138
Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical Engineering, Indian Institute of Technology, Delhi module 8: Production Planning Back to main index exit

Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Embed Size (px)

Citation preview

Page 1: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Project and Production Management

Module 8

Production Planning over the Short Term Horizon

Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical Engineering,Indian Institute of Technology, Delhi

module 8: Production Planning

Back to main index exit continue

Page 2: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MODULE 8: Production Planning over the Short

Term Horizon1. Forecasting

2. The Analysis of Time Series

3. Aggregate Production Planning: Basic Concepts

4. Aggregate Production Planning: Modelling approaches

5. Illustrative Examples

6. Self Evaluation Quiz

7. Problems for Practice

8. Further exploration

module 8: Production Planning

Back to main index exit

Page 3: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

1.Forecasting

module 8: Production Planning

Back to main index exit back to module contents

Page 4: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

FORECASTING

Forecasting is essential for a number of planning decisions

LONG TERM DECISIONS New Product Introduction Plant Expansion

module 8: Production Planning

Back to main index exit back to module contents

Page 5: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MEDIUM TERM DECISIONS Aggregate Production Planning Manpower Planning Inventory Policy

SHORT TERM DECISIONS Production planning Scheduling of job orders

module 8: Production Planning

Back to main index exit back to module contents

Page 6: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

PLANNING PROCESSA Forecast of Demand is an essential Input for

PlanningSystem

Objectives

System to beManaged

Constraints- Budget / Space

Resources - Men

- Equipment

DemandForecast

Plan ofAction

module 8: Production Planning

Back to main index exit back to module contents

Page 7: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

METHODS OF FORECASTING

(a) Subjective or intuitive methods Opinion polls, interviews DELPHI

(b) Methods based on averaging of past data Moving averages Exponential Smoothing

module 8: Production Planning

Back to main index exit back to module contents

Page 8: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

(c) Regression models on historical data Trend extrapolation

(d) Causal or econometric models

(e) Time - series analysis using stochastic models

Box Jenkins model

module 8: Production Planning

Back to main index exit back to module contents

Page 9: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

FORECASTING Objective Scientific Free from ‘BIAS’ Reproducible Error Analysis Possible

PREDICTION Subjective Intuitive Individual BIAS Non - Reproducible Error Analysis Limited

module 8: Production Planning

Back to main index exit back to module contents

module 8: Production Planning

Back to main index exit back to module contents

Page 10: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COMMONLY OBSERVED “NORMAL” DEMAND

PATTERNS

D

t

Constant

D

t

LinearTrend

module 8: Production Planning

Back to main index exit back to module contents

Page 11: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D

t

CyclicD

t

SeasonalPattern with

Growth

module 8: Production Planning

Back to main index exit back to module contents

Page 12: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ABNORMAL DEMAND PATTERNS

TransientImpulse

SuddenRise

SuddenFall

module 8: Production Planning

Back to main index exit back to module contents

Page 13: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

OPINION POLLSPersonal interviews

e.g. aggregation of opinion of sales representatives to obtain sales forecast of a region

Knowledge base (experience) Subjective bias

Questionnaire method questionnaire design choice of respondents obtaining respondents analysis and presentation of results (forecasting)

Telephonic conversation Fast

DELPHI

module 8: Production Planning

Back to main index exit back to module contents

Page 14: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DELPHIA structured method of obtaining responses from

experts.

Utilizes the vast knowledge base of experts

Eliminates subjective bias and ‘influencing’ by members through anonymity

Iterative in character with statistical summary at end of each round (Generally 3 rounds)

Consensus (or Divergent Viewpoints)

usually emerge at the end of the exercise.

module 8: Production Planning

Back to main index exit back to module contents

Page 15: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Coordinator

Expert 1

Expert 2

Expert n

1990 1995 2000 2005 20101990

year

• Mean•Median•Std. deviation

A Statisticalsummary

can be givenat end of

each round

module 8: Production Planning

Back to main index exit back to module contents

Page 16: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DELPHI (Contd.)

Round1

Round2

Round3

MovingTowards

Consensus

module 8: Production Planning

Back to main index exit back to module contents

Page 17: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DELPHI (Contd.)

Round1

Round2

Round3

MovingTowardsDivergent

View Points

module 8: Production Planning

Back to main index exit back to module contents

Page 18: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MOVING AVERAGESMonth Demand 3 Month MA 6 Month MA

Jan 199 Feb 202 Mar 199 200.00 Apr 208 203.00 May 212 206.33 Jun 194 203.66 202.33 Jul 214 205.66 207.83 Aug 220 208.33 210.83 Sep 219 216.66 213.13

Oct 234 223.33 217.46 Nov 219 223.00 218.63 Dec 233 227.66 225.13

module 8: Production Planning

Back to main index exit back to module contents

Page 19: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

K PERIOD MA = AVERAGE OF K MOST RECENT OBSERVATIONS

For instance : 3 PERIOD MA FOR MAY

= Demands of Mar, Apr, May / 3= (199 + 208 + 121) / 3 = 206.33

module 8: Production Planning

Back to main index exit back to module contents

Page 20: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CHARACTERISTICS OF MOVING AVERAGES

Dt

t

Dt

t

(1) MOVING AVERAGES LAG A TREND

module 8: Production Planning

Back to main index exit back to module contents

Page 21: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Dt

t

(2) MOVING AVERAGES ARE OUT OF PHASE

FOR CYCLIC DEMAND

module 8: Production Planning

Back to main index exit back to module contents

Page 22: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Dt

t

(3) MOVING AVERAGES FLATTEN PEAKS

module 8: Production Planning

Back to main index exit back to module contents

Page 23: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXPONENTIAL SMOOTHINGFt = one period ahead forecast made at

time time t

Dt = actual demand for period t

= Smoothing constant (between 0 & 1)

(generally chosen values tie between 0.01 and 0.3)

Ft = Ft-1 + (Dt - Ft-1)

module 8: Production Planning

Back to main index exit back to module contents

Page 24: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Ft = Dt +(1 - ) Ft-1

= Dt +(1 - ) [ Dt-1 +(1 - )2 Ft-2 ]

=……..

