PROCEDURE FOR MAKING APPLICATION FOR GRANT OF MEDIUM TERM OPEN ACCESS TO STS 1. OUTLINE 1.1. This Procedure is in accordance with the various provisions of the “Gujarat Electricity Regulatory Commission Terms and Conditions of Intra State Open Access, Notification No.3 of 2011 dtd.1-6-2011 hereinafter referred to as “the Regulations”. This procedure is to be read in conjunction with the Regulations. 1.2. This Procedure shall apply to the Applications made for Medium Term Open Access (MTOA) to the transmission lines or associated facilities of the intra-State transmission system (STS), received by the State Transmission Utility (STU) on or after the date notified by the Commission of coming into force of the Regulations. 1.3. The nodal agency for grant of MTOA shall be the STU i.e. Power Grid Corporation of India Ltd. The start date of MTOA can be any day of the month however, it shall not be earlier than 5 months and later than 1 year from the last day of the month in which application has been made. 1.4. MTOA is the right to use the STS for any period exceeding three months but not exceeding three years and shall be provided on the basis of availability of transmission capacity in the existing transmission system or transmission system under execution and likely to be available from the intended date of MTOA. In case of delay in commissioning of transmission system under execution considered for 1

PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

Embed Size (px)

Citation preview

Page 1: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

PROCEDURE FOR MAKING APPLICATION FOR GRANT OF MEDIUM TERM OPEN ACCESS TO STS

1. OUTLINE

1.1. This Procedure is in accordance with the various provisions of the “Gujarat ElectricityRegulatory Commission Terms and Conditions of Intra State Open Access, Notification No.3 of 2011 dtd.1-6-2011 hereinafter referred to as “the Regulations”. This procedure is to be read in conjunction with the Regulations.

1.2. This Procedure shall apply to the Applications made for Medium Term Open Access (MTOA) to the transmission lines or associated facilities of the intra-State transmission system (STS), received by the State Transmission Utility (STU) on or after the date notified by the Commission of coming into force of the Regulations.

1.3. The nodal agency for grant of MTOA shall be the STU i.e. Power Grid Corporation of India Ltd.

The start date of MTOA can be any day of the month however, it shall not be earlier than 5 months and later than 1 year from the last day of the month in which application has been made.

1.4. MTOA is the right to use the STS for any period exceeding three months but not exceeding three years and shall be provided on the basis of availability of transmission capacity in the existing transmission system or transmission system under execution and likely to be available from the intended date of MTOA. In case of delay in commissioning of transmission system under execution considered for such grant, which was beyond the control of the STU, then date of commencement of MTOA shall be extended upto the date of commercial operation of the above system..

1.5. No augmentation of transmission system is envisaged for granting MTOA. Construction of dedicated transmission line shall not be construed as augmentation of the transmission system.

1.6. After receipt of application, any change either in timeframe, drawl/injection point or increase in quantum of power shall require submission of a fresh application and the already made application shall stand disposed off and its application fees forfeited.

1

Page 2: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

A power transaction involving combination of both multiple injections and one drawl point in case the MTOA is sought by a single bulk consumer shall not require filing of separate applications.

2. APPLICANTS FOR MTOA

Application for MTOA can be made by a generating station including a captive generating plant, a consumer, an Electricity Trader or a distribution licensee, a State Government owning some quantum of power (like free power given to the State Government in which the hydro station is located, equity power given to a State for allowing a power station to be set up in the State), who desires to utilize STS for Intra state transfer of power, provided the power station from which the power is being sourced or the load, as the case may be, is already connected to the grid, whether the State grid or the intra-State grid, or is likely to get connected to the grid before the intended start date of MTOA. Documentary evidence needs to be submitted for establishing the condition of connectivity.

Note: (i) “consumer” means any consumer eligible to avail open access as specified by the

State Commission under sub-section (2) of section 42 of the Act.

(ii) If the Applicant is an Electricity Trader, it must have a valid trading license as per CERC (Procedure, Terms and Conditions for grant of Trading License and Related matter) Regulations, 2009 and subsequent amendments thereof. The Trader must have a valid contract for buying and selling of at least the same quantum of power and period of time for which Medium-term Open Access has been applied for.

(iii) There should exist required facility for metering and energy accounting at the point of injection and point of drawal, (iv) The trader shall submit a copy of valid trading license (v) All applicants shall submit an affidavit stating that they have a valid contract along with a copy of the contract.

