Proceedings of the 105 th SEIAA meeting held on 26 th September 2015 at Room No. 709, M.S Building, Bangalore . Members present : - 1. Dr. H.S. Ramesh - Chairman, SEIAA 2. Dr. H.R. Rajmohan - Member, SEIAA 3. Sri. Ramachandra - Member Secretary, SEIAA The Chairman welcomed the members and initiated the discussion. The subjects discussed and the decisions made under each of the agenda point are as follows: 105.1 Confirmation of the proceedings of 104 th SEIAA Meeting held on 14 th September 2015. Proceedings of 104 th SEIAA Meeting held on 14 th September 2015 was read and as there were no comments the same was accepted. 105.2 Action Taken reports on the proceedings of 101 st SEIAA Meeting held on 25 th July 2015, 102 nd SEIAA Meeting held on 14 th August 2015, 103 rd SEIAA Meeting held on 29 th August 2015 and 104 th SEIAA Meeting held on 14 th September 2015. The Authority perused the action taken reports on the proceedings of 101 st SEIAA Meeting held on 25 th July 2015, 102 nd SEIAA Meeting held on 14 th August 2015 and 103 rd SEIAA Meeting held on 29 th August 2015 are enclosed. The Authority noted the action taken. 105.3 Deferred Project (For Invite): Residential Apartment at Survey No. 21/1 and 12, Chikkanagamangala Village, Sarjapura Hobli, Anekal Taluk, Bangalore Urban District of M/s. M.J.Infrastructure, (SEIAA 37 CON 2015) It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 225 Units with BF + GF + 4 UF on a plot area of 14,012.24 Sq.mts and with total built up area of 34,346.67 Sqm. Total water requirement of project is 151.85 KLD. The subject was discussed in the SEAC meeting held on 5 th & 6 th June 2015 and 17 th & 18 th August 2015. The Committee has recommended to SEIAA for issue of

Proceedings of the 105 SEIAA meeting held on 26 ...environmentclearance.nic.in/writereaddata/FormB/agenda/...Residential Apartment at Survey No. 21/1 and 12, Chikkanagamangala Village,

  • Upload
    lediep

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

Proceedings of the 105th SEIAA meeting held on 26th September 2015 at Room No. 709, M.S Building, Bangalore.

Members present: -

1. Dr. H.S. Ramesh - Chairman, SEIAA 2. Dr. H.R. Rajmohan - Member, SEIAA 3. Sri. Ramachandra - Member Secretary, SEIAA

The Chairman welcomed the members and initiated the discussion. The subjects discussed and the decisions made under each of the agenda point are as follows:

105.1 Confirmation of the proceedings of 104th SEIAA Meeting held on 14th September 2015.

Proceedings of 104th SEIAA Meeting held on 14th September 2015 was read and as there were no comments the same was accepted.

105.2 Action Taken reports on the proceedings of 101st SEIAA Meeting held on

25th July 2015, 102nd SEIAA Meeting held on 14th August 2015, 103rd SEIAA Meeting held on 29th August 2015 and 104th SEIAA Meeting held on 14th September 2015.

The Authority perused the action taken reports on the proceedings of 101st SEIAA Meeting held on 25th July 2015, 102nd SEIAA Meeting held on 14th August 2015 and 103rd SEIAA Meeting held on 29th August 2015 are enclosed. The Authority noted the action taken.

105.3 Deferred Project (For Invite):

Residential Apartment at Survey No. 21/1 and 12, Chikkanagamangala Village, Sarjapura Hobli, Anekal Taluk, Bangalore Urban District of M/s. M.J.Infrastructure, (SEIAA 37 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 225 Units with BF + GF + 4 UF on a plot area of 14,012.24 Sq.mts and with total built up area of 34,346.67 Sqm. Total water requirement of project is 151.85 KLD.

The subject was discussed in the SEAC meeting held on 5th & 6th June 2015 and 17th & 18th August 2015. The Committee has recommended to SEIAA for issue of

105th SEIAA Meeting Proceedings Dated 26th September 2015

2

Environmental Clearance, with a condition that the proponent shall maintain more greenery on the mother earth and with the following observations:

1. The proposal is a low rise building having B+G+4UF only and the conceptual plan have been approved by the competent authority.

2. The proponent clarified that sufficient ventilation and lighting has already been provided by providing open to sky spaces wherever required in order to maintain the good ventilation and light.

3. NOC dated 17.03.2014 from the Village Panchayat for water supply has been submitted by the proponent and the water balance also calculated fresh water demand at the rate of 55 LPCD as per the norms prescribed for rural water supply and the scheme for meeting the additional requirement has been given.

4. Since the ground coverage is only 50%, there is a scope for providing more than 30% of the greenery on the mother earth.

The Authority during the meeting held on 29th August 2015 had perused the proposal and took note of the recommendation of SEAC. The Authority noted that the following observations were raised during the 99th SEIAA meeting held on 29th June 2015:

“The Authority perused the proposal and took note of the recommendation of SEAC. The Authority observed that the residential units are compactly arranged without adequate space for ventilation. The project does not have required recreational area and the greenbelt. The internal circulation roads are narrow and having varying width. The proposal do not have any proof assured source of water supply. The picturesque view of the drawing gives an indication of possible high level of indoor pollution in the proposed residential units.”

The Authority after discussion decided to get the following information for further considerations:

1. Modification in the conceptual plan keeping the observations of the Authority made on 29th June 2015.

2. Details of Recreation Ground Area. 3. Details of greenbelt with provision for at least 33% of the plot area. 4. Details of the internal circulation roads of at least 6m width and drive

way of 8 m width. 5. Possibility of high level indoor pollution and the proposed modified

plan for preventing indoor pollution.

The Authority also decided to invite the proponent.

The Authority perused the reply submitted by the proponent on 21.09.2015. The proponent appeared before the Authority and explained the proposal in brief.

The Authority opined that the reply submitted vide letter dated 21.09.2015 is incomplete and do not address the issues raised by SEIAA completely. The proponent sought for some time for submission of revised reply as directed by the Authority. The Authority after discussion decided to consider after the receipt of revised reply. The Authority also decided to invite the proponent.

105th SEIAA Meeting Proceedings Dated 26th September 2015

3

105.4 Fresh Projects:

Mining Projects:

105.4.1 Building Stone Quarry Project, Sy.No.617 (P) of Sattigeri Village, Soudatti Taluk, Belagavi District. (2 Acres) (QL No.1540) of Sri N B Hiremath, #7, Renuka Nivas, 3rd Cross, Hosur Hubli -21, Dharwad District (SEIAA 701 MIN 2015)

This is a Renewal proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted. 105.4.2 Building Stone Quarry Project, Sy.No.617 (P) & 618 (P) of Sattigeri

Village, Soudatti Taluk, Belagavi District. (4 Acres) (QL No.1539) of Sri N B Hiremath, #7, Renuka Nivas, 3rd Cross, Hosur Hubli -21, Dharwad District (SEIAA 702 MIN 2015)

This is a Renewal proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.3 Building Stone Quarry Project, Sy.No.139 of Arjunnagi Village, Afzalpur Taluk, Gulbarga District. (1 Acre) (QL No.956) of Sri Mohaseen Ahmed Patel, Arjunnagi Village, Afzalpur Taluk, Gulburga District (SEIAA 705 MIN 2015)

This is a Renewal proposal seeking Environmental clearance for quarrying of Building Stone in 1-00 Acre, Patta Land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

4

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind with a condition that, since the railway track is passing nearby (300 m from the project site), blasting is to be synchronized with movement of trains.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of Building stone limiting the production to 70% of the proposed production, as recommended by SEAC and with a condition that, since the railway track is passing nearby (300 m from the project site), blasting is to be synchronized with movement of trains.

105.4.4 Building Stone Quarry Project, Sy.No.63 of Gollarahalli Village, Hospet Taluk & Bellary District (4-0 Acres) (QL No.422) of Sri S. Sridhar D/N0. 148/A, 22 Ward, Housing Board Colony, J.R.Nagar, Bellary Road, Hospet -583201 Bellary District (SEIAA 714 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres, Government Revenue Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted. The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.5 Building Stone Quarry Project, Sy.No.39 (P) of Kanivenarayanapur Village, Chikkaballapura Taluk & District (10 Acres) (QL No.119) of M/s. Sri Manjunath Stone Pvt. Ltd. #24 (56/A-34), 1st main Road, Vyalivakaval, Bangalore -560003 (SEIAA 721 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 10-00 Acres, Government Revenue Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105th SEIAA Meeting Proceedings Dated 26th September 2015

5

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.6 Building Stone Quarry Project, Sy.No.90 of Mekhali Village, Raibag Taluk & Belgaum District (2-0 Acres) of M/s. Tarade Brothers Constructions (P) Ltd.# 582, Chinchali, Raibag Taluk, Belgaum District -591220 (SEIAA 722 MIN 2015)

This is a proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 80% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 80 % of the proposed production, as recommended by SEAC.

105.4.7 Building Stone Quarry Project, Sy.No.24 (P) of Medihala Village, Kolar

Taluk & District (10-0 Acres) (QL No.930) of Sri C Sonnegowda, # 67A, Munniramappa Garden, 1st Cross K.E.B Road, Sanjaynagar, Bangalore-94 (SEIAA 723 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 10-00 Acres, Government Land. The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted. The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105th SEIAA Meeting Proceedings Dated 26th September 2015

6

105.4.8 Black Granite Quarry Project, Sy.No.248 (P) of Melmala Village, Chamarajanagar Taluk & Dist. (2 Acres) (QL No.256) of M/s. Bharath Granites Pvt. Ltd. #S-113, 1st Main, Kodandaramapura Main Road, Malleshwaram, Karnataka (SEIAA 724 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Black Granite in 2-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information:

1. An undertaking that approach road to be asphalted. 2. An undertaking that the waste shall be dumped in their own land being

converted for the non agricultural purpose.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of black granite as per approved quarry plan, subject to submission of undertakings sought by SEAC.

105.4.9 Building Stone Quarry Project, Sy.No.39 (P), Kanivenarayanapur Village, Chikkaballapura Taluk & Dist. (6-20 Acres) (QL No.117) of M/s. Mines and Rocks Productions India Pvt. Ltd. #24 (56/A-34), 1st main Road, Vyalivakaval, Bangalore -560003 (SEIAA 725 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 6-20 Acres Government Revenue Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted and corrected mineable reserve calculations.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted and corrected mineable reserve calculations.

105.4.10 Building Stone Quarry Project, Sy.No.137/A, Hosakeri Village, Hagaribommanahalli Taluk & Bellary Dist. (5-0 Acres) (QL No.453) of Sri T. Gopal S/o. Bheemavva, Myasikeri, 33rd Ward, Hospet, Bellary District (SEIAA 726 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 5-00 Acres Government land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

7

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.11 Building Stone Quarry Project, Sy.No.233 of Moraba Village, Kudligi Taluk, Bellary Dist. (5 Acres) of Sri M Maresh S/o.M.Basappa, 14th Ward, Old Chapparada Hally, Sandur, Bellary District(SEIAA 729 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 5-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.12 Black Granite Quarry Project, Sy.Nos.604, 605/1B, 619/3, 712 (P) of Gumballi Village, Yelandur Taluk, Chamarajanagar Dist. (2-08 Acres) of Sri K Varadaraju & Sri D. Nagaraju S/o.Krishnappa Gowda, Chamrajanagar(SEIAA 730 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Black Granite in 2-08 Acres, Patta land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that the waste shall be dumped in their own land being converted for non agricultural purpose.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of black granite as per approved quarry plan, subject to submission of an

105th SEIAA Meeting Proceedings Dated 26th September 2015

8

undertaking from the proponent that the waste shall be dumped in their own land being converted for non agricultural purpose.

