Upload
lykhanh
View
226
Download
6
Embed Size (px)
Citation preview
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Pre feasibility Report of Proposed New Cement Plant at village Khrew District Pulwama Srinagar.J & K Project Proponent: Trumboo Cements Pvt. Ltd.
Dec 2012
Prepared by: EQMS India Pvt. Ltd,
New Delhi
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Project: Environmental Impact Assessment
Study for proposed new cement Plant at village Khrew, District:Pulwama srinagar,J&K
Client: Trumboo Cements Pvt. Ltd.
Project No.: EQMS/ © Copyright EQMS All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means without permission of the publish
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 1
TABLE OF CONTENTS
Table of Contents .................................................................................................................. 1 Executive summary ............................................................................................................... 3 1. Introduction .................................................................................................................... 8
1.1. Industry Background .............................................................................................. 8 1.2. Types of modern cement ....................................................................................... 8
1.2.1. Portland cement................................................................................................. 8 1.2.2. Non-Portland hydraulic cements ...................................................................... 10 1.2.3. Cement industry in the world............................................................................ 11 1.2.4. Global Cement Production in 2010 .................................................................. 12 1.2.5. Global Cement Capacity in 2010 ..................................................................... 13 1.2.6. Cement output in 2004..................................................................................... 14 1.2.7. China’s production ........................................................................................... 14
1.3. Cement Industry in India ...................................................................................... 14 1.3.1. Major Players in Indian Cement Industry ......................................................... 15 1.3.2. Recent Investments in the Indian Cement Industry .......................................... 15 1.3.3. Cemnt Production Scenario ............................................................................. 16 1.3.4. Capacity, Capacity Utilization and Production Growth...................................... 16
1.4. Cement industry in Jammu and Kashmir ............................................................. 16 1.4.1. Past Trend in Consumption ............................................................................. 16 1.4.2. Future Demand ................................................................................................ 17 1.4.3. Current Supply ................................................................................................. 18
1.5. LIMESTONE DEPOSIT, ITS LOCATION, RESERVE AND GRADE .................... 18 1.6. The setting of cement .......................................................................................... 18 1.7. Safety issues ....................................................................................................... 18
2. Process Description ..................................................................................................... 19 2.1. Introduction .......................................................................................................... 19 2.2. Process Technology ............................................................................................ 19
2.2.1. Dry Process Cement Manufacturing Technology ............................................. 19 2.2.2. Advantages of Dry Process System using precalciner system ........................ 19
2.3. Process Technolgy Description ........................................................................... 19 2.3.1. Limestone Crushing ......................................................................................... 19 2.3.2. Raw Material Drying & Grinding ....................................................................... 20 2.3.3. Raw Meal Homogenizing & Kiln Feed System ................................................. 20 2.3.4. Pyro-Processing (Preheated, Precalciner,Kiln & Cooler) Section ..................... 20 2.3.5. Clinker Storage, Grinding and gypsum crushing .............................................. 21 2.3.6. Cement Storage & Packing .............................................................................. 22
2.4. Product Storages ................................................................................................. 22 2.4.1. Sizing of storages ............................................................................................ 22
2.5. Raw materials and Auxillary Operations .............................................................. 22 2.5.1. Proposed mining operation .............................................................................. 23 2.5.2. Mining of Clay/silica stone............................................................................... 24
2.6. Broad sizing of major plant & machinery and storages ........................................ 26 2.6.1. Plant Capacity ................................................................................................. 26 2.6.2. Norms For Equipment Sizing ........................................................................... 26 2.6.3. Norms for Storage Capacity ............................................................................. 27
2.7. Instrument and Control Philosophy ...................................................................... 27 2.8. Project Utilities ..................................................................................................... 28
2.8.1. Compressed air system. .................................................................................. 28 2.8.2. Inplant laboratory and quality control. .............................................................. 29 2.8.3. Maintenance workshop .................................................................................... 29 2.8.4. Fuel ................................................................................................................. 29
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 2
2.8.5. Water Supply and Distribution(Water Balance to be provided) ......................... 29 2.8.6. Power .............................................................................................................. 30 2.8.7. Other facilities .................................................................................................. 31 2.8.8. Employement Generation: ............................................................................... 31
2.9. Environmental aspects ........................................................................................ 31 2.9.1. Land Degradation ............................................................................................ 31 2.9.2. Pollution by effluent gases .............................................................................. 32 2.9.3. Sulphur dioxide in the ambient ......................................................................... 32 2.9.4. Air pollution ...................................................................................................... 33 2.9.5. Water pollution ................................................................................................. 34 2.9.6. Noise pollution control...................................................................................... 34 2.9.7. Safety precautions. .......................................................................................... 34
3. Site Analysis ................................................................................................................ 35 3.1. The Site Location ................................................................................................. 35 3.2. Salient Feature Of The site: ................................................................................. 35
3.2.1. Sources of Raw Materials ................................................................................ 35 3.2.2. Availability of suitable land ............................................................................... 35 3.2.3. Road linkage and transportation of cement ...................................................... 35
3.4. Layout of the cement plant................................................................................... 36 4. Project Cost and Schedule ........................................................................................... 37
4.1. Project Implementation: ....................................................................................... 37 4.2. Estimated cost of the project and financial indicators. .......................................... 37
5. INDUSTRIAL POLICY 2004 ......................................................................................... 38
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 3
EXECUTIVE SUMMARY
Introduction The dynamic and progressive Trumboo Group of Industries Srinagar have strategically decided to set up 3500 TPD modern rotary kiln system at village Khrew, Dist :Pulwama with expected cost of Rs. 445 Crores. The proposed plant site is located 30 KM from Srinagar and on the Northern side of Jammu Srinagar national Highway.
TRUMBOO GROUP of Industries, Srinagar started their operation in 1952 and at present the group is engaged in the following business.
1. Textiles Tradin
2. Cement Manufacturing
3. Roller Flour Mills
Business activity of the group is concentrated in the J&K state.
Executive profile and strategy
The group is professionally managed private company and is running by the board of
directors. The names and qualifications of the directors are indicated below.
Name Qualification Designation
Mohd Shafi Trumboo Graduate Director
Mushtaq Trumboo BA, LLB Director
Waseem Trumboo B.Com, MBA Director
The company has formulated an ambitious strategy to set up a cement plant of 3500 TPD
capacity in the village of Khrew which is located north-west of Srinagar and 30 KM away
from Srinagar. The history of the company is in possession of logical and necessary
business acumen of growth and expansion and therefore the promoters have ventured for
3500 TPD cement plant.
Experience of the company
The chronological growth record in business expansion of Trumboo Group is as follows:
1. As started earlier the company was floated in 1952 by Mr. Haji Abdul Ahad Trumboo in
the business of Textile Trading. The founder had a strong business acumen foresight
and vision which resulted in further development.
2. An oil mill and flour Mill was installed in the year of 1957
3. The second flour mill was installed in the year of 1962.
4. In the year of 1979 the third flour mill was installed in the name of Trumboo Flour mill.
5. In the year of 1989 one more roller flour was installed in Srinagar in tune with their vision
of further expansion. This flour mill installation was known as Gulmarg flour mill Private
limited.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 4
6. The Trumboo Group installed cement plant of 200 TPD capacity based on VSK
technology in the year of 1997 on the outskirts of Srinagar. Subsequently, the plant
capacity was raised to 400 TPD capacity in the late 2003 and the plant is running
satisfactorily.
7. The Trumboo Group installed second cement plant of 1000 TPD capacity based on
rotary technology. The same was commissioned in oct.2010.
8. The group has enhanced their business activity in textile trading and at present it is a
largest trading house in J&K
The group employs around 800 people out of which 450 people are working in cement plant
and balance people are working n other activities.
Conclusion
The experience of the company reflects that they are interested to expand their business
activity. The Group is already managing cement plants from the year 1997.The group has
gained strong experience of running cement plants. It is expected that the group may be
able to utilise this experience gained so far effective installation and running of the proposed
3500 TPD cement plant.
Information on the Deposit and infrastructure
Location
The limestone deposit is situated about 30 K.m away from Srinagar and at a distance of 6.0
Km from the northern high way connecting Jammu and Kashmir.The deposit is in the form of
hilly terrain, one side is having gradual stiffness and the other side is very stiff. The length of
the deposit is approximately 1.5 k.m and having a gross deposit to the tune of 45 million
tonnes.
The above deposit is under the jurisdiction of Jammu and Kashmir government and leasing
of the same is done in favour of the company. The place where the limestone deposit is
located is named as village Khrew.
Geography and Economic Characteristics of the area.
The deposit area lies at a height of 1850m mean sea level but accessible by road from
Jammu and Kashmir. The limestone deposit about 53% of CAO and therefore, suitable for
cement production. The availability of power at a low tariff rate is also suitable for the
proposed plant. The climatic condition except the winter season is friendly for smooth
working in the cement plant. The economic condition of the people in the above area is
conducive for hiring unskilled & Semi skilled labours and staff at a cheaper rate but technical
staffs are generally expatriates. The temperature of the above area is varying between (-)7 C
(+) 25 C in various phases of the year
Location / Infrastructure
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 5
The proposed plant is located 30 Km away from Srinagar and 6 Km on northern side of the
national highway connecting Jammu and Srinagar. From the site visit it appears that no
infrastructure facilities are available in the area but the same can be developed along with
project as the land can be easily procured.
Limestone Deposit
The limestone deposit for the proposed cement plant is located at about 30 Km north-west of
Srinagar. The topography of the deposit area is hilly, and surface of the deposit is steeply
dipping. The approximate RL of the deposit site is about 1830 m above MSL. The size of
deposit is about 1.5 Km x 0.5 Km which has about 45 Million Tones of gross limestone
reserve. The average quality of limestone is as follows.
CaO : 53.01%
MgO : 1.89%
SiO2 : 0.97%
Fe2O3 : 0.41%
Al2O3 : 0.93% LOI : 43.00
Information about the Project
Plant capacity
Clinkerisation plant: 3500 TPD or 1155000 TPY clinker on the basis of 330 days of
working per year.
