Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
PRELIMINARY DAMAGE ASSESSMENT
REPORT
FOR
Construction of Commercial Complex “Spaze Corporate Parkk”
At
Sector-69,70, District- Gurgaon, Haryana
Being Developed By: -
M/s Spaze Towers Pvt. Limited.
Spazedge Commercial Complex
Sector-47, Gurgaon Sohna Road
Gurgaon- 122002, Haryana
BY
Environmental Consultant
M/s Perfact Enviro Solutions Pvt. Ltd.
(NABET Registered wide list of accredited consultants organizations/ Rev
51/March 2017 at S. No-114)
502-507, NN Mall, Sector-3, Rohini, New-Delhi-85
Phone: 011-49281360
CONTENT
1. Introduction
2. Environmental Legislation Applicable
3. Project Details
4. Environmental Damage Assessment
INTRODUCTION
M/S Spaze Towers Pvt. Ltd. has made a collaboration agreement with land owners of land
area 15503.482 sqm. On 27.06.2010 located at Khasra No. 20//21//2//22 , 16//17/1 min (0K-
15M), 1/2 min (31K-13M) Village Badshahpur, District- Gurgaon, Haryana. The land owners
have obtained the license from DTCP (Directorate of Town & Country Planning), Haryana on
27.06.2010.
M/S Spaze Towers Pvt. Ltd. has conceptualised the Commercial Complex on above area and
obtained approval of building plan.
The application for Environmental Clearance was submitted to SEIAA, Haryana on 18.06.2012.
It was appraised by SEAC, Haryana few queries were raised and the reply for the same was
submitted to SEAC on 10.09.2012.
The site visit of project site was conducted by members of SEAC. The Environmental Clearance
of the project was rejected, due to non-compliance of the Environmental Clearance and
starting the construction prior EC.
Now, as per gazette notification dated 14.03.2017 we are submitting the details for EC as per
the said notification as violation case.
ENVIRONMENTAL LEGISLATION APPLICABLE:
Following legislations are applicable to the project. Therefore, it is the responsibility of the
developer to comply with these legislations.
➢ THE WATER (PREVENTION AND CONTROL OF POLLUTION) ACT 1974
Under Section 25. Restrictions on New Outlets and New Discharges
– Applicable due to discharge of waste water from the group housing colony.
– Under the above-mentioned act, we shall take consent “consent to establish” &
“consent to operate” of the State Pollution Control Board.
➢ THE AIR (PREVENTION AND CONTROL OF POLLUTION) ACT, 1981
Under section 21. Restrictions on use of certain industrial plants.
– Applicable due to provision of DG Sets which will be source of air emission to
atmosphere. Stack shall be installed.
– Under the above mentioned act, we shall take consent “consent to establish” &
“consent to operate” from the State Pollution Control Board.
➢ THE WATER (PREVENTION AND CONTROL OF POLLUTION) CESS ACT, 1977
Under Section 3: Levy and Collection of Cess
– There shall be levied and collected a cess for the purpose of the Water (Prevention
and Control of Pollution) Act, 1974 (6 of 1974) and utilization there under.
– The cess under sub-section (1) shall be payable by—
– Every person extracting water from ground.
– Everyone using supply water.
➢ S.O.908 (E), [25/9/2000] - THE MUNICIPAL SOLID WASTES (MANAGEMENT AND
HANDLING) RULES, 2000 and as amended
As per this rule solid waste is to be segregated and disposed as per defined procedure at
MSW approved site or within its own colony by using different solid waste disposed
technologies.
➢ HAZARDOUS WASTES (MANAGEMENT, HANDLING & TRANSBOUNDRY MOVEMENT)
RULES, 2008 amended in 2016
– Hazardous wastes shall be collected, treated, stored at isolated locations.
– It will be given to authorized recyclers/ service providers only.
– Authorization under this rule shall be taken from SPCB.
➢ E-WASTE (MANAGEMENT & HANDLING) RULES, 2016
– E-waste shall be collected and stored at isolated location in the Complex.
– It shall be disposed through approved recycler only.
➢ PLASTIC WASTE MANAGEMENT RULES 2016
– Plastic waste shall be collected and disposed as per Plastic Waste Management Rules
2016
➢ CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT RULES 2016
– The Ministry of Environment, Forest and Climate Change notified the Construction &
Demolition Waste Management Rules, 2016 on 29 March 2016.
– Construction and demolition waste shall be disposed and managed as per C& D
Waste Management Rules 2016
➢ THE NOISE POLLUTION (REGULATION AND CONTROL) RULES, 2000
– The noise levels in any area shall not exceed the ambient noise quality standards in
respect of noise as specified in the schedule.