105.4.13 Building Stone Quarry Project, Sy.No.53 (P) of Dhanamantahalli Village, Kolar Taluk & Dist. (5 Acres) (QL No.623) of Smt. Gowramma D/o Ramaiah, #24, MR Garden, KEB Layout, Sanjaynagar, Bangalore- 94 (SEIAA 731 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 5-00 Acres, Gomala land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking that top soil will be preserved.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan subject to submission of an undertaking that top soil will be preserved.

105.4.14 Building Stone Quarry Project, Sy.No.102 (P) of Bastwad Village, Raibag Taluk & Belgaum Dist. (4 Acres) of M/s. Balaji Earth Movers Raibag Road, Harugeri, Raibag Taluk, Belgaum District (SEIAA 733 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking from the proponent that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking from the proponent that approach road to be asphalted.

105.4.15 Building Stone Quarry Project, Sy.No.26 (P) of H Thimmapura Village,

Tarikere Taluk & Chikkamagalur Dist. (1-0 Acre) of Sri B S Ramesh Belenahalli Village & Post, Tarikere Taluk, Chikkamagalur District (SEIAA 734 MIN 2015)

This is an new proposal seeking Environmental clearance for quarrying of building stone in 1-00 Acres, Government land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

9

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan.

105.4.16 Building Stone Quarry Project, Sy.No.12 (P) of Aragal Village, Arakalagud Taluk & Hassan Dist. (1-0 Acre) (QL No.442) of Sri T S Rithesh S/o.T.N.Shashidhar, Aragal Village, Arakalagud Taluk, Hassan District (SEIAA 735 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 1-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 60% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 60 % of the proposed production, as recommended by SEAC.

105.4.17 Building Stone Quarry Project, Sy.No.123 (P) of Bilakundi Village, Gokak Taluk & Belagavi Dist. (8-0 Acres) of Sri Kallappa Ramappa Kudari S/o. Sri.Ramappa Kudari, Sajjihal (Tapasi) Village, Gokak Taluk, Belagavi District (SEIAA 737 MIN 2015)

This is a New proposal seeking Environmental clearance for quarrying of Building Stone in 8-00 Acres, Govt. Gyrana Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The committee observed that, in Bilakundi village of Gokak Tq. & Belagavi Dist. only already five (5) proposals to a total extent of 40.50 Acres in Sy. No’s 2,2(P) & 76(P) are considered in the 146th SEAC meeting. And if the total area of mining exceeds 25 Ha or 62 Acres, the mining activity as per EIA Notification 2006, should be treated as B1 category and General Conditions shall apply. Therefore it is decided to consider this proposal having mining area of 8.00 Acres, so that the total mining area will be within 25 Ha.

The Committee after discussion decided to recommend the proposal to SEIAA for issue of Environmental Clearance subject to submission of the following information.

1. A combined sketch covering all the quarry leases sanctioned by DMG in this village and total extent of mining duly approved by DMG.

105th SEIAA Meeting Proceedings Dated 26th September 2015

10

2. An undertaking that existing cart track (karab land) running in the quarry area should be left open for public.

3. An undertaking that approach road to be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.18 Building Stone Quarry Project, Sy.No.79/4 of Nandur B Village, Gulbarga Taluk & Gulbarga Dist. (2.31 Acres) of Sri Imam Sab #56/1, Bolewaas H.No: 1/1 to 1067, Gulburga Taluk, Gulbarga – 585103 (SEIAA 739 MIN 2015)

This is a New proposal seeking Environmental clearance for quarrying of Building Stone in 2.31 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. Revised Geological & Mineable reserve and five year production quantity duly approved by DMG.

2. An undertaking that approach road to be metalled. The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.19 Black Granite Quarry Project, Sy.No.57/2 of Yalachagere Village, Chamarajanagara Taluk & Dist. (2-35 Acres) of Sri Doddalingappa (SEIAA 740 MIN 2015)

This is a Renewal proposal seeking Environmental clearance for quarrying of Black Granite in 2-35 Acres, patta land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. Scheme foe disposal of quarry waste. An undertaking that the adjoining land shall be used for waste dumping after getting NA for the same and if NA is not obtained, quarry activity will be stopped.

2. Toe wall to be constructed at waste dump area for protection of quarry waste dump.

105th SEIAA Meeting Proceedings Dated 26th September 2015

11

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of black granite as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.20 Building Stone Quarry Project, Sy.No.380 (P) of Hirekoppa Village, Ramdurga Taluk, Belagavi Dist. (1-0 Acre) of Sri Channabasappa M. Dandin S/o.Sri. Murigeppa #164/8, Bagalkot, Bagalkot District (SEIAA 742 MIN 2015)

This is a New proposal seeking Environmental clearance for quarrying of Building Stone in 1-00 Acre, Govt. Gyrana Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to submission of an undertaking from the proponent that approach road will be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 70 % of the proposed production, as recommended by SEAC and subject to submission of an undertaking from the proponent that approach road will be asphalted.

105.4.21 Building Stone Quarry Project, Sy.No.614 (P) of Sattigeri Village,

Savadatti Taluk, Belagavi Dist. (2-0 Acres) of Sri Mahantesh Chinnappa Godi S/o.Sri.Chinnappa Mallappa Godi, # 403, Mirji Oni, H.No. 378 -411, Sattigeri Village, Savadatti Taluk, Belagavi District (SEIAA 743 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Govt. Gyrana Land. The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind. The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

12

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 70% of the proposed production, as recommended by SEAC.

105.4.22 Building Stone Quarry Project, Sy.No.381 (P) of Hirekoppa Village, Ramadurga Taluk, Belagavi Dist. (2-0 Acres) of Sri Mahantesh Madiwalappa Hadimani S/o. Sri. Madiwalappa Hadimani, # 301/1, Bikkannavar Oni, Savadatti (Rural) Saundatti Taluk, Belagavi District (SEIAA 744 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Govt. Gyrana Land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 80% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to submission of an undertaking from the proponent that approach road will be asphalted. The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 80 % of the proposed production, as recommended by SEAC and subject to submission of an undertaking from the proponent that approach road will be asphalted.

105.4.23 Building Stone Quarry Project, Sy.No.614 (P) of Sattigeri Village, Savadatti Taluk, Belagavi Dist. (4-0 Acres) of Sri Abhishek Basavaraj Iliger S/o. Sri. Basavaraj Iiiger, Plot No. 10 +11, S.No.186/6 1st Cross, Vidyanagar, Gokak, Gokak Taluk, Belagavi Distirict (SEIAA 745 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres, Govt. Gyrana Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to submission of an undertaking from the proponent that approach road will be asphalted.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone limiting the production to 70 % of the proposed

105th SEIAA Meeting Proceedings Dated 26th September 2015

13

production, as recommended by SEAC and subject to submission of an undertaking from the proponent that approach road will be asphalted.

105.4.24 Black Granite Quarry Project, Sy.Nos.123/1, 123/2 & 124/1 of Yanagalli Village, Chamarajanagar Taluk & Dist. (6-03 Acres) of Smt. Sumathi C/o. Yusuf Kamil Khan, Nagavalli Village & Post, Chamrajnagar Taluk and District (SEIAA 746 MIN 2015)

This is a renewal proposal seeking Environmental clearance for quarrying of Black Granite in 6-03 Acres, patta land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. A copy of GPA 2. An undertaking that the waste will be disposed off as building material &

will be sold to PWD contractors.

The Authority perused the proposal and took note of the recommendation of SEAC along with the reply submitted by the proponent vide letter dated 10.09.2015.

The Authority after discussion decided to issue Environmental Clearance for extraction of black granite as per approved quarry plan. 105.4.25 Black Granite Quarry Project, Sy.No.248 of Doddabellalu Village,

Piriyapatna Taluk, Mysuru Dist. (5 Acres) (QL No.552) of Smt. L K Kamalajammani No.4002, 19th Cross, K.R.Road, Banashankari 2nd Stage, Bengaluru -560070 (SEIAA 748 MIN 2015)

This is a Renewal proposal submitted seeking Environmental clearance for quarrying of Black Granite in 5-0 Acres, Govt. Gyrana land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of scheme for disposal off quarry waste.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of black granite as per approved quarry plan, subject to submission of scheme for disposal off quarry waste.

105.4.26 Building Stone Quarry Project, Sy.No.15 of Huralihalli Village,

Hosadurga Taluk, Chitradurga Dist. (2 Acres) of Sri G L Shivalingaswamy Owner, S/o. G.P.Lingegowda, Gondedahalli, Sokke Post, Tarikere Taluk, Chikkamangalore District (SEIAA 749 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Govt. Revenue Land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

14

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following.

1. An undertaking that the approach road will be made pucca by asphalting. 2. Revised soil and water analysis test report.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of the information sought by SEAC.

105.4.27 Building Stone Quarry Project, Sy.No.88 of Siddapura Village, Chitradurga Taluk, Chitradurga Dist. (2 Acres) of Sri R Thippeswamy S/o. Rudrappa. K.Gurukrupa Nilaya, Vidyanagar, 1st Main Road, Medehalli, Chitradurga District -577502 (SEIAA 750 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acre, Govt. Revenue Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of revised soil & water analysis report.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of revised soil & water analysis report.

105.4.28 Building Stone Quarry Project, Sy.No.57 of Matadakurubarahatti Village, Chitradurga Taluk, Chitradurga Dist. (1-0 Acre) of Sri A Mallikarjun S/o.H.Aanandappa 42 Ward, Mathadakurubarahatti, Chitradurga Taluk and District -577502 (SEIAA 751 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 1-00 Acre, Govt. Revenue Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following.

1. Revised Geological reserve calculation 2. EMP budget to be revised.

The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

15

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.29 Building Stone Quarry Project, Sy.No.26 of Kenchapura Village, Holalkere Taluk, Chitradurga Dist. (2-0 Acres) of Sri P Basavaraja Naik S/o.Putta Naik, Tuppadahalli Lambanihatti, Holalkere Taluk, Chitradurga District -577502 (SEIAA 752 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Govt. Revenue Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking to make approach road pucca by doing metalling.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking to make approach road pucca by doing metalling.

105.4.30 Building Stone Quarry Project, Sy.Nos.222/P1 & 370/2 of Vittlamudnuru Village, Bantwal Taluk, Dakshina Kannada Dist. of Sri Santosh Menezes S/o. Sri. Robert Menezes, Santhosh Mahal, Pachanadi Bondel Post, Mangalore Taluk, Dakshina Kannada District (SEIAA 753 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 3.13 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance,. subject to submission of an undertaking to make approach road pucca by doing metalling.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking to make approach road pucca by doing metalling.

105.4.31 Building Stone Quarry Project, Sy.Nos.222/P1 & 408/2 of Vittlamudnuru Village, Bantwal Taluk, Dakshina Kannada Dist. of Sri Santosh Menezes (SEIAA 754 MIN 2015)

This is a renewal proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Government land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

16

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking to make approach road pucca by doing metalling.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking to make approach road pucca by doing metalling.

105.4.32 Building Stone Quarry Project, Sy.Nos.62/6, 62/7 & 62/8 (P) of Ambevadi Village, Belgaum Taluk & Dist. (2-30 Acres) of Sri Kuber Basavaneppa Benakatti, Plot.No.790, 2nd Cross, Srinagar, Belgaum. (SEIAA 757 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 2-30 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following.

1. Copy of RTC showing karab (cart track) in their own land 2. Consent from adjoining land owner for use of his land foe approach road

purpose.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.33 Building Stone Quarry Project, Sy.No.39 of Kanivenarayanapura Village, Chikkaballapura Taluk & Dist. (2 Acres) (QL No.39) of M/s. Manjunatha Enterprises Sri.Byregowda Owner, # 289, Bettalasuru, Jalahobli, Bangalore North -562157 (SEIAA 758 MIN 2015)

This is a renewal proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following.

1. An undertaking to make approach road pucca by asphalting 2. Mitigation measures to protect the forest from fire. Provision to be made in

the EMP budget.