2.1. A generating station, including captive generating plant or a bulk consumer, seeking MTOA to the intra-State transmission system cannot apply for medium-term open access without applying for connectivity, in case it is not already connected to the grid. It may, however, apply for connectivity and medium-term open access simultaneously. The connection, as finalized by STU, however, should be available from the intended start date of MTOA, for which documentary evidence

w.r.t. the condition of connectivity has to be submitted. Medium-term customer may arrange for execution of the dedicated transmission line at its own risk and cost before the start date of the MTOA.

2

Page 3: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

3

Page 4: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

3. INFORMATION / DATA TO BE FURNISHED ALONG WITH THEAPPLICATION

3.1. The information in the application shall be supported by a sworn in affidavit by the applicant as per the format given at FORMAT-MTOA-1.

3.2. The application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details like quantum of power to be injected at the suppliers point, details of injection & drawl points, time period from and upto which access is required, the source of power, clearance from respective SLDCs for intra state entities etc. and other details as sought in the application format.

4.0. APPLICATION FEE

4.1. An application for Medium-term open access shall be accompanied by a non-refundable application fee to be paid as per the following rate in favour of “Gujarat Energy Transmission Corporation Ltd.”S.No Quantum of Power to be injected/offtaken Non-refundable

into/from STS Application fee (Rs.)

1 Up to 100 MW 250002 More than 100 MW 50000

4.2. Application fees are to be paid through DD or directly credited to GETCOAccount electronically through RTGS (Real-time gross settlement) as per detailsgiven below:a) Payee :Gujarat Energy Transmission Corporation Limitedb) Name of Bank : Bank of Indiac) Branch :Alkapuri, Vadodarad) IFSC : BKID0002501e) A/c No. :250120100001167Provided that proof of payment directly credited to above GETCO account must be attached with the application.

4

Page 5: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

5. TIME LINES FOR MTOA

5.1. The start date of MTOA shall not be earlier than 5 months and later than 1 year from the last day of the month in which application has been made.

5.2. All applications shall be processed on first-come-first-served basis provided that the applications received during a month shall be construed to have come together on the last day of the month.

5.3. Provided that while processing applications for MTOA received during a month, those seeking access for a longer time shall have a higher priority.

5.4. Incomplete applications shall be rejected mentioning reason for rejections to the applicant.

6. APPLICATION6.1. Documents to be submitted alongwith the application:

Duly filled in Application in specified format. Incomplete application shall be rejected.

Proof of payment of Application fee PPA or Sale-purchase agreement of power In case of generating station or consumer not already connected to grid,

documentary evidence for completion of the connectivity showing that the same shall be completed before intending date of MTOA

** Note - Incomplete application shall be rejected.

6.2. The Application should be submitted in a sealed envelope with “Application for MTOA” clearly marked on the envelope. The application shall be addressed to

Additional Chief Engineer (R & C),Gujarat Energy Transmission Corporation Limited,Sardar Patel Vidhyut Bhavan,Race Course,Vadodara.390007.

7. GRANT OF MTOA

7.1 Calculation of Total Transfer Capability (TTC), Available Transfer Capability (ATC)and Transmission Reliability Margin (TRM) Definitions “Total Transfer Capability (TTC)” means the amount of electric power that can be transferred reliably over the intra-control area transmission system under a given set of operating conditions considering the effect of occurrence of the worst credible

5

Page 6: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

contingency.

“Transmission Reliability Margin (TRM)” means the amount of margin kept in the total transfer capability necessary to ensure that the intraconnected transmission network is secure under a reasonable range of uncertainties in system conditions

“Available Transfer Capability (ATC)” means the transfer capability of the intra-control area transmission system available for scheduling commercial transactions (through long term access, medium term open access and short term open access) in a specific direction, taking into account the network security. Mathematically ATC is the Total Transfer Capability less Transmission Reliability Margin

The STU shall assess the Total Transfer Capability (TTC), Available Transfer Capability (ATC) and Transmission Reliability Margin (TRM) of intra-State links / Corridors. TTC, ATC, and TRM along with the details of basis of calculations, including assumptions if any, shall be put up on the website of STU.

The TTC and TRM are the primary quantities which are to be arrived at from System Studies. The ATC would be derived as the difference between the two. The procedure for the calculation would be as follows:

1. A base case with the likely scenario during the time frame for which transfer capability is sought would be used in the System Studies for calculation of TTC of the required transmission corridors or “flowgates”.

