Project Control Earned

Embed Size (px)

Citation preview

  • 8/4/2019 Project Control Earned

    1/57

    Dr. Hesham A. Aziz 1

    Project Control

    American University in Cairo

    Egypt

    Presented By

    Dr. Hesham A. Aziz

    Project Cost Planning and Control

  • 8/4/2019 Project Control Earned

    2/57

    Dr. Hesham A. Aziz 2

  • 8/4/2019 Project Control Earned

    3/57

    Dr. Hesham A. Aziz 3

    Control The process of comparing actual performance

    against plan to identify deviations, evaluate courses

    of action, and take appropriate corrective action.

    Project Control Steps1. Setting a baseline plan.

    2. Measuring progress and performance.

    3. Comparing plan against actual.4. Taking actions

    The Project Control Process

  • 8/4/2019 Project Control Earned

    4/57

    Dr. Hesham A. Aziz 4

    Project Control

    Indirect &Overhead

    costs

    Changeorders

    Lump-sumContract

    costs

    Project Plan, Schedule,Budget, Quality

    Safety

    Other

    Contractcosts

    Materialcosts

    Equipment

    costs

    Laborcosts

    ProgressReports

    Projectplanning

    Design

    Collecting information for Project Control

  • 8/4/2019 Project Control Earned

    5/57

    Dr. Hesham A. Aziz 5

    A typical information filter

    Top management / executive

    Project Manger

    Project team

    Updated priceOn completion

    Project completiondate

    Money expendedSo far

    Project completionprice

    Programmedstatus

    WeeklySite

    reports

    Anticipatedclaims

    ChangesIn scope

    Future problemareas

    Site instructionsAnd variations

    Abortivework

    Percentage

    completion

    Monthlyvaluations

    MACROLEVEL

    MESOLEVEL

    MICROLEVEL

  • 8/4/2019 Project Control Earned

    6/57

    Dr. Hesham A. Aziz 6

    Information System Structure What data are collected?

    Current status of project (schedule and cost)

    Remaining cost to compete project

    Date that project will be complete

    Potential problems to be addressed now

    Out-of-control activities requiring intervention Cost and/or schedule overruns and the reasons for

    them

    Forecast of overruns at time of project completion

    Project Monitoring System for Control

  • 8/4/2019 Project Control Earned

    7/57

    Dr. Hesham A. Aziz 7

    Information System Structure (contd) Collecting data and analysis

    Who will collect project data?

    How will data be collected?

    When will the data be collected?

    Who will compile and analyze the data?

    Reports and reporting

    Who will receive the reports? How will the reports be transmitted?

    When will the reports be distributed?

    Project Monitoring System (contd)

  • 8/4/2019 Project Control Earned

    8/57

    Dr. Hesham A. Aziz 8

    Progress since last report Current status of project

    Schedule

    Cost

    Scope Cumulative trends

    Problems and issues since last report

    Actions and resolution of earlier problems

    New variances and problems identified

    Corrective action planned

    Project Progress Report Format

  • 8/4/2019 Project Control Earned

    9/57

    Dr. Hesham A. Aziz 9

    Time-Phase Baseline Plan

    Corrects the failure of most monitoring systems toconnect a projects actual performance to its

    schedule and forecast budget. Systems that measure only cost variances do not

    identify resource and project cost problemsassociated with falling behind or progressing

    ahead of schedule.

    Disparity Among Monitoring Systems

  • 8/4/2019 Project Control Earned

    10/57

    Dr. Hesham A. Aziz 10

    Earned Value Cost/Schedule System

    An integrated project management systembased on the earned value concept that uses atime-phased budget baseline to compare actual

    and planned schedule and costs.