Raw Material and Raw Mix Design.
a) Clinkerisation factor : About 1.56 tonnes of raw material required
to produce 1 tonne of clinker.
b) Limestone proportion source : About 76 % of raw mix.
Source Deposit near the plant location
c) Additive proportion : clay 21 %,sand 3%
Source Deposit near the plant location
d) Gypsum : About 4 % of cement ,
Source To be brought from outside the plantsite.
Process Technology and Requirement of Raw Material
Based on raw material, dry process for manufacturing of cement has been adopted for the
project. Requirement of raw material and fuel on raw mix design at 100 % plant capacity are
as follows:
Approximate raw material requirement per year are furnished below:
Limestone : 1350000 Tonne
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 6
Clay : 412500 Tonne
Sand : 50995 Tonne
Gypsum : 45570 Tonne.
Petcoke:coal: 60:40 9specific heat consumption)
Land
During the site visit, availability of land for plant site was seen and found that enough land is available for the plant close to the limestone deposits at Bajnar location.
Major Plant and Equipment
1. Crushing crusher for limestone
2. Raw material Grinding : Grinding of raw materials in right proportions in ball mill with
high efficiency separator.
3. Raw material blending: Rcc Continuous blending and storage silo 1 day storage
capacity.
4. Pyroprocessing section consisting of rotary kiln with string five stage preheater ,inline
precalciner will be irked by pet coke. Exhaust gas from kiln and raw mill be deducted by
glass bag filter and grate cooler exhaust by electrostatic precipitator for meeting the
present day emission level
FUEL Pet coke and coal will be used as a fuel in this project for providing the necessary thermal
energy for conversion of raw materials into cement Both pet coke and coal will be
transported to Jammu railway yard by box-type wagon. Thereafter, the same will be
transported to the proposed projected site by road transport
Electrical power
The power required for running the cement plant and its auxiliaries can be obtained from the
PDD Substation located at a distance of 3.5 Km from the proposed plant site. Thereafter,
necessary distribution of power can be thought of as per the electrical load requirement of
the different sections of the proposed cement plant. The total power requirement for the
3500 TPD cement plant as envisaged now is about 15 MVA’s.
Water
Source : from underground
Requirement : 500 m3
Pollution Control Equipment
The incorporation of highly efficient, low emitting ,fabric filters at all transfer points, glass bag
houses for raw mill kiln venting and ESP for high temperature gases from cooler shall be
considered and the project cost shall have to be decided accordingly.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 7
Clinker and cement manufacturing plants pose environmental hazards to the land,
vegetable, atmosphere and inhabitants within the vicinity of the factory. Most of these
environmental hazards have been identified and measures taken during the design of the
plant to minimize discomfort, inconvenience and ill health to the factory workers as well as
the local people.
Project Implementation: About 40 months after finalization of investment.
Project cost: The toal cost of the Project is 47,528.62,however details are given in chapter
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 8
1. INTRODUCTION
.
1.1. Industry Background
1. The history of the cement industry in India dates back to the 1889 when a
Kolkata-based company started manufacturing cement from Argillaceous. But
the industry started getting the organized shape in the early 1900s. In 1914,
India Cement Company Ltd was established in Porbandar with a capacity of
10,000 tons and production of 1000 installed. The World War I gave the first
initial thrust to the cement industry in India and the industry started growing at
a fast rate in terms of production, manufacturing units, and installed capacity.
This stage was referred to as the Nascent Stage of Indian Cement Company.
In 1927, Concrete Association of India was set up to create public awareness
on the utility of cement as well as to propagate cement consumption.
2. The cement industry in India saw the price and distribution control system in
the year 1956, established to ensure fair price model for consumers as well
as manufacturers. Later in 1977, government authorized new manufacturing
units (as well as existing units going for capacity enhancement) to put a
higher price tag for their products. Cement Company, in any country, plays a
major role in the growth of the nation. Cement industry in India was under full
control and supervision of the government. However, it got relief at a large
extent after the economic reform. But government interference, especially in
the pricing, is still evident in India. In spite of being the second largest cement
producer in the world, India falls in the list of lowest per capita consumption of
cement with 180 kg. The reason behind this is the poor rural people who
mostly live in mud huts and cannot afford to have the commodity
1.2. Types of modern cement
1.2.1. Portland cement
3. Cement is made by heating limestone (calcium carbonate) with small
quantities of other materials (such as clay) to 1450 °C in a kiln, in a process
known as calcination, whereby a molecule of carbon dioxide is liberated from
the calcium carbonate to form calcium oxide, or quicklime, which is then
blended with the other materials that have been included in the mix. The
resulting hard substance, called 'clinker', is then ground with a small amount
of gypsum into a powder to make 'Ordinary Portland Cement', the most
commonly used type of cement (often referred to as OPC).
India, being the second largest cement producer in the world after China with a total capacity of 151.2 Million Tones (MT), has got a huge Cement Company. With the government of India giving boost to various infrastructure projects, housing facilities and road networks, the cement industry in India is currently growing at an enviable pace. More growth in the Indian cement industry is expected in the coming years. It is also predicted that the cement production in India would rise to 236.16 MT in FY11. It's also expected to rise to 262.61 MT in FY12.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 9
4. Portland cement is a basic ingredient of concrete, mortar and most non-
specialty grout. The most common use for Portland cement is in the
production of concrete. Concrete is a composite material consisting of
aggregate (gravel and sand), cement, and water. As a construction material,
concrete can be cast in almost any shape desired, and once hardened, can
become a structural (load bearing) element. Portland cement may be grey or
white.
5. Portland cement blends are often available as inter-ground mixtures from
cement manufacturers, but similar formulations are often also mixed from the
ground components at the concrete mixing plan]
1.2.1.1 Portland blastfurnace cement
6. It contains up to 70 % ground granulated blast furnace slag, with the rest
Portland clinker and a little gypsum. All compositions produce high ultimate
strength, but as slag content is increased, early strength is reduced, while
sulfate resistance increases and heat evolution diminishes. Used as an
economic alternative to Portland sulfate-resisting and low-heat cements]
1.2.1.2 Portland flyash cement
7. It contains up to 35 % fly ash. The fly ash is pozzolanic, so that ultimate
strength is maintained. Because fly ash addition allows a lower concrete
water content, early strength can also be maintained. Where good quality
cheap fly ash is available, this can be an economic alternative to ordinary
Portland cement.]
1.2.1.3 Portland pozzolan cement
8. It includes fly ash cement, since fly ash is a pozzolan, but also includes
cements made from other natural or artificial pozzolans. In countries where
volcanic ashes are available (e.g. Italy, Chile, Mexico, the Philippines) these
cements are often the most common form in use.
1.2.1.4 Portland silica fume cement.
9. Addition of silica fume can yield exceptionally high strengths, and cements
containing 5–20 % silica fume are occasionally produced. However, silica
fume is more usually added to Portland cement at the concrete mixer.]
1.2.1.5 Masonry cements
10. These are used for preparing bricklaying mortars and stuccos, and must not
be used in concrete. They are usually complex proprietary formulations
containing Portland clinker and a number of other ingredients that may
include limestone, hydrated lime, air entrainers, retarders, waterproofers and
coloring agents. They are formulated to yield workable mortars that allow
rapid and consistent masonry work. Subtle variations of Masonry cement in
the US are Plastic Cements and Stucco Cements. These are designed to
produce controlled bond with masonry blocks.
1.2.1.6 Expansive cements
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 10
11. It contain, in addition to Portland clinker, expansive clinkers (usually
sulfoaluminate clinkers), and are designed to offset the effects of drying
shrinkage that is normally encountered with hydraulic cements. This allows
large floor slabs (up to 60 m square) to be prepared without contraction joints.
1.2.1.7 White blended cements
12. It may be made using white clinker and white supplementary materials such
as high-purity metakaolin.
1.2.1.8 Colored cements
13. These are used for decorative purposes. In some standards, the addition of
pigments to produce "colored Portland cement" is allowed. In other standards
(e.g. ASTM), pigments are not allowed constituents of Portland cement, and
colored cements are sold as "blended hydraulic cements".
1.2.1.9 Very finely ground cements
14. These are made from mixtures of cement with sand or with slag or other
pozzolan type minerals that are extremely finely ground together. Such
cements can have the same physical characteristics as normal cement but
with 50% less cement particularly due to their increased surface area for the
chemical reaction. Even with intensive grinding they can use up to 50% less
energy to fabricate than ordinary Portland cements.]
1.2.2. Non-Portland hydraulic cements
1.2.2.1 Pozzolan-lime cements
15. Mixtures of ground pozzolan and lime are the cements used by the Romans,
and can be found in Roman structures still standing (e.g. the Pantheon in
Rome). They develop strength slowly, but their ultimate strength can be very
high. The hydration products that produce strength are essentially the same
as those produced by Portland cement.
1.2.2.2 Slag-lime cements
16. Ground granulated blast furnace slag is not hydraulic on its own, but is
"activated" by addition of alkalis, most economically using lime. They are
similar to pozzolan lime cements in their properties. Only granulated slag (i.e.
water-quenched, glassy slag) is effective as a cement component.
1.2.2.3 Super sulfated cements
17. These contain about 80% ground granulated blast furnace slag, 15 % gypsum
or anhydrite and a little Portland clinker or lime as an activator. They produce
strength by formation of ettringite, with strength growth similar to a slow
Portland cement. They exhibit good resistance to aggressive agents,
including sulfate.
1.2.2.4 Calcium aluminate cements
18. These are hydraulic cements made primarily from limestone and bauxite. The
active ingredients are monocalcium aluminate CaAl2O4 (CaO · Al2O3 or CA
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 11
in Cement chemist notation, CCN) and mayenite Ca12Al14O33 (12 CaO · 7
Al2O3, or C12A7 in CCN). Strength forms by hydration to calcium aluminate
hydrates. They are well-adapted for use in refractory (high-temperature
resistant) concretes, e.g. for furnace linings.