105th SEIAA Meeting Proceedings Dated 26th September 2015

17

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.34 Iron Ore Mines Project, Sy.Nos.368/2, 3, 4 & 369/112, 113 of Amingad Village, Hungund Taluk, Bagalkot Dist. (12 Acres) (4.86 Ha) (ML No.2642) of Sri Ravi Sangappa Sardesai GPA Holder - Sri Anil .M.Kothari, Ward No.1, Near Ayurvedic Hospital, Hanamasagar Road, Iikal -587 125, Bagalkot District (SEIAA 759 MIN 2015)

This is a renewal proposal seeking Environmental clearance for quarrying of Iron Ore Mines Project, in r 12-0 Acres, patta land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following.

1. Compliance to earlier issued EC 2. Impact on the surrounding agricultural lands due to emission of dust by

screening , crushing & transportation in the quarrying area.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of iron ore as per approved mining plan, subject to submission of information sought by SEAC.

105.4.35 Building Stone Quarry Project, Sy.No.75 (P) of Murundi Village, Arasikere Taluk, Hassan Dist. (1 Acre) (QL No.400) of Sri G B Siddesh S/o G.S.Basavaraju, # 3495, Lakshmipura, Behind BSNL, Arasikere, Hassan (SEIAA 760 MIN 2015)

This is a renewal proposal r seeking Environmental clearance for quarrying of Building Stone in r 1-0 Acre, Govt. Gomala land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of an undertaking to make approach road pucca by asphalting.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of an undertaking to make approach road pucca by asphalting.

105th SEIAA Meeting Proceedings Dated 26th September 2015

18

105.4.36 Black Granite Quarry Project, Sy.No.42 of Melur Village, Chamarajanagara Taluk & Dist. (2-19 Acre) of Sri Madappa (SEIAA 883 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Black Granite in 2-19 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The proponent has given a letter stating that the DMG has declared a cluster combining four quarry leases adjoining each other of same village (883 MIN 2015, 884 MIN 2015, 885 MIN 2015 & 886 MIN 2015) and all the four will do a common EMP and submit the report.

The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to submission of the following.

1. An undertaking from the proponent that approach road will be asphalted. 2. Scheme of disposal of wastage.

The Authority perused the proposal and took note of the recommendation of SEAC. The Authority noted that this is a proposal having a lease area of 2-19 Acres. As per SCHEDULE II A of the Karnataka Minor Mineral Concession (Amendment) Rules, 2013, minimum area for grant of quarry lease in case of Ornamental and decorative building stones is 2-20 Acres. Therefore, this lease area does not meet the minimum requirement of the said Rules. The Authority further noted that the Director, Department of Mines & Geology vide cluster Notification dated 23.07.2015 have declared Melur Cluster. However, no details of other leases coming under the said cluster or whether all such leases result into cluster situation as defined in the O.M. No. J-13012/12/2013-IA.II (I) of the Ministry of Environment and Forests, Government of India dated 24th December 2013 is forthcoming in the said Notification. No information with regard to formation of cluster association as required under Rule 8-R of the Karnataka Minor Mineral Concession (Amendment) Rules, 2013 is formed for the collective implementation of approved Environment Management Plan is forthcoming from the proposal. In view of the above observations, the Authority decided to refer the proposal back to SEAC for further appraisal with all the relevant details.

105.4.37 Black Granite Quarry Project, Sy.No.43/4 of Melur Village, Chamarajanagara Taluk & Dist. (1-14 Acre) of Sri Sadashivappa (SEIAA 884 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Black Granite in 1-14 Acre, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The proponent has given a letter stating that the DMG has declared a cluster

105th SEIAA Meeting Proceedings Dated 26th September 2015

19

combining four quarry leases adjoining each other of same village (883 MIN 2015, 884 MIN 2015, 885 MIN 2015 & 886 MIN 2015) and all the four will do a common EMP and submit the report. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to submission of the following.

1. An undertaking from the proponent that approach road will be asphalted.

2. Scheme of disposal of wastage.

The Authority perused the proposal and took note of the recommendation of SEAC.

In view of the observation made in the Agenda No. 105.4.36, the Authority decided to refer the proposal back to SEAC for further appraisal.

105.4.38 Black Granite Quarry Project, Sy.No.147/1A of Melur Village, Chamarajanagara Taluk & Dist. (0-33 Acres) of Sri Guruswamappa (SEIAA 885 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Black Granite Quarry in 0-33 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The proponent has given a letter stating that the DMG has declared a cluster combining four quarry leases adjoining each other of same village (883 MIN 2015, 884 MIN 2015, 885 MIN 2015 & 886 MIN 2015) and all the four will do a common EMP and submit the report. The Committee has recommended to SEIAA for issue of Environmental Clearance, after submission of the following.

1. An undertaking from the proponent that approach road will be asphalted. 2. Scheme of disposal of wastage.

The Authority perused the proposal and took note of the recommendation of SEAC. In view of the observation made in the Agenda No. 105.4.36, the Authority decided to refer the proposal back to SEAC for further appraisal. 105.4.39 Black Granite Quarry Project, Sy.No.43/3 of Melur Village,

Chamarajanagara Taluk & Dist. (1-14 Acres) of Sri Lingannachar (SEIAA 886 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Black Granite in 1-14 Acres, Patta Land.

105th SEIAA Meeting Proceedings Dated 26th September 2015

20

The subject was discussed in the SEAC meeting held on 5th September 2015. The proponent has given a letter stating that the DMG has declared a cluster combining four quarry leases adjoining each other of same village (883 MIN 2015, 884 MIN 2015, 885 MIN 2015 & 886 MIN 2015) and all the four will do a common EMP and submit the report. The Committee has recommended to SEIAA for issue of Environmental Clearance, after submission of the following.

1. An undertaking from the proponent that approach road will be asphalted.

2. Scheme of disposal of wastage.

The Authority perused the proposal and took note of the recommendation of SEAC.

In view of the observation made in the Agenda No. 105.4.36, the Authority decided to refer the proposal back to SEAC for further appraisal.

105.4.40 Building Stone Quarry Project, Sy.No.14 of Gollahalli Village, Kasaba Hobli, Chikkaballapur Taluk & Dist. (3-07 Acres) of Smt. P Prathiba (SEIAA 887 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone 3-07 Acres, Govt. Revenue Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of revised EMP budgetary provision by including construction of compound wall around the quarry.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan and subject to submission of information sought by SEAC.

105.4.41 Building Stone Quarry Project, Sy.No.36 of Bittanakurke Village, Tumkur Taluk & Dist. (25-0 Acres) of M/s. Priyadarshini Granites Pvt. Ltd. No.171, AECS Extension, 1st Phase, 1st Main Road, 1st Cross, Sanjaya Nagara, Bangalore. (SEIAA 838 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone in 25-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 4h September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of following information

1. An undertaking that approach road to be asphalted. 2. Revised EMP budgetary provision by including construction of

compound wall around the quarry and sufficient Check dams.

105th SEIAA Meeting Proceedings Dated 26th September 2015

21

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan and subject to submission of information sought by SEAC.

105.4.42 Building Stone Quarry Project, Sy.No.43 of Kunthihalli Village, Tumkur Taluk & Dist. (10-0 Acres) of M/s. Pacific Natura Biotech Pvt. Ltd. Sri.T.J.Sandeep, Managing Director, No.202, 2nd Main Road, 14th Cross, HIG Colony, RMV 2nd Stage, Bangalore-94 (SEIAA 839 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of building stone in 10-00 Acres, Government land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of following information

1. An undertaking that approach road to be asphalted. 2. Revised EMP budgetary provision by including construction of

compound wall around the quarry and sufficient Check dams. The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of building stone as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.43 Building Stone Quarry Project, Sy.No.23 of Thammanayakanahalli Village, Anekal Taluk, Bangalore Urban Dist. (2.023 Ha) of Sri M.C. Umesh (SEIAA 420 MIN 2015)

This is a new proposal seeking Environmental clearance for quarrying of Building Stone Quarry in 2.023 Ha, Govt. Revenue Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, limiting the production to 70% of the total estimated production keeping the minable area quantity and the sustainability of the mine in the mind and subject to verification of not exceeds 5 Ha within 500 m distance from the boundary of the quarry site.

The Authority perused the proposal and took note of the recommendation of

SEAC.

The Authority observed that as per the presentation, the proposed quarry lease area is said to be located at a distance of 500 meters from inter-State boundary. In such situation if the sum total of the mining lease area of the said project or

105th SEIAA Meeting Proceedings Dated 26th September 2015

22

activity and that of existing operating mines and mining projects which were accorded environment clearance and are located within 500 metres from the periphery of such project or activity equals or exceeds 5 ha., the project activity , then it attracts General Condition in which case it has to be appraised as category A activity. The Authority noted that this proposal has been appraised without ascertaining whether it attracts General Condition of not. Therefore the Authority decided to refer the proposal back to SEAC for re-appraisal if the activity do not attracts General Condition.

105.4.44 Multi-Colour Granite Quarry Project, Sy.No.169 of Doddamudavadi Village, Kanakapura Taluk, Ramanagara Dist. (4 Acres) of Sri Hidayathulla (SEIAA 449 MIN 2015)

This is an expansion proposal seeking Environmental clearance for quarrying of Multi Colour Granite Quarry in 4.00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of multi-colour granite as per approved quarry plan.

105.4.45 Pink Granite Quarry Project, Sy.No.124/2 (P) of Hulageri Village, Kustagi Taluk, Koppal Dist. (3 Acres) (QL No.721) of Sri T P Selvaraj (SEIAA 535 MIN 2015)

This is a renewal proposal seeking Environmental clearance for quarrying of Pink Granite Quarry in 3.00 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. Scheme of disposal of waste and an undertaking from the proponent to obtain NA for the adjoining land and if not NA obtained, the quarrying activity will be stopped.

2. Approach road will be made pucca by asphalting 3. Scheme for preservation of top soil 4. Revised EMP budget.

The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

23

The Authority after discussion decided to issue Environmental Clearance for extraction of pink granite as per approved quarry plan, subject to submission of information sought by SEAC.

105.4.46 Pink Granite Quarry Project, Sy.No.50/2/1B of Antarathana Village, Kustagi Taluk, Koppal Dist. (3-10 Acres) of Sri S M Sangam (SEIAA 539 MIN 2015)

This is a renewal proposal, seeking Environmental clearance for quarrying of Pink Granite Quarry in 3.10 Acres, Patta Land.

The subject was discussed in the SEAC meeting held on 5th September 2015.

The Committee has recommended to SEIAA for issue of Environmental Clearance.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environmental Clearance for extraction of pink granite as per approved quarry plan.

