Upload
vanphuc
View
216
Download
1
Embed Size (px)
Citation preview
Proceedings for the 82nd meeting of State Level Environment Impact Assessment Authority to be held on 11.04.2015 at 11.00 am in the Committee Room, Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala.
The following were present:
1. Sh. Darshan Singh Jaidka,
Chairman, SEIAA
2. Sh. Anil Kumar Sondhi,
Member, SEIAA
3. Sh. Tejinder Singh Dhaliwal, IAS Member Secretary, SEIAA
Item No. 82.01: Confirmation of the minutes of 81st meeting of SEIAA held on 27.03.2015.
The SEIAA noted tht the proceedings of 81st meeting of SEIAA
held on 27.03.2015 were circulated to all concerned vide letter no. 1951-52 dated
31.03.2015. No observation has been received from any of the members. As such,
SEIAA confirmed the said proceedings.
Item No.82.02: Action taken on the proceedings of 81st meeting of SEIAA held on 27.03.2015.
It was seen by SEIAA.
Item No.82.03: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for a Group Housing Project namely “Pinnacle Homes” at GH-3, Pearl City, Sector-104, Distt. Mohali, Punjab by M/s Pinnacle Self Supporting Co-operative Welfare H/B Society Ltd.
The SEIAA observed that:
1. M/s Pinnacle Self Supporting Co-operative Welfare H/B Society Ltd. vide
letter dated 24.07.2014 has applied for obtaining environmental clearance as
required under EIA notification dated 14.09.2006 for development of a
group housing project namely “Pinnacle Homes” at GH-3, Pearl City, Sector-
104, Distt. Mohali. The project is covered under category 8 (a) of the
Schedule appended to the said notification.
2
The case was considered by the SEAC in its 99th meeting held
on 21.08.2014, which was attended by the following on behalf of the project
proponent:
Sh. Nikhal Sadaf, Secretary of the promoter Society
Dr. Rekha Singh (Coordinator) of M/s GRC India Pvt. Ltd, Environmental Consultant of the promoter Society
Mr. Puneet Bhardwaj, Assistant Manager, of M/s GRC India Pvt. Ltd, Environmental Consultant of the promoter Society
Dr. Rekha Singh (Coordinator) of M/s GRC India Pvt. Ltd,
Environmental Consultant of the promoter company, presented the salient
features of the project before the SEAC.
The SEAC observed that the presentation made by the project
proponent is not satisfactory and does not cover all aspects related to the
project such as identification of sources/activities and their impacts on
environment.
The SEAC further observed that the project proponent is again
required to make presentation after attending to the following observations:
(i) During, the presentation, the project proponent stated that the
fresh water requirement will be either met through own tubewell
or will be met from GMADA water supply or through the water
supply by the Pearl City. However, in the application submitted by
the project proponent, it has been mentioned that the fresh water
requirement will be met through GMADA water supply. Hence, the
project proponent is required to clarify the source from the
requirement of fresh water will be met.
(ii) The per capita water demand assumed by the project proponent
for calculating the water balance statement is 135 lpcd. The
SEIAA, Punjab (available on the official website of SEIAA i.e.
www.seiaapunjab.co.in) has already laid down criteria for
assessment of water demand and utilization of treated wastewater
for Building, Construction, Township & Area Development on the
basis of communities with different population size. Therefore, the
water balance statement submitted by the project proponent is
not as per the criteria specified by the SEIAA, Punjab.
3
(iii) The project proponent is required to submit the storm water
management plan for the areas other than the roof top including
the measures to be adopted to avoid the flooding of the areas
outside the project site.
(iv) The project proponent informed that the treated wastewater will
be disposed off into the sewer to be laid down by the GMADA,
which is at a distance of 1 km from the project site. However, the
project proponent is required to clarify as to how the connectivity
of the sewer line of the project will be ensured with the main
sewer line of GMADA simultaneously with the completion of the
project. In case of non-connectivity with main sewer line of
GMADA, an alternate arrangement for the disposal of the treated
wastewater is required to be submitted.
(v) The project proponent is required to identify and intimate the
sources available to utilize the treated wastewater during the
construction phase of the project.
(vi) The project proponent has not identified certain construction
wastes likely to be generated and measures to be adopted for its
proper management, handling and disposal.
(vii) The project proponent has proposed to use certain type of solid
waste for the filling purposes. However, the project proponent is
required to provide the details such as type, nature,
characteristics, quantity to be used for the filling purpose and in
case of excessive quantity its ultimate disposal.
(viii) The project proponent is required to identify all the sources which
may cause air & noise pollution due to the coming up of the
proposed project, their quantification and likely impacts on the
environment and mitigation measures to be adopted.
(ix) The project proponent is required to submit the bifurcated
quantity of the various types of the municipal solid waste to be
generated from the project, their likely impacts on the
environment and management, handling & disposal.
(x) The project proponent is required to submit the approved
landscape plan.
4
(xi) The proposed energy conservation measures needs to be
reviewed and more energy may be conserved with focus on
providing non-conventional / renewable sources of energy.
(xii) The project proponent is required to mention the names of the
villages to be adopted under the Corporate Social Responsibility
activities and the activities to be carried out in these villages.
After detailed discussions, the SEAC decided to defer the case till the
project proponent submits the reply to the above noted observations.
The decision of SEAC was conveyed to the project proponent vide
letter no. 2561 dated 26.08.2014.
2. Now, the project proponent vide letter no.2567 dated 18.09.2014 has
submitted the reply of the observations of SEAC, the details of which are as under:
Sr. no
Observations of the Committee
Reply submitted by the project proponent.
1. During, the presentation, the project proponent stated that the fresh water requirement will be either met through own tubewell or will be met from GMADA water supply or through the water supply by the Pearl City. However, in the application submitted by the project proponent, it has been mentioned that the fresh water requirement will be met through GMADA water supply. Hence, the project proponent is required to clarify the source from the requirement of fresh water will be met.
The GMADA vide letter no.3932 dated 02.09.2011 has intimated to M/s PACL India Ltd. That it has accounted for the water supply demand and the sewage load as per norms fixed by the govt. of India for Sec-100 & 104,while designing the trunk services to be laid by GMADA on the peripheral grid roads of Mohali Master Plan. The connections with these trunk services will be allowed after these services are laid and commissioned in due course of time.
2. The per capita water demand assumed by the project proponent for calculating the water balance statement is 135 lpcd. The SEIAA, Punjab (available on the official website of SEIAA i.e. www.seiaapunjab.co.in) has already laid down criteria for assessment of water demand
Submitted the revised water balance.
5
and utilization of treated wastewater for Building, Construction, Township & Area Development on the basis of communities with different population size. Therefore, the water balance statement submitted by the project proponent is not as per the criteria specified by the SEIAA, Punjab.
3. The project proponent is required to submit the storm water management plan for the areas other than the roof top including the measures to be adopted to avoid the flooding of the areas outside the project site.
Submitted.
4. The project proponent informed that the treated wastewater will be disposed off into the sewer to be laid down by the GMADA, which is at a distance of 1 km from the project site. However, the project proponent is required to clarify as to how the connectivity of the sewer line of the project will be ensured with the main sewer line of GMADA simultaneously with the completion of the project. In case of non-connectivity with main sewer line of GMADA, an alternate arrangement for the disposal of the treated wastewater is required to be submitted.
The GMADA has assured that the construction of sewer line approaching to project site will be completed within 1-1.5 years. While the completion of proposed project will require around 3 years and again around 6 months to be in complete operational phase. So the time gap is around 2 years between laying of sewer line and sewer discharge from the project.
5. The project proponent is required to identify and intimate the sources available to utilize the treated wastewater during the construction phase of the project.
Submitted
6. The project proponent has not identified certain construction wastes likely to be generated and measures to be adopted for its proper management, handling and disposal.
Submitted
7. The project proponent has proposed to use certain type of
Submitted
6
solid waste for the filling purposes. However, the project proponent is required to provide the details such as type, nature, characteristics, quantity to be used for the filling purpose and in case of excessive quantity its ultimate disposal.
8. The project proponent is required to identify all the sources which may cause air & noise pollution due to the coming up of the proposed project, their quantification and likely impacts on the environment and mitigation measures to be adopted.
Submitted
9. The project proponent is required to submit the bifurcated quantity of the various types of the municipal solid waste to be generated from the project, their likely impacts on the environment and management, handling & disposal.
Submitted
10. The project proponent is required to submit the approved landscape plan.
Submitted
11. The proposed energy conservation measures needs to be reviewed and more energy may be conserved with focus on providing non-conventional / renewable sources of energy.
Submitted
12. The project proponent is required to mention the names of the villages to be adopted under the Corporate Social Responsibility activities and the activities to be carried out in these villages.
Submitted
The case was considered by the SEAC in its 102nd meeting held on
17.10.2014, which was attended by the following on behalf of the project
proponent:
i) Sh. Nikhil Sadaf, Secretary of the promoter company
7
ii) Sh. Mervyn Gilbert of M/s Grass Roots Research & Creations
India (P) Ltd. Environmental Consultant of the promoter
company
A perusal of the application and presentation made by Sh. Mervyn
Gilbert, Environmental Consultant of the promoter company reveal, the salient
features of the project as under:-
The total plot area is 20,244.73 sqm having a built up area of 53,482.252
sqm. Plot no. 3 at Sector-104, Pearls City, Mohali has been allotted to
M/s The Pinnacle Co-op. Welfare Housing Society Ltd. by M/s Pearls
Infrastructure Projects Ltd. vide allotment letter no. 14901 dated
27.03.2012.
Dept. of Housing and Urban Development has granted CLU to M/s PACL
India Ltd. vide no. 6291 dated 10.07.2006.
Total water requirement for the project will be 245 KLD, out of which
187 KLD will be met through fresh water supply and remaining 58 KLD
will be met from treated wastewater.
The total wastewater generation from the project will be 196 KLD, which
will be treated in a STP of 250 KLD capacity to be installed within the
project premises. The project proponent has proposed to use 58 KLD of
treated wastewater for flushing purpose, 17 KLD for irrigation of green
area and remaining 101 KLD will be discharged to MC sewer in summer
season. In winter season, 58 KLD of treated wastewater will be used for
flushing purpose, 6 KLD will be used for irrigation of green area and
remaining 112 KLD will be discharged to MC sewer. In rainy season, 58
KLD of treated wastewater will be used for flushing purpose, 2 KLD will
be used for irrigation of green area and remaining 116 KLD will be
discharged to MC sewer.
GMADA has issued a letter no.3932 dated 02.09.2011 wherein, it has
been mentioned that the GMADA has accounted for the water supply
demand and the sewage load for the Sector- 100 & 104, while designing
the trunk services to be laid by GMADA on the peripheral grid roads of
Mohali Master Plan.
The total quantity of solid waste to be generated from the proposed
project has been estimated as 630 Kg/Day, which will be segregated into
8
bio-degradable and non-biodegradable waste as per the MSW Rules,
2000. The biodegradable waste will be converted into compost. The
recyclable waste will be sold off to recyclers. GMADA has issued a letter
no.3932 dated 02.09.2011 wherein, it has been mentioned that the
quantity of garbage likely to be generated from Sector-100 & 104 has
also been accounted for while calculating the capacity of Common Waste
Management Facility for GMADA cluster by Local govt. Punjab.
The total load of electricity required for proposed project will be 1503.1
KW which will be supplied by PSPCL. The project proponent has
proposed to install 2 DG sets OF 500 KVA capacity for backup power
supply.
The e-waste generated will be stored in an isolated room and will be sold
to authorized collection centers/re-processors as per provisions of the E-
Waste (Management & Handling) Rules, 2011 rules.
Used oil to be generated from the DG sets will be managed & handled as
per the provisions of the Hazardous Wastes (Management, Handling &
Transboundary Movement) Rules, 2008.
The ambient air monitoring has been got done from M/s GRC India
Training & Analytical Laboratory and the analysis results indicate that the
concentration of various pollutants such as PM2.5, PM10, SO2, NO2 and CO
have been measured. Also, ambient noise monitoring has been got done
from the said firm and the analysis results indicate that the noise levels
during day and night times, have been measured as 53.4 dB(A) leq and
43.2 dB(A) leq, respectively, against the prescribed standards of 55 and
45 dB(A) leq. The groundwater of the area is potable in nature as per
analysis report of groundwater.
Airport authority has issued a NOC dated 09.09.2013 wherein, it has
been mentioned that the maximum height shall not exceed 48.87m.
During construction phase, Rs.40 lacs will be incurred for implementation
of Environment Management Plan. During operation phase, Rs.50.5 lacs
will be incurred for implementation of EMP. The implementation of EMP
will be responsibility of Mr. Harinder Singh, Director, Mr. Dinesh Mahajan,
Project Manager, and Mr. Subrat Kumar Pradhan, AGM of the company
9
Rs. 1.00 crore will be utilized for following activities under Corporate
Social Responsibility:
• Rs. 10.65 lacs for shelters to labour class.
• Rs. 13.40 lacs for rural primary health centres.
• Rs. 27.35 lacs for distribution of clothes to poor people.
• Rs. 26.80 lacs for vocational training centres.
• Rs. 21.80 lacs for green plantation along the periphery of
project site.
The traffic circulation plan and Disaster/Risk Assessment &
Management Plan has been prepared and the same has been submitted.
The SEAC observed that the project proponent is required to submit
the following documents/clarification:
i. A copy of the agreement regarding the water supply and sewerage
connection to be provided by M/s PACL which is the Area
development promoter company and this project is a part of that Area
Development Project. .
ii. Source of treated wastewater to be used during construction phase.
iii. Details of the total energy saved w.r.t. building materials and
orientation of the buildings.
iv. Details of the solid waste likely to be generated during the
construction phase and its disposal arrangements.
The project proponent assured the SEAC that all the above
documents/clarification will be submitted shortly and requested for recommending
their case to SEIAA for grant of environmental clearance.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal and decided to
forward the case to the SEIAA with the recommendation to grant environmental
clearance to the project proponent for development of a group housing project
namely “Pinnacle Homes” at GH-3, Pearl City, Sector-104, Distt. Mohali, subject to
the following conditions in addition to the proposed measures as and when the
10
project proponent submits the above mentioned documents/clarification and the
same is approved by the Chairman SEAC on the case file of the project:
PART A – Specific conditions
I. Construction Phase
(i) “Consent to establish” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority before the start of any construction work at site.
(ii) All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.
(iii) A first aid room will be provided in the project both during construction and operation phase of the project.
(iv) All the topsoil excavated during construction activities should be stored for use in horticulture / landscape development within the project site.
(v) Disposal of muck during construction phase should not create any adverse effect on the neighbouring communities and be disposed off after taking the necessary precautions for general safety and health aspects of people with the approval of competent authority.
(vi) Construction spoils, including bituminous material and other hazardous material, must not be allowed to contaminate watercourses and the dump sites for such material must be secured, so that they should not leach into the groundwater.
(vii) The diesel generator sets to be used during construction phase should be of low sulphur diesel type and should conform to the provisions of Environment (Protection) Act, 1986 prescribed for air and noise emission standards.
(viii) Vehicles hired for bringing construction material to the site and other machinery to be used during construction should be in good condition and should conform to applicable air and noise emission standards.
(ix) Ambient noise levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
(x) Fly ash should be used as construction material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended on August, 2003 (This condition is applicable only if the project is within 100 Km of Thermal Power Station).
(xi) Ready mixed concrete should be used in building construction as far as possible.
(xii) Water demand during construction should be reduced by use of premixed concrete, curing agents and other best practices.
11
(xiii) Separation of drinking water supply and treated sewage supply should be done by the use of different colours.
(xiv) Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
(xv) Adequate steps shall be taken to conserve energy by limiting the use of glass, provision of proper thermal insulation and taking measures as prescribed under the Energy Conservation Building Code.
(xvi) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
(xvii) Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, disposal of waste water & solid waste in an environmentally sound manner, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project.
II. Operation Phase
i) The installation of sewage treatment plant (STP) and adequacy of disposal system should be certified by Punjab Pollution Control Board and a report in this regard should be submitted to the Ministry of Environment & Forests/State Level Environment Impact Assessment Authority before the project is commissioned for operation. The project proponent shall discharge not more than 116 KLD of treated wastewater into sewer during rainy season.
ii) The project proponent shall provide electromagnetic flow meter at the outlet of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing and for horticulture purpose/green etc. and shall maintain a record of readings of each such meter on daily basis.
iii) Adequate & appropriate pollution control measures should be provided to control fugitive emissions to be emitted within the complex.
iv) Adequate treatment facility for drinking water shall be provided, if required.
v) Rainwater harvesting for roof run-off should be implemented. Before recharging the roof run-off, pretreatment must be done to remove suspended matter, oil and grease. However, no run off from gardens/green area/roads/pavements shall be connected with the ground water recharging system.
vi) The solid waste generated should be properly collected and segregated. The recyclable solid waste shall be sold out to the authorized vendors and inerts shall be sent to disposal facility. The Bio-degradable solid waste shall be adequately treated as per the scheme submitted by the project proponent. Prior approval of competent authority should be obtained, if required.
12
vii) Hazardous waste/E-waste should be disposed off as per Rules applicable and with the necessary approval of the Punjab Pollution Control Board.
viii) The green belt along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential land use. The open spaces inside the plot should be suitably landscaped and covered with vegetation of indigenous species/variety.
ix) The project proponent should take adequate and appropriate measures to contain the ambient air quality within the prescribed standards. The proposal regarding mitigation measures to be taken at site should be submitted to the Ministry of Environment & Forests/ State Level Environment Impact Assessment Authority within three months.
x) Incremental pollution loads on the ambient air quality, noise and water quality should be periodically monitored after commissioning of the project.
xi) Application of solar energy should be incorporated for illumination of common areas, lighting for gardens and street lighting in addition to provision for solar water heating.
xii) Traffic congestion near the entry and exit points from the roads adjoining the proposed project site must be avoided. Parking should be fully internalized and no public space should be utilized.
xiii) A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about machinery of air conditioning, lifts, lighting, building materials, R & U Factors etc. and submitted to the respective Regional office of MoEF, the Zonal Office of CPCB and the SPCB/SEIAA in three months time.
xiv) Environmental Management Cell shall be formed during operation phase which will supervise and monitor the environment related aspects of the project.
PART B – General Conditions :
i) This environmental clearance will be valid for a period of five years from the date of its issue or till the completion of the project, whichever is earlier.
ii) The environmental safeguards contained in the application of the promoter / mentioned during the presentation before State Level Environment Impact Assessment Authority/State Expert Appraisal Committee should be implemented in letter and spirit.
iii) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
iv) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored
13
data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB and the SPCB/SEIAA.
v) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh/State Level Environment Impact Assessment Authority.
vi) In the case of any change (s) in the scope of the project, the project would require a fresh appraisal by State Environment Impact Assessment Authority.
vii) Separate distribution pipelines be laid down for use of treated effluent / raw water for horticultural/gardening purposes with different colour coding.
viii) All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest (Conservation) Act, 1980 and Wildlife (Protection) Act, 1972 etc. shall be obtained, by project proponents from the competent authorities including Punjab Pollution Control Board and from other statutory bodies as applicable. The project proponent shall also obtain permission from the NBWL, if applicable.
ix) The project proponent should advertise in at least two local newspapers widely circulated in the region, one of which shall be in the vernacular language informing that the project has been accorded environmental clearance and copies of clearance letters are available with the Punjab Pollution Control Board. The advertisement should be made within seven days from the day of issue of the clearance letter and a copy of the same should be forwarded to the Regional Office, Ministry of Environment & Forests, Chandigarh.
x) These stipulations would be enforced among others under the provisions of Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environmental (Protection) Act, 1986, the Public Liability (Insurance) Act, 1991 and EIA Notification, 2006.
xi) Environmental clearance is subject to final order of the Hon'ble Supreme Court of India in the matter of Goa Foundation Vs. Union of India in Writ Petition (Civil) No. 460 of 2004 as may be applicable to this project and decisions of any competent court, to the extent applicable.
xii) The project proponent shall comply with the conditions of the CLU granted to M/s PACL by the competent authority, vide letter no. 6291 dated 10.07.2006.
xiii) A copy of the clearance letter shall be sent by the proponent to concerned Panchayat, Zilla Parishad/ Municipal Corporation, Urban local body and the local NGO, if any, from whom suggestions / representations, if any, were
14
received while processing the proposal. The clearance letter shall also be put on the website of the Company by the proponent.
xiv) The proponent shall upload the status of compliance of the stipulated EC
conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SO2, NOx, CO, Pb, Ozone (ambient air as well as stack emissions) shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
xv) The project proponent shall adhere to the commitments made in the Environment Management Plan and shall spend Rs.50.5 Lacs as capital cost on the Environment Management Plan.
xvi) The project proponent shall adhere to the commitments made in the Corporate Social Responsibility and shall spend Rs. 1.00 crore as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
xvii) The State Environment Impact Assessment Authority reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
xviii) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
The decision of the SEAC was conveyed to the project proponent vide
letter no. 3270 dated 31.10.2014.
The project proponent vide letter dated 21.10.2014 and 27.11.2014
submitted the reply to the observations raised by the SEAC, the details of which are
as under:-
Sr.
No. Observations of the SEAC Detail of reply submitted by the
project proponent
1. A copy of the agreement regarding the water supply and sewerage connection to be provided by M/s PACL which is the Area development promoter company and this project is a part of that Area Development Project.
The project proponent has not submitted a copy of the agreement regarding the water supply and sewerage connection to be provided by M/s PACL. However, the project proponent has submitted a copy of receipt dated 15.05.2014, vide which it had applied to the CGWB for permission for
abstraction of groundwater.
15
2. Source of treated wastewater to be used during construction phase.
The project proponent has submitted that being a prime location, at GH-3, Pearl City, Sector-104, District Mohali, Punjab and there are few projects (Taj Towers, Municipal Heights, The Views and Central Plaza) in the vicinity of this project site, therefore, surplus treated wastewater from their STPs will be provided for construction
purposes.
3. Details of the total energy saved w.r.t. building materials and orientation of the buildings.
Submitted.
4. Details of the solid waste likely to be generated during the construction phase and its disposal arrangements.
The project proponent has submitted that the solid waste expected to be generated during the construction phase will comprise
of the following wastes:
(i) Excavated materials from the project
site.
(ii) Used bags of cement
(iii) Bricks, sand, concrete, tiles
(iv) MS rods
(v) Wood or timber projects
(vi) Salvaged building components such as doors, windows and plumbing fixtures.
The project proponent has proposed the following methods of disposal of solid
waste during construction phase.
1. The construction yards are proposed for
the storage of construction material.
2. The excavated material such as top soil and stones, aggregates will be stacked for reuse during later stages of
construction.
3. Excavated top soil will be stored in temporary constructed soil bank covered with tarpaulin sheets and will
be reused for land scaping.
4. Remaining soil shall be utilized for refilling / road work / rising of site level at locations and the surplus soil shall be
16
sold to outside agency for construction
of roads, etc.
5. Used cement bags will be used for road making purpose and surplus no. of bags will be sold to the Govt. approved
agency.
It is further intimated that the matter regarding permission of CGWA
or recommendation letter from CGWB to CGWA for abstraction of groundwater,
was discussed in the 8th combined meeting of SEIAA & SEAC held on 15.12.2014,
wherein it was decided that:
“Where municipal water supply is not available and/or groundwater is
to be abstracted, a condition be imposed in the environmental
clearance to be granted to the proposed project, to the effect that
project proponent shall obtain permission from the CGWA for
abstraction of groundwater & digging of borewell(s) and shall not
abstract any groundwater without prior written permission of the
CGWA, even if any borewell(s) exist at site.”
The case was considered by the SEAC in its 106th meeting held on
17.01.2015 and 107th meeting held on 21.01.2015 and was deferred due to paucity
of time in both the meetings.
The case was considered by the SEAC in its 108th meeting held on
06.02.2015, which was attended by Sh. Nikhal Sadaf, Secretary of the promoter
Society. The project proponent submitted a copy of letter issued by the GMADA
vide no. 3532 dated 28.07.2014, wherein it has been mentioned that this project
site has been allotted to Pinnacle Cooperative House Building Society, GH-3,
Sector-104, SAS Nagar by M/s PACL. The water supply to this project will be
provided by the supply network laid down by the M/s PACL and no separate water
supply connection will be provided. The project proponent further submitted that
no ground water will be abstracted.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal and decided to
forward the case to the SEIAA with the recommendation to grant environmental
17
clearance to the project proponent for development of a group housing project
namely “Pinnacle Homes” at GH-3, Pearl City, Sector-104, Distt. Mohali, subject to
the same conditions as already decided in 102nd meeting of SEAC held on
17.10.2014 in addition to the proposed measures.
The case was considered by the SEIAA in its 80th meeting held on
28.02.2015, which was attended by Sh. D.K. Singal, President of the Society. Sh.
D.K. Singal, President of the Society informed that the Secretary of the Society and
Environmental Consultant are out of station and he requested for deferment of the
case.
The SEIAA accepted the request of the President of the Society and
decided to defer the case to the next meeting.
The decision of the SEIAA was conveyed to the project proponent
vide letter no. 1463 dated 05.03.2015.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by Sh. Nikhil Sadaf, Secretary of the Society.
Sh. Nikhil Sadaf, Secretary of the Society presented the salient
features of the project before the SEIAA and requested to grant environmental
clearance for the project.
The SEIAA observed that the project proponent is required to mark
the location of DG set & other utilities on the layout plan and to correct the MSW
management in the presentation.
The project proponent marked the location of DG set & other utilities
on the layout plan and also corrected the MSW management in the presentation.
The SEIAA observed that the case stands recommended by SEAC and
the Committee awarded ‘Silver Grading’ to the project proposal. The SEIAA
looked into the details of the case and was satisfied with the same. Therefore, the
Authority decided to grant environmental clearance to the project proponent for
development of a group housing project namely “Pinnacle Homes” in an area of
20,244.73 sqm having built-up area of 53,482.252 sqm at GH-3, Pearl City, Sector-
104, Distt. Mohali, subject to the conditions as proposed by the SEAC in addition to
the proposed measures.
18
Item No.82.04: Application for obtaining Environmental Clearance
under EIA notification dated 14.09.2006 for construction of an Educational Institute namely “Rayat & Bahra Bio- Technology Centre Of Excellence” at Chandigarh-Ropar Road, Sahauran, Tehsil Kharar, District SAS Nagar, Punjab.
The SEIAA observed that:
M/s Rayat & Bahra Group of Institutes and Educational
Charitable Society, has applied vide letter No. 609 dated 20.12.2014 for obtaining
the environmental clearance as required under EIA notification dated 14.09.2006
for construction of an Educational Institute namely “Rayat & Bahra Bio- Technology
Centre Of Excellence” at Chandigarh-Ropar Road, Sahauran, Tehsil Kharar, District
SAS Nagar. The project is covered under category 8 (a) of the Schedule appended
to the said notification. The details of the project as per Form I & IA are as under:
The total project area is 33.5 acres having total built up area of 67,685 sqm.
The total cost of the project will be Rs.78.93 cores.
Total water requirement for the project will be 471 KLD (451 KLD for
domestic use and 20 KLD for Laboratory), out of which 340 KLD will be met
from own tubewell and remaining 131 KLD will be met from treated
wastewater.
The total wastewater generation from the project will be 381 KLD, which will
be treated in a CETP to be installed within the project premises. The project
proponent has proposed to use 131 KLD of treated wastewater for flushing
purpose, 45 KLD for irrigation of green area @ 5.51 sqm and remaining 205
KLD will be used for plantation as per karnal technology in summer season.
In winter season, 131 KLD of treated wastewater will be used for flushing
purpose, 14 KLD will be used for irrigation of green area @ 1.71 sqm and
remaining 236 KLD will be used for plantation as per karnal technology. In
rainy season, 131 KLD of treated wastewater will be used for flushing
purpose, 4 KLD for irrigation of green area @ 0.51 sqm and remaining 246
KLD will be used for plantation as per karnal technology.
The total quantity of solid waste to be generated from the proposed project
has been estimated as 2.6 T/day, which will be segregated into bio-
degradable and non-biodegradable waste as per the MSW Rules, 2000. The
19
bio-degradable will be used as manure after treatment. The non-
biodegradable like papers, plastic, metals etc will be sold to the authorized
recyclers.
The e-waste will be handled and managed as per the E-waste (Management
& Handling) Rules, 2011.
The used oil from the D.G. sets will be sold out to the registered recyclers as
per the provisions of the Hazardous Waste (Management, Handling &
Transboundary Movement), Rules, 2008.
The total load of electricity required for proposed project will be 246 KW
which will be supplied by PSPCL. The project proponent has proposed to
install 2 DG sets of capacity 250 KVA and 320 KVA each, for backup power
supply.