  • 8/4/2019 Project Control Earned

    11/57

    Dr. Hesham A. Aziz 11

    Baseline Data Relationships

  • 8/4/2019 Project Control Earned

    12/57

    Dr. Hesham A. Aziz 12

    Project Management System Overview

  • 8/4/2019 Project Control Earned

    13/57

    Dr. Hesham A. Aziz 13

    Integration of WBSand OBS

  • 8/4/2019 Project Control Earned

    14/57

    Dr. Hesham A. Aziz 14

    Direct Labor Budget

    Rollup (000)

  • 8/4/2019 Project Control Earned

    15/57

    Dr. Hesham A. Aziz 15

    Baseline andTracking Gantt

    Charts

  • 8/4/2019 Project Control Earned

    16/57

    Dr. Hesham A. Aziz 16

    Project Schedule Control Chart

  • 8/4/2019 Project Control Earned

    17/57

    Dr. Hesham A. Aziz 17

  • 8/4/2019 Project Control Earned

    18/57

    Dr. Hesham A. Aziz 18

  • 8/4/2019 Project Control Earned

    19/57

    Dr. Hesham A. Aziz 19

    Relationships Between Time and Work

    * Overall design effort a work/time curve can be developed.

    Example Illustrative Weight Multipliers for Design Work_________________________________________

    Weight Project

    Design Work Multiplier Timing

    _______________________________________________

    Review backup material 0.05 0% - 10%

    Design calculations 0.10 10% - 25%

    Initial drafting 0.25 15% - 45%

    Final calculations 0.20 35% - 60%

    Production drawings 0.30 50% - 90%

    Drawing approval 0.10 90% - 100%

    _________

    1.00________________________________________________

    The slope of each graph is the ratio of the weight multiplier to the timerequired for the work to be performed.

  • 8/4/2019 Project Control Earned

    20/57

    Dr. Hesham A. Aziz 20

    Work / Time Relationship (Design Work)

    Over Laps

  • 8/4/2019 Project Control Earned

    21/57

    Dr. Hesham A. Aziz 21

    Over Laps

  • 8/4/2019 Project Control Earned

    22/57

    Dr. Hesham A. Aziz 22

    Integrated Cost / Schedule / Work Graph.

  • 8/4/2019 Project Control Earned

    23/57

    Dr. Hesham A. Aziz 23

    Over Cost and Behind Schedule

    1

    2

    3

  • 8/4/2019 Project Control Earned

    24/57

    Dr. Hesham A. Aziz 24

    Under Cost and Behind Schedule

    1

    2 3

    Under Cost and Ahead of Sched le

  • 8/4/2019 Project Control Earned

    25/57

    Dr. Hesham A. Aziz 25

    Under Cost and Ahead of Schedule

    1

    23

  • 8/4/2019 Project Control Earned

    26/57

    Dr. Hesham A. Aziz 26

    Over Cost and Ahead of Schedule

    1

    23

  • 8/4/2019 Project Control Earned

    27/57

    Dr. Hesham A. Aziz 27

    Earned Value Management

    Earned Value Management is a methodology used to measureand communicate the real physical progress of a plan taking intoaccount the work complete, the time taken and the costs incurred tocomplete that work.

    Earned Value helps evaluate and control risk by measuring

    the progress in monetary terms.

    By taking a snap-shot of the projected plan and calculatingthe Earned Value metrics we can compare the planned with the actualand make a subjective assessment of the progress.

    By extrapolating the curves and further calculation allowsestimate the costs to completion and the probable completion date.

    The basics of Earned Value can best be shown on theubiquitous 'S-Curve'.

  • 8/4/2019 Project Control Earned

    28/57

    Dr. Hesham A. Aziz 28

    Earned value analysis makes use of the followingvariables:

    Actual cost of the works performed (ACWP); Budgeted cost of the works performed (BCWP); Budgeted costs of the works specified (BCWS); Scheduled time for work performed (STWP); Actual time for work performed (ATWP);

    Cost Variance (CV); Schedule variance (SV); Budget at completion (BAC); Estimate at completion (EAC); Variance at completion (VAC).

  • 8/4/2019 Project Control Earned

    29/57

    Dr. Hesham A. Aziz 29

    Total work package budgeted cost = 1 000 000The EVA analysis is taken up to week 6 (week 6 is time now).