105.4.47 River Sand Quarrying Project, Gurupura River Bed, Sy.No.45/1 of Badaga Bellur, Sy.No.51/1 of Mogaru Village, Sy.No.13 of Mutturu Village, Bantwal & Mangaluru Taluks, Dakshina Kannada District (24 Ha). (Block Nos.21, 30, 31 & 32) (Cluster No.09) of District Sand Monitoring Committee, Dakshina Kannada District (SEIAA 1017 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Gurupura River bed. It is located at Cluster No.9 in Block No.21 (5 Ha) at Sy.No.45/1 of Badaga Bellur Village, Bantwal Taluk, Block No.30 (5 Ha) and Block No.31 (5 Ha) at Sy.No.51/1 of Mogaru Village, Mangalore Taluk, Block No.32 (9 Ha) at Sy.No.13 of Muttur Village, Mangalore Taluk, Dakshina Kannada District for a total extent of 24.0 Ha (59.30 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105th SEIAA Meeting Proceedings Dated 26th September 2015

24

105.4.48 River Sand Quarrying Project, Gurupura River Bed, Sy.No.28 of Ammunje Village, Sy.No.52 of Karianagala Village, Sy.No.26 of Ulaibettu Village, Sy.Nos.26, 63 of Adduru Village, Bantwal & Mangaluru Taluks, Dakshina Kannada District (24.96 Ha) (Block Nos.17, 24, 25, 26 & 27) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1018 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Gurupura River bed. It is located at Cluster No.7 of Block No.17 (4.98 Ha) at Sy.No.28 and 52 Karigala Village, Bantwal Taluk, Block No.24 (5 Ha) & Block No. 25 (5 Ha) at Sy.No.26 of UlabettuVillage, Mangalore Taluk and Block No.26 (4.98 Ha) & Block No.27 (5 Ha) at Sy.No.26 and 63 of Addur Village, Mangalore Taluk, Dakshina Kannada District for a total extent of 24.96 Ha (61.68 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.49 River Sand Quarrying Project, Gurupura River Bed, Sy.Nos.46, 7 & 8 of Karianagala Village, Sy.Nos.11, 1 & 38 of Tenka Ulipadi Village, Bantwal & Mangaluru Taluks, Dakshina Kannada District (24.96 Ha) (Block Nos.18, 19 & 20, 28 29) (Cluster No.08) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1019 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina District seeking Environmental Clearance for River Sand Mining at Gurupura River bed. It is located at Cluster No.8 of Block No.18 (5 Ha), 19(5 Ha) & Block No.20 (4.98 Ha) at Sy.No.46, 7, 8 Kariangala Village, Bantwal Taluk and Block No. 28 (4.98 Ha) & Block No. 29 (5 Ha)at Sy.No.11, 1 & 38 of Tenka Ulipadi Village, Mangalore Taluk, Dakshina Kannada District for a total extent of 24.96 Ha (61.68 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

105th SEIAA Meeting Proceedings Dated 26th September 2015

25

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.50 River Sand Quarrying Project, Kumardhara River Bed, Sy.No.112/1 of Kenya Village, Sullia Taluks, Dakshina Kannada District (5 Ha). (Block No.38) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1020 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Kumaradhara River bed. It is located at Block No.38 of Sy.No. 112/1, Kenya Village, Sulliya Taluk, Dakshina Kannada District for a extent of 5 Ha (12.56 Acres) .

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.51 River Sand Quarrying Project, Kumardhara River Bed, Sy.No.1 of Alankaru Village, Puttur Taluk, Dakshina Kannada District (5 Ha). (Block No.37) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1021 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Kumaradhara River bed. It is located at Block No.37 of Sy.No.1, Alankaru Village, Puttur Taluk, Dakshina Kannada District for an extent of 5.0 Ha (12.56 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

105th SEIAA Meeting Proceedings Dated 26th September 2015

26

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.52 River Sand Quarrying Project, Gundya River Bed, Sy.No.72/1 of Nooji Baltila Village, Puttur Taluk, Dakshina Kannada District (5 Ha). (Block No.36) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1022 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Gundya River bed. It is located at Block No.36 of Sy.No.72/1, Nooji Baltila village Puttur Taluk, Dakshina Kannada District for an extent of 5.0 Ha (12.56 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.53 River Sand Quarrying Project, Netravati River Bed, Sy.No.166 of Kokkada Village, Sy.No.264 of Bandaru Village, Beltangadi Taluk, Dakshina Kannada District (5 Ha). (Block No.2) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1023 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Netravathi River bed. It is located at Block No.22 of Sy.No.166 & Sy.No.264, Kokkada & Bandaru Village, Beltangadi Taluk, Dakshina Kannada District for an extent of 5.0 Ha (12.56 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

105th SEIAA Meeting Proceedings Dated 26th September 2015

27

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.54 River Sand Quarrying Project, Gurupura River Bed, Sy.No.48 of Kulavuru Village, Mangaluru Taluk, Dakshina Kannada District (5 Ha). (Block No.33) of District Sand Monitoring Committee, Dakshina Kannada District(SEIAA 1024 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Dakshina Kannada District seeking Environmental Clearance for River Sand Mining at Gurupura River bed. It is located at Block No.33 of Sy.No.33, KulavuruVillage, Mangalore Taluk, Dakshina Kannada District for an extent of 5.0 Ha (12.56 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.55 River Sand Mining Project at Ghataprabha River Bed, Block-1, adjacent to Sy. Nos. 35, 36, 40, 46, 47 & 37 of Bargavi Village, Mudhol Taluk, Bagalkote District (5.00 Ha) of District Sand Monitoring Committee, Bagalkote (SEIAA 1067 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Bagalkote District seeking Environmental Clearance for River Sand Mining at Ghataprabha River bed. It is located at Block No. 1, adjacent to Sy.No. 35,36,40,46,47 & 37 of Baragi village, Mudhol Taluk, Bagalkote District for an extent of 5.00 Ha (12-35 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

28

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.56 River Sand Mining Project at Ghataprabha River bed, Nagaral Sand Block Quarry, adjacent to Sy. Nos. 183, 185, 186, 187, 188, 189, 190, 191, 193, 194 & 196 of Nagaral Village, Mudhol Taluk, Bagalkote District (5.00 Ha) of District Sand Monitoring Committee (SEIAA 1068 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Bagalkote District seeking Environmental Clearance for River Sand Mining at Ghataprabha River bed. It is located at Block No. 1, adjacent to Sy. Nos. 183, 185, 186, 187, 188, 189, 190, 191, 193, 194 & 196 of Nagaral Village, Mudhol Taluk, Bagalkote District for an extent of 5.00 Ha ( 12-35 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.57 River Sand Mining Project at Ghataprabha River bed, Jhanjharakoppa Sand Block, adjacent to Sy. Nos. 116, 117, 118, 132 & 133 of Jhanjharakoppa Village, Mudhol Taluk, Bagalkote District (5.00 Ha) of District Sand Monitoring Committee (SEIAA 1069 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Bagalkote District seeking Environmental Clearance for River Sand Mining at Ghataprabha River bed, Jhanjharakoppa Sand Block. It is located at Block No. 1, adjacent to Sy. Nos. 116, 117, 118, 132 & 133 of Jhanjharakoppa Village, Mudhol Taluk, Bagalkote District for an extent of 5.00 Ha ( 12-35Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

29

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.58 River Sand Mining Project at Ghataprabha River bed, Block – 1 adjacent to Sy. Nos. 194, 196, 197, 198, 199, 200, 201, 202, 203, 204, 205 & 206 of Mulali Village, Mudhol Taluk, Bagalkote District (5.00 Ha) of District Sand Monitoring Committee (SEIAA 1070 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Bagalkote District seeking Environmental Clearance for River Sand Mining at Ghataprabha River bed. It is located at Block No. 1, adjacent to Sy.Nos. 194, 196, 197, 198, 199, 200, 201, 202, 203, 204, 205 & 206 of Mulali village, Mudhol Taluk, Bagalkote District for an extent of 5.00 Ha ( 12-35 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.59 River Sand Mining Project, at Kiru Hole River Bed, of Block No. 1 adjacent to Sy. No. 307 East & 335 to West of Bembaluru Village, Somavarpete Taluk, Kodagu District (5-00 Acres) of District Sand Monitoring Committee (SEIAA 1112 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Kiru Hole River bed. It is located at Block No. 1 adjacent to Sy.No. 307 East and 335 to West of Bembaluru village, Somavarpete Taluk, Kodagu District for an extent of 2.023 Ha ( 5 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105th SEIAA Meeting Proceedings Dated 26th September 2015

30

105.4.60 River Sand Mining Project, at Lakshmana Thirtha River Bed, of Block No. 1 adjacent to Sy. No. 24, 25, 25/1, in North & Sy. No. 3, 23, 23/2, 25/3 in South of Kotagere Village, Virajapete Taluk, Kodagu District (8-00 Acres) of District Sand Monitoring Committee, Kodagu District (SEIAA 1113 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Lakshmana Thirtha River bed. It is located at Block No. 1 adjacent to Sy.No: 24,25,25/1 in North & Sy.No: 3,23,23/2,25/3 in South of Kotagere village Virajapete Taluk, Kodagu District for an extent of 3.237 Ha ( 8 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.61 River Sand Mining Project, at Lakshmana Thirtha River Bed, of Block No. 2 adjacent to Sy. No. 64/8, 64/19, 64/16A, 64/13, 64/10, 64/2, 59 of Bekkisodaluru Village, Virajapete Taluk, Kodagu District (4.79 Acres) of District Sand Monitoring Committee, Kodagu District (SEIAA 1114 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Lakshmana Thirtha River bed. It is located at Block No. 2 adjacent to Sy.No. 64/8, 64/9, 64/16A, 64/13, 64/10, 64/2, 59 of Bekkisodaluru village, Virajapete Taluk, Kodagu District for an extent of 1.938 Ha (4.79Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105th SEIAA Meeting Proceedings Dated 26th September 2015

31

105.4.62 River Sand Mining Project, at Lakshmana Thirtha River Bed, of Block No. 3 adjacent to Sy. No. 35/3, 49/1, 57, 59 of Bekkisodaluru Village, Virajapete Taluk, Kodagu District (6.13 Acres) of District Sand Monitoring Committee, Kodagu District (SEIAA 1115 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Lakshmana Thirtha River bed. It is located at Block No. 3, adjacent to Sy.No. 35/3, 49/1, 57, 59 of Bekkisodaluru village, Virajpete Taluk, Kodagu District for an extent of 2.48 Ha ( 6.13 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105.4.63 River Sand Mining Project, at Lakshmana Thirtha River Bed, of Block No. 2 adjacent to Sy. No. 34/2, in North and Sy. Nos. 35/1, 35/2 of Kotagere Village, Virajapete Taluk, Kodagu District (8-00 Acres) of District Sand Monitoring Committee, Kodagu District (SEIAA 1116 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Lakshmana Thirtha River bed. It is located at Block No. 2, adjacent to Sy.No. 34/2 in North & Sy.No. 35/1, 35/2 of Kotagere village, Virajpete Taluk, Kodagu District for an extent of 3.237 Ha ( 8 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

105th SEIAA Meeting Proceedings Dated 26th September 2015

32

105.4.64 River Sand Mining Project, at Kaveri River Bed, of Block No. 1 adjacent to Sy. No. 1/1, 2/1, Hachchinadu Village, Somavarpete Taluk, Kodagu District (8-00 Acres) of District Sand Monitoring Committee, Kodagu District (SEIAA 1117 MIN 2015)

This is a proposal submitted by Member Secretary, District Sand Monitoring Committee, Kodagu District seeking Environmental Clearance for River Sand Mining at Kaveri River bed. It is located at Block No. 1, adjacent to Sy.No. 1/1, 2/1 of Hachchinadu village, Somavarpete Taluk, Kodagu District for an extent of 3.237 Ha ( 8 Acres).

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with the standard conditions that are being imposed for sand mining in the River bed and with a specific condition that the mining activity shall be undertaken only in the dry weather season.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to issue Environment Clearance for undertaking mining of river sand as per the approved quarry plan and with the standard conditions that are being imposed for river sand mining.

Construction Projects:

105.4.65 Residential Apartment at Sy. No. 103/1, Khatha No.216, Doddatogur Village, Begur Hobli, Bengaluru South Taluk, Bengaluru Urban District of M/s Sree & Sree Builders & Promoters, (SEIAA 94 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 351 units with Basement+Ground Floor+11 Upper Floor on a plot area of 17,502.50 Sq.mts (karab area = 607.02 Sq.m) and with total built up area of 54,578.58 Sqm. Total water requirement of project is 237 KLD.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. Scientific assessment of the availability of the water from the bore well in the project site

2. Revised water balance calculating fresh water demand at the rate of 55 LPCD as per the norms prescribed for rural water supply and the scheme for meeting the additional requirement

3. Revised rain water harvesting calculations 4. Proposal to provide an underpass to connect the other side of the project

site.

105th SEIAA Meeting Proceedings Dated 26th September 2015

33

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority observed that the parcel of land in Part-2 is not of any practical use or beneficial to the project activities, as it is bifurcated by a public road and the entire activity is concentrated on the land in Part-1

The Authority after discussion decided to get the following information, in addition to information sought by SEAC for further consideration:

1. Revised layout plan exclusively for the land in Part-1 without considering the land in Part-2.

2. Details of Kharab land duly marking it on layout plan. 3. Revised land-use plan such as ground coverage, park & open spaces,

greenbelt, parking area, etc. with respect to Part-1 only. 4. Source of water and NOC from the competent authority. 5. Enhance energy savings to at least 25%. 6. Revised quantification of MSW as per the standards. 7. Revised water balance with due emphasis for utilization of the

treated water. 8. Design of rainwater harvesting pit as per CGWA norms.