= [Dt +(1 - ) Dt-1 +(1 - )2 Dt-2 + …..

+ (1 - )t-1 D1 + (1 - )t F0]

(1- ) (1- )2

tt-1t-2

Weightages given to past data decline exponentially.

module 8: Production Planning

Back to main index exit back to module contents

Page 25: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MOVING AVERAGESAND

EXPONENTIAL SMOOTHING

(Equivalence between & N :) = 2 / (N+1)

module 8: Production Planning

Back to main index exit back to module contents

Page 26: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

J F M A M J J A S O N D J190

200

210

220

230

Dem

and

Month

3 Month MA

6 Month MA

= 0.3

= 0.1

module 8: Production Planning

Back to main index exit back to module contents

Page 27: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Common Regression Functions

dt

t

dt’ forecast

dt actual demand (for time period t)

dt’ = a + bt (parameters a, b)

Linear

module 8: Production Planning

Back to main index exit back to module contents

Page 28: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

t

dt’ = a + u Cos (2/n)t + v Sin (2/n)t (parameters a, u, v)

Cyclic

module 8: Production Planning

Back to main index exit back to module contents

Page 29: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

t

dt’ = a +bt + u Cos (2/n)t + v Sin (2/n)t (parameters a,b,u, v)

Cyclic withGrowth

module 8: Production Planning

Back to main index exit back to module contents

Page 30: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

tdt’ = a +bt + ct2 (parameters a,b,c)

Parameters Determined by Minimizing the Sum of Squares of errors,

Quadratic

module 8: Production Planning

Back to main index exit back to module contents

Page 31: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

REGRESSION

J F M A M J J A S O N D J190

200

210

220

230

Dem

and

Month (t)

Actual Data 218

246

Ft = 193 + 3t(Regression Line)

Forecast for next

JAN

1 2 3 4 5 6 7 8 9 10 11 12 13

232

module 8: Production Planning

Back to main index exit back to module contents

Page 32: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Standard error of estimate = (Dt - Ft)2

Where

Dt = actual demand for period t = 7.32

Ft = forecast for period t

n = no. of data points

f = degrees of freedom lost (2 in this case)

95 % confidence limits for forecast of next JAN ~ 232 14 (* 2 sigma)

n

t = 1 n - f

module 8: Production Planning

Back to main index exit back to module contents

Page 33: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CAUSAL MODELSHere demand is related to

Causal variables GNP Per Capita income Consumer Price index …………

Demand for tyres

= f (Production of new automobiles, Replacements by existing autos,

Govt policy on automobiles, …..)

module 8: Production Planning

Back to main index exit back to module contents

Page 34: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Dt = Pt + Pt-5 +

could be a simplified causal model

(Here parameters , ,, are estimated by regression from data)

For a Causal Model to be Useful

The causal variables should be

Leading

Highly correlated with the variable of interest

module 8: Production Planning

Back to main index exit back to module contents

Page 35: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

TIME SERIES ANALYSISTime series decomposed into

Trend Seasonality Cycle Randomness

And Forecast generated from these components

module 8: Production Planning

Back to main index exit back to module contents

Page 36: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Stochastic modelling ( Box and Jenkins)

Various processes eg.Autoregressive (AR) order pMoving average (MA) order qARMA order (p,q)ARIMA order (p,d,q)

are used to fit the most appropriate model.These models are accurate (for short term demand forecasting) but highly cumbersome to develop.

module 8: Production Planning

Back to main index exit back to module contents

Page 37: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Past Data

ForecastGeneration

ManagerialJudgement

&Experience

ForecastControl

Current Data

ModifiedForecast

Forecasting System

module 8: Production Planning

Back to main index exit back to module contents

Page 38: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Moving Range Chart to Control Forecasts

MR = | (Ft -Dt) - (Ft-1 - Dt-1) |

(Moving Range)

MR = MR / (n – 1) ( There are n-1 moving ranges for n period)

Upper Control Limit (UCL) = + 2.66 MR

Lower Control Limit ( LML) = - 2.66 MR

module 8: Production Planning

Back to main index exit back to module contents

Page 39: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

VARIABLE TO BE PLOTTED = (Ft - Dt)

01020

30

-10

20

-20

30

-30 Month

(Control Chart for Example)

module 8: Production Planning

Back to main index exit back to module contents

Page 40: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SUMMARY

Importance of forecasting in planning

Various Methods of forecasting Subjective methods like opinion polls & Delphi Moving Averages & Exponential Smoothing Trend extrapolation by regression Causal models Time series decomposition

Forecast Control

module 8: Production Planning

Back to main index exit back to module contents

Page 41: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

2. The Analysis of Time Series

module 8: Production Planning

Back to main index exit back to module contents

Page 42: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CORRELATION

module 8: Production Planning

Back to main index exit back to module contents

Page 43: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CORRELATION vs REGRESSION?