2. The Load Generation scenario inputs would be taken from the planning data of GETCO, the Load Generation Balance Report of GETCO for the next year, and maintenance schedule agreed in RPCs. All operation conditions would be mentioned along with assumptions made.

3. The worst n-1 contingency for the flowgate under study, based on operating experience would be decided for which limiting cases are to be studied.

4. The degree of impact ( Sensitivity analysis) of planned /unplanned outage oftransmission lines in important corridors would be indicated.

5. While carrying out system studies for different conditions, it would be seen that the limiting condition on some portions of the transmission corridor or flow gates can shift among thermal, voltage and stability limits as the network operating conditions change over time. TTC would be the minimum of the transmission capability arrived at taking into consideration the Stability Limit, Voltage Limit and Thermal limit.

6. The limiting factors would be mentioned, for example, specific buses facing problemof low voltage, transmission line facing congestion or crossing stability /thermal limit,etc..

6

Page 7: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

7. The TRM would be arrived at by considering the worst credible contingency, i.e. one which would affect the transmission capability of the flowgate to the maximum possible extent.

8. The difference between the TTC and the TRM would be the ATC. The latest ATC would be the one which is still left over after taking into account the usage of the transmission capability by existing contracts

9. The STU may revise the TTC, ATC and TRM due to change in system conditions, which includes change in network topology or change in anticipated active or reactive generation or load, at any of the nodes in the study. Such revision should clearly state the reasons thereof.

10.a. While issuing MTOA permission STU may grant or reject or reduce the time period or reduce the quantum of power applied for MTOA Application during the intimation. In case of rejection or reduction of time period, STU shall inform the reasons for doing so, in writing to the Applicant, RLDCs and STUs. The grant of MTOA shall be as per format given at FORMAT-MTOA-3.

b. Prior to the grant of MTOA, the applicant shall sign the agreement for sharing the transmission charges for grant of MTOA, which will form a part of the medium-term open

access agreement (FORMAT-MTOA-4). The MTOA Agreement shall contain the quantum of power, date of commencement and end of medium-term open access, the point of injection of power into the grid and point of drawl from the grid, the details of dedicated transmission lines required, if any, and the bank guarantee required to be given by the applicant.

c. Before signing of the MTOA agreement, the applicant shall submit a Letter of Credit and Bank Guarantee (BG) to STU/Transmission Licensee equivalent to estimated transmission charges of two months.

d. The agreement for MTOA is to be signed by the applicant with the State Transmission Utility in case medium-term open access is granted by the State Transmission Utility. While seeking medium-term open access to an intra-State transmission licensee, other than the State Transmission Utility, the applicant shall

sign a tripartite MTOA agreement with the State Transmission Utility and the intra State transmission licensee.

e. In case the MTOA agreement has not been signed or requisite bank guarantee and Letter of Credit has not been submitted by the applicant within the stipulated period, the grant of MTOA shall be cancelled by the STU and the same shall be informed to Applicant and SLDC.

f. Immediately after grant of medium-term open access, the nodal agency shall inform the SLDCs concerned so that they can consider the same while processing requests for short- term open access received.

7

Page 8: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

g. On the expiry of period of the medium-term open access, the medium-term customer shall not be entitled to any overriding preference for renewal of the term.

8. SCHEDULING OF MEDIUM TERM OPEN ACCESS TRANSACTION

The scheduling jurisdiction and procedure, curtailment and revision of schedule of

MTOA transactions, metering, energy accounting and accounting of (Unscheduled

Intrachange) UI charges shall be as per the Regulations and the Indian Electricity Grid

Code/GEGC, as amended from time to time. While scheduling on day-ahead basis, long-

term access customers would have the highest priority, followed by medium term

customers and then followed by short-term customers.

a. Underutilization of transmission capacity In case it is observed by SLDCs that the MTOA customer request for scheduling is

consistently (for more than 5 days) lower than the capacity granted by the Nodal

Agency (i.e.; STU), SLDC may issue a notice to such MTOA customer asking the

reasons for such under-utilization. The MTOA customer shall furnish the reasons for such

under-utilization and will provide such details like the reduced requirement, likely

period, etc. by the following day. The un-utilized transfer capability will then be released

for scheduling of Short-term open access transaction.

b. No refund of transmission charges shall be made due to above curtailment.

9. TRANSMISSION CHARGES 9.1. The transmission charges for use of the STS shall be recovered from the medium-

term customers in accordance with terms and conditions of tariff specified by the Commission from time to time and the Regulations.