The Authority also decided to invite the proponent.

105.4.66 Residential Apartments at Plot No. 119, Kannamangala village, Devanahalli Taluk, Bangalore Rural District of M/s. Ozone Urbana Infra Developers Pvt. Ltd., (SEIAA 95 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 84 units with Basemen + Ground Floor + 3 upper floor on a plot area of 9191.55 Sq.mts and with total built up area of 23715.77 Sqm. Total water requirement of project is 57 KLD.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information.

1. An undertaking to treat the water using RO technology received from BWSSB and supplied to apartments.

2. Increase in the green belt area.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information, in addition to information sought by SEAC:

1. NOC from Gram Panchayat for supply of water. 2. Revised quantification of MSW as per the standards.

105th SEIAA Meeting Proceedings Dated 26th September 2015

34

3. Specific social commitment plan with budget, activity and time frame.

This clearance is subject to final outcome of the original application no.222 of 2014 before the Hon’ble National Green Tribunal, Principal Bench New Delhi.

105.4.67 Modification and expansion of Residential Apartment at Sy.no.7/1, 7/2, 7/3, 7/12, 16/3, 16/4, 16/5 (p), 16/9, 16/10, 16/11, 17/1(p) and 17/ 3, Gollahalli Village, Attibele Hobli, Anekal Taluk, Bangalore Urban District of M/s. Arattukulam Developers, (SEIAA 96 CON 2015)

It is a proposal seeking Environmental Clearance for expansion and modification of Residential Apartment of 224 units with Basement + Ground Floor + 14 Upper Floor on a plot area of 13607.44 Sq.mts and with total built up area of 42999.88 Sqm. (Enhancement from 30930.15 Sqm to 42999.88 Sqm). Total water requirement of project is 151 KLD.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, with a specific condition that the proponent shall use the entire excavated earth within the project site only.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information, with a specific condition that the proponent shall use the entire excavated earth within the project site only:

1. Revised parking calculations based on the requirement as per MoEF, BHK norms and BBMP norms providing for the maximum of the above requirements and parking plan for corresponding number of vehicles.

2. Justification for the new basement now proposed. 3. Specific social commitment plan with budget, activity and time

frame.

105.4.68 "Wynn Tower", Development of residential apartment at Sy. Nos. 11/2, 11/4, 11/5 and 11/6, Gottigere village, Uttarahalli Hobli, Bengaluru South Taluk, Bengaluru of M/s. Unishire Housing LLP (SEIAA 97 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 545 units with 2 Basement+Stilt+27 Upper Floor and club house on a plot area of 17,833.63 Sq.mts and with total built up area of 2B+Stilt+27UF and club house Sqm. Total water requirement of project is 380 KLD.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, subject to submission of the following information:

105th SEIAA Meeting Proceedings Dated 26th September 2015

35

1. Demand note of the BWSSB 2. Revised rain water harvesting calculations 3. Calculation of earthwork and its full utilization within the project site.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information, in addition to information sought by SEAC:

1. Proposal to enhance usage of treated/recycled water to reduce fresh water requirement and revised water balance chart.

2. Revised parking calculations based on the requirement as per MoEF, BHK norms and BBMP norms providing for the maximum of the above requirements and parking plan for corresponding number of vehicles.

3. Details of barrier free environment. 4. Specific social commitment plan with budget, activity and time

frame.

This clearance is subject to final outcome of the original application no.222 of 2014 before the Hon’ble National Green Tribunal, Principal Bench New Delhi.

105.4.69 Development Residential Apartment and a club house at Sy.No. 38/1 and 38/2, Choodasandra Village, Sarjapura Hobli, Anekal Taluk, Bengaluru of M/s G.R.C. Constructions, (SEIAA 99 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 210 units with Basement + Ground + 4 Upper Floor on a plot area of 11,057 Sq.mts and with total built up area of 29,391.58 Sqm. Total water requirement of project is 145 KLD.

The subject was discussed in the SEAC meeting held 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information:

1. Storm water management plan taking 5m level different into consideration.

2. Explore the possibility of enhancing drive way to 8 meters. 3. Revised parking calculations based on the requirement as per MoEF,

BHK norms and BBMP norms providing for the maximum of the

105th SEIAA Meeting Proceedings Dated 26th September 2015

36

above requirements and parking plan for corresponding number of vehicles.

4. Specific social commitment plan with budget, activity and time frame.

This clearance is subject to final outcome of the original application no.222 of 2014 before the Hon’ble National Green Tribunal, Principal Bench New Delhi.

105.4.70 Residential apartment with club house at Sy. No. 48/1, 48/6, 49/1, 49/2 and 49/3, Hallahalli village, Bidarahallli Hobli, K.R.Puram East, Bengaluru-560049 of M/s Casa Grands Pvt. Ltd. (SEIAA 100 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment with 13 Blocks (Block-1:GF+2UF, Block-2: GF + 2 UF, Block -3: GF + 2 UF, Block -4: GF + 2 UF, Block -5: GF + 2 UF, Block -6: GF + 2 UF, Block -7: GF + 2 UF, Block -8: GF + 2 UF, Block -9: GF + 2 UF, Block -10: GF + 2 UF, Block -11: GF + 2 UF, Block -12 Clubhouse: GF + 2 UF, Block -13 (EWS): GF + 2 UF on a plot area of 35,308.8 Sq.mts and with total built up area of 26,566.4 Sqm. Total water requirement of project is 87 KLD.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, after submission of the following information.

1. Revised rain water harvesting calculation

2. Revised water balance calculating fresh water demand at the rate of 55 LPCD as per the norms prescribed for rural water supply and the scheme for meeting the additional requirement.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information in addition to information sought by SEAC:

1. NOC from the Gram Panchayat for supply of water. 2. Revised parking calculations based on the requirement as per MoEF,

BHK norms and BBMP norms providing for the maximum of the above requirements and parking plan for corresponding number of vehicles.

3. Enhance energy savings to at least 35%. 4. Details of rainwater harvesting. 5. Details of Greenbelt development to at least 33% of the plot area. 6. Specific social commitment plan with budget, activity and time

frame.

This clearance is subject to final outcome of the original application no.222 of 2014 before the Hon’ble National Green Tribunal, Principal Bench New Delhi.

105th SEIAA Meeting Proceedings Dated 26th September 2015

37

105.4.71 Residential Apartment at Sy. No. 63, Khatha No.234/63, Pattanagere Vilalge, Kengeri Hobli, Bangalore South Taluk, Bangalore Urban District of M/s Panchmukhi Infrastructure, (SEIAA 101 CON 2015)

It is a proposal seeking Environmental Clearance for construction of Residential Apartment of 162 units with 3 Blocks in Basement + Ground + 9 Upper Floor on a plot area of 6,946.18 Sq.mts and with total built up area of 24,522.59 Sqm. Total water requirement of project is 110 KLD.

The subject was discussed in the SEAC meeting held on 5th September 2015. The Committee has recommended to SEIAA for issue of Environmental Clearance, after submission of the following information.

1. Revised water balance chart considering 95% of the total water demand as wastewater.

2. Scientific assessment of the availability of the water from the bore well in the project site

3. Revised rain water harvesting calculation

4. Revised hydrological study of the area influencing the surface water flow duly marking the ridges.

5. Quantification of the terrace area available for harnessing solar energy and an appropriate plan thereof with due calculations.

6. Project Proponent to plant fruit yielding and shade bearing tree species. 7. Demand note from BWSSB 8. CSR to be included in the EMP budget plan.

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority after discussion decided to clear the proposal for issue of Environmental Clearance subject to submission of following information in addition to information sought by SEAC:

1. Revised parking calculations based on the requirement as per MoEF,

BHK norms and BBMP norms providing for the maximum of the above requirements and parking plan for corresponding number of vehicles.

2. Revised water balance chart as per norms. 3. Details of Recreational Ground area with at least 15% of the plot

area. 4. Specific social commitment plan with budget, activity and time

frame.

This clearance is subject to final outcome of the original application no.222 of 2014 before the Hon’ble National Green Tribunal, Principal Bench New Delhi.

105th SEIAA Meeting Proceedings Dated 26th September 2015

38

105.5 Recommended for Closure:

105.5.1 Building Stone Quarry Project, Sy.No.23 of Thammanayakanahalli Village, Anekal Taluk, Bengaluru District. (4 Acres) (QL No.622) of M/s. G T B Enterprises (SEIAA 703 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“The proponent was invited to the meeting to provide required clarification. The proponent remained absent.

The committee observed that the quarry site is 500 m from the inter-state boundary. Also, already many proposals in this village are cleared by the committee. If the quarry site is located within 5Kms from the inter-state boundary, and if the total lease area exceeds 5 ha, it attracts general conditions of the EIA Notification. In such case the activity requires Environmental Clearance from the Ministry of Environment and Forests, Government of India.

The committee appraised the proposal and opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for

closure.” The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to provide one more opportunity and invite to the Authority meeting.

105.5.2 Building Stone Quarry Project, Sy.No.23 of Thammanayakanahalli Village, Anekal Taluk, Bengaluru District. (2 Acres) (QL No.625) of M/s. Sree Chakra Engineering Enterprises (SEIAA 704 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 2-00 Acres, Government Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“The proponent was invited to the meeting to provide required clarification. The proponent remained absent.

105th SEIAA Meeting Proceedings Dated 26th September 2015

39

The committee observed that the quarry site is 400 m from the inter-state boundary. Also, already many proposals in this village are cleared by the committee. If the quarry site is located within 5Kms from the inter-state boundary, and if the total lease area exceeds 5 ha, it attracts general conditions of the EIA Notification. In such case the activity requires Environmental Clearance from the Ministry of Environment and Forests, Government of India.

The committee appraised the proposal and opined that the appraisal cannot

be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for

closure.” The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to provide one more opportunity and invite to the Authority meeting.

105.5.3 Building Stone Quarry Project, Sy.No.23 of Thammanayakanahalli Village, Anekal Taluk, Bangalore District. (3-10 Acre) (QL No.623) of M/s. G T B Enterprises (SEIAA 706 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 3-10 Acres, Government Gomala Land.

The subject was discussed in the SEAC meeting held on 4th September 2015. The Committee has recommended the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“The proponent was invited to the meeting to provide required clarification. The proponent remained absent.

The committee observed that the quarry site is 700 m from the inter-state boundary. Also, already many proposals in this village are cleared by the committee. If the quarry site is located within 5Kms from the inter-state boundary, and if the total lease area exceeds 5 ha, it attracts general conditions of the EIA Notification. In such case the activity requires Environmental Clearance from the Ministry of Environment and Forests, Government of India.

The committee appraised the proposal and opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.” The Authority perused the proposal and took note of the recommendation of SEAC.

105th SEIAA Meeting Proceedings Dated 26th September 2015

40

The Authority decided to provide one more opportunity and invite to the Authority meeting.

105.5.4 Building Stone Quarry Project, Sy.No.343 of Thammanayakanahalli Village, Anekal Taluk & Bengaluru Dist. (4-0 Acres) (QL No.634) of M/s. Sree Chakra Engineering Enterprises (SEIAA 736 MIN 2015)

This is an existing proposal seeking Environmental clearance for quarrying of Building Stone in 4-00 Acres Government land.

The subject was discussed in the SEAC meeting held on 4th September 2015.

The Committee has recommended the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“The proponent was invited to the meeting to provide required clarification.

The proponent remained absent.

The committee observed that the quarry site is 800 m from the inter-state boundary. Also, already many proposals in this village are cleared by the committee. If the quarry site is located within 5Kms from the inter-state boundary, and if the total lease area exceeds 5 ha, it attracts general conditions of the EIA Notification. In such case the activity requires Environmental Clearance from the Ministry of Environment and Forests, Government of India.