The other details of the project have been given in the Form 1 & 1A
submitted by the promoter and the details of the proposed project are as under:
1. Properly filled Form 1 & 1A Yes
2. (a) In case(s) where land has already been purchased/acquired:
Proof of ownership of land
(b) In case where land is yet to be purchased/acquired:
Proof of ownership of land (existing owner) such as copy of latest Jamabandi (not more than one month old) and credible document showing status of land acquisition w.r.t. project site as prescribed in OM dated 07.10.2014 issued by MoEF)
Copy of Jamabandi attached
3. Copy of Master Plan of the area
showing land use pattern of the
proposed site/certificate from
Competent Authority intimating land
use pattern of the project site as
per proposals of Master Plan of the
area.
Permission for CLU has been granted
vide No. 6007 dated 07.06.2005 for an
area measuring 84 bighas and 7 biswas.
4. Layout plan duly approved by the
Competent Authority/Conceptual
plan of the project.
Submitted Conceptual plan of the project.
20
5. Topographical map of the area
showing Contour Plan.
Submitted.
6. Status of construction, if any,
alongwith photographs from all
the four sides.
Submitted, photographs showing that
construction has already been done at
site.
7. 500 meter radius map of the area
from periphery of project site
clearly indicating the various
industries (specifically red category
industries) and structures lying in
the area.
Submitted.
8. Location plan showing the exact
location of the project site w.r.t.
some permanent/important features
of the area and site plan of the
project showing the following
i) Location of STP ;
ii) Solid waste storage area.
iii) Green belt
iv) Parking space
v) RWH and water recharge pits
vi) Fire fighting equipment layout
vii) First aid room
viii) Location of Tubewells
ix) DG Sets and Transformers
x) Any other utilities
i) Marked ii) Marked iii) Marked iv) Marked. v) Marked. vi) Marked vii) Marked viii) Marked ix) Marked x) E-waste storage area
marked
9. Permission of Competent Authority
for;
a) Water and Sewerage connection
A letter from concerned Local
Body/Authority giving details about
existing status of sewer
connectivity and availability of
water supply in the area and
acceptance of Local Body for taking
the quantity of sewage to be
generated by the proposed project
and providing the water supply.
Existing position of public sewer
a) The treated wastewater will be used onto land for plantation.
21
and water supply line duly marked
on the lay out map/plan.
b) Collection of Solid waste
b) Solid waste will be used as manure after treatment.
10. Water balance chart for summer,
rainy and winter seasons
indicating critical requirements.
Submitted.
11. Availability of adequate land for
use of treated sewage and
plantation.
Submitted
12. Analysis reports of ambient air,
ground water and noise levels
from NABL / MoEF accredited
laboratories.
The ambient air monitoring has been got done from M/s Chandigarh Pollution Testing Laboratory and the analysis results indicate that the concentration of various pollutants such as PM2.5, PM10, SO2, NO2 and CO have been measured. Also, ambient noise monitoring has been got done from the said firm and the analysis results indicate that the noise levels during day and night times, have been measured in the range of 41-44 dB(A) leq and 35-38 dB(A) leq, respectively, against the prescribed standards of 55 and 45 dB(A) leq. The analysis report of groundwater has also been
submitted.
13. Quantification of energy saved
and renewable energy devices
used.
Submitted
14. Drawing showing plumbing
systems for use of fresh, treated
and hot water
The treated waste water will not be
reused for plumbing.
15. Construction schedule
(PERT/CPM Chart)
Construction work has already been
completed.
16. Affidavits for ;
a) Constitution of Environment Monitoring Cell
22
b) Use of ready mix concrete or use of fly ash during construction.
c) To provide Fire Fighting System
d) To provide wind breaking curtains and water sprinkling system to minimize dust emissions.
e) To provide adequate safety measures for the construction workers during the construction phase.
Submitted
17 Environmental Management Plan indicating the following: a) All mitigation measures for
each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.
b) Compliance of various environmental regulations
c) Steps to be taken in case of emergency such as accidents at the site including fire.
d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.
e) Capital & recurring cost for
the EMP per year and the
details of funds for the same.
f) Name of the individual
persons / organization, who
will be responsible for
Submitted
Submitted
Submitted Registrar will be responsible for implementation of Environment Management Plan. Rs.63 lacs will be incurred on account of capital cost and Rs.5.50 lacs/annum will be incurred on account of recurring charges for implementation of EMP during the operation phase.
Registrar will be responsible for
implementation of Environment
Management Plan.
23
implementation of EMP after
the lapse of the period for
which the project proponent
is responsible.
18 Corporate Social Responsibility indicating various activities to be undertaken, provisions of funds for the same, the period for which the same is to be implemented and the person(s) responsible for the implementation of the same.
The implementation of the Corporate
Social Responsibility will be
responsibility of the Registrar. Rs.17
Lacs will be utilized for the following
activities:
Donation for school welfare in Govt. Senior Secondary School, Dao Majra.
School books to disadvantaged students within 2km radius schools.
Environment awareness and tree plantation drive in all villages within 1km radius.
Medical check up cum cleanliness camps in all villages within 2km radius.
Free education upto primary level to children of slum dwellers of nearest villages.
19. Traffic Circulation System and
connectivity with a view to
ensure adequate parking, conflict
free movements, Energy efficient
Public Transport.
Submitted.
20. Disaster/Risk Assessment and
Management Plan
Submitted.
The case was considered by the SEAC in its 106th meeting held on
17.01.2015 and 107th meeting held on 21.01.2015 and was deferred due to paucity
of time in both the meetings.
The case was considered by the SEAC in its 108th meeting held on
06.02.2015, Sh. Jagjit Singh, Purchase Supervisor of the Ryat & Bahra, appeared
before the SEAC and requested for deferment of the case.
The SEAC decided to accept the request of the representative and
deferred the case till next meeting.
24
The case was considered by the SEAC in its 109th meeting held on
20.02.2015 and was attended by the following:
1. Sh. R.P. Chaudhary, AO
2. Sh. Sital Singh, CTPL Envirotech Chandigarh
Sh. Sital Singh, Environmental consultant of the promoter company
submitted that the promoter Company has completed all the civil construction work
and institute is functional.
The SEAC observed that the case is required to be dealt as per the
procedure mentioned in the Office Memorandum dated 12.12.2012 of the Ministry
of Environment & Forests as amended on 27.06.2013 since the promoter company
has violated the provisions of EIA notification dated 14.09.2006 by starting
construction of the project without obtaining environmental clearance under the
said notification.
After detailed deliberations, the SEAC decided as under:
(i) To forward the case to SEIAA with the recommendation to ask the
project proponent to submit a formal resolution passed by the Board
of Directors of the Company or to the Managing Committee / CEO of
the Society, Trust, partnership / individually owned concern, within 60
days, mentioning that violations will not be repeated in future and in
the meantime, the project may be delisted. In the eventuality of not
having any response from the project proponent within the prescribed
limit of 60 days, the project file may be closed.
(ii) To recommend to SEIAA for:
initiating credible action against project proponent /
responsible persons / promoter company under the
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance under EIA notification dated
25
14.09.2006 is obtained.
The SEIAA & SEAC in their 6th combined meeting held on 17.10.2014
had decided that parking for visitors/public transport should be provided by project
proponent(s) within the premises near the main gate/entrance to avoid parking
along the road side outside the premises. The project proponent should also
provide some security personnel to guide the visitors in this regard. It was further
decided to constitute a Committee of SEAC members and was requested to visit
Patiala-Chandigarh Road, Banur-Landran- Kharar Road, Mohali-Ropar Roads for this
purpose.
The Committee visited the said area and report of the Committee was
placed before the SEIAA in its 7th combined meeting held on 18.11.2014, wherein,
it was decided to issue notice u/s 5 of Environment (Protection) Act, 1986 with an
opportunity of personal hearing before the SEIAA, for violating provisions of EIA
notification dated 14.09.2006. The name of M/s Rayat & Bahra Educational
Complex also figured amongst the Educational Institutions visited by the
Committee.
As such, in compliance to the above mentioned decision of SEIAA &
SEAC and in exercise of the powers as delegated by MoEFCC vide notification no.
S.O. 637 (E) dated 28.02.2014, a notice u/s 5 of Environmental (Protection) Act,
1986 proposing to issue the certain directions as mentioned therein with an
opportunity of personal hearing before SEIAA on 24.12.2014 was issued to the
project proponent vide letter No. 3571 dated 04.12.2014.
The hearing before SEIAA was attended by Sh. Sandeep Puri, Director
(Planning) of the Society on 24.12.2014.
Sh. Sandeep Puri, submitted that 27 m wide strip of land outside the
boundary wall/along the Highway where vehicles are parked is self owned. He
further submitted that they will deploy security guards and take other traffic control
/ management measures and ensure that in future no traffic hazard is caused due
to the stoppage/parking of vehicles by students/visitors in front of the Institute. He
also informed that they have applied for obtaining environmental clearance under
EIA notification dated 14.09.2006 on 22.12.2014.
After hearing, the SEIAA observed that the Institute has completed
construction and is operating without obtaining environmental clearance in violation
26
of provisions of EIA notification dated 14.09.2006 and Environment (Protection)
Act, 1986.
After detailed deliberations, the SEIAA took certain decisions. The
details of the decision and the compliance made thereof is as under:
Sr.No.
Decision
Compliance
1. Ask the institute to submit approved plan and other documentary evidence to prove that the parking land belongs to the Institute and no encroachment of Government land is involved.
The decision was conveyed to the project proponent vide letter No. 20 dated 07.01.2015. The project proponent has submitted reply vide letter dated 17.02.2015 received on 24.02.2015 has informed that the traffic/parking plan of Institute has already been submitted vide letter dated 07.01.2015, wherein, khasra numbers of the land out of which area is used for parking have specifically been marked. The project proponent has also attached copy of registered land sale deeds. The plan submitted vide letter dated 07.01.2015 is not approved by any competent authority.
2. Ask the the Institute to submit complete traffic management plan, within 15 days, to ensure that no traffic congestion / obstruction takes place along the main road/highway in front of the Institute due to stoppage/parking of vehicles including public/private vehicles meant for loading/unloading passengers/ students of the Institute.
It has been informed that arrangement for traffic plan management were also explained in the letter dated 07.01.2015. The traffic plan submitted vide letter dated 07.01.2015 shows parking spaces and traffic movement / circulation route only and no complete traffic management plan has been submitted.
3. Ask the project proponent to submit, within 60 days, a formal resolution passed by the Board of Directors of the Company or to the Managing Committee / CEO of the Society, Trust, partnership / individually owned concern, mentioning that violations in respect of starting construction activities without obtaining
An undertaking dated 16.02.2015 by Sh. Gurvinder Singh Bahra, Chairman, Rayat & Bahra Group of Institutes has been submitted. However, formal resolution passed by Board of Directors has not been submitted.
27
environmental clearance under EIA notification dated 14.09.2006, are un-intentional and will not be repeated in future.
4. Initiate credible action against project proponent(s), responsible person(s) & promoter company by invoking powers u/s 19 of the Environment (Protection) Act, 1986 as delegated by Ministry of Environment & Forests vide notification No. S.O. 638 (E) dated 28.02.2014 due to start of construction activities of the project without obtaining Environmental Clearance under EIA notification dated 14.09.2006. Punjab Pollution Control Board be written in this regard for taking necessary legal action u/s 15 of the Environment (Protection) Act,1986 for the period for which the violation has taken place.
Punjab Pollution Control Board was requested to launch prosecution against the project proponent and its responsible persons vide letter no. 22 dated 07.01.2015. Now, Member Secretary, Punjab Pollution Control Board vide letter no. 650 dated 19.02.2015 has informed that in one of such cases where Board has launched prosecution against the project proponent and its responsible person on the direction of SEIAA, one of the person against whom prosecution was launched submitted representation to the Board/Court stating that he is not responsible for day to day work and requested to replace the name of another person in his place. It has been requested that to avoid legal complications lateron, SEIAA shall also convey the names of responsible persons to the Board against whom prosecution is to be launched.
5. Issue directions under section 5 of the Environment (Protection) Act, 1986 as delegated by Ministry of Environment & Forests vide notification No. S.O. 637 (E) dated 28.02.2014 to restrain the promoter company from carrying out any further construction or operation activity of the project till the environmental clearance under EIA notification dated 14.09.2006 is obtained.
Directions under section 5 of the Environment (Protection) Act, 1986 have been issued to the project proponent vide letter no. 20 dated 07.01.2015.
The project proponent while quoting the provisions of notification
dated 22.12.2014 issued by Ministry of Environment, Forests & Climate Change,
wherein, projects such as industrial sheds, school, college, hostel for educational
institution have been exempted from obtaining environmental clearance has
28
requested to reconsider their case under the provisions of above mentioned fresh
notificaction.
The SEIAA observed that an e-mail dated 27.02.2015 has been
received from Sh. Sandeep Puri, Director (Planning) Rayat & Bahra Group of
Institutes, wherein while expressing inability to attend the meeting of SEIAA on
28.02.2015 due to some un-avoidable circumstances and request has been made
to afford another opportunity of next meeting of SEIAA.
After deliberations, the SEIAA decided to accept the request of
project proponent and defer the case to the next meeting.
The decision of the SEIAA was conveyed to the project proponent
vide letter no. 1452 dated 05.03.2015.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015 and was attended by Sh. Sandeep Puri, Director (Planning) of the
promoter Company
Sh. Sandeep Puri, Director (Planning) of the promoter Company
submitted that the promoter Company has completed all the civil construction work
and institute is functional.
The SEIAA observed that in compliance of the decision taken by it
during the meeting held on 24.12.2014, the project proponent still required to
submit the following compliances:
(i) Complete traffic management plan is required to be submitted as only traffic
movement & parking arrangement marked on the layout map has been
submitted with the letter dated 07.01.2015
(ii) A formal resolution passed by the Board of Directors of the Company or to
the Managing Committee / CEO of the Society, Trust, partnership /
individually owned concern, mentioning that violations in respect of starting
construction activities without obtaining environmental clearance under EIA
notification dated 14.09.2006, are un-intentional and will not be repeated in
future.
(iii) Names of responsible persons against whom prosecution is to be launched
alongwith copy of Memorandum of Article & Association / partnership deed /
29
undertaking of sole proprietorship / list of Directors and names of other
persons responsible for managing the day-to-day affairs of the project.
The project proponent requested that as per notification dated
22.12.2014 issued by MoEF&CC, being a college they are exempted from obtaining
environmental clearance under EIA notification, 2006.
In this regard, the SEIAA observed that the SEAC members during
visit to the area on 14.11.2014 has intimated that the campus is being run in the
name of Rayat & Bahra University. The project proponent could not give any
satisfactory reply to this observation of SEIAA.
Therefore, the SEIAA decided to defer the case and ask the project
proponent to submit the complete reply alongwith supporting documents of the
above mentioned observations within 15 days.
Item No.82.05: Action u/s 5 of the Environmental (Protection) Act, 1986 against the Educational Complex namely "Chandigarh Group of Colleges" already existing in the revenue estate of Village Landran, Tehsil Kharar, District Mohali for violation of the provisions of EIA Notification dated 14.09.2006.
The SEIAA observed that:
The Ministry of Environment & Forests, Govt. of India, New
Delhi has issued EIA notification no. 1533 (E) dated 14/9/2006 under the provisions
of Environmental (Protection) Act, 1986 and as per the provisions of the said
notification, it is mandatory for the project/activities covered under the schedule
appended with the said notification, to obtain prior environmental clearance from
Ministry of Environment & Forest (MOEF)/ State Level Environment Impact
Assessment Authority (SEIAA).
It has been clearly provided in the said EIA notification dated
14/9/2006 that project proponent cannot start any construction work or
preparation of land except for securing of land before obtaining the environmental
clearance. The Ministry of Environment & Forests, Govt. of India, New Delhi vide
Office Memorandum dated 19.08.2010 has further clarified that no activity relating
to any project covered under this notification including civil construction, can be
undertaken at site without obtaining prior environmental clearance except fencing
30
of the site to protect it from getting encroached and construction of temporary
shed(s) for the guard(s).
M/s Shri Guru Ram Das Educational Society Regd. had applied for
obtaining the Environmental Clearance under EIA notification dated 14.09.2006 for
an Educational Complex namely "Chandigarh Group of Colleges" already existing in
the revenue estate of Village Landran, Tehsil Kharar, District Mohali.
In the 53rd meeting of SEAC held on 24.11.2011, the project
proponent, during presentation, himself had admitted that the entire construction
of the institute had already been completed.
Thereafter, the environmental clearance application submitted by the
Society was delisted by SEIAA on the recommendations of SEAC in its 51st meeting
held on 06.09.2013 and decision in this regard was conveyed to the Society vide
letter no. 42733 dated 24.09.2013. No fresh application for obtaining
environmental clearance under EIA notification dated 14.09.2006 has been
submitted by the Society, so far.
The Educational Complex, was visited by the Committee, comprising
of Ers. Malvinder Singh, Nirmal Singh Kahlon and JS Sekhon and observed that:
“A large number of cars and two wheelers were parked on both
sides of road. Since this institute is very close to main Chandigarh
crossing, parking on road is a big traffic hazard”
32
It is evident from above, that the project proponent is operating the
Educational Complex without obtaining environmental clearance and is violating the
provisions of the EIA notification dated 14.09.2006.
The matter was considered by the SEIAA & SEAC in its 7th combined
meeting held on 18.11.2014, wherein, it was decided to issue notice u/s 5 of
Environment (Protection) Act, 1986 with an opportunity of personal hearing before
the SEIAA, for violating provisions of EIA notification dated 14.09.2006.
The matter was considered by the SEIAA & SEAC in its 7th combined
meeting held on 18.11.2014, wherein, it was decided to issue notice u/s 5 of
Environment (Protection) Act, 1986 with an opportunity of personal hearing before
the SEIAA, for violating provisions of EIA notification dated 14.09.2006.
As such, in compliance to the above mentioned decision of SEIAA &
SEAC and in exercise of the powers as delegated by MoEFCC vide notification no.
S.O. 637 (E) dated 28.02.2014, a notice u/s 5 of Environmental (Protection) Act,
1986 proposing to issue the following directions with an opportunity of personal
hearing before SEIAA on 24.12.2014 has been issued to the project proponent vide
letter No. 3570 dated 04.12.2014:
1. That the group will stop forthwith operations of their Educational Complex.
2. That the group will not restart any operation till the required environmental
clearance is obtained.
3. That Punjab State Power Corporation Limited will disconnect the supply of
electricity available to Educational Complex.
4. That Municipal Council/Local Body will disconnect the water supply and
sewerage connection available to the premises of Educational Complex.
The hearing before SEIAA was attended by Sh. R.S. Rakhra, Assistant
Director (Amn) of the Institute on 24.12.2014.
He submitted that they are in the process of obtaining various
approvals/permissions from the concerned departments so as to attend to the
observations of SEAC completely and requested for one month's time to resubmit
the complete environmental clearance application. He further submitted that
vehicles are parked by students / visitors outside their premises at their own
though they have sufficient parking space available inside their premises. He
submitted that they will deploy security guards and take other traffic control /
33
management measures and ensure that in future no traffic hazard is caused due to
the stoppage/parking of vehicles by students/visitors in front of the Institute. He
also submitted that the construction activity has been stopped completely and at
present no construction activity is going on in the premises.
The SEIAA was apprised that Punjab Pollution Control Board in
compliance to the orders issued by Govt. of Punjab, Department of Science,
Technology & Environment has filed a criminal complaint in the Competent Court of
law u/s 15 & 16 read with section 19 of Environment (Protection) Act, 1986 and
issued directions vide letter no. 1476 dated 04.03.2014 u/s 5 of Environment
(Protection) Act, 1986 directing the project proponent to not to carry out any
further construction activity at site till it obtains environmental clearance.
Photocopies of the above said documents were procured from record file of Punjab
Pollution Control Board, Zonal Office-1, Patiala and have been placed in the record
file of SEIAA.
After hearing, the SEIAA observed that the Institute has
completed construction and is operating without obtaining environmental clearance
in violation of provisions of EIA notification dated 14.09.2006 and Environment
(Protection) Act, 1986.
After detailed deliberations, the SEIAA decided to:
(i) Ask the the Institute to submit complete traffic management plan,
within 15 days, to ensure that no traffic congestion / obstruction
takes place along the main road/highway in front of the Institute due
to stoppage/parking of vehicles including public/private vehicles
meant for loading/unloading passengers/ students of the Institute.
(ii) Ask the project proponent to submit, within 60 days, a formal
resolution passed by the Board of Directors of the Company or to the
Managing Committee / CEO of the Society, Trust, partnership /
individually owned concern, mentioning that violations in respect of
starting construction activities without obtaining environmental
clearance under EIA notification dated 14.09.2006, are un-intentional
and will not be repeated in future.
(iii) Ask the institute to submit application for environmental clearance
under EIA notification, 2006 within one month.
34
(iv) Sh. Gulshan Kumar, AEE (SEIAA) shall visit the Institute to verify the
construction status and submit the report.
The decision of the SEIAA was conveyed to the project proponent
vide letter no. 03 dated 02.01.2015.
The project proponent has not submitted any compliance report of
the above mentioned decisions.
However, Sh. Gulshan Kumar, AEE (SEIAA) has submitted its report,
the contents of the same are as under:
Visit Report
1. Name & Address of Institution : Chandigarh Group of Colleges. Landran.
2. Date of Visit : 07.01.2015
3. Person Contacted : Capt. R.S. Rakhra Asstt. Director
(Admn.)
Observations:
I. The institute has 3 no. of parkings available for students &
approximately 650 cars can be parked and about 1000
bikes/motorcycles/activas can be parked. The institute has 24 no of
buses, which were parked inside the campus. Apart from this the
faculty can park their vehicles inside the campus. The institute has
hired a contractor for parking arrangement of contract has been
signed (copy enclosed) with contractor on 20.06.2014. It seems that
adequate parking is available, however, Some students (about 50
bikes & 30-40 cars) along roadside inspite of clearcut instructions
issued by the Admn. that no one will park vehicle along roadside. The
college has also provided visitor parking.
II. The institute has completed the construction work of New (Block)
Applied Services – Block-10) and adjoining hostel already. Only
connection of sewerage, construction of boundary wall, landscaping
of lawns & minor finishing work is pending.
III. The institute has also completed construction work of STP, which will
be commissioned in next 1-2 weeks.
35
The case was considered by the SEIAA in its 80th meeting held on
28.02.2015, which was attended by the following on behalf of project proponent:
i. Sh. R.S. Rakhra, Director (Admn).
ii. Sh. Sandeep Garg of M/s Eco Labs, Mohali, Environmental Consultant of the promoter company
Sh. R.S. Rakhra, Director (Admn) of Chandigarh Group of Colleges
requested that total built up area of the premises is 1,48,000 sqm and in the
premises only group of Colleges affiliated with Punjab Technical University are
being run and they be exempted from the ambit of EIA notification, 2006.
After deliberations, the SEIAA decided to ask the project proponent to
submit documentary evidences towards his claim/contentions.
The decision of the SEIAA was conveyed to the project proponent
vide letter No. 1387 dated 05.03.2015.
Now, the project proponent vide letter No. 1212 dated 20.03.2015
has informed that the proposed built up area of the project is 148000 sqm out of
which 123875.52 sqm has already been constructed at the said site. The plan for
construction of additional land area of 24124.48 sqm has been dropped and no
new construction will be done at the site. The project proponent has submitted the
layout plan showing the details of area, but the same has not been approved
by the Competent Authority.
Further, the project proponent submitted that the name suggests that
Chandigarh Group of Colleges is an integrated campus of 5 colleges. All these
colleges are affiliated Punjab University and approved by AICTE.
The project proponent has also informed that if in future the built up
area of the project increased then the statutory clearances will be obtained under
EIA notification.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following on behalf of project proponent:
i. Sh. R.S. Rakhra, Director (Admn) of the promoter company
ii. Sh. Sandeep Garg of M/s Eco Labs, Mohali, Environmental Consultant of the promoter company.
36
The SEIAA observed that since construction has already been
completed, as such, project proponent is required to submit approved layout plan
to prove his contention that the total built up area of the premises is 1,48,000 sqm.
The SEIAA decided to ask the project proponent to submit the
approved layout plan and to defer the case till the project proponent submits the
same.
Item No.82.06: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for an Educational Complex namely "Gian Sagar Medical College & Hospital and Gian Sagar Dental College & Hospital established by Gian Sagar Educational & Charitable Trust, in the revenue estate of Village Ram
Nagar, Tehsil Rajpura, Distt. Patiala.
The SEIAA observed that:
1. M/s Gian Sagar Educational & Charitable Trust had applied for obtaining
environmental clearance as required under EIA notification dated 14.09.2006
for the Medical College, Hospital and allied requirements such as residential
apartments in the year 2008 and the same was refused by the SEIAA Punjab
vide letter no. 32906 dated 7.10.2009 due to the fact that the layout plan of
the Educational Institution-cum-hospital was not approved by the
Competent Authority of the State.
2. Thereafter, M/s Gian Sagar Educational & Charitable Trust has applied for
obtaining Environmental Clearance under EIA notification dated 14.09.2006
for an Educational Complex namely "Gian Sagar Medical College & Hospital
and Gian Sagar Dental College & Hospital established in the revenue estate
of Village Ram Nagar, Tehsil Rajpura, Distt. Patiala. The project is covered
under category 8 (b) of the Schedule appended to the said notification.
3. The case was considered by the SEAC in its 54th meeting held on
30.12.2011, which was attended by the following on behalf of the project
proponent:
i) Sh. S.C. Tyagi, Chief Project Manager ii) Sh. Jai Karan Sharma, Senior Manager (Admn & Liaison) iii) Sh. Sandeep Garg, Environmental Consultant of M/s Eco
Laboratories and Consultants, Mohali.
The Committee perused the minutes of 61st meeting of the
Accreditation Committee, National Accreditation Board for Education &
37
Training, Quality Council of India and noted that the accreditation of M/s Eco
Laboratories & Consultant Pvt. Ltd., Mohali has been cancelled. Therefore,
the Committee did not allow the environmental consultant of the promoter
company to make a presentation of the project proposal. The Committee
further noted that the project proponent is required to submit certain
information / data for scoping of the project proposal.
After detailed deliberations in the matter, the Committee
decided to defer the case till the project proponent submits the reply of its
observations. It was also decided to call the Medical Superintendent of
Rajindera Hospital, Patiala and Oncology Expert of PGI, Chandigarh in the
meeting of the SEAC in which the case is to be considered. The said decision
of the Committee was conveyed to the project proponent vide letter no. 392
dated 24.01.2012.
4. The project proponent vide letter no. GSMCH/11-12/150 dated 23.02.2012
has submitted reply of the observations of the SEAC, the details of which are
as under.
Sr. No.
Observations of the Committee Members
Reply of the observations
1 Whether 0.52 acres of land area, for which permission for CLU is yet to be obtained, is a part of the project proposal or not? If yes, then submit the CLU for the said area and intimate for what purpose the same will be used.
Permission to seek CLU for 0.52 acres of land area is in process with the concerned department and the said land area has been earmarked for the construction of residential complex.
2 The photographs submitted by the project proponent show that the construction of the Institute has already been completed, as such, intimate the reasons as to why the construction has been made in violation of provision of the EIA notification dated 14.09.2006 and submit an undertaking to the effect that no further construction will be done without obtaining environmental clearance required under the said notification.
No further construction will be done without obtaining the Environmental Clearance required under the EIA notification dated 14.09.2006. The project proponent has also informed that the earlier construction has been made prior to issuance of EIA notification dated 14.9.2006.
3 Whether the project proponent is yet to construct any additional building out of the total built-up area mentioned in the application
There is no proposal for construction of any additional building at present. Prior approval will be obtained in
38
for obtaining environmental clearance or not?
case any construction is made in future.
4. How much quantity of bio-medical waste is generated and how each category of bio-medical waste is being managed and handled? Further what is the status of authorization required under the Bio-medical Waste (Management & Handling) Rules, 1998.
Details have been submitted.
5. Whether any kind of hazardous waste like mercury is generated? If yes, the status of authorization under the Hazardous Wastes (Management, Handling & Transboundary Movement) Rules, 2008 and how the said wastes are being managed and handled?
The institution is using mercury thermometers and blood pressure apparatus. If there is any breakage of the apparatus containing mercury, the same is collected and sent to Bio-medical Workshop where the Biomedical Engineer conserves it for further use in repairable blood pressure apparatus. However, more than one third of blood Pressure Apparatus have been replaced by aneroid BP Apparatus in phase-1 and the remaining mercury containing apparatus will be replaced with non-mercury apparatus by the end of July, 2012.
6. Whether any kind of e-waste is generated and how the same is being managed & handled?
There is no generation of e-waste at present since the equipment purchased is fairly new and is being disposed off under exchange cost programme.
7. What are the present mode of treatment / disposal of bio-degradable, non-biodegradable and recyclable waste.
At present, the entire bio-degradable, non-bio-degradable and recyclable waste is sent to the STP. However, ETP equipments have been procured and civil work for installation of ETP is in progress and the same will be made operational by 22.03.2012.
8. What type of the industries are located within a radius of 500 m from the project site and their impact on the Institution?
There is one RCC Pipe plant within a radius of 500 m from the site of the Institute.
