18
PRELIMINARY DAMAGE ASSESSMENT REPORT FOR Construction of Commercial Complex “Spaze Corporate Parkk” At Sector-69,70, District- Gurgaon, Haryana Being Developed By: - M/s Spaze Towers Pvt. Limited. Spazedge Commercial Complex Sector-47, Gurgaon Sohna Road Gurgaon- 122002, Haryana BY Environmental Consultant M/s Perfact Enviro Solutions Pvt. Ltd. (NABET Registered wide list of accredited consultants organizations/ Rev 51/March 2017 at S. No-114) 502-507, NN Mall, Sector-3, Rohini, New-Delhi-85 Phone: 011-49281360

PRELIMINARY DAMAGE ASSESSMENT REPORTenvironmentclearance.nic.in/writereaddata/... · PRELIMINARY DAMAGE ASSESSMENT REPORT ... The site visit of project site was conducted by members

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

PRELIMINARY DAMAGE ASSESSMENT

REPORT

FOR

Construction of Commercial Complex “Spaze Corporate Parkk”

At

Sector-69,70, District- Gurgaon, Haryana

Being Developed By: -

M/s Spaze Towers Pvt. Limited.

Spazedge Commercial Complex

Sector-47, Gurgaon Sohna Road

Gurgaon- 122002, Haryana

BY

Environmental Consultant

M/s Perfact Enviro Solutions Pvt. Ltd.

(NABET Registered wide list of accredited consultants organizations/ Rev

51/March 2017 at S. No-114)

502-507, NN Mall, Sector-3, Rohini, New-Delhi-85

Phone: 011-49281360

CONTENT

1. Introduction

2. Environmental Legislation Applicable

3. Project Details

4. Environmental Damage Assessment

INTRODUCTION

M/S Spaze Towers Pvt. Ltd. has made a collaboration agreement with land owners of land

area 15503.482 sqm. On 27.06.2010 located at Khasra No. 20//21//2//22 , 16//17/1 min (0K-

15M), 1/2 min (31K-13M) Village Badshahpur, District- Gurgaon, Haryana. The land owners

have obtained the license from DTCP (Directorate of Town & Country Planning), Haryana on

27.06.2010.

M/S Spaze Towers Pvt. Ltd. has conceptualised the Commercial Complex on above area and

obtained approval of building plan.

The application for Environmental Clearance was submitted to SEIAA, Haryana on 18.06.2012.

It was appraised by SEAC, Haryana few queries were raised and the reply for the same was

submitted to SEAC on 10.09.2012.

The site visit of project site was conducted by members of SEAC. The Environmental Clearance

of the project was rejected, due to non-compliance of the Environmental Clearance and

starting the construction prior EC.

Now, as per gazette notification dated 14.03.2017 we are submitting the details for EC as per

the said notification as violation case.

ENVIRONMENTAL LEGISLATION APPLICABLE:

Following legislations are applicable to the project. Therefore, it is the responsibility of the

developer to comply with these legislations.

➢ THE WATER (PREVENTION AND CONTROL OF POLLUTION) ACT 1974

Under Section 25. Restrictions on New Outlets and New Discharges

– Applicable due to discharge of waste water from the group housing colony.

– Under the above-mentioned act, we shall take consent “consent to establish” &

“consent to operate” of the State Pollution Control Board.

➢ THE AIR (PREVENTION AND CONTROL OF POLLUTION) ACT, 1981

Under section 21. Restrictions on use of certain industrial plants.

– Applicable due to provision of DG Sets which will be source of air emission to

atmosphere. Stack shall be installed.

– Under the above mentioned act, we shall take consent “consent to establish” &

“consent to operate” from the State Pollution Control Board.

➢ THE WATER (PREVENTION AND CONTROL OF POLLUTION) CESS ACT, 1977

Under Section 3: Levy and Collection of Cess

– There shall be levied and collected a cess for the purpose of the Water (Prevention

and Control of Pollution) Act, 1974 (6 of 1974) and utilization there under.