Correlation examines if there is an association between two variables,

and if so to what extent.

Regression establishes an appropriate relationship between the variables

X

Y

module 8: Production Planning

Back to main index exit back to module contents

Page 44: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

r = 0

SCATTER DIAGRAM

*

*

*

** *

** *

***

**

**

* *

**

*

*

** * *

r > 0 r < 0

Positive correlation Negative correlation

No correlation Non-linear association

module 8: Production Planning

Back to main index exit back to module contents

Page 45: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

THE CORRELATION COEFFICIENT

Pearson’s correlation coefficient, r

= (1/n) Sum [(X- X) (Y-Y)]

sigma X sigma Y

(The numerator is the

Co-variance between X and Y)

module 8: Production Planning

Back to main index exit back to module contents

Page 46: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

METHODS OF COMPUTATION

Direct computations using the formulaCumbersome and lengthy computations

Short-cut or the U-V method Involves any conveniently assumed meanSuitable scaling of variables

module 8: Production Planning

Back to main index exit back to module contents

Page 47: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

S. No. X Y x=X-X

y=Y-Y

x2 y2 xy

1 50 700 21 274 441 75,076 5,754

2 50 650 21 274 441 50,176 4,704

3 50 600 21 174 441 30,276 3,654

4 40 500 11 74 121 5,476 814

5 30 450 1 24 1 576 246 20 400 -9 -26 81 676 2347 20 300 -9 -126 81 15,876 1,134

8 15 250 -14 -176 196 30,976 2,464

9 10 210 -19 -216 361 46,656 4,104

10 5 200 -24 -226 576 51,076 5,424

Total 290 4260 0 0 2,740 3,06,840

28,310

Advertisement expenditure (X) vs Sales (Y) figures for 10 years in Lacs of Rupees.

module 8: Production Planning

Back to main index exit back to module contents

Page 48: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

   

X = 290/10 = 29 : Y = 4260/10 =426 r = Σxy /[ Σx2Σy2]1/2 = 28310/ (2740 * 306840)1/2 = 0.976 Coefficient of Determination = r2 = 0.953  

module 8: Production Planning

Back to main index exit back to module contents

Page 49: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

WHAT IS REGRESSION?

Discovering how a dependent variable (Y) is related to one or more independent variables (X)

Y

X

Y = f(X)

module 8: Production Planning

Back to main index exit back to module contents

Page 50: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CRITERION FOR BEST FIT?

Y = f(X)

Mean error Minimize ? Mean absolute error Sum of Squares of Errors

Least Squares Criterion is the generally preferred criterion

Positiveerror

Negativeerror

module 8: Production Planning

Back to main index exit back to module contents

Page 51: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

FIITING IN A STRAIGHT LINE

• Ft = a + bt is the equation of the line to be fitted• Ft is the fitted function for time t• Dt is the actual demand for period t• Past data is available for n periods• Parameters a & b have to be estimated from the data using least squares criterion

module 8: Production Planning

Back to main index exit back to module contents

Page 52: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LEAST SQUARES NORMAL EQUATIONS

SSE = Σ(Dt – Ft)2 = Σ (Dt- a – bt)2

To minimize (SSE)

d(SSE)/da = Σ 2(Dt – a –bt)(-1) = 0

d(SSE)/db = Σ 2(Dt – a – bt)(-t) = 0

Or a (n) + b (Σ t) = Σ Dt

a(Σt) + b (Σ t2) = Σ t Dt

module 8: Production Planning

Back to main index exit back to module contents

Page 53: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LEAST SQUARES NORMAL EQUATIONS (2)

These are two linear simultaneous equations in the two unknown parameters a and b which can be solved by any of the well known methods eg Cramer’s Rule.

These equations are called

Least Squares Normal Equations

module 8: Production Planning

Back to main index exit back to module contents

Page 54: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

a (n) + b (Σ t) = Σ Dt ( Least Squares Normal

a(Σt) + b (Σ t2) = Σ t Dt Equations)

Σ Dt Σ t

a = Σ tDt Σt2 = ΣDt Σt2 – Σt ΣtDt

n Σt n Σt2 – (Σt)2

Σt Σt2

n ΣDt

b = Σt ΣtDt = n ΣtDt - Σt ΣDt

n Σt n Σt2 – (Σt)2

Σt Σt2

module 8: Production Planning

Back to main index exit back to module contents

Page 55: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ORGANIZING COMPUTATIONS

S. No ti Di tiDi ti2

1 t1 D1 t1D1 t12

2 t2 D2 t2D2 t22

         

n tn Dn tndn tn2

Totals ∑ti ∑ Di ∑tiDi ∑ti2

module 8: Production Planning

Back to main index exit back to module contents

Page 56: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COMPUTATIONAL SIMPLIFICATIONS

By choosing an origin and scale of data such that

Σ t = 0

the values of the parameters become

a = Σ Dt / n

b = Σ tDt / Σ t2

(This is useful for equally spaced data with even or odd number of data points)

module 8: Production Planning

Back to main index exit back to module contents

Page 57: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DEMAND HISTORYMonth Demand

Jan 199 Feb 202 Mar 199 Apr 208 May 212 Jun 194 Jul 214 Aug 220 Sep 219

Oct 234 Nov 219 Dec 233

module 8: Production Planning

Back to main index exit back to module contents

Page 58: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

REGRESSION

J F M A M J J A S O N D J190

200

210

220

230

Dem

and

Month (t)

Actual Data 218

246

Ft = 193 + 3t(Regression Line)