1.2.2.5 Calcium sulfoaluminate cements
19. These are made from clinkers that include ye'elimite (Ca4(AlO2)6SO4 or
C4A3 in Cement chemist's notation) as a primary phase. They are used in
expansive cements, in ultra-high early strength cements, and in "low-energy"
cements. Hydration produces ettringite, and specialized physical properties
(such as expansion or rapid reaction) are obtained by adjustment of the
availability of calcium and sulfate ions. Their use as a low-energy alternative
to Portland cement has been pioneered in China, where several million
tonnes per year are produced.[17][18] Energy requirements are lower
because of the lower kiln temperatures required for reaction, and the lower
amount of limestone (which must be endothermicallydecarbonated) in the
mix. In addition, the lower limestone content and lower fuel consumption
leads to a CO2 emission around half that associated with Portland clinker.
However, SO2 emissions are usually significantly higher.
1.2.2.6 "Natural" cements
20. These correspond to certain cements of the pre-Portland era, produced by
burning argillaceous limestones at moderate temperatures. The level of clay
components in the limestone (around 30–35 %) is such that large amounts of
belite (the low-early strength, high-late strength mineral in Portland cement)
are formed without the formation of excessive amounts of free lime. As with
any natural material, such cements have highly variable properties.
1.2.2.7 Geopolymer cements
21. These are made from mixtures of water-soluble alkali metal silicates and
aluminosilicate mineral powders such as fly ash and metakaolin.
1.2.3. Cement industry in the world
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 12
Figure 1.1 Cement industry in the world
1.2.4. Global Cement Production in 2010
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 13
Figure 1.2 Global Cement Production in 2010
1.2.5. Global Cement Capacity in 2010
Figure 1.3: Global Cement Capacity in 2010
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 14
1.2.6. Cement output in 2004
22. In 2010 the world production of hydraulic cement was 3,300 million tonnes.
The top three producers were China with 1,800, India with 220 and USA with
63.5 million tonnes for a combined total of over half the world total by the
world's three most populated states.
23. For the world capacity to produce cement in 2010 the situation was similar
with the top three states (China, India and USA) accounting for just under half
the world total capacity.
1.2.7. China’s production
24. "For the past 18 years, China consistently has produced more cement than
any other country in the world. [...] (However,) China's cement export peaked
in 1994 with 11 million tonnes shipped out and has been in steady decline
ever since. Only 5.18 million tonnes were exported out of China in 2002.
Offered at $34 a ton, Chinese cement is pricing itself out of the market as
Thailand is asking as little as $20 for the same quality."]
25. In 2006 it was estimated that China manufactured 1.235 billion tonnes of
cement, which was 44% of the world total cement production.] "Demand for
cement in China is expected to advance 5.4% annually and exceed 1 billion
tonnes in 2008, driven by slowing but healthy growth in construction
expenditures. Cement consumed in China will amount to 44% of global
demand, and China will remain the world's largest national consumer of
cement by a large margin.In 2010, 3.3 billion tonnes of cement was
consumed globally. Of this, China accounted for 1.8 billion tonnes
1.3. Cement Industry in India
26. The cement industry in India is dominated by around 20 companies, which
account for almost 70% of the total cement production in India. In the present
year, the Indian cement companies have produced 11 MT cement during
April-September 2009. It took the total cement production inFY09 to 231 MT
27. Cement industry in India has successfully maintained almost total capacity
utilization levels, which resulted in maintaining a 10% growth rate. In 2006-07,
the total despatch was 155 MT, which rose up to 170 MT in 2007-08. The
month of October 2009 saw a cement despatch of 12.22 MT, which was
almost 9% higher than the total cement despatch of 11.21 MT in the same
month in the previous year.
Table 1.1:Cement industry in India
2009-10 (Apr-Oct) (in MT) 2008-09 (Apr-Oct) in MT
Production 101.04 95.05
Despatches (Excluding Export) 100.24 94.33
Export 1.46 2.16
Capacity Utilization (%) 85 93
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 15
1.3.1. Major Players in Indian Cement Industry
28. There are a number of players prevailing in the cement industry in India.
However, there are around 20 big names that account for more than 70% of
the total cement production in India. The total installed capacity is distributed
over around 129 plants, owned by 54 major companies across the nation.
29. Following are some of the major names in the Indian cement industry:
Table 1.2 Major Players in Indian Cement Industry
Company Production Installed Capacity
ACC 17,902 18,640
Gujarat Ambuja 15,094 14,860
Ultratech 13,707 17,000
Grasim 14,649 14,115
India Cements 8,434 8,810
JK Group 6,174 6,680
Jaypee Group 6,316 6,531
Century 6,636 6,300
Madras Cements 4,550 5,470
Birla Corp. 5,150 5,113
1.3.2. Recent Investments in the Indian Cement Industry
30. The following table indicates the major players and their share in the Cement
sector:-
Table 1.3 Recent Investments in the Indian Cement Industry(Million tonnes)
S. No. Group Installed Capacity Cement Market *
As on Production Share (%)
31.3.2009
30.9.2009 2008-09
2009-10
(Apr-Sep)
1 A.C.C. Ltd. 22.41 22.41 20.95 10.38 10.73
2 Grasim Industries 19.65 19.65 16.32 9.50 9.82
3 Ambuja Cements Ltd. 18.30 18.30 18.01 9.13 9.44
4 UltraTech Cement Ltd. 21.90 21.90 15.86 8.25 8.53
5 India Cements 10.74 11.84 9.11 4.94 5.11
6 Jaypee Group 9.93 12.13 8.05 4.79 4.95
7 Shree Cement 9.10 9.10 7.78 4.57 4.72
8 J.K. Group 9.37 10.17 7.50 3.93 4.06
9 Madras Cements 8.92 10.12 6.27 3.91 4.04
10 Century Textiles 7.80 7.80 7.22 3.70 3.83
11 Dalmia Cement 6.50 9.00 3.38 2.05 2.12
All India 219.17 230.82 181.61 96.73
* Based on Cement Production - 2009-10 (Apr-Sep)
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 16
1.3.3. Cemnt Production Scenario
31. The annual domestic demand of cement, the annual production of cement
and the export of cement during the last five years is as given below:-
(in Million Tonnes) Table 1.4 Cemnt Production Scenario
Year Demand of Cement Production of Cement
Export of Cement
2005-06 135.56 141.81 5.98
2006-07 149.34 155.64 5.89
2007-08 164.03 168.31 3.65
2008-09 177.98 181.61 3.20
2009-10 196.12 201.00 2.27
32. As per the Report of the Working Group on Cement Industry for the XI Five
Year Plan (2007-2012), the projected demand of cement for the next three
years is as given below:-
Table 1.5: demand of cement for the next three years (in Million Tonnes)
Year Demand of Cement
2010-11 231.66
2011-12 257.61
2012-13 ` 290.00
1.3.4. Capacity, Capacity Utilization and Production Growth
Table 1.6: Capacity, Capacity Utilization and Production Growth(Million tonnes)
Year Capacity Utilization% Production Production Growth (%)
2005-06 157.35 90 141.81 11.16
2006-07 165.64 94 155.64 9.75
2007-08 179.10 94 168.31 8.14
2008-09 205.96 88 181.61 7.90
2009-10 240.85 84# 201.37 12.67@
1.4. Cement industry in Jammu and Kashmir
1.4.1. Past Trend in Consumption
33. Consumption of cement in Jammu and Kashmir (JK) has increased from 650
thousand tones per annum (tpa) in 1998-993 to 707 thousand tpa in 2002-03,
and to about 1225 thousand tpa in 2005-2006. At present the annual increase
in cement consumption is around 17 %.
34. Besides the local cement supplies, the region has been receiving large
quantities of cement from the manufacturers outside the region.
35. Marketwise, JK may be divided into the 3 distinct zones of Jammu, Indian
Kashmir and Indian Ladakh. During recent years, the majority of total cement
consumption of Jammu was met by the ACC, Gujarat Ambuja and Shree
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 17
Cement brands brought in from outside. The average cost of these brands, as
of now, is as follows:
Lean period(Dec-Jan) Normal period(other mths)
(Rs/50 kg bag of cement) (Rs/50 kg bag of cement)
370 400
36. The same in Kashmir and Ladakh was met by suppliers from the region itself
the average cost of these brands, as of now, is as follows:
Lean period(Dec-Jan) Normal period(other mths)
(Rs/50 kg bag of cement) (Rs/50 kg bag of cement)
280 325
37. Cement supplies to Jammu and Kashmir from outside the State travel through
the Lakhanpur Checkpoint only and are required to pay the usual taxes such
as toll tax, octroi, sales tax, etc.
38. Some grinding units as well as mini cement plants of the state apart from
those listed in Exhibit: 2 are also supplying to Kashmir and Ladakh, from
within its own confines.
1.4.2. Future Demand
39. The demand for cement in Jammu & Kashmir is likely to increase. This is
keeping in view the past trend in consumption and likely increase in housing
and infrastructure rebuilding in the state.
40. Also the following projects are in the pipeline:
Railway line from Jammu &Baramulla covering 300 km (100 bridges and
tunnels within)
Mini hydel projects (12 Nos. from 5 to 20 MW within another 3 to 10
years)
Baglier power projects –400 MW –under construction
Uri II power project at Uri –400 MW- constructions started.
Due to militancy, a lot of hotels, bridges, govtoffices need major repair/
reconstruction. Also, due to the resurgence of tourism there’ll be new
hotels needing a lot of cement.
At the start of Srinagar-Muzaffarabad Bus service the Honorable Prime
Minister of India, Dr. Man Mohan Singh announced an economic
package of Rs. 24000 Crores for infrastructure development and out of
this almost Rs. 18000 Crores is to be spending on construction of hydel
power projects in the state.
41. The largest consuming areas in the state are generally in and around
Srinagar, the capital of Jammu &Kashmir .