    The actual progress or works performed is 70 per cent. This means:Budgeted cost of the works performed (BCWP) = 1 000 000 70% = 700 000Actual cost to date = 750 000Work scheduled to date = 60%Budgeted cost of the works scheduled (BCWS) = 1 000 000 60% = 600 000

    Earned value analysis (EVA)

  • 8/4/2019 Project Control Earned

    30/57

    Dr. Hesham A. Aziz 30

    Sample SV and CV values

    Position at week 6

  • 8/4/2019 Project Control Earned

    31/57

    Dr. Hesham A. Aziz 31

    Position at week 7

    Comparative positions weeks 6 and 7

  • 8/4/2019 Project Control Earned

    32/57

    Dr. Hesham A. Aziz 32

  • 8/4/2019 Project Control Earned

    33/57

    Dr. Hesham A. Aziz 33

  • 8/4/2019 Project Control Earned

    34/57

    Dr. Hesham A. Aziz 34

  • 8/4/2019 Project Control Earned

    35/57

    Dr. Hesham A. Aziz 35

    EVM: A Simple Concept

    Time

    Actual Cost

    EarnedValue

    $

    Time Now

    Schedule

    Delay

    }

    Estimate atCompletion

    }Risk

    Planned Value

    Th i f l ti (VAC) i th diff b t th l d

  • 8/4/2019 Project Control Earned

    36/57

    Dr. Hesham A. Aziz 36

    The variance of completion (VAC) is the difference between the plannedand actual cost.

    The cost variance is the result of a comparison of how much the work hascost in comparison with what it was budgeted to cost, both in relation

    to works actually completed.

    Schedule variance (SV) is the difference between budgeted cost for theworks completed and performed and the budgeted cost of the worksscheduled

    The budget at completion (BAC) is the sum of all the individual budgets(BCWS) that make up . It is sometimes known as the baseline.

    The estimate at completion (EAC) is the estimated total cost . It is the sumof all direct and indirect costs to date plus authorized work remaining.The EAC can also be expressed in terms of a revised estimate.

    The cost accounting process of the PCCS involves looking at costvariance (CV) and schedule variance (SV) in order to assess theperformance of individual packages and groups of packages. This canbe done in several ways. The two most common are by direct evaluationof the variances themselves or by conversion of the variances toindices.

  • 8/4/2019 Project Control Earned

    37/57

    Dr. Hesham A. Aziz 37

    Scheduled time for work performed (STWP) This is the estimated timerequired to perform a defined amount of work.

    Actual time for work performed (ATWP) This is the actual time taken to

    perform a defined amount of work.

    Cost Variance (CV) The cost variance is the budgeted cost of workperformed (BCWP) minus the actual cost of work performed (ACWP).This is normally abbreviated to the formula:

    CV = BCWP ACWPCost variance is therefore a comparison of how much the work has cost inrelation to what it was budgeted to cost, both figures being in relation toworks actually completed.

    Schedule variance (SV) The schedule variance is the difference between

    budgeted cost for the works performed (BCWP) and the budgeted cost ofthe works scheduled (BCWS). This is normally abbreviated to the formula:

    SV = BCWP BCWSSchedule variance is therefore a measure of the performance of the worksin relation to budgeted costs.

  • 8/4/2019 Project Control Earned

    38/57

    Dr. Hesham A. Aziz 38

    Estimate at completion (EAC) :is the estimated total cost . It is the sum ofall direct and indirect costs to date plus authorized work remaining.

    EAC = ACWP + estimate to complete (ETC)and this is the updated estimate of the total cost.

    EAC can also be expressed in terms of the budget at completion BACas follows:

    EAC = BAC CV

    EAC can also be expressed in terms of the cost variance index (CVI) as

    EAC = (ACWP/BCWP) BAC

    Variance at completion (VAC) The variance at completion (VAC) is the

    difference between what should have cost (BAC) and what it isexpected to actually cost (EAC).

    VAC = BAC EAC

  • 8/4/2019 Project Control Earned

    39/57

    Dr. Hesham A. Aziz 39

  • 8/4/2019 Project Control Earned

    40/57

    Dr. Hesham A. Aziz 40

    Example EVA distribution

    CV = BCWPACWP = 75 00090 000 = 15 000 (i.e. a cost overrun of 15 000)SV = BCWPBCWS = 75 00050 000 = 25 000 (i.e. ahead of schedule by 25 000)

    TV = STWP ATWP = 3 months 2 month = 1 month (i.e. one month ahead of time schedule)

