Upload
waleed-tawfeek
View
220
Download
0
Embed Size (px)
Citation preview
8/4/2019 Project Control Earned
1/57
Dr. Hesham A. Aziz 1
Project Control
American University in Cairo
Egypt
Presented By
Dr. Hesham A. Aziz
Project Cost Planning and Control
8/4/2019 Project Control Earned
2/57
Dr. Hesham A. Aziz 2
8/4/2019 Project Control Earned
3/57
Dr. Hesham A. Aziz 3
Control The process of comparing actual performance
against plan to identify deviations, evaluate courses
of action, and take appropriate corrective action.
Project Control Steps1. Setting a baseline plan.
2. Measuring progress and performance.
3. Comparing plan against actual.4. Taking actions
The Project Control Process
8/4/2019 Project Control Earned
4/57
Dr. Hesham A. Aziz 4
Project Control
Indirect &Overhead
costs
Changeorders
Lump-sumContract
costs
Project Plan, Schedule,Budget, Quality
Safety
Other
Contractcosts
Materialcosts
Equipment
costs
Laborcosts
ProgressReports
Projectplanning
Design
Collecting information for Project Control
8/4/2019 Project Control Earned
5/57
Dr. Hesham A. Aziz 5
A typical information filter
Top management / executive
Project Manger
Project team
Updated priceOn completion
Project completiondate
Money expendedSo far
Project completionprice
Programmedstatus
WeeklySite
reports
Anticipatedclaims
ChangesIn scope
Future problemareas
Site instructionsAnd variations
Abortivework
Percentage
completion
Monthlyvaluations
MACROLEVEL
MESOLEVEL
MICROLEVEL
8/4/2019 Project Control Earned
6/57
Dr. Hesham A. Aziz 6
Information System Structure What data are collected?
Current status of project (schedule and cost)
Remaining cost to compete project
Date that project will be complete
Potential problems to be addressed now
Out-of-control activities requiring intervention Cost and/or schedule overruns and the reasons for
them
Forecast of overruns at time of project completion
Project Monitoring System for Control
8/4/2019 Project Control Earned
7/57
Dr. Hesham A. Aziz 7
Information System Structure (contd) Collecting data and analysis
Who will collect project data?
How will data be collected?
When will the data be collected?
Who will compile and analyze the data?
Reports and reporting
Who will receive the reports? How will the reports be transmitted?
When will the reports be distributed?
Project Monitoring System (contd)
8/4/2019 Project Control Earned
8/57
Dr. Hesham A. Aziz 8
Progress since last report Current status of project
Schedule
Cost
Scope Cumulative trends
Problems and issues since last report
Actions and resolution of earlier problems
New variances and problems identified
Corrective action planned
Project Progress Report Format
8/4/2019 Project Control Earned
9/57
Dr. Hesham A. Aziz 9
Time-Phase Baseline Plan
Corrects the failure of most monitoring systems toconnect a projects actual performance to its
schedule and forecast budget. Systems that measure only cost variances do not
identify resource and project cost problemsassociated with falling behind or progressing
ahead of schedule.
Disparity Among Monitoring Systems
8/4/2019 Project Control Earned
10/57
Dr. Hesham A. Aziz 10
Earned Value Cost/Schedule System
An integrated project management systembased on the earned value concept that uses atime-phased budget baseline to compare actual
and planned schedule and costs.
8/4/2019 Project Control Earned
11/57
Dr. Hesham A. Aziz 11
Baseline Data Relationships
8/4/2019 Project Control Earned
12/57
Dr. Hesham A. Aziz 12
Project Management System Overview
8/4/2019 Project Control Earned
13/57
Dr. Hesham A. Aziz 13
Integration of WBSand OBS
8/4/2019 Project Control Earned
14/57
Dr. Hesham A. Aziz 14
Direct Labor Budget
Rollup (000)
8/4/2019 Project Control Earned
15/57
Dr. Hesham A. Aziz 15
Baseline andTracking Gantt
Charts
8/4/2019 Project Control Earned
16/57
Dr. Hesham A. Aziz 16
Project Schedule Control Chart
8/4/2019 Project Control Earned
17/57
Dr. Hesham A. Aziz 17
8/4/2019 Project Control Earned
18/57
Dr. Hesham A. Aziz 18
8/4/2019 Project Control Earned
19/57
Dr. Hesham A. Aziz 19
Relationships Between Time and Work
* Overall design effort a work/time curve can be developed.
