Upload
others
View
6
Download
1
Embed Size (px)
Citation preview
Ibis House, Regent ParkSummerleys Road Princes RisboroughBuckinghamshire, HP27 9LE
Association for Project Management
Telephone 0845 458 1944International +44 (0)1844 271640Facsimile +44 (0)1844 274509
Email [email protected] www.apm.org.uk
The Earned Value Management Compass
C
M
Y
CM
MY
CY
CMY
K
Earned value book cover.pdf 13/10/10 10:27:38
The Earned ValueManagement Compass
A product of the Association for Project ManagementEarned Value Management Specific Interest Group (SIG)
Association for Project Management
Ibis House, Regent Park
Summerleys Road, Princes Risborough
Buckinghamshire
HP27 9LE
© Association for Project Management 2010
All rights reserved. No part of this publication may be reproduced, stored in a
retrieval system or transmitted, in any from or by any means, without the express
permission in writing of the Chief Executive of the Association for Project
Management. Within the United Kingdom exceptions are allowed in respect of
fair dealing for the purpose of research or private study, or criticism or review,
as permitted under the Copyright, Designs and Patents Act, 1988, and its
amendments, or in the case of reprographic reproduction in accordance
with the licences issued by the appropriate reprographic rights organisations,
such as the Copyright Licensing Agency. Enquiries concerning reproduction
outside these terms and in other countries should be sent to the
Rights Department of the Association for Project
Management at the address above.
Readers are responsible for the correct application of the information in this
publication and its conformity with all relevant legal and commercial obligations.
The Association for Project Management cannot accept legal responsibility or
liability for any errors or omissions in this publication or the consequences thereof.
All registered trademarks are hereby acknowledged and the publisher
makes no claim to these trademarks.
British Library Cataloguing in Publication Data is available
ISBN 10: 1-903494-33-8
ISBN 13: 978-1-903494-33-2
Cover design by Fountainhead Creative Consultants
Typeset by RefineCatch Limited, Bungay, Suffolk
ContentsForeword iv
Acknowledgements v
The EVM compass 1Introduction 1Fundamental concepts 1How is the compass used for assessment? 2What are the benefits? 2Assessment – the general process 3Assessment – presenting the results 5Implementation roadmap – EVM process maturity stages 7
Guidance information 9Introduction 9EVM foundations 9EVM basics 10Execute EVM 19EVM goal 25
EVM compass questions 26Conclusion 36Annex A – terminology and glossary 37Annex B – related documents 43
iii
ForewordMore and more companies are saying that they use earned value (EV) as partof their project control.However, use of earned value can run from full organisational US ANSI 748
accreditation to recognising that there is an earned value button available inyour personal copy of Microsoft® Project. This is potentially confusing and there is a very high risk of misunder-
standing and disappointed expectations between stakeholders.The APM Earned Value Specific Interest Group (SIG) recognises that EV
principles and the benefits they can bring to project control may be appliedin a variety of ways. In some cases the principles are being applied withoutknowing that they are part of earned value. The key is to understand howand where earned value principles are being applied and to encourage them.The earned value management (EVM) compass has been developed so that
a clear picture can be obtained of how earned value is being used currently.An assessment can then be made of how well that meets the actual require-ment for earned value; whether that is to meet a standard, a customer or aninternal organisational requirement. A route map to close the gap between asis and to be can then be plotted planned and managed.Now, when it is stated that earned value is in use, the compass can provide
a way for all involved to have a common understanding of what that reallymeans.The compass can be used in a variety of project control situations (not just
earned value). Here are some suggestions:
• Maturity model.• Audit tool.• Assurance tool.• Management tool.• As part of an external team’s review or as a personal self-assessment
exercise.
It is flexible. Please use it and let the SIG know how you get on.
Steve WakeChairman, APM Earned Value Specific Interest Group
iv
AcknowledgementsThe EVM compass was developed by a subgroup of the APM Earned ValueSpecific Interest Group (SIG), with contributions from Steve Wake (SIG chair-man), Mike Burke, Ewan Glen, John Flaherty, Paul Kidston, Simon Springate,Alan Bye, John Cox, Mick Higgins and Alex Davis. Review and testing of the compass has been completed by the wider APM
Earned Value SIG membership and cross-industry volunteers and we areextremely grateful to all the individuals who took part in this.
v
1
The EVM CompassINTRODUCTION
How do you measure an organisation’s capability in implementing andapplying earned value management (EVM) across its projects? For example,what is the subset of the Earned Value Management: APM Guidelines (orANSI/EIA 748 requirements) that are sufficient to initiate an EVM system?How do you know your potential alliance partner or subcontractor has acompetent EVM system? How do you know whether its constituent ele-ments such as scheduling, cost collection and adequate supplier project con-trol are in place? The EVM compass maturity model provides a step-by-step means to under-
standing the as is EVM condition and referencing it against a to be condition.The model uses a common framework and can be used for the assessment ofa single project or to benchmark and compare the relative strengths of vari-ous projects across an organisation. It gives EVM system reviewers a consis-tent method of assessing projects.This document is intended to be used in conjunction with the Earned Value
Management: APM Guidelines.
FUNDAMENTAL CONCEPTS
The EVM compass is intended to provide a defined means of establishingand improving project control capability. The EVM compass is intended tosupport projects or organisations by improving their project control andEVM processes. The project control processes should be well understood throughout a
mature project or organisation, usually through documentation and training.The processes should be continually monitored and improved. As a projector organisation gains in EVM process maturity, it formalises its processes viapolicies, standards, and organisational structures. It also builds an infra-structure and a corporate culture that support the methods, practices andprocedures of the project/organisation so they continue to function longafter those who originally defined them have moved on.Working within this environment, the fundamental concepts of the EVM
compass are that it:
• provides a comprehensive and systematic review of project EVMmaturity;
• uses a common framework that supports either the assessment of a singleproject or allows organisations to benchmark and compare the relativestrengths of their various projects, identifying systemic problems andallowing sharing of best practice;
The Earned Value Management Compass
2
• provides a defined means to support projects in establishing andimproving project control capability;
• allows projects to reference the as is EVM condition with the to becondition;
• gives EVM system reviewers a consistent method of assessing projects thatcan be repeated over a period of time, recognising that target performancelevels may change;
• allows organisations to establish their own target performance level(rather than define it for them);
• is open to a degree of customisation such that its application can betailored to the needs of an individual organisation, whether this is throughrevisions to the criteria or the application of weightings to the criteria.
HOW IS THE COMPASS USED FOR ASSESSMENT?
In the context of this framework, the EVM compass is a comprehensive andsystematic review of a project’s EVM maturity. This can be used to aidprocess improvement by identifying shortfalls against the target standard.The review is conducted using a maturity grid that outlines performance
levels against 25 attributes of an EVM system. A target standard should beestablished for the project or projects within an organisation at the outset andthe maturity at the time of review related to this target standard. The targetstandard to be achieved will typically be agreed with a customer of the proj-ect or within an organisation. It is for individual projects/organisations to settheir target standards. However, customers who require full ANSI 748 com-pliance are unlikely to be satisfied with maturity below level 3. When using the EVM compass, it is often beneficial to take a realistic and
pragmatic approach. Where an organisation doesn’t implement full EVM, asoutlined in ANSI 748, then the maturity level achieved will be less than ifthey did, with it being likely that several of the products identified will notbe available. This may be appropriate for that organisation.The assessment process allows the project to clearly discern its strengths
and weaknesses, and should culminate in planned improvement actionswhich are then monitored for progress.The frequency of reviews is a decision for the project or organisation.
WHAT ARE THE BENEFITS?
Using the EVM compass maturity framework for assessment should delivera range of benefits, including:
• identifying your organisation’s strengths and weaknesses;• providing a highly structured, fact-based approach to identifying and
assessing your project and measuring progress periodically;
The Earned Value Management Compass
3
• creating a common language and conceptual framework for the way youmanage and improve EVM on your project and, if applicable, projectswithin your organisation;
• educating people in your project on the fundamental elements of EVM andhow they relate to their roles and responsibilities;
• involving people at all levels in process improvement;• ranking EVM project maturity within an organisation or across the supply
chain;• identifying and allowing the sharing of best practice across projects within
an organisation;• using it to assess and present the findings from a variety of EVM reviews
in a format that is easy to understand;• facilitating comparisons with other projects;• supporting the development of your business plan and strategy.
ASSESSMENT – THE GENERAL PROCESS
There is no single right way to perform the assessment using the maturitygrid; the primary factors that determine the right approach for your organi-sation are its current culture and the desired outcomes from the assess-ment exercise. Different approaches deliver different benefits. Whicheverapproach is used, the key point to remember is that assessment is about thecontinuous improvement of your project. Greatest value may be achieved from an assessment if it involves someone
who has a working knowledge of the implementation and operation of anEVM system. This ensures that the assessment can be completed with anunderstanding of the nuances between the different maturity levels for eachof the attributes that are scored.The assessment can be performed in a number of different ways:
• Self assessment – from within the project.• Peer assessment – by other teams within the organisation.• Independent assessment – by reviewers external to the project.
The steps involved in the assessment are outlined in the figure below.
Form team
Assess projectagainst the
maturity levelsdescribed in
matrix
Develop actionplan
Re-assess tomeasure
improvement
Figure 1: Four-step assessment method
The Earned Value Management Compass
4
While the assessment is valuable, the most critical phase of the process isaction planning and implementation. Having completed the diagnosticphase, you may wish to consider your response to the following questions:
• What identified strengths must we maintain to maximum effect?• What identified strengths do we develop and exploit even further?• What identified areas for improvement do we acknowledge, but not
pursue because they are not key to our business?• What identified areas for improvement do we acknowledge and are vital
for us to address?• How are we going to monitor progress against the agreed improvement
actions?
The actions that are identified should be captured in a plan, with clearlydefined responsibilities and timescales for their implementation. To helpwith the prioritisation of the actions a grid such as that shown overleaf maybe of benefit.
0
1
2
3
4
5 Good practiceto share
Somethingto learn
1 2 3 4
Leve
l
Gap (target minus current level)
Figure 2: Action prioritisation
The grid may be used by taking your current score and identifying whereyou sit on the vertical axis. By then taking your current score away from yourtarget score you may identify your position on the horizontal axis. As theshade of blue darkens, the priority of actions increases.Where a project scores predominately light blue there is potential to share
learning with other projects in the organisation that may not be performing so well.
The Earned Value Management Compass
5
ASSESSMENT – PRESENTING THE RESULTS
The presentation of results from the assessment may be tailored to meet theneeds of specific organisations. As a general rule, presentation of the full setof results for the 25 criteria lends itself to use by project control staff. Sum-marised results, such as at the level of maturity stages, tend to be moreappropriate for presentation to management staff.
Full set of results
Figure 3 provides examples of two presentation formats, (a) radar plot and(b) bar chart, for the full set of results. While detailed, they allow easy com-parison of current performance against the target performance level. Byincluding the results of assessments from multiple projects it becomes possi-ble with the bar chart to identify systemic problems that can be addressed ifdesired.
Figure 3(a): Presentation of detailed results (radar plot)
5
4
3
2
1
0
1. Earned valuemanagement competencies
2. Sponsorship3. Project level authorisation
4. Work definition5. Detail workauthorisation and budgetassignment
6. Responsibility andaccountability
7. Materialmanagement
8. Basis of estimate
9. Managementreserve (cost and schedule)
10. Supplier budget integration
11. Schedule structure and content
12. Schedule resource allocation13. Objectivity of EV progress assessment
16. Actual cost collection
17. Scheduleprogress and control
18. Data integrity
19. Estimate atcomplete
20. Suppliermanagement and
reporting
21. Risk and opportunitymanagement
22. Baseline changemanagement
23. Senior management usage
24. Customerinvolvement
25. EVM as adecision support tool
14. Supplier scheduleintegration
15. Process documentationand consistency of application
As isTo be
Summarised resultsFigure 4 provides an example of a summarised results plot. Presenting theresults of assessments conducted across numerous projects becomes simplerat this level and differences between current and target performance levelsmay be highlighted.
