Presentation to:
By the Inglewood Town Hall Community Hub Project Working Group
24/9/2012
Project Stakeholders:
Presentation Agenda
Background and status to date
Community Hub project
Operational arrangements
Opportunity for business hub
What it can look like? ..plans.
Project timing & documentation
Funding
Discussion & Q&A
Project Background - Inglewood Community Hub Project
• 2010 – Project established to determine the need – In June 2010, Loddon Shire Council, in partnership with the Department of Planning and Community Development (DPCD), Inglewood and
District Community Bank, Inglewood and District health Service (IDHS), Inglewood Community Resource Centre (ICRC) and Inglewood Development and Tourism Committee (IDTC) commissioned a project to establish whether there is a need for a new community hub in Inglewood.
• Facilitator appointed and Community meetings held
• Survey focussed the needs and preference for linkage with Town Hall
• 2011 March Inglewood Focus on Feasibility Report and Strategic Plan ($3.15M estimate)
• 2011 April – Report Presented to Council and Endorsed with recommendations
• Project Working Group appointed
Working Group Members:
• Council - Tim Jenkyn • ICRC CoM - Jill Burdett • Town Hall CoM - Dona Martin • Community rep IDTC - Murray Baud • Dept. Planning & Community Development - Jenny Dyer • Inglewood C&D Bank Board Member - Dale Jackson • Loddon Shire Councillor - Geoff Curnow
What have we done to date? • Communication plan and web pages www.inglewood.vic.au/chpwg
• Draft budget options based on delivery of usage/functionality. (ie $ for minimum change such as kitchen upgrade, and varying amounts of up to full budget for upgrade of entire hall, landscape., etc see box below )
• Detailed hall and space requirements brief document.
• Rough draft business plan – identified need for master agreement and “operational” model to resolve financial model
• Draft master agreement leading to stakeholder discussions
• Range of concept plans developed, refined, narrowed to agreed one
• Building works quotations to refine budget and funding strategy
• Develop business hub
• Marketing material
• Stakeholder discussions
• Public Open day
Usage of Facility Options - driving requirements & budget
A - basic upgrade of wiring, meter, plumbing, building roof &kitchen. Continued adhoc usage of hall
B - Introduction of new toilet block on southern side
C1 - Tenancy for Community Hub - downstairs and upstairs rooms
C2 - Tenancy for Community Hub - downstairs and upstairs (balcony + lift) C3 - Multiple tenancy - addit Business hub (1st floor, mezzanine + lift)
D - Tenancy/ Convention and stage production
F - Multiple tenancy - including Tourism / Terrace Café
G - Main Hall - Canite removal
L - Major landscaping
Community Hub Proposal
• Focuses on utilising the existing Town Hall spaces and rooms for range of facilities.
• Requires significant building renovations and restoration to make safe.
• Requires new Lift and additional works for safety and access requirements to upper floor
• New hall toilets and Public Toilet renovation
• Migration of ICRC to Community Hub
• Limited new space for music, exercise and training.
Operational Arrangements
• Develop Master agreement between three organisations
• Roles Assignment matrix
• Detailed procedures
• Issue resolution process
Pay a bill
Book a room
Detailed Procedures
ie OH&S
Roles Assignments
Operational Charter
Issue Resolution
Process
TH CoM
ICRC
LSC
Hire Agreement Hire conditions Hire period Hire procedures Hiring fees
Commercial Lease Agreement (std) • Lease conditions • Lease timing, • Outgoings
agreement • Rental fee
Community Hub – Operational Governance
Loddon Shire Council
Inglewood
Town Hall
S.86 Committee
Community
• Private Users
• Groups
• Business Users
Operational Charter • Key agreement between parties on operational procedures and division of responsibility • Revenue and cost sharing • Review process • Dispute process
• Schedule 1 – Hall yearly rental and hire rates
Community Planning
Finance
Councillors
Business
With ongoing lease
Inglewood
Community Resource
Centre Inc.
Building Town
Planning Environment
Health Legal
S86. Key Roles • Site & Building Management • Site services and payments • Site OH&S Policies • Routine meetings • Annual GM and Election Office Bearers
Tourism
V1 – 1/6/12
Commercial Lease Agreement (std) • Lease conditions • Lease timing, • Outgoings agreement • Rental fee
Hire Agreements • Hire conditions • Hire period • Hire procedures • Hiring fees
+
ICRC Inc. (or equiv) Key Roles • Day to day operation • Hire and rental agreements • Core training and servies support • Community Groups support • Site OH&S supervision
+ THCH Procedures
ICRC Procedures
Opportunity for Business Hub
• With addition funding streams, an up to date business hub can be incorporated within the precinct plans.
• Provision of several smaller business offices and “Board Room” style meeting room, provides opportunity for discrete meeting and presentation areas for adhoc or routine meetings.
