Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
Prefeasibility ReportFor Environment Clearance from MOEF under EIA
Notification Dated 14th September, 2006 as Amended
1. SUMMARY
-
-
Village - Achholi
-
-
-
1. -
2. Geographical Co-ordinates LATITUDE
21°13'48.99"N
21°13'50.10"N
21°13'49.98"N
21°13'52.51"N
21°13'52.71"N
21°13'53.23"N
21°13'53.98"N
21°13'51.96"N
21°13'52.10"N
21°13'50.37"N
21°13'50.17"N
21°13'49.33"N
River -
Nalla - 440 m
Tanks - 170 m
Canal - 780 m
Reservoir - 12.20 km
4. -
-
6. -
Nalla towards south-east near mine
areaPond towards east near Achholi area
Canal towards north near Achholi
area
Towards south-east near Kauwajhar
village area
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
82°04'02.12"E
BL4
District Mahasamund
State Chhattisgarh
Mining Lease Area & Type of Land 1.87 hect. / Private Land
Project Achholi Flagstone Mine
Name of Company/Mine Kishore Ashani
Tehsil/Taluka Mahasamund
BL8 82°03'56.58"E
BL9 82°03'55.92"E
BL10 82°03'55.84"E
82°04'02.48"E
BL5 82°04'01.13"E
BL6 82°04'01.24"E
BL7 82°03'56.56"E
BL11 82°03'56.39"E
BL12 82°03'56.35"E
5. Topography of the area Flat Land devoid of vegitation
Altitude - Max. 267 aMSL and Min. 265 aMSL
Surface slope - Towards north
Toposheet No.- 64K/4
3. Name of River/ Nallahs /Tanks
/Spring / Lakes etc.
- 2.50 km (Mahanadi river at west) & 860 m (Kurar
river at west )
- BOUNDRY POINT LONGITUDE
BL1 82°03'58.05"E
BL2 82°03'58.20"E
BL3
Project Proposal Scientific mining of Flag stone for proposed capacity of
maximum 4885.57 MT per year.
Name of Reserve Forest(s), Wild Life
Sanctuary/National Park
No such area within 10 km from applied land
Signature of Project Proponent
________________________________________________________________________________________________
___
2
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
7. -
8. -
9. -
10. -
11. -
12. -
13. -
14. -
15. 1. 1.87 Hect.
2. 1.07 Hect.
3. 0.462 Hect.
4. 0.077 Hect.
5. 0.032 Hect.
6. 0.23 Hect.
1.87 Hect.
7. 0.277 Hect.
8. 0.277 Hect.
9. 0.185 Hect.
16. -
17. -
18. -
19. -
20. -
Kishore Ashani
Registered office Kishore AshaniS/o. Shri Chunni Lal AshaniVillage/Post - Nawapara RajimTehsil - AbhanpurDistrict - Raipur
State - Chhattisgarh
Mine Office Village - AchholiE-Mail
Name of Mineral Mined Flag stone
Rate of Production (in tons) Maximum 4885.57 MT/year
Mining Method Open Cast Semi Mechanized
Ground Water table Intersection Below 30 meter from surface level
Drainage Pattern/ Water Courses Natural drainage towards north
Mineral Reserve (in tons) Geological Reserve (till 6m depth) -134640 tons.
Recoverable Reserve (till 6m depth) - 56223.24 tons.
Life of Mine 12 years for the excavation of recoverable reserve of
56223.24 MT
Drilling/Blasting No Blasting Is proposed
Plantation Area proposed over the dump
on dumping area
No Activity Zone on Mine Boundary as
per MMR 1961
Water Requirement & Source Requirement - 6 kilo litre per day, Source - Mine pit/Setting
tank, dug well and tube well of nearby village within
permited limits.
Solid waste/Tailings Top Soil & OB - total 31084.2 cum (Maximum yearly
generation @ 3108.42 cum).