42. Taking into account these growth trends, the demand for cement in Jammu
and Kashmir is likely to increase to 2.5 million TPA by 2015-2016.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 18
1.4.3. Current Supply
43. The cement plants in Jammu and Kashmir contribute a total installed capacity
of 1250000 TPA producing about 1100000 TPA at a capacity utilization level
of about 80% (average).
1.5. LIMESTONE DEPOSIT, ITS LOCATION, RESERVE AND GRADE
44. The limestone deposit for the proposed cement plant is located at about 30
Km north-west of Srinagar. The topography of the deposit area is hilly, and
surface of the deposit is steeply dipping. The approximate RL of the deposit
site is about 1830 m above MSL. The size of deposit is about 1.5 Km x 0.5
Km which has about 45 Million Tones of gross limestone reserve. The
average quality of limestone is as follows.
CaO : 53.01% MgO : 1.89%
SiO2 : 0.97% Fe2O3 : 0.41%
Al2O3 : 0.93% LOI : 43.00
Distance from present mine to : About 1.5 Km Proposed Cement Plant Present cost of mining of : Rs. 125/- Limestone per Tone inclusive Of breaking, loading, transport- Station and unloading Royalties and cuss per Tone : Rs. 63/- Of Limestone
1.6. The setting of cement
45. Cement sets when mixed with water by way of a complex series of hydration
chemical reactions still only partly understood. The different constituents
slowly hydrate and crystallise while the interlocking of their crystals gives to
cement its strength. After the initial setting, immersion in warm water will
speed up setting. In Portland cement, gypsum is added as a compound
preventing cement flash setting. The time it takes for cement to set varies;
and can take anywhere from twenty minutes for initial set, to twenty-four
hours, or more, for final set.
1.7. Safety issues
46. Bags of cement routinely have health and safety warnings printed on them
because not only is cement highly alkaline, but the setting process is
exothermic. As a result, wet cement is strongly caustic and can easily cause
severe skin burns if not promptly washed off with water. Similarly, dry cement
powder in contact with mucous membranes can cause severe eye or
respiratory irritation. Cement users should wear protective clothing.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 19
2. PROCESS DESCRIPTION
2.1. Introduction
2.2. Process Technology
2.2.1. Dry Process Cement Manufacturing Technology
47. The most important advancement in cement industry is has been the
development of dry process rotary kiln systems using pre-calcination
technology for manufacture of cement clinker in rotary kiln. In pre-calcination
system a degree of calcination of raw meal up to around 90-95% is achieved
in the pre heater itself before the raw meal enters the kiln.This is achieved by
introducing a secondary firing at the pre heater. With this the volume rating of
the kiln increases and same size of kiln can give much higher output. In fact
precalcination technology is adopted for larger size plants, however, the same
can be used for increasing the output of an existing plant as well.
2.2.2. Advantages of Dry Process System using precalciner system
Stable coating in the burning zone, so higher refractory life which
leads to higher availability of the kiln itself and lower inventory cost on
refractories.
Due to stable kiln operation, the quality of clinker as well as thru’ put
from the kiln shall also be consistent over a longer period of operation.
Considerable savings in cost of fuel.
Better advantage in marketing of cement as produced from rotary kiln
than existing Vertical Shaft Kiln System.
In the precalciner vessel low grade fuel can be used successfully, if
required.
The No emission itself is lower than conventional kiln. No level can
further be reduced in case of pre-calciner system by suitably designed
precalciner vessel in a simple and inexpensive way.
48. Due to the above advantages it is a very common practice now a days to
install dry process rotary kiln system using precalciner system.
2.3. Process Technolgy Description
49. Cement manufacturing process in our plant is described in section wise
manner as under:
2.3.1. Limestone Crushing
50. Run of mines (ROM) limestone is transported to the plant using tipper
trucks. The ROM limestone is unloaded in the hopper of the limestone
crusher and transported to the double impactor crusher by an apron
feeder. To maintain a buffer stock, ROM limestone will be taken to
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 20
uncovered storage for use during peak winter season. A hammer
crusher will be employed to crush the raw material to -25 mm size.
51. Crushed limestone is taken to the limestone bunker. Limestone from the
bunker is extracted by set of weigh feeders and delivered to a set of belt
conveyor for further feeding to the raw mill.
2.3.2. Raw Material Drying & Grinding
52. Based on the raw mix design three raw material hoppers have been
provided in the raw mill department. Hoppers are covered and vented
through a dust filter.
53. Raw materials and additives are withdrawn from the hoppers by
electronic weigh feeders to maintain its proportion as per raw mix design.
Discharge from the weigh feeders is conveyed by a belt conveyor and is
fed to a ball mill for grinding of raw material. After grinding coarse
fraction is separated and returned to the mill by the classifier followed by
air slide and impact scale. Material thus separated is further ground
inside the mill while the fines i.e. product is sucked by the Separator ID
fan through a battery of cyclones where the product is separated from
the gas stream.
2.3.3. Raw Meal Homogenizing & Kiln Feed System
54. In raw mill department various raw meal components are proportioned,
however, the composition of raw material varies over a period. The
variation in the raw material composition is controlled and evened out
such that it is acceptable to kiln for a stable operation.
55. A continuous homogenizing & storage silo of RCC is provided for
homogenizing the raw mealBlended materials from continuous flow silo
is conveyed by air slide and discharged to a bucket elevator which, in
turn, discharges it to a load cell hopper known as kiln feed bin.
Controlled materials discharged from the kiln feed bin is sampled for
quality control and fed to bucket elevator for feeding to pre heater.
Recirculation sys tem is provided at the discharge of bucket elevator
which takes the material back to the blending silo when kiln is not
operating for a short duration.
56. Kiln feed bin and bucket elevator is vented by separate dust filter.
2.3.4. Pyro-Processing (Preheated, Precalciner,Kiln & Cooler) Section
57. A single stream of five stage pre heater of the latest proven high
efficiency, low pressure drop design with in-line precalciner is provided
for preheating of raw meal. Pre heater consists of a system of cyclones
connected with gas ducts. The gas is sucked by the pre heater fans
through the kiln and pre heater system. Raw meal is introduced in the
gas duct to the to stage cyclone. Gas and raw meal are intimately mixed
as they enter the gas duct. The heat exchange between the gas and raw
meal takes place in the gas ducts and separation of the heated raw meal
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 21
takes place in the cyclones. This separated raw meal is fed to the gas
duct of the next stage cyclone.
58. Raw meal from Stage-IV cyclone is fed to the precalciner. Fuel and
combustion air are fed to the precallciner at a point, where they are all
intensely mixed and combustion of fuel takes place and the heat is
transferred to raw meal. The gas velocities and length of the precalciner
duct are so arranged that the required degree of precalcination is easily
achieved.
59. The combustion air for the fuel fired in precalciner is taken from the
cooler Ist grate through dust settling chamber and tertiary air duct.
60. The precalcined raw meal (about 90% precalcination) enters the Stage-
V cyclone of the pre heater and is separated and fed to the kiln inlet.
61. The kiln is equipped with a three channel burner. Control on the axial air
and swirl air allows for a precise control on the flame under all
conditions. Kiln is fired with pulverized coal and latest design swirl
chamber burner has been provided for generation of low Nox and
greater heat transfer.
62. The clinker formed in the kiln is cooled in a third generation reciprocating
grate cooler with maximum heat recovery by addition of cooling air, from
the red hot clinker and subsequent utilization of the same as tertiary air
in the calciner. Secondary air required for combustion in kiln I sucked by
pre heater fan from cooler. This reduces the overall energy consumption
for the clinkerisation process. Adequate number of cooling air fans are
provided to supply necessary cooling air. An Electrostatic precipitator
has been provided for dedusting of dust laden cooler gas to meet
pollution norms and the gas is vented to the atmosphere. The spillage
from the cooler is collected in the hopers below the grates and
discharged to the drag chain conveyor.
63. The cooled clinker is discharged to a deep bucket conveyor. Spillage
from the cooler as well as the dust collected in the ESP hopper is also
discharged to the same deep bucket conveyor for further transport to
clinker stockpile.
2.3.5. Clinker Storage, Grinding and gypsum crushing
64. Clinker from the grate cooler is stored in a tent type storage hall with
central column for minimizing dust generation. Clinker is extracted using
set of vibrating feeders and delivered to a pair of belt conveyor followed
by common belt for gypsum & clinker for taking to cement mill feed
hopers.
65. The system provided consists of one no. closed circuit clinker grinding
system with ball mill. Proportioned quantity of clinker and gypsum to be
ground is extracted from the hopers by electronic weight feeder. Mixture
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 22
of clinker & gypsum thus extracted is transported to the ball mill by a belt
conveyor.
66. Ground material from the mill is discharged via an air slide to a bucket
elevator which in turn discharges it to a high efficiency separator. The
material is fed into the centre of the distribution plate and evenly
dispersed throughout the separating chambers. The finished material is
collected in externally mounted high efficiency cyclones. The coarse
material from the separator is fed back to the mill via an air slide and a
solid flow meter.
67. The separated finished material is fed to the cement transport system by
air slides. Mill venting is achieved by a bag dust filter along with other
auxiliary vents.
2.3.6. Cement Storage & Packing
68. The cement produced is stored in RCC float bottom type silo. For
feeding the cement to the packing section air slide and bucket elevator is
used. Cement from the bucket elevator is discharged to the vibrating
screen. Foreign materials, if any are separated in the vibrating screen
and cement is dropped to the packer bin located below. 1 No Electronic
rotary packing machine is installed. Bagged cement is delivered to the
two plat form mounted type truck loaders for loading on trucks.
2.4. Product Storages
2.4.1. Sizing of storages
NORMAL CAPACITY OF KILN PLANT : 3500 TPD Clinker
CLINKERISATION FACTOR : 1.56
Sr.No. Major Storages Capacity TPH
1 Limestone, Crushed 50000
2 Sand stone/Sand Under Shed 15000
3 Wet Clay Under Shed 20000
4 Raw Coal 15000
5 Pet Coke 5000
6 Raw meal in RCC silo 25000
7 Clinker Tent 30000
8 Cement RCC Silo 10000
9 Gypsum Storage 5000
2.5. Raw materials and Auxillary Operations
69. One of the basic raw materials for the proposed plant is limestone which
is available within a distance of 1.0 Km from the proposed plant site. The
limestone deposit is approximately 1.5 Km long and is in the form of hill.