Forecast for next

JAN

1 2 3 4 5 6 7 8 9 10 11 12 13

232

module 8: Production Planning

Back to main index exit back to module contents

Page 59: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Standard error of estimate = (Dt - Ft)2

= 7.32WhereDt = actual demand for period tFt = forecast for period tn = no. of data pointsf = degrees of freedom lost (2 in this

case)95 % confidence limits for forecast of next

JAN ~ 232 14 (2 sigma limits)

t=1,n

n-f

module 8: Production Planning

Back to main index exit back to module contents

Page 60: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Common Regression Functions

dt

t

dt’ forecast

dt actual demand (for time period t)

dt’ = a + bt (parameters a, b)

Linear

module 8: Production Planning

Back to main index exit back to module contents

Page 61: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

t

dt’ = a + u Cos (2/n)t + v Sin (2/n)t (parameters a, u, v)

Cyclic

module 8: Production Planning

Back to main index exit back to module contents

Page 62: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

t

dt’ = a +bt + u Cos (2/n)t + v Sin (2/n)t (parameters a,b,u, v)

Cyclic withGrowth

module 8: Production Planning

Back to main index exit back to module contents

Page 63: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

dt

tdt’ = a +bt + ct2 (parameters a,b,c)

Parameters Determined by Minimizing the Sum of Squares of errors,

Quadratic

module 8: Production Planning

Back to main index exit back to module contents

Page 64: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

2. Analysis of Time series

module 8: Production Planning

Back to main index exit back to module contents

Page 65: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COMPONENTS OF A TIME SERIES

Trend, Tt

Seasonality St

Cycle Ct

Randomness Rt

module 8: Production Planning

Back to main index exit back to module contents

Page 66: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MULTIPLICATIVE MODEL

Xt = Tt * St * Ct * Rt

Time t Identify

Tt

St

Ct

Rt

Obtain Xt

module 8: Production Planning

Back to main index exit back to module contents

Page 67: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DE-SEASONALIZING THE TIME SERIES

If the time series represents a seasonal pattern of L periods, then by taking a moving average Mt of L periods, we would get the mean value for the year. This would be free of seasonality and contain little randomness (owing to averaging)

Thus Mt = Tt * Ct

module 8: Production Planning

Back to main index exit back to module contents

Page 68: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DETERMINATIN OF THE TREND

To the de-seasonalized series, a suitable trend line could be fitted using RegressionThe choices could beLinearQuadraticExponentialOther

module 8: Production Planning

Back to main index exit back to module contents

Page 69: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ESTIMATING THE CYCLE COMPONENT

After the Trend Tt has been estimated

one can use

Ct = Mt / Tt

to estimate the Cycle Component, Ct

module 8: Production Planning

Back to main index exit back to module contents

Page 70: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DETERMINATION OF SEASONAL INDICES

To isolate seasonality, one could simply divide the original series by the moving average

Xt/ Mt = Tt *St* Ct* Rt /Tt *Ct

= St * Rt

Averaging over same months eliminates randomness and yields seasonality indices

module 8: Production Planning

Back to main index exit back to module contents

Page 71: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

PROCEDURE FOR DECOMPOSTION

1 Decompose the time series into its components Find seasonal component Deseasonalize the demand Find trend component

2 Forecast future values of each component Project trend component into the future Multiply trend component by seasonal component

module 8: Production Planning

Back to main index exit back to module contents

Page 72: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 1

Past Sales Average Sales Seasonal Factor (1000/4)

Spring200 250 200/250 = 0.8Summer 350 250 350/250 = 1.4Fall 300 250 300/250 = 1.2Winter150 250 150/250 = 0.6

Total 1000

module 8: Production Planning

Back to main index exit back to module contents

Page 73: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 1(contd)

Expected Average Sales Seasonal Factor next year demand (1100/4) Next year forecastSpring 275 * 0.8 = 220Summer 275 * 1.4 = 385Fall 275 * 1.2 = 330Winter 275 * 0.6 = 165

Total 1100

module 8: Production Planning

Back to main index exit back to module contents

Page 74: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 2

Quarter Amount

I- 2000 300II- 2000 200III- 2000 220IV- 2000 530

Quarter Amount

I - 2001 520II- 2001 420III- 2001 400IV- 2001 700

Computing Trend & Seasonal Factor

on a 2 year demand history

module 8: Production Planning

Back to main index exit back to module contents

Page 75: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 2 (contd 1)

Quarter Demand

2000I 300II 200III 220IV 5302001I 520II 420III 400IV 700

From Trend Equation Ratio of Seasonal Tt = 170+55t Actual / Factor Trend

225 1.33 I 1.25 280 0.71 II 0.78335 0.66 III 0.69390 1.36 IV 1.25

445 1.17500 0.84555 0.72610 1.15

module 8: Production Planning

Back to main index exit back to module contents

Page 76: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 2 (contd 2)Forecast for 2002 using Trend and Seasonal factors

I – 2002 [170+ 55*09] 1.25 = 831II –2002 [170+ 55*10] 0.78 = 562III-2002 [170+ 55*11] 0.69 = 535IV- 2002 [170 + 55*12] 1.25 = 1,038

Trend * Seasonal factor = Forecast

module 8: Production Planning

Back to main index exit back to module contents

Page 77: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 3

For the given demand history prepare a forecast using decomposition

Period Actual Period Actual

1 300 5 416 2 540 6 7603 885 7 11914 580 8 760

module 8: Production Planning

Back to main index exit back to module contents

Page 78: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 3 (Contd 1)Period Actual Period Seasonal Deseasonalized x Y Average Factor Demand