Example Illustrative Weight Multipliers for Design Work_________________________________________
Weight Project
Design Work Multiplier Timing
_______________________________________________
Review backup material 0.05 0% - 10%
Design calculations 0.10 10% - 25%
Initial drafting 0.25 15% - 45%
Final calculations 0.20 35% - 60%
Production drawings 0.30 50% - 90%
Drawing approval 0.10 90% - 100%
_________
1.00________________________________________________
The slope of each graph is the ratio of the weight multiplier to the timerequired for the work to be performed.
8/4/2019 Project Control Earned
20/57
Dr. Hesham A. Aziz 20
Work / Time Relationship (Design Work)
Over Laps
8/4/2019 Project Control Earned
21/57
Dr. Hesham A. Aziz 21
Over Laps
8/4/2019 Project Control Earned
22/57
Dr. Hesham A. Aziz 22
Integrated Cost / Schedule / Work Graph.
8/4/2019 Project Control Earned
23/57
Dr. Hesham A. Aziz 23
Over Cost and Behind Schedule
1
2
3
8/4/2019 Project Control Earned
24/57
Dr. Hesham A. Aziz 24
Under Cost and Behind Schedule
1
2 3
Under Cost and Ahead of Sched le
8/4/2019 Project Control Earned
25/57
Dr. Hesham A. Aziz 25
Under Cost and Ahead of Schedule
1
23
8/4/2019 Project Control Earned
26/57
Dr. Hesham A. Aziz 26
Over Cost and Ahead of Schedule
1
23
8/4/2019 Project Control Earned
27/57
Dr. Hesham A. Aziz 27
Earned Value Management
Earned Value Management is a methodology used to measureand communicate the real physical progress of a plan taking intoaccount the work complete, the time taken and the costs incurred tocomplete that work.
Earned Value helps evaluate and control risk by measuring
the progress in monetary terms.
By taking a snap-shot of the projected plan and calculatingthe Earned Value metrics we can compare the planned with the actualand make a subjective assessment of the progress.
By extrapolating the curves and further calculation allowsestimate the costs to completion and the probable completion date.
The basics of Earned Value can best be shown on theubiquitous 'S-Curve'.
8/4/2019 Project Control Earned
28/57
Dr. Hesham A. Aziz 28
Earned value analysis makes use of the followingvariables:
Actual cost of the works performed (ACWP); Budgeted cost of the works performed (BCWP); Budgeted costs of the works specified (BCWS); Scheduled time for work performed (STWP); Actual time for work performed (ATWP);
Cost Variance (CV); Schedule variance (SV); Budget at completion (BAC); Estimate at completion (EAC); Variance at completion (VAC).
8/4/2019 Project Control Earned
29/57
Dr. Hesham A. Aziz 29
Total work package budgeted cost = 1 000 000The EVA analysis is taken up to week 6 (week 6 is time now).