• Video, Multi media, Audio conferencing facilities in modern environment
• Attract visiting professionals, provide offices, cater for small to larger conferences and support up to date communication needs
• Expands facilities for existing businesses and provides an opportunity for investment in the community
• Extends capability for Council and other Organisations to provide services on an outreach basis.
• Integrated and managed by Community Hub.
• Available for use by Shire, Bank, Hospital, out reach or visiting organisations, representatives, etc.
How did the Business hub come about?
• Review of Architect estimates and savings identified (assumed as turnkey and higher costs)
• Build can have more local management
• Clear lack of new “space” in original solution
• Review of design with 5.4m floor level to first floor, allows mezzanine floors @2.7m
• Additional requirements identified for stage access, lighting, ramp
• Need for solution for public/hall toilets to resolve security concerns
Can it work?
• Depends on planning permit, building regulations and ultimately the budget and funding.
• Does it make sense?
• Yes. Renovated space was 181m2. Increase is around 380m2, for a similar amount of funding (exc the toilets).
• Increase ROI and significantly enhances building utility and functionality.
• Need to develop risk matrix and strategies
Positive outcomes
for community
Tiers of Government
Initiatives
Community Groups and
Leaders
So how would it all look?
• Here’s our solution.
( a lot have been worked through and rejected !)
Consulting engineers have reviewed the design and
indicated it appears doable!
Laucke Mill expansions, Bridgewater Hub - Artist impression
Ground Floor
Renovate and refresh
New building
Example of Draft Plans
Verdon St Entry
Mezzanine Floor
Garden
Bed
Light Void - clear glazed
Up
Services
Riser
Activity
room
Cleaner &
Store
security
door
Plumbing
A/C Riser
Showe
r
Health &
Exercise
Multi-purpose
Health, Music
Workshop
Multi-purposeStore
room
Multi-purpose
Optional
Sick,
Quiet
room
VoidAbove
Ramp
Display
Depending on stage/ramp
height, this area may not
be possible Void
1400mm
Glass wall
Seminar
Cinema
Training
Multi purpose
Up
New building
Example of Draft Plans
Example of Draft Plans
Up
Fire
Fire
place
Roof
Balcony
Internet
Multi purpose
room
Multi purpose
Office
Light Void - clear glazed
Up
Services
RiserAudio
Visual
Pu
ll
do
wn
scre
en
whiteboard
Reception,
Office,
IT
Library
...
Suspended
Video projector
Fridge
under
bench
Plumbing
A/C Riser
Tea Bench
Office OfficeOffice
Board Room
Meeting
Room
wh
ite
bo
ard
Light Void - clear glazed 1400mm
Glass wall
Galvanised steel gantry – with
side mesh fence
Access to Terrace
ram
p
Ra
ise
d flo
or
(pro
jecto
r)
He
rita
ge
Dis
pla
y
up
Seminar
Cinema
Training
Multi purpose
Internet CafeOffice
Multi-
purpose
Renovate and refresh
New building
First Floor
Hub – Example of Elevations
Examples: many variation possible for final external form.
New
ScreenBowling Club Toilets
Remove
& repair
lawn
Storm Lane
Market St.
Ve
rdo
n S
t.
A
Garden
bed
Hub
Entry
New Public Toilets
Existing concrete / paving
Legend
Inglewood Town Hall – Site plan
Town HallMain hall entry
What next? When will build begin?
•Full building drawings and engineering calculations
•Planning permit and Health plans
•Energy ratings
•Soil test results
BuildingPermit
•Need good drawings and elevations
•Process has public communications and time for objections
•Resolution of any issues
•Planning Permit OK
•Heritage folk OK
Planning Permit
EOIOK?
All go ! Make it happen
N
$ OK?
N
Yes Yes
So when do we open?