1 300 358 0.527 568.992 540 650 0.957 564.093 885 1038 1.529 578.924 580 670 0.987 587.795 416 0.527 789.016 760 0.957 793.917 1191 1.529 779.088 760 0.987 770.21Total 5432 2716 8.0Average 679 679 1.0

module 8: Production Planning

Back to main index exit back to module contents

Page 79: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 3 (Contd 2)

Period x Deseazonalized demand, y x2 xy 1 568.99 1 569.0 2 564.09 4 1128.23 578.92 9 1736.74 587.79 16 2351.25 789.01 25 3945.0 6 793.91 36 4763.47 779.08 49 5453.68 770.21 64 6161.7Su ms 5432 204 26,108.8Average 679

module 8: Production Planning

Back to main index exit back to module contents

Page 80: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 3 (Contd 3)The regression equation for deseasonalized data:

26108 – (8) (4.5) (679) = 39.64 (slope of st. line) 9204) – (8) )(4.5)2

a = Y – bx = 679- 39.64(4.5) = 500.6 (intercept of st.line)

Thus, Y = 500.6+ 39.64x

is the result of the deseasonalized regression line

b =

module 8: Production Planning

Back to main index exit back to module contents

Page 81: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE 3 (Contd 4)

Forecasts for the next four quarters of the following year

Period Trend Seasonal Final

Forecast Factor Forecast

9 857.4 * 0.527 = 452.0

10 897.0 * 0.957 = 858.7

11 936.7 * 1.529 = 1431.9

12 976.3 * 0.987 = 963.4

module 8: Production Planning

Back to main index exit back to module contents

Page 82: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

APPLICATION OF AUTO-CORRELATION

Random data

Trend

Seasonal

lag

lag

lag

Autocorrelation (range –1 to 1) plotted on the x-axis

module 8: Production Planning

Back to main index exit back to module contents

Page 83: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CONCLUSIONS

Choice of forecasting technique Problem context Accuracy desired Cost Planning horizon

Importance of Correlation and Regression in analysis of Time Series Least Squares Normal Equations with examples

Time series decomposition Components (Trend, seasonal, cycle & random) Deseasonalization Re-construction of the time series

module 8: Production Planning

Back to main index exit back to module contents

Page 84: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CONCLUSIONS (Contd)

Three illustrative examples of decomposition

Use of Auto-correlations to identify the kind of time seriesRandomTrend Seasonality

module 8: Production Planning

Back to main index exit back to module contents

Page 85: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

3. Aggregate Production Planning: Basic Concepts

module 8: Production Planning

Back to main index exit back to module contents

Page 86: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

AGGREGATE PRODUCTION PLANNING

Concerned with planning overall production of

all products combined (in tonnes of steel,

litres of paint etc.) Over a planning horizon

(generally next 3 to 6 months) for a given

(forecast) demand schedule.

module 8: Production Planning

Back to main index exit back to module contents

Page 87: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

CapacitiesCost

Commitments

Forecast ofDemand

Aggregate Production

Plan

Work force

M/c TimeAllocation over planning horizon

module 8: Production Planning

Back to main index exit back to module contents

Page 88: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

MANAGEMENT OPTIONS TO MEET FLUCTUATING

DEMANDBuild inventories in slack periods in anticipation of higher demands later in planning horizon.Carry backorders or tolerate lost sales during peak periods.Use over time in peak periods, under time in slack periods to vary output, while holding work force and facilities constant

module 8: Production Planning

Back to main index exit back to module contents

Page 89: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Vary capacity by changing size of work force through hiring and firing

Vary capacity through changes in plant and equipment (generally long term option)

Each option involves cost (tangible or intangible). Aim in aggregate production planning is to choose best option.

module 8: Production Planning

Back to main index exit back to module contents

Page 90: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

KINDS OF COSTS INVOLVED

Procurement Costs

Production Costs

Inventory holding Costs

Shortage losses associated with backorders and lost sales

Costs of increasing / decreasing work force

Cost of overtime / under time

Cost of changing production rates (Set ups, opportunity losses etc)

module 8: Production Planning

Back to main index exit back to module contents

Page 91: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Period Expected Demand

Cumulative Demand

1 100 100

2 180 280

3 220 500

4 150 650

5 100 950

6 200 950

7 250 1200

8 300 1500

module 8: Production Planning

Back to main index exit back to module contents

Page 92: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Period Expected Demand

Cumulative Demand

9 260 1760

10 250 2010

11 240 2250

12 210 2460

13 140 2600

EXPECTED SALES FOR A ONE YEAR PLANNING HORIZON BROKEN INTO 13 (4 WEEK) PERIODS

module 8: Production Planning

Back to main index exit back to module contents

Page 93: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

GRAPHICAL PROCEDURE

1 2 3 4 5 6 7 8 9 10 11 12 13

500

1000

1500

2000

2500

3000

0

Plan 1 - - Constant Production: 200/period

Plan 2 - - Varying Production. 150 /period Period 1 - 5

250 /period Period 6 - 11

175 /period Period 12 - 13

Actual Cumulative Demand

module 8: Production Planning

Back to main index exit back to module contents

Page 94: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Analysis of plan1Period Prod. Inv. Back