The Earned Value Management Compass
6
1. Earned value management competencies2. Sponsorship
3. Project level authorisation4. Work definition
5. Detail work authorisation and budget assignment6. Responsibility and accountability
7. Material management8. Basis of estimate
9. Management reserve (cost and schedule)10. Supplier budget integration
11. Schedule structure and content12. Schedule resource allocation
13. Objectivity of EV progress assessment14. Supplier schedule integration
15. Process documentation and consistency of application16. Actual cost collection
17. Schedule progress and control18. Data integrity
19. Estimate at complete20. Supplier management and reporting
21. Risk and opportunity management22. Baseline change management
23. Senior management usage24. Customer involvement
25. EVM as a decision support tool
EVM maturity assessment
To be
As is
0 1 2 3 4 5
Figure 3(b): Bar chart
The Earned Value Management Compass
7
IMPLEMENTATION ROADMAP – EVM PROCESSMATURITY STAGES
The structure of the EVM compass aims to reflect the stages that a project willpass through when implementing an EVM system (Figure 5). An organisa-tion that has little experience of establishing an EVM system should focus onthe stages in the order outlined below to achieve the greatest benefit. Wherean organisation has more experience of using EVM it is likely that the initialstages will be established and focus may be on the latter ones. The stages are:
1. EVM foundations. The first step in establishing an effective EVM systemis to establish the correct foundations. Without appropriate sponsorshipand the development of the correct competencies EVM systems are morelikely to fail.
2. EVM basics. The attributes within the EVM basics stage form the buildingblocks of an effective EVM system. This maturity stage is concerned withensuring that these meet the needs of the project, formally controlling thescope of work and associated delivery schedule and budget within asystem that has defined processes.
3. Execute EVM. Having established the foundations and performance base-line it is possible to start to manage using EVM. This maturity stage is
4
5
Project A as is
Project B as isOrganisation to be
3
2
1
0
EVM fo
undations
EVM bas
ics - o
rgan
isatio
nEVM
basics
- budget
EVM bas
ics - p
roce
ssExecu
te EVM
EVM goal
EVM bas
ics - s
chedule
manag
ement
Figure 4: Presentation of summarised results (bar chart only)
The Earned Value Management Compass
8
concerned with assessing the effectiveness of the processes followedthough the delivery stage of a project.
4. EVM goal. The ultimate aim of an EVM system is to establish theinformation generated by the system as a decision support tool.
Building up from the foundations it provides a logical path for EVM imple-mentation. The compass measures the maturity of the implementation attrib-utes as a project establishes the basics, before starting to execute EVM andfinally using EVM as a decision support tool (the goal). The attributes within each of the stages are outlined in detail in the guid-
ance text that follows.
Figure 5: The four maturity stages of the EVM compass
EVM as decisionsupport tool
Actual costcollection
Data integrityEstimate at completion
Senior managementusage
Supplier management and reporting
Customerinvolvement
Schedule progressand control
EVM goal
Execute EVM
EVM basics
EVM foundations
Baseli
ne ch
ange
man
agem
ent Risk and opportunity m
anagement
Organisation Budget Schedule Tools and processes
Project levelauthorisation
Workdefinition
Responsibility andaccountability
Materialmanagement
Detail work authorisation andbudget assignment
Basis of estimate
Managerial reserve(cost and schedule)
Supplier budgetintegration
Processdocumentationand consistencyof application
Schedule structureand content
Schedule resourceallocation
Objectivity of EVprogress assessment
Supplier scheduleintegration
Sponsorship
EVM competencies (including education, training, experience and CPD)
Time
9
Guidance informationINTRODUCTION
This section aims to provide guidance to support the use of the EVM com-pass maturity assessment tables. For each of the four stages the followingexplanatory text is provided for the underpinning attributes. This text out-lines:
• The aim – the objective of the attribute;• The reason – why the attribute is important;• Guidance information – additional information to assist users who are less
familiar with the implementation and utilisation of earned valuemanagement systems.
EVM FOUNDATIONS
Attribute 1 – earned value management competencies
Aim:
• To ensure that the project team has the appropriate competencies toimplement and manage using an earned value management system.
Reason:
• EVM is often a new process to a project or business and requiresappropriate training and education for its implementation to be a success.Implementation and operation of an EVM system can be a complexexercise and can be facilitated by the use of experienced resources.
Guidance information:
It is important that training and support are provided during EVM imple-mentation and that on-going training is also available. The team membersshould be trained in EVM techniques appropriate to their role within theproject team. Implementation of EVM is best facilitated by using resources with previous
implementation experience. Learned experience from other projects is also avaluable source of information.
The Earned Value Management Compass
10
Attribute 2 – sponsorship
Aim:
• To ensure that there is clear and visible EVM sponsorship for the projectfrom within the delivery organisation.
Reason:
• It is important that the implementation and execution of EVM is sponsoredat an appropriate level within the project/organisation.
Guidance information:
The introduction of EVM may cause the need for a significant culturalchange, which must be led with senior management support and sponsor-ship. This should be communicated throughout the entire project structure.The understanding and commitment of the entire project team and organi-sational functional areas is vital for success, and hence there is a need forcomprehensive communication outlining the nature of EVM, the aim andobjectives of the implementation.
EVM BASICS
Attribute 3 – project level authorisation
Aim:
• To ensure that the project has been given appropriate approval andauthority to proceed.
Reason:
• The project should be formally approved by the responsible organisation.This approval should indicate the overall budget available and assigndelivery responsibility/authority onto the key individuals within theproject team. It should also indicate the sponsor within the organisation.
Guidance information:
Prior to commencement of work on the project, the approval authorityshould formally sanction the project to proceed and assign the required levelof responsibility, authority and accountability (RAA) to the project manager.To further delegate this RAA to the team delivering the project, a responsi-bility assignment matrix (RAM) is used.The RAM process is principally concerned with defining the work to be
done, as a work breakdown structure (WBS), and assigning that work to
The Earned Value Management Compass
11
specific parts of the project’s organisation via the organisational breakdownstructure (OBS). The WBS and OBS should be aligned and combined to pro-duce a concise RAM, an example of which is shown below.
CA
CA
CA
CA
Assignment of asingle work elementto a single team allows you to roll up the costs in either direction.
Workbreakdownstructure(WBS)
Organisationbreakdown
structure(OBS)
CA = Control account
Figure 6: Example responsibility assignment matrix
Within the RAM, each element of work is assigned to an organisational ele-ment and a single person within the organisation. This is regarded as an indi-vidual control account (CA). Each control account will be owned by a controlaccount manager (CAM) and will contain lower level, detailed work pack-ages (or near term work) and also summarised planning packages (or farterm work).
Attribute 4 – work definition
Aim:
• To ensure that the full scope of work associated with the project has beenbroken into manageable elements in a manner that supports performancereporting.
The Earned Value Management Compass
12
Reason:
• The project scope of work should be broken into manageable elements ina manner that supports delivery of work and performance reporting.Failure to break down work appropriately can lead to difficulties withassigning a single point of accountability for delivery of the work and alsolead to confusing, conflicting and sometimes incomplete performancedata.
Guidance information:
All work authorised to be performed under the contract must be formallyauthorised and defined within the framework of a logical breakdown ofwork, normally via a work breakdown structure (WBS) and will be assignedto individuals responsible for undertaking that work. The WBS provides a common management framework for all project activ-
ities, and so there must only be one WBS for any single contract. The WBSwill be cross-referenced with the contract statement of work or a statementof requirements to ensure the full scope of work has been covered.The level to which a WBS is broken down depends upon the complexity of
the contract and the level of detail required for effective management. Essen-tially, the breakdown should continue until all contract requirements andbusiness requirements can be attributed to meaningful packages of work.In any project the WBS is of critical importance because it defines not only
how the work of the project is broken down, but also provides the frame-work for collecting actual cost, reporting progress and measuring achieve-ment.
Attribute 5 – detail work authorisation and budget assignment
Aim:
• To ensure that all distributed work has an associated budget, has beenassigned to an individual with delivery responsibility, and that all work isauthorised before it commences.
Reason:
• Every package of work within the WBS should be assigned an agreedbudget for its completion that is commensurate with the scope of work tobe delivered (i.e. is sufficient to cover labour, material and other directcosts that will be incurred while delivering the work). Before workcommences, the associated budget and schedule must be authorised toindicate approval to proceed (typically this would open associated costbooking numbers).
The Earned Value Management Compass
13
Guidance information:
The detail work authorisation and budget assignment process ensures thatevery package of work within the WBS is assigned an agreed budget for itscompletion. This is part of the formal authorisation process that allows workto commence against the agreed schedule baseline for each control account -and therefore the project as a whole. These budgets may consist of a labourelement (resources) and/or materials element and will be assigned to allwork packages (WP) and planning packages (PP). However, it is recom-mended that the different cost types should be kept in separate WPs/PPswhere possible.To manage the completion of work against work packages they will usually
only be opened when they have been formally authorised (typically whenthey are due to commence in the next few months) and will be closed whenthey are completed. This also helps to ensure that full control is maintainedover the work package and no work is completed against it, either before itis authorised or after it has been deemed to be complete and full earnedvalue claimed.
Attribute 6 – responsibility and accountability
Aim:
• To ensure that identified staff within the project team have appropriatelydelegated and documented responsibilities and accountabilities and thatthese have been communicated.
Reason:
• It is important that staff within the project are clear on what they areresponsible for delivering, and that they have the necessary authority.Whilst achieving this it is also crucial that accountability rests with singleindividuals.
Guidance information:
The project team (inclusive of control account managers) have responsibilityfor the delivery of the project. It is essential that individuals within the proj-ect have a clear definition and understanding of their terms of reference andthat these are clearly understood by those within the project and the associ-ated functional organisational areas. A control account manager (CAM) hasmanagement responsibility for ensuring that the defined scope of work for acontrol account is achieved to the budget, timescale and quality standards inaccordance with the project requirements. They manage the control accountas a contract between themselves and the project manager /project director.
The Earned Value Management Compass
14
Typical CAM terms of reference are for someone:
• who is accountable for ensuring that the defined scope of work for a discretecontrol account is achieved to budget and timescales;
• with the delegated authority to manage the deployment and mix ofresources required to achieve budget and timescales;
• who is empowered to manage the internal contract between the project andthe organisation performing the work;
• who is experienced in project delivery/management and can strike thebalance between technical and business requirements;
• who can demonstrate adequate knowledge, commitment and ownership oftheir control accounts.
Attribute 7 – material management
Aim:
• To ensure that the material budget is included in the earned valuemanagement system (EVMS) to support accurate performance reporting.
Reason:
• To establish the complete project budget and enable material performancemanagement, it is essential to ensure that the material elements arecontained within the performance measurement baseline.
Guidance information:
The management of purchased material/services covers the processes andactivities that directly affect the purchase of bill of material items or servicesfrom external suppliers. These elements should all be captured in the EVMSwith appropriate progress measurement and actual cost collection tech-niques.
Attribute 8 – basis of estimate
Aim:
• To ensure that the rationale for producing the estimates that underpin thebudget and schedule data are contained in a formal document.
Reason:
• The basis of estimate (BoE), accompanied with related assumptions,ensures that the project can demonstrate how it developed its budget andschedule. It aids future reviews of the budget, which is particularlyimportant if the staff involved in their original development are no longeravailable.
The Earned Value Management Compass
15
Guidance information:
In reviewing this area it is important to understand the CAM’s role in for-mulating the proposal estimate/budget for the effort. A number of questionsshould be asked:
a) How did they arrive at the proposed estimates? b) Are there backup worksheets to give more detail? c) Was there a negotiation process for the budgets after the contract was
awarded? d) Is the budget adequate and what risks are there in achieving the work
within budget?
The data justifying the responses to these questions should be formally doc-umented in the BoE file.
Attribute 9 – management reserve (cost and schedule)
Aim:
• To ensure that management reserve is identified, documented andapproved, and is subject to formal change approval when drawn upon bythe project.
Reason:
• Projects should have a separately identified management reserve budgetthat can be used for unplanned scope. The management reserve budgetwill typically be sized based upon the risk exposure of the project asrepresented in the risk register.
Guidance information:
Management reserve (MR) is set aside for project management control pur-poses only. It is not a contingency that can be eliminated by the customerduring subsequent negotiations, nor can it be used by the customer to absorbthe cost of contract changes.MR is derived during the budgeting process. It is held separately for future
allocation to control accounts (using the project change process) and will beused, if required, to cover increased work-scope requirements for unforeseenchanges that fall within the overall scope of the contract. For more detail onthe interfacing of risk and EVM, reference should be made to the InterfacingRisk and Earned Value Management guide on this subject.