The one side of the deposit is very stiff and the other side has gradual
inclination. The gradual inclination is on the northern side of proposed
plant and mining on this side will be easier. Accordingly, the plant
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 23
location has been determined on the southern part of the deposit. The
present requirement is about 1350000 tones of limestone per annum
which can be directly sent from mines to the proposed location by
suitable tipper truck. The estimated annual requirement for other raw
materials for the production of cement is
(i) clay/silica stone – 425000T,
(ii) sand – 150000 T and
(iii) gypsum – 60000T.
(iv) coal 200000 T
(v) Packing bags.
70. Based on the raw mix design as mentioned hereinafter, the requirement
of other raw materials and fuels for the 3500 TPD rotary Kiln plant will
be clay, sand, gypsum, and steam coal . The clay, gypsum and sand are
locally available. Iron ore, and steam coal will have to be procured from
Punjab and South Africa respectively.
2.5.1. Proposed mining operation
2.5.1.1 Scale of Operation for Limestone Mine
71. Based on the clinker production of 3500 TPD, the proposed requirement
of limestone has been worked out as follows.
Table 2.1: SCALE OF OPERATION
1 Capacity of Clinkerising Plant, Tonnes per day 3500
2 Clinkerising Factor 1.56
3 Moisture Content, @ 6% 1.06
4 Transit Loss, 2% 1.02
5 Limestone in Raw Mix @ 76% 0.76
6 Requirement of Limestone Tonnes per day 4000
7 No. of operating days of Cement Plant per year 330
8 Limestone required for Clinkerising plant Tonnes per year 1350000
9 Operating days of mines per year considering 30 days will be lost for severe cold and 65 days for Sundays, holidays and other festival leaves
270
10 Daily mining requirement of limestone, Tones 5000
11 Say in Tonnes per day 5000
12 No. of shift per day 2
13 Anticipated stripping ratio Lst: ob:T:T 0.15
14 Overburden to the handled per day in tones 250
2.5.1.2 Proposed Method of Mining
72. The proposed Method of Mining will be fully mechanized open cast,
adopting drilling & blasting and with the use of heavy earth moving
equipment. Based on the scale of operating and considering the cement
plant life of about 30 years, the deposit has ample reserve to supply the
limestone to the proposed plant on sustainable basis.
2.5.1.3 Requirement of Equipment & Infrastructure
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 24
73. Based on the scale of operation and method of mining as mentioned
above, the type of mining equipment & infrastructure has been shown
below. The requirement of Civil & Structural works is also mentioned
here and some of them are required by statue. The other infrastructure
requirements for mining like electric power supply (for auto-workshop &
mine illumination), water supply (for drinking) and colony for
accommodation of mining personnel will be part of the in the cement
plant infrastructure.
Table 2.2: PROPOSED REQUIREMENT OF MINING & GARAGE EQUIPMENT
Sr. No. Equipment Particulars
A Mining Equipment
1 DTH Drill Rig-100-130 mm dial. Holes
2 Compressor –450 cam, 150 phi
3 Jack Hammer –32 mm dial. hole
4 Compressor –360 cam, 120 phi
5 Hydraulic Excavator – 2.8 m3
6 Wheel Loader 1.7 m3 bucket capacity
7 Dumper-35 Toner,
8 Dozer –165 HP
9 Explosive Van –10 Tone Capacity
10 Ambulance
B Garage Equipment
1 HOT Crane 10T
2 Compressor
3 Welding Transformer, 500 amps each
4 Washing machine with air compressor(stationary & mobile each)
5 Lifting tackle, Chain block
6 Pneumatic grease & oil pump
2.5.2. Mining of Clay/silica stone.
74. It has been mentioned earlier that the clay/silica stone is available in
nearby sources.
75. The method of mining of clay/silica stone deposit will be open cast for
excavation, loading and transportation of clay/silica stone with the
following considerations.
(a) Proposed capacity of the cement plant is 3500 Toner per day.
(b) Considering the intensity and duration of severe cold, the no. of operating days/year has been considered as 270 days, whereas cement plant will be operated 330 days/year.
(c) The clay/silica stone quarry is proposed to be worked in one eight hour shifts per day to achieve the contemplated rate of production.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 25
(d) Clay/silica stone will be mined with deployment of major mining equipment like hydraulic excavator (backhoe type) and tipper truck as mentioned earlier.
(e) The haul distance from clay/silica stone quarry to cement plant has been considered about 7Km. The support services for clay quarry will be available either from cement plants as and when required.
2.5.2.1 Scale of Mining for Clay/Silica stone
76. The scale of clay/silica stone mining has been derived as follows based
on the proposed capacity of the cement plant (clinker) is 3500 Tone per
day.
SCALE OF CLAY/ silica stone MINING OPERATION
Sl. No. Particulars
1 Quantity of Raw Mix @ 1.6 times of Clinker production in Tonnes per
day
5600
2 No. of Operating days of cement plant per year 330
3 Operating days of mines per year 270
4 Requirement of Clay/ silica stone @ 21 % of Raw mix, Tonnes per
day
1176
5 Requirement of Clay/ silica stone Considering moisture content 5%
Tonnes per day
1235
6 Say 1250
2.5.2.2 Production and development programmed for clay/ silica stone quarry
77. The scale of mining operation of clay/ silica stone is @ 1250 TPD.
Before starting the regular production operation from the clay/ silica
stone quarry, the initial mine cut and terminal approach road from the
quarry to existing road to plant may have to be prepared.
2.5.2.3 Requirement of Mining Equipment
78. Based on the Production and Development Programmed as mentioned
earlier, the requirement of mining equipment is given below in the Table.
REQUIREMENT OF CLAY/ SILICA STONE MINING EQUIPMENT & BUILDING
Sr. No Particulars of Equipment
1 Hydraulic Excavator- 1.0m3
2 Tipper- 10 Tone
79. For production of 3500 TPD the following would be the annual
requirement of Non –coking coal
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 26
Requirement OF Non-coking coal
Sl. No. Particulars
1 Daily Clinker production 3500
2 No. of Operating days of cement plant per year 330
3 Annual production 1155000
4 Coal consumption @ 17 % 196350
5 Say 200000
2.6. Broad sizing of major plant & machinery and storages
2.6.1. Plant Capacity
80. This plant has been designed for daily production of 3500 Tonnes of
clinker which works out to 1155000 tones per annum of clinker based on
norms for operation.
2.6.2. Norms For Equipment Sizing
81. The following norms based on consultant’s experience with the
international cement industry have been developed for sizing of plant &
machinery. This will enable the plant to deliver output at a desired level
on sustained basis.
Clinkerisationfactor : 1.56 Raw Meal : 1 Clinker
Fuel : Petcoke : Coal = 60 : 40
Raw Mix : Limestone : Clay/silica stone : Sand = 76:21:3
82. The operating hours for main machinery are given in Table. These
operating hours have been established based on the operating data of
cement plants.
SIZING OF PLANT & MACHIHNERY
NORMAL CAPACITY OF KILN PLANT : 3500 TPD Clinker CLINKERISATION FACTOR : 1.56
SR.No
Major Equipment Effective hours of Operation per Working Day
Working day per Week
Capacity TPH
1. L/S Crusher 10 6 600
2. Tripper Conveyor 10 6 700
3. Reclaim Conveyor 13 7 700
4. Clay Drier 16 7 75
5. Raw Mill 22 7 300
6. Raw Coat/Pet Coke/ Gypsum Crusher
12 7 75
7. Rotary Kiln 24 24*7 150 TPH
8. Coal Mill 20 7 40
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 27
9. Cement Mill 20 7 200
10. Packing Plant 15 6 400
11. Truck Loader 15 6 400
2.6.3. Norms for Storage Capacity
83. Norms for sizing of storages vary from plant to plant depending upon the
location of the plant with respect to location of the sources of various
input material.
84. Taking into consideration the proposed plant location, the norms given in
Table- have been adopted for deciding the storage capacity.
TABLE :SIZING OF STORAGES
NORMAL CAPACITY OF KILN PLANT : 3500 TPD Clinker CLINKERISATION FACTOR : 1.56
Sr.No. Major Storages Capacity TPH
1 Limestone, Crushed 50000
2 Sand stone/Sand Under Shed 15000
3 Wet Clay Under Shed 20000
4 Raw Coal 15000
5 Pet Coke 5000
6 Raw meal in RCC silo 25000
7 Clinker Tent 30000
8 Cement RCC Silo 10000
9 Gypsum Storage 5000
2.7. Instrument and Control Philosophy
85. For complete automation of the various sub-sections of the proposed
plant, an integrated as well as Segregated control system has been
envisaged. The integrated system has been adopted for the main plant
section viz. the operation of the Raw Mill, Kiln, and Cooler whereas a
segregated control system is adopted for lime stone crushing section.
86. A geographically as well as functionally distributed PLC based control
system with decentralized intelligence has been envisaged for the main
plant section viz. Raw Mills section. Kiln feed and pyroprocessing section
whereas a conventional Relay based system has been envisaged for the
limestone crusher.
87. A PLC based control system has been envisaged for the control of the
entire cement grinding and packing plant whereas a conventional relay
based system has been envisaged for gypsum crushing section.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 28
88. Programmable controller PC with in built microprocessor based
controller shall be used for automatic control of the main plant and
cement Mill section.
89. The system will encompass the following sub-areas:
a) Automatic closed loop control
b) Binary logic (interlocks, protection and sequential logic control)
c) Monitoring system
90. Programmable controller with integrated facility of control and data
acquisition system for monitoring of plant parameters along with
programmable logic control feature of meeting requirement of sequential
starting/stopping of drivers, plant interlock and protection has been
conceived.