Break-up of Land Utilization Pattern - Total Lease Area
Area proposed under mining pits
Area covered by statuary/mine boundary
Area for cutting, sizing etc
Area Kept for storage of stone
Unused Area within Lease area
Total Area (2+3+4+5+6) =
Dumping Area proposed within proposed
Statutory/mine Boundary
Name and Address of the company /
Proponent
Nil
IBM approval: Date Not Applicable
Cost of Project (Rs. Lacs) Rs. 13 lacs
Any Other (Specify) NIL
Signature of Project Proponent
________________________________________________________________________________________________
___
3
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
Prospecting Agency
Type of Activity
Utilities (Power, Water Requirement)
Manpower requirement
2. INTRODUCTION OF PROJECT/BACK INFORMATION
Kishore Ashani
S/o. Shri Chunni Lal Ashani
Village/Post - Nawapara Rajim
Tehsil - Abhanpur
District - Raipur
State - Chhattisgarh
(ii) Brief Description of Nature of the Project
Not Applicable
Open Cast Semi Mechanized Flag stone Quarry Mining
Power- 5 HP
Water – 6 KLD for Domestic, Dust Suppression & Plantation
Purpose
13 workers per day
The proposed project is mining activity of Flag stone with the name of 'Achholi Flagstone Mine'
which is situated at Khasra no. 1100/1, 1100/2, 1100/3, 1100/4, 1100/5, 1094, 1112 at village
Achholi, tehsil Mahasamund and district Mahasamund (C.G.). This site is 14.50 km away from
district office Mahasamund. The LOI for quarry lease of Flag stone mining has been sanctioned
for Lease period of 30 years from first commencement of lease as per Rule 38A(4) of MMR
2015 as ammended. to project proponent Kishore Ashani resident of Nawapara Rajim district
Raipur (C.G.). The LOI is granted for 1.87 hectare and the proposed maximum production
capacity is 4885.57 t. per annum. The excavation of Flag stone will be done by Open Cast Semi
Mechanized method without blast.
Letter of Intent for sanction of quarry lease has been granted by collectorate mining branch
vide letter is enclosed.
Proposed Flag stone Deposit is located at village Achholi, Tehsil Mahasamund, District Mahasamund
and state Chhattisgarh over an area of 1.87 ha. The proposed capacity of the project is maximum
4885.57 tones/annum. Proposed land is Private non forest revenue land. Open Cast Semi
Mechanized without blast method of mining is the most suitable mining procedure for this mine.
This method of mining is used for highest productivity and the lowest cost of any of the broadly used
mining methods Brief description of the project is described below –
(i) Identification of Project and Project Proponent
(a) Name of the Project: Achholi Flagstone Mine
(b) Project Proponent : Kishore Ashani
(c) Postal /Correspondence Address of Project Proponent:
Signature of Project Proponent
________________________________________________________________________________________________
___
4
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(iii)
(iv)
For compliance of Rule 24 and 63 to 66 of MMR 2015 proponent was submitted quarry plan
before mining authorities and the plan so submitted has been duly approved by the sanctioning
authority vide letter no. Kha.Li./Teen-6/2017/301 Raipur, Dated 10.07.2017.
Demand - Supply Gap
Flag Stone is basic raw material of civil construction works likes building, dams, platforms etc.
for construction of walls/base.
Chhattisgarh is a developing state in map of India. Considering the growth, State Government
has divided the state in 27 districts out of which 9 are recently declared districts. State
Government, is carrying on various Infrastructure development projects in all districts, like
Pachri Nirman, Dams, Over bridge on rivers/nalla, approach roads etc. in addition to these
various power plants, steel plant and cement plants in private sectors are under
implementations, all above civil works require stone in different sizes which is in huge in
demand. However supply of flag stone in the above sectors are in huge shortage.
The proposed project is < 5 hect. Minor mineral and non-coal mining project thus it is classified
as “CATEGORY – B2” project under activity 1(a) of the schedule of EIA notification dated 14th
September 2006 as amended by Ministry of Environment, Forests and Climate Change, New
Delhi by S.O. 141(E) dated 15 January 2016, hence it comes under jurisdiction of DEIAA.