The Earned Value Management Compass
16
Attribute 10 – supplier budget integration
Aim:
• To ensure that the suppliers budget is included in the EVMS to supportaccurate performance reporting.
Reason:
• To establish the complete project budget and enable supplier performancemanagement it is essential to ensure that the supplier budget elements arecontained within the performance measurement baseline.
Guidance information:
The nature of budget integration will depend on the earned value approachprescribed for the supplier. This could be full EVM requirements floweddown to the supplier to report budgeted cost for work performed (BCWP)and actual cost of work performed (ACWP) periodically, milestone based EVmeasurement where a milestone payment plan linked to physical progress isagreed with the supplier and this forms the BCWS, or, for commodities andconsumables, a BCWS is established based on the planned receipt.The approach defined will depend upon the nature of the item being pro-
cured, the criticality and the risk/opportunities. Where full EVM is floweddown to the supplier, the contract should clearly define the requirement. For more guidance on the selection of the best approach reference should be
made to Earned Value Management: APM Guidelines.
Attribute 11 – schedule structure and content
Aim:
• To ensure that there is a robust, time-phased, logically-linked set ofactivities and milestones that show how products/outputs will bedelivered.
Reason:
• The critical objectives for any project are the delivery of the product totime, specification and cost. As such, a schedule or suite of schedules needsto be created to display the logic, durations and interdependencies of allproject activities.
Guidance information:
The schedule should cover all work-scope and will include all master mile-stones (i.e. payment milestones, contract deliverables and key programmemilestones). There will be a clear link between the established control
The Earned Value Management Compass
17
accounts and work packages created within the EVM system and the activi-ties within the schedule.The schedule should enable the critical path to be clearly visible. Supplier
schedules should be integrated at a level of detail dependent on the type ofscope or service being purchased. The amount of detail within the schedulewill be dependent on the nature and scale of the project.
Attribute 12 – schedule resource allocation
Aim:
• To ensure that the schedule is resourced, and that resource planning isundertaken.
Reason:
• The schedule should be resourced with the amount and type of resourcerequired to deliver the project, typically using a resource breakdownstructure to identify the skill types within an organisation. Resourcelevelling should be conducted to ensure that the resources required todeliver the project are available when required.
Guidance information:
The schedule resource requirements should be understood within the con-text of the wider resource requirements of the organisation. Use of the sched-ule should allow proactive, flexible resource management to optimise theutilisation of the workforce within an organisation.
Attribute 13 – objectivity of EV progress assessment
Aim:
• To ensure that appropriate earned value techniques (EVT) are applied.
Reason:
• To accurately assess progress it is important to assign the most appropriateEVT to activities/work packages. Without this, the performance reportedmay fail to reflect actual performance achieved.
Guidance information:
The EVT is the technique used to measure achievement; also known as thebudgeted cost of work performed (BWCP) or earned value (EV). The opti-mum EVT must be assigned to individual work packages. The vast majorityof work packages on a project should be a discrete type as these provide themost objective measure of the value of in progress work.
The Earned Value Management Compass
18
The EVT chosen must best represent the effort to be accomplished and pro-vide the most appropriate method for planning, scheduling and evaluatingperformance. Work Packages should be identified as one of 3 types:
1) Discrete tasks – that have a specific end product or result.2) Apportioned – factored effort that can be directly related to other
identified discrete tasks.3) Level of effort (LOE) – support/management type of work which does
not result in a final product – performance/achievement cannot bemeasured since there is no tangible output.
The earned value techniques for each work package on a project should bedocumented, and the WBS should be structured such that the amount ofLOE on a project is capable of being reported. For more guidance on the selection of EVTs, reference should be made to
Earned Value Management: APM Guidelines.
Attribute 14 – supplier schedule integration
Aim:
• To ensure that project schedules reflect supplier activities and deliverables,giving visibility of the interaction between the schedules of all parties.
Reason:
• To enable supplier progress tracking and fully understand theinterdependencies, it is essential to ensure that the supplier schedules arecontained within the project master schedule.
Guidance information:
The way in which subcontractor effort is integrated into the baseline will dif-fer according to its importance to the project. The distinction between majorand minor subcontractor should be based upon factors such as equipmentvalue, criticality, or risk to the project (e.g. single source supply) and/orwhether they are an ‘off the shelf’ supplier or not.It is essential to ensure that sub-contractors’ schedules are represented
within the project master schedule to an appropriate level of detail, and thatthere is a process for reporting and managing the sub-contracted effort. Therequirements for sub-contractor schedule provision and reporting should bedefined in their contract. In the event of progress payments being used, a definition of the method of
validating the supplier’s performance should be recorded in the purchaseorder (or contract).Schedules on a major project can be very large and complex; decisions have
to be taken as to the level of detail to be incorporated into the project’s mas-ter schedule. If there is too much detail, the maintenance of the plan becomes
The Earned Value Management Compass
19
a burdensome overhead, whilst if there is insufficient detail, the exact statusof the project is difficult to ascertain. It is usually the key deliverables that need to be monitored and controlled
by the contractor. The focus of supplier schedules is typically:
• payment milestones (ideally one per period);• key events and/or way points (identified by period where possible);• deliverables into the contractor;• deliverables to other sub-contractors (interface milestones).
If milestone based EVM is being used, identified milestones will be allocateda budget/resource, based on the agreed payment to the sub-contractor – ideally following the agreed payment profile (refer to Attribute 10 – supplierbudget integration). Budgeted milestones will be time-phased to create aBCWS for the subcontractor.
Attribute 15 – process documentation and consistency of application
Aim:
• To ensure that the EVM processes are formally described and documentedto allow consistent application.
Reason:
• Documented processes can be communicated to all relevant stakeholders,ensuring consistent understanding and application.
Guidance information:
Formal process documentation should be created and be in operational usefor all the EVM processes to an appropriate level of detail. It is important todocument processes and procedures to enable continued operation of theprocess as new people join the project. Where generic EVM processes are in use they may be tailored with guide-
lines to meet specific local requirements in the form of local project/processinstructions for different projects. A pragmatic balance should be reachedbetween any internal procedures and external contract-specified standards.Any local project instructions are under configuration control.
EXECUTE EVM
Attribute 16 – actual cost collection
Aim:
• To ensure that costs are collected at a level appropriate for performancereporting and that they can be reconciled with the accounting system.
The Earned Value Management Compass
20
Reason:
• It is important to ensure accuracy of cost collection and ensure that it isrelated to the correct activity within the activity/work package. Withoutthis information the project will not fully understand how much it has costto perform the authorised work.
Guidance information:
The accounting processes ensure that complete and accurate cost informa-tion is collected in a timely manner, to enable the transfer of actual cost infor-mation into the project control system’s cost reporting tool (by period). Costs will be associated with the planned work and will be recorded at
activity, work package or control account level, and will be rolled-up to pro-vide actual costs across the control account(s) and at the summary projectlevel. The creation of booking or charge numbers, matched to the discreteaspects of the WBS, will also make it possible to measure progress/achievement in a meaningful manner (against the baseline plan). This willfacilitate effective financial control of the project by enabling the organisationto identify the full cost associated with the project activity and, through link-age with the recording of progress against ‘tasks’, to identify the estimatedcosts at completion for the planned work remaining. Direct costs are accumulated as labour man hours and non-labour pounds
against the relevant booking or charge numbers. Across the project, the proj-ect control system’s source collection systems will collect information andfeed it into the cost ledger. The appropriate charging rates will be applied tolabour hours to give a complete picture of the actual cost of the work per-formed. Indirect costs should also be captured at a level appropriate to allowtheir effective management.Once the actual spend is available, all CAMs are responsible for verifying
that they are both accurate and a true reflection of the actual costs of per-forming the work in that period. Material costs should also be collected in the same period as the earned
value is claimed. This may require the use of estimated actuals or accruals. A process to check the accuracy of the actual costs should be developed and
performed periodically. Corrections to actual costs should be appropriatelydocumented.If there are differences between the finance systems and the EVMS it should
be possible to identify and determine the reason for the differences.
Attribute 17 – schedule progress and control
Aim:
• To ensure that the schedule is updated and analysed to capture progress
The Earned Value Management Compass
21
and determine the performance against the baseline, enabling informedmanagement actions.
Reason:
• Establishing earned value performance requires the schedule progress tobe captured on a periodic basis.
Guidance information:
Every period, schedule progress and achievement (i.e. earned value) are col-lected and processed. Schedule variances against the baseline should bedetermined and reported. Critical path analysis of the current schedule andbaseline schedule should be performed. Float should also be determined. Asa result of the analysis information, management actions (corrective actions)are determined and implemented. Schedule progress and control will also allow the impact to current resource
plans to be evaluated and an estimate to complete to be generated for theremaining work.
Attribute 18 – data integrity
Aim:
• To ensure that data is checked for accuracy.
Reason:
• To provide confidence that it is accurate enough to support managementdecisions.
Guidance information:
Checking processes should be in place to identify errors in the EVM data set.Any adjustments required must be to correct errors. Any financial transfersthat are required should be made in the period following the error. Genuinecost variances should not be disguised through this process
Attribute 19 – estimate at complete (EAC)
Aim:
• To ensure that the project generates a valid estimate at complete (includingcost and schedule).
Reason:
• The EAC provides an indication of the final funding requirements for theproject, in addition to the likely completion date. (See also Attribute 17 –schedule progress and control)
The Earned Value Management Compass
22
Guidance information:
There are two main types of EAC:
• a CAM estimate* of the resources over time required to complete the workpackage
• independent estimates based upon standard EV calculations.
When establishing an ETC the following aspects should be considered:
• Past performance (efficiency) and trends.• Costs incurred to date.• Commitments placed (to date and potential future).• Required efficiency to ‘recover’ variances.• Technical assessment of remaining activities.• Anticipated future efficiency (should relate to past performance).• Forecast of schedule (time) to complete activity.• Associated risks with remaining activity.• Future economic conditions, e.g. rate changes, escalation indices, revised
supplier contracts.• Previous ETC trend.
Independent estimate: there is a range of standard independent estimates atcomplete (IEAC) calculation formulae that can be used to identify the poten-tial project out-turn based upon performance to date. These are outlined inthe Earned Value Management: APM Guidelines.The CAM EAC should be compared to the standard IEAC calculations
that are based on previous performance to provide a check on their realism.
Attribute 20 – supplier management and reporting
Aim:
• To ensure that supplier performance reporting is aligned with therequirements of the project, to enable effective supplier management.
Reason:
• Significant areas of projects are often managed and delivered by suppliers.It is important that these suppliers report relevant, agreed progressinformation periodically.
*CAM estimate: this is typically done by determining the estimate to complete (ETC)for each work package and summing it with the actual cost to date to produce theEAC.
The Earned Value Management Compass
23
Guidance information:
Sub-contractors should provide a periodic progress report which containsinformation relevant to the nature of the procurement (see Attribute 14 – supplier schedule integration). It is important that there is verification of theaccuracy of the supplier information. This may be achieved during perform-ance reviews with the supplier or by physical on site verification.
Attribute 21 – risk and opportunity management
Aim:
• To ensure that there is alignment between the risk management and earnedvalue management processes.
Reason:
• The risk management processes within a project overlap with the EVMprocesses, particularly around unplanned work-scope and estimate atcompletion.
Guidance information:
Risk and opportunity management is an integral part of EVM and is con-cerned with managing threats to the baseline. The management of opportu-nity is concerned with improving performance against the baseline. Earned value and risk and opportunity management are fully integrated
into the project team’s project management and control processes, and regu-lar reviews which seek to maintain or improve this position are undertaken.Approved and budgeted risk mitigation or opportunity realisation activi-
ties should be included in the baseline project master schedule. The con-sumption of management reserve should be tracked in relation to theremaining risk exposure of the project.
Attribute 22 – baseline change management
Aim:
• To ensure that changes to the performance measurement baseline (the‘baseline’) are carried out in a timely and controlled manner.
Reason:
• The baseline should contain the complete, agreed scope of work. Asprojects progress change is inevitable; the introduction of these changesinto the baseline must be controlled.
