Project Steering Committee
Inception Report12 September 2012
Intrasoft International Project Team Presentation
Project Steering Committee Meeting No. 1 (12 September 2012) 1
Support to the Establishment of Single Window for Export, Import and Transit Procedures in the
Republic of Tajikistan
Project Objective
• The overall objective of the project is to contribute to poverty alleviation through the improvement of the business climate in Tajikistan.
• The specific objective is trade facilitation through the establishment of Single Window for export, import and transit procedures.
Project Steering Committee Meeting No. 1 (12 September 2012) 2
Overall Expected Project Results
1. SW IS Development and Testing • Project Plan• Detailed specification (SRS) • System software developed• Implementation Plan• Training Plan
2. SW IS Pilot Implementation • At SUE SW office and two SW agencies• Including the same two SW agencies in two regional centres
3. Replication of SW IS • Roll out to all planned regional centres • All involved SW agencies at all those regional centres
4. Warranty and Support Services• Support, training and correction of faults and bugs in the SWIS• 6 months after system goes live
Project Steering Committee Meeting No. 1 (12 September 2012) 3
The Inception Period
• 12 June to 11 July 2012• 29 formal meetings with stakeholders• Senior Management mission (9 July – 15 July)• Providing a baseline assessment• Updating prior knowledge of the SW project
Project Steering Committee Meeting No. 1 (12 September 2012) 4
Prior Assumptions
From the EU Terms of Reference:
• Enthusiasm and high motivation levels amongst the Government officials and donor community will continue in designing the SWIS and its implementation;
• Through gaining experience, the inter-service Single Window Coordination Committee will take a strong lead in implementing the project and received good response and cooperation from the part of the Government SW Agencies; and
• The Coordination Committee will implement the Action Plan approved by the Coordination Committee on 26 July 2010. The Action plan includes developing a legal framework for Single Window and proposing amendments in particular in regulatory framework for Digital Signature and Electronic Documents.
Project Steering Committee Meeting No. 1 (12 September 2012) 5
General Findings
• Hi level support• State Unitary Enterprise “Single Window
Centre”• SW Coordination Committee• E document/e signature legislation• Business Process Analysis• Data Harmonisation
Project Steering Committee Meeting No. 1 (12 September 2012) 6
Structure
Project Steering Committee Meeting No. 1 (12 September 2012) 7
Project Resourcing
Non-Key ExpertsBudget Days
Tajikistan Field Days
% of Total Days Athens
% of Total Days
Project Director 53 35 66,04% 18 33,96%
Quality Assurance Manager 123 20 16,26% 103 83,74%
Junior Legal Expert 105 105 100,00% 0 0,00%
Business PrSenior ocess Re-engineering Expert 102 35 34,31% 67 65,69%
Analysts 189 125 66,14% 64 33,86%
Trainers 31 31 100,00% 0 0,00%
Technical Writers 63 15 23,81% 48 76,19%Senior Data Management and System Integration Expert 63 20 31,75% 43 68,25%
Technical and Security Experts 136 40 29,41% 96 70,59%
Application Developers 756 70 9,26% 686 90,74%
Testing Team Leader 30 0 0,00% 30 100,00%
Testers 126 40 31,75% 86 68,25%
Service Desk Personnel 252 170 67,46% 82 32,54%
Total Non-Key Expert 2029 706 34,80% 1323 65,20%
Key Expert
Team Leader 300 300 100,00% 0 0,00%
Senior ICT Expert 250 250 100,00% 0 0,00%
Total Key Expert 550 550 100,00% 0 0,00%
Total 2579 1256 48,70% 1323 51,30%
Project Steering Committee Meeting No. 1 (12 September 2012) 8
Stakeholder Engagement Activities
• Consultation on SRS (roundtables, stakeholder meetings)
• Website • SW agencies meetings• Continued stakeholder education (written
material, media engagement, general visibility, DVD)
• Consultation with private sector (national)• Continued donor collaboration (GIZ, IFC, UNDP,
WB)
Project Steering Committee Meeting No. 1 (12 September 2012) 9
Project Phases
• Inception Tue 12/6/12 Fri 13/7/12• Elaboration Mon 16/7/12 Fri 28/9/12• Construction Mon 3/9/12 Fri 10/5/13• Transition Mon 22/4/13 Fri 11/4/14
– Pilot Mon 22/4/13 Fri 23/8/13– Complete Mon 26/8/13 Fri 11/10/13– Warranty Mon 14/10/13 Fri 11/4/14
Project Steering Committee Meeting No. 1 (12 September 2012) 10
Elaboration Phase Deliverables
• Functional Requirements (SRS) Fri 14/9/12
• Draft Service Level Agreement Fri 14/9/12
• Detailed Design (DTD) Fri 28/9/12
• System Design (Equipment) Fri 28/9/12
Project Steering Committee Meeting No. 1 (12 September 2012) 11
Current State
• Functional Requirements (SRS) 75%
• Draft Service Level Agreement 95%
• Detailed Design (DTD) 40%
• System Design (Equipment) 20%
Project Steering Committee Meeting No. 1 (12 September 2012) 12
SRS Functional Areas
Project Steering Committee Meeting No. 1 (12 September 2012) 13
SRS Issues in Progress(Risks)
1. SW – UAIS Integration 2. Payments (SW Agencies, Customs)3. BRIS Integration---------------------1. SW Agencies processing details2. User Registration------------1. Electronic Documents2. Electronic Signatures
Project Steering Committee Meeting No. 1 (12 September 2012) 14
System Design (Equipment)
• Document structure ready• Will describe the hardware and
communications requirements of the SWIS• Hardware details depend upon SRS and DTD
Project Steering Committee Meeting No. 1 (12 September 2012) 15
Draft Service Level Agreement
• Almost completed• Technical Justification for the SLA completed
and is in review by the EU Project Manager• Proposed approach for SLA agreed with SUE
Project Steering Committee Meeting No. 1 (12 September 2012) 16
DTD Progress
• Document structure is defined • Stable architecture is selected• COTS are selected
– JBOSS Application Server– MySql database– JEE /JSE– Spring Framework– Apache Camel Integration Framework– Apache HTTP Server
Project Steering Committee Meeting No. 1 (12 September 2012) 17
Remaining Activities of the Elaboration Phase
• Resolve open issues• Submit and review SRS• Submit other documents• Accept SRS• Review and accept other documents
Project Steering Committee Meeting No. 1 (12 September 2012) 18
Construction 180days Mon 3/9/12 - Fri 10/5/13
• Initial stage Mon 3/9/12 Fri 28/9/12• Development Mon 1/10/12 Tue 19/3/13• Test SWIS (FAT) Wed 20/3/13 Tue 7/5/13• Package/Deliver Wed 8/5/13 Thu 9/5/13• Documentation Mon 1/10/12 Tue 7/5/13
Project Steering Committee Meeting No. 1 (12 September 2012) 19
Thank you for you attention
Project Steering Committee Meeting No. 1 (12 September 2012) 20