Order Capacity Change

Over Time

Sub Contract

1 200 100 0 +20 0 0

2 200 120 0 0 0 0

3 200 100 0 0 0 0

4 200 150 0 0 0 0

5 200 250 0 0 0 0

6 200 250 0 0 0 0

7 200 200 0 0 0 0

8 200 100 0 0 0 0

module 8: Production Planning

Back to main index exit back to module contents

Page 95: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Analysis of plan1

Period Prod. Inv. Back Order

Capacity Change

Over Time

Sub Contract

9 200 40 0 0 0 0

10 200 0 10 0 0 0

11 200 0 50 0 0 0

12 200 0 60 0 0 0

13 200 0 0 0 0 0

module 8: Production Planning

Back to main index exit back to module contents

Page 96: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Analysis of plan2Period Prod. Inv. Back

Order Capacity Change

Over Time

Sub Contract

1 150 50 0 -30 0 0

2 150 20 0 0 0 0

3 150 0 50 0 0 0

4 150 0 50 0 0 0

5 150 0 0 0 0 0

6 250 50 0 +50 40 10

7 250 50 0 0 40 10

8 250 100 0 0 40 10

module 8: Production Planning

Back to main index exit back to module contents

Page 97: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Analysis of plan2

Period Prod. Inv. Back Order

Capacity Change

Over Time

Sub Contract

9 250 0 10 0 40 10

10 250 0 10 0 40 10

11 250 0 0 0 40 10

12 175 0 35 -25 0 0

13 175 0 0 0 0 0

module 8: Production Planning

Back to main index exit back to module contents

Page 98: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ASSUMPTIONSAll shortages backlogged

Regular Time Capacity = 200 units/period

Max. Overtime = 20% of Regular Time Capacity

Overtime Preferable to Subcontract

Assumed Initial Inventory = 0

Initial Regular Time Prodn. Capacity = 180

module 8: Production Planning

Back to main index exit back to module contents

Page 99: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

NATURE OF COSTS AND SOLUTION PROCEDURES

Production Inventory Cost Linear Cost

Cost

•LP

•Simplified Transportation

•Transportation

Xt It

Ct (

Xt)

0

module 8: Production Planning

Back to main index exit back to module contents

Page 100: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

NATURE OF COSTS AND SOLUTION PROCEDURES

Production Inventory Cost Convex Cost

Cost

•Transportation

(after piece wise linearization

•HMMS ( LDR)

(quadratic cost)Xt It

Ct (

Xt)

0

module 8: Production Planning

Back to main index exit back to module contents

Page 101: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

NATURE OF COSTS AND SOLUTION PROCEDURES

Production Inventory CostConcave and Cost

Piecewise Concave Cost

•Dynamic Programming

(Shortest path Wangner / Whitin)Xt It

Ct (

Xt)

0

module 8: Production Planning

Back to main index exit back to module contents

Page 102: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LINEAR DECISION RULESHolt, Modigliani, Muth & Simon (HMMS) 1955

(Study in large paint manufacturing unit)

Wt = Work force level in period t, t =1,…..T

Xt = Aggregate prodn.level in period t

It = Actual aggregate net inventory at end of period t

It* = Desired (ideal) aggregate net inventory at end of period t

module 8: Production Planning

Back to main index exit back to module contents

Page 103: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COSTS INCURRED IN PERIOD IN PERIOD t

1. Regular time payroll cost

C1Wt + C13

2. Work force change cost

C2 (Wt - Wt-1 - C11 )2

Wt

Wt - Wt-1

module 8: Production Planning

Back to main index exit back to module contents

Page 104: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

3. Overtime Cost

C3 (Xt - C4 Wt)2 + C5Xt - C6 X Wt + C12XtWt

4. Inventory related costs

C7 (It - It*)2 = C7 (It - C8 - C9Dt)2

LDR W1*

X1 *

Linear fns. of Dt, W0, I0

module 8: Production Planning

Back to main index exit back to module contents

Page 105: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

Other Methods To Handle Aggregate Planning

Linear Programming Formulation(Hanssmann & Hess)

Search Decision Rules(Taubert)

Goal Programming Formulation(Multiple goals)

Parametric production planning(Jones)

Management coefficients model(Bowman)

module 8: Production Planning

Back to main index exit back to module contents

Page 106: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SUMMARY

Aggregate Production Planning relevant for fluctuation demands for medium term horizons (6 months -1 year)A simple graphical procedure that generates good solutions by examining the demand pattern was presentedVarious ways to meet a fluctuating demand were consideredA summary of solution procedures including the Linear Decision Rules were indicated.

module 8: Production Planning

Back to main index exit back to module contents

Page 107: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

4. Aggregate Production Planning:Modelling Approaches

module 8: Production Planning

Back to main index exit back to module contents

Page 108: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SOLUTION TECHNIQUES

Linear costsLinear ProgrammingTransportation Model

Piecewise linear and Convex costsHolt, Modigliani, Muth and Simon’s LDRsTransportation Model

Concave and Arbitrary CostsNetwork based ModelNon linear programming

module 8: Production Planning

Back to main index exit back to module contents

Page 109: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LP : DEFINITION OF VARIABLES

r,v = cost /unit produced during regular time and overtime respectivelyPt, Ot = units produced during regular time and overtime, respectivelyH,f = hiring and layoff costs per unit, respectivelyAt, Rt = number of units increased or decreased, respectively, during consecutive periodsC = inventory costs [per unit per periodDt = sales forecastMt, Yt = Available regular time and overtime capacities respectively

module 8: Production Planning

Back to main index exit back to module contents

Page 110: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LP: OBJECTIVE FUNCTION

Min C (production, hiring, layoffs, overtime, undertime and inventory)