39
9. Whether any laundry plant has been installed and how much wastewater is generated from the said plant and which treatment facility has been installed for the same and what mode of disposal has been provided for the same?
The laundry plant has been installed in which the average usage of water is about 10,000 liters per day. The wastewater generated from the said plant is treated in the existing STP. However, there is a proposal to install a separate ETP for the same.
10. Whether any nuclear liquid/solid waste is generated and how the same is being managed & handled and whether any permission for the same has been obtained from Atomic Energy Regulatory Board (AERB) or not?
No nuclear (liquid/solid) waste is generated in the Institute.
11. Whether any radio-active material is used or not? If yes, whether permission for the same has been obtained from AERB or not?
No radioactive material is used in the Institute.
12. How much wastewater is generated from X-ray section and how the same is being managed and handled?
No such waste is generated from the X-ray section in the Institute.
5. The project proponent was requested by the SEAC vide letter no.1086 dated
20.03.2012 to attend its 57th meeting on 27.03.2012. However, the project
proponent vide letter no 657 dated 27.3.2012 informed that the responsible
person dealing with the case had resigned and now the matter is being
looked into by Mr. S.C Tyagi, who is abroad due to some personal work.
Therefore, the promoter company will not be in a position to present the
project proposal on 27.03.2012 and requested for some more time to
present the project proposal.
In compliance to decision taken by the SEAC in its 54th
meeting held on 30.12.2011, Director, Post Graduate Institute of Medical
Education Research (PGIMER), Chandigarh and Medical Superintendent,
Govt. Rajindera Hospital, Patiala were requested vide letter no. 1086 dated
20.03.2012 and 1088 dated 20.03.2012, respectively to attend the 57th
meeting of the SEAC on 27.03.2012, so as to advise the Committee.
Accordingly, Dr Sushmita Ghoshal, Professor, Deptt of Radiotherapy
PGIMER, Chandigarh and Dr V.K Dangwal, Associate Professor,
40
Department of Radiotherapy, GMC Patiala attended the said meeting of the
SEAC and informed that:
i) For setting up of radiotherapy unit and radio diagnostic centre, the
hospital is required to get the layout plan approved from Atomic
Energy Regulatory Board (AERB) before carrying out any
construction activity at site. Also, AERB issues certificate for
operation of said unit/centre and inspections are being carried out
from time to time by the officials of the AERB, so as to ensure as to
whether the guidelines/regulations of the AERB are adhered with or
not.
ii) Similarly, for setting up of Nuclear Medicine Centre and X-ray units
/CT scan units, the hospital is required to get the layout plan
approved from Atomic Energy Regulatory Board (AERB) before
carrying out any construction activity at site. Also, AERB issues
certificate for operation of said centre/ X-ray/CT scan units and
inspections are being carried out from time to time by the officials
of the AERB, so as to ensure as to whether the
guidelines/regulations of the AERB are adhered with or not.
iii) Only qualified person authorized from AERB can handle Nuclear
medicine & isotopes and this authorization generally remains valid
for three years.
iv) Every hospital having Radiotherapy or Radio-activity unit, is required
to appoint Radiological Safety Officer (RSO), who is responsible for
activities related to the Radio-therapy and Radio-activity unit.
After detailed deliberations in the matter, the Committee was
of the opinion, that there is a need to ask the project proponent to submit
the reply of above-mentioned points brought out by the Experts for
scoping of the project proposal. The Committee, therefore, decided to
defer the case till the proper reply of observations of the Experts is
received. The decision of the Committee was conveyed to the project
proponent vide letter No. 15921 dated 09.04.2012.
41
6. The project proponent submitted the reply of the observations of the
Committee, the details of which are as under:
Sr. No.
Observations of the SEAC Reply submitted by the project proponent
1. For setting up of radiotherapy unit and radio diagnostic centre, the hospital is required to get the layout plan approved from Atomic Energy Regulatory Board (AERB) before carrying out any construction activity at site. Also, AERB issues certificate for operation of said unit/centre and inspections are being carried out from time to time by the officials of the AERB, so as to ensure as to whether the guidelines/regulations of the AERB are adhered with or not.
Submitted a copy of the letter vide which layout plan has been approved by the AERB vide letter no. AERB/RSD/X-ray/ PJ / 2006 / 26444 dated 05.03.2007 and submitted a copy of layout plan photocopied in pieces, as such, nothing can be seen and concluded from the same.
2. Similarly, for setting up of Nuclear Medicine Centre and X-ray units / CT scan units, the hospital is required to get the layout plan approved from Atomic Energy Regulatory Board (AERB) before carrying out any construction activity at site. Also, AERB issues certificate for operation of said centre/ X-ray/CT scan units and inspections are being carried out from time to time by the officials of the AERB, so as to ensure as to whether the guidelines/regulations of the AERB are adhered with or not.
Submitted a copy of letter issued by AERB vide No. AERB/RSD/X-ray/ PB / 2011 /7592 dated 22.06.2011, vide which the management of the hospital has been requested by the AERB to comply with the observations before installation of Mammography unit.
3. Only qualified person authorized from AERB can handle Nuclear medicine & isotopes and this authorization generally
No nuclear medicine is used in the hospital, as such, no authorization from AERB is required.
42
remains valid for three years.
4. Every hospital having Radiotherapy or Radio-activity unit, is required to appoint Radiological Safety Officer (RSO), who is responsible for activities related to the Radio-therapy and Radio-activity unit.
No radio-therapy or radio activity unit has been installed in the hospital, as such, no RSO is required.
7. The project proponent was requested by the SEAC vide letter no. 30350
dated 16.07.2012 to attend its 62nd meeting on 21.07.2012 to present the
reply of its observations. Also, Director, Post Graduate Institute of Medical
Education Research (PGIMER), Chandigarh and Medical Superintendent,
Govt. Rajindera Hospital, Patiala were requested vide letter no. 3222 dated
19.07.2012 and 3223 dated 19.07.2012, respectively to attend the 57th
meeting of the SEAC on 27.03.2012, so as to advise the Committee
Following were present in the said meeting on behalf of the
project proponent:
i) Sh. A.S. Sekhon, Dean of the Institute ii) Sh. S.C. Tyagi, Chief Project Manager of the Institute iii) Sh. Jai Karan Sharma, Senior Manager (Admn & Liaison)
Besides above, Dr. V.K. Dangwal, Associate Professor,
Department of Radiotherapy, GMC Patiala attended the meeting and he
informed that he is satisfied with the reply submitted by the project
proponent regarding the observations of 57th meeting of the Committee.
Thereafter, Sh. J.K. Sharma, AGM submitted a letter no.
GSECT/Admn/2012/43 dated 19.07.2012, in which it has been mentioned
that:
(i) Permission for CLU for additional land area (0.52 acres) in addition to
14 acres has been obtained from the Department of Town & Country
Planning vide letter no. 1605-CTP (Pb)/SP-432 (P) dated 23.04.2012
and submitted a copy of the said permission.
(ii) The area of the project has been increased from 56.61 acres to 58.31
acres and the revised layout plan is yet to be approved by the
Competent Authority of the State.
43
(iii) The construction of the project was started in the month of October,
2005 and the major construction has already been completed. The
representative of the project proponent submitted a copy of the
resolution passed by the Board of Trustees in which it has been
stated that no further construction will be done in the complex
without obtaining the environmental clearance.
(iv) The total built up area with the revised proposal has been increased
from 1,90,824.93 sqm to 2,25,212.14 sqm.
(v) There is a proposal to construct NRI Boys hostel having built up area
4771.45 sqm.
(vi) The categorywise quantity of bio-medical generated during the period
January, 2011 to December, 2011 is as under.
Sr. No Category Quantity(Kg)
1. Yellow Bags 5604
2. Red Bags 6726
3. Blue Bags 4002
4. White Waste 2839
5. Sharp 459.2
The entire bio-medical waste is being given to M/s
Rainbow Environments (P) Ltd., Village Balyali, District SAS Nagar and
the authorization from the Punjab Pollution Control Board under the
Bio-Medical Waste (Management & Handling) Rules, 1998 has been
obtained and the same is valid upto 31.03.2015.
(vii) Only source of hazardous waste is mercury from B.P. apparatus,
majority of which had been replaced with aneroid type B.P.
apparatus. The old mercury based B.P. apparatus had been sent back
to the supplier.
(viii) The e-waste is being handled as per E-waste (Management &
Handling) Rules, 2011.
(ix) The municipal solid waste is being collected and disposed off to the
Municipal Council dumping site through a private contractor.
(x) Submitted a copy of plan showing various features within a radius of
500 m.
44
(xi) About 10 KLD of wastewater is generated from the laundry plant and
a separate ETP will be installed for the same.
The SEAC observed that the project proponent has now
revised the project proposal due to which there may be changes in the data
/ information in the earlier application submitted by the project proponent
for obtaining environmental clearance under EIA notification dated
14.09.2006. After detailed deliberations in the matter, the SEAC further
observed that the project proponent is required to intimate the Committee
as to what will be the changes in the data / information in the application
submitted by it after revised project proposal and to submit the revised
layout plan, before scoping of the project proposal.
The Dean of the Institute requested the Committee to give 10
days to submit the reply of observations of the Committee and revised
layout plan. The Committee agreed to accept the request of the Dean of the
Institute and decided to defer the case till the project proponent submits
proper reply of its observations. The decision of the Committee was
conveyed to the project proponent vide letter no. 32785 dated 03.08.2012.
8. Thereafter, the Ministry of Environment & Forests vide Office Memorandum
on 30.10.2012 informed that all projects which are pending between 3 to 6
months of the SEAC meeting for want of information, reminder may be sent
seeking information within a month. If the information is not received within
this period, even these projects may be de-listed.The case of this project
was considered by the SEAC in its 66th meeting held on 11.01.2013 in light
of said OM of the Ministry of Environment and Forests and decided to issue
reminder to the promoter company regarding the above. The decision of the
SEAC was conveyed to the project proponent vide letter no. 6886 dated
12.02.2013.
9. Thereafter, the project proponent vide letter no. 23 dated 11.03.2013
informed that the Gian Sagar Educational & Charitable trust got approved its
layout plan from the Chief Town Planner, Punjab vide their office memo no.
5198-SP-463 dated 25th July 2011 for an area measuring 56.61 acres. The
layout plan was submitted by the Trust to the said authority for an area of
57.13 acres, but it was considered only for 56.61 acres as some buildings
were under construction on the remaining area. However, after getting
45
change of land use for additional land, the area of the project was increased
from 56.61 acres to 58.31 acres and accordingly, the Trust submitted the
revised layout plans for approval to the Chief Town Planner, Punjab vide
letter no. GSECT/ADMN/2012/25 dated 14.06.2012. The CTP office advised
the Trust vide its letter no. 4980/CTP (PB)/SP-463 dated 25.09.2012 to
deposit a sum of RS. 22,49,350.00 as scrutiny fee. The Trust have already
deposited the required fee vide pay order no. 100731 and 100732 dated 18th
February 2013. The revised layout plans for approval are under process in
the office of CTP, Punjab. Therefore, the revised project proposal shall be
submitted as soon as the layout plans are approved by the competent
authority. The project proponent has further requested to consider the case
sympathetically and give him more time for submission of revised project
proposal.
10. The case was considered by the SEAC in its 69th meeting held on
18.04.2013, wherein, the SEAC deliberated upon the matter and decided as
under:
(i) To recommend to SEIAA to send the case to the Govt. of Punjab,
Department of Science, Technology & Environment for simultaneously
initiating credible action against project proponent /responsible
persons /promoter company under the Environment (Protection) Act,
1986 due to start of construction activities of group housing project
without obtaining Environmental Clearance under EIA notification
dated 14.09.2006.
(ii) To accept the request made by the project proponent and to give
three months time to submit the revised project proposal.
11. The case was considered by the SEIAA in its 47th meeting held on
15.05.2013, wherein, the SEIAA noted that the project proponent vide letter
no. GSMCH/11-12/150 dated 23.02.2012 has already informed that the
earlier construction had been made prior to issuance of EIA notification
dated 14.9.2006 and no further construction will be carried out without
obtaining Environmental Clearance under the EIA notification dated
14.09.2006.
After detailed discussions and deliberations, the SEIAA decided as under:
46
i) To ask the project proponent to attend the next meeting of SEIAA
and to bring material evidence in that meeting to substantiate the
written statement submitted by the promoter company to the SEAC to
the effect that no construction work of this project has been carried
after 14.9.2006.
ii) To defer the case to next meeting of SEIAA.
The above said decision of the SEIAA was conveyed to the
project proponent vide letter no. 24313 dated 24.05.2013 for compliance.
12. The project proponent was requested by the SEIAA vide letter no. 24313
dated 24.05.2013 to attend its 48th meeting on 03.06.2013, which was
attended by the following on behalf of the project proponent:
i) Sh. Harnam Singh, President of the promoter company
ii) Sh. J.K. Sharma, Asstt. General Manager of the promoter company
iii) Sh. Arun Kumar, Environmental Consultant of M/s Grass Roots
Research & Creation India Ltd., New Delhi.
Sh. Harnam Singh, President of the promoter company informed that:
a) The Gian Sagar Educational & Charitable Trust started the construction of
buildings before issuance of EIA Notification dated 14.9.2006 by the MoEF.
As soon as the PPCB officials directed the trust for NOC, the Trust applied
for the same and NOC's from pollution angle were issued by PPCB for
setting up of Gian Sagar Dental College & Hospital and Gian Sagar Medical
College & Hospital vide vide letter No.ZO/PTA/2006/NOC/70 dated
20.7.2006 and No.ZO/PTA/2006/NOC/81 dated 18.9.2006, respecitively.
b) The Trust had also applied to Ministry of Environment & Forests for
obtaining environmental clearance under EIA notification and the public
hearing was conducted by the Punjab Pollution Control Board on
24.8.2006. After conduct of the public hearing, the proceedings of the public
hearing were sent by Punjab Pollution Control Board to the Ministry of
Environment & Forests.
c) In the meantime, the SEIAA/SEAC was constituted for the State of Punjab
and accordingly the application was submitted to SEIAA, Punjab on 2.4.2008
for obtaining environmental clearance. The case was heard by the SEAC on
47
9.8.2008 and some observations were made, which were cleared by the
Trust.
d) The case was considered by SEIAA in its meeting held on 19.9.2009 and the
application for environmental clearance was refused by SEIAA vide their
letter dated 7.10.2009 due to the reason of not submitting the layout /
building plans duly approved by the Competent Authority and advised to
apply afresh for environmental clearance after getting the layout plans
approved.
e) After getting the layout plans approved by CTP, Punjab vide letter dated
25.7.2011, the Trust again submitted the project proposal on 2.12.2011 to
SEIAA, which was heard by the SEAC in its meeting held on 30.12.2011 and
the Committee pointed out some obeservations, reply for which was given
and the same was considered by SEAC in its meeting held on 21.07.2012.
In the said meeting, the committee observed that the project proponent has
now revised the project proposal due to which there may be changes in the
data/information in the earlier application submitted for obtaining
environmental clearance. After detailed deliberations in the matter, the
committee directed the trust to submit the revised layout plans alongwith
the changed data/infromation (area from 56.61 to 58.31 acres). The revised
layout plans was again submitted to the Chief Town Planner, Punjab on
14.6.2012 for approval, which are still pending and therefore, the SEAC was
requested to give more time to submit revised project proposal.
f) The Trust has followed the instructions issued by the authorities from time
to time and as such, there is no violation of EIA notification. The case my
be considered sympathetically and allow the trust to submit the revised
project proposal as soon as the revised layout plans are approved by the
Chief Town Planner, Punjab.
The SEIAA noted that the SEAC while noting down the decision of its
69th meeting held on 18.04.2013 mentioned the word 'group housing
project' in the following paragraph, which seems to be typographical error
and the may be read as 'medical institute':
"To recommend to SEIAA to send the case to the Govt. of Punjab,
Department of Science, Technology & Environment for simultaneously
initiating credible action against project proponent /responsible
48
persons /promoter company under the Environment (Protection) Act,
1986 due to start of construction activities of group housing project
without obtaining Environmental Clearance under EIA notification
dated 14.09.2006."
The SEIAA also looked into the provisions of EIA notification dated
27.01.1994 as amended on 07.07.2004 and noted that:
a) The new construction projects such as new townships, industrial
townships, settlement colonies, commercial complexes, hotel
complexes, hospitals and office complexes for 1,000 persons or above
or discharging sewage of 50,000 liters per day or above or with an
investment of Rs. 50 crores or above are required to obtain
environmental clearance under the EIA notification.
b) New construction projects which were undertaken without obtaining
the clearance required under the notification and where construction
work had not come up to the plinth level, shall require clearance
under the notification with effect from the 7th day of July, 2004.
The SEIAA also looked into Circular dated 15.01.2008 of the Ministry
of Environment & Forests, New Delhi in which it has been mentioned that:
(i) Since the EIA notification, 1994 has now been superseded by EIA
notification, 2006, all project activities listed under the EIA notification
dated 14.09.2006 require environmental clearance.
(ii) Only such projects listed under EIA Notification, 2006 shall not require
environmental clearance under the said notification which were not listed
in EIA notification 1994 and for which NOC was issued on or before
September 14, 2006.
(iii) All such projects listed in both EIA Notifications of 1994 and 2006 shall
require prior environmental clearance irrespective of issue of NOC if the
project related activity has not yet commenced at site. The validity of
NOC should not be extended without asking the proponent to seek prior
environmental clearance under the EIA Notification, 2006.
49
After detailed discussions and deliberations, the SEIAA observed that
the project proponent is required to submit following information to ascertain as to
whether the project proponent has violated the provisions of EIA notification dated
14.09.2006 by starting construction activities of the project without obtaining
environmental clearance under the said notification or not.
a) On which date the Trust had submitted application for obtaining
environmental clearance in the office of the Ministry of Environment &
Forests, New Delhi for which the public hearing was conducted by the
Punjab Pollution Control Board on 24.8.2006 alongwith photocopy of the
said application and any communication received from the Ministry of
Environment & Forests/ with regard to said application.
b) The total investment of the project, expected discharge of wastewater and
expected strength of students including staff at the time of commencement
of the project/start of construction activities of the project.
c) The below mentioned proforma duly filled-in and supported with material
evidence to corroborate the data mentioned in the said proforma.
Sr.
No. Activity Date of
start of
activity
Date of completion
of activity
Project area in
acres
Built up area in
sqm
Remarks,
if any
The SEIAA decided to ask the project proponent to submit the reply
of above noted observations, at the earliest and to defer the case till the project
proponent submits the same.
The above noted observations were conveyed to the project
proponent vide letter no. 24156 dated 11.06.2013, however, no reply has been
received, so far.
The case was considered by the SEIAA in its 69th meeting held on
30.08.2014, however, no representative of the Trust attended the meeting.
After deliberations, the SEIAA decided that one last
opportunity be afforded to the project proponent to submit the desired
information as sought vide letter no. 24156 dated 11.06.2013 and a
50
reminder be issued to submit the requisite information within 15 days. The
SEIAA further decided that the case be deferred to the next meeting.
13. Now, the project proponent vide letter no. 132 dated 20.11.2014 has
submitted the reply to the observations of SEIAA and the same is
reproduced as under:
“Gian Sagar Educational & Charitable Trust started construction of
buildings earlier than the EIA notification issued by the MOEF i.e. during the
year 2005-2006. As soon as the PPCB officials directed the Trust to get
NOC/environmental clearance the Trust submitted the application alongwith
the Rapid EIA report on dated 18.7.2006 to Member Secretary PPCB,
Patiala. Accordingly NOC’s from pollution angle were issued by the PPCB for
setting up Gian sagar Dental College & Hospital & Gian Sagar Medical
College & Hospital vide their letters No.ZO/PTA/2006/NOC/70 dated
20.7.2006 and No.ZO/PTA/2006/NOC/81 dated 18.9.2006 respectively and
also directed to conduct public hearing for EIA clearance in the presence of
competent authority. Accordingly the public hearing was conducted on
24.8.2006.
After the public hearings the case for consideration for grant of
environmental clearance to the project proponent was forwarded to the
Secretary to Govt. of India, Ministry of Environment & Forests, New Delhi
vide letter No.CSA/PH-06/G-14/6602 dated 12.09.2006 by the Member
Secretary, PPCB and later on it was known that the State Level
Environmental Impact Assessment Authority will clear the projects.
Accordingly the Trust submitted the case for grant of environmental
clearance to SEIAA on 02.04.2008 and the case was heared by the SEAC on
26.07.2008 (which was constituted in November 2007 and came into
operation during March 2008).
The total investment of the project was Rs.139, 66, 51,417.00. An
STP of 800 kld capacity has been installed and the treated water is being
used for irrigation purposes in the lawns and in the earmarked area for this
purpose. The total strength of students shall be 100 students each of MBBS
& BDS courses.
It is further submitted that we had purchased land for our project
initially in the year 2004 and process for land purchase was completed in the
51
year 2007 and no land was purchased after 2007. Construction activities of
the project were started during the year 2005. No doubt our project was
covered under the amendment made in 2004 in EIA notification of 1994 as
well as the new EIA notification dated 14.9.2006. It was not clear whether
the projects which had started their construction activities prior to their
projects covered under EIA notification of 2006 and also whether they could
continue further construction activities simultaneously with the process of
obtaining environmental clearance. As such we applied for the environment
clearance and continued the construction activities after obtaining NOC from
the PPCB. It was only on 15.1.2008 when the MOEF vide their circular No.
J[11013/41/2006-IA-II(I)(Part) clarified that all such projects listed in both
EIA Notifications, 1994 and 2006, shall require prior environment clearance
irrespective of issue of NOC if the project related activity has not yet
commenced at site. The validity of NOC should not be extended without
asking the proponent to seek prior environment clearance under the EIA
Notification, 2006.
The Ministry further clarified in the said circular that:
“In view of the above, it is advised to the State Pollution Control
Boards not to grant/extend/revalidate NOC/CTE without advising the
proponent to seek environment clearance under EIA Notification, 2006 for
the projects which were listed in EIA Notification, 1994 and are now also
listed under EIA Notification, 2006 even if they have acquired the land
before January 1994. All such projects, which were issued NOC/CTE before
September 2006 and listed in both the Notifications, but have not
commenced project activities at the site shall not start project activity now
without obtaining prior environment clearance under EIA Notification, 2006
even if the land was acquired before January 1994.”
Even in the said circular, the Ministry had not stressed upon the
stopping of ongoing construction activities and has directed only in case of
projects where no construction activity had started. However, we received
directions from the SEIAA vide letter No.SEAC/948 dated 9th January 2012
as under:
“The photograph submitted by the project proponent show that the
construction of the Institute has already been completed, as such, intimate
52
the reasons as to why the construction has been made in violation of
provision of EIA notification dated 14.9.2006 and submit an undertaking to
the effect that no further construction will be done without obtaining
environment clearance required under the said notification.”
In compliance to the directions, we immediately stopped the
construction activities and also submitted a resolution passed by the Board
of Trustees that:
“The Trust has submitted an application to the State Environment
Impact Assessment authority for grant of environmental clearance for Gian
Sagar Hospital Complex situated at Ram Nagar (Rajpura) Distt. Patiala.
Resolved that no further construction will be done in this complex without
obtaining environmental clearance from the competent authority and a copy
of this resolution be submitted to State Expert Appraisal Committee,
Punjab”.
No construction activities have been undertaken since then.”
Further, the project proponent has submitted the following documents:
i) Copy of the letter vide which the Trust submitted the application alongwith
the Rapid EIA report on 18.07.2006 to MS, PPCB, Patiala.
ii) Copy of the NOC’s granted by the Punjab Pollution Control Board dated
21.07.2006 and 18.09.2006.
iii) Copy of the letter vide which the MS, Punjab Pollution Control Board has
forwarded the proceedings of the public hearing to Secretary to Govt. of
India, MoEF, New Delhi.
iv) Copy of the proceedings of the public hearing conducted on 24.08.2006 for
the devolpment of Medical Institute named as “Gian Sagar Medical College
and Hospital” at Vill. Ramnagar, Near Banur, Tehsil Rajpura, Distt. Patiala.
v) CA certificate dated 19.11.2014 wherein, it has been mentioned that the
buildings have an undepreciated value of Rs. 139,66,51,417/- as on
31.03.2014.
vi) Details of Construction of Buildings alongwith the details of the built up area
and date of start & completion.
vii) Date wise details of land acquisition starting from 33 bigha dated
06.10.2004 to 10 K-13-1/3M dated 30.04.2007.
53
The case was considered by the SEIAA in its 74th meeting held on
24.12.2014, but no one from the Trust the attended the meeting. However, a SMS
requesting another opportunity of hearing has been received from the Trust.
The SEIAA accepted the request of the Trust and decided to defer the
case to the next meeting.
The decision of the SEIAA was conveyed to the project proponent
vide letter No. 91 dated 07.01.2015.
The case was considered by the SEIAA in its 75th meeting held on
09.01.2015, which was attended by the following on behalf of project proponent:
(i) Sh. Shailender Choudhary, CEO of the Trust.
(ii) Sh. J.K. Sharma, General Manager (Admn) of the Trust.
(iii) Sh. Shashank Srivastava of M/s Grassroots Research & Creation India (P) Ltd, Environmental Consultant of the Trust.
Sh. Shailender Choudhary, CEO of the Trust stated that the Trust
needs some time to submit the complete clarification of the observations of the
SEIAA and requested for one month's time.
After deliberations, the SEIAA accepted the request of the Trust and
granted one months' time to submit the reply. It was further decided that Sh.
Gulshan Kumar, Asstt. Environmental Engineer, shall visit the project site and
submit a report regarding construction status at site.
No reply has been received from the Trust. Sh. Gulshan Kumar, Asstt.
Environmental Engineer, submitted his visit report, the contents of the same are as
under:
Visit Report
Name of project: M/s Gian Sagar Education & Charitable Trust Vill Ram Nagar Banur, Distt.-Patiala.
Date of Visit : 26.02.2015
Person Contacted : Sh. J.K. Sharma GM of the Promoter Company.
Observations:
1. No construction work was going on during the visit.
Representative of promoter company informed that the
construction work has been stopped since 11.06.2012.
54
2. Project proponent has constructed Blocks A, B, C, D1, D2, E,
F, G1, G2, G3, J1, J2, H1, H2, K, L, M, O, P, Q, R.
3. Out of above building plans for Blocks J2, H1, & H2 have not
been approved by the competent authority.
4. Structural work of Auditorium (Block-R) has already been
completed, finishing is yet to be completed.
Construction work for Block Q2 (NRI students Hostel) is yet to be
started.
The case was considered by the SEIAA in its 80th meeting held on
28.02.2015, which was attended by Sh. Sucha Singh representative of project
proponent informed that the Sh. J.K. Sharma GM of the Promoter Company, who is
conversant with the facts of the case is not available and he requested for
deferment of the case.
The SEIAA accepted the request of the promoter company and
decided to defer the case to the next meeting.
The decision of the SEIAA has been conveyed to the project
proponent vide letter 1462 dated 05.03.2015.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following on behalf of project proponent:
(i) Sh. J.K. Sharma, General Manager (Admn) of the Institute.
(ii) Sh. Kamaljit Singh, Deputy Director of the Institute
(iii) Sh. Sandeep Garg of M/s Eco Labs, Mohali, Environmental Consultant of the Institute
The SEIAA observed that the matter is required to be deliberated in
detail and more time is required. Therefore, the SEIAA due to paucity of time
decided to defer the case.
Item No.82.07: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for construction of a Housing Project namely “Ansal Florence Estate” at G.T. Road, Amritsar, by M/s Ansal Buildwell Infrabuild (P) Ltd.
The SEIAA observed that:
55
1. M/s Ansal Buildwell Infrabuild (P) Ltd., 118, UFF, Prakashdeep Building, 7,
Tolstoy Marg, New Delhi vide letter dated 03.07.2013 has applied for
obtaining the environmental clearance as required under the EIA notification
dated 14.09.2006 for construction of a Housing Project namely “Ansal
Florence Estate” at G.T. Road, Amritsar. The project is covered under
category 8 (b) of the Schedule appended to the said notification.
2. The project proponent was requested by SEAC vide letter no. 2262 dated
22.07.2014 to attend its 96th meeting on 23.07.2014, which was attended by
the following on behalf of the project proponent:
i) Sh. Vipin Vashishta, Addl. General Manager of the promoter company.
ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
From the perusal of the application and presentation made by
Sh. Deepak Gupta, Environmental Consultant of the promoter company, the
salient features of the project are as under:
The total project area is 16.1089 acres having total built up area of
161645.86 sqm. The layout plan has been approved vide no 48/6
dated 25.09.2013.
Total water requirement for the project will be 600 KLD, out of which
446 KLD will be met from own tubewell and remaining 154 KLD will be
met from treated wastewater.
