    Project Planning and Management

    1

    Primavera Project Management 6

    Product Demo/ Hands-on

  • 8/9/2019 Primavera Product Demo

    2/26

    Project Planning and Management

    2

    Develop the schedule and apply the resources and cost for the Plant Erection project bycreating the Organisation Breakdown Structure and Enterprise Project Structure for the XYZCompany.

    The Organisation Breakdown Structure is as Shown below.

    President

    Prince

    Vice President

    Special Projects

    Zakir

    Vice President

    Major Projects

    Siddiqqui

    Director Plant

    Works

    Aslam

    Director Civil

    Works

    Mohammed

    Director Piping

    Works

    Siddharth

    Director Explora-

    tionTalaue

    Program Manager

    InternalRoshan

    Program Manager

    BridgesRaja

    Program Manager -

    CCPFelix

    Program Manager

    Oil Exploration

    Ahmed

    Project Manager

    Plant 1

    Dilna

    Project Manager

    Plant 2

    Francis

    Project Manager

    Bridge 1

    Muthu

    Project Manager

    Bridge 2

    Joe

    Project Manager

    North

    Regin

    Project Manager

    South

    Ramu

    Project Manager

    Central

    Azhar

    Project Manager

    East & WestReji

  • 8/9/2019 Primavera Product Demo

    3/26

    Project Planning and Management

    3

    The Project Structure is as shown below.

    Assign the OBS to the EPS elements and projects. For this Plant erection project create a sixday work week calendar with 9:00 AM to 6:00 PM and assign it as project calendar. Also create

    a five day work week calendar with timing as 10:00 AM to 6:00 PM and assign this calendar fortwo tasks. The start date of the project is May 2, 2009.

    The activities are shown with WBS for two levels and the resources are given below. Analysethe resources by using profile and table. The table given below shows the list of activities.

    XYZ

    Special Projects Major Projects

    Plant Works Civil Works Piping Works Exploration

    Internal

    Works

    Bridges Cross Country

    Pipeline

    Oil Exploration

    Plant 1 Project

    Plant 2 Project

    Bridge 1 Project

    Bridge 2 Project

    North side

    Projects

    South SideProjects

    Gas Exploration

  • 8/9/2019 Primavera Product Demo

    4/26

    Project Planning and Management

    4

    ID Name Duration Predecessors

    SS Project

    1 Start of project 0 -

    101 Tendering

    2 Preparation of Tender 20 1

    3 Evaluation of Technical Bid 15 2

    4 Evaluation of Commercial Bid 7 3

    5 Award of Contract 7 4

    102 Procurement

    6 Ordering of Equipment 4 5

    7 Site Handing Over 7 5

    8 Delivery of Equipment 60 6

    103 Erection Works

    9 Erection of Civil Structures 20 7,8

    10 Erection of Mechanical Equipment 35 7,8

    11 Erection of Electrical Equipment 25 7,8

    104 Testing & Closing

    12 Testing of Plant 7 9,10,11

    13 On load Testing 7 12

    14 Commissioning 1 13

    15 Finish of project 0 14

  • 8/9/2019 Primavera Product Demo

    5/26

    Project Planning and Management

    5

    Resource Definition

    The table given below shows the list of resources that are available for the whole project.

    Name Max. Avail. Price/ Unit

    Materials Manager 1 550/day

    Engineer 3 500/day

    Quality Controller 2 550/day

    Supervisor 4 400/day

    Office Assistant 1 200/day

    Electrician 1 250/day

    Labour 20 100/day

    Crane 1 450/day

    Excavator 1 400/day

    Assigning Resources

    The table given below shows the list of resources that are needed for each and every activity.Analyse the resources by using resource profile.

    Name Resource Names No. of units

    Preparation of Tender Engineer

    Office Assistant

    1

    1

    Evaluation of Tech. Bid Engineer 1

    Evaluation of Comm. Bid Engineer 1

    Award of Contract Engineer

    Office Assistant

    1

    1

  • 8/9/2019 Primavera Product Demo

    6/26

    Project Planning and Management

    6

    Name Resource Names No. of units

    Ordering of Equipment Materials Manager

    Office Assistant

    1

    1

    Site Handing Over Engineer

    Office Assistant

    1

    1

    Delivery of Equipment Materials Manager

    Engineer

    Labour

    1

    1

    10

    Erection of Civil Structures Engineer

    Supervisor

    Labour

    Excavator

    Materials Manager

    1

    2

    15

    1

    1

    Erection of Mechanical Equipment Engineer

    Supervisor

    Labour

    Crane

    1

    2

    15

    1

    Erection of Electrical Equipment Engineer

    Supervisor

    Electrician

    Labour

    Crane

    1

    2

    1

    10

    1

    Testing of Plant Quality Controller

    Supervisor

    Labour

    2

    1

    5

    On load Testing Quality Controller

    Supervisor

    Labour

    1

    1

    5

  • 8/9/2019 Primavera Product Demo

    7/26

    Project Planning and Management

    7

    Name Resource Names No. of units

    Commissioning Engineer

    Office Assistant

    Labour

    1

    5

    5

    Report

    1) Prepare the schedule and find the critical path and finish date of the project.2) Assign the resources and find the total cost of the project.3) Track the project after 15 days with some delay in the activities.4) Prepare the following report

    a. Resource ControlDetail by Activityb. Monthly Project Cask Flowc. Resource Units Loading Daily organised by WBS

  • 8/9/2019 Primavera Product Demo

    8/26

    Project Planning and Management

    8

    To define Organizational Breakdown Structure

    1) Select ENTERPRISE OBS

    2) Select the level below which you want to add the level and select ADD.