The Earned Value Management Compass
24
Guidance information:
To ensure that the project is managed in a controlled manner it is importantthat all changes are embodied into the PMB in an orderly, controlled and doc-umented manner. Change management addresses the controlled processwhereby the project incorporates formal change, conducts internal re-planning and adjusts past, present and future information to incorporatechanges. The baseline change process exists in order to ensure all requests for change
are recorded, progressed and tracked in a timely manner. Change can berequested through four sources: the project, CAM, customer or sub-contrac-tor. Where it impacts the baseline then the associated CAM must define theimpacts on work-scope, schedule, budget and product configuration. Thelevel of authority for approving PMB changes must be clearly defined ineither the project management plan or a project control plan and any changesthat are approved must be implemented within the PMB in a timely manner. Budgets should not be transferred without corresponding work-scope.
Change should also not be used to remedy or hide poor performance.
Attribute 23 – senior management usage
Aim:
• To ensure that EVM information is available to senior management toinform decision making during project, programme and portfolio reviews.
Reason:
• Senior management staff must have a basic understanding of EVM to beable to interpret the data that they receive. They may also need to beinvolved in providing project direction should variances becomesignificant.
Guidance information:
Adopting the principle of management by exception, there may be timeswhen senior management need to become involved in the project decision-making process. It is important that the senior management team have aclear understanding of EVM in project management and are able to interpretthe information provided.
Attribute 24 – customer involvement
Aim:
• To ensure that EVM is operated in a manner that allows customerinvolvement.
The Earned Value Management Compass
25
Reason:
• To ensure that where the customer is involved, EVM is used in an open andtransparent manner.
Guidance information:
The customer is typically the client or organisation that is funding the project. The nature of customer involvement may be largely shaped by whether the
customer has stated the requirement for EVM within the contract or if theproject is using EVM as part of its standard company policy. If the customerhas specified EVM, the expectation is that they have an active interest inEVM and would receive the relevant EVM reports. They would typically beinvolved in the decision-making process and be party to recovery planning.
EVM GOAL
Attribute 25 – EVM as a decision support tool
Aim:
• To ensure that EVM information forms a key component of project per-formance management reviews.
Reason:
• The value provided by EVM is achieved through using the data to makeinformed decisions. Producing EV data but not linking this to the decision-making process does not meet the aims of the process.
Guidance information:
The purpose of EVM is to provide management information to make betterdecisions. The EVM data should be used during project performance reviewsto report the status of the project against the performance measurement base-line (PMB). Variance to include explanation, impact, actions, summary from last period
– so management can understand how this is affecting the project/programme and show what has previously been done (from summary) – giving continuity of the issue and showing closure.The requirement for a variance report is typically triggered by establishing
cost, schedule and EAC thresholds. Variance reporting facilitates manage-ment by exception.
26
EV
M c
omp
ass
qu
esti
ons
12
34
5C
omm
ents
As
isTo
be
EVM
foun
datio
ns
1.Ea
rned
val
ue m
anag
emen
t co
mpe
tenc
ies
Littl
e or
no
trai
ning
in th
e co
ncep
tsof
EV
M is
ava
il-ab
le a
nd ta
ke-u
pis
inco
nsis
tent
.
Form
al tr
aini
ng a
nd a
budg
et to
sup
port
its
roll-
out e
xist
s in
the
conc
epts
of E
VM
for
all k
ey ro
les
with
in th
epr
ojec
t org
anis
atio
nbu
t tak
e-up
is in
con-
sist
ent.
Ther
e is
littl
eor
no
prev
ious
exp
eri-
ence
of E
VM
sys
tem
impl
emen
tatio
n w
ithin
the
team
.
Coo
rdin
ated
, fun
ded
trai
ning
pro
vide
s co
n-si
sten
cy in
EV
Map
proa
ch a
nd a
ll te
amm
embe
rs h
ave
been
suff
icie
ntly
trai
ned
inEV
M to
fulfi
l the
ir ro
les.
Refr
eshe
r and
mor
ead
vanc
ed E
VM
trai
ning
is p
rovi
ded
to th
ose
that
requ
ire it
. The
team
is a
lso
able
to d
raw
upon
the
prev
ious
impl
emen
tatio
n ex
peri-
ence
of e
ither
team
mem
bers
or s
uppo
rtpe
rson
nel.
Trai
ning
is li
nked
into
per
son-
nel d
evel
opm
ent
proc
esse
s. T
rain
ing
and
com
pete
ncy
reco
rds
are
mai
ntai
ned.
Pre
viou
s ex
pe-
rienc
e of
EV
M s
yste
mim
plem
enta
tion
is c
onsi
d-er
ed a
cru
cial
ele
men
tw
hen
cons
truc
ting
proj
ect
team
s. P
roje
ct te
ams
are
supp
orte
d by
sta
ff w
ith th
ekn
owle
dge
to im
plem
ent
an a
ppro
pria
tely
sca
led
EVM
S fo
r the
pro
ject
and
then
sup
port
its
use
thro
ugh
initi
al m
onth
s or
data
chu
rn a
nd re
view
.
Trai
ning
cou
rses
are
tailo
red
to m
eet
spec
ific
proj
ect
need
s an
d th
eco
urse
mat
eria
l is
perio
dica
llyup
date
d to
refle
ctle
sson
s le
arne
dfr
om p
roje
cts.
Thes
e le
sson
s ar
eth
en d
irect
ly fe
din
to n
ew p
roje
cts
whe
n fo
rmin
g th
ete
ams.
2.Sp
onso
rshi
p
The
EVM
sys
tem
ises
tabl
ishe
d w
ith-
out t
he s
uppo
rtor
com
mitm
ent
of a
sen
ior
man
ager
.
The
EVM
sys
tem
ises
tabl
ishe
d w
ith th
epa
ssiv
e su
ppor
t of a
seni
or m
anag
er.
The
EVM
spo
nsor
pro
-vi
des
proa
ctiv
e w
ith v
is-
ible
sup
port
pro
vidi
ngcl
ear t
actic
al d
irect
ion.
The
EVM
spo
nsor
pro
vide
sst
rate
gic
dire
ctio
n on
the
use
of E
VM
acr
oss
the
busi
ness
and
into
the
cus-
tom
er a
nd s
uppl
ier c
hain
s.
EVM
spo
nsor
ship
and
adop
tion
isac
tivel
y su
p-po
rted
by
all
appr
opria
te s
en-
ior m
anag
emen
tte
am m
embe
rs.
Organisation
27
12
34
5C
omm
ents
As
isTo
be
EVM
bas
ics
3.Pr
ojec
t le
vel a
utho
risa
tion
The
proj
ect h
as c
om-
men
ced
with
no
form
al a
utho
risa-
tion
docu
men
ta-
tion
from
the
appr
oval
auth
ority
.
The
appr
oval
aut
horit
yha
ve s
anct
ione
d th
epr
ojec
t usi
ng a
form
alpr
oces
s. R
espo
nsib
ility
,ac
coun
tabi
lity,
and
auth
ority
for d
eliv
erin
gth
e pr
ojec
t wor
k sc
ope
are
held
by
an a
utho
-ris
ed in
divi
dual
.
The
proj
ect o
rgan
isat
iona
lst
ruct
ure
is d
efin
ed a
nddo
cum
ente
d, in
clud
ing
the
maj
or s
ubco
ntra
ctor
sre
spon
sibl
e fo
r acc
om-
plis
hing
the
auth
oris
edw
ork.
Res
pons
ibili
ty,
acco
unta
bilit
y, a
ndau
thor
ity fo
r pro
ject
wor
k sc
ope
are
held
by
the
seni
or p
roje
ct m
an-
ager
and
del
egat
edap
prop
riate
ly. O
rgan
isa-
tiona
l res
pons
ibili
ty is
defin
ed fo
r all
elem
ents
of w
orki
ng u
sing
an
OBS
. All
activ
ities
are
assi
gned
to a
n el
emen
tof
the
OBS
. A d
ocu-
men
ted
corr
elat
ion
exis
tsbe
twee
n th
e W
BS a
ndO
BS, u
tilis
ing
the
Resp
onsi
bilit
y A
ssig
n-m
ent M
atrix
(RA
M).
Resp
onsi
ble
man
ager
s (R
Ms)
have
fully
doc
umen
ted
scop
e, d
eliv
erab
les,
bud
get,
assu
mpt
ions
, and
exc
lusi
ons
for t
heir
elem
ents
of w
ork.
The
OBS
is s
ubje
ct to
form
alch
ange
con
trol
. OBS
and
RAM
are
mai
ntai
ned.
This
leve
l con
side
red
and
left
blan
k.
4.W
ork
defin
ition
Ther
e is
no
form
alW
BS o
r onl
y an
outli
ne W
BSex
ists
.
Scop
e is
doc
umen
ted
and
deco
mpo
sed
into
mea
ning
ful,
man
age-
able
ele
men
ts. A
reco
gnis
ed w
ork
brea
kdow
n st
ruct
ure
and/
or o
ther
app
ropr
i-at
e st
ruct
ure
e.g.
pr
oduc
t bre
akdo
wn
stru
ctur
e (P
BS) i
ses
tabl
ishe
d.
All
auth
oris
ed w
ork
ele-
men
ts a
re d
efin
ed fo
r the
proj
ect.
A w
ork
brea
k-do
wn
stru
ctur
e (W
BS) i
sus
ed in
this
pro
cess
.W
BS e
lem
ents
are
appr
opria
tely
doc
u-m
ente
d. T
he p
roje
ctob
ject
ives
are
cle
arly
defin
ed a
nd d
ocum
ente
dan
d re
late
d to
the
WBS
.Th
e sc
ope
of w
ork
isun
der c
onfig
urat
ion
con-
trol
. The
sco
pe is
doc
u-m
ente
d in
an
audi
tabl
ean
d tr
acea
ble
way
(e.g
.W
BS d
ictio
nary
).
A s
yste
mat
ic p
roce
ss, s
uch
asus
ing
stan
dard
WBS
str
uc-
ture
s to
ena
ble
stan
dard
ised
repo
rtin
g, d
ecom
pose
s pr
ojec
t req
uire
men
ts a
ndid
entif
ies
the
scop
e of
wor
kne
cess
ary
to d
eliv
er th
ese
requ
irem
ents
. The
link
betw
een
cust
omer
requ
ire-
men
ts a
nd W
BS e
lem
ents
iscl
early
def
ined
. The
impa
ctof
cha
nges
to s
cope
, tec
hni-
cal s
peci
ficat
ion
or re
quire
-m
ent a
re a
sses
sed
for t
heir
impa
ct o
n th
e W
BS s
truc
-tu
re a
nd it
s do
cum
enta
tion.
The
stru
ctur
e of
the
WBS
is re
view
ed to
ensu
re th
at fu
ture
proj
ects
ben
efit
from
any
less
ons
lear
ned,
part
icul
arly
rela
ting
to h
ow fa
r it f
acili
-ta
ted
good
dis
sem
i-na
tion
of w
ork
prod
ucts
, col
lect
ion
of p
erfo
rman
ce d
ata
and
resu
lting
abi
lity
to c
ontr
ol th
e pr
ojec
t.
(Con
tinue
d on
follo
win
g pa
ge)
Organisation
28
12
34
5C
omm
ents
As
isTo
be
EVM
bas
ics
5.D
etai
l wor
k au
thor
isat
ion
and
budg
et a
ssig
nmen
t
Ther
e is
no
mec
ha-
nism
for f
orm
alau
thor
isat
ion
ofw
ork
and
budg
ets.
Ther
e is
a fo
rmal
mec
ha-
nism
for w
ork
auth
ori-
satio
n bu
t it i
sin
cons
iste
ntly
app
lied
and
budg
et is
not
alw
ays
asso
ciat
ed w
ithw
ork
scop
e.
The
budg
et/w
ork/
sche
dule
is fo
rmal
lyau
thor
ised
prio
r to
wor
kco
mm
enci
ng. T
ask
own-
ers
have
form
ally
agr
eed
to c
ompl
ete
the
wor
k as
defin
ed. B
udge
ts a
rees
tabl
ishe
d (b
y co
ntro
lac
coun
t or o
ther
aut
ho-
rised
low
-leve
l acc
ount
)fo
r aut
horis
ed w
ork.
Budg
ets
are
cons
iste
ntw
ith re
sour
ces
appl
ied
tosc
hedu
les.
Bud
get i
s di
s-tr
ibut
ed fo
r dur
atio
n of
cont
rol a
ccou
nts.
For
mal
man
agem
ent p
roce
dure
sex
ist t
o op
en/c
lose
/su
spen
d w
ork
but
ther
e is
inco
nsis
tent
appl
icat
ion.