= r Pt + h At + f Rt + v Ot + c It

module 8: Production Planning

Back to main index exit back to module contents

Page 111: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

LP: CONSTRAINTS

Pt <= Mt, t=1,2, , k

Ot<= Yt, t= 1,2, , k

It=It-1 + Pt +Ot-Dt , t= 1, 2, , k

At >= Pt-Pt-1 t= 1,2, , k

Rt >= Pt-1 – Pt t= 1,2, k

(All variables non-negative)

module 8: Production Planning

Back to main index exit back to module contents

Page 112: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

TRANSPRTATION MODELPeriod (month) 1 2 3 4Demands 100 105 200 95Production capacity(units)

Regular time 100 80 120 60Overtime 40 40 50 30

Production Costs (Rs) Regular time 16 20 22 18Overtime 24 30 30 26

Holding cost/unit/period (Rs) 2 2 4 5Initial on hand inventory (units) 50 unitsFinal desired inventory (units) 20 units

module 8: Production Planning

Back to main index exit back to module contents

Page 113: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 50

R1 100

O1 40

R2 80

O2 40

R3 120

O3 50

R4 60

O4 30

100 105 200 95 20 50 570

Setting up the Transportation Problem

module 8: Production Planning

Back to main index exit back to module contents

Page 114: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0 2 4 8 13 0

50

R1 16 18 20 24 29 0 100

O1 24 26 28 32 37 0 40

R2 20 22 26 31 0 80

O2 30 32 36 41 0 40

R3 22 26 31 0 120

O3 30 34 39 0 50

R4 18 23 0 60

O4 26 31 0 30

100 105 200 95 20 50 570

Introducing Unit Costs

module 8: Production Planning

Back to main index exit back to module contents

Page 115: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2 4 8 13 0

50/0

R1 16 50

18 20 24 29 0 100/50

O1 24 26 28 32 37 0 40

R2 20 22 26 31 0 80

O2 30 32 36 41 0 40

R3 22 26 31 0 120

O3 30 34 39 0 50

R4 18 23 0 60

O4 26 31 0 30

100 105 200 95 20 50 570

Satisfying 1st Period Demand

module 8: Production Planning

Back to main index exit back to module contents

Page 116: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2 4 8 13 0

50/0

R1 16 50

18 50

20 24 29 0 100/50/0

O1 24 26 28 32 37 0 40

R2 20 55

22 26 31 0 80/25

O2 30 32 36 41 0 40

R3 22 26 31 0 120

O3 30 34 39 0 50

R4 18 23 0 60

O4 26 31 0 30

100 105 200 95 20 50 570

Satisfying 2nd Period Demand

module 8: Production Planning

Back to main index exit back to module contents

Page 117: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2

4 8 13 0

50/0

R1 16 50

18 50

20 24 29 0 100/50/0

O1 24 26

28 40

32 37 0 40/0

R2 20 55

22 25

26 31 0 80/25/0

O2 30

32 36 41 0 40

R3 22 120

26 31 0 120/0

O3 30 15

34 39 0 50/35

R4 18 23 0 60

O4 26 31 0 30

100 105 200 95 20 50 570

Satisfying 3rd Period Demand

module 8: Production Planning

Back to main index exit back to module contents

Page 118: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2 4 8 13 0

50/0

R1 16 50

18 50

20 24 29 0 100/50/0

O1 24 26 28 40

32 37 0 40/0

R2 20 55

22 25

26 31 0 80/25/0

O2 30 32 36 41 0 40

R3 22 120

26 31 0 120/0

O3 30 15

34 5

39 0 50/35/30

R4 18 60

23 0 60/0

O4 26 30

31 0 30/0

100 105 200 95 20 50 570

Satisfying 4th Period Demand module 8: Production Planning

Back to main index exit back to module contents

Page 119: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2 4 8 13 0

50/0

R1 16 50

18 50

20 24 29 0 100/50/0

O1 24 26 28 40

32 37 0 40/0

R2 20 55

22 25

26 31 0 80/25/0

O2 30 32 36 41 0 40

R3 22 120

26 31 0 120/0

O3 30 15

34 5

39 20

0 50/35/30/10

R4 18 60

23 0 60/0

O4 26 30

31 0 30/0

100 105 200 95 20 50 570

Satisfying final inventory restrictions module 8: Production Planning

Back to main index exit back to module contents

Page 120: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

D1 D2 D3 D4 Ifinal Dummy I in 0

50 2 4 8 13 0

50/0

R1 16 50

18 50

20 24 29 0 100/50/0

O1 24 26 28 40

32 37 0 40/0

R2 20 55

22 25

26 31 0 80/25/0

O2 30 32 36 41 0 40

40/0

R3 22 120

26 31 0 120/0

O3 30 15

34 5

39 20

0 10

50/35/30/10/0

R4 18 60

23 0 60/0

O4 26 30

31 0 30/0

100 105 200 95 20 50 570

Satisfying Dummy restrictions

module 8: Production Planning

Back to main index exit back to module contents

Page 121: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

OPTIMAL SOLUTION

Total Cost of optimal solution = Sum of (unit cost x

quantity) = Rs 10370 for the planning horizon

This includes the costs of production on regular and overtime and the costs of holding inventories

module 8: Production Planning

Back to main index exit back to module contents

Page 122: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

OPTIMAL PRODUCTION PLAN

Period 1

Period 2 Period 3 Period 4

Regular time production

100 80 120 60

Overtime production

40 ----

(-40)