    3) If the newly created level wants to be inside the selected level, use SHIFT RIGHT.

    To define Enterprise Project Structure

  • 8/9/2019 Primavera Product Demo

    9/26

    Project Planning and Management

    9

    1) Select ENTERPRISEEnterprise Project Structure

    2) Select the level below which you want to add the level and select ADD.

    3) If the newly created level wants to be inside the selected level, use the SHIFT RIGHT.

    To create new project

    1) Select ENTERPRISE Projects

  • 8/9/2019 Primavera Product Demo

    10/26

    Project Planning and Management

    10

    2) Select the EPS node in which project has to be created. Then ADD.

    3) Enter the details about the project in activity details. View Show on BottomProject Details.

  • 8/9/2019 Primavera Product Demo

    11/26

    Project Planning and Management

    11

    To create new calendar.

    1) Select ENTERPRISE Calendars

    2) Select Project andADD.

  • 8/9/2019 Primavera Product Demo

    12/26

    Project Planning and Management

    12

    3) Select the calendar which you want to copy. Click .

  • 8/9/2019 Primavera Product Demo

    13/26

    Project Planning and Management

    13

    4) Select

    5) To define each days working time, click

  • 8/9/2019 Primavera Product Demo

    14/26

    Project Planning and Management

    14

    To assign a calendar as Project Calendar

    1) Select ENTERPRISE

    Projects2) View Show on Bottom Project Details3) Select Defaults

  • 8/9/2019 Primavera Product Demo

    15/26

    Project Planning and Management

    15

    4) Select calendar and click

    To assign a calendar as Task Calendar1) Open the project. FileOpen2) View Show on Bottom Activity Details3) Select General

  • 8/9/2019 Primavera Product Demo

    16/26

    Project Planning and Management

    16

    Adding Activities1) Open project

  • 8/9/2019 Primavera Product Demo

    17/26

    Project Planning and Management

    17

    2) Click to add activities.

    Activity Sequencing1) Open the project2) View Show on Bottom Activity Details3) Select Relationships

  • 8/9/2019 Primavera Product Demo

    18/26

    Project Planning and Management

    18

    Use either Predecessor or Successor to link the activities and give relationship type and lag.

    WBS

    To define the WBS for the project1) Project WBS

    2) Click .3) To add one level below the selected level.

  • 8/9/2019 Primavera Product Demo

    19/26

    Project Planning and Management

    19

    To assign WBS level for the project4) Use Activity Details General

    5) Click

    6) Select WBS level and click .

  • 8/9/2019 Primavera Product Demo

    20/26

    Project Planning and Management

    20

    Resources

    To define the resources1) Enterprise Resources

    1) ClickGeneral to give resource ID, name etc.2) Click Details to mention whether it is labour, non labour or material. Currency andovertime factor can also be mention here.3) In the Units & Prices we can give the availability of resources and the price.

  • 8/9/2019 Primavera Product Demo

    21/26

    Project Planning and Management

    21

    To assign resources1) ProjectActivities2) View Show on bottom Activity Details3) Select Resources

    4) Click to assign resource directly.

  • 8/9/2019 Primavera Product Demo

    22/26

    Project Planning and Management

    22

    5) Select the resource and click

    Resource Analysis

    View Show on bottom Resource Usage Profile

  • 8/9/2019 Primavera Product Demo

    23/26

    Project Planning and Management

    23

    Red colour indicates the over allocation of resources.

  • 8/9/2019 Primavera Product Demo

    24/26

    Project Planning and Management

    24

    Update Progress1) Save the baseline. Project Maintain Baselines

    Click to create new baseline.

    To assign the baseline ProjectAssign Baselines

  • 8/9/2019 Primavera Product Demo

    25/26

    Project Planning and Management

    25

    1) Select each and every activity and for each activity, you need to specify the Actual

    Start, Actual Finish and the percent complete and the remaining duration for the

    activities in status tab

    2) Then, you need to schedule the project by specifying the data date that is the status

    date what you are going to set.

  • 8/9/2019 Primavera Product Demo

    26/26

    26

    3) For comparing the actual progress and the baseline schedule go to View Bars and

    display the baseline bar.

    Earned Value Analysis

    For doing the earned value analysis, follow all the steps mentioned in the previous topic. Go to

    Activity details Expenses. Give the extra amount which you spend in the Actual cost and

    find the EVA. To get the EVA, Planned Value, Earned Value and Actual Cost , go to

    Tools

    Reports

    Earned Value.

    Report Generation

    For taking tabular reports, ToolsReports Reports