The committee appraised the proposal and opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.”

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to provide one more opportunity and invite to the Authority meeting.

105.5.5 River Sand Quarrying in Shirgur Inam Block I at Bhima River bed, opposite to Sy.No. 104 (part), 1, 2 and 4 (Part) of Shirgur Inam village, Indi Taluk, Bijapur District. (4.856 Ha / 12 Acres) of Deputy Director & Member Secretary, District Sand Monitoring Committee, Dept. of Mines & Geology (SEIAA 318 MIN 2014)

This is a proposal submitted by District Sand Monitoring Committee, Bijapura seeking Environmental Clearance for Sand Mining at Sy.No. 104 (part), 1, 2 and 4 (Part) of Shirgur Inam village, Indi Taluk, Bijapur District over an area of 4.856Ha of Revenue Land on the banks of Bhima River.

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

105th SEIAA Meeting Proceedings Dated 26th September 2015

41

“Project Proponent along with Environment Consultant presented the proposal in the 119th Special meeting held on 1st October 2014.

The activity is an extraction of sand from Bhima river (excluding water course).

1. As proposed by proponent the extraction of the sand is done only during non-monsoon season when there is lean flow in the river.

2. The process proposed is a manual operation. 3. The PP proposes to extract only 1 m depth of sand, which is equal to

replenishment of sand which takes place in this water course in 5 years as admitted by PP during the presentation.

4. There are no sensitive locations in 5km distance around the sand mining area.

5. All preventive measures suggested by MoEF are considered in the proposal. 6. PP stated that there are no structures such as bridges and retaining walls

across/ along the above water course which are susceptible to erosion. 7. As stated by PP, the extracted sand will not be carried through any village

or habitation. However, PP was asked to furnish on the day of meeting, a key plan indicating approach road to the proposed site. PP submitted Toposheet/key map with marking of location of site & approach road.

8. PP stated that the EMP submitted is sufficient to mitigate the adverse effects, if any, due to sand mining.

Observations of the Committee:

1. PP was advised to plant Terminalia arjuna (Holemathi), Sygigium cumini (Nerale), Pongamia pinnata (Honge), Mangifera indica (Mango), Vitis nigandu (Lakki) and Agave to strengthen the river banks and on road sides Madhuca indica (Hippe), Holoptelia integrifolia (Thapasvi), Hardwickia binata (Anjana), Acacia ferruginea (Bannimara), Thespesia populnea (Bugari), Acacia arabica ( Kari jali)

2. The Committee suggests that the EC may be issued only for two years as approved in the plan period shown in the approved mining plan.

Based on the above submission made by the PP and also EMP proposed the Committee decided to recommend the proposal to SEIAA for consideration to issue of EC with the conditions that the PP Strictly adheres to,

1. The conditions laid in Karnataka Minor Mineral Concession (Amendment) Rules, 2013 vide G.O. No. CI 357 MMN 2012 dated 16.12.2013.

2. The stipulations/Guidelines issued by MoEF, GoI with regard to sand mining activities.

The Authority perused the proposal and took note of the recommendation of SEAC in its 82nd meeting held on 7th October 2014.

The Authority noted that Dr. Sarvabhoum Bagali, Ex-MLA, Indi, Bijapur District have filed an objection praying for rejection of Environmental Clearance to

105th SEIAA Meeting Proceedings Dated 26th September 2015

42

this sand block. The reasons attributed by Dr. Sarvabhoum Bagali for the said objection are as follows;

1) The proposed sand block is having an area less than 5.0 Ha, therefore it may not be considered as per O.M. dated 24-12-2013 issued by the Ministry of Environment & Forest, Government of India.

2) A barrage constructed at Hilli-Gubbewad village on the Bhima river is located within 5 km from the proposed sand block.

3) Water of the above said barrage stagnates up to Inam Shiragur and Padanur Villages even during summer. No stream mining is permitted as per the above mentioned O.M. dated 24-12-2013.

4) Mining activities in this block will result in pollution of drinking water that is being supplied to the neighboring villages on either sides of the Bhima River.

5) This sand block is an on-going sand excavation project, big pits to the depth of 7 mtrs (21 feet) have been already dug. This big pits are not filled up by Public Works Department and Sand Mafia.

6) Sand mining is to be done manually, if Environment Clearance is given the Executive Engineer, Bijapur may continue to violate directions of MoEF.

7) The Executive Engineer, PWD, Bijapur and Sand Mafia has done sand mining by use of Pokliner, JCB / Hitachi in contravention of the rules. He is likely to continue mining in contravention of the rules.

8) The vehicles transporting sand pass through Shiragur Village and cause noise pollution and air pollution in the village. These vehicles being very heavy damage the roads. It is difficult for small children and school going children to pass through this heavy traffic.

The Authority also noted that Dr. Sarvabhouma Bagali have alleged that this proposal attracts General Condition of EIA Notification, 2006 by virtue of being close to the Inter-State boundary and therefore need to be appraised as category ‘A’ project.

The Authority observed that the O.M. dated 24-12-2013 issued by the Ministry of Environment & Forest, Government of India has been stayed by the Principle Bench of Hon’ble National Green Tribunal, New Delhi – Circuit Bench at Shimla in so far as it relates to the minor minerals like sand vide order dated 28th March 2014 in application No. 343 of 2013 and connected matters. Therefore the proposal need to be considered in accordance with the orders of Hon’ble Supreme Court dated 27-02-2012 in IA No. 12-13 of 2011 in SLP (C) No.19628-19629 of 2009, EIA Notification 2006 and the amendments made there on apart from the orders of the Hon’ble National Green Tribunal, Principle Bench, New Delhi dated 05-08-2013 made in original application No. 171 of 2013 and connected matters.

In view of the above said statutory position the Authority is bound to consider all application seeking Environment Clearance for mining of minor minerals in an area up to 50.0 Hectares.

105th SEIAA Meeting Proceedings Dated 26th September 2015

43

However, the Authority after discussion had decided to refer the file back to SEAC for re-appraisal keeping the above objections made by Dr. Sarvabhouma Bagali in view and sending recommendations deemed fit based on merit.

Committee took note of the decision of the Authority in the 122nd SEAC meeting held on 24th, 25th and 26th November 2014.

Committee perused the proposal from file and had decided to deliberate further after receipt of the comments from project proponent (Deputy Commissioner, Bijapur District) and reply for the letter sent from SEIAA.

The representative of the proponent and the RQP/Environment Consultant attended in the 141st SEAC meeting held on 30th June and 1st July 2015 to give clarification/additional information.

The committee observed that the case is still pending in NGT. There is a barrage near Hilli – Gubbevadi which supplies drinking water to Padanur, Shirgur Inam villeges. The levels of these places should be checked and impact due to mining has to be verified and to be submitted. The GPS coordinates of certain blocks are identical which leads to confusion.

The committee after discussion decided to recall the proponent after the submission of the following information:

1. Un undertaking from the proponent there is no sand mining in Maharashtra- Karnataka border

2. Consolidated sketch showing all the blocks and structures with GPS coordinates.

The proponent was invited for the 144th meeting of SEAC held on 5th and 6th August 2015 to provide required clarification. The proponent remained absent.

The Committee had decided to provide one more opportunity to proponent with intimation that the proposal will be appraised based on merit in his absence, in case he remains absent.

The proponent was invited to provide required clarification. The proponent remained absent.

The proponent has not submitted the replies sought by the SEAC in the earlier meetings.

The committee appraised the proposal considering the information provided in the Statutory Applications Form-1, Pre Feasibility Report, Approved Mining Plan and information provided in the earlier meetings.

The committee opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.”

105th SEIAA Meeting Proceedings Dated 26th September 2015

44

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to close the file and delist from the pendency.

105.5.6 River Sand Quarrying in Padanur Sand Block 1 at Bhima River bed, opposite to Sy.No. 216 and 217 (part) of Padanur village, Indi Taluk, Bijapur District. (4.856 Ha / 12 Acres) of Deputy Director & Member Secretary, District Sand Monitoring Committee, Dept. of Mines & Geology (SEIAA 319 MIN 2014)

This is a proposal submitted by District Sand Monitoring Committee, Bijapur seeking Environmental Clearance for Sand Mining at Sy.No. 216 and 217 of Padanur village, Indi Taluk, Bijapur District over an area of 4.856Ha.

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“Project Proponent along with Environment Consultant presented the proposal in the 119th Special meeting held on 1st October 2014.

The activity is an extraction of sand from Bhima river (excluding water course).

1. As proposed by proponent the extraction of the sand is done only during non-monsoon season when there is lean flow in the river.

2. The process proposed is a manual operation. 3. The PP proposes to extract only 1 m depth of sand, which is equal to

replenishment of sand which takes place in this water course in 5 years as admitted by PP during the presentation.

4. There are no sensitive locations in 5km distance around the sand mining area. 5. All preventive measures suggested by MoEF are considered in the proposal. 6. PP stated that there are no structures such as bridges and retaining walls

across/ along the above water course which are susceptible to erosion. 7. As stated by PP, the extracted sand will not be carried through any village or

habitation. However, PP was asked to furnish on the day of meeting, a key plan indicating approach road to the proposed site. PP submitted Toposheet/key map with marking of location of site & approach road.

8. PP stated that the EMP submitted is sufficient to mitigate the adverse effects, if any, due to sand mining.

Observations of the Committee:

1. PP was advised to plant Terminalia arjuna (Holemathi), Sygigium cumini (Nerale), Pongamia pinnata (Honge), Mangifera indica (Mango), Vitis nigandu (Lakki) and Agave to strengthen the river banks and on road sides Madhuca indica (Hippe), Holoptelia integrifolia (Thapasvi), Hardwickia binata (Anjana), Acacia ferruginea (Bannimara), Thespesia populnea (Bugari), Acacia arabica ( Kari jali)

105th SEIAA Meeting Proceedings Dated 26th September 2015

45

2. The Committee suggests that the EC may be issued only for two years as approved in the plan period shown in the approved mining plan.

Based on the above submission made by the PP and also EMP proposed the Committee decided to recommend the proposal to SEIAA for consideration to issue of EC with the conditions that the PP Strictly adheres to,

1. The conditions laid in Karnataka Minor Mineral Concession (Amendment) Rules, 2013 vide G.O. No. CI 357 MMN 2012 dated 16.12.2013.

2. The stipulations/Guidelines issued by MoEF, GoI with regard to sand mining activities.

The Authority perused the proposal and took note of the recommendation of SEAC in its 82nd meeting held on 7th October 2014.

The Authority noted that Dr. Sarvabhoum Bagali, Ex-MLA, Indi, Bijapur District have filed an objection praying for rejection of Environmental Clearance to this sand block. The reasons attributed by Dr. Sarvabhoum Bagali for the said objection are same as enumerated in agenda item No.82.4.60 except for the following:

i) Existence of a Railway Bridge within 5 km from the proposed sand block.

ii) Gram Sabha conducted on 09-06-2014 at Padanur village passed a resolution opposing sand mining.

iii) The Chairman and Members of Gram Panchayath, Padanur and publics have requested Deputy Commissioner, Bijapur on 16-06-2014 not to allow sand mining in Padanur and Baragudi villages.

iv) This sand block is one of the subject matter in miscellaneous application No. 438 of 2014 and 507/2014 in original application 171 of 2014 before Hon’ble National Green Tribunal, Principal Bench, New Delhi where SEIAA is also a party.

The Authority therefore decided to refer the file back to SEAC for re-appraisal keeping the above objections made by Dr. Sarvabhouma Bagali in view and sending recommendations deemed fit based on merit.

Committee took note of the decision of the Authority in the 122nd SEAC meeting held on 24th, 25th and 26th November 2014.

Committee perused the proposal from file and had decided to deliberate further after receipt of the comments from PP (Deputy Commissioner, Bijapur District) and reply for the letter sent from SEIAA.

