Project Planning and Management
1
Primavera Project Management 6
Product Demo/ Hands-on
8/9/2019 Primavera Product Demo
2/26
Project Planning and Management
2
Develop the schedule and apply the resources and cost for the Plant Erection project bycreating the Organisation Breakdown Structure and Enterprise Project Structure for the XYZCompany.
The Organisation Breakdown Structure is as Shown below.
President
Prince
Vice President
Special Projects
Zakir
Vice President
Major Projects
Siddiqqui
Director Plant
Works
Aslam
Director Civil
Works
Mohammed
Director Piping
Works
Siddharth
Director Explora-
tionTalaue
Program Manager
InternalRoshan
Program Manager
BridgesRaja
Program Manager -
CCPFelix
Program Manager
Oil Exploration
Ahmed
Project Manager
Plant 1
Dilna
Project Manager
Plant 2
Francis
Project Manager
Bridge 1
Muthu
Project Manager
Bridge 2
Joe
Project Manager
North
Regin
Project Manager
South
Ramu
Project Manager
Central
Azhar
Project Manager
East & WestReji
8/9/2019 Primavera Product Demo
3/26
Project Planning and Management
3
The Project Structure is as shown below.
Assign the OBS to the EPS elements and projects. For this Plant erection project create a sixday work week calendar with 9:00 AM to 6:00 PM and assign it as project calendar. Also create
a five day work week calendar with timing as 10:00 AM to 6:00 PM and assign this calendar fortwo tasks. The start date of the project is May 2, 2009.
The activities are shown with WBS for two levels and the resources are given below. Analysethe resources by using profile and table. The table given below shows the list of activities.
XYZ
Special Projects Major Projects
Plant Works Civil Works Piping Works Exploration
Internal
Works
Bridges Cross Country
Pipeline
Oil Exploration
Plant 1 Project
Plant 2 Project
Bridge 1 Project
Bridge 2 Project
North side
Projects
South SideProjects
Gas Exploration
8/9/2019 Primavera Product Demo
4/26
Project Planning and Management
4
ID Name Duration Predecessors
SS Project
1 Start of project 0 -
101 Tendering
2 Preparation of Tender 20 1
3 Evaluation of Technical Bid 15 2
4 Evaluation of Commercial Bid 7 3
5 Award of Contract 7 4
102 Procurement
6 Ordering of Equipment 4 5
7 Site Handing Over 7 5
8 Delivery of Equipment 60 6
103 Erection Works
9 Erection of Civil Structures 20 7,8
10 Erection of Mechanical Equipment 35 7,8
11 Erection of Electrical Equipment 25 7,8
104 Testing & Closing
12 Testing of Plant 7 9,10,11
13 On load Testing 7 12
14 Commissioning 1 13
15 Finish of project 0 14
8/9/2019 Primavera Product Demo
5/26
Project Planning and Management
5
Resource Definition
The table given below shows the list of resources that are available for the whole project.
Name Max. Avail. Price/ Unit
Materials Manager 1 550/day
Engineer 3 500/day
Quality Controller 2 550/day
Supervisor 4 400/day
Office Assistant 1 200/day
Electrician 1 250/day
Labour 20 100/day
Crane 1 450/day
Excavator 1 400/day
Assigning Resources
The table given below shows the list of resources that are needed for each and every activity.Analyse the resources by using resource profile.
Name Resource Names No. of units
Preparation of Tender Engineer
Office Assistant
1
1
Evaluation of Tech. Bid Engineer 1
Evaluation of Comm. Bid Engineer 1
Award of Contract Engineer
Office Assistant
1
1
8/9/2019 Primavera Product Demo
6/26
Project Planning and Management
6
Name Resource Names No. of units
Ordering of Equipment Materials Manager
Office Assistant
1
1
Site Handing Over Engineer
Office Assistant
1
1
Delivery of Equipment Materials Manager
Engineer
Labour
1
1
10
Erection of Civil Structures Engineer
Supervisor
Labour
Excavator
Materials Manager
1
2
15
1
1
Erection of Mechanical Equipment Engineer
Supervisor
Labour
Crane
1
2
15
1
Erection of Electrical Equipment Engineer
Supervisor
Electrician
Labour
Crane
1
2
1
10
1
Testing of Plant Quality Controller
Supervisor
Labour
2
1
5
On load Testing Quality Controller
Supervisor
Labour
1
1
5
8/9/2019 Primavera Product Demo
7/26
Project Planning and Management
7
Name Resource Names No. of units
Commissioning Engineer
Office Assistant
Labour
1
5
5
Report
1) Prepare the schedule and find the critical path and finish date of the project.2) Assign the resources and find the total cost of the project.3) Track the project after 15 days with some delay in the activities.4) Prepare the following report
a. Resource ControlDetail by Activityb. Monthly Project Cask Flowc. Resource Units Loading Daily organised by WBS
8/9/2019 Primavera Product Demo
8/26
Project Planning and Management
8
To define Organizational Breakdown Structure
1) Select ENTERPRISE OBS
2) Select the level below which you want to add the level and select ADD.