91. DAS, DDC, and PLC functions are generally envisaged as an integral
system to be performed by the CPU of the programmable controller.
2.8. Project Utilities
92. The utilities and auxiliary service of the proposed cement plant shall
comprise the following.
2.8.1. Compressed air system.
93. Compressed air to be supplied to the following equipment:
All pulse jet just filters.
Packing machine.
Cement mill water spray system.
Girth gear spray lab system
Pneumatic air-seals, pneumatic operated valves etc.
Process instruments and control as applicable.
94. Centralized compressed air system has been considered for the plan.
Three nose (2 working & 1 stand by ) none lubricating, reciprocating
horizontal, balanced opposed water cooled compressor has been
considered.
95. Compressor shall be designed for continues duty operation. Necessary
Silencer to be provided to reduce noise during depressurization of the
vessel. Each compressor shall be provided with dedicated air drying
plant.
96. The dryer shall be latest design refrigerant type. Air coming out from
drier have a dew point above 4000C.. Major transfer point shall be
provided with invertible bag-filtered tarrest the dust nuisance.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 29
97. Brief specification of the compressor proposed for the project shall be as
follow:-
Nos. : 3 ( 2 W & 1 SB
Type : Reciprocating, non lab
Free air delivery : 12N m3/min.
Discharge pressure : 8kg/c m2
Type of air drier used : Refrigerant type
Capacity of air drier : 12N m3/min. ( W &1 SB)
2.8.2. Inplant laboratory and quality control.
98. The Plant laboratory is presently equipped to carry out various tests on
cement raw materials e.g. Limestone, iron ore, clay, clinker & gypsum
essential for sustained production of quality product ( cement ) as per the
adopted standard.
2.8.3. Maintenance workshop
99. A full flagged self sufficient maintenance workshop has been provided
for day to day maintenance of the plant equipment and the same is
sufficient to cater the plant requirement even after expansion
2.8.4. Fuel
100. Petcoke and coal will be used as a fuel in this project for providing the
necessary thermal energy for conversion of raw materials into cement
Bothpetcoke and coal will be transported to Jammu railway yard by box-
type wagon. Thereafter, the same will be transported to the proposed
projected site by road transport. The source of the coal will be from the
collieries of Bengal and Bihar.
2.8.5. Water Supply and Distribution(Water Balance to be provided)
101. The infrastructure facility for supplying water to the proposed location of
Cement Plant is available as sufficient quantity of underground water is
available. This water can be utilised by existing bore-well. The water IS
kept in a ground reservoir of capacity of 500 m3/day and from this
reservoir a distribution network takes water to various areas.
2.8.5.1 Industrial Water.
Mines
- Drinking water : 0.25m3/hr
- Car washing, Sprinkling : 1.0m3/hr
- Sub total : 1.25m3/hr
Cement Plant
- Drinking water : 1.3m3/hr
- Including colony
- Colony : 4.5m3/hr
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 30
- Process water cement mill : 3.5m3/hr
- Sub-total : 8.3m3/hr
Consumption in laboratory : 1.0m3/hr
Workshop, air conditioning, etc.
2.8.5.2 Cooling water
Raw Mill bearing, gearbox, : 40m3/hr
mill lubrication.
Cement mill gearbox, bearing and : 45m3/hr
HES gearbox.
Pyroprocessing including kiln drive : 25m3/hr
Gearbox, supporting rollers, etc.
Air compressors : 10m3/hr
- Sub total : 120m3/hr.
Make up water for cooling water : 12m3/hr
@ 10% of cooling water
-Total consumption : 20.05 m3/hr
In mines and names plant i.e about 480m3/hr
Excluding firefighting water.
102. To cater the need for the mines and the cement plant, bore well
pumps (2nos ) shall be installed. The water will be pumped and stored
into a ground water reservoir with a day storage capacity. Further
distribution will be done through circulating pumps and separate
overhead tank shall be installed on roof of respective building. Return hot
water shall be collected into a pit and shall flow to the return hot water
tank by gravity. Further cooling may be done in spray pond and goes
back to the its tank for further distribution.
103. Drinking water shall directly collect over a drinking water storage
overhead tank for gravity distribution of water to various consumption
points.
2.8.6. Power
104. The power required for running the cement plant and its auxiliaries can
be obtained from the PDD Substation located at a distance of 3.5 Km
from the proposed plant site. A 33 KVA line is to be drawn from the
above source and can be connected to the transformer of the proposed
cement plant. Thereafter, necessary distribution of power can be thought
of as per the electrical load requirement of the different sections of the
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 31
proposed cement plant. The total power requirement for the 3500 TPD
cement plat as envisaged now is about 15 MVA’s
2.8.7. Other facilities
105. Other facilities such as school, housing, bank, police station, fire fighting
facility, medical service etc. are available within a stretch of 5 Km from
the plant site. It will be necessary for the project to provide some basic
infrastructure facilities to their staff, workers and their families.
2.8.8. Employement Generation:
106. By taking the above factors in consideration, the main-power
requirement has been estimated. The summary is given below:-
Quarry (Through Contract) :200
Administration : 50
Production :150
Maintenance : 150
Others : 50
Sub-Total :------
Total (direct and Indirect) :600
2.9. Environmental aspects
107. Cement industry is classified as a pollution – prone industry by
International Funding Agencies with the potential to cause environment
problems if proper mitigation measures are not taken.
108. Clinker and cement manufacturing plants pose environmental hazards to
the land, vegetable, atmosphere and inhabitants within the vicinity of the
factory. Most of these environmental hazards have been identified and
measures taken during the design of the plant to minimize discomfort,
inconvenience and ill health to the factory workers as well as the local
people. The main identified areas of degradation land pollution are as
follows.
i) Land degradation due to mining activities.
ii) Noise hazards associated with ball mills.
iii) Hazards from toxic and corrosive exhaust gases from the kiln
especially toxic gas like carbon monoxide ( CO ), corrosive gas
like sulphur dioxide ( SO2 ).
iv) Emission of cement dust.
2.9.1. Land Degradation
109. Limestone deposit at the proposed plant location will be mined by the
open cast method. By this method the land will be stripped of its
vegetable and underlying to soil called overburden in order to get to the
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 32
limestone layer. In order to minimize the land degradation, deforestation,
overburden disposal and water pollution adequate and suitable
measures shall be considered during the conceptual design of the plant
2.9.2. Pollution by effluent gases
110. The main pollutants is exhaust gases in a clinker plant are gases from
the combustion of the residual oil and dust from the kiln operation. The
exhaust gases include carbon dioxide expelled from carbonates of
calcium and magnesium of the raw meal during calcination of clinker and
nitrogen from the theoretical air needed to provide the oxygen for
burning the fuel.
111. The combustion therefore gives out carbon dioxide predominantly from
the combustion of carbon, a little water vapor from the combustion of
hydrogen and some traces of sulphur dioxide from the burning of
sulphur. From the above, the effluent gases contain mostly carbon
dioxide from decarbonization and from combustion, water vapor,
nitrogen and traces of sulphur dioxide. Except for the sulphur dioxide,
the rest are not nuisible, especially in a rural area. The sulphur dioxide
is nuisible. It picks up water from the atmosphere to from sulphurous
acids, a corrosive acid responsible for corrosion in roofing sheets and
metallic installation. Design of the plant has taken care of this problem.
2.9.3. Sulphur dioxide in the ambient
112. Based on the daily production of 600 tons and maximum percentage of
sulphur in the fuel as 0.3% an attempt is made to calculate the possible
amount of sulphur dioxide in the kiln effluent gases and to establish its
acceptability in line with EPA norms.
113. From the above calculate, it can be concluded that the possible amount
of sulphur dioxide which may be emitted by the kiln exhaust ( 25/m 3 )
is within the acceptable level of EPA norms of up to 80 u/m 3 in an
industrial area for one year.
114. There is also the possibility of burning carbon to carbon monoxide, which
is very toxic, instead of carbon dioxide. This occurs, when burning
conditions are not well controlled, especially when there is not enough
oxygen or when the burning zone temperature reduces suddenly, or
when there is too much dust in the clinkerisation zone.
115. Ducts will be provided at vantage point to draw exhaust gases from time
to time to analysis in the laboratory to make sure that they are free from
suspended particles and nuisible gases.
116. Continuous carbon monoxide and excess oxygen analysers will be
provided to facilitate the control of CO formation. To achieve this, the
combustion on fuel should be carried out in the presence of a minimum
of 1.5% excess oxygen in the kiln outlet to ensure complete combustion.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 33
117. Moreover, apart from environment pollution, the carbon monoxide is very
nuisible to the operation of the kiln itself, ( 1 ) it is endothermic i.e. it
reduce the temperature of the zone and (2) it can cause explosion in the
electrostatic filters and in the cyclones. The operation will strictly
monitored to check the production of carbon monoxide.
2.9.4. Air pollution
118. Control of dust emission into atmosphere shall be achieved by the
following facilities provided for the plant and machinery of the project:-
Designing the production system so as to generate minimum dust and
arrest the dust at its source. All storage facilities of material like
limestone, raw meal, clinker, cement etc shall be in the form of RCC
silos completely covered to completely eliminate dust emission at
these storage points.
Minimizing the number of material transfer points and maintaining
optimum height of fall of materials.
Providing high efficiency pulse-jet bag filters at material transfer points
including mill feed hoppers. Special bag filters shall be designed to
take care of the condensation problem which leads to bag filter
choking particularly in J & K.
Covering the belt conveyors including walkways.
Providing suitable dust collecting equipment either pulse-jet bag filters/
glass bag houses or ESP for process exhaust gases.
Providing metal roads inside the plant.
Efficient cleaning of plant internals using vacuum cleaners.
119. Control of emission of toxic gases can be achieved to fulfill the prevailing
pollution control norms by:-
Using latest technology and equipment in order to minimize generation of various toxic gases.
Reducing the concentration of pollutants like NOX and SOX in the flue gas.