– The authority shall be responsible for the enforcement of noise pollution control
measures and the due compliance of the ambient noise quality standards in respect
of noise.
➢ EIA NOTIFICATION, 2006 AND AMENDMENTS
EIA Notification, 2006 falls under EPA, 1986 under this act any project which has probable impact
on the environment is listed under 34 categories, then unit are required to take prior
environmental clearance after occupying/identifying the land for particular use.
The project comes under category “B” & listed in 8(a) schedule as per EIA notification, 2006.
All projects or activities in the schedule, whether expansion and modernization of existing
projects or activities and change in product mix shall require prior environmental clearance
from the MoEF&CC/State Environmental Impact Assessment Authority (SEIAA) or in absence
of SEIAA, Central Government in the ministry of Environment and Forests on the
recommendation of Expert Appraisal Committee to be constituted by the Central
Government.
AMENDMENTS:
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE NOTIFICATION
dated 9th December, 2016
– The integrated environmental conditions with the building permission being granted
by the local authorities and the construction of buildings as per the size shall adhere
to the objectives and monitorable environmental conditions
– The States adopting the objectives and monitorable environmental conditions
referred to in subparagraph(1), in the building bye-laws and relevant State laws and
incorporating these conditions in the approvals given for building construction making
it legally enforceable shall not require a separate environmental clearance from the
Ministry of Environment, Forest and Climate Change for individual buildings.
– When the State Governments notifies the bye-laws and rules concurred by the
Ministry of Environment, Forest and Climate Change, the Central Government may
issue an order stating that no separate environmental clearance is required for
buildings to be constructed in the States or local authority areas.
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE
NOTIFICATION 14th March, 2017
• In case the projects or activities requiring prior environmental clearance under
Environment Impact Assessment Notification, 2006 from the concerned Regulatory
Authority are brought for environmental clearance after starting the construction
work, or have undertaken expansion, modernization, and change in product- mix
without prior environmental clearance, these projects shall be treated as cases of
violations and in such cases, even Category B projects which are granted
environmental clearance by the State Environment Impact Assessment Authority
constituted under sub-section (3) Section 3 of the Environment (Protection) Act,
1986 shall be appraised for grant of environmental clearance only by the Expert
Appraisal Committee and environmental clearance will be granted at the Central
level.
• In cases of violation, action will be taken against the project proponent by the
respective State or State Pollution Control Board under the provisions of section 19 of
the Environment (Protection) Act, 1986 and further, no consent to operate or
occupancy certificate will be issued till the project is granted the environmental
clearance.
PROJECT DETAILS AND DESCRIPION
The proposed project Construction of Commercial Complex “Spaze Corporate Park” is
proposed at Sector- 69-70, District-Gurgaon, Haryana. The project will be developed by M/s
Spaze Tower Pvt. Ltd. Built-up area of the project is 46264.209 Sqm.
Site location and Connectivity
The proposed commercial complex is located at Sector- 69-70, District-Gurgaon, Haryana. The
nearest railway station is Basai Dhankot Railway Station is ~9.0 km in NNW direction and
Indira Gandhi International Airport is approximate 21.0 km in NNE direction.
AREA DETAILS: Project details along with detailed area break-up are given below:
Table 1. Area details
S.No. Particulars Total
1. Type of Project Commercial Complex
2. Total Plot Area 15503.482 sq m (3.83 Acre)
3. Ground Coverage (Permissible)
(40%)
6201.393 sq m
4. Ground Coverage (Achieved)
(34.11%)
5288.256 sq m
5. F.A.R (Permissible) (1.75) 27131.09 sq m
6. F.A.R (Proposed) (1.74) 26979.651 sq m
7. Basement Area – Tower A 14413.018 sq m
8. Basement Area – Tower B 4871.54 sq m
9. Total Basement area 19284.558 sq m
10. Total Built up Area (FAR+ +
Basement Area)