Therefore application is being filed before jurisdictional DEIAA of district Mahasamund for
getting permanent environmental clearance before starting of mining activity on granted lease
area.
All the other necessary permission and noc’s has been taken by the proponent. Consent to
establish & operate/Air/Water clearances from CGCECB will also be taken if instructed by
jurisdictional DEIAA.
Need for the Project and its Importance to the Country and/or Region
The Flag Stone will be used mainly for the purpose of house building materials i.e. Flooring /
Roofing / Beams / Paving / Doorsill / Boundary Construction and now a days it is widely used for
purpose of Footpath along the road shoulders, Flag Stone is also used in carving.
Chhattisgarh is a new state in map of India. Considering the growth, State Government has
divided the state in 27 districts out of which 9 are recently declared districts. State Government,
is carrying on various Infrastructure development projects in all districts. In addition to these
various power plants, steel plant and cement plants in private sectors are under
implementations, all above civil works require flagstone in different sizes which is in huge in
demand.
Signature of Project Proponent
________________________________________________________________________________________________
___
5
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(v)
(vi)
a) Direct Employment
S.N.
1
2
3
4
b)
3. PROJECT DESCRIPTION
(i)
Demand - Supply Analysis
Exploiting this Flag stone deposit is important for the country’s long term economic growth and
regional growth. By mining the deposit, the lessee acts as bridge and fills the gap between
demand and supply of Flag stone in the market surrounding the area.
Therefore, a ready market is available for the proposed unit hence looking to the use and
demand of Flag stone which exist a good scope for the proposed project.
Skilled labours 9
Extra Skilled labours 2
Mining mate (Qualified) 1
Employment Generation (direct and indirect) due to the Project
Labors will be required for various purposes like excavation of stone and loading of stone in
various vehicle, management, maintenance & development of mine, making & maintenance of
ramp, transportation of material and book keeping. Experienced personals will be employed as
per the requirement.
The mining establishment presents opportunities of employment to various posts under various
cedars viz. supervisory, skilled workmen, semiskilled workmen and unskilled workmen beside
casual workmen. However the maximum required labours at the site to justify the production of
stone at applied land are detailed below-
Taking standard O.M.S. to be one the strength of labour, a labour can work for 2 tons of mineral
in one sift of 8 hours a day. Considering this parameter the manpower need for project is –
Particulars No of Workers
The proposed project is < 5 hect. Minor mineral and non-coal mining project thus it is classified
as “CATEGORY – B2” project under activity 1(a) of the schedule of EIA notification dated 14th
September 2006 as amended by Ministry of Environment, Forests and Climate Change, New
Delhi by S.O. 141(E) dated 15 January 2016, hence it comes under jurisdiction of DEIAA.
Chowkidars (Experienced) 1
Total 13
Indirect employment - Driver, cleaner for loader & dumper are the points were labors are
required. Moreover, manager, accountants will also be appointed as per need.
Type of Project (Including interlinked and interdependent projects, if any):
Signature of Project Proponent
________________________________________________________________________________________________
___
6
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(ii)
The details of the lease area are as under:
The Coordinates of the area are:
BOUNDARY
POINT
LATITUDE
BL7 21°13'53.98"N
BL8 21°13'51.96"N
BL9 21°13'52.10"N
BL10 21°13'50.37"N
BL11 21°13'50.17"N
BL12 21°13'49.33"N
(iii)
(iv)
Waste in Stone
in cum
566.05
678.55
678.55
678.55
678.55
Location (map showing general location, specific location, and project boundary & project
site layout) with coordinates.
District / State Mahasamund / Chhattisgarh
Tehsil Mahasamund
BL2 21°13'50.10"N 82°03'58.20"E 82°03'56.58"E
Village Achholi
Area(ha) 1.87 hect.