– The cess under sub-section (1) shall be payable by—

– Every person extracting water from ground.

– Everyone using supply water.

➢ S.O.908 (E), [25/9/2000] - THE MUNICIPAL SOLID WASTES (MANAGEMENT AND

HANDLING) RULES, 2000 and as amended

As per this rule solid waste is to be segregated and disposed as per defined procedure at

MSW approved site or within its own colony by using different solid waste disposed

technologies.

➢ HAZARDOUS WASTES (MANAGEMENT, HANDLING & TRANSBOUNDRY MOVEMENT)

RULES, 2008 amended in 2016

– Hazardous wastes shall be collected, treated, stored at isolated locations.

– It will be given to authorized recyclers/ service providers only.

– Authorization under this rule shall be taken from SPCB.

➢ E-WASTE (MANAGEMENT & HANDLING) RULES, 2016

– E-waste shall be collected and stored at isolated location in the Complex.

– It shall be disposed through approved recycler only.

➢ PLASTIC WASTE MANAGEMENT RULES 2016

– Plastic waste shall be collected and disposed as per Plastic Waste Management Rules

2016

➢ CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT RULES 2016

– The Ministry of Environment, Forest and Climate Change notified the Construction &

Demolition Waste Management Rules, 2016 on 29 March 2016.

– Construction and demolition waste shall be disposed and managed as per C& D

Waste Management Rules 2016

➢ THE NOISE POLLUTION (REGULATION AND CONTROL) RULES, 2000

– The noise levels in any area shall not exceed the ambient noise quality standards in

respect of noise as specified in the schedule.

– The authority shall be responsible for the enforcement of noise pollution control

measures and the due compliance of the ambient noise quality standards in respect

of noise.

➢ EIA NOTIFICATION, 2006 AND AMENDMENTS

EIA Notification, 2006 falls under EPA, 1986 under this act any project which has probable impact

on the environment is listed under 34 categories, then unit are required to take prior

environmental clearance after occupying/identifying the land for particular use.

The project comes under category “B” & listed in 8(a) schedule as per EIA notification, 2006.

All projects or activities in the schedule, whether expansion and modernization of existing

projects or activities and change in product mix shall require prior environmental clearance

from the MoEF&CC/State Environmental Impact Assessment Authority (SEIAA) or in absence

of SEIAA, Central Government in the ministry of Environment and Forests on the

recommendation of Expert Appraisal Committee to be constituted by the Central

Government.

AMENDMENTS:

MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE NOTIFICATION

dated 9th December, 2016

– The integrated environmental conditions with the building permission being granted

by the local authorities and the construction of buildings as per the size shall adhere

to the objectives and monitorable environmental conditions

– The States adopting the objectives and monitorable environmental conditions

referred to in subparagraph(1), in the building bye-laws and relevant State laws and

incorporating these conditions in the approvals given for building construction making

it legally enforceable shall not require a separate environmental clearance from the

Ministry of Environment, Forest and Climate Change for individual buildings.

– When the State Governments notifies the bye-laws and rules concurred by the

Ministry of Environment, Forest and Climate Change, the Central Government may

issue an order stating that no separate environmental clearance is required for

buildings to be constructed in the States or local authority areas.

MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE

NOTIFICATION 14th March, 2017

• In case the projects or activities requiring prior environmental clearance under

Environment Impact Assessment Notification, 2006 from the concerned Regulatory

Authority are brought for environmental clearance after starting the construction

work, or have undertaken expansion, modernization, and change in product- mix

without prior environmental clearance, these projects shall be treated as cases of

violations and in such cases, even Category B projects which are granted

environmental clearance by the State Environment Impact Assessment Authority

constituted under sub-section (3) Section 3 of the Environment (Protection) Act,

1986 shall be appraised for grant of environmental clearance only by the Expert

Appraisal Committee and environmental clearance will be granted at the Central

level.