The representative of the proponent and the RQP/Environment Consultant attended in the 141st SEAC meeting held on 30th June and 1st July to give clarification/additional information.

The committee observed that the case is still pending in NGT. There is a barrage near Hilli – Gubbevadi which supplies drinking water to Padanur, Shirgur Inam villeges. The levels of these places should be checked and impact due to mining has to be verified and to be submitted. The GPS coordinates of certain blocks are identical which leads to confusion.

105th SEIAA Meeting Proceedings Dated 26th September 2015

46

The committee after discussion decided to recall the proponent after the submission of the following information:

1. Un undertaking from the proponent there is no sand mining in Maharashtra- Karnataka border

2. Consolidated sketch showing all the blocks and structures with GPS coordinates.

The proponent was invited to provide required clarification. The proponent remained absent.

The Committee decided to provide one more opportunity to proponent with

intimation that the proposal will be appraised based on merit in his absence, in case he remains absent.

The proponent was invited to provide required clarification. The proponent remained absent.

The proponent has not submitted the replies sought by the SEAC in the earlier meetings.

The committee appraised the proposal considering the information provided in the Statutory Applications Form-1, Pre Feasibility Report, Approved Mining Plan and information provided in the earlier meetings.

The committee opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.”

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to close the file and delist from the pendency.

105.5.7 Mining Project: River Sand Quarrying in Padanur Sand Block II at

Bhima River bed, opposite to Sy.No. 231 (part), 232 and 237 (part) of Padanur village, Indi Taluk, Bijapur District. (4.856 Ha / 12 Acres) of Deputy Director & Member Secretary, District Sand Monitoring Committee, Dept. of Mines & Geology (SEIAA 322 MIN 2014)

This is a proposal submitted by the District Sand Monitoring Committee, Bijapur seeking Environmental Clearance for Sand Mining at Sy.No. 231 (part), 232 and 237 (part) of Padanur village, Indi Taluk, Bijapur District over an area of 4.856Ha on the banks of Bhima River.

105th SEIAA Meeting Proceedings Dated 26th September 2015

47

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“Project Proponent along with Environment Consultant presented the proposal in the 119th Special meeting held on 1st October 2014.

The activity is an extraction of sand from Bhima river (excluding water course).

1. As proposed by proponent the extraction of the sand is done only during non-monsoon season when there is lean flow in the river.

2. The process proposed is a manual operation. 3. The PP proposes to extract only 1 m depth of sand, which is equal to

replenishment of sand which takes place in this water course in 5 years as admitted by PP during the presentation.

4. There are no sensitive locations in 5km distance around the sand mining area. 5. All preventive measures suggested by MoEF are considered in the proposal. 6. PP stated that there are no structures such as bridges and retaining walls

across/ along the above water course which are susceptible to erosion. 7. As stated by PP, the extracted sand will not be carried through any village or

habitation. However, PP was asked to furnish on the day of meeting, a key plan indicating approach road to the proposed site. PP submitted Toposheet/key map with marking of location of site & approach road.

8. PP stated that the EMP submitted is sufficient to mitigate the adverse effects, if any, due to sand mining.

Observations of the Committee:

1. PP was advised to plant Terminalia arjuna (Holemathi), Sygigium cumini (Nerale), Pongamia pinnata (Honge), Mangifera indica (Mango), Vitis nigandu (Lakki) and Agave to strengthen the river banks and on road sides Madhuca indica (Hippe), Holoptelia integrifolia (Thapasvi), Hardwickia binata (Anjana), Acacia ferruginea (Bannimara), Thespesia populnea (Bugari), Acacia arabica ( Kari jali)

2. The Committee suggests that the EC may be issued only for two years as approved in the plan period shown in the approved mining plan.

Based on the above submission made by the PP and also EMP proposed the Committee decided to recommend the proposal to SEIAA for consideration to issue of EC with the conditions that the PP Strictly adheres to,

1. The conditions laid in Karnataka Minor Mineral Concession (Amendment) Rules, 2013 vide G.O. No. CI 357 MMN 2012 dated 16.12.2013.

2. The stipulations/Guidelines issued by MoEF, GoI with regard to sand mining activities.

The Authority perused the proposal and took note of the recommendation of SEAC in its 82nd meeting held on 7th October 2014.

The Authority noted that Dr. Sarvabhoum Bagali, Ex-MLA, Indi, Bijapur District have filed an objection praying for rejection of Environmental Clearance to

105th SEIAA Meeting Proceedings Dated 26th September 2015

48

this sand block. The reasons attributed by Dr. Sarvabhoum Bagali for the said objection are same as enumerated in agenda item No.82.4.60 and agenda item No.82.4.61 except for the reason that excavation of sand in this block is done with the help of mechanized boats, fitted diesel generator and suction pumps.

The Authority therefore decided to refer the file back to SEAC for re-appraisal keeping the above objections made by Dr. Sarvabhouma Bagali in view and sending recommendations deemed fit based on merit.

Committee took note of the decision of the Authority in the 122nd SEAC meeting held on 24th, 25th and 26th November 2014.

Committee perused the proposal from file and had decided to deliberate further after receipt of the comments from PP (Deputy Commissioner, Bijapur District) and reply for the letter sent from SEIAA.

The representative of the proponent and the RQP/Environment Consultant attended the in the 141st SEAC meeting held on 30th June and 1st July 2015 to give clarification/additional information.

The committee observed that the case is still pending in NGT. There is a barrage near Hilli – Gubbevadi which supplies drinking water to Padanur, Shirgur Inam villeges. The levels of these places should be checked and impact due to mining has to be verified and to be submitted. The GPS coordinates of certain blocks are identical which leads to confusion.

The committee after discussion decided to recall the proponent after the submission of the following information:

1. Un undertaking from the proponent there is no sand mining in Maharashtra- Karnataka border

2. Consolidated sketch showing all the blocks and structures with GPS coordinates.

The proponent was invited to provide required clarification. The proponent remained absent.

The Committee decided to provide one more opportunity to proponent with intimation that the proposal will be appraised based on merit in his absence, in case he remains absent.

The proponent was invited to provide required clarification. The proponent remained absent.

The proponent has not submitted the replies sought by the SEAC in the earlier meetings.

The committee appraised the proposal considering the information provided in the Statutory Applications Form-1, Pre Feasibility Report, Approved Mining Plan and information provided in the earlier meetings.

105th SEIAA Meeting Proceedings Dated 26th September 2015

49

The committee opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.”

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to close the file and delist from the pendency.

105.5.8 River Sand Quarrying in Baragudi Sand Block at Bhima River bed, opposite to Sy.No.123, 126, 127, 130 and 132 (part) of Baragudi village, Indi Taluk, Bijapur District. (4.856 Ha / 12 Acres) of Deputy Director & Member Secretary, District Sand Monitoring Committee, Dept. of Mines & Geology (SEIAA 324 MIN 2014)

District Sand Monitoring Committee., have applied for EC from SEIAA for proposed Sand Mining with estimated extraction of 93960 TPA at Sy.No. 123, 126, 127, 130 and 132 (part) of Baragudi village, Indi Taluk, Bijapur District over an area of 4.856Ha of Revenue Land on the banks of Bhima River under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B.

The subject was discussed in the SEAC meeting held on 23rd September 2015. The Committee has recommended to the proposal to SEIAA for closure and the extract of the proceedings of the Committee meeting is as below:

“Project Proponent along with Environment Consultant presented the proposal in the 119th Special meeting held on 1st October 2014.

The activity is an extraction of sand from Bhima river (excluding water course).

1. As proposed by proponent the extraction of the sand is done only during non-monsoon season when there is lean flow in the river.

2. The process proposed is a manual operation. 3. The PP proposes to extract only 1 m depth of sand, which is equal to

replenishment of sand which takes place in this water course in 5 years as admitted by PP during the presentation.

4. There are no sensitive locations in 5km distance around the sand mining area. 5. All preventive measures suggested by MoEF are considered in the proposal. 6. PP stated that there are no structures such as bridges and retaining walls

across/ along the above water course which are susceptible to erosion. 7. As stated by PP, the extracted sand will not be carried through any village or

habitation. However, PP was asked to furnish on the day of meeting, a key plan indicating approach road to the proposed site. PP submitted Toposheet/key map with marking of location of site & approach road.

8. PP stated that the EMP submitted is sufficient to mitigate the adverse effects, if any, due to sand mining.

105th SEIAA Meeting Proceedings Dated 26th September 2015

50

Observations of the Committee:

1. PP was advised to plant Terminalia arjuna (Holemathi), Sygigium cumini (Nerale), Pongamia pinnata (Honge), Mangifera indica (Mango), Vitis nigandu (Lakki) and Agave to strengthen the river banks and on road sides Madhuca indica (Hippe), Holoptelia integrifolia (Thapasvi), Hardwickia binata (Anjana), Acacia ferruginea (Bannimara), Thespesia populnea (Bugari), Acacia arabica ( Kari jali)

2. The Committee suggests that the EC may be issued only for two years as approved in the plan period shown in the approved mining plan.

Based on the above submission made by the PP and also EMP proposed the Committee decided to recommend the proposal to SEIAA for consideration to issue of EC with the conditions that the PP Strictly adheres to, 1. The conditions laid in Karnataka Minor Mineral Concession (Amendment)

Rules, 2013 vide G.O. No. CI 357 MMN 2012 dated 16.12.2013. 2. The stipulations/Guidelines issued by MoEF, GoI with regard to sand mining

activities.

The Authority noted that Dr. Sarvabhoum Bagali, Ex-MLA, Indi, Bijapur District have filed an objection praying for rejection of Environmental Clearance to this sand block. The reasons attributed by Dr. Sarvabhoum Bagali for the said objection are same as enumerated in agenda item No.82.4.60 and agenda item No.82.4.61.

The Authority therefore decided to refer the file back to SEAC for re-appraisal keeping the above objections made by Dr. Sarvabhouma Bagali in view and sending recommendations deemed fit based on merit.

Committee took note of the decision of the Authority in the 122nd SEAC meeting held on 24th, 25th and 26th November 2014.

Committee perused the proposal from file and had decided to deliberate further after receipt of the comments from PP (Deputy Commissioner, Bijapur District) and reply for the letter sent from SEIAA.

The representative of the proponent and the RQP/Environment Consultant attended in the 141st SEAC meeting held on 30th June and 1st July 2015 to give clarification/additional information.

The committee observed that the case is still pending in NGT. There is a barrage near Hilli – Gubbevadi which supplies drinking water to Padanur, Shirgur Inam villeges. The levels of these places should be checked and impact due to mining has to be verified and to be submitted. The GPS coordinates of certain blocks are identical which leads to confusion.

The committee after discussion decided to recall the proponent after the submission of the following information:

1. Un undertaking from the proponent there is no sand mining in Maharashtra- Karnataka border

2. Consolidated sketch showing all the blocks and structures with GPS coordinates.

105th SEIAA Meeting Proceedings Dated 26th September 2015

51

The proponent was invited to provide required clarification. The proponent remained absent.

The Committee decided to provide one more opportunity to proponent with intimation that the proposal will be appraised based on merit in his absence, in case he remains absent.

The proponent was invited to provide required clarification. The proponent remained absent.

The proponent has not submitted the replies sought by the SEAC in the earlier meetings.

The committee appraised the proposal considering the information provided in the Statutory Applications Form-1, Pre Feasibility Report, Approved Mining Plan and information provided in the earlier meetings.

The committee opined that the appraisal cannot be completed for want of the above information and since the proponent also remained absent to provide the required clarification.

The committee therefore decided to recommend the proposal to SEIAA for closure.”

The Authority perused the proposal and took note of the recommendation of SEAC.

The Authority decided to close the file and delist from the pendency.