CA
Ms
man
age
a to
tal b
udge
t(£
, $) a
nd a
re re
spon
sibl
efo
r mat
eria
l pur
chas
es a
sw
ell a
s m
an-h
ours
. For
mal
clos
ure
proc
esse
s an
dm
echa
nism
s o
nce
the
wor
ksc
ope
has
been
com
plet
edan
d ar
e co
nsis
tent
lyap
plie
d.
Budg
ets
and
actu
al c
ost
are
used
to in
form
futu
re e
stim
atin
g.
6.R
espo
nsib
ility
and
acc
ount
abili
ty
Ther
e ar
e no
per
-so
nal t
erm
s of
ref-
eren
ce (T
ORs
)is
sued
that
are
appr
opria
te to
the
proj
ect.
The
seni
or p
roje
ct m
an-
agem
ent t
eam
hav
ebe
en is
sued
with
appr
opria
te T
ORs
that
have
bee
n co
mm
uni-
cate
d to
all
man
age-
men
t sta
ff w
ithin
the
orga
nisa
tion.
The
proj
ect m
anag
emen
tte
am (i
nclu
sive
of
CA
Ms)
hav
e be
en is
sued
with
app
ropr
iate
TO
Rsth
at h
ave
been
com
mu-
nica
ted
to a
ll m
anag
e-m
ent s
taff
with
in th
eor
gani
satio
n. T
here
are
clea
r rep
ortin
g lin
es to
both
the
proj
ect m
anag
e-m
ent t
eam
and
func
tiona
lm
anag
emen
t whe
reap
prop
riate
.
Ther
e is
a c
hang
epr
oces
s/fe
edba
ck in
TO
Rsan
d fo
r the
han
d ov
er o
fsc
ope
and
budg
et b
etw
een
CA
Ms,
whi
ch a
re m
ain-
tain
ed o
ver t
he p
roje
ct li
feto
pro
vide
con
sist
ency
.
The
indi
vidu
als
TORs
are
inte
grat
ed w
ithth
eir r
espe
ctiv
e H
Rpe
rson
al d
evel
op-
men
t pla
ns fo
r per
-so
nal o
bjec
tives
.
Organisation
29
7.M
ater
ial m
anag
emen
t
Mat
eria
ls a
reex
clud
ed fr
om th
eea
rned
val
ue m
an-
agem
ent s
yste
m(E
VM
S).
Mat
eria
l/co
nsum
able
sbu
dget
s ar
e in
clud
ed in
the
EVM
S an
d ar
e se
p-ar
ated
into
app
ropr
iate
wor
k an
d pl
anni
ngpa
ckag
es.
Mat
eria
l/co
nsum
able
sbu
dget
s ar
e in
clud
ed in
the
EVM
S w
ith a
ppro
pri-
ate
mea
sure
s of
pro
gres
san
d ap
prop
riate
act
ual
cost
col
lect
ion
mec
ha-
nism
s ar
e em
ploy
ed.
Mat
eria
ls/c
onsu
mab
les
can
betr
aced
from
the
purc
hase
orde
r req
uire
men
t dat
eth
roug
h to
the
need
dat
e.M
ater
ial c
osts
with
in th
eEV
MS
can
be tr
aced
to th
epu
rcha
se o
rder
.
Mat
eria
l/co
nsum
able
sbu
dget
s an
d ac
tual
cost
are
use
d to
info
rm fu
ture
est
imat
-in
g. R
esid
ual i
nven
-to
ry h
as a
ppro
pria
tedi
spos
al c
ontr
ols
with
in th
e EV
MS.
8. B
asis
of e
stim
ate
Ther
e is
an
abse
nce
of e
stim
atin
g.Th
ere
is a
reco
rd o
f the
cost
and
sch
edul
e es
ti-m
ates
but
form
al e
sti-
mat
ing
tech
niqu
es a
ndpr
oces
ses
have
not
been
app
lied.
A fo
rmal
str
uctu
red
esti-
mat
e ha
s be
en g
ener
ated
follo
win
g st
anda
rd e
sti-
mat
ing
proc
edur
es. A
llco
st a
nd s
ched
ule
esti-
mat
ing
assu
mpt
ions
are
fully
doc
umen
ted.
Estim
ate
is b
ased
on
prev
ious
proj
ect n
orm
s, h
isto
rical
data
, or p
aram
etric
est
imat
-in
g. A
ll es
timat
ing
assu
mp-
tions
are
fully
doc
umen
ted.
The
estim
ate
has
been
revi
ewed
by
an in
de-
pend
ent a
utho
rity.
Upo
n co
mpl
etio
n of
proj
ects
the
actu
alpe
rfor
man
ce d
ata
isus
ed to
info
rm fu
ture
estim
ates
/upd
ate
proj
ect n
orm
s.
9.M
anag
emen
t re
serv
e (c
ost
and
sche
dule
)
The
auth
oris
ed p
roj-
ect b
udge
t doe
sno
t con
tain
any
man
agem
ent
rese
rve
(MR)
.
The
auth
oris
ed p
roje
ctbu
dget
doe
s co
ntai
n an
elem
ent f
or M
R bu
tca
n no
t be
subs
tant
i-at
ed.
MR
has
been
iden
tifie
d an
dca
n be
sub
stan
tiate
d by
rela
tion
to th
e ris
k re
gis-
ter a
nd b
y us
ing
one
orm
ore
of th
e fo
llow
ing:
- ris
k as
sess
men
t/an
alys
is-
prev
ious
pro
ject
out
turn
s -
indu
stry
nor
ms
- co
nfid
ence
mod
ellin
gTh
e ch
ange
con
trol
pro
cess
is u
sed
to m
anag
ech
ange
s to
the
MR.
The
MR
budg
et is
man
aged
on
a re
gula
r bas
is in
ligh
t of
outs
tand
ing
risks
and
oppo
rtun
ities
. Con
fiden
cem
odel
ling
is u
sed
on a
regu
-la
r bas
is to
sup
port
the
MR
budg
et.
Met
rics
on th
e dr
aw-
dow
n an
d us
e of
MR
are
man
aged
and
fed
back
into
the
estim
at-
ing
and
risk
asse
ss-
men
t sta
ndar
ds.
10.
Supp
lier
budg
et in
tegr
atio
n
No
supp
lier/
part
ner
budg
et d
ata
isen
tere
d in
to th
epr
ojec
t EV
MS.
Supp
lier/
part
ner b
udge
tda
ta is
ent
ered
into
the
proj
ect E
VM
S at
a le
vel
inap
prop
riate
to th
ena
ture
of t
he p
rocu
red
item
.
Supp
lier/
part
ner b
udge
tde
tail
is e
nter
ed in
to th
epr
ojec
t EV
MS
at a
leve
lap
prop
riate
to th
e na
ture
of th
e pr
ocur
ed it
em.
The
supp
lier/
part
ner
budg
et d
ata
with
in th
epr
ojec
t EV
MS
is a
ppro
-pr
iate
ly a
ligne
d w
ith th
ede
taile
d in
form
atio
nw
ithin
the
supp
lier/
part
ner p
roje
ct m
anag
e-m
ent s
yste
m (w
hich
coul
d be
an
EVM
S).
Ther
e is
eff
ectiv
e ch
ange
cont
rol b
etw
een
the
proj
ect
and
supp
lier/
part
ner b
udg-
ets
ensu
ring
that
the
base
-lin
e bu
dget
is a
ligne
d at
all
times
.
Ther
e is
full
inte
grat
ion
of c
omm
erci
al a
ndpr
ojec
t pro
cess
esen
ablin
g a
colla
bora
-tiv
e op
erat
ing
envi
-ro
nmen
t bet
wee
n th
epr
ojec
t and
sup
plie
rsth
at is
ope
n to
inde
-pe
nden
t ver
ifica
tion
of p
erfo
rman
ce.
(Con
tinue
d on
follo
win
g pa
ge)
Organisation Budget
12
34
5C
omm
ents
As
isTo
be
30
12
34
5C
omm
ents
As
isTo
be
EVM
bas
ics
11.
Sche
dule
str
uctu
re a
nd c
onte
nt
A ti
me
phas
ed b
asis
sche
dule
exi
sts
but i
t con
tain
s lit
tlede
tail.
Low
-leve
lan
d hi
gh-le
vel
activ
ities
are
mix
ed. T
here
are
few
logi
c lin
ked
activ
ities
. Con
-st
rain
ts a
re u
sed
toac
hiev
e tim
e ph
as-
ing.
If a
var
iety
of
sche
dule
s ex
ist i
tis
not
cle
ar w
hich
has
prec
eden
ce.
Ther
e is
a s
ingl
e tim
eph
ased
sch
edul
e bu
tth
ere
is in
cons
iste
ncy
in th
e us
e of
logi
c, c
on-
stra
ints
and
act
ivity
defin
ition
suc
h th
at th
eva
lidity
of t
he c
ritic
alpa
th c
an n
ot b
e su
bsti-
tute
d.
A ti
me
phas
ed s
ched
ule
exis
ts a
t an
appr
opria
tele
vel o
f det
ail s
truc
ture
dor
can
be
map
ped
to th
eW
BS. T
he C
P ca
n be
subs
tant
iate
d. V
ertic
alan
d ho
rizon
tal t
race
abil-
ity c
an b
e de
mon
stra
ted.
The
stru
ctur
e of
the
sche
dule
sup
port
s an
appr
opria
te h
iera
rchy
of
sche
dule
s. A
rtifi
cial
con
-st
rain
ts a
re n
ot u
sed
tore
plac
e lo
gic.
Sup
plie
rsc
hedu
les
are
appr
opri-
atel
y re
pres
ente
d in
the
proj
ect s
ched
ule.
Supp
lier a
nd c
usto
mer
sch
ed-
ules
are
ver
tical
ly a
ligne
d.C
reat
ion
of th
e pr
ojec
tsc
hedu
le is
fully
inte
grat
edw
ith th
e pr
ojec
t pro
cess
es(e
.g. b
asel
ine
chan
ge, f
ore-
cast
ing,
risk
, res
ourc
e m
an-
agem
ent)
and
the
stru
ctur
esu
ppor
ts th
e m
anag
emen
tof
the
orga
nisa
tions
por
tfo-
lio o
f pro
ject
s (in
clud
ing
ente
rpris
e-w
ide
reso
urce
plan
ning
, for
ecas
ting
and
risk
miti
gatio
n ac
tiviti
es).
Adv
ance
d sc
hedu
ling
tech
niqu
es e
.g.
reso
urce
leve
lling
,M
onte
Car
lo s
ched
-ul
e ris
k an
alys
is a
reus
ed s
yste
mat
ical
ly in
optim
isin
g th
e sc
hedu
le.
12.
Sche
dule
res
ourc
e al
loca
tion
The
sche
dule
is n
otre
sour
ced.
The
sche
dule
is p
artia
llyre
sour
ced
but n
ot a
tth
e le
vel t
hat p
erm
itsre
sour
ce le
velli
ng to
be
effe
cted
.
Reso
urce
s ar
e de
fined
tosu
ffic
ient
gra
nula
rity
allo
win
g ef
fect
ive
reso
urce
leve
lling
to b
eco
nduc
ted
at a
ctiv
ityle
vel a
nd th
is le
velli
ngha
s be
en p
erfo
rmed
.
The
curr
ent v
ersi
on o
f the
sche
dule
is m
aint
aine
d to
refle
ct fu
ture
reso
urce
requ
irem
ents
thro
ugho
utth
e lif
e of
the
proj
ect a
ndle
velli
ng is
app
lied
tode
mon
stra
te a
ppro
pria
teal
loca
tion.
The
effe
ctiv
enes
s of
reso
urce
allo
catio
n is
revi
ewed
to e
nsur
efu
ture
reso
urce
opt
i-m
isat
ion
and
this
isfu
lly in
tegr
ated
with
ente
rpris
e-w
ide
reso
urce
pla
nnin
g.
Schedule management
31
13.
Obj
ectiv
ity o
f EV
pro
gres
s as
sess
men
t
Form
al e
arne
d va
lue
tech
niqu
es (E
VTs
)ar
e no
t use
d. L
evel
of e
ffor
t (Lo
E)ac
coun
ts fo
r the
maj
ority
of t
hepe
rfor
man
cem
easu
rem
ent
base
line
(PM
B).
