56
Lecture at Nanyang Technical Univerity 16th January 2015 Lessons learned from international underground projects during 30 years Professor emeritus Einar Broch NTNU; Norwegian University of Science and Technology Trondheim, Norway

Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

  • Upload
    lyxuyen

  • View
    220

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Lecture at Nanyang Technical Univerity

16th January 2015

Lessons learned from international

underground projects during 30 years

Professor emeritus Einar Broch

NTNU; Norwegian University of Science and Technology

Trondheim, Norway

Page 2: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Geology of Norway

Two thirds: Precambrian rocks. Gneiss

dominating (granites, gabbros and quartzite).

One third: Paleozoic rocks. Gneisses,

mica-schists and greenstones + sandstones,

shales, limestones.

Typical hard rock province.

Folding, faulting and high tectonic stresses

influence the stability in tunnels and

underground caverns

Page 3: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

TUNNELS AND UNDERGROUND WORKS FOR

HYDROPOWER PROJECTS

• The development of underground hydropower projects in Norway

• Applying the experience from air cushions to gas storage caverns

• Roof stability of large underground powerhouses.

• Lessons learned from water tunnels around the world

• Concluding remarks

Page 4: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Norwegian hydroelectric power capacity and

accumulated length of tunnels excavated for the period

1950 – 1990

Page 5: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

NORWEGIAN HYDROPOWER PROJECTS

• 99% of a total annual production of 125 TWh of

electric energy is generated from hydropower

• Of the world's 600 - 700 underground powerhouses

200 are located in Norway

• More than 4000 km of hydropower tunnels.

• 2 – 4 % of the tunnels are lined with concrete or

shotcrete

Page 6: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Development of

the general lay-

out of

hydroelectric

plants in

Norway.

Page 7: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

EARLY REASONS FOR GOING

UNDERGROUND

• Traditional design was to bring the water to the powerhouse through a steel penstock

• Both the penstock and the powerhouse were above ground structures.

• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the years 1919-21 because of shortage of steel after the war

• Water heads varied from 72 to 152 m.

Page 8: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

DEVELOPMENT AFTER 1945

• After the Second World War, underground location of powerhouses was given preference based on safety considerations

• Rapid advances in rock excavation methods soon showed that this was the most economic solution.

• Underground solutions also gave freedom of layout independent of the surface topography.

• Underground location of the powerhouse is now chosen whenever sufficient rock cover is available.

Page 9: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Early underground hydropower stations

Page 10: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Modern underground hydropower station

Page 11: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Steelfibre

reinforced

shotcrete arch

Rock bolt

supported crane

beam.

Page 12: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Exposing and illuminating the gneissic rock wall at

Tafjord K5 hydropower station

Page 13: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Extension of the Nedre Vinstra hydropower

station

Page 14: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Development of

the general lay-

out of

hydroelectric

plants in

Norway.

UNLINED

PRESSURE

SHAFTS

Page 15: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

The development of unlined pressure shafts and

tunnels in Norway

Page 16: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Plan and

cross section

of an

underground

hydropower

plant with

unlined

waterways.

CROSS SECTION THROUGH THE WATERWAY

LINING LINING

PLAN OF AN UNDERGROUND HYDROPOWERPLANT WITH UNLINED WATERWAY

TR

AN

SPO

RT TUNNEL & SURGE CH

AM

BE

R

TAILRACE TUNNEL

GATETURBINE

TRASHRACK

PRESSURESHAFT

CONCRETE PLUG ACCESS TUNNEL

STEEL & CONCRETE

Page 17: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Development of

the general lay-

out of

hydroelectric

plants in

Norway.

AIR CUSHION

SURGE

CHAMBER

Page 18: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Plan and

profile of

the Ulset

air

cushion

surge

chamber

53 m

plan

section A - A

A

A

unlined rock

unlined rock

headrace flow

headracepressuretunnel

air cushion surge chamber

53 m

connectiontunnel

el. 599

el. 595

air cushion

water bed

Page 19: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Plan and

profile of the

Torpa air

cushion

surge

chamber plug

Plan

Vertical section

cavern

connectiontunnel toheadrace

connectiontunnel

air pressure4.44 Mpa (abs.)

water bed

water-curtainborehole

water-curtainborehole

water-curtaingallery

Page 20: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Main data for compressed air storage

Page 21: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

PRINCIPLES FOR STORING OF GAS IN

UNLINED ROCK CAVERNS

• Internal storage pressure must be sustained by the minimum in-situ rock stress to avoid hydraulic splitting

• The ground water pressure and the gradient of the water seepage towards the cavern provides containment

• Ground water infiltration from ‘curtains’ of drill-holes supplements the natural ground water

• The Norwegian authorities require a safety margin of 15m water head above the storage pressure

Page 22: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

GAS STORAGE - GROUTING

• If the rock mass is too permeable, grouting is

performed to obtain the required permeability.

• As a rule, grouting shall be performed as pre-

excavation grouting of the rock mass ahead of the

cavern, around the periphery

• Post- excavation grouting is limited to supplementing

pre-excavation grouting where required

Page 23: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Unlined gas storage development in

Norway

• Pressurised water tunnels up to 10 MPa

• LPG storage pressure up to 1 MPa at rock

temperature

• Refrigerated LPG storage down to – 42

degrees C at atm. pressure

• Air cushion chambers up to 8 MPa

Page 24: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Xiaolangdi Powerhouse (China)

• Span: 26 m, Length: 250 m, Heigth: 58 m

• Flatlying sandstone, Q = 8 – 12, RMR = 59 – 66

• Rock overburden: 85 – 115 m

• Original roof support: 8 and 12 m long rock bolts, spacing 1.5 m + 20 cm reinforced shotcrete

• Added support: 345 pieces of 25 m long tendon anchors, capacity 1500 kN

Page 25: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Flatlying sandstone in the roof of Xiaolangdi

powerhouse

Page 26: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Xiaolangdi

powerhouse

in China

Page 27: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Xiaolangdi Powerhouse (China)

Stability analyses of the cavern show:

• Displacements in walls are greater than in roof

• A natural 5 m thick crown arch is formed

• The grouted rock bolts contribute to the reduction of

the roof subsidence.