46264.209 sq m
11. Green Area (16.47 %) 2553.75 sq m
12. Road Area, open area & surface
parking area
7661.476 sq m
13. No. of Floors G+12
14. Levels of Basement 3 No.
15. Height of Building (Tower A) 58.6 m
16. Height of Building (Tower B) 42.6 m
Construction Status
S no
Floors Slab Leve
l
Internal
Brickwork
External Brickwor
k
Interna
l Plaster
Externa
l plaster
1 12th Floor
100% 95% 100% 95% 50%
2 11th Floor
100% 95% 100% 95% 50%
3 10th Floor
100% 95% 100% 95% 50%
4 9th Floor
100% 95% 100% 95% 50%
5 8th Floor
100% 95% 100% 95% 50%
6 7th Floor
100% 95% 100% 95% 50%
7 6th Floor
100% 95% 100% 95% 50%
8 5th Floor
100% 95% 100% 95% 50%
9 4th Floor
100% 95% 100% 95% 50%
10 3rd Floor
100% 95% 100% 95% 50%
11
2nd/service Floor
100% 95% 100% 95% 50%
12 01st Floor
100% 95% 100% 95% 50%
13 Ground Floor
100% 95% 95% 95% 50%
14 Basement 1
100% 95% N/A 95% 100%
15 Basement 2
100% 95% N/A 95% 100%
16 Basement 3
100% 95% N/A 95% 100%
BUILDING CONSTRUCTION PROCESS
STEPS WORK
ENVIRONMENTAL ASPECTS
EMISSIONS TO AIR
RELEASES TO WATER
WASTE GENERATION
LAND CONTAMINATION
USE OF NATURAL RESOURCES AND RAW MATERIALS LOCAL ISSUES
TRA
NSP
OR
T IS
SUES
ENV
IRO
NM
ENTA
L A
CC
IDEN
TS
EFFE
CTS
ON
BIO
DIV
ERSI
TY
No
ise
Po
lluti
on
Soil
Qu
alit
y an
d M
anag
em
en
t
Ge
olo
gy
Hyd
rolo
gy
Current Status P
M
Gas
eo
us
Emis
sio
ns
Exe
cuti
on
of
fou
nd
atio
ns
and
re
tain
ing
wal
ls
Cle
anin
g p
roce
ss o
f m
ach
ine
ry &
to
ols
San
itar
y w
ate
r
C &
D w
aste
No
n-H
azar
do
us
Haz
ard
ou
s
Use
of
con
cre
te r
ele
ase
an
d s
urf
ace
cle
ain
g ag
en
ts
Du
mp
ing
of
oth
er
liqu
id w
aste
chan
ge
in
nat
ura
l d
rain
age
&
Top
ogr
aph
y
Wat
er
Ene
rgy
Raw
Mat
eri
als
No
ise
an
d v
ibra
tio
ns
Od
ou
r
Du
st
Lan
dsc
ape
Alt
era
tio
n
STEP 1 Land occupation 100
STEP 2
Removal of vegetation or old buildings 100 -1 -3 -3 -4 -3 -3 -4 -4 -2 -4 -2
STEP 3 Excavation work 100 -3 -1 -1 -1 -3 -1 -4 -1
-3 -4 -4 -3 -4 -1 -4 -4 -3
STEP 4 Foundation 100 -2 -1 -2 -1 -1 -4 -1 -2 -2 -2 -3 -3 -3 -2 -3 -2 -2
STEP 5 Piling 100 -2 -1 -2 -1 -1 -4
-
3 -2 -2 -2
STEP 6 RCC Work 100 -3 -2 -3 -2 -2 -3 -1 -3 -2 0 -3 -2 -4 -2 -2 -2 -1
STEP 7 Masonary Work 100 -2 -1 -3 -1 -1 -3 -1 -2 -1 -3 -2 -4
-2 -2 -2 -2
STEP 8 Roofs 100 -2 -2 -3 -2 -1 -3 -1 -2 -1 0 -3 -2 -4 -2 -2 -2 -2
STEP 9
Timber work (Door and windows) 100 -2 -1 -2 -4
-
2 -2 -3 -2
STEP 10
Piping of water & sewage 100 -2 -3 -2 -2
STEP 11
Drainage system 100 -2 -2 -2 -2 3 -2 -2 -2
-1
-3 -1 -1 -1 -2
3
STEP 12
Sewage Treatment Plant 100 -2 -1 -2 3 -2 -2 -1 3 4 4 -2 -2 -2
-3 -1 4 4 4
3
STEP 13
Rainwater Harvesting 20 -2 -2 -2 -2 -1 -2 3 -2 -2 -2
-1 -1
STEP 14 Plantation 20 3 3 2 2 1 1 2 2 2 4 3 3 2 2 3 3 4 4 3 3 4 3 3 2
3
STEP 15 Roads 20 -3 -2 -2 -2 -2 -2 -3
-
3 -2 -3 -3 -3 -3
STEP 16
Installation of Electrical and mechanical items & fire 20 -1 -2 -3 -3 -4 0 -3
-
2 -2
STEP 17 Plastering 70 -3 -3 -3 -2 -3
-2 -2
STEP 18
Bathroom fitting & Plumbing work 10 -2 -1 -2 -2 -2 -2 0 -4 -2
-
3
-
1 -3
STEP 19 Flooring 10 -3 -1 -1 -2 -2 -3 0 -3 -2
-3
-1 -3
STEP 20
Painting and exteriors 80 -4 -3 -3 -4 -2 -3 -3 -3 -2 -4 -1
Total -32 -15 -18 -5 -2 -31 -15 -13 -22 -5 -1 -23 -29 -42
-26
-8
-23 -5 -19 1 4 -24 5 -13 1
Damage Assessment Matrix
ENVIRONMENTAL BASELINE MATRIX
S. No. Identification Damage Evaluation
Environmental Element/ Units
Base Scale Impact
(Percentage %) (Negative/Positive)
1 Emissions to Air 29.37 % Negative
2 Releases to Water 10.41 % Negative
3 Waste Generation 24.58 % Negative
4 Land Contamination 11.66 % Negative
5 Use of natural resources and raw materials
39.16 % Negative
6 Local Issues 19.37 % Negative
7 Transport Issues 23.75 % Negative
8 Environmental Accidents 1.25 % Positive
9 Effects on Biodiversity 5 % Positive
10 Noise Pollution 30 % Negative
110 Soil Quality and Management 6.25 % Positive
12 Geology 16.25 % Negative
13 Hydrology 1.25 % Positive
Scale of Measurement
1 Major
2 Moderate
3 Minor
4 Negligible
0 None
-1 Negligible