RDAF Funding Expression of interest
Project must be
“Ready to Go”
•All documentation
•Alignment with Loddon Mallee region development strategies
• Requirements understood
• Plans drawn • Council
endorsed • Scope agreed • Funding
strategies known
• Solutions for water, sewer, SWD, power, A/C, etc
Plans
Project Timing (1 major project)
Key Documentation status
Have Action Final Who By
Requirements Document -Draft Power & Finish Reqmts - Draft New building Reqmts - Draft
Review Full Fit-out Requirements
PWG V1 - Oct 12 Final – Jun 13
Operational Arrangements – Concept documents only
Create Operational Arrangements Consultant June 13
Business Plan – Rough Draft Complete Project Business Plan Consultant V1 – Nov 12
Concept Plan Drawings – Bldg Details for remaining areas
Review Review
Concept plans - Final PWG Nov - 12
Full Technical Drawings - in conjunction with Cons Eng’g
Create Interim Final (Bldg permit)
Draftsman
Nov 12 Feb 13
Detailed Master Project Plan Inc pre works
Create Draft Final - Proj Mngr
PWG Proj Mngr
Nov 12 Jul 13
Project Budget – Draft Refine Match EOI s PWG Oct 12
Marketing collateral - draft Review Final PWG Aug 12
RDV Application – EOI / Application Create Full Application LSC CP/DPCD Aug 12
RDAF - EOI RDAF Application
Create Create
EOI Full Application
LSC Exec LSC Exec
Nov 12 Jan 13
Heritage - part of PP Review LSC Planning LSC TP na
Planning Permit Apply LSC Submit – (2-3mnths) PWG/LSC? Sept 12
Building Permit Apply LSC Submit - (2-3 mnths) PWG/LSC? Jan 13
Project Funding
• Initial Funding streams identified early in project: – Loddon Shire Community Planning (2011 – 2013) $250k
– State : RDV Project Planning $ 30k – State: Regional Development (PLF) on 2:1 basis: $400k – Philanthropic organisations $100k
Approximate total for preliminary project stages $ 780k
– This provided for the basic restoration work, access requirements, kitchen upgrade, toilet building, etc for the Community hub establishment.
– It doesn’t provide for the establishment of the business hub or additional restoration work, which would need to be funded and scheduled in later years.
Stage Construction
Cost Professional
Fees Contingency
Project Cost
Stage 1A - Existing building upgrade, lift and amenities $1,876,760 $281,514 $469,190 $2,627,464
Stage 2 B- Landscape $57,500 $10,000 $3,375 $70,875
Stage 2 - Stage & change rooms $77,000 $15,400 $13,475 $105,875
Stage 3 - Hall gallery $68,500 $13,700 $10,275 $92,475
Stage 4 - Foyer & administration $195,000 $29,250 $14,625 $238,875
Total $2,274,760 $349,864 $510,940 $3,135,564
DOCUMENT INTENT (source: Mitsuori report)
“This preliminary opinion of cost has been prepared at feasibility stage. It has been produced by applied general rates to key building floor areas and components to provide the client with an order of cost key components. It is indicative only and is not intended to be a cost plan for the project. Project cost analysis should be undertaken by a qualified Quantity Surveyor at commencement of the project.”
Works Budget – Mitsuori Estimates
Project works budget - single project
* V3 draft: Dependent on roof analysis, energy audit, equip hire, further trades & builder estimates, quantity surveyor review
Financial data has been somewhat dynamic as requirements understood and estimates refined
Budget Allocations Labor & Services Materials TOT (Exc) GST TOT (Inc)
Prework, Project Setup, Permits 75.0 0.0 75.0 7.5 82.5
Construction - Proj Manager 90.0 2.0 90.0 9.0 99.0
Basic Building integrity upgrade 158.0 68.0 226.0 22.6 248.6
Stairs and Foyer 15.0 10.0 25.0 2.5 27.5
Ground Front Rooms 6.0 4.0 10.0 1.0 11.0
New Entry - East Side (Glass & Concrete) 25.0 37.0 62.0 6.2 68.2
Kitchen & Store 61.0 88.5 149.5 15.0 164.5
Supper Room - Lights, a/c power and floor 15.0 11.0 26.0 2.6 28.6
Passage 31.0 15.0 46.0 4.6 50.6
Stage upgrade, Sound and Lighting 25.0 29.0 54.0 5.4 59.4
Stage Rooms 11.0 5.0 16.0 1.6 17.6
New building & toilets 425.8 469.9 895.7 89.6 985.2
First Foyer 6.0 4.0 10.0 1.0 11.0
First floor computer room 15.0 6.0 21.0 2.1 23.1
First floor office 5.0 2.0 7.0 0.7 7.7
Internal Balcony 40.0 30.0 70.0 7.0 77.0
First Floor and Projection Room 12.0 6.0 18.0 1.8 19.8
First floor MPR 10.0 4.0 14.0 1.4 15.4
Tower 10.0 10.0 20.0 2.0 22.0
A/C Ground & First floor 4.0 12.0 16.0 1.6 17.6
Misc Space & Cupboards 6.0 4.0 10.0 1.0 11.0
New addit furniture, fittings and misc 10.0 22.0 32.0 3.2 35.2
Comms, equip hire, misc 10.0 5.0 15.0 1.5 16.5
Roof Terrace & Access gantry 20.0 15.0 35.0 3.5 38.5
Hall (inc some HVAC) 25.0 31.0 56.0 5.6 61.6
Landscaping 50.0 20.0 70.0 7.0 77.0
TOTAL @ Today estimates 1160.8 910.4 2069.2 206.9 2276.1
Project contingency - 2012-2014 build 8% 2,234.7 223.5 2,458.2
Community Hub – Proposed Funding
Timeline 2012 2013 2014
Project 1 - n
2013
RDAF Round 3
n Selected Projects for funding
2013
RDV Putting Locals First Program
Selected Projects for funding
RDA Loddon Mallee – Southern Region
Stage
2
1A
1B
Community Planning Grants
2010 2011 2012
Community Planning Strategic Fund 2013 Uncertain potential
Philanthropic Funding
2014
RDAF Round 4
n selected Projects for funding
What if we don’t
get the money ?