105.6 Miscellaneous:

Building Stone Quarry Project, Sy.No.365/3 of Santhur Village, Udupi Taluk & Dist. (0.50 Acre) of Sri Suresh Shetty S/o. Sri Sitharam Shetty, Mundraguttu, Nandikur Post, Udupi Taluk & District (SEIAA 259 MIN 2015)

Sri Suresh Shetty S/o. Sri Sitharam Shetty had submitted two applications seeking Environmental Clearance for quarrying of Building stone in respect of QL No. 2947 and QL No. 2948, each with a lease area of 0.50 Acres. The said proposals were dealt in File No. SEIAA 255 MIN 2015 and SEIAA 259 MIN 2015 respectively.

Pursuant to the order dated 11.6.2015 of the Senior Geologist, Mines &

Geology Department, Udupi, both the above said leases have been merged. The proponent subsequently submitted revised application on 28.7.2015 along with quarry plan duly modified and approved by the DMG. The modified proposal was considered in the along with the old application in File No. SEIAA 255 MIN 2015. The Committee during the meeting held on 6th August 2015 have recommended the proposal for the amalgamated lease area of one Acre. Accordingly, the Authority also have cleared the proposal for issued of Environmental Clearance for amalgamated lease area.

105th SEIAA Meeting Proceedings Dated 26th September 2015

52

While, considering the revised proposal of Sri Suresh Shetty, the Committee ought to have recommended the File No. SEIAA 259 MIN 2015. However, by oversight the 2nd file also have been recommended for Environmental Clearance and the same has been approved by the Authority during the meeting held on 29th August 2015.

Since, the area under lease in QL No. 2947 have been merged with QL No.

2948 due to amalgamation of leases, QL No. 2947 have lost its existence and hence the proposal being dealt in File No SEIAA 259 MIN 2015 is in fructuous. Therefore deserves to be closed.

The Authority perused the proposal and decided to close the File No. SEIAA

259 MIN 2015 and delist from the pendency.

105.7 With the permission of the Chair:

105.7.1 Review of Progress in disposal of applications by the Committee/Authority –reg.

The Member Secretary brought to the notice of the Authority that submission of online application in the MoEF portal has been made mandatory. The application so received are being forwarded to SEAC for online appraisal. The SEAC is also considering applications and sending their recommendation online in such proposals that have been received. The Member Secretary informed that 12 such proposals are being considered today by the Authority in addition to the offline applications submitted prior to the online portal by MoEF, Government of India. The Authority perused the applications received for ToR and for E.C., the applications returned to the proponent for shortfall information, the applications forwarded to SEAC for appraisal and the applications acknowledged by the SEAC. The Authority expressed satisfaction and pleasure for having initiated early action for transparent and time bound decision making in Environmental Clearance process. The Authority noted that only Karnataka and Gujarath States are actively involved in making use of the online portal of the MoEF. The Authority applauded for the efforts made by the Member Secretary in this regard.

105.7.2 Software Development Blocks at Plot No.57, 58, 59, 63 on Sy.Nos.12 of

Konnapanna Agrahara & Sy.Nos.157, 158, 161, 64, 65 of Doddathogur Village, Electronic City, Begur, Bangalore South Taluk, Bangalore Urban District by M/s. Infosys Limited (SEIAA 129 CON 2014)

It is a proposal for construction of two Blocks of Software Development buildings (SDB-01, and SDB-02) with 2B + GF + 8F + T on an area of 40,591.72 Sqm and with the total built up area of 1,25,693.76 Sqm. The total water requirement is 607.39 KLD.

The subject was discussed in the SEAC meeting held on 19th, 20th & 21st January 2015 and 30th June & 1st July 2015. The Committee has recommended for issue of environmental clearance, subject to submission of the following information:

105th SEIAA Meeting Proceedings Dated 26th September 2015

53

1. Revised soil analysis report for the chemical parameters 2. Write up on bus shelter provided 3. Corrected water balance and mass balance 4. Estimation of the e-waste and earmarking dedicated area for

collection and disposal in accordance with the provisions of law 5. STP flow chart to be simplified.

The Authority during the meeting held on 25.07.2015 had perused the proposal and took note of the recommendation of SEAC. The Authority observed from the Google Imagery that large scale construction activity has been taken place without prior Environmental Clearance. The Authority therefore decided to consider this as case of violation and to seek clarification from the proponent. The Authority also decided to get the project site inspected.

The Authority perused the replies submitted by the proponent vide letters dated 31.07.2015 and 04.09.2015. The Authority also perused the inspection note submitted by Shri H.S. Sudheendra, Scientific Officer. The Authority noted that the proposed construction is a modification of the project for which Environmental Clearance has been issued vide letter No.SEIAA 78 CON 2007 dated 04.06.2009 in favour of M/s Tyche Developers for a total built up area of 1,76,220.31 Sqm. The project site along with the construction so undertaken has been taken over by M/s Infosys Limited who have submitted this application for the modification of the earlier E.C. The modified proposal has a reduced built up area of 1,25,693.76 Sqm which is to be used only for IT Park. The Authority opined that as the construction activity has been undertaken as per the earlier E.C. it cannot be construed as violation.

The Authority after discussion decided to issue Environmental Clearance.

105.7.3 Complaint regarding construction of Additional VIP and VVIP Guest house at Kumara Krupa Guest House without obtaining mandatory Environmental Clearance- reg.

The Authority perused the complaint submitted by Mrs. K. Sudha, No.1202, 12th Floor, F Block, Jalavayu Heights Apartments, HMT Main Road, Jalahalli, Bangalore vide letter dated 3.9.2015 regarding the subject above. The Authority also perused the legal notice dated 14.09.2015 of Shri Umapathi S., Advocate under the instructions of Smt. Sudha on the subject above.

The Authority after discussion, decided to communicate a copy of both the complaint and the legal notice to the Executive Engineer concerned and M/s BG Shirke Construction Technology Pvt. Ltd. directing them to show cause why action should not be taken against them for the alleged violation.

105.7.4 Authorizing officers for filing complaint under section 19 of E (P) Act.

The Member Secretary brought to the notice of the Authority that the Authority have been delegated with the powers to file complaint against the violators in the jurisdiction court of law under section 19 of Environment

105th SEIAA Meeting Proceedings Dated 26th September 2015

54

(Protection) Act, 1986 vide Notification No. S.O. 638 (E) dated 28.02.2015. Accordingly, complaints have been filed before different courts of law by the Member Secretary as per the decision taken in the Authority. The Member Secretary informed the Authority that it would be difficult possible for the Member Secretary himself to go before the jurisdictional courts throughout the State. In view of this opinion of Learned Advocate Shri Joshi with regard to authorizing other officers assisting the Authority to file complaints in accordance with the decision taken in the Authority. The Learned Advocate informed that SEIAA is a statutory Authority constituted by the Ministry of Environment, Forests and Climate Change under the Environment (Protection) Act, 1986. The Authority is expected to discharge the assigned functions through the officers and officials attached to them. Therefore expecting the entire Authority or the Member Secretary alone to shoulder the responsibility is impracticable. The Learned Advocate have therefore informed that the provisions under section 19 (1) of the General Clauses Act, 1897 can be made applicable for lawfull discharge of the functions of the Authority by the officers/officials attached to the Authority.

In view of the above opinion, the Member Secretary suggested that a list of officers attached to the Authority may be notified by the Authority for lawfull execution of the functions of the Authority including discharge of functions under section 19 of the Environment (Protection) Act, 1986.

The Authority after discussion, agreed with the opinion of the Learned Advocate and decided to issue notification authorizing the following officers of the Authority for lawfull implementation of the decision taken by the State Level Environment Impact Assessment Authority including filing of complaints before the Hon'ble jurisdictional courts of law as required under section 19 of the Environment (Protection) Act, 1986 wherever the Authority decides so. The Authority however clarified that the said officers may execute the decisions of the Authority subject to being authorized in each case through appropriate minutes/proceedings of the meetings of the Authority.

1. The Special Director (Technical Cell), Department of Ecology and Environment and the Secretary, State Expert Appraisal Committee, Karnataka.

2. The Scientific Officer (Grade-1), SEIAA, Department of Ecology and Environment, Government of Karnataka.

3. The Scientific Officer (Grade-1), SEAC, Department of Ecology and Environment, Government of Karnataka.

The Authority decided to issue a notification in this regard. The Authority further clarified that the Member Secretary being the executive head of the Authority will continue to have the powers inherited to that post in all such matters pertaining to the State Level Environment Impact Assessment Authority.

105.7.5 Inclusion of Shri H.K.Vasanth, Advocate in the panel of advocates of the Authority-reg.

The Member Secretary brought to the notice of the Authority that services of an advocate is required in addition to Shri D. Nagaraj for providing legal assistances

105th SEIAA Meeting Proceedings Dated 26th September 2015

55

and for filing of complaints under section 19 of the Environment (Protection) Act, 1986 wherever violations are noticed. The Member Secretary also brought the interest expressed by Shri H.K. Vasanth, Advocate to assist the Authority. The Authority perused the interest and decided to approve Shri H.K. Vasanth, Advocate on the panel of advocates of the Authority. The Authority also decided to pay the following fee and remuneration.

1) Drafting complaint and miscellaneous - Rs. 5,000.00 2) Professional fee - Rs. 5,000.00 3) Hearing fee per day (up to 20 hearing) - Rs. 500.00

The Authority after discussion, decided to hire the services of Sri

H.K.Vasanth, Advocate for the purpose of filing complaint against the violators and to pay the charges as above. The Authority also decided to provide actual bus fare or III AC railway charges as Travelling Allowance and D.A. admissible for a Group-A officer of Government, while attending the courts in the places outside Bengaluru.

The Authority further decided to hand over the following files to

Sri H.K.Vasanth, Advocate for the purpose of filing complaint against the violators. The Authority also decided to authorize Shri H.K.Ananda, Scientific Officer, SEIAA to file complaint in the respective courts of law against the concerned persons responsible for violation of the provisions of EIA Notification, 2006 on behalf of the Authority:

1) Residential Apartment Building Project at Sy.Nos. 345, Shivalli Village,

Udupi Taluk, Udupi District by M/s. Kusuma Bhandary Construction Pvt. Ltd (SEIAA 156 CON 2014)

2) “Rohan Jharoka” Residential Apartment at Sy.No.20/1, 2, 3, 4, 5, 6, 7, 32, 33/2, Kempapura Village, Varthur Hobli, Bangalore South Taluk, Bangalore District of M/s. Rohan Housing Pvt. Ltd (SEIAA 221 CON 2014)

3) "Green City Eutopia", Development of Residential Apartment at Municipal No.9 (Old No.31 & 32/2) 16th Main Road, N.S. Palya Village, Begur Hobli, Bengaluru South Taluk, Bengaluru. (SEIAA 113 CON 2015)

105.7.6. Mixed Use Development Project at various Sy.Nos. of Agara Village and Sy.No. &P of Jakkasandra Village, Begur Hobli, Bangalore South by M/s Manipal ETA Infotech Ltd. (SEIAA 30 CON 2011)

The Member Secretary brought the letter dated 18th September 2015 submitted by M/s Mantri Tech Zone Pvt. Ltd. seeking clarification with regard to compliance of condition No. 39 in the Environmental Clearance letter No. SEIAA 30 CON 2011 dated 17th February 2012. The proponent have requested the Authority to confirm whether compliance of said condition No.39 is required on completion of the project and not during construction phase and that this is a general condition which is included in all the ECs for construction projects.

105th SEIAA Meeting Proceedings Dated 26th September 2015

56

The Authority perused the request and observed that the proponent is seeking clarification on the conditions imposed in Environmental Clearance issued on 17th February 2012, after lapse of 3 and half years. The Authority further observed that the issue is pending before the Hon'ble National Green Tribunal, Principal Bench, New Delhi. Therefore taking any decision on the issue would be sub-judice. The Authority therefore decided to file the representation and await decision of the Hon'ble National Green Tribunal.

Meeting concluded with thanks to the Chair.

Sd/- Sd/- Sd/- (Dr. H. S. RAMESH)

Chairman, SEIAA, Karnataka

(Dr. H. R. RAJMOHAN) Member,

SEIAA, Karnataka.

(RAMACHANDRA)Member Secretary, SEIAA, Karnataka.