• In cases of violation, action will be taken against the project proponent by the

respective State or State Pollution Control Board under the provisions of section 19 of

the Environment (Protection) Act, 1986 and further, no consent to operate or

occupancy certificate will be issued till the project is granted the environmental

clearance.

PROJECT DETAILS AND DESCRIPION

The proposed project Construction of Commercial Complex “Spaze Corporate Park” is

proposed at Sector- 69-70, District-Gurgaon, Haryana. The project will be developed by M/s

Spaze Tower Pvt. Ltd. Built-up area of the project is 46264.209 Sqm.

Site location and Connectivity

The proposed commercial complex is located at Sector- 69-70, District-Gurgaon, Haryana. The

nearest railway station is Basai Dhankot Railway Station is ~9.0 km in NNW direction and

Indira Gandhi International Airport is approximate 21.0 km in NNE direction.

AREA DETAILS: Project details along with detailed area break-up are given below:

Table 1. Area details

S.No. Particulars Total

1. Type of Project Commercial Complex

2. Total Plot Area 15503.482 sq m (3.83 Acre)

3. Ground Coverage (Permissible)

(40%)

6201.393 sq m

4. Ground Coverage (Achieved)

(34.11%)

5288.256 sq m

5. F.A.R (Permissible) (1.75) 27131.09 sq m

6. F.A.R (Proposed) (1.74) 26979.651 sq m

7. Basement Area – Tower A 14413.018 sq m

8. Basement Area – Tower B 4871.54 sq m

9. Total Basement area 19284.558 sq m

10. Total Built up Area (FAR+ +

Basement Area)