Reduce CO formation by use of calciner.
120. For the project, the emission standards will be so formulated as to limit
dust concentration in exhaust gases from the following source points
within a maximum limit of 40 mg/ Nm3 of exhaust volume. This would be
one of the lowest emission levels in the country.
Limestone silo,Raw meal silo, clinker stockpile and cement silos by bag – filters.
Raw mill and cement mill hoppers by bag-filters.
Raw grinding and kiln exit gases by glass bag filter.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 34
Clinker cooler exhaust by ESP.
Raw and cement mill and cement packing plants by bag – filters.
2.9.5. Water pollution
121. Because of the technology of cement production, the degree of water
pollution caused by waste water is relatively low. The major pollutants
are lubricating oil, grease and dust in the water. Care will therefore, be
exercised to design feeding and draining of water for all machinery on
close circuit basis so that no waste water is discharged from the plant
during normal operation and the same is rescirculated after proper
treatment.
2.9.6. Noise pollution control
122. Noise has been defined as “any undesired sound” unwanted sound” and
thus is concept of feeling having adverse effect on human health. The
unit of noise measurement used in scientific studies is a “decible” ( dB)
and the prescribed norms for occupational exposure for cement plant is
90 dB in 8 hours period. For any noise control programme, the basic
elements of noise – source, path and receiver must be attended to.
123. In a cement plant, the main source of noise generation are mills, fans,
blowers etc. while selecting the main plants and equipment for the
proposed cement plant, installation of alternative low noise generating
equipment shall be preferred, all drives and transmission mechanisms
shall be put under enclosures. Persons working in and around the noise
generating spots shall be provided with ear plugs/ear muffs. In addition
to the above, wherever possible, the travel path of noise shall be
obstructed by providing walls and green belts between the source and
receiver.
2.9.7. Safety precautions.
124. In compliance with international standards on safety, a unit will be
created under the production division to see to the implementation of all
safety measures in the factory. The unit will be headed by an inspector
who will go round and ensure that all safety devices and measures put in
place are infact. This unit shall be responsible for the supply of protective
working clothes, safety helmets and safety boots to all personnel in the
production division. It will also supply ear and nose masks to personnel
at the raw meal mill and the cement mill, as well as safety goggles,
asbestos aprons and asbestos gloves to personnel at the preheated and
kiln outlet. Welders will be provided with face masks and goggles and
electricians with insulating gloves. The safety inspector will see to it that
all workers wear these safety aids.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 35
3. SITE ANALYSIS
3.1. The Site Location
125. Trumboo Industries Pvt. Ltd. is planning to set up a 3500 TPD cement
plant at Khrew Dist : Pulwama located in the north-west side of Srinagar,
15 km away from it and on the western side of Jammu-Srinagar National
Highway from where the plant is 10 km away and is connected by a
moderately (20 ft.) wide kachha road.
S.No. Particulars Description
1) Village, Tehsil, District, State Near kherw,Distic Pulwama
2) Longitude and Latitude 3404’34.14”N
74058’35.5”E
3) Land 40 Hectares Required
4) Land status Barran Land
5) Most Populated area Khanmao 3.28km(SW),Wuyan,5.63km(SSW),Andorssa,7.14km(S)
6) Nearest High Way NH-1A,8.27 km(South WEST)
7) Nearest Village khrew
8) Nearest Town Pulwama
9) Nearest Air Port Srinagar
10) Location of National parks
/Wildlife Sanctuary within 10 km radius of the project site
There is a Dachigam National forest at a distance of 2.58 km(North)
3.2. Salient Feature Of The site:
126. The important factors which influence its selection of a project site are as
below.
3.2.1. Sources of Raw Materials
Availability of suitable Land
Road and rail linkage
Transport facility for finished products viz. Cement
Availability of fuel, power and water.
Availability of skilled Manpower.
Nearness to market for finished goods viz. Cement.
Social infrastructure viz. Banks, post office, schools, markets, community centre, housing etc.
3.2.2. Availability of suitable land
127. During the site visit, availability of land for plant site was seen and found
that enough land is available for the plant close to the limestone deposits
at Bajnar location.
3.2.3. Road linkage and transportation of cement
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 36
128. The proposed location is connected with National Highway between
Jammu and Srinagar by a link road of 10 Km stretch.
129. Considering the above factors, the site for the project has been located
and selected in the village Khrew, Dist: Srinagar which is 30 km away
from Srinagar and at a distance of 15 km away from National Highway
connecting Jammu and Srinagar.
3.3. Layout Of the Plant
130. The layout of the facilities in the Cement plant has been planned,
keeping in view the technological concept in cement plant operation.
Following are the basic criteria for preparation of the respective layouts.
131. Direction and flow of materials, both input and output.
Directions of incoming power supply.
Ground contour of the plant areas.
Compactness of the plants keeping in view enough space for easy
movement of men, materials and plant machinery.
Provision for expansion of the plant in future
Direction of prevailing wind
Nearness to colony
3.4. Layout of the cement plant
132. The layout of the proposed cement plant shall be prepared after
finalization of main machinery and equipment and keeping in
consideration of the existing plant facilities. The plant layout shall also be
based on the soil investigation report and contour survey.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 37
4. PROJECT COST AND SCHEDULE
4.1. Project Implementation:
About 40 months after finalization of investment.
4.2. Estimated cost of the project and financial indicators.
Sl. No.
Cost Head Estimate in (Rs.)
Estimate in (Lacs. of Rs.)
% of Total
1 Land and Site Development
100,000,000 1,000.00 2.10
2 Building & Civil Works 1,019,000,000 10,190.00 21.44
3 Plant and Machinery 2,593,400,000 25,934.00 54.57
3.1 Foundation 8,300,000 83.00 0.17
4 Technical Know-how Fees
7,500,000 75.00 0.16
5 Miscellaneous Fixed Assets
100,000,000 1,000.00 2.10
6 Preliminary & Capital Issue Expenses
5,000,000 50.00 0.11
7 Pre-operative Expenses
16,173,600 161.74 0.34
8 Start-up Expenses 5,441,926 54.42 0.11
9 Sub-Total (1 to 8) 3,854,815,526 38,548.16 81.11
10 Contingency 150,000,000 1,500.00 3.16
11 Sub-Total (9 to 10) 4,004,815,526 40,048.16 84.26
12 Interest during Construction
500,000,000 5,000.00 10.52
13 Margin Money for Working Capital
248,046,000 2,480.46
5.22
14 TOTAL PROJECT COST
4,752,861,526 47,528.62 100.00
Financial Indicators. (All Figures in Rs Lakhs)
Clinker Production: 3,500 TPD IRR 33.30%
No. of Working days per Year
330 Rs. in Lacs
Annual Production of Cement :
1,155,000 T LOAN Rs30,893.60
Debt: Equity 1.86 : 1 EQUITY Rs. 16,635.02
Interest p.a. (Long Term)
10.50% TOTAL Rs.47,528.62
Interest p.a. (Short Term
11% D:E 1 .86: 1
Per ton investment cost
4,115 DSCR 7.36
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 38
5. INDUSTRIAL POLICY 2004
1.0 Introduction
1.1 Despite attractive fiscal incentive under the State’s Industrial Policy (1998-2003),
the rate of growth of industrial sector could not be accelerated primarily on account
of the disturbed conditions in the State. Competition from cheaper imported
products, coming into the country as a result of the policy of globalization and
economic liberalization pursued by the Government of India, has also forced many
local SSI units to down their shutters. With the problem of unemployment,
particularly of the educated, being high, the Industrial Policy 2004 has been
evolved keeping in view the experience gained in the last five years and some new
positive elements that have entered the scene.
Duration 1.2 Industrial Policy 2004 will remain in operation from 1st February, 2004 until 31-03-2015.
2.0 Advantage J&K Some specific advantages enjoyed by the State are: 2.1 Introductions of incentives for industries based on the package for the North-
Eastern State in Jammu & Kashmir by the Government of India has created a
new window of opportunity. This package of incentives is attached at
Annexure - I.
2.2 Centrally sponsored schemes available for development of infrastructure and
common facility Centres are fully utilized to strengthen and broaden the
infrastructure base of the State in general and for industries in particular.
2.3 Refinance facilities are available from the prime leading financial institutions.
2.4 Infrastructure in the State for handicrafts and handloom sectors is being
strengthened to further hone the already superb craftsmanship available in
the State by providing professional assistance in design, product
development, quality control, marketing and human resources development,
with emphasis on active private sector participation.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 39
2.5 The state is endowed with rare agriculture and horticulture germplasm. The
State has three distinct agro-climatic zones, each with its characteristic
products, thus offering a wider choice for establishing agro-industries. With
57% of apples and 92% of walnut produced in the country being from the
State, besides a host of other horticulture produce such as almonds, pears,
plums and cherry, the availability in terms of quantity and quality of a wide
range of agricultural and horticultural products signifies good potential for
value addition through food processing.
Besides, the state is ideally suited for growing aromatic and medicinal plants
that can be the raw material for a wide range of essential oils and herbal
medicines. A special package of incentives has been offered for this sector by
the Ministry of Food Processing, Government of India. The State Government
has also kept this sector in its thrust area.
2.6 The State is endowed with rich mineral wealth of excellent quality, Limestone,
gypsum, quartzite, dolomite, magnesite and bauxite, besides sapphire are
available in the State.
2.7 Technical, managerial and other knowledge based resources available in
government departments,universities and professional colleges, R&D
institutions like the Regional Research Laboratory of CSIR can be networked
and utilized for the growth of the Industry.
2.8 There is a large scope for the commercial banks to push up investment within
the state. The current credit deposit ratio is much lower compared to the
national average.
2.9 There is a clear recognition by the state government of the fact that the
industrial sector has a prominent role to play in its economic development and
is an effective vehicle to reduce pressure on the strained employment
opportunities in the government and public sectors.