The total wastewater generation from the project will be 480 KLD,
which will be treated in a STP to be installed within the project
premises. The project proponent has proposed to use 154 KLD of
treated wastewater for flushing purpose, 114 KLD for irrigation of
green area and remaining 212 KLD will be discharged to MC sewer in
summer season. In winter season, 154 KLD of treated wastewater
will be used for flushing purpose, 31 KLD will be used for irrigation of
green area and remaining 295 KLD will be discharged to MC sewer. In
rainy season, 154 KLD of treated wastewater will be used for flushing
purpose and remaining 326 KLD will be discharged to MC sewer.
Application for obtaining permission for abstracting groundwater has
56
been submitted to the CGWB, Chandigarh and CGWB has raised
certain queries, which are being clarified.
Green area will be developed in an area measuring 20801 sqm. The
treated wastewater storage tank of adequate capacity will also be
constructed to hold treated wastewater.
The total quantity of solid waste to be generated from the proposed
project has been estimated as 1786 kg/day, which will be segregated
into bio-degradable and non-biodegradable waste as per the MSW
Rules, 2000. The bio-degradable waste would be sent to approved
site. The non-biodegradable and recyclable waste would be sold to the
recyclers. Municipal Corporation, Amritsar has issued letter no. 304
dated 26.06.2014 in which it has been mentioned that the solid waste
to be generated from this project will be sent to the 'Municipal Solid
Waste Management Facility' at Bagwantwala with condition that the
company will deposit the requisite charges with Municipal Corporation.
The e-waste will be handled and managed as per the E-waste
(Management & Handling) Rules, 2011 and earmarked the site for e-
waste storage room on the approved layout site plan.
The used oil from the D.G. sets will be sold out to the registered
recyclers as per the provisions of the Hazardous Waste (Management,
Handling & Transboundary Movement), Rules, 2008.
The total load of electricity required for proposed project will be 4.8
MW (4800 KW) which will be supplied by PSPCL. The project
proponent has proposed to install DG sets, for backup power supply.
The ambient air monitoring has been got done from Chandigarh
Pollution Testing Laboratory and the analysis results indicate that the
concentration of various pollutants such as PM2.5, PM10, SO2, NO2 and
CO have been measured. Also, ambient noise monitoring has been got
done from the said firm and the analysis results indicate that the noise
levels during day and night times, have been measured in the range
of 49.8 dB(A) leq and 35.7 dB(A) leq, respectively, against the
57
prescribed standards of 55 and 45 dB(A) leq. The groundwater of the
area is potable in nature as per analysis report of groundwater.
Airports Authority of India has issued NOC vide no. 2056 dated
18.09.2012 and allowed the construction upto the height of 68.21m.
During construction phase, Rs.18.50 lacs will be incurred for
implementation of EMP and Rs.11.50 lacs/annum will be incurred on
account of recurring charges. During operation phase, Rs.105 lacs will
be incurred for implementation of EMP and Rs. 14.50 lacs will be
incurred on account of recurring charges. Association of the residents
or M.C. whosoever takes over the project, will be responsible for
implementation of EMP.
Rs. 12.00 lacs will be utilized for following activities under Corporate
Social Responsibility and Director, of company will be responsible for
implementation of CSR:
i) The management will give preference in the job to nearby area people (Village sultanwind and jandiala Guru).
ii) Blood donation camps and other health related camps will be organized in the 5 Km area of the project
iii) Widening of road in the vicinity of the project.
iv) Camps will be organized for awareness of cancer and other diseases
v) Saplings will be distributed in the area.
vi) Training to the unemployed youths in the field of computer repairing.
vii) The implementation of the CSR will be responsibility of director of the company
viii) A fund of Rs. 12 Lac has been earmarked by the management for the activities stated as above and other related activities
o The traffic circulation plan has been prepared and the same has been
submitted alongwith application.
o Disaster/Risk Assessment & Management Plan has been prepared and the
same has been submitted alongwith application.
o No construction activity has been started at site.
58
During the meeting, Environmental Consultant of the promoter
company submitted a copy of sanction letter dated 26.11.2013 vide which layout
plan has been approved by M.C. Amritsar.
To a query regarding storm water disposal, project proponent
submitted that the storm water for areas other than roof top will be harvested for
90 percentile of rainfall event at site and will be utilized for other purposes such as
fire fighting, irrigating green areas. The project proponent earmarked the site for
storm water harvesting tank on the approved layout site plan.
The SEAC observed that though the project proponent has
satisfactorily clarified all the technical observations, however, has not submitted
recommendation letter from CGWB to CGWA for abstraction of groundwater.
The project proponent assured the SEAC that the above noted
document will be submitted shortly and requested for recommending their case to
SEIAA for grant of environmental clearance.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal and decided that
as and when the project proponent submits recommendation letter from CGWB to
CGWA for abstraction of groundwater and the same is approved by the Chairman
SEAC on the case file of the project, the case be forwarded to the SEIAA with the
recommendation to grant environmental clearance to the project proponent for
construction of a Housing Project namely “Ansal Florence Estate” in an area of
16.1089 acres having total built up area of 161645.86 sqm at G.T. Road, Amritsar,
subject to certain conditions as mentioned in the proceedings of the said meeting
in addition to the proposed measures.
The decision of the SEAC was conveyed to the project proponent vide
letter No. 2386 dated 05.08.2014.
Thereafter, the project proponent vide letter dated 27.08.2014
submitted a copy of letter No. 2217 dated 27.08.2014 vide which CGWB has
forwarded the proposal of the project proponent for abstraction of groundwater @
446 KLD.
The above noted reply submitted by the project proponent has been
considered by the Chairman, SEAC and as per the decision taken by the SEAC in its
59
96th meeting, approval was accorded for recommending the case to SEIAA for
grant of environmental clearance.
The case was considered by the SEIAA in its 69th meeting held on
30.08.2014, which was attended by the following on behalf of the project
proponent:
(i) Sh. Harmanjit Singh Malhotra, Addl. General Manager of the promoter company
(ii) Sh. Ritesh Jain, Senior Manager of the promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company
Sh. Deepak Gupta Environmental Consultant of the promoter
company presented the salient features of the project before the Authority and
requested for grant of environmental clearance.
The SEIAA observed that the total built up area of the proposed
project is 161645.86 sqm and per notification No. S.O. 562 (E) dated 26.02.2014
of the Ministry of Environment & Forests, New Delhi, the original EIA notification
No. S.O. 1533 (E) dated 14.09.2006 has been amended as under:
In the said notification, in paragraph 7, in sub para II, in
item (i), in the first proviso, for item (i), the following item
shall be substituted, namely: -
"(i) all projects or activities listed under category, 'B' against
item 8 (a) of the Schedule".
The SEIAA further observed that as per the above mentioned
amendment, now all the projects covered under category 8 (b) of the Schedule
appended with the EIA notification dated 14.09.2006, are required to be appraised
on the basis of EIA study report instead of Form-1, 1A and conceptual plan only, as
was being done earlier.
After detailed deliberations, the SEIAA decided to remand the case to
SEAC for re-examining the same in light of the said notification.
The case was considered by the SEAC in its 101st meeting held on
18.09.2014, The SEAC observed that as per the amendment dated 26.02.2014
60
issued by the MoEF, now all the projects covered under category 8 (b) of the
Schedule appended with the EIA notification dated 14.09.2006, are required to be
appraised on the basis of EIA study report instead of Form-1, 1A and conceptual
plan only as was being done earlier. The meeting was attended by the following
on behalf of project proponent:
(i) Sh. Harman Singh representative of the promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company
After detailed deliberations in the matter, it was decided to categorize
this project as category B-1 and to finalize and issue the following "Terms of
Reference" to the project proponent for preparation of the draft Rapid EIA report:
A. Construction stage
1. The project falls under category B-1 under item 8(b) Township and Area Development projects and requires an Environmental Impact Assessment Study for the entire site area.
2. Examine and submit the details of the environmental impacts at the stage of land acquisition including aspects such as displacement of families, acquiring of agricultural/forest land, acquiring of ecologically important lands and
water bodies.
3. Examine and submit the details of the environmental impacts due to change of land use and land cover including aspects such as hydrological
characteristics, imperviousness of land and drainage pattern being altered.
4. Examine and submit the details of the environmental impacts at the stage of construction of boundaries & fencing including its impact on the pattern of natural drainage and flooding pattern and barriers being constructed for restricting wildlife movement into project area.
5. Examine and submit the details of the environmental impacts due to leveling and landscaping including aspects such as excavation & filling of soil, clearing of vegetation, change of topography, development of plantation, green belt, lawns & parks and development of impervious areas.
6. Examine and submit the details of the environmental impacts due to excavation, transportation and filling of earth including aspects such as
excavation, filling, sourcing, transportation and disposal of soil.
7. Examine and submit the details of the construction material to be used at the construction stage including aspects such as quarries and transportation, stone crushing and screening, mining & transportation of sand, soil
excavation, transportation and filling.
61
8. Examine and submit the impacts being caused due to transportation of construction materials and men such as increase in traffic and load on public transportation facility, destruction and damage of transportation infrastructure, increase of risk due to road accident, pollution caused due to
dust and tail pipe emissions and consumption of fuel by transport vehicles.
9. Examine and submit the details of the temporary housing and amenities to be created and used by the work force including aspects such as water supply, electrical energy and fuel supply.
10. Examine and submit the details of the environmental impacts at the stage of creation of roads, transportation facility and other physical infrastructure including aspects such as use of construction materials, excavation and /or filling of soil, generation of construction waste, creation of impervious
surfaces, noise & suspended dust pollution and accidental risk.
11. Examine and submit the details of the noise pollution, air pollution, consumption of fuel and generation of scrap being caused due to operation
and maintenance of construction machinery and equipment.
12. Examine and submit the details of the source and supply of water for construction activity.
13. Examine and submit the details of the source and quantity of power for
construction activity.
14. Examine and submit the details of the fuel consumption, noise pollution, emissions of the exhaust gas, engine & coolant oil and batteries being discarded due to captive and emergency power generation.
15. Examine and submit the details of the handling of wastewater during construction including the domestic wastewater being generated from
amenities.
16. Examine and submit the details of the environmental impacts at the stage of development of residential buildings, commercial, institutional and industrial infrastructure including aspects such as construction materials to be used, earth work (excavation and/or soil filling), generation of construction waste, lighting, HVAC units, waste generation from packaging, residual paints and chemicals and their cans, Generation of wooden, glass, metal and other scrap materials, plumbing and sanitary waste generation, creation of impervious surfaces, noise pollution, suspended dust pollution and risk of
accidents.
17. Examine and submit the details of the environmental impacts due to the laying of the water supply system including aspects such as use of piping, fittings ad pumps, water pumping stations, earth work and water treatment
plant.
18. Examine and submit the details of the environmental impacts due to the laying of the sewerage and sewage treatment and disposal system including aspects such as use of construction material, piping, fittings ad pumps, earth work, laying of sewers & manholes, sewage pumping stations and swage
treatment plant.
62
19. Examine and submit the details of the environmental impacts due to the laying of the storm water drainage system including aspects such as use of construction material, piping, fittings and pumps, earth work, storm drains,
storm water inlets and catch basins and storm water outfalls.
20. Examine and submit the details of the environmental impacts due to the electrical power system and street lighting to be provided including aspects such as construction materials to be used, distribution lines, cables, control panels, transformers and meters.
B. Operation stage
1. Examine and submit the details of the environmental impacts due to the residential, commercial, institutional, industrial, recreational, social, cultural
& religious activities to be carried out.
2. Examine and submit the details of the environmental impacts due to the facilities to be provided such as water supply, electrical power supply, fuel
supply & consumption including LPG, transportation and communication.
3. Examine and submit the details of the environmental impacts due to the coming up of the activities such as urban agriculture and animal husbandry.
4. Examine and submit the details of the environmental impacts due to the sewerage & sewage treatment and its disposal systems and storm water &
its drainage system.
5. Examine and submit the details of the environmental impacts caused due to the generation of captive power & emergency power.
6. Submit the details of the management & handling of municipal solid waste, e-waste, hazardous waste, scrap, estate management, construction and
demolition waste management.
7. Submit the details of the socio economic impact due to the employment to
be generated from the household activities.
C. General
1. Other details as indicated in Appendix III of EIA Notification 2006 and the manual titled as "EIA guidance Manual-Building, Construction, Township and area Development projects" published by the Ministry of Environment & Forests, New Delhi, should also be attended.
2. Environmental aspects identified under some of the project activities may not be comprehensive and some of the significant aspects under some of the activities of the project in question might not have been identified. All such environmental aspects may be added to the list.
3. Some of the activities with their associated environmental aspects of the project in question might be of significant magnitude and not included in the list project activities. All such activities may be added to the list of project activities.
63
4. The project proponent may add additional project activities and environmental aspects, if any, fill the impact matrix (copy attached) and carryout significance analysis for identifying the significant environmental aspects. Scale, sensitivity and duration of impacts; type, size and frequency of environmental aspects; applicable legal requirements; and concerns of interested parties and local public may be used as the basis for the significance analysis of the environmental aspects.
5. In the EIA study each of the environmental aspects listed in the TOR should be quantified, their positive and negative impacts on different areas of impacts should be identified and assessed and the results of such assessment should be reported in the EIA report.
6. In the Environment Management Plan, management of each of the significant environmental aspects (with identified and assessed significant environmental impacts) for mitigating the impacts should be objectively stated.
7. Environment Management Plan should include technical and institutional aspects for pre-treatment by constituent units.
8. Environmental Management Plan should be accompanied with Environmental Monitoring Plan and environmental cost and benefit assessment.
9. Examine separately the details for construction and operation phases both for Environmental Management Plan and Environmental Monitoring Plan.
10. Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.
11. Does the Environment policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions? If so, it may be detailed in the EIA.
12. What is the hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.
13. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the Company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA report.
14. Delineate the concrete proposal regarding activities to be undertaken under Corporate Social Responsibility programme, which should be long lasting in nature and should be as per the needs of a particular Village/area/ local habitats/ stakeholders to be adopted by the promoter company, which can be done by involving a person having knowledge and experience of socio-economic activities.
The aforesaid 'Terms of Reference' will be valid for a period of two
years from its issuance. A detailed draft EIA/EMP report should be prepared as per
the above noted TOR.
The SEAC further decided to request the Punjab Pollution Control
64
Board to verify the construction status of the project at site and send the detailed
status report (with quantification) to SEAC within 15 days.
Before, issuance of the ToRs, the Punjab Pollution Control Board was
requested to verify the construction status of the project at site and send the
detailed status report (with quantification) to SEAC within 15 days.
Now, the Environmental Engineer, Punjab Pollution Control Board,
Regional Office, Amritsar through e-mail has informed that the residential colony
namely M/s Florence Estate, was visited by Environmental Engineer, Regional
Office along with AEE on 27/11/2014 and observed that the work regarding laying
down of sewerage network has been completed, the office building of project has
also been completed, at some places premix road has been laid down while at
other places stabilized roads have been laid down. The Photographs showing above
said development work in the residential colony as e-mailed by Regional Office,
Amritsar are as under: [
65
[
[[
In view of the changed status as reported by Regional Office, the
matter is placed before the SEAC for reconsideration.
The case was considered by the SEAC in its 104th meeting held on
05.12.2014, which was attended by the following on behalf of the project
proponent:
i) Sh. Vipin Vashista, Addl. General Manager of the promoter company.
ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental
Consultant of the promoter company contended that no construction has been
carried out at site and only a temporary office building has been established at site
66
as the company has got approval of the same from the M.C. Amritsar vide letter
no. 1160 dated 17.10.2011.
The SEAC noted that as per report & photographs sent by Punjab
Pollution Control Board, Regional Office, Amritsar the work regarding laying of
sewerage network has been completed, the office building of project has also been
completed, at some places premix road has been laid while at other places
stabilized roads have been laid. The SEAC observed that from the photographs sent
by the Punjab Pollution Control Board and shown to the project proponent during
the meeting, the structure constructed at site is not a temporary building.
Moreover, the other infrastructure developments such as laying of sewer,
construction of roads, lighting etc. have also been undertaken without obtaining
the environmental clearance.
The SEAC further observed that as per Office Memorandum No. J-
11013/41/2006-IA.II(I) dated 19.08.2010, no activity relating to any project
covered under the EIA notification dated 14.09.2006 including civil construction can
be undertaken at site without obtaining prior environmental clearance except
fencing of the site to protect it from getting encroached and construction of
temporary shed(s) for the guard(s).
After detailed deliberations, the SEAC decided that:
(i) ToRs as finalized in 101st meeting of SEAC held on 18.09.2014 and
are under issue, may not be issued.
(ii) To forward the case to SEIAA with the recommendation to ask the
project proponent to submit a formal resolution passed by the Board
of Directors of the Company or the Managing Committee / CEO of the
Society, Trust, partnership / individually owned concern, within 60
days, mentioning that violations will not be repeated in future and in
the meantime, the project may be delisted. In the eventuality of not
having any response from the project proponent within the prescribed
limit of 60 days, the project file may be closed.
(ii) To recommend to SEIAA:
For initiating credible action against the project proponent /
responsible persons / promoter company under the
67
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
For issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance is obtained under EIA notification
dated 14.09.2006.
The case was considered by the SEIAA in its 74th meeting held on
24.12.2014, which was attended by the following on behalf of the project
proponent:
(i) Sh. Vipin Vashishta, Addl. General Manager of the promoter company.
(ii) Sh. Rajeev Kumar, Manager of the promoter company.
(iii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
Sh. Vipin Vashishta, Addl. General Manager of the promoter company
contended that temporary office and pavements etc. as reported is not part of the
original project proposal for which the environmental clearance application has
been filed and will be demolished once the project related activity is started at site.
He requested to get the site re-visited to check the construction status of the
project.
After detailed discussions, the SEIAA decided to remand the case to
SEAC to review the matter in light of contentions made by the project proponent
and send its recommendations accordingly.
The case was considered by the SEAC in its 106th meeting held on
17.01.2015 and 107th meeting held on 21.01.2015 and was deferred due to paucity
of time in both the meetings.
The case was considered by the SEAC in its 108th meeting held on
06.02.2015, which was attended by the following on behalf of the project
proponent:
i) Sh. Vipin Vashista, Additional General Manager of the promoter company.
68
ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
The project proponent submitted that they have constructed a
temporary site office structure at site which will be dismantled at the time of
completion of project. This structure is not a part of their project. The project
proponent requested the SEAC to revisit the site with advance intimation to them,
before taking any action in this matter.
After detailed deliberations, the SEAC decided to get the site revisited
by Sh. M S Bhatti, member SEAC along with Environmental Engineer, Regional
Office, Punjab Pollution Control Board, Amritsar and under advance intimation to
project proponent and submit report. It was further decided to defer the case till
the report is received.
As decided, Sh. M S Bhatti, Member (SEAC) and Environmental
Engineer, Regional Office, Punjab Pollution Control Board, Amritsar were requested
vide letter No. 1280-81 dated 18.02.2015 to visit the project site and submit report.
Sh. M S Bhatti, member SEAC and Environmental Engineer, Regional
Office, Punjab Pollution Control Board, Amritsar have visited the project site and
the report is being prepared and the same will be placed before the SEAC during
the meeting.
The case was considered by the SEAC in its 110th meeting held on
18.03.2015, which was attended by Sh. O.P. Wahi, Addl. Vice President (S) of the
promoter company and he stated that the construction carried out at site is not
part of the project proposal and the said construction is purely temporary and will
be demolished before starting of project related activities. He requested to issue
the ToRs for preparation of EIA study.
The report submitted by Sh. M S Bhatti, Member SEAC was placed
before the SEAC during the meeting. As per the said report, the site was visited by
Sh. M S Bhatti, Member SEAC on 07.03.2015. Shri Vipin Vashista, Additional
General Manager, Civil and Shri Harmanjit Singh Malhotra, Additional General
Manager, Liason. Sh. Kamaljit Singh, AEE, Regional Office, PPCB, Amritsar
accompanied the visiting Member of the SEAC. It has been mentioned in the report
that the project proponent has constructed a site office showing elegantly
69
designed entry gate, demonstration housing unit, working office with provision for
air conditioning, water supply.
In light of the visit report, the SEAC observed that the case is
required to be dealt as per the procedure mentioned in the Office Memorandum
dated 12.12.2012 of the Ministry of Environment & Forests as amended on
27.06.2013 since the promoter company has violated the provisions of EIA
notification dated 14.09.2006 by starting construction of the project without
obtaining environmental clearance under the said notification.
After detailed deliberations, the SEAC decided as under:
(i) To forward the case to SEIAA with the recommendation to ask the
project proponent to submit a formal resolution passed by the Board
of Directors of the Company or the Managing Committee / CEO of the
Society, Trust, partnership / individually owned concern, within 60
days, mentioning that violations will not be repeated in future and in
the meantime, the project may be delisted. In the eventuality of not
having any response from the project proponent within the prescribed
limit of 60 days, the project file may be closed.
(ii) To recommend to SEIAA:
For initiating credible action against the project proponent /
responsible persons / promoter company under the
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
For issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance under EIA notification dated
14.09.2006 is obtained.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following on behalf of the project
proponent:
i) Sh. O.P. Wahi, Addl. Vice President (S) of the promoter company.
70
ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental
Consultant of the promoter company contended that no construction has been
carried out at site and only a temporary office building has been established at site
as the company has got approval of the same from the M.C. Amritsar vide letter
no. 1160 dated 17.10.2011, and submitted a copy of the same, which was taken
on record by the SEIAA.
The SEIAA observed that:
i. The report sent by SEAC is incomplete as no comments have been
given on the earlier report sent by the Punjab Pollution Control
Board wherein other construction activities such as laying of
sewage network, roads, etc. were also reported.
ii. The permission letter issued by M.C. Amritsar vide letter no. 1160
dated 17.10.2011 for construction of a temporary office building
also needs to be looked into and commented upon.
After detailed deliberations, the SEIAA decided to remand the case
to SEAC.
Item no.82.08: Application for obtaining environmental clearance for developing a 'Model Industrial Park' in the revenue estate of Village Vallah, District Amritsar by M/s Penguin Buildtech Pvt. Ltd. and Veer Colonizers & Builders Pvt. Ltd.
The SEIAA observed that:
1. M/s Penguin Buildtech Pvt. Ltd. and Veer Colonizers & Builders Pvt. Ltd has
applied on 18.02.2013 for obtaining environmental clearance as required
under the EIA Notification dated 14.09.2006 for developing a 'Model
Industrial Park' in the revenue estate of Village Vallah, District Amritsar. The
project is covered under category 7 (c) of the Schedule appended to the
said Notification.
2. The case was considered by the SEAC in its 68th meeting on 18.03.2013, which was attended by the following on behalf of the project proponent:
71
(i) Lt. Col. N. S. Narang, Region Head. (ii) Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant
of the project proponent.
The SEAC allowed Sh. Yashpal Jain of M/s Ace Engineers &
Consultants, Patiala to make presentation of the case before the Committee
in compliance to orders dated 09.10.2012 passed by the Hon'ble Punjab &
Haryana High Court in 19598 of 2012 titled as M/s Ace Engineers &
Consultants V/s Union of India & another and in light of contents of Office
Memorandum dated 04.08.2009 of the Ministry of Environment & Forests.
Accordingly, Sh. Yashpal Jain of M/s Ace Engineers & Consultants, Patiala
presented the project proposal before the Committee. He informed that the
site of the project is located in the industrial zone of the notified Master Plan
of Amritsar and he submitted a copy of the Notification dated 10.12.2012
vide which the Master Plan of Amritsar has been notified by the Department
of Town and Country Planning, Punjab. He contended to waive off the public
hearing due to the fact that the site of the project is located in the industrial
zone of the Master Plan and the Master Plan of Amritsar was notified after
inviting objections from the general public. During presentation, the
representative of the promoter company submitted the following documents,
which were taken on record by the Committee:
1. A copy of letter bearing no. 13920 dated 08.03.2013 of Divisional
Forest Officer, Amritsar in which it has been mentioned that there is
no protected area notified under the Wildlife(Protection) Act, 1972
falls within a radius of 10 Km from the project site.
2. 500 meter radius map of the area from periphery of project site
clearly indicating the various industries and structures etc.
The SEAC brought into the notice of representative of the
promoter company that as per sub para regarding 'Public Consultation' of
Para 7 of the EIA Notification dated 14.09.2006, no public consultation is
required for the projects/activities located within 'Industrial Estates or Parks'
approved by the concerned authorities. The SEAC further informed to the
representative of the project promoter that the site of the project has not
been declared as Industrial Estate or Park by the Department of Industries
72
and Commerce, Punjab, therefore, the request of the promoter company for
waiving off public hearing can not be considered.
The Committee noted that the case pertains to category 7(c)
of the Schedule appended to the EIA Notification dated 14.9.2006 and such
type of projects are to be appraised as category B-1 as per the said
Notification. Thus, the project proponent is required to be issued 'Terms of
Reference' for preparation of draft Rapid EIA study report.
After detailed deliberations in the matter, it was decided to
categorize this project as category B-1 and to finalize "Terms of Reference"
and to convey the same to the project proponent for preparation of detailed
draft Rapid EIA report. The SEAC also decided not to waive off the public
hearing in light of the facts stated above.
The 'Terms of Reference' (TOR), were conveyed to the project
proponent vide letter No. 47707 dated 08.11.2012 for preparation of rapid
EIA report and EMP. Also, the project proponent was asked to submit the
documents in respect of following:
(i) There is no Notified Eco-sensitive area u/s 3 of the Environment (Protection) Act, 1986 within a radius of 10 km from the periphery of the project site.
(ii) There is no Inter-State and International boundary within a radius of 10 km from the periphery of the project site.
3. The case was considered by the SEAC in its 93rd meeting held on 03/02.2014.
Following were present on the behalf of the project proponent in the meeting:
Lt. Col. N. S. Narang, Region Head Sh. Yash Pal Jain of M/s ACE Consultants, Environmental
Consultant of the project proponent.
Sh. Yash Pal Jain, presented the salient features of the EIA study
report before the SEAC as under:
The study for getting the primary data for preparation of EIA report
was carrying out during the period from 01/04/2013 to 30/06/2013.
73
The total project area is 146.428 acres, which will be developed as
under:
40 % of the total industrial plots would have green category of
industries/industries exempted from taking NOC (Consent to
Establish) from Punjab Pollution Control Board. These industries
would come up in the plot size varying from 200 sq. yards to 1000 sq.
yards. These industries would generate only domestic effluent.
20 % of the total plots would be having mechanical
industry/industries generating inorganic wastewater such as wire
drawing units, electroplating units, zinc sulphate/ferrous sulphate
plants, electrical appliances units, automobile workshops etc.
Maximum wastewater generation from such type of units would be 5
KL/unit/day.
The remaining 40 % of the industrial plots would house industries
generating organic wastewaters such as formulation of drugs,
formulation of pesticides/ insecticides/herbicides, milk chilling centers,
small milk plants, mineral water/carbonated soda bottling plants,
packaged food industries, board mills etc. Maximum wastewater
generation from such type of units would be 20 KL/unit/day.
Permission for change of land use for an area measuring 146.428
acres has been obtained from the Department of Town and Country
Planning, Punjab vide memo no. 6749/CTP(Pb)/SP-432(A) dated
13.12.2012.
The industrial park would not house any industrial unit which requires
Environmental Clearance under category ‘A’ as per EIA Notification,
2006 and its subsequent amendments. However, category-B
industries of the 'Schedule' appended to EIA Notification can be
established in the park.
The industrial park would not house any industrial unit covered under
MAH (Major Accidental Hazards) category of industries.
The industrial park would not house any highly polluting industries
namely manufacturing of fertilizers (Urea/DAP etc.), Cement Plants,
Pulp and Paper Industries, Dyeing and Processing Units, Bulk
Pesticides Units, Bulk Drugs Units, Sugar Mills, Distilleries, Caustic
74
Soda Units, Copper Smelters, Integrated Iron and Steel Industries,
Asbestos and Asbestos based industries, Chorates, Perchlorates and
Peroxide Units, Chlorine, Fluorine, Bromine, Iodine and their
compounds, Coke Making, Coal Liquefaction, Coal Tar Distillation or
Fuel Gas making units, Explosives including detonators, fuses etc.,
dry coal processing/mineral processing industries like ore sintering,
palletization.
The water supply will be taken from main canal branch and each
industry will be supplied metered water supply and permission has
been obtained from the concerned department vide no. 4955 dated
08/07/2013 for getting the canal based water supply.
Proper meters will be installed at the source of water supply and at
the outlet of each industry from where the trade effluent and the
domestic effluent will be discharged for further sending the same to
the Common facility developed for the entire project.
The green belt will be developed in an area of 7.2 hectares, out of
which 2.7 hectares will be under the parks, 4.4 hectares along the
road side and 0.5 hectares within the public building.
Common Infrastructural facility will have the following:
Parking area at the entrance of the project for the visitors.
Toilets within the projects.
Sitting area for the drivers etc. in the parks of the project
Sewer lines for organic as well as domestic effluent.
MSW management and handling facility.
HW collection and disposal facility.
E-waste collection facility.
The project proponent will lay two parallel lines for carrying the waste
streams inorganic and organic in nature. The domestic effluent will be
carried out by the pipeline through which trade effluent organic in
nature will be sent for further treating in the common facilities.