    CV ratio =BCWP/ACWP=75 000/90 000= 0.83

    SV ratio =BCWP/BCWS=75 000/50 000= 1.5

    TV ratio =STWP/ATWP=3/2= 1.5

  • 8/4/2019 Project Control Earned

    41/57

    Dr. Hesham A. Aziz 41

    Cost/Schedule Graph

  • 8/4/2019 Project Control Earned

    42/57

    Dr. Hesham A. Aziz 42

    Earned Value Review Exercise

  • 8/4/2019 Project Control Earned

    43/57

    Dr. Hesham A. Aziz 43

    Example budget and actual costs to end of month 4 Example planned and actual schedule performance

  • 8/4/2019 Project Control Earned

    44/57

    Dr. Hesham A. Aziz 44

    The critical ratio can often be used to trigger alarm bells

    if work performance falls below a certain level.

    The critical ratio is equivalent to (actual progress /

    scheduled progress) (budget cost / actual cost)

    A critical ratio of unity or more is good and means thatactual performance is better than planned performance.

    Conversely, a critical ratio less than

    unity is poor and is an indication of underperformance.

  • 8/4/2019 Project Control Earned

    45/57

    Dr. Hesham A. Aziz 45

    Typical variance envelope

    cost variance (CV) = BCWP ACWP. Therefore

    BCWP > ACWP: work performed has cost less.

    BCWP < ACWP: work performed has cost more.

    BCWP = ACWP: work on cost plan. .And

    schedule variance (SV) = BCWP BCWS. Therefore

    BCWP > BCWS: works ahead of programmed.

    BCWP < BCWS: works behind programmed.

    BCWP = BCWS: works on programmed.

    These values can also be shown as indices:

    Cost Variance Index (CVI) =BCWP/ACWP

    CVI > 1.0: good

    CVI < 1.0: bad

    CVI = 1.0: ok . And

    Schedule Variance Index (SVI)=BCWP/BCWS

    so that

    SVI > 1.0: good

    SVI < 1.0: bad

    SVI = 1.0: ok

  • 8/4/2019 Project Control Earned

    46/57

    Dr. Hesham A. Aziz 46

    CVI > 1.0, SVI > 1.0 Excellent: the project is under cost and ahead on

    programmed.

    CVI > 1.0, SVI = 1.0 Good: the project is under cost and is on schedule. CVI > 1.0, SVI < 1.0 Good/bad: the project is under cost but behind on

    programmed.

    CVI = 1.0, SVI > 1.0 Good: the project is on cost and ahead of programmed.

    CVI = 1.0, SVI = 1.0 Good: this scenario means that the project is on cost

    and on schedule.

    CVI = 1.0, SVI < 1.0 Bad: the project is on cost but is behind schedule

    CVI < 1.0, SVI > 1.0 Good: this scenario is probably caused by faster than expected

    working practices.

    CVI < 1.0, SVI = 1.0 Poor: the project has a cost overrun and is on programmed.

    CVI < 1.0, SVI < 1.0 Very bad: this is the worst case. The project is

    running over cost and behind on programmed.