40

(-10)

30

module 8: Production Planning

Back to main index exit back to module contents

Page 123: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

NETWORK FLOW PROCEDURE

General cost structure

Linear Non-linear arbitrary Concave with set ups

Nature of Inventory Holding and Shortage Costs

It ItIt

cost

module 8: Production Planning

Back to main index exit back to module contents

Page 124: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

PRODUCTION COST

Qty Qty Qty

Cos

t of

Pro

duct

ion

Linear Piecewise linear Piecewise linear convex concave with set up

module 8: Production Planning

Back to main index exit back to module contents

Page 125: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

EXAMPLE PROBLEM

Four period problem (t = 1, 2, 3, 4)Production in period t involves a set up cost At

and a unit variable cost ct for raw materials, utilities, labour etc

Ct(Xt) = At + ct Xt , if Xt >0 = 0, if Xt =0

Linear holding costs (no shortage)

At

ct

Xt

Ct(

Xt)

module 8: Production Planning

Back to main index exit back to module contents

Page 126: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

PROBLEM DATA

Period 1 Period 2 Period 3 Period 4

Demand

(units)10 20 5 15

Set up

(Rs)100 120 120 140

Variable cost (Rs/unit)

8 9 10 10

Holding cost (Rs/unit)

2 4 5 7

module 8: Production Planning

Back to main index exit back to module contents

Page 127: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SETTING UP THE NETWORK

0 1 2 3 4

For N periods there will be N+1 nodes and N(N+1)/2 arcs, withN emanating from Node 0, N-1 from Node 1,…,1 from Node N-1

module 8: Production Planning

Back to main index exit back to module contents

Page 128: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ARC INTERPRETATIONS

Mjk = Cost of producing in period (j+1) for

the requirements of the periods

(j+1), (j+2), … (k). (j<k)

j k

module 8: Production Planning

Back to main index exit back to module contents

Page 129: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COST COMPUTATIONS I

M01= A1+c1(D1)

M02 =A1 + c1 (D1+D2) +h1(D2)

M03 =A1 + c1 (D1+D2+D3) + h1 (D2+D3)+ h2 (D3)

M04 = A1 +c1 (D1+D2+ D3+D4) + h1 (D2+D3+ D4) +

h2(D3+ D4) + h3( D4)

M12 = A2 +c2(D2)

M13 = A2 +c2(D2+ D3) + h2(D3)

M14= A2 + c2 (D2+D3+D4)+ h2 (D3+D4) +h3 (D4)

module 8: Production Planning

Back to main index exit back to module contents

Page 130: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COST COMPUTATIONS II

M23 = A3 + c3(D3)

M24 = A3 + c3(D3+D4) + h3 (D4)

M34 = A4 + c4 (D4)

module 8: Production Planning

Back to main index exit back to module contents

Page 131: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COMPUTATION OF ARC LENGTHS

M01 = 100+ 8(10) = 180

M02 = 100+8(30) +2(20) = 380

M03 = 100+8(35) +2(25) + 4(5) = 450

M04 = 100 + 8(50) +2(40) +4(20) +5(15) = 735

M12= 120 +9(20)= 300

M13 = 120+9(20)+ 4(5) = 365

M14 = 120 + 9(40) +4(20) +5(15) = 635

module 8: Production Planning

Back to main index exit back to module contents

Page 132: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

COMPUTATION OF ARC LENGTHS

M23 = 120+ 10(5) = 170

M24 = 120+10(20) +5(15) = 395

M34 = 140+10(15) = 290

module 8: Production Planning

Back to main index exit back to module contents

Page 133: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SETTING UP THE NETWORK

0 1 2 3 4M01=180

M02= 380

M03= 450

M04= 735

M12= 300

M13=365

M14 = 635

M23=170

M24= 395

M34=290

module 8: Production Planning

Back to main index exit back to module contents

Page 134: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DETERMINING THE SHORTEST PATH IN THE

NETWORK

0 1 2 3 4M01=180

M02= 380

M03= 450

M04= 735

M12= 300

M13=365

M14 = 635

M23=170

M24= 395

M34=290

0 180 380 450 735

module 8: Production Planning

Back to main index exit back to module contents

Page 135: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

DETERMINING THE OPTIMAL PRODUCTION PLAN

The Shortest path is M04 which yields the optimal production plan with a total cost of Rs 735.

Period

1 2 3 4

Production

50 -- -- --

module 8: Production Planning

Back to main index exit back to module contents

Page 136: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

ARC INTERPRETATIONS(for the problem with shortages)

Mjk = Minimum Cost of producing for the

requirements of the periods

(j+1), (j+2), … (k). (j<k)

(Notice that production may take place

in any period between (j+1), (j+2),… (k) )

j k

module 8: Production Planning

Back to main index exit back to module contents

Page 137: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SUMMARY

LP is a versatile tool to handle Aggregate Production Planning Problems with a variety of linear costs and constraintsThe Transportation Model is capable of dealing with problems with piecewise linear convex costs (regular time, overtime, subcontracting) No shortage case handled by a simple greedy procedure Case with shortages treated by regular transportation

problem procedure

module 8: Production Planning

Back to main index exit back to module contents

Page 138: Project and Production Management Module 8 Production Planning over the Short Term Horizon Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical

SUMMARY II

The case of concave and arbitrary costs can be solved using a shortest path procedure on a network. Both cases with and without shortages

can be handled

Sample problems for both procedures were solved to illustrate the procedures

module 8: Production Planning

Back to main index exit back to module contents