The project proponent will install separate common Effluent
Treatment Plants to treat trade effluent organic in nature and
domestic effluent combinedly and inorganic wastewaters.
75
The industrial plots would not house any bathrooms for the bathing
operations within the industrial premises. Only urinals and toilets
would be permitted in the industrial plots. Domestic water supply @
30 litres/person/day would be provided to the industrial plots as given
in the table:
Sr. No
Size of the Plot Max. number of
workers per day
Domestic water supply per plot
(litres/day)
1. 200 to 300 sq. yards plots 15 450
2. 300 to 600 sq. yards plots 25 750
3. 600 to 1000 sq. yards plots 50 1500
4. 1000 to 1500 sq. yards plots
75 2250
5. 1500 to 2000 sq. yards plots
100 3000
6. 2000 to 3000 sq. yards plots
150 4500
7. 3000 to 4000 sq. yards plots
200 6000
8. > 4000 sq. yards plots 300 9000
The wastewater generation will be based on the following criteria:
Green Category of industries @ 40 % of the total plots would generate
only domestic effluent
Red Category industries @ 40 % of the total plots would generate only
organic effluent @ max. 20 KL/plot/day
Red Category of industries (mechanical industries) @ 20 % of the total
plots would generate only inorganic effluent @ max. 5 KL/plot/day
Overall domestic water consumption would be as per the following, depending upon the plot size:
Sr.
No.
Size of the Plot
Domestic water supply per plot (litres/day)
Number of Plots
Overall domestic water consumption (KL/day)
1. 200 to 300 sq. yards plots
450 84 37.8
2. 300 to 600 sq. yards plots
750 157 117.75
3. 600 to 1000 sq. yards plots
1500 153 229.5
76
4. 1000 to 1500 sq. yards plots
2250 49 110.25
5. 1500 to 2000 sq. yards plots
3000 19 57.0
6. 2000 to 3000 sq. yards plots
4500 19 85.5
7. 3000 to 4000 sq. yards plots
6000 3 18.0
8. > 4000 sq. yards plots
9000 1 9.0
Total 485 664.8
Domestic sewage generation would be 90 % of the total domestic water
consumption i.e. around 600 KL/day
Organic effluent generation will be as under:
a) Domestic Sewage - 600 KL/day
b) Industrial Effluent @ 20 KL/unit for 194 units – 3880 KL/day
c) Total organic effluent generation - 4480 KL/day
Inorganic effluent generation rate will be @ 5 KL/unit and 97 units will
generate about 485 KL/day of inorganic effluent.
The Industrial Park will produce about 4500 m3/day of organic
wastewater including domestic sewage. Similarly, the Industrial Park will
produce about 500 m3/day of inorganic wastewater from mechanical
industries/industries generating inorganic wastewater.
The biodegradable industrial wastewater and domestic effluent to be
generated by the industries will be carried out through common sewer
and the same shall be treated in 2 modules of CETP of capacity 2500
KLD each consisting of the collection tank, oil and grease trap,
neutralization tank, buffer tank, UASB, clarifier, aeration tank, secondary
clarifier, intermediate storage tank, multimedia, sand filter and activated
carbon filter press to treat the domestic effluent and biodegradable trade
effluent.
The average characteristics of the organic wastewater will be as under:
Flow rate 4500 KLD
BOD 2000 mg/l
77
COD 5000 mg/l
Total suspended solids 1000 mg/l
Flow peaking factor 3
The treated wastewater will be discharged into Vallah drain near SGRD
medical college and a permission in this regard has been obtained from
the Executive Engineer, Bari Dwab, Drainage Division.
The average characteristics of the inorganic wastewater will be as under:
Flow rate 500 KLD
Oil and Grease 100 mg/l
Trace metals 100 mg/l
Total suspended solids 1000 mg/l
Total dissolved solids/impurities 3000 mg/l
Flow peaking factor 3
To treat the inorganic streams to be generated from industrial units, will
be treated in a CETP of capacity 500 KLD consisting of collection tank,
reaction tank, flocculator, clarifier and treated wastewater storage tank
will be installed to treat the said wastewater against the actual
generation of 485 KLD.
There is no eco sensitive area declared under the Environment Protection
Act, 1986 in the State of Punjab as per the list available on the website
of MoEF. There is no Inter-State and International boundary of the
project site.
No construction/ development activity has been started at the site.
All the environmental concerns raised during the public hearing have
been properly addressed.
The SEAC noted certain observations and decided to defer the case
till the project proponent submits the reply of the said observations. The
decision of the SEAC was conveyed to the project proponent vide letter no.
2006 dated 04.02.2014.
78
4. Thereafter, the project proponent vide letter no. PBPL/2014/189 dated
10.06.2014, has submitted the reply of the observations, the details of which
are as under:
Sr. No.
Observations raised by the SEAC
Reply submitted by the promoter company
1. The promoter company is required to delineate the allotment of the each plot for specific category of the industry and in no case the occupier of the plot may be allowed to establish any other unit for which the plot has been kept for, but no proposal in this regard has been prepared by the promoter company, as such, the proposal of the promoter company is not complete one and on the basis of the same, it is difficult to assess the likely impacts on the environment.
The project proponent has submitted that 'Model Industrial Park' has been proposed for Green, Orange and Red category of industries with special restriction for highly polluting 17 categories of industries as described by CPCB. The promoters of the project would sale the plots to the interested parties for industrial purposes based on Green, Orange and Red category of industries. As described in the EIA report, 40% of the plots would be reserved for Green category, 20% for industries generating inorganic wastewater and 40% of the remaining plots for industries generating organic wastewater. All the proposed industries will obtain consent to establish as well as consent to operate under the respective Acts and for the specific purpose from the Competent Authority. The industries would be bound by the Punjab Pollution Control Board.
2. The promoter company has not proposed any foolproof mechanism as to how the consumption of water supply to each industry will be ensured so that actual consumption of the water by each industry can be recorded properly.
The project proponent has submitted that the metered domestic water supply would be provided by the promoters of the project as a common service to each of the plot holder based on the plot size. For industrial activity, the plot holder would make their own arrangements for the water
79
requirement as per their industrial activity.
3. The promoter company proposed to discharge the treated wastewater into the Vallah drain, which is not the proper and scientific mode of the disposal and the promoter company will not be allowed to discharge any treated wastewater into any drain/water body in any case, therefore, the promoter company is required to submit a concrete proposal for reuse of the treated wastewater for various purposes in the proposed industrial park so as to reduce the consumption of the fresh water vis a vis conservation of natural resources/ water bodies.
'Model Industrial Park' would provided two separate common effluent treatment plants (1 for organic wastewater and other for inorganic wastewater) in the complex. After treatment, the treated wastewater would be reused for irrigation purposes within the complex. The remaining wastewater would be disposed into the public sewer after obtaining the requisite permission from the Industries Department, for which the project proponent has already applied for. Further, the project proponent has undertaken that till the said permission is obtained and necessary connection is made the project proponent will be responsible for the handling of treated wastewater in lawful manner.
4. The promoter company has not carried out mathematical modeling to assess the impact of the air pollutants on the environment. The promoter company is required to mention the likely impacts of the air pollution and their impacts on the environment by carrying out mathematical modeling.
'Model Industrial Park' has been proposed for Green, Orange and Red category of industries with special restriction for highly polluting 17 categories of industry as described by CPCB. As described in the EIA report, 40% of the plots would be reserved for Green category, 20% for industries generating inorganic wastewater and 40% of the remaining plots for industries generating organic wastewater. The assessment of impact of the air pollutants is as under:
(i) 40% of the green category industries would not generate any air pollutants, which may adverse impact on the
80
environment.
(ii) 20% of the industries, which are generating inorganic wastewater and involved in activities such as electroplating, heat treatment, galvanizing etc. will cause air pollution. However, heat treatment in these industries would be done by using oil/gas based heating system which will cause minimum air pollution. The industries would install suction system for the electroplating and galvanizing process. The fumes after suction would be treated in alkaline scrubbers and hence there would not be any considerable impact on air pollutant.
(iii) 40% of the organic industry would be having air polluting activities from boiler operations, thermopack etc. More than 99% of the plots in the industrial park are less than 3000 sq. yards. Based on the size of the plot, the industry cannot install individual boiler/thermopack of capacity more than 1 TPH. Further, the industry would install air pollution control devices with the boiler/thermopack. Hence, the impact on the air quality would be minimum.
5. The promoter company has not properly calculated the hazardous waste to be generated from the various industries to be established in the industrial park and the impact of hazardous waste to be generated by the industries on the environment.
Following hazardous waste would be generated from the industrial park:
(i) Used oil from DG sets @ 5 KL/annum
(ii) ETP sludge from CETP @ 1 MTD
81
(iii) Sludge in containers from industries generating wastewater @ 5 MT/annum.
The project proponent would common hazardous waste storage area in an area of 100 sqm which would be covered and impervious in nature. All the hazardous waste would be stored in the said area and henceforth sent to the common hazardous waste treatment and landfill site located at Nimbua, Dera Bassi.
6. No proposal has been given as to how the wastewater to be generated from treatment of raw water will be handled and disposed off/ reused.
All the wastewater generated from the treatment of raw water would be disposed of in the organic sewer line from where it would go to the CETP for further treatment.
5. The project proponent was requested by the SEAC vide letter no. 2069 dated 27.06.2014 to attend its 95th meeting on 28.06.2014. Following were
present in the meeting on behalf of the project proponent:
(i) Col. N.S. Narang, Vice President of the promoter company
(ii) Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant of the promoter company.
Sh. Yash Pal Jain Environmental Consultant of the promoter company presented the reply of the observations raised by the SEAC. He also informed that:
(i) The construction of the CETP attracts environmental clearance under EIA
Notification, 2006, as such the promoter company had applied to the SEAC
for grant of environmental clearance under category 7 (c) of the EIA
Notification, 2006. There will not be any industry falling under category 'A'
or category 'B' except CETP (category 7 H) as per the EIA Notification, 2006
in the proposed project.
(ii) Model Industrial Park would provide two separate common effluent
treatment plants (one for organic wastewater and the other for inorganic
wastewater) in the complex. After treatment, the treated wastewater would
82
be reused for irrigation purposes within the complex. Remaining treated
wastewater would be disposed off into the public sewer.
(iii) The green area available for the reuse of treated wastewater for irrigation
purposes within the complex is around 77360 sqm. Water application @
around 10 mm would be applied during summer season and around 5 mm
would be applied during winter season. So, treated wastewater consumption
for irrigation purposes during summer season would be around 775 m3 and
would be around 385 m3 during winter season. The remaining wastewater
would be disposed off in the public sewer.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal for developing a
'Model Industrial Park' in the revenue estate of Village Vallah, District Amritsar
having total project area 146.428 acres which has been proposed to be developed
as under:
40% of the total industrial plots would have green category of
industries and/or industries exempted from obtaining Consent to
Establish from Punjab Pollution Control Board under the Water & Air
Acts. These industries would come up in the plot size varying from
200 sq. yards to 1000 sq. yards. These industries would generate
only domestic effluent.
20 % of the total plots would be having mechanical
industry/industries generating inorganic wastewater such as wire
drawing units, electroplating units, zinc sulphate/ferrous sulphate
plants, electrical appliances units, automobile workshops etc.
Maximum wastewater generation from such type of units would be 5
KL/unit/day.
The remaining 40 % of the industrial plots would house industries
such as formulation of drugs, formulation of pesticides/
insecticides/herbicides, milk chilling centers, small milk plants, mineral
water/carbonated soda bottling plants, packaged food industries,
board mills etc. Maximum wastewater generation from such type of
units would be 20 KL/unit/day;.
83
The SEAC decided to forward the case to the SEIAA with the
recommendation to grant environmental clearance to the project proponent subject
to certain conditions in addition to the proposed measures.
The project proponent was requested by the SEIAA vide letter No.
2141-46 dated 10.07.2014 to attend its 66th meeting on 11.07.2014, which was
attended by the following on behalf of the corporation:
(i) Col. (Retd) Avinash K. Sharma, AGM of the promoter company
(ii) Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant of the promoter company.
Sh. Yash Pal Jain, Environmental Consultant of the promoter company
presented the salient features of the project before the Authority and requested to
grant environmental clearance for the proposed project.
The SEIAA observed that the SEAC had recommended the case for
disposal of the treated trade effluent into the Focal Point sewer. However, during
the meeting the project proponent submitted that they have applied for permission
for discharging the treated trade effluent into the Focal Point sewer, but the same
has not been granted so far to the project proponent.
In view of the above, the SEIAA decided to defer the case till the
project proponent submits the permission for disposal of the treated trade effluent
into the Focal Point sewer, from the Department of Industries & Commerce,
Punjab.
The decision of SEIAA was conveyed to the project proponent vide
letter no. 2286 dated 25.07.2014. Further, the project proponent was issued
reminder vide letter no. 3516 dated 28.11.2014. However, no reply has been
received from the project proponent so far.
The case was considered by the SEIAA in its 74th meeting held on
24.12.2014.
After deliberations, the SEIAA decided to request the Punjab Pollution
Control Board to get the proposed site visited and submit construction status,
within 10 days. It was further decided to put up the case before the SEIAA with the
report of Punjab Pollution Control Board.
84
As decided, the Punjab Pollution Control Board was requested vide
letter No. 26 dated 07.01.2015.
The Punjab Pollution Control Board vide letter no. 780 dated
21.01.2015 informed that:
"It is intimated that the industry was visited by the Officers of this
office on 20.01.2015 and observed as under:
1. An entry gate of the Model Industrial Park has been
constructed by the project proponent.
2. Formation bed for the roads has been prepared only for the
stretch 150 m approx. from the entry gate.
3. Storm water sewer has been laid for the same stretch approx.
4. An office building exists near the entry gate of the park.
5. Plots in the compounding area of Model Industrial Park were
vacant and no construction activity was seen in progress at the
time of visit.
6. Sh. Damandeep Singh (Project Head) told that the proposal to
install the STP, CETP for the industries is yet to be finalized."
The project proponent vide letter dated 01.01.2015 has submitted a
copy of letter dated 31.12.2014 issued by PSIEC, Chandigarh, wherein, in-principal
approval has been accorded for the disposal treated effluent of Model Industrial
Park, Amritsar through existing sewer/rising main by strengthening / upgradation
of existing system of Industrial Focal Point, Mehta Road, Amritsar subject to
conditions that all expenses to be incurred including for
upgradation/strengethening / regular maintenance etc. will be borne by project
proponent and NOC from various authorities required for disposal of effluent will be
obtained by the project proponent at his own level.
The case was considered by the SEIAA in its 80th meeting held on
28.02.2015 and Mr. (Col) Navdeep Singh Norang, Vice President & Region Head of
the promoter company attended the meeting.
Vice President & Region Head of the promoter company requested
the SEIAA to grant environmental clearance as they have provided all the
documents sought by the SEIAA.
85
After deliberations, the SEIAA decided to remand the case to SEAC
for fresh recommendations in light of the report of Punjab Pollution Control Board
and NOC issued by PSIEC for disposal of treated effluent of Model Industrial Park,
Amritsar through existing sewer/rising main.
The case was considered by the SEAC in its 110th meeting held on
18.03.2015, which was attended by the following on behalf of the promoter
company:
(i) Col. (Retd) N.S. Narang, Vice President & Region Head of the promoter company
(ii) Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant of the promoter company.
SEAC observed that as per the report of Punjab Pollution Control
Board, construction activityrelated to the project such as laying of storm water
sewer, preparation of formation bed for the roads, entry gate, office building and
development of plots has already been carried out at site without obtaining
environmental clearance. Further, the project proponent is required to clarify the
position with regard to connectivity of sewer line of project to the existing
sewer/rising main as permitted by PSIEC.
Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant
of the promoter company clarified to the observations of the SEAC as under:
(i) The project proponent intends to develop a Model Industrial Park in an area
of 146.428 acres and a common effluent treatment plant within the said
Model Industrial Park. The two components i.e. development of industrial
park as well as proposal of CETP are independent of each other. Though
initially application was made for complete project under category 7 (c) of
Schedule-1 of notification, 2006, however, during presentation before the
SEAC in its 95th meeting held on 28.06.2014 it was categorically stated that
there is no industry falling under category 'A' or category 'B' as prescribed
under EIA notification, 2006 will be allowed to come up in the proposed
Industrial Park, Hence, their project be treated under category 7 (h) of the
Schedule-1 of EIA notification, 2006 i.e. only for the development &
construction of CETP in the Industrial Park. In fact his request had already
vbeen acceded to by the SEAC in the said and case was recommended to
86
SEIAA for grant of environmental clearance. He further clarified that no
construction activity relating to CETP project has been started at site.
(ii) Regarding disposal of treated effluents to be discharged from the proposed
project, the permission has been accorded by PSIEC to connect its sewer
line with the existing sewer of Focal Point. The sewer line of the project will
be connected to the collection sump of the Focal Point sewer system from
where the entire effluents will be pumped to the Focal Point main sewer line
which ultimately leads to 'Kasoor Nallah'.
He also submitted a written clarification in this regard alongwith
layout plan indicating location of CETP, collection sump of PSIEC Focal Point and
sewerlines. He further submitted a copy of letter dated 06.01.2015 vide which in-
principle approval has been accorded by the MoEF&CC, Northern Regional Office,
Chandigarh for diversion of 0.079 ha of forest land for approach road to Model
Industrial Park. The above said documents were taken on record.
After detailed deliberations, the SEAC decided to forward the case to
the SEIAA with the recommendation to grant environmental clearance for
establishment of 2 modules of CETP (one for organic wastewater and the other for
inorganic wastewater) of capacity 2500 KLD each consisting of the collection tank,
oil and grease trap, neutralization tank, buffer tank, UASB, clarifier, aeration tank,
secondary clarifier, intermediate storage tank, multimedia, sand filter and activated
carbon filter to treat the domestic effluent and biodegradable trade effluent in the
Model Industrial Park to be located in the revenue estate of Village Vallah, District
Amritsar, subject to the following conditions in addition to the proposed measures:
Part A – SPECIFIC CONDITIONS i. The project proponent shall ensure that no other industry falling under
category 'A' or category 'B' except the proposed CETP (category 7 h) of schedule attached to EIA Notification dated 14/9/2006 is allowed to come up
in the Model Indsutrial Park.
ii. The project proponent shall provide two separate common effluent treatment plants (one for organc wastewater and the other for inorganic wastewater) in the complex. After treatment most of the treated wastewater will be used onto land for watering of green areas etc. within the complex. Remaining treated wastewater shall be disposed off into the public sewer.
iii. Upcoming industrial units in the proposed project shall provide adequate and appropriate primary treatment facilities within their premises so as to ensure
87
that the quality of effluent being received at the inlet of CETP is as per prescribed norms. The project proponent shall impose a condition in the allotment letters to the plot allottees in this regard.
iv. “Consent for Establishment” shall be obtained from the Punjab Pollution Control Board and a copy shall be furnished to the SEIAA, Punjab before taking up any construction activity at the site.
v. To facilitate inspection and collection of effluent from all the member units
at least one dedicated inspection chamber for each type of effluent should be provided by each unit. The intermediate distance between two consecutive man holes should be so adjusted that the cleaning of the pipeline remains operational all the time.
vi. Based on the cumulative design flow the size of the pipeline should be so adjusted that the industrial effluent attains the self cleaning velocity of 0.75 m/sec.
vii. Free flow of effluent should be ensured either by providing adequate slope in the Common Effluent Conveyance System or by providing common sump and pumping arrangement.
viii. Regular monitoring operation and maintenance of the conveying system will be performed by the project proponent so that the pipeline is protected from corrosion, silting, choking and explosion.
ix. The project proponent will collect the sample of effluent from each industry and measure the flow from such industries on regular basis to check
whether the industries meet the CETP influent standards or not.
x. Provisions should be made for disconnecting any unit from common conduit
and facility if it fails to comply with the allowable discharge parameters.
xi. The receiving sump(s) at CETP should be of adequate capacity and should have arrangement for adequate no. of pumps, keeping one as stand-by. The pumps are required to have regular maintenance schedule adopting preventive maintenance system. The leakages are required to be attended to regularly and as per preventive maintenance system. The operator is required to maintain a logbook for duration of operation of each pump and also for the flow / quantity of waste water pumped.
xii. The various operating parameters such as Color, pH, Mixed Liquor Suspended Solids (MLSS), Mixed Liquor Volatile Suspended Solids (MLVSS) and minimum Dissolved Oxygen (DO) in case of aerobic system should be maintained as per design. It is also necessary to record these parameters on regular basis.
xiii. At CETP site a well equipped laboratory and associated facilities should be established with the following sections: Physical-Chemical Lab, instrumental, Instrumental Analysis Lab, R&D section, Sample preparation and Storage Section for regular monitoring of influent and treated effluent before final
discharge.
xiv. For successful operation of the CETP and the effluent conveyance system, a routine monitoring system should be in place.
88
xv. The project proponent and the operator of the CETP will be responsible for
compliance of final liquid discharge by proper Operation and Maintenance of common effluent conveyance system and different subunits of CETP.
xvi. The gaseous emissions, if any, from various process units should confirm to the load / mass based standards prescribed by the Ministry of Environment & Forests and the State Pollution Control Board from time to time. At no time, the emission level should go beyond the prescribed standards.
xvii. Adequate provision for rainwater harvesting system and recycling of water should be introduced. Recharging of ground water is not permitted without prior permission of competent authority.
xviii. Adequate green belt covering an area 77360 sqm. as proposed shall be developed in and around the plant premises. Selection of appropriate species for the plantation programme may be done in consultation with the Forest Department of the respective area.
xix. Ambient noise level should not exceed the permissible limit. The overall noise levels in and around the plant area shall be kept well within the standards by providing noise control measures including acoustic hoods, silencers, enclosures etc. on all sources of noise generation. The ambient noise levels should confirm to the standards prescribed under EPA Rules, 1989.
xx. All internal roads should be pitched. Proper lighting and proper pathway inside the factory premises should be provided to ensure safe vehicular movement. Provision of separate pathway for entry and exit of vehicles should be considered. Vehicles should confirm to pollution under control (PUC) norms. Proper house keeping shall be maintained within the premises.
xxi. Health and safety of workers should be ensured. Workers should be provided with adequate personnel protective equipment and sanitation facilities. Occupational Health Surveillance of the workers shall be done on a regular basis and records maintained as per the Factories Act.
xxii. Adequate provisions for the infrastructure facilities including water supply and sanitation shall be ensured for the laborers during the construction period.
xxiii. Construction materials and wastes including hazardous substances, if any, shall not be allowed to pollute the surrounding land or aquatic environment as the case may be.
xxiv. Adequate measures shall be adopted to ensure industrial safety. Proper fire detection & protection systems shall be provided to control fire and explosion hazards. The implementation and monitoring of Environmental Management Plan and Disaster Management Plan should be carried out, as proposed.
xxv. The proponent should abide by the Hazardous Wastes (Management and Handling and Transboundary Movement) Amendment Rules, 2008. Collection and storage of hazardous wastes during Pre-construction and Post construction activity should be planned properly. The expected hazardous wastes should be disposed off separately as per the Hazardous Wastes
89
(Handling & Management & Transboundary Movement) Amendment Rules, 2008.
xxvi. Spent oil from DG Sets shall be stored in HDPE drums in an isolated covered facility and disposed off as per the Hazardous Wastes (Handling & Management) Amendment Rules, 2003. Spent oil from DG Sets should be disposed off through recyclers registered with Central Pollution Control Board only.
xxvii. Firefighting systems should be designed in compliance with the Fire Service
and NBC norms. Preventive measures should be adopted for Risk & Disaster Management as per the provisions of the National Building Code 2005.
xxviii. Environmental Management Information System shall be in position and maintained properly.
xxix. This Environmental Clearance does not imply that the other statutory / administrative clearances shall be granted to the project by the concerned authorities. Such authorities would be considering the project on merits and take decisions independently of the Environmental Clearance.
B. GENERAL CONDITIONS: i. The Environmental Clearance does not absolve the applicant/proponent of
his obligation/requirement to obtain other statutory and administrative clearance from other statutory and administrative authorities.
ii. No further expansion or modifications in the plant shall be carried out without prior approval of the SEIAA. In case of deviations or alterations in the project proposal from those submitted for clearance, a fresh reference shall be made to the SEIAA to assess the adequacy of conditions imposed and to add additional environmental protection measures required, if any.
iii. Occupational health surveillance of the workers shall be carried out on a regular basis and records shall be maintained as per the Factories Act.
iv. Proper House keeping programmes shall be taken up.
v. Usage of Personal Protective Equipments (PPEs) by all employees/ workers shall be ensured.
vi. This Environmental Clearance is valid for five years from the date of issue.
vii. The project proponent shall comply with all the environmental protection measures and safeguards proposed in the EMP report.
viii. A separate Environmental Management Cell shall be set up to carry out the Environmental Management and Monitoring functions.
ix. The project proponent should advertise in at least two local newspapers widely circulated in the region, one of which shall be in the vernacular language informing that the project has been accorded environmental clearance and copies of clearance letters are available with the Punjab Pollution Control Board. The advertisement should be made within seven days from the day of issue of the clearance letter and a copy of the same
90
should be forwarded to the Regional Office, Ministry of Environment & Forests, Chandigarh.
x. The SEIAA may revoke or suspend the clearance, if implementation of any
of the above conditions is not satisfactory.
xi. The SEIAA reserves the right to stipulate additional conditions, if found necessary. The Proponent shall implement these conditions in a time bound
manner.
xii. The above conditions will be enforced, inter-alia under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986, Hazardous Wastes (Management, Handling and Transboundary Movement) Rules, 2008 and the Public Liability Insurance Act, 1991 along with their amendments and rules.
xiii. All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire and Rescue Services Department, Forest Conservation Act, 1980 and Wild Life (Protection) Act, 1972, State / Central Ground Water Authority, other statutory and other authorities as applicable to the project shall be obtained by project proponent from the
competent authorities.
xiv. The Environmental Statement for each financial year ending 31st March in Form-V as is mandated has to be submitted by the project proponent to the Punjab Pollution Control Board as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently and shall also be put on the website of the company along with the status of compliance of EC conditions and shall also be sent to the Regional Office of MoEF, Chandigarh and SEIAA, Punjab by e-mail.
xv. The proponent shall upload the status of compliance of the stipulated EC
conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, SEIAA, Punjab, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
xvi. A copy of the clearance letter shall be sent by the proponent to the concerned Panchayat, Zila Parishad / Commissioner, Municipal Corporation, Amritsar and the Local NGO, if any, from whom suggestions /representations, if any, were received while processing the proposal. The clearance letter shall also be put on the website of the Company by the proponent.
xvii. Environmental clearance is subject to final order of the Hon'ble Supreme Court of India in the matter of Goa Foundation Vs. Union of India in Writ Petition (Civil) No. 460 of 2004 as may be applicable to this project and decisions of any competent court, to the extent applicable.
xviii. Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State
91
Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh and State Level Environment Impact Assessment Authority, Punjab.
xix. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following on behalf of the promoter
company:
(i) Col. (Retd) N.S. Narang, Vice President & Region Head of the promoter company
(ii) Sh. Yash Pal Jain of M/s ACE Consultants, Environmental Consultant of the promoter company.
Sh. Yash Pal Jain presented the salient features of the project
before the SEIAA and requested to grant environmental clearance for the project.
The SEIAA observed that the case stands recommended by SEAC and
the Committee awarded ‘Silver Grading’ to the project proposal. The SEIAA
looked into the details of the case and was satisfied with the same. Therefore, the
Authority decided to grant environmental clearance for establishment of 2 modules
of CETP (one for organic wastewater and the other for inorganic wastewater) of
capacity 2500 KLD each consisting of the collection tank, oil and grease trap,
neutralization tank, buffer tank, UASB, clarifier, aeration tank, secondary clarifier,
intermediate storage tank, multimedia, sand filter and activated carbon filter to
treat the domestic effluent and biodegradable trade effluent in the Model Industrial
Park to be located in the revenue estate of Village Vallah, District Amritsar, subject
to the conditions as proposed by the SEAC and to amend condition no. (ii) of
'Specific Conditions' in addition to the proposed measures.
Specific Conditon No. (ii)
“The project proponent shall provide two separate common effluent treatment plants (one for organic wastewater and the other for inorganic wastewater) in the complex. After treatment most of the treated wastewater will be used onto land for watering of green areas etc. within the complex.
92
Remaining treated wastewater shall be connected and discharged into manhole/sewer system of Focal Point before the final collection tank.”
Item No.82.09: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for construction of Jang-E-Azadi memorial at NH-1, Kartarpur, District Jalandhar by M/s Punjab Freedom Movement Memorial Foundation.
The SEIAA observed that:
M/s Punjab Freedom Movement Memorial Foundation vide
letter No. 1766 dated 11.03.2015 has applied to MoEF for obtaining environmental
clearance as required under EIA notification dated 14.09.2006 for construction of
Jang-E-Azadi memorial at NH-1, Kartarpur, District Jalandhar. The project is
covered under category 8 (a) of the Schedule appended to the said notification.