BOUNDARY
POINT
LATITUDE LONGITUDE LONGITUDE
BL3 21°13'49.98"N 82°04'02.12"E 82°03'55.92"E
BL4 21°13'52.51"N 82°04'02.48"E 82°03'55.84"E
BL1 21°13'48.99"N 82°03'58.05"E 82°03'56.56"E
The site can be depicted in the toposheet number 64K/4 of Survey of India. Study area map in
Khasra map, toposheet and site specific surface map is attached as Plate-1, Plate -2 and Plate -4
of enclosed mine plan respectively.
Details of alternate sites considered and the basis of selecting the proposed site, particularly
the environmental considerations gone into should be highlighted:
BL5 21°13'52.71"N 82°04'01.13"E 82°03'56.39"E
BL6 21°13'53.23"N 82°04'01.24"E 82°03'56.35"E
1st Year 4075.57 3108.42
2nd Year 4885.57 3108.42
It is naturally occurring rocks which is site specific due to its geological origin. Mining is site
specific project. This lease is being granted by the state govt., hence alternative site is not
applicable. Size or Magnitude of Operation:
The total applied lease area is 1.87 hectare and total proposed maximum production capacity
will be 4885.57 TPA through Open Cast Semi Mechanized method of mining without blast.
Proposed production details during lease period are shown in below -
Production During Plan Period
Year Stone (ROM)
in tonne
Top Soil & OB
in cum
5th Year 4885.57 3108.42
3rd Year 4885.57 3108.42
4th Year 4885.57 3108.42
Signature of Project Proponent
________________________________________________________________________________________________
___
7
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
678.55
678.55
678.55
678.55
678.55
6673 cum
(v)
-
-
-
-
-
-
-
-
6th Year 4885.57 3108.42
9th Year 4885.57 3108.42
10th Year 4885.57 3108.42
7th Year 4885.57 3108.42
8th Year 4885.57 3108.42
7.50 m boundary will be left from the lease boundary around 4 sides (N, E, S, W) as barrier for
safety provisions, dumping of top soil & OB and afforestation.
The proposed heights of working bench will be as tabled below. Separate bench for soil is
proposed. Bench details and specifications are as under -
Bench Number Bench Specification Bench Height Bench Width along
the periphery of mine
Total 48045.7 t 31084.2 cum
Project description with process details (a schematic diagram/flow chart showing the project
layout, components of the project etc. should be given)-
It is proposed to carry out mining operation Open Cast Semi Mechanized method. The
development has been proposed for systematic and scientific mining.The excavation activity will be carried out till the depth of 6 m below general ground level or
occurrence of ground water table at the site which ever encountered earlier.
3rd Quarry Bench Mineral Bench 1.50 m 1.50 m
4th Quarry Bench Mineral Bench 1.50 m -
1st Quarry Bench Soil Bench 1.50 m 1.50 m
2nd Quarry Bench Soil Bench 1.50 m 1.50 m
Excavation and Resizing of stone by cutter
machine
Overall bench slope will be less than 450 with the horizontal.
Adequate slope and water sump will be gradually developed at the working pit.
Large size of stone will be manually sized as per the demand.
Loading will be done manually and the transporting will be done by 4.5 tones tractor or 10
tones tippers.
Flow chart of the ProjectRemoval of Overburden & Top Soil
Loading by Manually
Transportation by Tractor or Truck
Signature of Project Proponent
________________________________________________________________________________________________
___
8
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(vi)
(vii)
Mine Site
Dust Suppression 3.00 KLD
Green Belt 2.00 KLD
Domestic
Sanitation & Drinking 1.00 KLD
Total 6.00 KLD
I)
II)
A)
Drilling & Blasting : Not Applicable
Raw material/consumables required along with estimated quantity, likely source, marketing
area of final products/s, Mode of transport of raw Material and Finished Product.
No raw material is required for the mining of Flag stone.
Marketing area: Flag stone will be used in form of building material in civil constructions
activity.
The excavated mineral will be transported to the destination by tipper/dumper/trucks and
broken Flag stone will be loaded manually or by loaders.