9.2. The transmission charges shall be paid directly to the State Transmission Utility.9.3. For payment of monthly transmission charges, irrevocable revolving LC through a

scheduled commercial bank in favour of “Gujarat Energy Transmission Corporation Limited.” Equivalent to two months transmission charges shall be opened by MTOA applicant 15 days before the commencement date of MTOA. LC should remain valid upto one month after MTOA period. Further the bank guarantee equivalent to 2 (two) months estimated average monthly billing would also be required to be furnished in favour of “Gujarat Energy Transmission Corporation Limited”, which would be in place 3 (three) months prior to the date of scheduled commencement of MTOA with validity upto 1 (one) month after the expiry of MTOA period.

9.4. The fees and charges for the State Load Despatch Centre including charges for the Area Load Despatch and Communication Centre shall be payable by the medium-term customer directly to the State Load Despatch Centre or the State Load

8

Page 9: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

Despatch Centre concerned.

10. ENCASHMENT / DISCHARGE OF BANK GUARANTEE 10.1. The Bank Guarantee will be encashed in case the applicant defaults on payment of

transmission charges. The Bank Guarantee shall be recouped and remain valid upto one month after MTOA period.

10.2. In case any request for downsizing the power transfer is received after signing of the BPTA and submission of Bank Guarantee, any adjustment of Bank Guarantee shall be carried out after expiry of the MTOA term.

12. EXIT OPTION12.1. A customer who has been granted MTOA, may relinquish rights, fully or partly, as per the

Terms and conditions of Intra State Open Access regulations 2011. Further, the above compensation paid by medium-term customer shall be used for reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long term customers and medium-term customers.

13. GENERAL13.1. The applicant shall keep the nodal agency and SLDC indemnified at all times

and shall undertake to indemnify, defend and keep the nodal agency, SLDC harmless from any and all damages, losses, claims and actions including those relating to injury to or death of any person or damage to property, demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the long-term access transaction.

13.2. All costs/expenses/charges associated with the application, including bank draft, bankguarantee etc. shall be borne by the applicant.

13.3. The applicant shall abide by the provisions of the Electricity Act, 2003, theRegulations and Indian Electricity Grid Code , as amended from time to time.

13.4. This procedure aims at easy and pragmatic disposal of applications made for Medium Term Open Access in STS. However, some teething problems may still be experienced. The various implications would be known only after practical experience is gained by way of implementing these procedures. In order to resolve the same, this procedure shall be reviewed or revised by the Nodal agency with prior approval of CERC.

13.5. All complaints regarding unfair practices, delays, discrimination, lack of information, supply of wrong information or any other matter related to Medium-term Open access in STS shall be directed to CERC for redressal.

9

Page 10: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

FORMAT-MTOA-1

On Non Judicial Stamp paper of `.50

AFFIDAVIT

In the matter of filing application to Gujarat Energy Transmission Corporation Limited., for grant of Medium Term Open Acces.

I……(Name)……S/o Shri ……(Father‟s name)… working as ……. (Post)……. in ……(name of the Company)………..,having its registered office at ……… (address of the company)…….., do solemnly affirm and say as follows:

1. I am the ….. (Post)……. of …..(Name of the Company)………, therepresentative in the above matter and am duly authorized to file the aboveapplication and to make this affidavit.

4. I submit that M/s……..(name of the company)……. is a registered company …….(Public Ltd/Pvt. Ltd.)……. Registered under Companies Act. Under the Article of Association of the Company and in accordance with the provisions of Electricity Act, 2003/relevant Regulation(s) of GERC, the company can file the enclosed application.

5. I submit that all the details given in the enclosed application for grant of Medium Term Open Accesss alongwith necessary documents are true and correct and nothing material has been concealed thereof.

(Signature) Name of the Applicant

(To be duly attested by Notary)

10

Page 11: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

FORMAT-MTOA-2

Application for Grant of Medium Term Open Access (MTOA)

1 Name the Applicant2 Address for Correspondence3 Contact Details

Prime Contact Person Designation

Phone No.(Landline) Phone No.(Mobile)

Fax E-Mail

Alternate Contact Person Designation

Phone No.(Landline) Phone No.(Mobile)

Fax E-Mail

4 Nature of the Applicant Normal Generator (other than captive)

Captive Generator Bulk Consumer

Electricity Trader Distribution Licensee

Others

5 Details for Medium Term Open Access(MTOA)

5a Quantum (MW) for which MTOArequired

5b Date from which MTOA required(not earlier than 5months and not later than

1 year from the last day of the month in which application has been received)

5c Date upto which MTOA required(3 months to 3 years from the date from

which MTOA is required)

5d Injection of Power

Entity State/Region Quantum

Connectivity with the Grid 11

Page 12: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

5e Drawal of Power

Entity State/Region

Quantum Connectivity with the Grid

6 Details of DD/Cheque (Application Fee)

Amount (in Rs.) DD/Cheque No.