The case was considered by the SEAC in its 110th meeting held
on 18.03.2015, which was attended by the following on behalf of the project
proponent:
(i) Sh. N.P. Singh, Executive Engineer, Public Health, Jalandhar
(ii) Sh. T.R. Katnoria, Executive Engineer, PWD (B&R)
(iii) Sh. Ankit Bansal, Architect
(iv) Sh. Vishal Duggal of M/s Ace Engineers & Consultants,
Patiala Environmental Consultant
Sh. Vishal Duggal, Environmental Consultant presented project
proposal before the SEAC as under:
The total plot area is 101171 sqm having a built up area of 35146.62 sqm.
Permission for CLU for land area measuring 25 acres has been granted by
the Self Loca Govt. vide Memo No. 2014/2 dated 13.01.2014.
Total water requirement for the project will be 230-550 KLD, out of which
120-420 KLD will be met through groundwater and remaining requirement
will be met from treated wastewater.
The total wastewater generation from the project will be 115-130 KLD,
which will be treated in a STP to be installed within the project premises.
The project proponent has proposed to use 129 KLD of treated wastewater
93
for green area in summer season. In winter season, 47 KLD of treated
wastewater will be used for flushing purpose and 67 KLD will be used for
irrigation of green area. In rainy season, 30 KLD of treated wastewater will
be used for HVAC, 50 KLD for flushing, 19 KLD for green area and remaining
20 KLD will be discharged into M.C. sewer.
M.C. Kartarpur has issued NOC vide No. 319 dated 27.02.2015, wherein the
details of existing status of sewer connectivity has been mentioned.
The green area will be developed in an area of 37,580 sqm.
The total quantity of solid waste to be generated from the proposed project
has been estimated as 800 Kg/day, which will be segregated into bio-
degradable and non-biodegradable waste as per the MSW Rules, 2000. The
recyclable waste will be sold to the authorized and non-recyclable will be
disposed through M.C. M.C. Kartarpur has issued NOC vide No. 319 dated
27.02.2015 in this regard.
The ambient air monitoring has been got done from M/s Sophisticated
Analytical Instruments Laboratories, Thapar Technology Campus, Patiala and
the analysis results indicate that the concentration of various pollutants such
as PM2.5, PM10, SO2, NO2, and CO have been measured. Also, ambient noise
monitoring has been got done from the said firm and the analysis results
indicate that the noise levels during day and night times, have been
measured as 65.8 dB(A) leq and 59.9 dB(A) leq, respectively, against the
prescribed standards of 55 and 45 dB(A) leq.
The e-waste will be handled and managed as per the E-waste (Management
& Handling) Rules, 2011.
The used oil from the D.G. sets will be sold out to the registered recyclers as
per the provisions of the Hazardous Waste (Management, Handling &
Transboundary Movement), Rules, 2008.
The total load of electricity required for proposed project will be 2.4 MW
which will be supplied by PSPCL. The project proponent has proposed to
install DG sets of 1500 KVA capacity for backup power supply.
Rs.163 Lacs will be utilized as capital cost and Rs.68 Lacs will be incurred as
operational cost for the EMP. Administrative Officer, Punjab Freedom
Movement Memorial Foundation. Executive Engineer, Construction Division-
94
2, PWD (B&R) Branch, Jalandhar, Executive Engineer, Electrical, PWD (B&R)
Branch, Jalandhar. Executive Engineer, Water Supply & Sanitation Division-
2, Jalandhar will be responsible for implementation of EMP.
The traffic circulation plan and Disaster/Risk Assessment & Management
Plan have been prepared and submitted.
After hearing the presentation, the SEAC raised certain observations
and the Environmental Consultant given the reply to the same, the detail of which
is as under:
Sr. No.
Observation raised Reply given by the project proponent
1. The water balance diagram submitted by project proponent reveals that optimum reuse of treated wastewater has not been taken into account and same can be reused for various purposes such as public toilets, HVAC and plantation area.
The project proponent submitted a revised water balance statement by making the necessary changes regading reuse of treated wastewater for use in public toilets, HVAC and plantation area thereby achieving ZLD.
2. The project proponent has proposed to use CFL and LED lamps whereas only LED lamps should be used.
The project proponent agreed to the suggestion and stated that only LED lamps will be used.
3. The project proponent is required to mark existing positon of public sewer and water supply on the layout map.
The project proponent marked the position of existing public sewer on the layout map. However, he further clarified that after submission of revised water balace statement in response to observation at Sr. No. 1 above, the project is now ZLD based and no wastewater will be discharged into public sewer/outside the premses.
4. The project proponent is required to submit construction schedule (PERT/CPM chart).
The project proponent submitted the construction schedule (PERT/CPM chart).
5. The project proponent is required to submit details of Corporate Social Responsibility activities to be undertaken, provisions of funds for the same etc.
The project proponent clarified that the whole project being developed as a memorial and museum in the memory of martyrs of nation's freedom struggle by the State Govt. is itself a Corporate Social Responsibility chapter.
6. The project proponent is required to submit concrete documentary
The project proponent submitted a copy of acknowledgement towards
95
evidence regarding submission of application for obtaining forest clearance from the Forest Department for using forest area as approach to the project premises.
filing the application for obtaining the requisite permission from the the Forest Department.
The SEAC was apprised that the Punjab Pollution Control Board,
Regional Office, Jalandhar vide letter No. 5356 dated 17.03.2015 has informed that
the site of the project was visited on 16.03.2015 and observed that the boundary
walls of the project was under construction on its 3 sides whereas on the fourth
side i.e. towards NH-1, it is yet to be started. The said construction on 3 sides of
boundary walls is about 1.5 m above ground level as on date. Further there is no
construction activities started within the plot except the boundary walls as detailed
above.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal and decided to
forward the case to the SEIAA with the recommendation to grant environmental
clearance to the project proponent for construction of Jang-E-Azadi memorial in an
area of 101171 sqm having built up area 35146.62 sqm at NH-1, Kartarpur, District
Jalandhar, subject to the following conditions in addition to the proposed
measures:
PART A – Specific conditions
I. Pre-Construction Phase
(i) “Consent to establish” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority before the start of any construction work at site.
(ii) All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.
(iii) A first aid room will be provided in the project both during construction and operation phase of the project.
(iv) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments
96
etc. as per National Building Code including protection measures from lightning.
(v) Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, disposal of waste water & solid waste in an environmentally sound manner, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project.
II. Construction Phase:
(i) All the topsoil excavated during construction activities should be stored for use in horticulture / landscape development within the project site.
(ii) Disposal of muck during construction phase should not create any adverse effect on the neighbouring communities and be disposed off after taking the necessary precautions for general safety and health aspects of people with the approval of competent authority.
(iii) Construction spoils, including bituminous material and other hazardous material, must not be allowed to contaminate watercourses and the dump sites for such material must be secured, so that they should not leach into the groundwater.
(iv) Construction/provision of the STP, tubewell, DG Sets, Utilities etc, earmarked by the project proponent on the layout plan, should be made in the earmarked area only. In any case the position/location of these utilities should not be changed later-on.
(iv) Vehicles hired for bringing construction material to the site and other machinery to be used during construction should be in good condition and should conform to applicable air and noise emission standards.
(v) Ambient noise levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
(vi) Fly ash should be used as construction material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended on August, 2003 and notification No. S.O. 2804 (E) dated 03.11.2009 (This condition is applicable only if the project is within 100 Km of Thermal Power Station).
(vii) Ready mixed concrete should be used in building construction as far as possible.
(viii) Water demand during construction should be reduced by use of premixed concrete, curing agents and other best practices.
(ix) Separation of drinking water supply and treated sewage supply should be done by the use of different colours.
(x) Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
(xi) Adequate steps shall be taken to conserve energy by limiting the use of glass, provision of proper thermal insulation and taking measures as prescribed under the Energy Conservation Building Code.
97
(xii) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
(xiii) The diesel generator sets to be used during construction phase should be of low sulphur diesel type and should conform to the provisions of Environment (Protection) Act, 1986 prescribed for air and noise emission standards.
III. Operation Phase
i) “Consent to operate” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority at the time of start of operation.
ii) The installation of sewage treatment plant (STP) and adequacy of disposal system should be certified by Punjab Pollution Control Board and a report in this regard should be submitted to the Ministry of Environment & Forests/State Level Environment Impact Assessment Authority before the project is commissioned for operation.
iii) The project proponent shall not discharge any wastewater into public sewer/outside the premises. Entire treated wastewater shall be reused for flushing (public toilets), HVAC and plantation area, so as to achieve ZLD.
iv) The project proponent shall provide electromagnetic flow meter at the outlet
of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing and for horticulture purpose/green etc. and shall maintain a record of readings of each such meter on daily basis.
v) The position / location of the STP, tubewell, DG Sets, Utilities etc, installed by the project proponent as per the provisions made in the layout plan, should not be changed later-on under any circumstances.
vi) Adequate & appropriate pollution control measures should be provided to control fugitive emissions to be emitted within the complex.
vii) Adequate treatment facility for drinking water shall be provided, if required.
viii) The green belt along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential land use. The open spaces inside the plot should be suitably landscaped and covered with vegetation of indigenous species/variety.
ix) The project proponent should take adequate and appropriate measures to contain the ambient air quality within the prescribed standards. The proposal regarding mitigation measures to be taken at site should be submitted to the Ministry of Environment & Forests/ State Level Environment Impact Assessment Authority within three months.
98
x) Application of solar energy should be incorporated for illumination of common areas, lighting for gardens and street lighting in addition to provision for solar water heating.
xi) A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about machinery of air conditioning, lifts, lighting, building materials, R & U Factors etc. and submitted to the respective Regional office of MoEF, the Zonal Office of CPCB and the SPCB/SEIAA in three months time.
xii) Environmental Management Cell shall be formed during operation phase which will supervise and monitor the environment related aspects of the project.
xiii) Ambient noise levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
xiv) Separation of drinking water supply and treated sewage supply should be done by the use of different colors.
xv) Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
IV. Entire Life:
i) “Consent to operate” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and get it renewed from time to time and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority.
ii) The project proponent shall not discharge any wastewater into public sewer/outside the premises. Entire treated wastewater shall be reused for flushing (public toilets), HVAC and plantation area, so as to achieve ZLD.
iii) The project proponent shall provide electromagnetic flow meter at the outlet of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing and for horticulture purpose/green etc. and shall maintain a record of readings of each such meter on daily basis.
iv) The position / location of the STP, tubewell, DG Sets, Utilities etc, installed by the project proponent as per the provisions made in the layout plan, should not be changed later-on under any circumstances.
v) Rainwater harvesting for roof run-off should be implemented. Before recharging the roof run-off, pretreatment must be done to remove suspended matter, oil and grease. However, no run off from gardens/green area/roads/pavements shall be connected with the ground water recharging system.
99
vi) The solid waste generated should be properly collected and segregated. The recyclable solid waste shall be sold out to the authorized vendors and inert shall be sent to disposal facility. The Bio-degradable solid waste shall be adequately treated as per the scheme submitted by the project proponent. Prior approval of competent authority should be obtained, if required.
vii) Hazardous waste/E-waste should be disposed off as per Rules applicable and with the necessary approval of the Punjab Pollution Control Board.
viii) Incremental pollution loads on the ambient air quality, noise and water quality should be periodically monitored.
ix) Traffic congestion near the entry and exit points from the roads adjoining the proposed project site must be avoided. Parking should be fully internalized and no public space should be utilized.
x) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
PART B – General Conditions :
I. Pre-Construction Phase
i) This environmental clearance will be valid for a period of five years from the date of its issue or till the completion of the project, whichever is earlier.
ii) The environmental safeguards contained in the application of the promoter / mentioned during the presentation before State Level Environment Impact Assessment Authority/State Expert Appraisal Committee should be implemented in letter and spirit.
iii) All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest (Conservation) Act, 1980 and Wildlife (Protection) Act, 1972 etc. shall be obtained, by project proponents from the competent authorities including Punjab Pollution Control Board and from other statutory bodies as applicable. The project proponent shall also obtain permission from the NBWL, if applicable.
iv) The project proponent should advertise in at least two local newspapers widely circulated in the region, one of which shall be in the vernacular language informing that the project has been accorded environmental clearance and copies of clearance letters are available with the Punjab Pollution Control Board. The advertisement should be made within seven days from the day of issue of the clearance letter and a copy of the same should be forwarded to the Regional Office, Ministry of Environment & Forests, Chandigarh and SEIAA, Punjab.
v) These stipulations would be enforced among others under the provisions of Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environmental (Protection) Act, 1986, the Public Liability (Insurance) Act, 1991 and EIA Notification, 2006.
100
vi) The project proponent shall obtain permission from the CGWA for abstraction of groundwater & digging of borewell(s) and shall not abstract any groundwater without prior written permission of the CGWA, even if any borewell(s) exist at site
vii) The project proponent shall comply with the conditions imposed by the Competent Authority while granting CLU.
viii) A copy of the clearance letter shall be sent by the proponent to concerned Panchayat, Zilla Parishad/ Municipal Corporation, Urban local body and the local NGO, if any, from whom suggestions / representations, if any, were received while processing the proposal. The clearance letter shall also be put on the website of the Company by the proponent.
ix) The State Environment Impact Assessment Authority, Punjab reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
x) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
II. Construction Phase
i) The environmental safeguards contained in the application of the promoter / mentioned during the presentation before State Level Environment Impact Assessment Authority/State Expert Appraisal Committee should be implemented in letter and spirit.
ii) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
iii) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB, the SPCB and SEIAA, Punjab.
iv) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh and State Level Environment Impact Assessment Authority, Punjab.
101
v) In the case of any change(s) in the scope of the project, the project would require a fresh appraisal by State Environment Impact Assessment Authority, Punjab.
vi) Separate distribution pipelines be laid down for use of treated effluent / raw water for horticultural/gardening purposes with different colour coding.
vii) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
viii) The State Environment Impact Assessment Authority, Punjab reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
ix) Separation of drinking water supply and treated sewage supply should be done by the use of dual plumbing line for separation of drinking water and treated sewage.
x) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
III. Operation Phase
i) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
ii) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB, the SPCB and SEIAA, Punjab.
iii) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh and State Level Environment Impact Assessment Authority, Punjab.
iv) The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional
102
Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SO2, NOx, CO, Pb, Ozone (ambient air as well as stack emissions) shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
v) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
xi) The State Environment Impact Assessment Authority, Punjab reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
xii) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
IV Entire Life
i) Environmental clearance is subject to final order of the Hon'ble Supreme Court of India in the matter of Goa Foundation Vs. Union of India in Writ Petition (Civil) No. 460 of 2004 as may be applicable to this project and decisions of any Competent Court, to the extent applicable.
ii) The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SO2, NOx, CO, Pb, Ozone (ambient air as well as stack emissions) shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
iii) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
iv) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
v) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB, the SPCB and SEIAA, Punjab.
103
vi) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh and State Level Environment Impact Assessment Authority, Punjab.
xiii) The State Environment Impact Assessment Authority, Punjab reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/measures in a time bound and satisfactory manner.
xiv) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following on behalf of the project
proponent:
(i) Sh. N.P. Singh, Executive Engineer, Public Health,
Jalandhar
(ii) Sh. T.R. Katnoria, Executive Engineer, PWD (B&R)
(iii) Sh. Ankit Bansal, Architect
(iv) Sh. Vishal Duggal of M/s Ace Engineers & Consultants,
Patiala Environmental Consultant
Sh. Vishal Duggal, Environmental Consultant presented the salient
features of the project before the SEIAA and requested to grant environmental
clearance for the project.
The SEIAA observed that the case stands recommended by SEAC and
the Committee awarded ‘Silver Grading’ to the project proposal. The SEIAA
looked into the details of the case and was satisfied with the same. Therefore, the
Authority decided to grant environmental clearance to the project proponent for
construction of Jang-E-Azadi memorial in an area of 101171 sqm having built up
104
area 35146.62 sqm at NH-1, Kartarpur, District Jalandhar, subject to the conditions
as proposed by the SEAC in addition to the proposed measures.
Item No.82.10: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Moga for mining of minor minerals in the revenue estate of Village Kot Sadar Khan, Tehsil Dharamkot, District Moga in the name of Sh. Ranjit Singh S/o Sh. Darshan Singh, r/o Zira Road, Kot
Ise Khan, District Moga
The General Manager-Cum-Mining Officer, Moga, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2208
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 93,312 Ton
over a period of 3 years in an area of 2.40 hectares outside the river bed in the
revenue estate of Village Kot Sadar Khan, Tehsil Dharamkot, District Moga in H.B.
no. 245, Khasra no.:8//5(8-0), 6(8-0), 3(8-0), 4(8-0), 7(8-0), 8(7-12), subject to
the conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Moga vide letter no.
947 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11671-B dated 28.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Moga vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, to GMDIC, Moga and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iii) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Moga and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(iv) Self declaration by Sh. Paramjit Singh to the effect that he is the Sole Prop. Of the mining site and will comply with the conditions of environmental clearance.
105
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Kuldeep Singh Thind, General Manager-cum-Mining Officer, Moga.
(ii) Sh. Ranjit Singh S/o Sh. Darshan Singh, r/o Zira Road, Kot Ise Khan, District Moga .
The SEIAA observed that in the agenda item the self declaration has
been shown to be given by Paramjit Singh whereas the environmental clearance is
to be transferred in the name of Ranjit Singh. The SEIAA further observed that
Paramjit Singh has been written as a typographical error and all the documents as
well as request letter are in the name of Sh. Ranjit Singh.
The SEIAA also observed that as per EIA notification dated
14.09.2006, the environmental clearance granted for a specific project or activity to
an applicant can be transferred during its validity to another legal person entitled to
undertake the project or activity on application by the transferor, or by the
transferee with a written “no objection” by the transferor, to, and by the regulatory
authority concerned, on the same terms and conditions under which the prior
environmental clearance was initially granted, and for the same validity period. No
reference to the State Level Expert Appraisal Committee concerned is necessary in
such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Moga vide no. 2208 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 93,312 Ton over a period of 3
years in an area of 2.40 hectares outside the river bed in the revenue estate of
Village Kot Sadar Khan, Tehsil Dharamkot, District Moga in H.B. no. 245, Khasra
no.:8//5(8-0), 6(8-0), 3(8-0), 4(8-0), 7(8-0), 8(7-12), in the name of contractor Sh.
Ranjit Singh S/o Sh. Darshan Singh, r/o Zira Road, Kot Ise Khan, District Moga for
a period upto 31.10.2016 (validity period of the contract) subject to the same
conditions as mentioned in the environmental clearance issued vide no. 2208 dated
31.03.2015.
106
Item No.82.11: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Moga for mining of minor minerals in the revenue estate of Village Dargah Sadan, Tehsil Dharamkot, District Moga in the name of Sh. Ranjit Singh S/o Sh. Darshan Singh, r/o Zira Road, Kot Ise Khan, District Moga
The General Manager-Cum-Mining Officer, Moga, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2138
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 1,37,635 Ton
over a period of 3 years in an area of 3.54 hectares outside the river bed in the
revenue estate of Village Dargah Sadan, Tehsil Dharamkot, District Moga in H.B.
no. 179, Khasra no.:4//4(0-1), 4//7(3-5), 4//8(5-6), 4//9(0-15), 4//11(2-9),
4//12(7-8), 4//13(8-0), 4//14(4-0), 4//15(4-0), 4//18(8-0), 4//19(7-18), 4//20(6-4),
4//22(0-13), 4//23(2-18), 15//16(1-4), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Moga vide letter no.
949 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11671-B dated 28.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Moga vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, to GMDIC, Moga and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iii) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Moga and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
107
(iv) Self declaration by Sh. Paramjit Singh to the effect that he is the Sole Prop. Of the mining site and will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Kuldeep Singh Thind, General Manager-cum-Mining Officer, Moga.
(ii) Sh. Ranjit Singh S/o Sh. Darshan Singh, r/o Zira Road, Kot Ise Khan, District Moga.
The SEIAA observed that in the agenda item the self declaration has
been shown to be given by Paramjit Singh whereas the environmental clearance is
to be transferred in the name of Ranjit Singh. The SEIAA further observed that
Paramjit Singh has been written as a typographical error and all the documents as
well as request letter are in the name of Sh. Ranjit Singh.
The SEIAA also observed that as per EIA notification dated
14.09.2006, the environmental clearance granted for a specific project or activity to
an applicant can be transferred during its validity to another legal person entitled to
undertake the project or activity on application by the transferor, or by the
transferee with a written “no objection” by the transferor, to, and by the regulatory
authority concerned, on the same terms and conditions under which the prior
environmental clearance was initially granted, and for the same validity period. No
reference to the State Level Expert Appraisal Committee concerned is necessary in
such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Moga vide no. 2138 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 1,37,635 Ton over a period of 3
years in an area of 3.54 hectares outside the river bed in the revenue estate of
Village Dargah Sadan, Tehsil Dharamkot, District Moga in H.B. no. 179, Khasra
no.:4//4(0-1), 4//7(3-5), 4//8(5-6), 4//9(0-15), 4//11(2-9), 4//12(7-8), 4//13(8-0),
4//14(4-0), 4//15(4-0), 4//18(8-0), 4//19(7-18), 4//20(6-4), 4//22(0-13), 4//23(2-
18), 15//16(1-4), in the name of contractor Sh. Ranjit Singh S/o Sh. Darshan
Singh, r/o Zira Road, Kot Ise Khan, District Moga for a period upto 31.10.2016
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2138 dated 31.03.2015.
108
Item No.82.12: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Hashmatwala, Tehsil Makhu, District Ferozpur in the name of M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2219 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 82,026
Ton over a period of 3 years in an area of 2.63 hectares outside the river bed in
the revenue estate of Village Hashmatwala, Tehsil Makhu, District Ferozpur in H.B.
no. 26, Khasra no.: 4/1(7-12), 11/2(4-15), 12/1(7-13), 21(8-0), 22(8-0), 1(8-0),
2(8-0), subject to the conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1034 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2517 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Kamboj & Co. vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iii) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(iv) Partnership Deed dated 15.06.2011.
109
(v) Power of Attorney dated 15.06.2011 vide which Sh. Gurvinder Singh authorized to act as attorney on behalf of the firm.
(vi) Self declaration by Sh. Gurvinder Singh partner of the firm to the effect that they will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Gurvinder Singh, M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2219 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 82,026 Ton over a
period of 3 years in an area of 2.63 hectares outside the river bed in the revenue
estate of Village Hashmatwala, Tehsil Makhu, District Ferozpur in H.B. no. 26,
Khasra no.: 4/1(7-12), 11/2(4-15), 12/1(7-13), 21(8-0), 22(8-0), 1(8-0), 2(8-0), in
the name of contractor M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil
Jalalabad, District Fazilka for a period upto 31.10.2016 (validity period of the
contract) subject to the same conditions as mentioned in the environmental
clearance issued vide no. 2219 dated 31.03.2015.
Item No.82.13: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Lokhe Khurd, Tehsil Zira, District Ferozpur in the name of M/s
110
Kamboj & Company, V.P.O. Aamir Khas, Tehsil
Jalalabad, District Fazilka.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2038 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 50,387
Ton over a period of 3 years in an area of 1.85 hectares outside the river bed in
the revenue estate of Village Lokhe Khurd, Tehsil Zira, District Ferozpur in H.B. no.
11, Khasra no.: 9//21(6-16), 18//10(6-16), 25//12(8-0), 25//16(8-0), 17(8-0),
subject to the conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1029 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2517 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Kamboj & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Gurvinder Singh authorized to act as attorney on behalf of the firm.
111
(vii) Self declaration by Sh. Gurvinder Singh partner of the firm to the effect that they will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Gurvinder Singh partner of M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2038 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 50,387 Ton over a
period of 3 years in an area of 1.85 hectares outside the river bed in the revenue
estate of Village Lokhe Khurd, Tehsil Zira, District Ferozpur in H.B. no. 11, Khasra
no.: 9//21(6-16), 18//10(6-16), 25//12(8-0), 25//16(8-0), 17(8-0), in the name of
contractor M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District
Fazilka for a period upto 31.10.2016 (validity period of the contract) subject to
the same conditions as mentioned in the environmental clearance issued vide no.
2038 dated 31.03.2015.
Item No.82.14: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Nijamdinwala, Tehsil & District Ferozpur in the name of M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil
Jalalabad, District Fazilka.
112
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2196 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @
2,08,202 Ton/year in an area of 4.76 hectares from the Satluj river bed in the
revenue estate of Village Nijamdinwala, Tehsil & District Ferozpur in H.B. no. 51,
Khasra no.: 14//18(8-0), 23(8-0), 17(7-8), 24(8-0), 19(8-0), 20(8-0), 21(8-0),
22(8-0), 19//1(8-0), 2(8-0), 3(8-0), 4(7-8), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1028 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2507 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Kamboj & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Gurvinder Singh authorized to act as attorney on behalf of the firm.
(vii) Self declaration by Sh. Gurvinder Singh partner of the firm to the effect that they will comply with the conditions of environmental clearance.
113
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer,
Ferozepur.
(ii) Sh. Gurvinder Singh, partner of M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2196 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 2,08,202 Ton/year
in an area of 4.76 hectares from the Satluj river bed in the revenue estate of
Village Nijamdinwala, Tehsil & District Ferozpur in H.B. no. 51, Khasra no.:
14//18(8-0), 23(8-0), 17(7-8), 24(8-0), 19(8-0), 20(8-0), 21(8-0), 22(8-0), 19//1(8-
0), 2(8-0), 3(8-0), 4(7-8), in the name of contractor M/s Kamboj & Company,
V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka for a period upto 31.10.2016
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2196 dated 31.03.2015.
Item No.82.15: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Kohala, Tehsil Zira, District Ferozpur in the name of M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District
Fazilka.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
114
2027 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 24,166
Ton over a period of 3 years in an area of 0.80 hectares outside the river bed in
the revenue estate of Village Kohala, Tehsil Zira, District Ferozpur in H.B. no. 6,
Khasra no.:49//21(8-0), 22(8-0), subject to the conditions including the following
condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1030 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2521 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Kamboj & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Gurvinder Singh authorized to act as attorney on behalf of the firm.
(vii) Self declaration by Sh. Gurvinder Singh partner of the firm to the effect that they will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
115
(ii) Sh. Gurvinder Singh, Partner M/s Kamboj & Company, V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2027 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 24,166 Ton over a
period of 3 years in an area of 0.80 hectares outside the river bed in the revenue
estate of Village Kohala, Tehsil Zira, District Ferozpur in H.B. no. 6, Khasra
no.:49//21(8-0), 22(8-0), in the name of contractor M/s Kamboj & Company,
V.P.O. Aamir Khas, Tehsil Jalalabad, District Fazilka for a period upto 31.10.2016
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2027 dated 31.03.2015.
Item No.82.16: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Shekhpur Takhtuwala, Tehsil Zira, District Ferozpur in the name of Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No.
2539, Sector 40-C, Chandigarh.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2016 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @
1,21,224 Ton over a period of 3 years in an area of 4.052 hectares outside the river
bed in the revenue estate of Village Shekhpur Takhtuwala, Tehsil Zira, District
Ferozpur in H.B. no. 175, Khasra no.:23//4/2(5-8), 6(8-0), 7/1(5-8), 3(8-0), 4/1(2-
0), 7/2(2-0), 8(8-0), 35//2(7-0), 9(4-0), 29//22(7-11), 30//25(2-0), 14(2-0),
116
42//3/2(4-0), 6(8-0), 7(8-0), subject to the conditions including the following
condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1031 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2493 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Sikkander Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Sikander Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
117
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2016 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 1,21,224 Ton over
a period of 3 years in an area of 4.052 hectares outside the river bed in the
revenue estate of Village Shekhpur Takhtuwala, Tehsil Zira, District Ferozpur in
H.B. no. 175, Khasra no.:23//4/2(5-8), 6(8-0), 7/1(5-8), 3(8-0), 4/1(2-0), 7/2(2-0),
8(8-0), 35//2(7-0), 9(4-0), 29//22(7-11), 30//25(2-0), 14(2-0), 42//3/2(4-0), 6(8-
0), 7(8-0), in the name of contractor Sh. Sikander Singh S/o Sh. Mangat Singh, r/o
House No. 2539, Sector 40-C, Chandigarh for a period upto 31.10.2016 (validity
period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2016 dated 31.03.2015.
Item No.82.17: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Malluwala, Tehsil Zira, District Ferozpur in the name of Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House
No. 2539, Sector 40-C, Chandigarh.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2183 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 59,832
Ton over a period of 3 years in an area of 1.368 hectares outside the river bed in
the revenue estate of Village Malluwala, Tehsil Zira, District Ferozpur in H.B. no.