  • 8/4/2019 Project Control Earned

    47/57

    Dr. Hesham A. Aziz 47

    Critical-ratio analysis

    Zone A: Take no action Zone B: Record and monitor

    Zone C: Act immediately Zone D: Emergency response required

    Zone A1: Observe and note Zone A2: Investigate and correct

  • 8/4/2019 Project Control Earned

    48/57

    Dr. Hesham A. Aziz 48

  • 8/4/2019 Project Control Earned

    49/57

    Dr. Hesham A. Aziz 49

  • 8/4/2019 Project Control Earned

    50/57

    Dr. Hesham A. Aziz 50

    WBS CAC Start Finish Target Target Scheduled Performed BCWS BCWP ACWP

    Code week week Cost Duration Complete%

    complete%

    A-37 A1 35 45 10,000 10 100 50 10000 5000 6000

    A-38 A2 35 50 12,000 15 66.67 50 8000 6000 6000

    A-39 A3 40 50 14,000 10 50 45 7000 6300 6500

    A-40 A4 42 50 8,000 8 37.5 45 3000 3600 4100

    A-41 A5 44 50 6,000 6 16.67 30 1000 1800 2300

    A-31 A11 40 50 12,000 10 50 60 6000 7200 7200

    A-32 A22 40 50 14,000 10 50 60 7000 8400 8500

    A-33 A33 40 50 18,000 10 50 50 9000 9000 8000

    A-34 A44 40 50 8,000 10 50 50 4000 4000 3000

    A-35 A55 42 55 6,000 13 23.077 50 1384.6 3000 3000

    A-36 A66 44 55 10,000 11 9.090 50 909.0 5000 5500

    Budget Cost calculations

    Time now = week 45

    Cost and Schedule Variance

  • 8/4/2019 Project Control Earned

    51/57

    Dr. Hesham A. Aziz 51

    WBS CAC ACWP BCWP BCWS CV SV Comments

    A-37 A1 6000 5000 10000 -1000 -5000 Very over budget and very late.

    A-38 A2 6000 6000 8000 0 -2000 On cost but very late

    A-39 A3 6500 6300 7000 -200 -700Over budget and late.

    A-40 A4 4100 3600 3000 -500 600 Over budget but ahead of schedule

    A-41 A5 2300 1800 1000 -500 800 Over budget but ahead of schedule

    A-31 A11 7200 7200 6000 0 1200 On cost and way ahead of schedule.

    A-32 A22 8500 8400 7000 -100 1400 Over cost but way ahead on schedule.

    A-33 A33 8000 9000 9000 1000 0 Under cost and on schedule.

    A-34 A44 3000 4000 4000 1000 0 Under cost and on schedule.

    A-35 A55 3000 3000 1385 0 1615 On cost and way ahead of schedule

    A-36 A66 5500 5000 909 -500 4091 Over cost but way ahead of schedule

    Total -800 2006 Over cost but well ahead.

    Cost and Schedule Variance.

    Example : Variance Analysis

  • 8/4/2019 Project Control Earned

    52/57

    Dr. Hesham A. Aziz 52

    Estimate at Completion. EAC = (ACWP/BCWP) * BACThen: EAC = (360/340) * 579,000 = 613,059

    Projected Overrun = 613,059 - 579,000 = 34,059

    Cost summary: CV%= CV/ BCWP (from Total row)Costs are running 5.88% above budget. This has been caused by wage rate increases.Schedule summary: SV%= SV/BCWS (from Total row)The project is 24.4% behind schedule as a result of packages 6 and 8 not having started yet.These packages have been delayed because of a lack of material.

    Corrective action report -----------------------------------------------------------------------------------------------------------------------------------------

    Example : Variance Analysis.

    Assume budget at completion = 579.000Task. Status ACWP BCWP BCWS CV SV CV% SV%

    1 Completed 100 100 100 0 0 0 0

    2 Completed 55 50 50 -5 0 -10 03 Completed 40 50 50 10 0 20 0

    4 Not started 0 0 70 0 -70 - -100

    5 Completed 140 90 90 -50 0 -55.56 0

    6 Not started 0 0 40 0 -40 - -100

    7 Started 25 50 50 25 0 50 0

    8 Not started 0 0 0 - -

    Total 360 340 450 -20 -110 -5.88 -24.44

  • 8/4/2019 Project Control Earned

    53/57

    Dr. Hesham A. Aziz 53

    Cost and schedule variance performance grid Example variance tracking

    CV and SV tracking and

    corrective monitoring

  • 8/4/2019 Project Control Earned

    54/57

    Dr. Hesham A. Aziz 54

    CVI and SVI figures for team 2 in weeks 14

    EVA values for the project as a whole

  • 8/4/2019 Project Control Earned

    55/57

    Dr. Hesham A. Aziz 55

    Scope Changes to a Baseline

    FIGURE 13.14

  • 8/4/2019 Project Control Earned

    56/57

    Dr. Hesham A. Aziz 56

    Other Control Issues

    Issues In Maintaining Control Of ProjectsIssues In Maintaining Control Of Projects

    Baseline ChangesBaseline Changes

    Contingency ReserveContingency Reserve

    Costs and Problems of Data AcquisitionCosts and Problems of Data Acquisition

    Scope CreepScope Creep

    Managing the Portfolio of ProjectsManaging the Portfolio of Projects

  • 8/4/2019 Project Control Earned

    57/57

    D H h A A i 57