Date Bank Name

Branch Name

7 Details of Bank Guarantee Amount (in Rs.)

Bank Name Period of Validity

12

Page 13: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

13

Page 14: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

FORMAT-MTOA-3

Intimation for grant of Medium Term Open Access (MTOA)

1 Intimation No.Date :

2 Ref. Application No.Date :

3 Name of the Applicant

4 Address for Correspondence

5 Nature of the ApplicantNormal Generator (other than captive)

Captive Generator Bulk Consumer

Electricity Trader Distribution Licensee

6 Details for Medium Term Open Access (MTOA)6a Quantum (MW) for which MTOA is granted6b Date from which MTOA is granted6c Date upto which MTOA is granted

7 Injection of Power

Entity State/Region

Quantum Connectivity with the Grid

8 Drawal of Power

Entity State/Region

Quantum Connectivity with the Grid

9 Transmission Charges Applicable

14

Page 15: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

FORMAT-MTOA-4 On Non Judicial Stamp Paper of `.100/-

BULK POWER TRANSMISSION AGREEMENT

BETWEEN………………………………………

ANDGUJARAT ENERGY TRANSMISSION CORPORATION LTD.

This Power Transmission Agreement hereinafter called the “ Agreement” entered into on the 21st December 2010, between GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED, a Company incorporated under the companies Act, 1956 and wholly owned by Government of Gujarat, having its registered office at Additional Chief Engineer (Commerce) (Transmission), Sardar Patel Vidyut Bhavan, Race Course, Vadodara – 390007. (hereinafter called “GETCO” which expression shall unless repugnant to the context or meaning therof incluse its successors and assigns) as party of the first part; and …………………….. Ltd, having its regd office at ……………………………… (hereinafter called “Medium term transmission Customer” which expression shall unless repugnant to the context or meaning thereof include its successors, and assigns) as party of the second part.

And whereas Gujarat Energy Transmission Corporation Limited is a company wholly owned by the Govt. of Gujarat and was established with a view to develop the State grid to ensue transmission of power within and across the different regions of Gujarat on more scientific, efficient and economic basis.

As where ……………………….. Ltd has setup its ……..(……………..) MW Power Plant at …………………...

15

Page 16: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

As where as ……………………… Ltd is desirous of Transmission of its Power from Power Plant at …………….., District ……….., Gujarat, within the state of Gujarat and has requested GETCO to transmit the power to the beneficiaries within Gujarat on mutually agreed terms and conditions mentioned hereunder.

And whereas the Medium term transmission customer is a Generating Company as per the provisions of EA 2003 and is desirous to avail Medium Term Open Access in accordance with Gujarat Electricity Regulatory Commission Order No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011 as amended from time to time and Electricity Act 2003.

And whereas in accordance with Gujarat Electricity Regulatory Commission Order No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011 as amended from time to time, Medium Term Open Access shall be allowed by GETCO to Open Access customer within the state of Gujarat.Now therefore in consideration of the premises and mutual agreements, covenants and conditions set forth herein, it is agreed by and between the parties as follows:

1.Injection Consumer / CompanyName :………………………………..Location :……………, District ……., GujaratTransmission / Distribution Licensees :GETCOCapacity (MW) :……..(…………..) MW

Drawee Consumer / Company (ies)

Name :Location :Transmission/Distribution Licensees(s) : GETCOCapacity(MW) :

Date from which the Medium Term Open Access is required DTD……………………….

2. ALLOCATION OF POWER FROM

The transmission of power would be subject to opening/enhancing irrevocable revolving letter of credit by ……………………. Ltd to cover full amount of two monthly billing to be raised by GETCO as per the Transmission charges approved by GERC for timely payment to GETCO. The operation of LC shall not be dependent on the recoupment of the amount by ……………………….. Ltd. The supply of power would be coordinated by State Load Dispatch Center (SLDC). The supply to GETCO shall be made on radial basis from the Generating power plant.