173, Khasra no.: 24//6/2(3-0), 15(3-7), 25//1(8-0), 2(6-6), 3(0-14), 9(0-7), 10(5-
13), 11(0-3), subject to the conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his
118
name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1033 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2493 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Sikkander Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Sikander Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
119
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2183 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 59,832 Ton over a
period of 3 years in an area of 1.368 hectares outside the river bed in the revenue
estate of Village Malluwala, Tehsil Zira, District Ferozpur in H.B. no. 173, Khasra
no.: 24//6/2(3-0), 15(3-7), 25//1(8-0), 2(6-6), 3(0-14), 9(0-7), 10(5-13), 11(0-3) in
the name of contractor Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No.
2539, Sector 40-C, Chandigarh for a period upto 31.10.2016 (validity period of
the contract) subject to the same conditions as mentioned in the environmental
clearance issued vide no. 2183 dated 31.03.2015.
Item No.82.18: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Kamawali, Tehsil & District Fazilka in the name of Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector
40-C, Chandigarh.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2060
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 43,157 Ton
over a period of 3 years in an area of 1.11 hectares outside the river bed in the
revenue estate of Village Kamawali, Tehsil & District Fazilka in H.B. no. 297, Khasra
no.:46M21(7-7), 47M23(7-7), 25 (7-7), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
395 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
120
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2511 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Sikkander Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Sikander Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2060 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 43,157 Ton over a
period of 3 years in an area of 1.11 hectares outside the river bed in the revenue
121
estate of Village Kamawali, Tehsil & District Fazilka in H.B. no. 297, Khasra
no.:46M21(7-7), 47M23(7-7), 25 (7-7) in the name of contractor Sh. Sikander
Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh for a
period upto 31.10.2016 (validity period of the contract) subject to the same
conditions as mentioned in the environmental clearance issued vide no. 2060 dated
31.03.2015.
Item No.82.19: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Gagan Ke, Tehsil & District Fazilka in the name of Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539,
Sector 40-C, Chandigarh.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2071
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 49,378 Ton
over a period of 3 years in an area of 1.27 hectares outside the river bed in the
revenue estate of Village Gagan Ke, Tehsil & District Fazilka in H.B. no. 291, Khasra
no.:19/2(3-11), 22(4-2), 16(5-4), 17/1(6-12), 24/2(3-15), 25(2-4), subject to the
conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
393 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
122
(ii) Copy of letter no. 2511 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Sikkander Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Sikander Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh.
The SEIAA observed that environmental clearance was granted for
the for carrying out mining of minor minerals (Sand) @ 49,378 Ton over a period
of 3 years in an area of 1.27 hectares outside the river bed in the revenue estate of
Village Gagan Ke, Tehsil & District Fazilka in H.B. no. 291, Khasra no.:19/2(3-11),
22(4-2), 16(5-4), 17/1(6-12), 24/2(3-15), 25(2-4) whereas HB No. 291 is in respect
of Village Badha, Tehsil & District Fazilka.
The SEIAA scrutinized the environmental clearance application and
observed that in the application HB No. 291 has been mentioned and all the
documents attached with the application are of Village Badha having HB No. 291.
To this observation of SEIAA, GMDIC, Fazilka clarified that the HB No.
291 is of Village Badha and inadvertently this HB Number was mentioned in the
application and documents related to Badha site were attached with the application
for mining site of Village Gagan Ke. In fact, HB Number of Village Gagan Ke is 295.
The SEIAA observed that environmental clearance application has
been appraised and processed with documents not relating to Village Gagan Ke and
needs to be withdrawn.
123
After detailed deliberations, the SEIAA decided to withdraw the
environmental clearance granted vide no. 2071 dated 31.03.2015 for carrying out
mining of minor minerals (Sand) @ 49,378 Ton over a period of 3 years in an area
of 1.27 hectares outside the river bed in the revenue estate of Village Gagan Ke,
Tehsil & District Fazilka in H.B. no. 291, Khasra no.:19/2(3-11), 22(4-2), 16(5-4),
17/1(6-12), 24/2(3-15), 25(2-4) due to above said reasons.
Item No.82.20: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Hastan Kalan, Tehsil & District Fazilka in the name of Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector
40-C, Chandigarh.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2061
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 82,944
Ton/year in an area of 3.84 hectares from the Satluj river bed in the revenue
estate of Village Hastan Kalan, Tehsil & District Fazilka in H.B. no. 298, Khasra
no.:132M//1 (8-0), 9 (8-0), 10(8-0), 12(8-0),, 20(4-0), 12(6-0), 19(8-0), 21(8-0),
123M//19(8-0), 22(8-0),, 132M//2(8-0), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
397 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
124
(ii) Copy of letter no. 2511 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Sikkander Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Sikander Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Sikander Singh S/o Sh. Mangat Singh, r/o House No. 2539, Sector 40-C, Chandigarh.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2061 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 82,944 Ton/year in
an area of 3.84 hectares from the Satluj river bed in the revenue estate of Village
Hastan Kalan, Tehsil & District Fazilka in H.B. no. 298, Khasra no.:132M//1 (8-0), 9
(8-0), 10(8-0), 12(8-0), 20(4-0), 12(6-0), 19(8-0), 21(8-0), 123M//19(8-0), 22(8-
0),, 132M//2(8-0) in the name of contractor Sh. Sikander Singh S/o Sh. Mangat
Singh, r/o House No. 2539, Sector 40-C, Chandigarh for a period upto 31.10.2016
125
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2061 dated 31.03.2015.
Item No.82.21: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Ferozepur for mining of minor minerals in the revenue estate of Village Bula, Tehsil Zira, District Ferozpur in the name of Sh. Hardip Singh S/o Sh. Pargat Singh, r/o Village Nuhon, P.O.
Ghanauli, District Roop Nagar.
The General Manager-Cum-Mining Officer, Ferozepur, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2172 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 13,778
Ton over a period of 3 years in an area of 0.6 hectares outside the river bed in the
revenue estate of Village Bula, Tehsil Zira, District Ferozpur in H.B. no. 162, Khasra
no.: 15//3 (4-0), 6//22/1(5-4), 22/2(2-17), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Ferozepur vide letter
no. 1032 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2513 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Friends & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
126
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Hardip Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Ferozepur.
(ii) Sh. Hardip Singh S/o Sh. Pargat Singh, r/o Village Nuhon, P.O. Ghanauli, District Roop Nagar.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Ferozepur vide no. 2172 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 13,778 Ton over a
period of 3 years in an area of 0.6 hectares outside the river bed in the revenue
estate of Village Bula, Tehsil Zira, District Ferozpur in H.B. no. 162, Khasra no.:
15//3 (4-0), 6//22/1(5-4), 22/2(2-17) in the name of contractor Sh. Hardip Singh
S/o Sh. Pargat Singh, r/o Village Nuhon, P.O. Ghanauli, District Roop Nagar for a
period upto 31.10.2016 (validity period of the contract) subject to the same
conditions as mentioned in the environmental clearance issued vide no. 2172 dated
31.03.2015.
Item No.82.22: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Mohar Singh Wala, Tehsil Jalalabad, District Fazilka in the name of
127
Sh. Hardip Singh S/o Sh. Pargat Singh, r/o Village
Nuhon, P.O. Ghanauli, District Roop Nagar.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2093
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 53,265 Ton
over a period of 3 years in an area of 1.37 hectares outside the river bed in the
revenue estate of Village Mohar Singh Wala, Tehsil Jalalabad, District Fazilka in
H.B. no. 356, Khasra no.61M//16/2(4-0), 17/2(4-0), 18/2(3-2), 25/1(4-11),
62M20/2(4-0), 21/1(4-0), 6M21/2(4-0), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
392 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2515 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Friends & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Self declaration by Sh. Hardip Singh to the effect that he is the sole owner of the mining site and he will comply with the conditions of environmental clearance.
128
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Fazilka. (ii) Sh. Hardip Singh S/o Sh. Pargat Singh, r/o Village Nuhon, P.O.
Ghanauli, District Roop Nagar.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Fazilka vide no. 2093 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 53,265 Ton over a period of 3
years in an area of 1.37 hectares outside the river bed in the revenue estate of
Village Mohar Singh Wala, Tehsil Jalalabad, District Fazilka in H.B. no. 356, Khasra
no.61M//16/2(4-0), 17/2(4-0), 18/2(3-2), 25/1(4-11), 62M20/2(4-0), 21/1(4-0),
6M21/2(4-0) in the name of contractor Sh. Hardip Singh S/o Sh. Pargat Singh, r/o
Village Nuhon, P.O. Ghanauli, District Roop Nagar for a period upto 31.10.2016
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2093 dated 31.03.2015.
Item No.82.23: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Badha Tehsil & District Fazilka in the name of M/s Friends & Co., Village Rampura, Tehsil & District Fazilka.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2104
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 1,85,030 Ton
over a period of 3 years in an area of 4.759 hectares outside the river bed in the
revenue estate of Village Badha, Tehsil & District Fazilka in H.B. no. 291, Khasra
129
no.: 11m6 (1-6), 7(8-0), 8(8-0), 9(8-0), 10/1(3-1), 14(8-13), 6m8(5-14), 5m1/2(2-
0), 2(3-0), 3(7-7), 5(4-0), 2(4-7), 2m22(4-0), 5m5(4-0), 4m2(1-5), 5m4(6-12),
4m1(8-0), 2m23/1(1-15), 23/1(5-1), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
396 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2524-25 dated 30.06.2011 issued by GMDIC, Ferozepur to Sh. Hardip Singh vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Iqwak Singh has been appointed as attorney to work on behalf of the partnership firm.
(vii) Self declaration by Sh. Iqwak Singh to the effect that he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Fazilka.
(ii) Iqbak Singh, Partner M/s Friends & Co., Village Rampura, Tehsil & District Fazilka.
130
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Fazilka vide no. 2104 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 1,85,030 Ton over a period of 3
years in an area of 4.759 hectares outside the river bed in the revenue estate of
Village Badha, Tehsil & District Fazilka in H.B. no. 291, Khasra no.: 11m6 (1-6),
7(8-0), 8(8-0), 9(8-0), 10/1(3-1), 14(8-13), 6m8(5-14), 5m1/2(2-0), 2(3-0), 3(7-7),
5(4-0), 2(4-7), 2m22(4-0), 5m5(4-0), 4m2(1-5), 5m4(6-12), 4m1(8-0), 2m23/1(1-
15), 23/1(5-1) in the name of contractor M/s Friends & Co., Village Rampura,
Tehsil & District Fazilka for a period upto 31.10.2016 (validity period of the
contract) subject to the same conditions as mentioned in the environmental
clearance issued vide no. 2104 dated 31.03.2015.
Item No.82.24: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Rukhna Qasim, Tehsil Jalalabad, District Fazilka in the name of M/s
Friends & Co., Village Rampura, Tehsil & District Fazilka.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2149
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 43,274 Ton
over a period of 3 years in an area of 1.113 hectares outside the river bed in the
revenue estate of Village Rukhna Qasim, Tehsil Jalalabad, District Fazilka in H.B. no.
218, Khasra no.:29M//16(8-0), 25(4-0), 30M//2(2-0), 11(8-0), subject to the conditions
including the following condition:
131
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
398 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2519 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Friends & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Iqwak Singh has been appointed as attorney to work on behalf of the partnership firm.
(vii) Self declaration by Sh. Iqwak Singh to the effect that he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Fazilka.
(ii) Sh. Iqbak Singh, Partner of M/s Friends & Co., Village Rampura, Tehsil & District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
132
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Fazilka vide no. 2149 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 43,274 Ton over a period of 3
years in an area of 1.113 hectares outside the river bed in the revenue estate of
Village Rukhna Qasim, Tehsil Jalalabad, District Fazilka in H.B. no. 218, Khasra
no.:29M//16(8-0), 25(4-0), 30M//2(2-0), 11(8-0) in the name of contractor M/s
Friends & Co., Village Rampura, Tehsil & District Fazilka for a period upto
31.10.2016 (validity period of the contract) subject to the same conditions as
mentioned in the environmental clearance issued vide no. 2149 dated 31.03.2015.
Item No.82.25: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Fazilka for mining of minor minerals in the revenue estate of Village Abdul Khalik Alias Miami Basti, Tehsil & District Fazilka in the name of M/s Friends & Co., Village Rampura, Tehsil & District
Fazilka.
The General Manager-Cum-Mining Officer, Fazilka, was granted
environmental clearance under EIA notification dated 14.09.2006 vide no. 2082
dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 1,88,568 Ton
over a period of 3 years in an area of 4.85 hectares outside the river bed in the
revenue estate of Village Abdul Khalik Alias Miami Basti, Tehsil & District Fazilka in H.B.
no. 293, Khasra no.:12/7/1(7-10), 8(8-0), 9(8-0), 13(8-0), 14(8-0), 15(8-0), 39/5(8-0),
6(8-0), 7(8-0), 8(8-0), 13/2(7-2), 14(9-13), subject to the conditions including the
following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his
133
name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Fazilka vide letter no.
394 dated 06.04.2015 has requested to transfer the Environmental Clearance for
the above noted mining site in the name of above mentioned person for a period
upto 31.10.2016. The GMDIC has submitted the following documents alongwith
the request:
(i) Copy of letter no. 11759-B dated 30.06.2011 issued by Director of Industries & Commerce, Punjab, Chandigarh to GMDIC, Ferozepur vide which contract of the mining site has been allotted.
(ii) Copy of letter no. 2524-25 dated 30.06.2011 issued by GMDIC, Ferozepur to M/s Friends & Co. vide which validity of the contract period was extended from 01.07.2011 to 30.06.2014.
(iii) Copy of letter no. 5218-B dated 30.06.2014 issued by Govt. of Punjab, Department of Industries & Commerce, Punjab to GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.07.2014 to 31.03.2016.
(iv) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(v) Partnership Deed dated 15.06.2011.
(vi) Power of Attorney dated 15.06.2011 vide which Sh. Iqwak Singh has been appointed as attorney to work on behalf of the partnership firm.
(vii) Self declaration by Sh. Iqwak Singh to the effect that he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Gursharan Singh, General Manager-cum-Mining Officer, Fazilka.
(ii) Iqbak Singh Partner of M/s Friends & Co., Village Rampura, Tehsil & District Fazilka.
The SEIAA observed that as per EIA notification dated 14.09.2006, the
environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
134
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Fazilka vide no. 2082 dated 31.03.2015
for carrying out mining of minor minerals (Sand) @ 1,88,568 Ton over a period of 3
years in an area of 4.85 hectares outside the river bed in the revenue estate of
Village Abdul Khalik Alias Miami Basti, Tehsil & District Fazilka in H.B. no. 293,
Khasra no.:12/7/1(7-10), 8(8-0), 9(8-0), 13(8-0), 14(8-0), 15(8-0), 39/5(8-0), 6(8-
0), 7(8-0), 8(8-0), 13/2(7-2), 14(9-13) in the name of contractor M/s Friends &
Co., Village Rampura, Tehsil & District Fazilka for a period upto 31.10.2016
(validity period of the contract) subject to the same conditions as mentioned in the
environmental clearance issued vide no. 2082 dated 31.03.2015.
Item No.82.26: Regarding transfer of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Amritsar for mining of minor minerals in the revenue estate of Village Khanpur, Tehsil Baba Bakala, District Amritsar in the name of Sh. Parshant Joshi S/o Sh. Lalit Joshi, 5-A, Agar Nagar
Extension, Ludhiana.
The General Manager-Cum-Mining Officer, Amritsar, was
granted environmental clearance under EIA notification dated 14.09.2006 vide no.
2149 dated 31.03.2015 for carrying out mining of minor minerals (Sand) @ 35,381
Ton/year in an area of 0.91 hectares from the Beas river bed in the revenue estate
of of Village Khanpur, Tehsil Baba Bakala, District Amritsar in H.B. no. 3, Khasra no.
205/23(8-0), 24(9-0), subject to the conditions including the following condition:
"The Mining Officer may apply for transfer of environmental clearance under EIA notification dated 14.09.2006 to the contractor/lessor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the lessor/contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance".
Now, the General Manager-cum-Mining Officer, Amritsar vide letter
no. 2156 dated 06.04.2015 has requested to transfer the Environmental Clearance
for the above noted mining site in the name of above mentioned person for a
135
period upto 31.10.2016. The GMDIC has submitted the following documents
alongwith the request:
(i) Copy of letter no. 5821 dated 29.06.2011 issued by GMDIC, Amritsar to Sh. Parshant Joshi vide which contract of the mining site has been allotted from 01.07.2011 to 30.06.2014
(ii) Copy of letter no. 1126-A dated 02.02.2015 issued by Director Mining, GMDIC, Ferozepur and others vide which validity of the contract period was extended from 01.04.2016 to 31.10.2016.
(iii) Self declaration by Sh. Parshant Joshi to the effect that he is sole owner of the mining site and he will comply with the conditions of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by the following:
(i) Sh. Sukhpal Singh, Functional Manager O/O General Manager-cum-Mining Officer, Amritsar.
(ii) Sh. Parshant Joshi S/o Sh. Lalit Joshi, 5-A, Agar Nagar Extension, Ludhiana.
Sh. Sukhpal Singh, Functional Manager O/O General Manager-cum-
Mining Officer, Amritsar submitted the authorization letter vide which he has been
authorized to attend the meeting of SEIAA. The above mentioned document taken
on record by the SEIAA.
The SEIAA observed that as per EIA notification dated 14.09.2006,
the environmental clearance granted for a specific project or activity to an applicant
can be transferred during its validity to another legal person entitled to undertake
the project or activity on application by the transferor, or by the transferee with a
written “no objection” by the transferor, to, and by the regulatory authority
concerned, on the same terms and conditions under which the prior environmental
clearance was initially granted, and for the same validity period. No reference to
the State Level Expert Appraisal Committee concerned is necessary in such cases.
In compliance to said provision of the EIA notification dated
14.09.2006, the SEIAA decided to transfer the environmental clearance granted to
the General Manager- Cum-Mining Officer, Amritsar vide no. 2149 dated
31.03.2015 for carrying out mining of minor minerals (Sand) @ 35,381 Ton/year in
an area of 0.91 hectares from the Beas river bed in the revenue estate of of Village
Khanpur, Tehsil Baba Bakala, District Amritsar in H.B. no. 3, Khasra no. 205/23(8-
136
0), 24(9-0) in the name of contractor Sh. Parshant Joshi S/o Sh. Lalit Joshi, 5-A,
Agar Nagar Extension, Ludhiana for a period upto 31.10.2016 (validity period of
the contract) subject to the same conditions as mentioned in the environmental
clearance issued vide no. 2149 dated 31.03.2015.
137
Item No.82.27: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for construction of a commercial project namely “Chandigarh Citi Center” at Zirakpur, Tehsil Derabassi, Distt. Mohali by M/s Citi Center Developers.
The SEIAA observed that:
M/s Citi Center Developers has applied for obtaining the
Environmental Clearance under EIA notification dated 14.09.2006 for construction
of a commercial project namely “Chandigarh Citi Center” at Zirakpur, Tehsil
Derabassi, Distt. Mohali. The project is covered under category 8 (a) of the
Schedule appended to the said notification.
2. The case was placed in the agenda of the 96th meeting of SEAC held on
23.07.2014. But no one from the project proponent attended the said
meeting.
In view of above, the SEAC decided to defer the case in light of Office
Memorandum dated 25.02.2010 of MoEF, Govt. of India.
The case was considered by the SEAC in its 97th meeting held on
28.07.2014, which was attended by the following:
(i) Sh. Raj Kumar, General Manager (Technical) of the promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental
Consultant of the promoter company.
Sh. Raj Kumar, General Manager (Technical) and Sh. Deepak Gupta
Environmental Consultant informed that 1% of the construction activities of the
proposed project have already been completed at the site.
The SEAC observed that the case is required to be dealt as per the
procedure mentioned in the Office Memorandum dated 12.12.2012 of the Ministry
of Environment & Forests as amended on 27.06.2013 since the promoter company
has violated the provisions of EIA notification dated 14.09.2006 by starting
construction of the project without obtaining environmental clearance under the
said notification.
After detailed deliberations, the SEAC decided as under:
138
(ii) To forward the case to SEIAA with the recommendation to ask the
project proponent to submit a formal resolution passed by the Board
of Directors of the Company or the Managing Committee / CEO of the
Society, Trust, partnership / individually owned concern, within 60
days, mentioning that violations will not be repeated in future and in
the meantime, the project may be delisted. In the eventuality of not
having any response from the project proponent within the prescribed
limit of 60 days, the project file may be closed.
(ii) To recommend to SEIAA:
For initiating credible action against the project proponent /
responsible persons / promoter company under the
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
For issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance under EIA notification dated
14.09.2006 is obtained.
The project proponent was requested by the SEIAA vide letter No.
2515-23 dated 14.08.2014 to attend its 68th meeting on 23.08.2014, which was
attended by the following on behalf of the project proponent:
(i) Sh. Raj Kumar, General Manager (Technical) of the promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the promoter company.
The project proponent informed that 1.5% of construction has
already been completed. The foundations have been laid and the slab of the lower
ground floor is under progress.
After detailed deliberations, the SEIAA decided as under:
a) To send the case to the Govt. of Punjab, Department of Science,
Technology & Environment:
For initiating credible action against project proponent /
139
responsible persons / promoter company under the
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
For issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance under EIA notification dated
14.09.2006 is obtained.
b) To ask the project proponent to submit a formal resolution passed by
the Board of Directors of the Company or the Managing Committee /
CEO of the Society, Trust, partnership / individually owned concern,
within 60 days, mentioning that violations will not be repeated in
future and in the meantime, the project may be delisted. In the
eventuality of not having any response from the project proponent
within the prescribed limit of 60 days, the project file may be closed.
c) To inform the project proponent that the application for
environmental clearance under EIA Notification dated 14.09.2006 will
be considered only after the action is initiated by the Govt. of Punjab,
Department of Science, Technology & Environment for violating the
provisions of the said notification due to start of construction work of
the project without obtaining environmental clearance & resolution as
at (b) above is received within the stipulated period.
d) To ask the Punjab Pollution Control Board to verify and send the
status of construction of the project at site.
Thereafter, the Govt. of India, Ministry of Environment & Forests, New Delhi
has also issued notification No. S.O. 638 (E) dated 28.02.2014 and the same is
reproduced as under:
In exercise of the powers conferred by clause (a) of section 19 of the
Environment (Protection) Act, 1986 (29 of 1986), the Central
Government hereby authorises the Authority or Officer mentioned in
column (2) of the Table hereto for the purpose of the said section
140
with the jurisdiction mentioned against each of them in column (3) of
that table:
Table
Sr. No.
Authority/Officer Jurisdiction
1. State or Union Territory level Environment Impact Assessment Authority (SEIAA) constituted by the Central Government under sub-section (3) of section 3 of the Environment (Protection) Act, 1986.
Whole of State or Union Territory.
2. Any Director, Conservator of Forests or Additional Principal Chief Conservator of Forests Posted in any of the Regional Offices of the Ministry of Environment and Forests Environment and Forests (MoEF).
Jurisdiction of the Regional Office as decided by the Ministry of Environment & Forests.
Accordingly, the Govt. of Punjab, Deptt. of Science, Technology &
Environment vide Memo No. 302633/1 dated 08.09.2014 has mentioned that as
per the notification dated 06.06.2014, the PPCB has been designated as Nodal
Agency for providing Secretariat/logistic and financial support to SEIAA/SEAC. Now,
in addition to this, the PPCB shall provide the following services to SEIAA/SEAC as
monitoring mechanism:
(i) The task of visiting the sites of various projects, verifying the compliance
of conditions stipulated in the environmental clearances and sending
reports to the SEIAA for taking further necessary action.
(ii) PPCB should regularly monitor all the projects for which environmental
clearances have been issued by SEIAA at reasonable intervals.
(iii) The task of ensuring compliance and sending the compliance report of
directions issued by SEIAA u/s 5 of Environment (Protection) Act, 1986
as delegated by MoEF vide notification No. S.O. 637 (E) dated
28.02.2014.
(iv) Once the decision regarding initiation of action against the project
proponent for violating the conditions of environmental clearance and /
or provisions of EIA Notification dated 14.09.2006 in exercise of powers
delegated under clause (a) of Section 19 of Environment (Protection)
141
Act, 1986 is taken by SEIAA, the legal process such as filing a complaint
in the Competent Court of Law and its follow up etc.
The matter was deliberated upon by the SEIAA in its 70th meeting
held on 16.09.2014 and noted that as per the opinion given by the Senior Law
Officer, Punjab Pollution Control Board, the SEIAA can exercise the powers u/s 5 of
Environment (Protection) Act, 1986 as delegated by MoEF vide notification No. S.O.
637 (E) dated 28.02.2014 for issuance of show cause notices and directions in all
the cases of violation(s) where competency to grant environmental clearance lies
with SEIAA including the cases where violation(s) has been committed by not
obtaining prior environmental clearance.
After detailed discussions, the SEIAA decided that:
(i) In future, all such cases of violation where credible action against the
project proponent is to be initiated & directions u/s 5 of Environment
(Protection) Act, 1986 are to be issued, instead of sending the
recommendations to State Govt., the decision be taken at SEIAA level.
Punjab Pollution Control Board shall be instructed to file a complaint against
the project proponent in a competent court of Law.
(ii) The cases where decision has already been taken to recommend to State
Govt. for initiation of credible action & issuance of directions u/s 5 of
Environment (Protection) Act, 1986 and the letters for the same are under
issue, be also sent to Punjab Pollution Control Board for initiating credible
action & directions u/s 5 of Environment (Protection) Act, 1986 be issued by
SEIAA.
Accordingly the Punjab Pollution Control Board was requested
to launch prosecution u/s 15, 16 read with section 19 of the Environment
(Protection) Act, 1986 against the project proponents and its responsible persons
bid letter no. 2875 dated 22.09.2014.
Now the Punjab Pollution Control Board has intimated that in
compliance to the orders of the SEIAA, a complaint has been filed u/s 15 and 16,
read with section 19 of Environment (Protection) Rules, 1986, in the Hon'ble Court
of Sub Divisional Magistrate, Dera Bassi by this office on 17/12/2014 against the
project proponent and the persons responsible for starting construction of project
without obtaining the environmental clearance under the EIA Notification dated
14/09/2006.
142
The case was considered by the SEAC in its 109th meeting held
on 20.02.2015, which was attended by the following on behalf of project
proponent:
(i) Sh. Anil Mehta, Liaison officer of promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the project proponent
Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental
Consultant of the project proponent presented the project proposal before the
SEAC as under:-
The total project area will be 31910 sqm and the total built up area will be
41000 sqm.
The layout plan has been approved by the MC, Zirakpur.
The total cost of the project will be Rs. 90 cores.
o The total water requirement for the project will be 117 KL/day, out of which
90 KL/day will be met through own tubewell and remaining 27 KL/day will
be met through recycling of treated wastewater.
o The total wastewater generation from the project will be 94 KL/day, which
will be treated in a STP to be installed within the project premises. The
project proponent has proposed to use 27 KL/day of treated wastewater for
flushing purpose, 1 KL/day will be used for irrigation of green area and
remaining 66 KL/day will be discharged to public sewer in summer season.
In winter season, 27 KL/day of treated wastewater will be used for flushing
purpose and remaining 67 KL/day will be discharged to public sewer. In
rainy season, 27 KL/day of treated wastewater will be used for flushing
purpose and remaining 67 KL/day will be discharged to public sewer. .
The M.C. Zirakpur, vide letter no. 546 dated 27.01.2014 has issued a
certificate to the effect that the MC has no objection for giving sewer
connection from its main sewer to project proponent, after deposition of
applicable connection charges and other requisite charges.
The project proponent has proposed to provide rain water harvesting wells
for recharging 6577 KL/annum of rain water into groundwater.
The total quantity of solid waste generation will be 425 kg/day, which will be
segregated at source as biodegradable and non-biodegradable components
143
as per the Municipal Solid Waste (Management & Handling) Rules, 2000.
The non-biodegradable and recyclable waste will be sold to the
authorized vendors and the biodegradable waste will be sent to approved
site.
The M.C. Zirakpur, vide letter no. 566 dated 27.01.2014 issued a certificate
to the effect that the solid waste to be generated from project site will be
taken care by MC, Zirakpur, after deposition of applicable charges.
The e-waste will be handled and managed as per the E-waste (Management
& Handling) Rules, 2011.
The total load of electricity required for group housing will be 1950 KW
which will be taken from the PSPCL. There is a proposal to install DG sets for
stand-by arrangement
The used oil from the D.G. sets will be stored in an isolated place and would
be sold out to the approved recyclers as per the provisions of the Hazardous
Waste (Management, Handling & Transboundary Movement), Rules, 2008.
The ambient air monitoring has been got done from M/s Chandigarh
Pollution Testing Laboratory and the analysis results indicate that the
concentration of various pollutants such as PM2.5, PM10, SO2, NO2 and CO
have been measured. Also, ambient noise monitoring has been got done
from the said firm and the analysis results indicate that the noise levels
during day and night times, have been measured in the range of 47.5 dB(A)
leq and 36.4 dB(A) leq, respectively, against the prescribed standards of 55
and 45 dB(A) leq.
GM (Projects), will be responsible for implementation of Environment
Management Plan during the construction phase and operational phase. Rs.