The actual progress or works performed is 70 per cent. This means:Budgeted cost of the works performed (BCWP) = 1 000 000 70% = 700 000Actual cost to date = 750 000Work scheduled to date = 60%Budgeted cost of the works scheduled (BCWS) = 1 000 000 60% = 600 000
Earned value analysis (EVA)
8/4/2019 Project Control Earned
30/57
Dr. Hesham A. Aziz 30
Sample SV and CV values
Position at week 6
8/4/2019 Project Control Earned
31/57
Dr. Hesham A. Aziz 31
Position at week 7
Comparative positions weeks 6 and 7
8/4/2019 Project Control Earned
32/57
Dr. Hesham A. Aziz 32
8/4/2019 Project Control Earned
33/57
Dr. Hesham A. Aziz 33
8/4/2019 Project Control Earned
34/57
Dr. Hesham A. Aziz 34
8/4/2019 Project Control Earned
35/57
Dr. Hesham A. Aziz 35
EVM: A Simple Concept
Time
Actual Cost
EarnedValue
$
Time Now
Schedule
Delay
}
Estimate atCompletion
}Risk
Planned Value
Th i f l ti (VAC) i th diff b t th l d
8/4/2019 Project Control Earned
36/57
Dr. Hesham A. Aziz 36
The variance of completion (VAC) is the difference between the plannedand actual cost.
The cost variance is the result of a comparison of how much the work hascost in comparison with what it was budgeted to cost, both in relation
to works actually completed.
Schedule variance (SV) is the difference between budgeted cost for theworks completed and performed and the budgeted cost of the worksscheduled
The budget at completion (BAC) is the sum of all the individual budgets(BCWS) that make up . It is sometimes known as the baseline.
The estimate at completion (EAC) is the estimated total cost . It is the sumof all direct and indirect costs to date plus authorized work remaining.The EAC can also be expressed in terms of a revised estimate.
The cost accounting process of the PCCS involves looking at costvariance (CV) and schedule variance (SV) in order to assess theperformance of individual packages and groups of packages. This canbe done in several ways. The two most common are by direct evaluationof the variances themselves or by conversion of the variances toindices.
8/4/2019 Project Control Earned
37/57
Dr. Hesham A. Aziz 37
Scheduled time for work performed (STWP) This is the estimated timerequired to perform a defined amount of work.
Actual time for work performed (ATWP) This is the actual time taken to
perform a defined amount of work.
Cost Variance (CV) The cost variance is the budgeted cost of workperformed (BCWP) minus the actual cost of work performed (ACWP).This is normally abbreviated to the formula:
CV = BCWP ACWPCost variance is therefore a comparison of how much the work has cost inrelation to what it was budgeted to cost, both figures being in relation toworks actually completed.
Schedule variance (SV) The schedule variance is the difference between
budgeted cost for the works performed (BCWP) and the budgeted cost ofthe works scheduled (BCWS). This is normally abbreviated to the formula:
SV = BCWP BCWSSchedule variance is therefore a measure of the performance of the worksin relation to budgeted costs.
8/4/2019 Project Control Earned
38/57
Dr. Hesham A. Aziz 38
Estimate at completion (EAC) :is the estimated total cost . It is the sum ofall direct and indirect costs to date plus authorized work remaining.
EAC = ACWP + estimate to complete (ETC)and this is the updated estimate of the total cost.
EAC can also be expressed in terms of the budget at completion BACas follows:
EAC = BAC CV
EAC can also be expressed in terms of the cost variance index (CVI) as
EAC = (ACWP/BCWP) BAC
Variance at completion (VAC) The variance at completion (VAC) is the
difference between what should have cost (BAC) and what it isexpected to actually cost (EAC).
VAC = BAC EAC
8/4/2019 Project Control Earned
39/57
Dr. Hesham A. Aziz 39
8/4/2019 Project Control Earned
40/57
Dr. Hesham A. Aziz 40
Example EVA distribution
CV = BCWPACWP = 75 00090 000 = 15 000 (i.e. a cost overrun of 15 000)SV = BCWPBCWS = 75 00050 000 = 25 000 (i.e. ahead of schedule by 25 000)
TV = STWP ATWP = 3 months 2 month = 1 month (i.e. one month ahead of time schedule)
CV ratio =BCWP/ACWP=75 000/90 000= 0.83
SV ratio =BCWP/BCWS=75 000/50 000= 1.5
TV ratio =STWP/ATWP=3/2= 1.5
8/4/2019 Project Control Earned
41/57
Dr. Hesham A. Aziz 41
Cost/Schedule Graph
8/4/2019 Project Control Earned
42/57
Dr. Hesham A. Aziz 42
Earned Value Review Exercise
8/4/2019 Project Control Earned
43/57
Dr. Hesham A. Aziz 43
Example budget and actual costs to end of month 4 Example planned and actual schedule performance
8/4/2019 Project Control Earned
44/57
Dr. Hesham A. Aziz 44
The critical ratio can often be used to trigger alarm bells
if work performance falls below a certain level.