• Plan B, or C or
…or wait.
Application with
RDV & RDA
Loddon Mallee
Community Planning Grants
Philanthropic Contributions
Other fund raising
RDV Grant?
Review
Revise Scope
Defer Project
N
Project Plan C
Reduced options
Minimum delivery
RDA Grant?
Y
Plan A - Full Stage 1 (A+B)
$ = L+ RDV & RDA
Project Timeline 1
Proceed with project
Y
Review
Analyse Rejection
Defer Project and re
submit next round?
N
Revise Scope
N
Plan B Part Stage 1A
$ = L+ RDV
Project Timeline 2
Proceed with project
Depends on $ budget
v Bare minimum hub
v Spouting upgrade
v Kitchen complete
v Electrical & min a/c
v Some painting
v No upper floor disability
access
v No Planning Permit
v Bldg Permit only?
Y
v Planning Permit
v Building Permit
v Roof & Spout upgrade
v Kitchen refit
v Renovate existing rooms
v Electrical Wiring & A/C
v New Toilets & Busn’s hub
with access lift
v Stage Ramp
v New Hub entrance
v Stage lighting
v Old toilet removal &
landscaping
Potential Future works
(identified in strategic plan)
v Hall ceiling restoration
v Sound engineering
v Stage redevelopment
v Fit-out for any remaining hub
areas
v Tower restoration
v Clock upgrade
v Main Hall A/C
v Market St. parking realignment
Y
RDA Round 3 - Loddon Mallee region
EOI anticipated to be Nov 2012
If shortlisted, full application requested
(perhaps Dec -Jan13)
RDV – Can submit
application at any time.
Max $500k 1:2
Community Hub / Inglewood Town Hall
Project & Funding Strategy Strategic Plan
deployment
N
Defer
Project?
Y
RDV Accept
scope change?N
NDepends on $ budget
v No Hub
v Spouting upgrade
v Kitchen basic
v No upper floor access
v No Planning permit
v Building permit required ?
v THC manage project
RDV leverage
Threshhold?N
Y
1
1
1
Note:
Inclusion of items in plans depends on
more accurate quotations for supply
and installation.
Assumes project management by
LSC for larger projects.
Funding Linkages
Local RDV RDAF(CP + Other Org)
Philanthropic 150 1:3
Project Planning 10 30
143
1:2 1:1
500 500 810
803 530 810
Total Funding 2,143 k
Key issue for multi stage projects: Limited build whilst retaining captial seed funding ratios
Staged new build impact Note: Any additional rework due to split project not factored in.
165.1
143.4
729.2
234.5
227.0
204
77 0 202
0100200300400500600700800900
1,0001,1001,2001,3001,4001,5001,6001,7001,8001,9002,0002,100
Do
llars
(,0
00
)
Single Build, Stage Funding Exc GST
165.1
143.4
555.1
234.5
227.0
204.0
77.0
174.1
202.0
0100200300400500600700800900
100011001200130014001500160017001800190020002100
Shell build, Stage Funding Exc GST
Risk Management • The risk management matrix requires further working group review.
• The key project risks are associated with funding availability; particularly seed funding to achieve the required funds to match grant conditions.
• Medium are budget issues e.g. roof replacement, fire pump required
• Lower risks identified can generally be overcome by project staging or resubmission of applications.
9-10 0 0 1 0 0
Impact7-8 1 0 1 1 0
5-6 1 1 1 0 0Funding rejections - LSC, RDV, RDA
3-4 1 1 0 0 0
1-2 3 2 0 0 0Resdesigns, delays,
1-20% 21-40% 41-60% 61-80% 81-100%
Major project proceeding issues, Overbudget at build,
Fire systems, New roof
Zone Total: 2
Zone Total: 2
Zone Total: 10
Probability
Project Risk Matrix
Discussion Q&A
Next Steps • Public forum @ Town Hall- Sept 30 • Council executive to sign off on project strategy • Roofing assessment and water damage • Awaiting outcome from Project Planning (RDV) grant $30k
– Initiate: – EOI bid consultancy , energy audit, engineering report – Initiate building drawings (up to 3 mnths)
• Submission of EOI for funding streams (RDV) – can submit now • Submission of RDAF round when announced (anticipated Nov 12)
• Initiate detailed building plans and eng’ng calculations • Submit Planning Permit. • Finalisation of project group documentation • …………..await funding bid outcomes
Q & A
Thankyou for your time and attention.