3. TARRIF AND TERMS AND CONDITIONSThe tariff applicable to ………………. Ltd would be the tariff of the transmission system of GETCO in the Gujarat as approved by GERC from time to time from where the supply of the power to beneficiaries of ………………. LTD is mentioned in the State Energy Accounts issued by SLDC.

If any of the terms and conditions of the Agreement with beneficiaries differs from the corresponding specific provision of Agreement then terms and conditions of this Agreement shall prevail.

16

Page 17: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

The transmission charges for the total State Transmission System shall be calculated on monthly basis and shall be leviable to each beneficiary as per the formula prescribed in the GERC No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011 and ARR of GETCO. In case no beneficiaries for the full or part quantum of committed evacuation of power (………. MW) are found by ………………pvt. Ltd, the full Transmission charges of ………. MW shall be payable by ……………………. Ltd on monthly basis from the date mentioned under para 1 of this Agreement for the term of this Agreement.

4. STATE ENERGY ACCOUNTSIt is specifically agreed between the parties that ……………….. LTD shall accept without any reservation and condition the State Energy Account issued by SLDC. ………………. LTD shall accept and make full payment to GETCO in respect of the GETCO bills raised on this basis. Any change in the State Energy Account methodology by SLDC shall also be binding on all concerned.

5. ESTABLISHMENT OF LC AND PAYMENT OF BILLSa. GETCO Corporate office, shall present bills for transmission charges to all the

Medium term open access customers on monthly basis. In event of any revision in Regional Energy Account issued by WREB & State energy account issued by SLDC Gotri, GETCO shall adjust the difference between the amount already billed and revised amount by raising a supplementary bill along with a debit/credit note as the case may be.

b. Payment of bills shall be made by Medium Term Open Access user through irrevocable revolving Letter of Credit (LC) to be opened in the favor of GETCO. LC shall be established for amount equivalent to two months billing.

c. Further the bank guarantee equivalent to 2 (two) months estimated monthly billing would also be required to be furnished in favour of “Gujarat Energy Transmission Corporation Limited”, which would be in place on the date of signing this Agreement of MTOA with validity upto 1 (one) month after the expiry of MTOA period.

The Medium Term Open Access user will be communicated by GETCO an approximate amount of LC required based on total approved transmission charges of GETCO and the ratio of capacity to be booked by the Medium term open access customer.

d. LC Shall be without any limitation or restriction with regard to the manner and dates on which the bill can be presented to the concerned banks by GETCO. The bills so presented by GETCO to the bank shall be promptly paid on their presentation. The amount of LC shall be reviewed by GETCO every quarter commencing from April, July, October and January in each financial year and the amount of LC shall be enhanced/reduced, as necessary. The LC charges shall be borne by the respective Medium Term Open Access Users.

e. All the Medium Term Open Access users shall open a Letter of Credit three months prior to the date of signing of this Transmission Agreement.

f. All such direct payment shall be paid by the Medium Term Open Access users to GETCO through a cheque/ECS/EFT/Demand Draft.

17

Page 18: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

g. The transmission charges for the total state transmission system of GETCO shall be calculated on monthly basis and shall be leviable to each beneficiary as per the formula prescribed in the GERC No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011 and/or subsequent tariff notifications/ARR issued by GERC from time to time.

h. The bills of GETCO shall be paid without any deductions.

i. In case of Letter of Credit is not established or maintained by the Medium Term Open Access user the same shall be considered as default the Open Access granted by GETCO shall stand cancelled.

j. ENCASHMENT / DISCHARGE OF BANK GUARANTEE The Bank Guarantee will be encashed in case the applicant defaults on payment of transmission charges. The Bank Guarantee shall be recouped and remain valid upto one month after MTOA period. In case any request for exit the power transfer is received after signing of the BPTA and submission of Bank Guarantee, any adjustment of Bank Guarantee shall be carried out after expiry of the MTOA term. All costs/expenses/charges associated with the application, including bank draft, bank guarantee,LC etc. shall be borne by the MTOA applicant

6.0Late payment surcharges :

In case the payment of bills of Transmission charges by the beneficiary or beneficiaries is delayed beyond a period of 5 working days from the receipt of the bill, late payment surcharge at the rate of 1.25% per month on billed amount shall be levied on the amounts remained unpaid after the said date in proportion to the number of days of delay after the said date. The late payment surcharge amount shall also be payable aMedium with the next bill. In case …………………. Ltd fails to make payment of the amount due to them within 60 days of issue of Invoice the Medium Term Open Access granted shall be discontinued by GETCO due to non payment of Transmission charges and actions shall be initiated under section 142 of the Act in addition to the action under Section 56 of EA 2003.