The critical ratio is equivalent to (actual progress /
scheduled progress) (budget cost / actual cost)
A critical ratio of unity or more is good and means thatactual performance is better than planned performance.
Conversely, a critical ratio less than
unity is poor and is an indication of underperformance.
8/4/2019 Project Control Earned
45/57
Dr. Hesham A. Aziz 45
Typical variance envelope
cost variance (CV) = BCWP ACWP. Therefore
BCWP > ACWP: work performed has cost less.
BCWP < ACWP: work performed has cost more.
BCWP = ACWP: work on cost plan. .And
schedule variance (SV) = BCWP BCWS. Therefore
BCWP > BCWS: works ahead of programmed.
BCWP < BCWS: works behind programmed.
BCWP = BCWS: works on programmed.
These values can also be shown as indices:
Cost Variance Index (CVI) =BCWP/ACWP
CVI > 1.0: good
CVI < 1.0: bad
CVI = 1.0: ok . And
Schedule Variance Index (SVI)=BCWP/BCWS
so that
SVI > 1.0: good
SVI < 1.0: bad
SVI = 1.0: ok
8/4/2019 Project Control Earned
46/57
Dr. Hesham A. Aziz 46
CVI > 1.0, SVI > 1.0 Excellent: the project is under cost and ahead on
programmed.
CVI > 1.0, SVI = 1.0 Good: the project is under cost and is on schedule. CVI > 1.0, SVI < 1.0 Good/bad: the project is under cost but behind on
programmed.
CVI = 1.0, SVI > 1.0 Good: the project is on cost and ahead of programmed.
CVI = 1.0, SVI = 1.0 Good: this scenario means that the project is on cost
and on schedule.
CVI = 1.0, SVI < 1.0 Bad: the project is on cost but is behind schedule
CVI < 1.0, SVI > 1.0 Good: this scenario is probably caused by faster than expected
working practices.
CVI < 1.0, SVI = 1.0 Poor: the project has a cost overrun and is on programmed.
CVI < 1.0, SVI < 1.0 Very bad: this is the worst case. The project is
running over cost and behind on programmed.
8/4/2019 Project Control Earned
47/57
Dr. Hesham A. Aziz 47
Critical-ratio analysis
Zone A: Take no action Zone B: Record and monitor
Zone C: Act immediately Zone D: Emergency response required
Zone A1: Observe and note Zone A2: Investigate and correct
8/4/2019 Project Control Earned
48/57
Dr. Hesham A. Aziz 48
8/4/2019 Project Control Earned
49/57
Dr. Hesham A. Aziz 49
8/4/2019 Project Control Earned
50/57
Dr. Hesham A. Aziz 50
WBS CAC Start Finish Target Target Scheduled Performed BCWS BCWP ACWP
Code week week Cost Duration Complete%
complete%
A-37 A1 35 45 10,000 10 100 50 10000 5000 6000
A-38 A2 35 50 12,000 15 66.67 50 8000 6000 6000
A-39 A3 40 50 14,000 10 50 45 7000 6300 6500
A-40 A4 42 50 8,000 8 37.5 45 3000 3600 4100
A-41 A5 44 50 6,000 6 16.67 30 1000 1800 2300
A-31 A11 40 50 12,000 10 50 60 6000 7200 7200
A-32 A22 40 50 14,000 10 50 60 7000 8400 8500
A-33 A33 40 50 18,000 10 50 50 9000 9000 8000
A-34 A44 40 50 8,000 10 50 50 4000 4000 3000
A-35 A55 42 55 6,000 13 23.077 50 1384.6 3000 3000
A-36 A66 44 55 10,000 11 9.090 50 909.0 5000 5500
Budget Cost calculations
Time now = week 45
Cost and Schedule Variance
8/4/2019 Project Control Earned
51/57
Dr. Hesham A. Aziz 51
WBS CAC ACWP BCWP BCWS CV SV Comments
A-37 A1 6000 5000 10000 -1000 -5000 Very over budget and very late.