Availability of Water, its source, Energy/power requirement and source should be given -
Water Requirement:
Domestic usage: Drinking water is available from dug well and tube well in villages near the
applied area which is portable, pure and clean.However, if required, water might be supplied
from tube well within lease area.
Energy & Power Requirement and Source
Fossil Fuels :
Fuel is to be used in form of diesel for mining operations and running of tractors and other
transportation vehicles.
Quantity for fuel will depend upon the usage of transportation vehicle and other machineries
and level of achievement of estimated production. Diesel will be outsourced from nearby diesel
pumps.
It is expected that the total water need is about 6 kilo litter per day in the mine. The details of
water balance of existing / proposed mining project are given below:
Water Balance of Project
Process Total (KLD- Kilo Litter Per Day)
Sources of water:
For Green belt and dust suppression: Water will be made available from quarry mine pit which
is accumulated during the rainy season and shall be collected in settling tank for utilization in
green belt and dust suppression.However, if required, water might be supplied from tube well
within lease area or from nearby nalla or pond.
Signature of Project Proponent
________________________________________________________________________________________________
___
9
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
B)
S.N. Power
requirement
1 5 HP
C)
(viii)
a)
b)
c)
a)
Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal –
Solid Waste:
Top Soil & overburden:
Top soil & OB. 31084.2 cum will be generated in total at the rate of maximum 3108.42 cum per
year for period of approved mine plan.
Mining Loss or Unusefull Waste Material:
All ROM mineral is useful and saleable.
Electricity :
Electricity will be required for Pumping of water and for administrative building & rest shelters.
The requirement of Power is estimated as under-
Particulars
Domestic Purpose
Source of Electricity:
The power requirement for the project will be met by electricity lines of Chhattisgarh State
Power Distribution Copany Limited available at village or nearby site area.
Top Soil & overburden:
Whatsoever quantity of top soil and overburden generated during the quarrying operation will
be stacked at the periphery of mine along the statutory/mine boundary in such manner that no
stacking will be done at the edge of quarry pit.
Mine/Statutory boundary is 7.50 m wide in order to comply the rules of MMR1961. Out of this
mine/statutory boundary 3.0 m wide area from the edge of mine pit is proposed to left to
comply the provisions of MMR1961. Dumping area is proposed on balance outer 4.50 m wide
area of mine/statutory boundary i.e. after 3.0 m of no activity zone. Threfore saperate dumping
area in the mine is not proposed. Rather outer 4.50 meter wide area under mine/statutory
boundary is itself considered as dumping area. plantation is also proposed on the same
dumping area over the dump. Roads within mine area is also peoposed to be constructed within
mine boundary only.
Sub grade material:
6673 cum material may be generated as unusefull subgrade material or may occur as mining
loss respectivelly during the plan period. "
Liquid Effluent:
Only domestic effluent is expected to be generated which will be treated through septic tank
followed by soak pits.
Selection of Dumping Site:
Signature of Project Proponent
________________________________________________________________________________________________
___
10
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
b)
c)
i)
ii)
iii)
a) Top Soil & Overburden :
b) Waste & Subgrade Material :
4. SITE ANALYSIS
Connectivity
Further if the area for dumping of OB gets short then the land (adjoining or nearby the mine)
owned or controlled by the lessee will be utilised with due permission of district mining office
for dumping of excess OB. Such excess OB dump will be utilised in priority for reclamation at the
time of reclalation of mine.
Manner of waste disposal & configuration:
Top Soil initially removed will be temprerorly stacked on mine boundary or other location
within lease area. Then whatsoever quantity of overburden & unusefull waste generated during
the quarrying operation will be spread at the periphery of mine along the mine boundary on
specified dumping areas. After proper dumping of OB and unusefull waste on mine boundary
the preserved Top Soil will be spreyed over the OB and/or unsuefull waste dump. Stack of dump
OB, waste & Top soil so developed is proposed to be stabilized the by grass plantation or cutting
of local bushes and dence plantation on it as per plantation programme so that spillage of
dump does not occur in the surroundings.