21.50 lacs will be incurred for implementation of EMP and Rs.17.5
lacs/annum will be incurred on account of recurring charges during the
construction phase. Rs.25.50 Lacs will be incurred as capital cost and Rs.
7.25 lacs/annum as recurring charges during operation phase.
The implementation of the CSR will be responsibility of Director of the
Company and Rs.7 Lacs have been earmarked for the following activities to
be undertaken under Corporate Social Responsibility:
o The management will give preference in the job to nearby area people.
144
o Blood donation camps and other health related camps will be organized
in the 5 Km area of the project.
o Carpeting of road of the village Bishangarh.
o Arrangements will be made for training to the youths of village bishangarh in vocational courses.
o Camps will be organized for awareness of cancer and other diseases
o Saplings will be distributed in the area. ( Within 10 Km)
o Toilet for girls in Govt. School.
Traffic Circulation System and disaster/risk management plan has been
prepared and submitted.
The project proponent marked the location of DG Sets,
transformers and other utilities on the layout plan during the meeting, which were
taken on record by the SEAC.
To a query raised by the SEAC, regarding treatment of
rainwater other than rooftop before recharging it into the ground water, the project
proponent submitted that adequate treatment will be provided as prescribed by the
CGWA.
To another query raised by the SEAC, regarding treatment of
biodegradable waste, the project proponent submitted that the biodegradable
waste will be treated at site using vermi technology.
The committee observed that the project proponent has not
submitted the requisite document from the MC mentioning quantity of sewage, as
per decision of combined meeting of SEIAA and SEAC held on 15.12.2014. The
project proponent requested to recommend the case to SEIAA and meanwhile he
will submit the requisite document.
The Committee observed that the project proponent has provided
adequate and satisfactory clarifications of the observations raised by it. Therefore,
the Committee awarded 'Silver Grading' to the project proposal and decided that
as and when the project proponent submit the requisite document from MC
Zirakpur and if the same is found in order and approved by the Chairman SEAC on
the case file of the project, the case be forwarded to the SEIAA with the
recommendation to grant environmental clearance to the project proponent for for
145
construction of a housing project namely “Chandigarh Citi Center” in an area of
31910 sqm having total built up area 41000 sqm, in the revenue estate at Zirakpur,
Tehsil Derabassi, Distt. Mohali of Village Bishangarh, Tehsil Derabassi, District
S.A.S. Nagar, subject to the following conditions in addition to the proposed
measures:
PART A – Specific conditions
I. Pre-Construction Phase
(i) “Consent to establish” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority before the start of any construction work at site.
(ii) All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.
(iii) A first aid room will be provided in the project both during construction and operation phase of the project.
(iv) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
(v) Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, disposal of waste water & solid waste in an environmentally sound manner, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project.
II. Construction Phase:
(i) All the topsoil excavated during construction activities should be stored for use in horticulture / landscape development within the project site.
(ii) Disposal of muck during construction phase should not create any adverse effect on the neighboring communities and be disposed off after taking the necessary precautions for general safety and health aspects of people with the approval of competent authority.
(iii) Construction spoils, including bituminous material and other hazardous material, must not be allowed to contaminate watercourses and the dump sites for such material must be secured, so that they should not leach into the groundwater.
(iv) Construction/provision of the STP, tubewell, DG Sets, Utilities etc, earmarked by the project proponent on the layout plan, should be made in the
146
earmarked area only. In any case the position/location of these utilities should not be changed later-on.
(xiv) Vehicles hired for bringing construction material to the site and other machinery to be used during construction should be in good condition and should conform to applicable air and noise emission standards.
(xv) Ambient noise levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
(xvi) Fly ash should be used as construction material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended on August, 2003 (This condition is applicable only if the project is within 100 Km of Thermal Power Station).
(xvii) Ready mixed concrete should be used in building construction as far as possible.
(xviii) Water demand during construction should be reduced by use of premixed concrete, curing agents and other best practices.
(xix) Separation of drinking water supply and treated sewage supply should be done by the use of different colours.
(xx) Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
(xxi) Adequate steps shall be taken to conserve energy by limiting the use of glass, provision of proper thermal insulation and taking measures as prescribed under the Energy Conservation Building Code.
(xxii) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
(xxiii) The diesel generator sets to be used during construction phase should be of low sulphur diesel type and should conform to the provisions of Environment (Protection) Act, 1986 prescribed for air and noise emission standards.
III. Operation Phase
ii) “Consent to operate” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority at the time of start of operation.
iii) The installation of sewage treatment plant (STP) and adequacy of disposal system should be certified by Punjab Pollution Control Board and a report in this regard should be submitted to the Ministry of Environment & Forests & State Level Environment Impact Assessment Authority before the project is commissioned for operation.
147
iv) The project proponent shall discharge not more than 66 KLD wastewater into sewer during summer season, 67 KLD wastewater into sewer during winter season and 67 KLD wastewater into sewer during rainy season.
v) The project proponent shall provide electromagnetic flow meter at the outlet of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing and for horticulture purpose/green etc. and shall maintain a record of readings of each such meter on daily basis.
vi) The position / location of the STP, tubewell, DG Sets, Utilities etc, installed by the project proponent as per the provisions made in the layout plan, should not be changed later-on under any circumstances.
vii) Adequate & appropriate pollution control measures should be provided to control fugitive emissions to be emitted within the complex.
viii) Adequate treatment facility for drinking water shall be provided, if required.
ix) The green belt along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential land use. The open spaces inside the plot should be suitably landscaped and covered with vegetation of indigenous species/variety.
x) The project proponent should take adequate and appropriate measures to contain the ambient air quality within the prescribed standards. The proposal regarding mitigation measures to be taken at site should be submitted to the Ministry of Environment & Forests/ State Level Environment Impact Assessment Authority within three months.
xi) Application of solar energy should be incorporated for illumination of common areas, lighting for gardens and street lighting in addition to provision for solar water heating.
xii) A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about machinery of air conditioning, lifts, lighting, building materials, R & U Factors etc. and submitted to the respective Regional office of MoEF, the Zonal Office of CPCB and the SPCB/SEIAA in three months time.
xiii) Environmental Management Cell shall be formed during operation phase which will supervise and monitor the environment related aspects of the project.
xiv) Ambient noise levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
xv) Separation of drinking water supply and treated sewage supply should be done by the use of different colors.
xvi) Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
xvii) The project proponent shall convert the bio-degrdable waste into compost and shall not dispose the waste in any other manner.
148
IV. Entire Life:
i) “Consent to operate” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974 and get it renewed from time to time and a copy of the same shall be submitted to the Ministry of Environment & Forests / State Level Environment Impact Assessment Authority.
ii) The project proponent shall discharge not more than 66 KLD wastewater into sewer during summer season, 67 KLD wastewater into sewer during winter season and 67 KLD wastewater into sewer during rainy season.
iii) The project proponent shall provide electromagnetic flow meter at the outlet of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing and for horticulture purpose/green etc. and shall maintain a record of readings of each such meter on daily basis.
iv) The position / location of the STP, tubewell, DG Sets, Utilities etc, installed by the project proponent as per the provisions made in the layout plan, should not be changed later-on under any circumstances.
v) Rainwater harvesting for roof run-off should be implemented. Before
recharging the roof run-off, pretreatment must be done to remove suspended matter, oil and grease. However, run off from gardens/green area/roads/pavements shall be connected with the ground water recharging system only after providing adequate treatment.
vi) The solid waste generated should be properly collected and segregated. The recyclable solid waste shall be sold out to the authorized vendors and inert shall be sent to disposal facility. The Bio-degradable solid waste shall be adequately treated with mechanical vermi composter to convert it into manure. Prior approval of competent authority should be obtained, if required.
vii) Hazardous waste/E-waste should be disposed off as per Rules applicable and with the necessary approval of the Punjab Pollution Control Board.
viii) Incremental pollution loads on the ambient air quality, noise and water quality should be periodically monitored.
ix) Traffic congestion near the entry and exit points from the roads adjoining the proposed project site must be avoided. Parking should be fully internalized and no public space should be utilized.
x) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
PART B – General Conditions :
149
IV. Pre-Construction Phase
i) This environmental clearance will be valid for a period of five years from the date of its issue or till the completion of the project, whichever is earlier.
ii) The environmental safeguards contained in the application of the promoter / mentioned during the presentation before State Level Environment Impact Assessment Authority/State Expert Appraisal Committee should be implemented in letter and spirit.
iii) All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest (Conservation) Act, 1980 and Wildlife (Protection) Act, 1972 etc. shall be obtained, by project proponents from the competent authorities including Punjab Pollution Control Board and from other statutory bodies as applicable. The project proponent shall also obtain permission from the NBWL, if applicable.
iv) The project proponent should advertise in at least two local newspapers widely circulated in the region, one of which shall be in the vernacular language informing that the project has been accorded environmental clearance and copies of clearance letters are available with the Punjab Pollution Control Board. The advertisement should be made within seven days from the day of issue of the clearance letter and a copy of the same should be forwarded to the Regional Office, Ministry of Environment & Forests, Chandigarh and SEIAA, Punjab.
v) These stipulations would be enforced among others under the provisions of Water (Prevention & Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981, Environmental (Protection) Act, 1986, the Public Liability (Insurance) Act, 1991 and EIA Notification, 2006.
vi) The project proponent shall obtain CLU from the competent authority, if any authority insists.
vii) The project proponent shall obtain permission from CGWA for abstraction of groundwater.
viii) AA copy of the clearance letter shall be sent by the proponent to concerned Panchayat, Zilla Parishad/ Municipal Corporation, Urban local body and the local NGO, if any, from whom suggestions / representations, if any, were received while processing the proposal. The clearance letter shall also be put on the website of the Company by the proponent.
ix) The State Environment Impact Assessment Authority reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
x) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
150
V. Construction Phase
i) The environmental safeguards contained in the application of the promoter / mentioned during the presentation before State Level Environment Impact Assessment Authority/State Expert Appraisal Committee should be implemented in letter and spirit.
ii) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
iii) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB, SPCB and SEIAA, Punjab.
iv) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh & State Level Environment Impact Assessment Authority, Punjab.
v) In the case of any change(s) in the scope of the project, the project would require a fresh appraisal by State Environment Impact Assessment Authority.
vi) Separate distribution pipelines be laid down for use of treated effluent / raw water for horticultural/gardening purposes with different colour coding.
vii) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
viii) The State Environment Impact Assessment Authority reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
ix) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
VI. Operation Phase
i) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent
151
until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
ii) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, the Zonal Office of CPCB, SPCB &SEIAA, Punjab.
iii) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh & State Level Environment Impact Assessment Authority, Punjab.
iv) The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, SEIAA, Punjab the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SO2, NOx, CO, Pb, Ozone (ambient air as well as stack emissions) shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
v) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
xi) The State Environment Impact Assessment Authority reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/ measures in a time bound and satisfactory manner.
xii) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
IV Entire Life
i) Environmental clearance is subject to final order of the Hon'ble Supreme Court of India in the matter of Goa Foundation Vs. Union of India in Writ Petition (Civil) No. 460 of 2004 as may be applicable to this project and decisions of any Competent Court, to the extent applicable.
ii) The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall
152
update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, SEIAA, Punjab, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SO2, NOx, CO, Pb, Ozone (ambient air as well as stack emissions) shall be monitored and displayed at a convenient location near the main gate of the company in the public domain.
iii) The project proponent shall adhere to the commitments made in the Environment Management Plan and Corporate Social Responsibility and shall spend the amount as proposed or atleast minimum required to be spent under the provisions of the Companies Act 1956, whichever is higher.
iv) The entire cost of the environmental management plan (i.e. capital cost as well as recurring cost) will continue to be borne by the project proponent until the responsibility of environmental management plan is transferred to the occupier/residents society under proper MOU after obtaining prior permission of the Punjab Pollution Control Board.
v) The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by mail) to the respective Regional office of MoEF, SEIAA, Punjab, the Zonal Office of CPCB and the SPCB.
vi) Officials from the Regional Office of Ministry of Environment & Forests, Chandigarh / State Level Environment Impact Assessment Authority / State Level Expert Appraisal Committee / Punjab Pollution Control Board who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents / data by the project proponents during their inspection. A complete set of all the documents submitted to State Environment Impact Assessment Authority should be forwarded to the CCF, Regional Office of Ministry of Environment & Forests, Chandigarh/State Level Environment Impact Assessment Authority.
xiii) The State Environment Impact Assessment Authority reserves the right to add additional safeguards/ measures subsequently, if found necessary, and to take action including revoking of the environmental clearance under the provisions of the Environmental (Protection) Act, 1986, to ensure effective implementation of the suggested safeguards/measures in a time bound and satisfactory manner.
xiv) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
Thereafter, the project proponent vide e-mail dated 20.02.2015 has
submitted copy of NOC issued by MC by Zirakpur vide letter no. 361 dated
20.02.2015 wherein, it has been mentioned that:
“It is certified that the commercial project of Chandigarh Citi
Center, VIP Road, Zirakpur is sanctioned by MC Zirakpur.
153
After the technical Clearance of Director Town Planning Local
Government Chandigarh MC, Zirakpur has no Objection for
giving sewerage connection from its main sewer of MC,
Zirakpur for Discharge of its Treated Water 70 KLD as per
your request after deposition of applicable connection
charges and other requisite charges of MC, Zirakpur & Water
Supply sewerage department of Zirakpur after completion of
project”.
As clear from above, the project proponent has submitted the
requisite document and the same is affirmative.
The above noted reply submitted by the project proponent has been
considered by the Chairman, SEAC and as per the decision taken by the SEAC in its
109th meeting, approval has been accorded for recommending the case to SEIAA
for grant of environmental clearance.
The case was considered by the SEIAA in its 82nd meeting held on
20.02.2015, which was attended by the following on behalf of project proponent:
(i) Sh. Anil Mehta, Liaison officer of promoter company
(ii) Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental Consultant of the project proponent.
Sh. Deepak Gupta of M/s Jalvayu Consultants, Environmental
Consultant of the project proponent presented the salient features of the project
before the SEIAA and requested to grant environmental clearance for the project.
The SEIAA observed that the case stands recommended by SEAC and
the Committee awarded ‘Silver Grading’ to the project proposal. The SEIAA
looked into the details of the case and was satisfied with the same. Therefore, the
Authority decided to grant environmental clearance to the project proponent for
construction of a commercial project namely “Chandigarh Citi Center” in an area of
31910 sqm having total built up area 41000 sqm, in the revenue estate at Zirakpur,
Tehsil Derabassi, Distt. Mohali of Village Bishangarh, Tehsil Derabassi, District
S.A.S. Nagar, subject to the conditions as proposed by the SEAC in addition to the
proposed measures.
154
Item No.82.28: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for construction of a Dental College namely “RAYAT & BAHRA DENTAL COLLEGE & HOSPITAL” at Village Daon Majra, Tehsil Kharar, District SAS Nagar, Punjab by M/s Rayat & Bahra Group of Institutes and Educational Charitable Society.
The SEIAA observed that:
1. M/s Rayat & Bahra Group of Institutes and Educational Charitable Society,
has applied vide letter No. RBGI/D (P)/14/537 dated 01.08.2014 (received
on 20.08.2014) for obtaining the environmental clearance as required under
EIA notification dated 14.09.2006 for construction of a Dental College
namely “RAYAT & BAHRA DENTAL COLLEGE & HOSPITAL” at Village
Daon Majra, Tehsil Kharar, District SAS Nagar. The project is covered under
category 8 (a) of the Schedule appended to the said notification. The details
of the project as per Form I & IA are as under:
The total project area is 8.96 acres having total built up area of 30,864 sqm.
The total cost of the project will be Rs.57 cores.
Total water requirement for the project will be 229 KLD, out of which 190
KLD will be met from own tubewell and remaining 39 KLD will be met from
treated wastewater.
The total wastewater generation from the project will be 187 KLD, which will
be treated in an STP to be installed within the project premises. The project
proponent has proposed to use 39 KLD of treated wastewater for flushing
purpose, 19 KLD for irrigation of green area @ 5.51 sqm and remaining 129
KLD will be used for plantation as per karnal technology in summer season.
In winter season, 39 KLD of treated wastewater will be used for flushing
purpose, 6 KLD will be used for irrigation of green area @ 1.81 sqm and
remaining 142 KLD will be used for plantation as per karnal technology. In
rainy season, 39 KLD of treated wastewater will be used for flushing
purpose, 1.7 KLD for irrigation of green area @ 0.51 sqm and remaining
146.3 KLD will be used for plantation as per karnal technology.
The total quantity of solid waste to be generated from the proposed project
has been estimated as 420 kg/day, which will be segregated into bio-
degradable and non-biodegradable waste as per the MSW Rules, 2000. The
155
bio-degradable will be treated through vermiculture. The non-biodegradable
and recyclable waste would be sold to the recyclers.
The quantity of BMW will be about 262 kg/day. It will be sent to BMWTF at
village Balyali, District Mohali, for final disposal.
The e-waste will be handled and managed as per the E-waste (Management
& Handling) Rules, 2011.
The used oil from the D.G. sets will be sold out to the registered recyclers as
per the provisions of the Hazardous Waste (Management, Handling &
Transboundary Movement), Rules, 2008.
The total load of electricity required for proposed project will be 2000 KW
which will be supplied by PSPCL. The project proponent has proposed to
install 2 DG sets having capacity 500KVA each, for backup power supply.
The other details of the project have been given in the Form 1 & 1A
submitted by the promoter and the details of the proposed project are as under:
1. Properly filled Form 1 & 1A Yes
2. Proof of ownership of land Submitted.
3. CLU status Permission for CLU has been granted
vide No. 9223 CTP(PB)/SP-432(M)
dated 27.11.2008 for an area
measuring 8.96 acres.
4. Approved Layout plan and
Building plan from Competent
Authority.
Building plan has been approved by
the Chief Town Planner, Chandigarh
vide no. 1357 CTP(Pb)/SC-122 dated
18.02.2010.
5. Topographical map of the area
showing Contour Plan.
Submitted.
6. Status of construction, if any,
alongwith photographs from all
the four sides.
Submitted, photographs showing that
construction has already been started at
site.
7. 500 meter radius map of the
area from periphery of project
site clearly indicating the various
industries (specifically red
category industries) and
structures lying in the area.
Submitted.
156
8. Site plan of the project showing
the following
i) Location of STP ; ii) Solid waste storage area. iii) Green belt iv) Parking space v) RWH and water recharge
pits vi) Fire fighting equipment
layout vii) First aid room
viii) Location of Tubewells
xi) Marked xii) Marked xiii) Marked xiv) Marked. xv) Marked. xvi) Marked xvii) Marked xviii) Marked
9. Permission of Competent
Authority for;
a) Water and Sewerage connection
b) Collection of Solid waste c) Use of groundwater
a) Not submitted.
b) Solid waste will be treated through vermi-culture
c) Applied for abstraction of groundwater vide letter no. Nil dated 08-07-2013 to CGWB, Chandigarh.
10. Water balance chart for summer,
rainy and winter seasons
indicating critical requirements.
Submitted.
11. Availability of adequate land for
use of treated sewage and
plantation.
Submitted
12. Analysis reports of ambient air,
ground water and noise levels
from NABL / MoEF accredited
laboratories.
The ambient air monitoring has been got done from M/s Chandigarh Pollution Testing Laboratory and the analysis results indicate that the concentration of various pollutants such as PM2.5, PM10, SO2, NO2 and CO have been measured. Also, ambient noise monitoring has been got done from the said firm and the analysis results indicate that the noise levels during day and night times, have been measured in the range of 41-44 dB(A)
157
leq and 35-38 dB(A) leq, respectively, against the prescribed standards of 55 and 45 dB(A) leq. The analysis report of groundwater has also been
submitted.
13. Quantification of energy saved
and renewable energy devices
used.
Submitted
14. Drawing showing plumbing
systems for use of fresh, treated
and hot water
Submitted.
15. Construction schedule
(PERT/CPM Chart)
Submitted.
16. Affidavits for ;
f) Constitution of Environment Monitoring Cell
g) Use of ready mix concrete or use of fly ash during construction.
h) To provide Fire Fighting System
i) To provide wind breaking curtains and water sprinkling system to minimize dust emissions.
j) To provide adequate safety measures for the construction workers during the construction phase.
Submitted
17 Environmental Management Plan indicating the following: a) All mitigation measures for
each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.
b) Compliance of various environmental regulations
Submitted
Submitted
158
c) Steps to be taken in case of emergency such as accidents at the site including fire.
d) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.
e) Capital & recurring cost for
the EMP per year and the
details of funds for the same.
f) Name of the individual
persons / organization, who
will be responsible for
implementation of EMP after
the lapse of the period for
which the project proponent
is responsible.
Submitted Director Planning of the Project proponent will be responsible for implementation of Environment Management Plan. Rs.8 lacs will be incurred on account of capital cost and Rs.2 lacs/annum will be incurred on account of recurring charges for implementation of EMP during construction phase. Rs.85 lacs will be incurred on account of capital cost and Rs.11.5 lacs/annum will be incurred on account of recurring charges for implementation of EMP during the operation phase.
Mr. Sandeep Puri (Director Planning)
18 Corporate Social Responsibility indicating various activities to be undertaken, provisions of funds for the same, the period for which the same is to be implemented and the person(s) responsible for the implementation of the same.
Rs.100 Lacs will be utilized for free
medical facility to poor people and
Mobile Ambulance for adjoining villages.
The implementation of the Corporate
Social Responsibility will be
responsibility of the Director (Planning)
of the Company.
19. NOC of the nearest Air Port issued by its Authority.
Not submitted.
20. Traffic Circulation System and
connectivity with a view to
ensure adequate parking, conflict
free movements, Energy efficient
Submitted.
159
Public Transport.
21. Disaster/Risk Assessment and
Management Plan
Submitted.
Sh. P. Thareja, Member (SEAC) said that he is associated with M/s
Rayat & Bahra Group of Institutes and Educational Charitable Society. Keeping in
view the likely conflict of interest, Sh. P. Thareja, recused himself from the
deliberations of SEAC on the case of “RAYAT & BAHRA DENTAL COLLEGE &
HOSPITAL” at Village Daon Majra, Tehsil Kharar, District SAS Nagar. The request of
Sh. P. Thareja, Member (SEAC) was acceded by Chair. Accordingly, the project
proposal was heard by other members of SEAC.
The case was considered by the SEAC. The following were present on
behalf of the project proponent:
(i) Sh. Sandeep Puri, Director (Planning)
(ii) Sh. Sital Singh, Environmental Consultant engaged by the
project proponent of M/s CPTL Enviro-Tech, Chandigarh
Sh. Sandeep Puri, Director (Planning) and Sh. Sital Singh
Environmental Consultant of the promoter company informed that 40% of the
construction activities on the proposed project have already been completed at
site.
To a query raised by SEAC regarding the start of construction activity
without obtaining environment clearance, the project proponent stated that the
permission from Ministry of Health & Family Welfare, Govt. of India was granted
subject to condition that initially for a period of 5 years classes may be conducted
in the premises of “Rayat Bahra Engineering College” situated across the project
site and for the training purposes of the students, agreement may be made with
the Government Hospital, Mohali. As the permission obtained from the Ministry of
Health & Family Welfare, Govt. of India, which was valid for a period of 5 years
was about to lapse, therefore, the construction was started without obtaining the
environment clearance.
160
To a query raised by SEAC regarding the status of environment clearance of
“Rayat Bahra Engineering College”, the project proponent informed that the total
built up area of the college is more than 20,000sqm and no environment clearance
has been obtained for the same.
The SEAC observed that the case is required to be dealt with as per
the procedure mentioned in the Office Memorandum dated 12.12.2012 of the
Ministry of Environment & Forests as amended on 27.06.2013 since the promoter
company has violated the provisions of EIA notification dated 14.09.2006 by
starting construction of the project without obtaining environmental clearance
under the said notification.
After detailed deliberations, the SEAC decided as under:
a) To forward the case to SEIAA with the following recommendations:
For initiating credible action against project proponent /
responsible persons / promoter company under the
Environment (Protection) Act, 1986 due to start of construction
activities of the project without obtaining Environmental
Clearance under EIA notification dated 14.09.2006.
For issuance of directions under Section 5 of the Environment
(Protection) Act, 1986 to restrain the promoter company from
carrying out any further construction activity of the project till
the environmental clearance under EIA notification dated
14.09.2006 is obtained.
To ask the project proponent to submit a formal resolution
passed by the Board of Directors of the Company or the
Managing Committee / CEO of the Society, Trust, partnership /
individually owned concern, within 60 days, stating therein that
the violations will not be repeated in future and in the
meantime, the project may be delisted. In the eventuality of
not having any response from the project proponent within the
prescribed limit of 60 days, the project file may be closed.
b) To write to the Punjab Pollution Control Board to verify and send the
status of construction of the project at site. Also, the Punjab Pollution
161
Control Board be asked to visit the site of “Rayat Bahra Engineering
College” to check whether the project is covered under the provisions
of EIA, Notification dated 14.09.2006 and send a detailed report in
this regard.
c) To write to the Punjab Pollution Control Board to check other such
projects which are covered under the EIA notification dated
14.09.2006 but have been established without obtaining the
environmental clearance and to send a detailed report in this regard
within one month.
As decided all the Regional Offices of PPCB were written vide letter
no. 3370-84 dated 14.11.2014 to check other such projects which are covered
under the EIA notification dated 14.09.2006 but have been established without
obtaining the environmental clearance and to send a detailed report in this
regard within one month.
As decided, PPCB, RO, Mohali was requested vide letter no. 2714
dated 10.09.2014.
Now, the PPCB, RO, Mohali vide letter No. 6742 dated 28.11.2014 has
submitted the following visit report:
“It is intimated that the site of the “Rayat & Bahra Dental College &
Hospital” was visited on 15.11.2014 and Sh. Sandeep Puri, Director of
the Institute was contacted. During visit, it was observed as under:
1. The project is a multi-speciality hospital and Dental College
located at NH-21 in the revenue estate of Village Daon Majra,
Tehsil Kharar, SAS Nagar.
2. The plot area of the project is 8.96 acres as per layout plan
approved by the CTP dated 18.02.2010.
3. The project proponent has constructed about 60% of the
project building.
4. No construction work of the rest of the project was going on.
5. The project proponent has started the construction of STP.
It is further intimated that as regard to check as to whether “Rayat &
Bahra Engineering College” is covered under EIA notification or not,
162
necessary documents are being procured from the promoter company
and a separate report will be sent in this regard in due course of
time.”
The case was considered by the SEIAA in its 82nd meeting held on
11.04.2015, which was attended by Sh. Sandeep Puri, Director (Planning) of the
promoter company.
Sh. Sandeep Puri, Director (Planning) informed that 40% of the
construction activities on the proposed project have already been completed at
site.
The project proponent also submitted a written request vide letter
dated 07.03.2015 stating that as per latest notification dated 22.12.2014 issued by
Ministry of Environment, Forests and Climate Change, New Delhi whereby the
project such as Industrial sheds, Schools, Colleges, Hostels for Educational
Institution have been exempted from obtaining environmental clearance.
Therefore, the project proponent has requested that before taking any incredible
action, the provisions of the above mentioned notification may kindly be viewed.
The project proponent has also submitted, the names of persons
responsible for the implementation/execution of the above referred project:
1. S. Gurvinder Singh Bahra (Chairman)
2. Col. (Retd.) Satindera Singh (Director, Admn.)
3. Sh. Vikas Sharma (Project Manager)
The SEIAA observed that as per latest notification dated 22.12.2014
only Industrial sheds, Schools, Colleges, Hostels for Educational Institution have
been exempted from obtaining environmental clearance, whereas, the proposed
institution is a Dental College and 350 bedded Multi-Specialty Hospital.
The SEIAA further observed that the list of names of responsible
persons submitted by the project proponent is incomplete and project proponent is
required to submit the names of all the persons responsible for the conduct of the
business of the company alongwith documentary evidence such as Memorandum of
Article & Association/Partnership Deed/Sole Prop. Affidavit etc.
The project proponent could not give satisfactory reply to the
observations of SEIAA.
163
The SEIAA observed that the project proponent is required to submit
the following documents:
(i) A formal resolution passed by the Board of Directors of the Company or to
the Managing Committee / CEO of the Society, Trust, partnership /
individually owned concern, mentioning that violations in respect of starting
construction activities without obtaining environmental clearance under EIA
notification dated 14.09.2006, are un-intentional and will not be repeated in
future.
(ii) Names of responsible persons against whom prosecution is to be launched
alongwith copy of Memorandum of Article & Association / partnership deed /
undertaking of sole proprietorship / list of Directors and names of other
persons responsible for managing the day-to-day affairs of the project.
After deliberations, the SEIAA decided to ask the project proponent to
submit the above mentioned documents within 15 days and to defer the case.
Item No.82.29: Regarding monitoring EIA Notification dated 14.09.2006, which fall in the competence of SEIAA, by the Ministry of Environment & Forests, New Delhi, for the months of February & March, 2015.
It was seen by the SEIAA.
The meeting ended a vote of thanks to the Chair. *******