46264.209 sq m

11. Green Area (16.47 %) 2553.75 sq m

12. Road Area, open area & surface

parking area

7661.476 sq m

13. No. of Floors G+12

14. Levels of Basement 3 No.

15. Height of Building (Tower A) 58.6 m

16. Height of Building (Tower B) 42.6 m

Construction Status

S no

Floors Slab Leve

l

Internal

Brickwork

External Brickwor

k

Interna

l Plaster

Externa

l plaster

1 12th Floor

100% 95% 100% 95% 50%

2 11th Floor

100% 95% 100% 95% 50%

3 10th Floor

100% 95% 100% 95% 50%

4 9th Floor

100% 95% 100% 95% 50%

5 8th Floor

100% 95% 100% 95% 50%

6 7th Floor

100% 95% 100% 95% 50%

7 6th Floor

100% 95% 100% 95% 50%

8 5th Floor

100% 95% 100% 95% 50%

9 4th Floor

100% 95% 100% 95% 50%

10 3rd Floor

100% 95% 100% 95% 50%

11

2nd/service Floor

100% 95% 100% 95% 50%

12 01st Floor

100% 95% 100% 95% 50%

13 Ground Floor

100% 95% 95% 95% 50%

14 Basement 1

100% 95% N/A 95% 100%

15 Basement 2

100% 95% N/A 95% 100%

16 Basement 3

100% 95% N/A 95% 100%

Site Photographs

BUILDING CONSTRUCTION PROCESS

STEPS WORK

ENVIRONMENTAL ASPECTS

EMISSIONS TO AIR

RELEASES TO WATER

WASTE GENERATION

LAND CONTAMINATION

USE OF NATURAL RESOURCES AND RAW MATERIALS LOCAL ISSUES

TRA

NSP

OR

T IS

SUES

ENV

IRO

NM

ENTA

L A

CC

IDEN

TS

EFFE

CTS

ON

BIO

DIV

ERSI

TY

No

ise

Po

lluti

on

Soil

Qu

alit

y an

d M

anag

em

en

t

Ge

olo

gy

Hyd

rolo

gy

Current Status P

M

Gas

eo

us

Emis

sio

ns

Exe

cuti

on

of

fou

nd

atio

ns

and

re

tain

ing

wal

ls

Cle

anin

g p

roce

ss o

f m

ach

ine

ry &

to

ols

San

itar

y w

ate

r

C &

D w

aste

No

n-H

azar

do

us

Haz

ard

ou

s

Use

of

con

cre

te r

ele

ase

an

d s

urf

ace

cle

ain

g ag

en

ts

Du

mp

ing

of

oth

er

liqu

id w

aste

chan

ge

in

nat

ura

l d

rain

age

&

Top

ogr

aph

y

Wat

er

Ene

rgy

Raw

Mat

eri

als

No

ise

an

d v

ibra

tio

ns

Od

ou

r

Du

st

Lan

dsc

ape

Alt

era

tio

n

STEP 1 Land occupation 100

STEP 2

Removal of vegetation or old buildings 100 -1 -3 -3 -4 -3 -3 -4 -4 -2 -4 -2

STEP 3 Excavation work 100 -3 -1 -1 -1 -3 -1 -4 -1

-3 -4 -4 -3 -4 -1 -4 -4 -3

STEP 4 Foundation 100 -2 -1 -2 -1 -1 -4 -1 -2 -2 -2 -3 -3 -3 -2 -3 -2 -2

STEP 5 Piling 100 -2 -1 -2 -1 -1 -4

-

3 -2 -2 -2

STEP 6 RCC Work 100 -3 -2 -3 -2 -2 -3 -1 -3 -2 0 -3 -2 -4 -2 -2 -2 -1

STEP 7 Masonary Work 100 -2 -1 -3 -1 -1 -3 -1 -2 -1 -3 -2 -4

-2 -2 -2 -2

STEP 8 Roofs 100 -2 -2 -3 -2 -1 -3 -1 -2 -1 0 -3 -2 -4 -2 -2 -2 -2

STEP 9

Timber work (Door and windows) 100 -2 -1 -2 -4

-

2 -2 -3 -2

STEP 10

Piping of water & sewage 100 -2 -3 -2 -2

STEP 11

Drainage system 100 -2 -2 -2 -2 3 -2 -2 -2

-1

-3 -1 -1 -1 -2

3

STEP 12

Sewage Treatment Plant 100 -2 -1 -2 3 -2 -2 -1 3 4 4 -2 -2 -2

-3 -1 4 4 4

3

STEP 13

Rainwater Harvesting 20 -2 -2 -2 -2 -1 -2 3 -2 -2 -2

-1 -1

STEP 14 Plantation 20 3 3 2 2 1 1 2 2 2 4 3 3 2 2 3 3 4 4 3 3 4 3 3 2

3

STEP 15 Roads 20 -3 -2 -2 -2 -2 -2 -3

-

3 -2 -3 -3 -3 -3

STEP 16

Installation of Electrical and mechanical items & fire 20 -1 -2 -3 -3 -4 0 -3

-

2 -2

STEP 17 Plastering 70 -3 -3 -3 -2 -3

-2 -2

STEP 18

Bathroom fitting & Plumbing work 10 -2 -1 -2 -2 -2 -2 0 -4 -2

-

3

-

1 -3

STEP 19 Flooring 10 -3 -1 -1 -2 -2 -3 0 -3 -2

-3

-1 -3

STEP 20

Painting and exteriors 80 -4 -3 -3 -4 -2 -3 -3 -3 -2 -4 -1

Total -32 -15 -18 -5 -2 -31 -15 -13 -22 -5 -1 -23 -29 -42

-26

-8

-23 -5 -19 1 4 -24 5 -13 1

Damage Assessment Matrix

ENVIRONMENTAL BASELINE MATRIX

S. No. Identification Damage Evaluation

Environmental Element/ Units

Base Scale Impact

(Percentage %) (Negative/Positive)