Further if the area for dumping of OB gets short then the land (adjoining or nearby the mine)
owned or controlled by the lessee will be utilised with due permission of district mining office
for dumping of excess OB. Such excess OB dump will be utilised in priority for reclamation at the
time of reclalation of mine.
No need of planing for dumping management of waste and subgrade material as all ROM is
saleable except Top Soil and Overburden.
The area is approachable from district office Mahasamund by fair weather road. The area is
14.50 km from Mahasamund. The applied area is 4.00 km away from Bhoring bus stand.
Hospital is available at Achholi at 800 m/Belsonda at 8.50 km distance. The nearest railway
station is at Belsondha (9.00 km) (S.E.C.RLY) and Nearest active airport is Raipur (34.00 km).
Waste:
No mining waste except from mining losses & OB will be generated during excavation of Flag
stone. All ROM mineral will be used. Flag stone is usable as building material hence saleable
therefore no mineral waste will be generated which requires their due management.
Sub grade material:
Removal of broken stone out of lease area for making stone chip by due approval of
district authority after payment of applied fee or royalty. However it depends upon the
availability of market and demand.
Utilise for reclamation purpose within the mine itself.
Utilise for road or ramp maintanance within the mine itself.
Signature of Project Proponent
________________________________________________________________________________________________
___
11
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(i)
Form & Use : Flat, Non Forest, Revenue land.
Ownership : Private land.
Forest - Nil Area (ha)- Nil 1.87 Hect. Area
Nil
Nil
Nil
(ii)
(iii)
5. PLANNING BRIEF
Land form, Land Use & Land Ownership
(iv) others (specify)
Climate Data from Secondary Sources:
The climate of Mahasamund district in general and the Mahasamund in particular is
characterized by a hot summer and a well-distributed rainfall during the southwestern
monsoon season extending from end of June to October. The area has 4 well-defined seasons in
a year. The winter season commences from early December and continues up to the end of
February, summer season extends from March to early June, rainy season generally from mid-
June to September and the post-monsoon season from October to November.
Topography:
Existing land use pattern: Existing land use pattern of the proposed mining area is given in
below table.
Forest Area Non-forest Area
(i) waste land (Private),
(ii) grazing land,
(iii) Agriculture land,
Planning concept: It is a Flag stone mining project, for safe, scientific & systematic working to
follow the principles of safety & conservation of human health & mineral the planning for
mining of stone shall be governed by the approved Quarry Plan under Chhattisgarh Minor
Mineral Rules, 2015 vide letter no. Kha.Li./Teen-6/2017/301 Raipur, Dated 10.07.2017.
The study area consists of essentially Flat land with a very small pit. Gentle slope towards north,
Maximum elevation of the lease area is 267 meters above MSL
Social Infrastructure Available
Power line, telephone line, school, bank, govt. office, Hospital, Police station etc. at
Mahasamund.
The road facility is already available which shall be used and properly maintained. Preference
will be given to local labor from nearby villages. Other requisite infrastructure as transport of
mine labors is available by way of jeep, two-wheeler. Medical facility is available for first aid at
project site.
Planning concept (type of industries, facilities, transportation etc.) Town and country
Planning/Development authority Classification-
Signature of Project Proponent
________________________________________________________________________________________________
___
12
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
(i)
(ii)
Proposed Land Use Pattern of Proposed Quarry Lease Area
1. 1.87 Hect.
2. 1.07 Hect.
3. 0.462 Hect.
4. 0.077 Hect.
5. 0.032 Hect.6. 0.23 Hect.
1.87 Hect.
7. 0.277 Hect.
8. 0.277 Hect.
9. 0.185 Hect.
(iii)
Population projection:
The project is very small in magnitude. The project will employ most of the workers from nearby
villages. There will not be any increase in population of the area due to the establishment of
project. However, few people from other area may migrate in this area for business
opportunities.