7.0 Medium term Transmission customer shall in addition to Transmission charges pay O & M charges for the dedicated transmission system of GETCO as mentioned above to be exclusively used for the open access for the Medium term transmission customer.

8.0 GETCO agrees to provide Medium Term Open Access required by Medium term transmission customer as per the details mentioned above and in accordance with the Regulations under the Gujarat Electricity Regulatory Commission (No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011 and conditions specified by the GERC from time to time.

18

Page 19: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

9.0 The Medium term transmission customer shall not relinquish or transfer its rights and obligations specified in the Bulk Power Transmission Agreement, with out prior approval of GETCO and subject to payment of compensation, as determined in the No.3 of 2011 Dtd.1-6-2011 (Terms and Conditions of Intra state Open Access) regulation 2011.

10.0 All differences/disputes between the parties arising out of or in connection with this Agreement shall be resolved in terms of the Redressal Mechanism provided under Regulation of the GERC Regulations.

11.0 This Agreement shall be valid for ……. Months/years from the date of Agreement signed with GETCO

12.0 Medium term open access user agrees to pay the reactive energy as per GERC grid code and Tariff order as applicable from time to time.

13.0Effective Date and Duration of AgreementThis agreement shall be deemed to have come in force for all purpose and intends from the date of approval given by GETCO Dt ……………… and shall remain operative upto Dt…………….. provided this agreement is may be mutually extended, renewed or replaced by another agreement on such terms and conditions for such further period of time as the parties may mutually agree.

14.0Metering :The Meters shall be provided and governed as per the Central Electricity Authority (Installation and Operation of Meters) Regulation, 2006 notified on dt. 17th March 2006 and as amended from time to time. The Ownership of Meters, Standards, Meter failure or discrepancies, Calibration and periodical testing of the meters installed shall be as per the CEA Regulations. The Meter related accessories like CT and PT shall also be as per the said regulations.

15.0Successors and AssignsIn case GETCO is wound up and/or its transmission are taken over by other organization(s)/ agency (ies), In such an event, LC arrangement referred to in Para 6 above shall also be binding in respect of the successors organization(s)/ agency(ies) with such modifications and changes as may be considered necessary.

16.0JurisdictionThe courts of Ahemdabad shall have exclusive jurisdiction in all matters under this Agreement.

In witness whereof both the parties have executed this Agreement through their authorized representative.

Witness GUJARAT ENERGY TRANSMISSING CORPORATION LIMITED.VADODARA

1. For and on behalf of GETCO 2. For and on behalf

Addl Chief Engineer(R & C)19

Page 20: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

Corporate Office, GETCO,VADODARA.

20

Page 21: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

ANNEXURE-‘X’

PROFORMA FOR BANK GUARANTEE (To be on non-judicial stamp paper of appropriate value as per Stamp Act relevant to place of execution(Gujarat). To be provided in the name of Gujarat Energy Transmission Corporation Limited) Ref…………….. Bank Guarantee No……………….Dated ………..……..To M/s Gujarat Energy Transmission Corporation Limited,Sardar Patel Vidhyut Bhavan,Race Course,Vadodara. Dear Sirs, In consideration of the ……………………..[Insert name of the ……. Power Project Developer, Address] agreeing to undertake the obligations under the Transmission Agreement and Gujarat Energy Transmission Corporation Limited (herein after referred to as GETCO), agreeing to execute Agreement for Transmission of power from …… Power Project on Medium term basis as per Bulk Power Transmission Agreement signed with GETCO, the ………………………………. [Insert name and address of the bank issuing the guarantee and address of the head office] (hereinafter referred to as “Guarantor Bank”) hereby agrees unequivocally, irrevocably and unconditionally to pay to the GETCO at Sardar Patel Vidyut Bhavan, Race Course, Vadodara forthwith on demand in writing from the GETCO or any Officer authorized by it in this behalf, any amount up to and not exceeding Rupees ………………………….. only [Insert the amount of the bank guarantee] with respect to the Contracted Capacity of the GETCO as per the terms of Agreement on behalf of M/s. …………………………………. [Insert name of ……..Power Project Developer (PPD)].