1 Emissions to Air 29.37 % Negative

2 Releases to Water 10.41 % Negative

3 Waste Generation 24.58 % Negative

4 Land Contamination 11.66 % Negative

5 Use of natural resources and raw materials

39.16 % Negative

6 Local Issues 19.37 % Negative

7 Transport Issues 23.75 % Negative

8 Environmental Accidents 1.25 % Positive

9 Effects on Biodiversity 5 % Positive

10 Noise Pollution 30 % Negative

110 Soil Quality and Management 6.25 % Positive

12 Geology 16.25 % Negative

13 Hydrology 1.25 % Positive

Scale of Measurement

1 Major

2 Moderate

3 Minor

4 Negligible

0 None

-1 Negligible

-2 minor

-3 Moderate

-4 Major

DAMAGE ASSESSMENT

For assessment of damage to environment following Environmental aspects has been

identified: -

1. Air Quality: Deterioration due to air emission

2. Water Environment: Due to groundwater exploitation pollution in water bodies.

3. Soil Quality: Due to unorganised solid waste management, land contamination and

unplanned disposal of soil.

4. Exploitation of Natural resources.

5. Socio Economic scenario of the surrounding areas.

6. Environmental accidents.

7. Ecology & Biodiversity

8. Noise levels

9. Geological changes

10. Hydrological changes

To assess these environmental parameters team has been deputed to assess preliminary

assessment of damage to environment.

Based on site inspection and the documentary evidences the environmental aspects vs

activity has been filled.

SUMMARY OF ENVIRONMENTAL DAMAGE

Ambient Air Quality

The project work was started in march, 2013. Due to summer season dust emission was there.

The machineries & DG sets generated air emissions.

Water Generation

Since ground water table is quite low there was no dewatering done. Occasional ground water

was used due to scarcity of water. However most of the water is procured through tanker.

Waste Generation

Construction & demolition waste was generated and it was used in refilling of low lying area

& roads.

Non-Hazardous waste like packaging material wood, carton & plastics are sold to recycler.

Only Hazardous waste was paint and used oils. The used oil has been sold to recyclers.

Land Contamination

There was a defined space for construction machinery and land contamination was done to

spillage of oil.

There was no spillage of cleaning agent however concrete mixture was dumped at few places.

All the liquid were stored in drum and no spillage of any liquid were reported. The toilets were

having soak pits no surface water discharge.

The project plot was agriculture land and no natural drain was passing through the plot.

Use of Natural Resources

Water was taken through tanker; no ground water is used. Energy use was through diesel and

petrol.

Raw Material was RCC (Through RMC), Iron & Steel (From Secondary Steel), Cement, Door &

Windows were made-up of timber (Hence natural resources were used). Stone is used for

flooring tiles used in bathroom & Kitchen.

Local Issues

The nearest habitat is Rampur which is 1 Km in N direction. There were other projects in the

vicinity and no local issues. There was noise during construction activities. Dust was generated

during excavation & transportation.

The land was agriculture land and converted into residential purpose.

Transport Issue

The transportation of material was done using Rampur.

Due to well-maintained approach road dust generation was quite low.

Environmental Accident

The project work was done by experienced and qualified contractor hence no environmental

accident like land subsidence or land slide happened.

Effect on biodiversity

The land was an agriculture land and hence there was no significant flora & fauna. However,

with organized plantation after completion of project biodiversity will improve.

Noise Pollution

The area was earlier an agriculture is and there were no noise sources in the vicinity. However,

with construction activity noise level is increased.

Soil quality & Management

The project was conceptualized with 3 level basements hence soil excavation was essential.

Mining permission was taken from Department of Mines & Geology, Gurugram.

The excess soil was given by contractor for refilling of low lying area.

Geology

There was no mineral at project site and there was only ordinary soil. The soil excavation and

construction of basement has changed the geological profile.

Hydrology

There was no use of ground water in the area. The depletion of ground water in the area is

due to over exploitation of ground water by operational industrial & commercial units.