Proposed Land Use Planning
Total Area (2+3+4+5+6) =
Dumping Area proposed within proposed
Statutory/mine Boundary
Plantation Area proposed over the dump on
dumping area
No Activity Zone on Mine Boundary as per MMR
1961
Assessment of infrastructure demand (physical and social)
Total Lease Area
Area proposed under mining pits
Area covered by statuary/mine boundary
Area for cutting, sizing etc
Area Kept for storage of stoneUnused Area within Lease area
Amenities / Facilities:
Specific amenities / facilities are not required in this mining project. However the same can be
provided as per prescribed instructions.
Road & Connectivity:
The road facility is already available around 30 m from the site which shall be used and properly
maintained.
Site Services:
Site services are required per the statutory provisions i.e rest shelters, toilets, drinking water
facilities, safety appliances, and regular medical checkup facilities are suitably needs to be
provided for labors and their families. The health and safety of the employees is required to be
given first priority during the mining operation. Training program organize for first aid.
First aid:
Specified first Aid station is needed to be maintained at the site office and the rest shelter as
per applicable statutory provision.
Office and stores:
Office and stores is needed to be provided as per applicable statutory provision.
Signature of Project Proponent
________________________________________________________________________________________________
___
13
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
6. PROPOSED INFRASTRUCTURE
(i) Industrial Area (Processing Area)
Not Applicable
(ii)
(iii)
No. OF SAPLING
(iv)
Manpower Requirement:
Apart from indirect manpower requirement for Driver, cleaner for loader & dumper, manager,
accountants; approx. 13 labours will be required directly for mining operation.
Afforestation program shall be started with the commencement of mining operation with
simultaneous clearing of land by spreading of soil along barrier of proposed lease boundary.
2.5m X 2.5m spacing with 0.6m depth have been suggested for sapling pits on which local
species will be planted as the following manner-
Year PROPOSED SITE SPECIES
1st Year Along boundary of quarry area Seesam, Bargad, Neem, Aam,
Pipal, etc.
100
Other requisite infrastructure: Transport of mine labors is available by way of jeep, two-
wheeler. Medical facility is available for first aid at project site.
Power line, telephone line, school, bank, govt. office, Hospital, Police station etc. are the other
requisites needed for mine operation and social facilitation.
Residential Area (Non Processing Area)
No residential area is proposed for the project except temporary rest shelters proposed for
labors.
Green belt
Under the afforestation plan, plantation in nearby villages and connecting roads be undertaken.
The implementation for development of greenbelt will be of paramount importance as it will
not only add up as an aesthetic feature but will also act as a pollution sink. The species to be
grown in the areas should be dust tolerant and fast growing species so that a permanent
greenbelt is created. Plantation in the barrier zone and roads is necessary as these areas will
contain fine particulates resulting from mining operation and vehicle movement Plantation will
also be carried out as social forestry programme in village, school and the areas allocated by the
Panchayat/State authorities. Native plants like Neem, Peepal, Khejri and other local species will
be planted. A suitable combination of trees that can grow fast and also have good leaf cover
shall be adopted to develop the greenbelt.
Social infrastructure
For the social developmental program on the need base assessment some development
program will be undertaken by the project proponent i.e. development of or maintenance of
urinals, toilets, safety appliances & training program, confirming availability of pure and clean
drinking water, periodic health checkup program, transportation facility to labours and their
children’s to schools etc.
Signature of Project Proponent
________________________________________________________________________________________________
___
14
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
OCCUPATIONAL HEALTH AND SAFETY
Occupational Health and Safety works as follow-
1)
2)
3)
4)
(v)
(vi)
(vii)
(viii)
A)
B)
S.N. Power
requirement1 5 HP
C)
Awareness program be conducted about likely occupational health hazards so as to
have preventive action in place.
Promote occupational health and safety within workers in mine and develop safer and
healthier ways of working;
Occupational Health and Safety are important. Periodic assessment of it will be useful.
Identifying workplace hazards, assessing risks to employee health and safety, are important.
Health and Safety points are also important in many of the environmental aspects of the
workplace.