A-38 A2 6000 6000 8000 0 -2000 On cost but very late
A-39 A3 6500 6300 7000 -200 -700Over budget and late.
A-40 A4 4100 3600 3000 -500 600 Over budget but ahead of schedule
A-41 A5 2300 1800 1000 -500 800 Over budget but ahead of schedule
A-31 A11 7200 7200 6000 0 1200 On cost and way ahead of schedule.
A-32 A22 8500 8400 7000 -100 1400 Over cost but way ahead on schedule.
A-33 A33 8000 9000 9000 1000 0 Under cost and on schedule.
A-34 A44 3000 4000 4000 1000 0 Under cost and on schedule.
A-35 A55 3000 3000 1385 0 1615 On cost and way ahead of schedule
A-36 A66 5500 5000 909 -500 4091 Over cost but way ahead of schedule
Total -800 2006 Over cost but well ahead.
Cost and Schedule Variance.
Example : Variance Analysis
8/4/2019 Project Control Earned
52/57
Dr. Hesham A. Aziz 52
Estimate at Completion. EAC = (ACWP/BCWP) * BACThen: EAC = (360/340) * 579,000 = 613,059
Projected Overrun = 613,059 - 579,000 = 34,059
Cost summary: CV%= CV/ BCWP (from Total row)Costs are running 5.88% above budget. This has been caused by wage rate increases.Schedule summary: SV%= SV/BCWS (from Total row)The project is 24.4% behind schedule as a result of packages 6 and 8 not having started yet.These packages have been delayed because of a lack of material.
Corrective action report -----------------------------------------------------------------------------------------------------------------------------------------
Example : Variance Analysis.
Assume budget at completion = 579.000Task. Status ACWP BCWP BCWS CV SV CV% SV%
1 Completed 100 100 100 0 0 0 0
2 Completed 55 50 50 -5 0 -10 03 Completed 40 50 50 10 0 20 0
4 Not started 0 0 70 0 -70 - -100
5 Completed 140 90 90 -50 0 -55.56 0
6 Not started 0 0 40 0 -40 - -100
7 Started 25 50 50 25 0 50 0
8 Not started 0 0 0 - -
Total 360 340 450 -20 -110 -5.88 -24.44
8/4/2019 Project Control Earned
53/57
Dr. Hesham A. Aziz 53
Cost and schedule variance performance grid Example variance tracking
CV and SV tracking and
corrective monitoring
8/4/2019 Project Control Earned
54/57
Dr. Hesham A. Aziz 54
CVI and SVI figures for team 2 in weeks 14
EVA values for the project as a whole
8/4/2019 Project Control Earned
55/57
Dr. Hesham A. Aziz 55
Scope Changes to a Baseline
FIGURE 13.14
8/4/2019 Project Control Earned
56/57
Dr. Hesham A. Aziz 56
Other Control Issues
Issues In Maintaining Control Of ProjectsIssues In Maintaining Control Of Projects
Baseline ChangesBaseline Changes
Contingency ReserveContingency Reserve
Costs and Problems of Data AcquisitionCosts and Problems of Data Acquisition
Scope CreepScope Creep
Managing the Portfolio of ProjectsManaging the Portfolio of Projects
8/4/2019 Project Control Earned
57/57
D H h A A i 57