-2 minor
-3 Moderate
-4 Major
DAMAGE ASSESSMENT
For assessment of damage to environment following Environmental aspects has been
identified: -
1. Air Quality: Deterioration due to air emission
2. Water Environment: Due to groundwater exploitation pollution in water bodies.
3. Soil Quality: Due to unorganised solid waste management, land contamination and
unplanned disposal of soil.
4. Exploitation of Natural resources.
5. Socio Economic scenario of the surrounding areas.
6. Environmental accidents.
7. Ecology & Biodiversity
8. Noise levels
9. Geological changes
10. Hydrological changes
To assess these environmental parameters team has been deputed to assess preliminary
assessment of damage to environment.
Based on site inspection and the documentary evidences the environmental aspects vs
activity has been filled.
SUMMARY OF ENVIRONMENTAL DAMAGE
Ambient Air Quality
The project work was started in march, 2013. Due to summer season dust emission was there.
The machineries & DG sets generated air emissions.
Water Generation
Since ground water table is quite low there was no dewatering done. Occasional ground water
was used due to scarcity of water. However most of the water is procured through tanker.
Waste Generation
Construction & demolition waste was generated and it was used in refilling of low lying area
& roads.
Non-Hazardous waste like packaging material wood, carton & plastics are sold to recycler.
Only Hazardous waste was paint and used oils. The used oil has been sold to recyclers.
Land Contamination
There was a defined space for construction machinery and land contamination was done to
spillage of oil.
There was no spillage of cleaning agent however concrete mixture was dumped at few places.
All the liquid were stored in drum and no spillage of any liquid were reported. The toilets were
having soak pits no surface water discharge.
The project plot was agriculture land and no natural drain was passing through the plot.
Use of Natural Resources
Water was taken through tanker; no ground water is used. Energy use was through diesel and
petrol.
Raw Material was RCC (Through RMC), Iron & Steel (From Secondary Steel), Cement, Door &
Windows were made-up of timber (Hence natural resources were used). Stone is used for
flooring tiles used in bathroom & Kitchen.
Local Issues
The nearest habitat is Rampur which is 1 Km in N direction. There were other projects in the
vicinity and no local issues. There was noise during construction activities. Dust was generated
during excavation & transportation.
The land was agriculture land and converted into residential purpose.
Transport Issue
The transportation of material was done using Rampur.
Due to well-maintained approach road dust generation was quite low.
Environmental Accident
The project work was done by experienced and qualified contractor hence no environmental
accident like land subsidence or land slide happened.
Effect on biodiversity
The land was an agriculture land and hence there was no significant flora & fauna. However,
with organized plantation after completion of project biodiversity will improve.
Noise Pollution
The area was earlier an agriculture is and there were no noise sources in the vicinity. However,
with construction activity noise level is increased.
Soil quality & Management
The project was conceptualized with 3 level basements hence soil excavation was essential.
Mining permission was taken from Department of Mines & Geology, Gurugram.
The excess soil was given by contractor for refilling of low lying area.
Geology
There was no mineral at project site and there was only ordinary soil. The soil excavation and
construction of basement has changed the geological profile.
Hydrology
There was no use of ground water in the area. The depletion of ground water in the area is
due to over exploitation of ground water by operational industrial & commercial units.