EV is
ass
esse
d ba
sed
onsc
hedu
le p
erce
nt c
om-
plet
e or
sch
edul
e w
ork
rem
aini
ng. L
OE
iscl
early
iden
tifie
d b
ut is
inap
prop
riate
ly a
pplie
don
dis
cret
e m
easu
rabl
eta
sks.
EV is
rela
ted
to p
hysi
cal
prod
ucts
, mile
ston
es,
tech
nica
l per
form
ance
goal
s, a
nd/o
r oth
er
indi
cato
rs u
sed
to
mea
sure
pro
gres
s.
Thei
r use
ext
ends
to s
up-
plie
rs a
s ap
prop
riate
.LO
E is
cle
arly
iden
tifie
dan
d it
is ti
me
phas
ed to
prop
erly
refle
ct w
hen
wor
k w
ill b
e ac
com
-pl
ishe
d. L
OE
can
be s
eg-
rega
ted
for r
epor
ting
purp
oses
. The
EV
T us
edfo
r eac
h w
ork
pack
age
isfo
rmal
ly d
ocum
ente
d.
The
amou
nt o
f LO
E is
opt
i-m
ised
app
ropr
iate
ly fo
rth
e pr
ojec
t. W
here
dis
-cr
ete
mea
sure
s ca
n no
tbe
iden
tifie
d ap
por-
tione
d ef
fort
is a
pplie
d in
pref
eren
ce to
LO
E. F
or-
mal
doc
umen
tatio
n(s
uch
as th
e sy
stem
desc
riptio
n) e
xist
s st
at-
ing
how
EV
Ts a
re d
eter
-m
ined
and
use
d (e
.g.
expl
aini
ng h
ow %
com
-pl
ete
is im
plem
ente
d).
EVTs
are
revi
ewed
in li
ght o
fpr
ojec
t exp
erie
nce
and
this
is fe
d ba
ck in
to th
ede
finiti
on o
f EV
mea
sure
-m
ent t
ypes
and
sup
port
-in
g m
etric
s.
14.
Supp
lier
sche
dule
inte
grat
ion
Supp
lier/
part
ner
sche
dule
sta
n-da
rds
are
iIIde
fined
and
ther
eis
irre
gula
r pro
vi-
sion
of s
ched
ule
info
rmat
ion
from
supp
liers
/pa
rtne
rs.
Sche
dulin
g re
quire
men
tsar
e ap
prop
riate
lyflo
wed
-dow
n to
sup
pli-
ers/
part
ners
. Bas
elin
esc
hedu
les
are
prov
ided
but a
re n
ot in
corp
o-ra
ted
into
the
base
line
proj
ect m
aste
rsc
hedu
le.
Supp
lier/
part
ner m
ilest
ones
and
lead
-tim
es a
re in
cor-
pora
ted
into
the
base
line
proj
ect m
aste
r sch
edul
e.A
ll de
pend
enci
esbe
twee
n te
ams
have
been
iden
tifie
d an
d do
c-um
ente
d.
Ther
e is
eff
ectiv
e ch
ange
cont
rol b
etw
een
the
proj
ect a
nd s
up-
plie
r/pa
rtne
r sch
edul
esen
surin
g th
at th
e ba
se-
line
and
fore
cast
sch
ed-
ules
are
alig
ned
at a
lltim
es.
Fore
cast
sch
edul
es a
rere
view
ed a
nd c
halle
nged
with
refe
renc
e to
indu
stry
norm
s an
d/or
revi
sed
reso
urce
requ
irem
ents
and
avai
labi
lity.
15.
Proc
ess
docu
men
tatio
n an
d co
nsis
tenc
y of
app
licat
ion
Littl
e or
no
proc
ess
docu
men
tatio
nex
ist t
o su
ppor
tth
e ap
plic
atio
n of
EVM
.
Doc
umen
ted
EVM
proc
esse
s ex
ist b
utth
ere
is in
cons
iste
ntad
here
nce.
The
EV
Mpr
oces
ses
are
not i
nte-
grat
ed w
ith th
e w
ider
busi
ness
pro
cess
es.
A fo
rmal
doc
umen
ted
EVM
proc
ess
exis
ts (e
.g. a
sys
-te
m d
escr
iptio
n). T
here
is c
onsi
sten
t adh
eren
ceto
the
proc
esse
s. T
heEV
M p
roce
sses
are
fully
inte
grat
ed w
ith o
ther
busi
ness
and
pro
ject
proc
esse
s. T
he E
VM
Spr
oces
ses
are
unde
rco
nfig
urat
ion
cont
rol.
Gen
eric
EV
M p
roce
sses
may
be
tailo
red
with
guid
elin
es to
mee
t spe
-ci
fic lo
cal r
equi
rem
ents
in th
e fo
rm o
f loc
al p
roj-
ect i
nstr
uctio
ns fo
r dif-
fere
nt p
roje
cts.
Any
lo
cal p
roje
ct in
stru
ctio
nsar
e un
der c
onfig
urat
ion
cont
rol.
Con
tinuo
us m
onito
ring
ofpr
oces
s ap
plic
atio
n is
inpl
ace.
Poo
r pro
cess
per
-fo
rman
ce is
isol
ated
, and
corr
ectiv
e ac
tion
plan
s ar
eim
plem
ente
d. P
roce
ssim
prov
emen
ts a
re id
enti-
fied
and
docu
men
ted,
and
intr
oduc
ed u
nder
con
figu-
ratio
n co
ntro
l. Im
plem
en-
tatio
n of
pro
cess
cha
nges
are
rolle
d ou
t to
user
s in
atim
ely
man
ner.
(Con
tinue
d on
follo
win
g pa
ge)
Schedule management Process
12
34
5C
omm
ents
As
isTo
be
32
12
34
5C
omm
ents
As
isTo
be
Exec
ute
EVM
16.
Act
ual c
ost
colle
ctio
n
The
proc
ess
for
actu
al c
ost a
reco
llect
ion
is n
otde
fined
. Cos
tsco
llect
ed a
t the
proj
ect l
evel
.
Cos
ts (£
) are
col
lect
edat
Con
trol
Acc
ount
(CA
) lev
el o
n a
mon
thly
bas
is. T
here
is in
cons
iste
nt c
ost
allo
catio
n an
d ac
cu-
racy
. Sub
-con
trac
t or
mat
eria
l cos
ts a
reno
t alw
ays
repo
rted
with
in th
e sa
me
acco
untin
g pe
riod
asth
e as
soci
ated
earn
ed v
alue
iscl
aim
ed, l
eadi
ng to
cost
var
ianc
e.
Cos
ts (£
and
uni
ts) a
re c
ol-
lect
ed in
the
EVM
S at
CA
leve
l as
a m
inim
um o
n a
mon
thly
bas
is. T
here
is a
form
al p
roce
ss fo
r che
ck-
ing
and
corr
ectin
g er
rors
that
ens
ures
con
sist
ent,
accu
rate
cos
t allo
catio
n.Th
e ac
coun
ting
polic
y fo
rdi
ffer
ent c
ost t
ypes
(e.g
.ov
erhe
ad, G
&A
, dire
ct,
mat
eria
ls) i
s cl
early
defin
ed a
nd c
onsi
sten
tlyap
plie
d. S
ubco
ntra
ct o
rm
ater
ial c
osts
are
repo
rted
with
in th
e sa
me
acco
untin
g pe
riod
as th
eas
soci
ated
ear
ned
valu
e is
clai
med
. Whe
re m
ater
ial
actu
als
are
not a
vaila
ble,
estim
ated
act
uals
or
accr
uals
are
use
d.
Cos
ts (£
and
uni
ts) a
re c
ol-
lect
ed in
the
EVM
S at
wor
k pa
ckag
e (W
P) le
vel
as a
min
imum
on
aw
eekl
y ba
sis.
The
‘act
ual
cost
’ ref
lect
s ac
crua
ls &
com
mitm
ents
plu
s ot
her
defin
ed a
djus
tmen
ts a
ndca
n be
fully
reco
ncile
dw
ith th
e ac
coun
ting
sys-
tem
s.
Proc
ess
adhe
renc
eon
cos
t col
lect
ion
usin
g m
etric
s is
appl
ied
and
sys-
tem
ic is
sues
(e.g
.tim
ing)
are
cor
-re
cted
in a
tim
ely
fash
ion.
17.
Sche
dule
pro
gres
s an
d co
ntro
l
The
sche
dule
is p
ro-
gres
sed
in a
nin
cons
iste
nt a
ndirr
egul
ar m
anne
r.Th
ere
is n
o re
fer-
ence
to p
erfo
rm-
ance
aga
inst
the
base
line.
The
sche
dule
is c
onsi
s-te
ntly
pro
gres
sed
base
d on
wor
k ac
com
-pl
ishe
d on
a re
gula
rba
sis
- at l
east
mon
thly
.Th
ere
is n
o re
fere
nce
to p
erfo
rman
ce a
gain
stth
e ba
selin
e.
Regu
lar v
aria
nce
anal
ysis
ispe
rfor
med
on
curr
ent
sche
dule
vs.
bas
elin
ecr
itica
l pat
h an
d flo
atan
alys
is is
con
duct
ed.
Shor
t ter
m re
cove
rypl
anni
ng is
use
d on
am
onth
ly b
asis
. On
am
onth
ly b
asis
long
term
sche
dule
fore
cast
toco
mpl
etio
n is
con
duct
ed.
Proj
ect s
ched
ules
are
revi
ewed
and
pro
gres
sed
on a
wee
kly
basi
s to
redi
rect
shor
t ter
m re
cove
ry p
lans
whe
re a
ppro
pria
te. F
orm
alre
cove
ry p
lans
are
util
ised
to e
ffec
t rec
over
y ac
tion.
On
a re
gula
r bas
is th
ere
is in
depe
nden
t ver
ifi-
catio
n of
pro
gres
s to
date
and
val
idat
ion
ofth
e sc
hedu
le to
com
-pl
etio
n. L
esso
nsle
arnt
dur
ing
thes
ere
view
s ar
e fe
d ba
ckin
to th
e sc
hedu
ling
proc
esse
s.
Execution
33
18.
Dat
a in
tegr
ity
Ther
e is
littl
e or
no
unde
rsta
ndin
g of
data
inte
grity
with
in th
e pr
ojec
t.al
l dat
a is
trea
ted
as a
ccur
ate
with
-ou
t che
cks.
Ther
e is
an
unac
cept
able
leve
l of e
rror
s in
out
put
data
(acr
oss
earn
edva
lue,
act
ual c
ost a
ndpl
anne
d va
lue
data
)th
at h
as a
det
rimen
tal
impa
ct o
n th
e in
tegr
ityof
the
proj
ect d
ata
set.
Ther
e is
an
acce
ptab
le le
vel
of e
rror
s in
out
put d
ata
that
has
a m
inim
al im
pact
on th
e in
tegr
ity o
f the
proj
ect d
ata
set.
Dis
crep
-an
cies
are
iden
tifie
d,as
sess
ed a
nd m
anag
ed.
The
proj
ect a
ctiv
ely
atte
mpt
sto
redu
ce re
sidu
al d
ata
inte
grity
pro
blem
s by
mea
s-ur
ing
the
qual
ity a
nd ti
mel
i-ne
ss o
f the
EV
dat
a us
ing
met
rics.
Ther
e is
full
data
inte
grity
and
err
ors
are
rare
.
19.
Estim
ate
of c
ompl
ete
The
proj
ect E
AC
ifpr
oduc
ed a
t all
isde
term
ined
on
anin
cons
iste
nt a
ndirr
egul
ar b
asis
.
The
proj
ect E
AC
(gen
er-
ated
eith
er b
y m
anag
e-m
ent o
r sys
tem
atic
ally
)is
det
erm
ined
on
a co
n-si
sten
t and
regu
lar
basi
s bu
t can
not
be
subs
tant
iate
d us
ing
deta
iled
proj
ect d
ata.
The
proj
ect E
AC
(for
cos
tan
d sc
hedu
le o
ut-t
urn)
isde
term
ined
at a
n ap
pro-
pria
te le
vel o
n a
mon
thly
basi
s, w
hich
is s
ubst
anti-
ated
thro
ugh
low
er le
vel
perf
orm
ance
, ris
k m
itiga
-tio
n an
d re
sour
ces
requ
ired
to c
ompl
ete
the
rem
aini
ng p
lann
ed w
ork.