• Only small loads within limited lengths of the bolts

• Self-supported natural crown arch is established

Page 28: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Xiaolangdi Powerhouse (China)

• Tensioned cables have marginal reduction effect on

roof settlement

• Tension cables may increase wall displacement

• The upward support force counteracts the forming of

an arch

• Tensioned rock anchors may have a negative

influence on the stability of the roof in a cavern

Page 29: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Application of high tension cables apply upward

force to the cavern roof arch, thus might not work

as expected

Page 30: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Gjøvik

Olympic

Mountain

Hall

Span: 61m

Page 31: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Gjøvik Olympic Mountain Hall

Page 32: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Guavio tailrace

tunnel

(Colombia)

Page 33: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Guavio Tailrace Tunnel

Page 34: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

GUAVIO TAILRACE TUNNEL, COLUMBIA

• 7.Nov. 1983 water under high pressure in probe hole

25 m ahead of tunnel face

• Leakage increased rapidly to 7 l/sec.

• During following day two slides, leakages up to 40

l/sec and 70 l/sec

• 350 m3 of sand flushed into the tunnel

• Tunnel face moved 4 m

• Tunnel face was blocked by concrete

Page 35: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

GUAVIO TAILRACE TUNNEL, COLUMBIA

• During following months several attempts to reduce

groundwater level

• Many small inflows of sand , total 5,000 m3

• Impossible to reduce pore water pressure below 20

bars (Annual rainfall 4,000-5,000 mm)

Page 36: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

GUAVIO TAILRACE TUNNEL, COLUMBIA

• Decided to excavate 3.5 m diameter pilotunnel

and to grout a head of tunnel face.

• 15 months for excavation of 77 m pilot tunnel

• Several slides and inflows, total 15,000 m3

• Most serious water inflow 400 l/sec

Page 37: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Guavio Tailrace Tunnel

Page 38: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Guavio Tailrace Tunnel

• Final tunnel has diameter 8.5

• Radial grouting and drainage.

• Max. distance between grout holes 1.5 m

• Max. distance between drain holes 3.0 m

• All drilling through blow-out preventers

• Total amount of grout for pilot tunnel and final tunnel

was 15,000 m3

Page 39: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Grouting and drainage pattern for

enlargement of the Guavio tunnel

Page 40: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

GUAVIO TAILRACE TUNNEL, COLUMBIA

• The 77 m of tailrace tunnel was excavated by

roadheader in 1 m steps

• Heavy steel ribs, spacing 1 m and shotcrete

• Final support: circular concrete lining

• Tunnelling through the 77 m difficult zone completed

after 3.5 years

Page 41: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Guavio Tailrace Tunnel

Lysbilde_2.jpg

Page 42: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Plan and longitudinal section of the Lesotho

Highland Water Project.

Upper formation: Basalt, Lower formation: Sandstone

Page 43: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Dog-earing” in sandstone due to high vertical

stresses in tunnel in Lesotho

Page 44: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Dog-earing” in sandstone due to high

vertical stresses in tunnel in Lesotho

• Spalling developed very slowly several weeks after

the TBM excavation

• Spalling always occurred were the ratio of the uniaxial

strength/vertical stress was lower than 2.5

• Time dependent overstressing was also observed in

areas with ratios up to 4.0

Page 45: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Dog-earing” in sandstone due to high

vertical stresses in tunnel in Lesotho

Page 46: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Plan and longitudinal section of the Lesotho

Highland Water Project.

Upper formation: Basalt, Lower formation: Sandstone

Page 47: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Crazing” due to weathering in

amygdaloidal basalts

• The 45 km long, 5.0 m diameter Transfer tunnel was

basically dry during excavation.

• After some time cracking was observed in the few wet

places

• Caused by swelling smectite minerals and zeolites

• Comprehensive system for evaluation of the rock and

the need for support

Page 48: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

” ”Crazing” due to weathering in

amygdaloidal basalts

Page 49: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Crazing” due to weathering in

amygdaloidal basalts

Page 50: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

”Crazing” due to weathering in

amygdaloidal basalts

Page 51: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Glendoe HPP in Scotland

Page 52: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Collaps in headracetunnel Glendoe HPP

Page 53: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

Nessies oldemor

Page 54: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

CONCLUDING REMARKS

Hydropower tunnels are special because:

• During excavation they are filled with air

• During operation they are filled with water

Some rocks and particularly some gouge material in

weakness zones are sensitive to water.

Stability problems if not properly supported.

Worst case is full tunnel collapse, - has happened in four

projects: Norway(1989), Scotland(2009), Chile(2011),

Peru (2012).

Page 55: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

CONCLUDING REMARKS

Many rocks are not sensitive to water.

Leaving hydropower tunnels basically unlined gives

considerable cost savings.

Minot rock falls are accepted. Rock trap needed at the

end of the unlined tunnel.

Page 56: Professor emeritus Einar Broch - cee.ntu.edu.sg · PDF file• Four Norwegian hydropower stations with unlined pressure shafts were put into operation during the ... water seepage

CONCLUDING REMARKS

Internal water pressure in hydropower tunnels can be counter-acted by localising the tunnels or shafts deep enough.

Considerable cost and time saving if steel lining can be avoided.

From the operation of unlined air cushions we have learned that also air and gas under high pressure can be stored underground.

Only fantasy sets limits to the utilization of the underground.