This guarantee shall be valid and binding on the Guarantor Bank up to Twenty Five (25) years and three (3) months from scheduled commercial operation date…………… [Insert date of validity of BG] and shall in no event be terminable by notice or any change in the constitution of the Bank or the term of the Agreement or by any other reasons whatsoever and our liability hereunder shall not be impaired or discharged by any extension of time or variations or alternations made, given, or agreed with or without our knowledge or consent, by or between parties to the respective agreement.

Our liability under this Guarantee is restricted to Rupees… (`. …………………………….. only). Our Guarantee shall remain in force until ……………………………………….. [Insert date of validity BG]. The GETCO shall be entitled to invoke this Guarantee any time up to thirty (30) days of the last date of the validity of this Guarantee by issuance of a written demand to invoke this guarantee.

The Guarantor Bank hereby expressly agrees that it shall not require any proof in addition to the written demand from the GETCO, made in any format, raised at the above mentioned address of the Guarantor Bank, in order to make the said payment to the GETCO at Vadodara.

The Guarantor Bank shall make payment hereunder on first demand without restriction or conditions and notwithstanding any objection by, …………………………… [Insert name of Power Project Developer] and/or any other person. The Guarantor Bank shall not require the GETCO to justify the invocation of this BANK GUARANTEE, nor shall the Guarantor Bank have any recourse against the GETCO in respect of any payment made hereunder.

21

Page 22: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

This BANK GUARANTEE shall be interpreted in accordance with the laws of India and the courts at Vadodara shall have exclusive jurisdiction.

The Guarantor Bank represents that this BANK GUARANTEE has been established in such form and with such content that it is fully enforceable in accordance with its terms as against the Guarantor Bank in the manner provided herein.

This BANK GUARANTEE shall not be affected in any manner by reason of merger, amalgamation, restructuring, liquidation, winding up, dissolution or any other change in the constitution of the Guarantor Bank.

This BANK GUARANTEE shall be a primary obligation of the Guarantor Bank and accordingly the GETCO shall not be obliged before enforcing this BANK GUARANTEE to take any action in any court or arbitral proceedings against the Power Project Developer, to make any claim against or any demand on the Power Project Developer or to give any notice to the Power Project Developer or to enforce any security held by the GETCO or to exercise, levy or enforce any distress, diligence or other process against the Power Project Developer.

The Guarantor Bank hereby agrees and acknowledges that the GETCO shall have a right to invoke this Bank Guarantee either in part or in full, as it may deem fit.

Notwithstanding anything contained hereinabove, our liability under this Guarantee is restricted to `. ………………….. (`. ………………….. only) and it shall remain in force until ………………………[Insert date of validity of BG], with an additional claim period of thirty (30) days thereafter. We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee only if the GETCO serves upon us a written claim or demand.

In witness whereof the Bank, through its authorized officer, has set its hand and stamp on this …………….. day of ……………………… at …………………….

Witness:1. ……………………………………. SignatureName and Address. Name:2. ………………………………….. Designation with Bank StampName and Address

Attorney as per power of attorney No. …………………

For:……………………………………………. [Insert Name of the Bank]

Banker’s Stamp and Full Address:Dated this ………………… day of …………… 20…..Notes:

i. The Stamp Paper should be in the name of the Executing Bank.ii. Contracted Performance Bank Guarantee shall be provided from any of the bank listed

in Annexure 1 only. Bank Guarantee of any other Bank will not be accepted.

Annexure 1. - List of Banks

Scheduled Commercial Banks

22

Page 23: PROCEDURE FOR MAKING APPLICATION FOR … FOR... · Web viewThe application for MTOA shall be made as per the enclosed application format (FORMAT-MTOA-2) and shall include details

SBI and Associates1. State Bank of India2. State Bank of Bikaner and Jaipur3. State Bank of Hyderabad4. State Bank of Indore5. State Bank of Mysore6. State Bank of Patiala7. State Bank of Saurashtra8. State Bank of Travancore

Nationalised Banks9. Allahabad Bank10. Andhra Bank11. Bank of India12. Bank of Maharashtra13. Bank of Baroda14. Canara Bank15. Central Bank of India16. Corporation Bank17. Dena Bank18. Indian Bank19. Indian Overseas Bank20. Oriental Bank of Commerce21. Punjab National Bank22. Punjab and Sind Bank23. Syndicate Bank24. Union Bank of India25. United Bank of India26. UCO Bank27. Vijaya Bank

Scheduled Private Banks1 ICICI Bank Ltd.2 HDFC Bank Ltd.3 IDBI Bank Ltd4 Axis Bank (formerly UTI Bank)