Except dust generation there is no source which can show a probability for health
related diseases and proper dust suppression will control dust generation and
dispersion.
Power requirement & supply/source:
Fossil Fuels :
Fuel is to be used in form of diesel for mining operations and running of tractors and other
transportation vehicles. Quantity for fuel will depend upon the usage of transportation vehicle
and other machineries and level of achievement of estimated production. Diesel will be
outsourced from nearby diesel pumps.
Electricity :
Electricity will be required for Pumping of water and for administrative building & rest shelters.
The requirement of Power is estimated as under-
Particulars
Develop and implement training sessions for management, supervisors and workers on
health and safety practices and legislation;
Drinking Water Management (source & supply of water):
Drinking water is available in dug well and tube well at nearby village of the applied area which
is portable, pure and clean. It is also proposed to provide hand pump if needed in the lease area
for mitigating of drinking water, such hand pump will be arranged after taking statutory
permission.Sewerage System: No construction or sewage waste is expected from the mining process.
However the domestic waste from the toilets shall be given treatment through septic tank and
soak pit arrangement.
Industrial waste management: No industrial waste will be generated.
Domestic Purpose
Source of Electricity:
The power requirement for the project will be met by electricity lines of Chhattisgarh State
Power Distribution Copany Limited available at village or nearby site area.
Signature of Project Proponent
________________________________________________________________________________________________
___
15
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
7. REHABILITATION AND RESETTLEMENT (R&R) PLAN:
8. PROJECT SCHEDULE AND COST ESTIMATES
A)
B) Estimated project cost of the project -
S.N. Amount in Lacs
1 10.00
2 0.50
3 1.00
4 1.00
5 0.50
13.00
Likely date of start construction and likely date of completion (time schedule for project) –
The proposed mining project will be started after obtaining Environmental Clearance of quarry
lease and order to enter in lease area by District Collector (Mining Branch). Consent to establish
& operate from CGCECB will also be taken if instructed by DEIAA.
Particulars
Land Cost (market value)
Administrative Building & Rest Shelters
Mining Machineries & Equipment’s
No R&R plan is required as the mine area does not cover any habitation. Hence the mining
activity does not involve any displacement of human settlement. No public buildings, places,
monuments etc. exist within the lease area or in the vicinity of the mine lease area. The mining
operation will not disturb/ relocate any village or need resettlement. Thus no adverse impact is
anticipated.
Impact of the stone mining will be positive, as it will upgrade the socio-economic status of local
inhabitants in the nearby areas by giving employments to poor people of nearby villages. Due to
this positive impact the living standard will increase and will lead to educational upliftment.
Effect on Flora & Fauna:
Mining is restricted to very small area. No study have been conducted or record found on effect
on Floora & Fauna for mine area. However mining activity causes impact on flora and fauna due
to land degradation/deforestation etc.,
Land Development & Establishment cost
Others
Total Cost of Project :
Signature of Project Proponent
________________________________________________________________________________________________
___
16
Pre - Feasibility ReportFor Achholi Flagstone Mine at Village - Achholi
Tehsil- Mahasamund & District- Mahasamund, State- Chhattisgarh.
9. CONCLUSION
(a)
(b)
(c)
(d)
(e)
Kishore Ashani
Date : / /2017
Place : Nawapara Rajim
The Proposal does not require further Infrastructure facilities other than few Mining
Machineries.
The Project is viable and environmental friendly as it’s a development project for the State &
Country.Increased financial benefits accruing to state and central agencies by ways of taxes, royalties,
cesses etc.
Signature of the applicant
In any human activity there are always possibilities of finding various options. Project proponent has
decided to examine and adopt one such option that will be both environment friendly and best
suited for Flag stone production. Various alternatives in terms of site, technology, and equipment
are considered. A final selection is thus arrived–The Proposal is for the Environment Clearance of the Proposed Mine.
The quarry project will create local employment to the villagers and they will get employment
in nonagricultural season.
Signature of Project Proponent
________________________________________________________________________________________________
___
17