Com
para
tive
fore
cast
s (e
.g.
stat
istic
al E
AC
s an
d TC
PI)
are
prod
uced
and
use
d to
revi
ew th
e re
ason
able
ness
of th
e pr
ojec
t for
ecas
t.Po
tent
ial E
AC
cha
nges
(with
cons
ider
atio
n to
act
ions
tom
anag
e fu
ture
risk
s an
dop
port
uniti
es) a
re d
ocu-
men
ted
and
revi
ewed
dur
-in
g th
e fo
rmal
EA
C c
ycle
.3
poin
t EA
Cs
are
gene
rate
dat
pro
ject
leve
l tha
t can
be
subs
tant
iate
d.
Ther
e is
inde
pend
ent
valid
atio
n of
the
EAC
on a
regu
lar b
asis
.EA
Cs
calc
ulat
ed o
n a
time
phas
ed E
TCba
sed
on:
- th
e cu
rren
t sch
edul
efo
reca
st;
- re
sour
ce re
quire
men
tsan
d av
aila
bilit
y;-
past
per
form
ance
; and
- la
test
risk
miti
gatio
nan
d op
port
unity
real
i-sa
tion
posi
tion.
20.
Supp
lier
man
agem
ent
and
repo
rtin
g
Supp
lier/
part
ner
repo
rts
perf
orm
-an
ce a
nd fo
reca
ston
an
irreg
ular
basi
s an
d to
an
inco
nsis
tent
sta
n-da
rd. N
o su
pplie
rda
ta is
bei
ng re
p-re
sent
ed in
the
proj
ect E
VM
dat
a.
Supp
lier/
part
ner r
epor
tspe
rfor
man
ce a
nd fo
re-
cast
on
a tim
ely
basi
s to
an in
cons
iste
nt s
tan-
dard
. Sup
plie
r dat
a is
repr
esen
ted
in th
e pr
oj-
ect E
VM
dat
a, b
ut m
ayno
t be
base
d on
Info
r-m
atio
n de
liver
ed fr
omth
e su
pplie
r.
Supp
lier/
part
ner r
epor
tspe
rfor
man
ce a
nd fo
re-
cast
on
a tim
ely
basi
s to
an c
onsi
sten
t sta
ndar
d.Su
pplie
r per
form
ance
data
is v
erifi
ed b
y th
epr
ojec
t and
is d
eem
ed to
be re
liabl
e an
d ac
cu-
rate
ly p
rese
nted
.
Regu
lar s
uppl
ier/
part
ner p
er-
form
ance
revi
ews
are
con-
duct
ed u
sing
the
supp
lier/
part
ner E
V d
ata
as th
e ba
sis
of th
e re
view
, with
sup
port
-in
g va
rianc
e an
alys
is a
ndco
rrec
tive
actio
n pl
anni
ng.
Verif
icat
ion
is c
ondu
cted
at
appr
opria
te p
oint
s w
ithin
the
sche
dule
.
Supp
liers
are
incl
uded
in re
gula
r EV
mee
t-in
gs a
nd s
uppo
rtva
rianc
e an
alys
is a
ndco
rrec
tive
actio
npl
anni
ng. S
uppl
iers
are
revi
ewed
as
part
of th
e as
sura
nce
proc
ess
(e.g
. IBR
,D
R, S
R, m
atur
ityas
sess
men
ts).
(Con
tinue
d on
follo
win
g pa
ge)
Execution1
23
45
Com
men
tsA
s is
To b
e
34
12
34
5C
omm
ents
As
isTo
be
Exec
ute
EVM
21.
Ris
k an
d op
port
unity
man
agem
ent
Risk
and
opp
ortu
nity
man
agem
ent
proc
ess
not c
on-
side
red
in th
e EV
syst
em.
Risk
/opp
ortu
nity
man
-ag
emen
t and
ear
ned
valu
e m
anag
emen
tpr
oces
ses
are
loos
ely
linke
d. T
he d
ata
from
the
two
proc
esse
s ar
eco
mpa
red
and
con-
tras
ted
but n
otre
flect
ed in
eith
er th
eba
selin
e or
mon
thly
fore
cast
s.
App
rove
d ris
k m
itiga
-tio
n/op
port
unity
real
isa-
tion
activ
ities
are
budg
eted
and
incl
uded
with
in th
e pr
ojec
t sch
ed-
ule.
The
cha
nge
proc
ess
is u
tilis
ed to
app
rove
and
sche
dule
new
risk
miti
ga-
tion/
oppo
rtun
ity re
alis
a-tio
n ac
tiviti
es.
Risk
and
opp
ortu
nity
man
age-
men
t and
EV
pro
cess
es a
rein
tegr
ated
. Inf
orm
atio
n pr
o-vi
ded
on u
ncer
tain
ty a
ndris
ks h
elps
to d
eter
min
e th
eco
nfid
ence
the
proj
ect
base
line
and
fore
cast
(incl
udin
g as
sess
ing
the
appr
opria
tene
ss o
f the
rem
aini
ng m
anag
emen
tre
serv
e).
Proc
esse
s ar
e pe
riodi
-ca
lly re
view
ed a
ndm
atur
ity m
etric
s ar
eus
ed to
driv
e co
ntin
-uo
us im
prov
emen
t.
22.
Bas
elin
e ch
ange
man
agem
ent
Base
lines
are
not
mai
ntai
ned.
No
form
al p
roce
ss fo
rin
corp
orat
ing
orre
cord
ing
chan
ges
to th
e ba
selin
eex
ists
.
Base
line
chan
ges
are
cont
rolle
d by
a d
ocu-
men
ted
proc
ess.
Bas
e-lin
es a
re m
aint
aine
din
cons
iste
ntly
and
irreg
ular
ly. T
he p
roce
ssof
cha
nge
appr
oval
and
embo
dim
ent i
s no
ttim
ely.
Inap
prop
riate
chan
ges
are
appl
ied
toth
e ba
selin
e eg
. fre
-qu
ent r
epla
ns o
ccur
with
the
resu
lt of
wip
-in
g ou
t pre
viou
sly
reco
rded
var
ianc
esan
d/or
bud
get b
eing
tran
sfer
red
with
out t
heco
rres
pond
ing
tran
sfer
of w
ork.
Base
line
chan
ges
are
con-
trol
led
by a
doc
umen
ted
proc
ess.
Dire
ct a
nd c
on-
sequ
entia
l im
pact
ass
ess-
men
ts a
re c
ondu
cted
by
the
proj
ect t
eam
.A
ppro
val i
s ba
sed
onty
pe o
f cha
nge
and
valu
e. B
asel
ines
are
mai
ntai
ned
cons
iste
ntly
and
regu
larly
. Pro
cess
of
chan
ge a
ppro
val a
ndem
bodi
men
t is
timel
y.A
ppro
pria
te c
hang
es a
reap
plie
d to
the
base
line.
Budg
et is
not
tran
sfer
red
with
out t
he c
orre
spon
-di
ng tr
ansf
er o
f wor
k.
Dire
ct a
nd c
onse
quen
tial
impa
ct a
sses
smen
ts o
fch
ange
s ar
e co
nduc
ted,
coor
dina
ted
with
and
unde
rsto
od b
y th
e af
fect
edte
ams,
func
tions
and
sup
pli-
ers
prio
r to
appr
oval
.
Base
line
chan
ges
are
asse
ssed
and
alig
ned
with
oth
er p
roje
ctba
selin
es (e
.g. c
on-
figur
atio
n, re
quire
-m
ents
) prio
r to
appr
oval
. The
per
-fo
rman
ce o
f the
base
line
chan
gepr
oces
s is
per
iodi
-ca
lly re
view
ed to
ensu
re it
is p
erfo
rm-
ing
adeq
uate
ly a
ndm
eetin
g th
e ne
eds
ofal
l pro
ject
s.
Execution
35
23.
Seni
or m
anag
emen
t us
age
Ther
e is
neg
ligib
lese
nior
man
age-
men
t und
erst
and-
ing
or re
view
of
the
EV d
ata.
The
EVM
per
form
ance
data
is re
view
ed o
n an
irreg
ular
bas
is w
ith o
nly
a lim
ited
unde
rsta
ndin
gof
the
data
by
the
sen-
ior m
anag
emen
t tea
m.
The
EVM
per
form
ance
dat
ais
revi
ewed
on
a re
gula
rba
sis
with
a g
ood
unde
r-st
andi
ng/i
nter
pret
atio
nof
the
data
by
the
seni
orm
anag
emen
t tea
m, w
hoco
mm
it to
mea
ning
ful
actio
ns b
ased
on
the
data
on a
n irr
egul
ar b
asis
.
The
seni
or m
anag
emen
t tea
mre
cogn
ises
the
impo
rtan
ceof
the
data
, con
sist
ently
unde
rsta
nds
wha
t it i
s te
lling
them
, and
com
mit
to m
ean-
ingf
ul a
ctio
ns b
ased
on
the
data
on
a re
gula
r bas
is.
The
seni
or m
anag
emen
tte
am u
ses
the
data
as
a ke
y in
put t
o bu
si-
ness
dec
isio
n m
akin
g.
24.
Cus
tom
er in
volv
emen
t
The
cust
omer
has
little
or n
o in
tere
stin
EV
M.
The
cust
omer
pro
vide
spa
ssiv
e su
ppor
t and
requ
ests
mon
thly
per
-fo
rman
ce re
port
s su
m-
mar
ised
to p
roje
ctle
vel.
The
cust
omer
does
not
hav
e th
e re
le-
vant
EV
M e
xper
tise
but
may
hav
e pa
rtic
ipat
edin
EV
M s
yste
mre
view
s e.
g. in
tegr
ated
base
line
revi
ew.
The
cust
omer
is in
volv
ed in
proj
ect E
VM
revi
ews
and
help
s de
fine
and
impr
ove
EVM
repo
rtin
g fo
rmat
s.Th
e cu
stom
er re
ceiv
esfo
rmal
repo
rts
on a
per
i-od
ic b
asis
from
the
EVM
syst
em. T
he in
form
atio
npr
ovid
ed is
at a
n ag
reed
leve
l of t
he W
BS o
n pe
r-fo
rman
ce tr
ends
, and
corr
ectiv
e ac
tion
plan
s.Th
e cu
stom
er h
as th
ere
leva
nt E
VM
exp
ertis
e.
Cus
tom
er re
pres
enta
tives
enga
ge w
ith p
roje
ct te
amop
posi
te n
umbe
rs in
the
ongo
ing
revi
ew o
f pro
ject
heal
th, u
tilis
ing
EVM
info
r-m
atio
n. T
he c
usto
mer
isin
volv
ed in
EV
M s
yste
mre
view
s (e
.g. I
BRs,
dem
on-
stra
tion
revi
ews
and
ongo
ing
surv
eilla
nce)
.
The
cust
omer
is in
stru
-m
enta
l in
supp
ortin
gth
e de
velo
pmen
t and
usag
e of
the
EVM
syst
em. T
here
is fu
lltr
ansp
aren
cy in
pro
j-ec
t hea
lth (e
.g. c
osts
,va
rianc
e an
alys
is,
prog
ress
, ris
ks) a
ndcu
stom
er c
omm
it-m
ents
.
EVM
goa
l
25.
EVM
as
a de
cisi
on s
uppo
rt to
ol
EV d
ata
is o
nly
used
in th
e fo
rmal
pro
j-ec
t rev
iew
pro
cess
on a
n irr
egul
arba
sis
and/
or is
lim
-ite
d to
onl
y pa
rts
of th
e pr
ojec
tw
ork
scop
e (e
.g.
criti
cal p
ath
perf
orm
ance
).
EV d
ata
is u
sed
on a
con
-si
sten
t and
regu
lar
basi
s to
sup
port
form
alpr
ojec
t rev
iew
s. M
an-
agem
ent e
xpla
in c
ause
and
impa
ct o
f dev
ia-
tions
from
the
base
line
base
d on
cos
t and
sche
dule
var
ianc
e bu
tfo
rmal
var
ianc
e re
port
-in
g is
not
per
form
ed.
EV d
ata
form
s a
key
ele-
men
t of t
he p
roje
ctre
view
. Res
pons
ible
man
ager
s ex
plai
n ca
use
and
impa
ct o
f dev
iatio
nsfr
om th
e ba
selin
e us
ing
afo
rmal
var
ianc
e an
alys
isre
port
ing
(VA
R) tr
ig-
gere
d by
exc
eedi
ngm
anag
emen
t set
th
resh
olds
. The
VA
R is
used
to in
form
reco
very
plan
ning
.