3) If the newly created level wants to be inside the selected level, use SHIFT RIGHT.
To define Enterprise Project Structure
8/9/2019 Primavera Product Demo
9/26
Project Planning and Management
9
1) Select ENTERPRISEEnterprise Project Structure
2) Select the level below which you want to add the level and select ADD.
3) If the newly created level wants to be inside the selected level, use the SHIFT RIGHT.
To create new project
1) Select ENTERPRISE Projects
8/9/2019 Primavera Product Demo
10/26
Project Planning and Management
10
2) Select the EPS node in which project has to be created. Then ADD.
3) Enter the details about the project in activity details. View Show on BottomProject Details.
8/9/2019 Primavera Product Demo
11/26
Project Planning and Management
11
To create new calendar.
1) Select ENTERPRISE Calendars
2) Select Project andADD.
8/9/2019 Primavera Product Demo
12/26
Project Planning and Management
12
3) Select the calendar which you want to copy. Click .
8/9/2019 Primavera Product Demo
13/26
Project Planning and Management
13
4) Select
5) To define each days working time, click
8/9/2019 Primavera Product Demo
14/26
Project Planning and Management
14
To assign a calendar as Project Calendar
1) Select ENTERPRISE
Projects2) View Show on Bottom Project Details3) Select Defaults
8/9/2019 Primavera Product Demo
15/26
Project Planning and Management
15
4) Select calendar and click
To assign a calendar as Task Calendar1) Open the project. FileOpen2) View Show on Bottom Activity Details3) Select General
8/9/2019 Primavera Product Demo
16/26
Project Planning and Management
16
Adding Activities1) Open project
8/9/2019 Primavera Product Demo
17/26
Project Planning and Management
17
2) Click to add activities.
Activity Sequencing1) Open the project2) View Show on Bottom Activity Details3) Select Relationships
8/9/2019 Primavera Product Demo
18/26
Project Planning and Management
18
Use either Predecessor or Successor to link the activities and give relationship type and lag.
WBS
To define the WBS for the project1) Project WBS
2) Click .3) To add one level below the selected level.
8/9/2019 Primavera Product Demo
19/26
Project Planning and Management
19
To assign WBS level for the project4) Use Activity Details General
5) Click
6) Select WBS level and click .
8/9/2019 Primavera Product Demo
20/26
Project Planning and Management
20
Resources
To define the resources1) Enterprise Resources
1) ClickGeneral to give resource ID, name etc.2) Click Details to mention whether it is labour, non labour or material. Currency andovertime factor can also be mention here.3) In the Units & Prices we can give the availability of resources and the price.
8/9/2019 Primavera Product Demo
21/26
Project Planning and Management
21
To assign resources1) ProjectActivities2) View Show on bottom Activity Details3) Select Resources
4) Click to assign resource directly.
8/9/2019 Primavera Product Demo
22/26
Project Planning and Management
22
5) Select the resource and click
Resource Analysis
View Show on bottom Resource Usage Profile
8/9/2019 Primavera Product Demo
23/26
Project Planning and Management
23
Red colour indicates the over allocation of resources.
8/9/2019 Primavera Product Demo
24/26
Project Planning and Management
24
Update Progress1) Save the baseline. Project Maintain Baselines
Click to create new baseline.
To assign the baseline ProjectAssign Baselines
8/9/2019 Primavera Product Demo
25/26
Project Planning and Management
25
1) Select each and every activity and for each activity, you need to specify the Actual
Start, Actual Finish and the percent complete and the remaining duration for the
activities in status tab
2) Then, you need to schedule the project by specifying the data date that is the status
date what you are going to set.
8/9/2019 Primavera Product Demo
26/26
26
3) For comparing the actual progress and the baseline schedule go to View Bars and
display the baseline bar.
Earned Value Analysis
For doing the earned value analysis, follow all the steps mentioned in the previous topic. Go to
Activity details Expenses. Give the extra amount which you spend in the Actual cost and
find the EVA. To get the EVA, Planned Value, Earned Value and Actual Cost , go to
Tools
Reports
Earned Value.
Report Generation
For taking tabular reports, ToolsReports Reports