitary and Epidemiological Supervision
BPA and BPO reports submitted to EU Delegation for review
Project Steering Committee Meeting No. 4 (11 June 2013) 17
General BPA Findings
• Payment varies from in advance to multi-step• Redundant procedures identified• Use of multiple registers – duplication of same data• No provision for e-submission in internal regulations• Non-alignment of regulations with Permits Law and no
clear clarification of procedures in internal regulations• Workflow paperwork is excessive• 100% testing of all shipments is the norm (no risk
management)
Project Steering Committee Meeting No. 4 (11 June 2013) 18
General BPO Recomendations• Simplification of procedures• Reduction in paper documents• Use of automation to minimise paperwork (e.g. SimBase) and integrate
with SWIS• Allow electronic submission of all documents• Implement the principles of the Single Window• Implement one single new regulation to govern the certification/permit
procedures• Adopt proposal on classificators to standardise, improve transparency
and remove uncertainty• Eliminate all cash payments and move payment to the end of the
process• Introduce sampling techniques for lab testing with clear and
understandable rules
Project Steering Committee Meeting No. 4 (11 June 2013) 19
SWIS Classifiers preparation• A set of classifiers for SW Agencies and related Permit Documents
(Certificates) was prepared by the third working group.• 15 SWIS classifiers were already officially approved by Coordination
Committee decision in May 2013 (including set of classifiers used internally by Custom Service and collected from UAIS Web site);
• Some more classifiers will be added for Custom declaration support and will be based on UAIS classifiers and code lists (data was already requested from Custom Service as an UAIS database dump);
• Agency’s classifier was agreed with all Agencies in June 2013 and will be presented for approval at the next Coordination Committee;
Project Steering Committee Meeting No. 4 (11 June 2013) 20
Assistance in the legal definition for Agencies responsibility per TNVED subsets
• Assistance to Government to create clear end-to-end regulation in relationship between TNVED – Permit Documents/Certificates – Agency/Agency Branch;
• Proposal to harmonise government Regulation N-310 and internal Agencies regulations was raised and supported by Coordination Committee;
• Related working material/proposal based on Custom Union approach was prepared and distributed between Agencies in February and June (regulation, government registers, TNVED tables per each Agency and so on);
• Working group (WG) led by SUE SW was established by Coordination Committee decision in May 2013 and has already started to work.
• First WG meeting took place, agreed main points about TNVED, WG agenda and the schedule
Project Steering Committee Meeting No. 4
(11 June 2013) 21
Working group tasks (Agency’s TNVED)
• Define TNVED subset for each Agency based on existing regulation R-310 (Tajikstandard agreed for the draft preparation);
• Each Agency has to prepare own TNVED based lists of goods not covered by R-310 for future discussion;
• Prepare concrete proposals about TNVED for Coordination Committee approval;
• Results can be used by SW and also by government in a future improvement to reduce number of obligatory goods for control.
Open issues: • problems with “cultural value” definition based on TNVED codes for
Ministry of Culture;• future clarification of relationship between TNVED codes and
branded goods in government registers (pharmaceutics and others).
Project Steering Committee Meeting No. 4
(11 June 2013) 22
The Transition Phase
• Installation of Pilot Environment Infrastructure(Hardware, software and training preparation)
• Pilot Implementation (Training, testing, rectification, site acceptance tests,
final SLA with each SW agency)
• Supervision of all equipment installation activities
• Replication of the SWIS across all sites• Warranty period
Project Steering Committee Meeting No. 4 (11 June 2013) 23
The Pilot Activities• Preparations (users, logistics etc) • VPN Communications arrangements.• Installation of Pilot Environment Infrastructure.• Supervision of all equipment installation
activities.• Deployment of SWIS.• Testing at Pilot sites.• Running SWIS in parallel with existing manual
procedures.Project Steering Committee Meeting No. 4
(11 June 2013) 24
Main Issues Regarding Pilot
1. Equipment1. Server side equipment In Athens.
2. Communications infrastructure.
3. Hardware for Pilot SW agencies.
2. Digital signature not included in Pilot
3. Integration with Commercial Bank and Treasury not included
Project Steering Committee Meeting No. 4 (11 June 2013) 25
The Supervision Activities• Supervised supply and installation of Central Servers Mon 09/09/13 Fri 04/10/13
• Supervised supply and installation of workstations and network equipment Mon 09/09/13 Fri
04/10/13• Full load testing. Acceptance and commissioning Mon 07/10/13 Fri 11/10/13• Infrastructure Installation Report Mon 14/10/13 Tue
15/10/13
Project Steering Committee Meeting No. 4 (11 March 2013)
26
Potential Extensions of the Project
• Full integration of the SW system software with one or more agency’s processes.– Pharmaceutical Agency
• Additional SW certification member (Cotton)• We are examining integration with SimBase or
we may add an additional agency for the above integration
Project Steering Committee Meeting No. 4 (11 June 2013) 27
Open Issues and Risks
1. SW – UAIS Integration. 2. BRIS Integration.3. Integration with GIZ/SimBase system--------1. Single payment foreseen in SRS is not
yet accepted by all agencies2. Use of Electronic Digital Signatures.3. Need for further elaboration of some
functional specifications
Project Steering Committee Meeting No. 4 (11 June 2013) 28
Open Issues and Risks(SC.01)
1. SW – UAIS Integration. 2. Payments (SW Agencies , Customs).3. BRIS Integration.---------------------1. SW Agencies processing details.2. User Registration.------------1. Electronic Documents.2. Electronic Signatures.
Project Steering Committee Meeting No. 4 (11 June 2013) 29
Summary
• ICT tender evaluated – contract by start July• Service Level Agreement Resolution and SLA
template being finalised• Construction Phase is well advanced• Basic ICT Training commenced and ongoing
assessment of Training Needs at SW agencies in progress
• Pilot Implementation preparation continues• SWIS training plan implementation in progress
Project Steering Committee Meeting No. 4 (11 June 2013) 30
Demonstration of SWIS
Project Steering Committee Meeting No. 4 (11 June 2013) 31
Thank you for you attention
Project Steering Committee Meeting No. 4 (11 June 2013) 32