Resp
onsi
ble
man
ager
s re
view
tren
ds, p
erfo
rman
ce in
dice
san
d V
ARs
to re
gula
rlyin
form
reco
very
pla
nnin
gan
d to
det
erm
ine
requ
ired
futu
re p
erfo
rman
ce le
vels
and
asso
ciat
ed re
sour
cere
quire
men
ts.
Effic
acy,
eff
icie
ncy,
and
effe
ctiv
enes
s of
cor
-re
ctio
n ac
tions
and
man
agem
ent d
eci-
sion
s ar
e m
easu
red
as p
art o
f the
man
-ag
emen
t fee
dbac
klo
op. R
espo
nsib
lem
anag
ers
addr
ess
syst
emic
pro
blem
area
s.
Execution
12
34
5C
omm
ents
As
isTo
be
36
ConclusionThe EVM compass aims to provide organisations with a customisable frame-work that provides the base for ongoing assessments of projects, enablingcontinuous improvement of EVM practice and delivering real business benefit.
37
Annex A
Terminologyand glossary
The definitions provided below are aligned to Earned Value Management:APM Guidelines.
Activity An element of work performed during the course of a project. Anactivity normally has an expected duration, an expected cost, and expectedresource requirements. Activities are often subdivided into tasks.
Actual cost of work performed (ACWP) The costs actually incurred andrecorded in achieving the work performed.
Actual cost The costs actually incurred and recorded in accomplishing workperformed.
Actual time expended The elapsed time from the beginning of the task todate.
Allocated budget See Total allocated budgetApplied direct costs The actual direct costs recognised in the time period
associated with the consumption of labour, material, and other directresources, without regard to the date of commitment or the date of pay-ment. These amounts are to be charged to work-in-process when any of thefollowing takes place:a. labour, material, or other direct resources are actually consumed;b. material resources are withdrawn from inventory for use;c. material resources are received that are uniquely identified to the con-
tract; ord. major components or assemblies that are specifically and uniquely
identified to a single serially numbered end item are received on a lineflow basis.
Apportioned effort Effort that, by itself, is not readily measured or divisibleinto discrete work packages but which is related in direct proportion to theplanning and performance on other measured effort.
Authorised work All work performed, pursuant to the contract, within thecontract price.
Authorised unpriced work (AUW) Includes work that has been authorised,but for which the cost has not been finalised by virtue of a formal contractamendment.
Baseline See Performance measurement baseline.
The Earned Value Management Compass
38
Budget The resources (in money and/or hours) assigned for the accom-plishment of a specific task or group of tasks.
Budget at completion The total authorised budget for achieving the projectscope of work. It is equal to the sum of all allocated budgets plus anyundistributed budget (management reserve is not included.)
Budgeted cost for work performed (BCWP) The sum of the budgets forcompleted work packages and completed portions of open work pack-ages, plus the applicable portion of the budgets for level of effort andapportioned effort.
Budgeted cost for work scheduled (BCWS) The sum of the budgets for allwork packages, planning packages, etc. scheduled to be achieved (includ-ing in-process work packages), plus the amount of level of effort and appor-tioned effort scheduled to be achieved. This may be expressed as the BCSWwithin a given time period, such as period BCWS or cumulative BCWS.
Budgets for work packages. See Work package budgets.Commitment That portion of purchased items or services which has been
ordered, but for which no actuals have been incurred.Contract budget base The contract target cost plus the estimated cost of
authorised unpriced work.Contract price The price payable by the customer under the contract for the
proper delivery of the supplies and services specified in the scope of workof the contract.
Contract target cost The total of the sum of all control accounts plus undis-tributed budget plus management reserve.
Control account A management control point at which actual costs can beaccumulated and compared to earned value and budgets (resource plans)for management control purposes. A control account is a natural manage-ment point for cost/schedule planning and control since it represents thework assigned to one responsible organisational element on one contractwork breakdown structure (CWBS) element.
Control account manager The performing manager who is responsible forplanning, performing, and monitoring the elements of work definedwithin that control account.
Cost performance report A contractually required report, prepared by thecontractor, containing information derived from the internal system. Pro-vides status of progress on the contract.
Cost variance A metric for the cost performance on a project. It is the alge-braic difference between earned value and actual cost (CV = BCWP –ACWP.) A positive value indicates a favourable position and a negativevalue indicates an unfavourable condition.
Critical path method A network analysis technique used to predict projectduration by analysing which sequence of activities (which path) has theleast amount of scheduling flexibility (the least amount of float). Early
The Earned Value Management Compass
39
dates are calculated by means of a forward pass using a specified startdate. Late dates are calculated by means of a backward pass starting froma specified completion date (usually the forward pass’s calculated projectearly finish date).
Direct costs The costs of resources expended in the achievement of work,which are directly charged to the project, without inclusion of indirectcosts.
Distributed budget All budgets that have been assigned to the controlaccounts. Distributed budget excludes management reserve and undis-tributed budget.
Earned value The value of completed work expressed in terms of the budgetassigned to that work.
Earned value management (EVM) A best practice project control processthat is based on a structured approach to planning, cost collection and per-formance measurement. It facilitates the integration of project scope,schedule, cost, risk and resource objectives and the establishment of abaseline plan for performance measurement.
Earned value management system (EVMS) An integrated management sys-tem which uses earned value to measure progress objectively.
Earned value techniques (EVT) The technique used to objectively assessprogress.
Estimate at completion (EAC) Actual direct costs, plus indirect costs allocat-able to the contract, plus the estimate of costs (direct and indirect) forremaining authorised work.
Estimate to completion (ETC) The forecast of labour hours and costs requiredto complete the remaining authorised work. It is based on a bottom-up analysis of remaining work in which consideration of past and future performance, along with the availability of resources, is taken intoconsideration.
Forecast cost at completion See Estimate at completion.Funding Funding represents the actual money available for expenditure in
the achievement of contract work. The planning of work and the time-phasing of budgets and estimates to completion (ETCs) should be consis-tent with the known available funding for that period.
Indirect costs The costs for common or joint objectives which cannot be iden-tified specifically with a particular project or activity. Also referred to asoverhead cost or burden.
Initial budget See Original budget.Integrated baseline review (IBR) An IBR is a formal process conducted to
assess the content and integrity of the performance measurement baseline(PMB). The purpose of the IBR is to achieve and maintain a project andcustomer understanding of the risks inherent in the PMB and the manage-ment control processes that will operate during its execution.
The Earned Value Management Compass
40
Latest revised estimate See Estimate at completion.Level of effort (LOE) Effort of a general or supportive nature which does not
produce definite end products. Earned value (budgeted cost for work per-formed) for LOE always equals the planned budget to date (budgeted costfor work scheduled) whether or not any work is performed.
Management reserve (MR) An amount of the total allocated budget with-held for management control purposes rather than designated for theachievement of a specific task or set of tasks. It is not a part of the per-formance measurement baseline.
Material The term to encompass all non-labour classes of resource.Milestone An activity of zero duration principally used to enhance the clar-
ity of the programme structure.Network diagram Any schematic display of the logical relationships of proj-
ect activities. Always drawn from left to right to reflect project chronology. Organisational breakdown structure. A functionally oriented code estab-
lished to identity the performance responsibility for work on a specificcontract.
Original budget The budget established at, or near, the time the contract wassigned, based on the negotiated contract cost.
Original duration The duration established at, or near, the time the contractwas signed, based on the negotiated contract cost.
Other direct costs (ODC) A group of costs which can be identified to specifictasks, other than labour, material and subcontract. Included in ODC are suchcosts as travel, accommodation, insurance, computer time and services.
Overhead Indirect labour, material, supplies, services costs and othercharges, which cannot be consistently identified with individual projects.See Indirect costs.
Over target baseline When remaining budgets are deemed insufficient tocomplete the remaining work, the budgets may be increased by seekingapproval in advance from the customer. Work is then be done to a newtotal budget which exceeds the original contract budget base, or an overtarget baseline. Now the total allocated budget equals the previous con-tract budget base (CBB) plus the previously budgeted margin plus anycontractor contribution.
Performance measurement baseline (PMB) The time-phased budget planagainst which contract performance is measured. It is formed by the budg-ets assigned to scheduled control accounts and the applicable indirectbudgets. For future effort, not planned to the control account level, the per-formance measurement baseline also includes budgets assigned to higherlevel CWBS elements and undistributed budgets. It equals the total allo-cated budget less management reserve.
Performing organisation A defined unit within the contractor’s organisationstructure, which applies the resources to perform the work.
The Earned Value Management Compass
41
Period A defined block of time that forms the financial and reporting calen-dar for an EVM system. Typically weekly or monthly.
Planning package A logical aggregation of work within a control account,normally the far-term effort, that can be identified and budgeted in earlybaseline planning, but is not yet defined into work packages.
Product breakdown structure (PBS) A hierarchical structure, which breaksdown the product into its constituent parts, in a similar way to a bill ofmaterials.
Responsible organisation A defined unit within the contractor’s organisa-tional structure which is assigned responsibility for achieving specifictasks.
Responsibility assignment matrix A depiction of the relationship betweenthe contract work breakdown structure elements and the organisationsassigned responsibility for ensuring their accomplishment.
Rolling wave The action of converting a planning package into a work pack-age.
Schedule The timing and sequence of tasks within a project, as well as theproject duration. The schedule consists mainly, of tasks, dependenciesamong tasks, durations, constraints, resources and time-oriented projectinformation.
Schedule variance A metric for the schedule performance on a program. It isthe difference between earned value and the budget (schedule variance =earned value - budget). A positive value is a favourable condition while anegative value is unfavourable.
Significant variances Those differences between planned and actual per-formance, which require further review, analysis, or action. Appropriatethresholds should be established as to the magnitude of variances that willautomatically require variance analysis.
Statement of work A narrative description of products or services to bedelivered by the project.
Supplies The goods and services including intellectual property required tobe supplied under the contract.
Total allocated budget The sum of all budgets allocated to the contract. Totalallocated budget consists of the performance measurement baseline plusall management reserve. The total allocated budget reconciles directly tothe contract budget base.
Undistributed budget Budget applicable to contract effort that has not yetbeen allocated into the performance measurement baseline or placed inreserve.
Variance at completion The difference between the total budget assigned toa contract, WBS element, organisational entity or control account, and theestimate at completion. It represents the amount of expected overrun orunderrun.
The Earned Value Management Compass
42
Variances See Significant variances.Work breakdown structure (WBS) A product-oriented family tree division
of hardware, software, services and other work tasks which organises,defines, and graphically displays the product to be produced as well as thework to be done to achieve a specified product.
a. Project summary work breakdown structure A summary WBS tailored toa specific defence material item by selecting applicable elements from oneor more summary WBSs or by adding equivalent elements unique to theproject.
b. Contract work breakdown structure (CWBS) The complete WBS for acontract, developed and used by a contractor within the guidelines ofMIL-STD-881 and according to the contract work statement. The CWBSincludes the levels specified in the contract.
Work breakdown structure (WBS) dictionary A description of all individualelements within each level of the WBS which is sufficient to define theirscope, including tasks, dependencies and deliverables.
Work-package budgets Resources, which are formally assigned by the con-tractor to achieve a work package, expressed in dollars, hours, standardsor other measurable units.
Work-packages Detailed short-span jobs, or material items identified by thecontractor for achieving work required to complete the contract.
43
Annex B
Related documentsIn using the APM EVM compass the following documents provide addi-
tional information.1. Association for Project Management (2008) Earned Value Management:
APM Guidelines ISBN: 978-1-903494-26-42. Association for Project Management (2008) Interfacing Risk and Earned
Value Management ISBN: 978-1-903494-24-0 3. Association for Project Management (2006) APM Body of Knowledge, 5th
edition ISBN: 978-1-903494-13-4
Ibis House, Regent ParkSummerleys Road Princes RisboroughBuckinghamshire, HP27 9LE
Association for Project Management
Telephone 0845 458 1944International +44 (0)1844 271640Facsimile +44 (0)1844 274509
Email [email protected] www.apm.org.uk
The Earned Value Management Compass
C
M
Y
CM
MY
CY
CMY
K
Earned value book cover.pdf 13/10/10 10:27:38