2.10 A perceptible improvement in the law and order situation, generated by the
sincere desire of the people of the State for peace, has created a favourable
atmosphere for investors. This has also created a new hope in the local
educated youth.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 40
2.11 The state has a long history of excellent labour-management relations;
mandays lost due to labour problems are minimum.
2.12 A wide network of roads, telecommunication and other infrastructure existing
in the State is constantly improved. Railhead at Jammu will be extended to
the valley of Kashmir by 2007.
3.0 Objectives The primary objectives of the Industrial Policy 2004 are : i) To achieve sustainable industrial development in all regions for increasing the
rate of growth, value of output, employment, income and overall economic
development of the State.
ii) To strive towards balanced economic and social development in all regions of
the State by promoting industrialization particularly of the industrially
backwards areas;
iii) To encourage and sustain the cottage and tiny industrial sector which, with
law investment, is able to provide employment to a large number of people in the
state.
iv) To create a supportive environment with transparency and easy access in
information, technology and financial resources.
v) To revive potentially viable sick industrial units so as to put to optimum use
the capital and other resources already employed in such enterprises.
vi) To promote the growth of thrust and export-oriented industries and encourage
high-tech and knowledgeable based industries including information
technology.
vii) To take necessary steps in the field of Human Resources Development to
make available skilled / technical manpower as per the needs of industry.
4.0 Approach and Strategy 4.1 The strategy for achieving the objectives, and the main elements, of the
Industrial Policy 2004 are:
i) Providing improved infrastructure and support services, with emphasis on
regular and Uninterrupted power supply.
ii) Attractive incentives of the Government of India and of the state government.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 41
iii) Single window clearance system for power, pollution control, land allotment
and registration of industrial unit.
iv) Closer interaction with financial Institution and commercial banks, to ensure
regular and adequate flow of finances to the industrial sector.
v) Rehabilitation of potentially viable sick industrial units.
vi) Improving competitiveness of existing industrial units by facilitating
modernisation aimed at enhancing productivity, energy efficiency and better
environment management.
vii) Enabling manufacturers of quality consistent products to augment their sales
within and outside the state by brand promotion.
viii) Reorienting Industries and Commerce Department.
ix) Export promotional measures to augment export of products of the state
outside the country.
x) Permanent Grievance Redressal System to remove bottlenecks in import and
export of products to and fro the state.
xi) Environment protection, to conform to state, national and global regulations.
xii) Entrepreneurship development in the state, to provide opportunities to
educated unemployed.
xiii) Encouraging Research & Development.
xiv) Focussing on thrust areas with natural advantages in the state and facilitating
large investments in prestigious projects.
4.2 Improved infrastructure and support services : The government will strive to improve general infrastructure of the state. In respect of
infrastructure for industries, the policy emphasizes the following :
i) Development of modern industrial areas and estates, growth centers,
Integrated Infrastructure Development Centers (IID) etc. will be done in a time
bound manner. These focal points of Industry will meet all the basic
requirements of a competitive industrial environment. An action Plan with
specific implementation model and time frame will be adopted.
ii) Operational management of the major industrial estates will be rationalized,
involving local Industrialists through a suitable local self managed model both
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 42
for development works and Management of the estates including regulation of
power and water supply.
iii) The State Government will encourage private sector participation in
infrastructure development and such private sector participation will be treated
as an industry for the purpose of availing incentives. The Government will also
facilitate acquisition of land for such private sector initiatives.
iv) Efforts will be made to ensure that the power supply within industrial areas,
estates, IIDCs, etc. is regular, reliable and of good quality.
v) Private sector investment in generation and distribution of regular power
supply in industrial areas, estates, IIDCs etc. will be actively encouraged. The
government will provide necessary support for such ventures on a case to
case basis to assure their sustainability.
vi) Micro-hydel projects are already open for private sector investment. A
separate policy on the subject has been announced and implemented by the
Power Development Department.
4.3 Incentives for Industries
Incentives for industries provided by the Government of India are presented at
Annexure I. A revised package of incentives, offered by the state government, is at
Annexure-II. Industries availing the incentives must always strive to plough back
resources to constantly upgrade products and productivity, design and quality, so
that after the incentives cease, they are able to survive on their own
competitiveness.
4.4 Single Window Clearance System
With the objective of facilitating a new entrepreneur in getting necessary
clearances within a short time, a Single Window Clearance System, for registration
of the Industrial Unit, allotment of land, clearance of pollution control Board for
commencing construction and certificate of power availability, at the State and
District levels, has been set up. A separate notification in this regard will be issued.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 43
4.5 Institutional/Commercial Bank funding
Industrial Policy 2004 recognizes that Financial Institutions/Commercial Banks
have to play an important role in the industrial development of the State. An
environment has to be created to arrest the present trend of flight of capital from the
State. The procedures presently followed have not withstood the test of time. There
have been glaring instance of delay and under-financing of projects resulting in cost
and time over run. It will also be necessary to strengthen the state owned Financial
Institutions. Moving in this direction, the government will adopt the following course
of action :
i) The present arrangement of credit flow monitoring through State Level
Banker’s Committee (SLBC) and State Level Inter Institutional Committee (SLIIC)
forums will be actively utilized.
ii) State owned development financial institutions shall be reoriented to facilitate
availing of refinance facilities from national level institutions optimally; and,
encouraged to raise finance from the market.
iii) Divisional and district level co-ordination committees will be constituted to
monitor expeditious settlement of the loan cases within prescribed time limit.
4.6 Rehabilitation of Sick Units
An enormous amount of capital is locked in sick/closed industrial units in the
form of infrastructure and investment. Though industrial sickness is a wide spread
phenomenon, its impact is comparatively high in J&K. The initiative for rehabilitation
of sick units should primarily come from the concerned industrial unit, financial
institutions and the commercial banks, the government playing a catalytic and
supportive role. Government Order No. 47-Ind of 1999 dated 10-02-1999, currently
in vogue, will continue. Besides, the Government will separately announce an debt
relief package too. This sick industrial units shall have the option of taking advantage
of either of the two packages.
4.7 Improving Competitiveness - Modernization
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 44
Industrial units operating in the State must realize that with globalization and
economic liberalization, the inflow of cheaper and better quality products into the
country and eventually into the state cannot be halted. In order, therefore, to
encourage such industrial units as are desirous of modernizing themselves with a
view to increase productivity, energy efficiency and environment protection, the
capital investment subsidy of the state will be extended to them all over the state.
The procedure for availing this incentive has been separately prescribed.
4.8 Brand Promotion
With increasing competition in the market, manufacturers of quality consistent
consumer products can sustain themselves only if they adopt an intelligent marketing
strategy and build a brand of their own. In order to encourage efforts of such
manufacturers who are desirous of developing and propagating their own brands
within and outside the state, the government will extend assistance to them. Details
are provided in the package of incentives of the state government.
4.9 Re-Orientation of Industries & Commerce Department
In the liberalized economy, it is imperative that the capacity of Industries &
Commerce Department and related PSUs is strengthened to meet the challenges of
the new era. In the area of information technology, the process of computerization
will be accelerated at the cutting edge level. Accordingly, the computerizations of
Directorate of I&C will be further expedited with a view to not only provide all relevant
policy and information on the web site but also data relating to status of applications
for registration, incentives etc. An investor and industry friendly atmosphere will be
created.
4.10 Export Promotion
Exports have come to be regarded as an engine of economic growth.
However, the share of J&K in the overall exports of the country is very low, limited
mostly to handicrafts and dry fruits processed by the SSI sector. The State has a
vast potential for exports, both in traditional and nontraditional items.
4.11 Permanent Grievance Redressal System
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 45
In the past, despite provisions in the Industrial policy, there have been many
instances of consignments of raw materials, capital goods, fuels, etc. being detained
in the entry point of the state, often resulting in delays and payment of fines and
penalties. With a view to ensure that the industrial policy is honoured in letter and
spirit, an order will be issued by the Finance
Department that no consignment for industries, covered by the industrial
policy, will be detained at the entry point for more than 24 hours. In the event of any
doubt, a notice will be issued by the concerned authority to the firm outlining the
objections but he consignment will be instantly released. A Permanent Grievance
Redressal Committee, consisting of Director Industries and Commerce,
Commissioner Sales Tax and Commissioner Excise, to be set up by the Finance
Department, shall meet once every fortnight to consider all such notices and pass
orders which shall be final and binding on all concerned. In emergent situations,
such meetings could be called at shorter notice too. This procedure is expected to
check alleged arbitrary actions at the entry point of the State.
4.12 Environment Protection Pollution Control and environment protection will be accorded high priority. The
Pollution Control Board shall give necessary clearances to new units to start
construction only after satisfying itself that the required pollution control measures
have been included in the project by the promoter. The State Government will assist
setting up of Common Effluent Treatment Plants and providing sites of solid waste
disposal etc. availing of the existing schemes of the Government of India as well as
the States own resources. Procedures for environment clearances will be
streamlined to achieve speedy disposal. Environment friendly projects will be
accorded greater priority. Incentive for procurement of pollution control devices has
been provided in the state government’s package.
4.13 Entrepreneurship Development Lack of entrepreneurial skills of the local youth has been identified as an impediment
for sustained industrial growth, J&K Entrepreneurship Development Institute
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 46
(J&KEDI), a society registered under the J&K Societies Registration Act, has
recently been activated to provide entrepreneurship training to youth of the state.
Universities will be encouraged to include comprehensive entrepreneurial education
in the course curriculum both at the undergraduate and postgraduate levels in the
state. The state will encourage setting up of training institutions in the private sector,
in the areas of Information Technology, Biotechnology and Communication.
Educational and research institutions of international standards related to
business/industry shall be provided land in industrial parks/growth centres at a
concessional rate of 50%.
4.14 Thrust Areas and Prestigious Projects The following industries will be the Thrust Areas of the government:
1. Electronics (integrated circuits and micro assemblies)/computer hardware and
software.
2. Food processing including agro-based industries (excluding conventional
grinding/extraction units)
3. Floriculture
4. Handicrafts.
5. Leather processing and leather goods.
6. Sports goods, articles and equipments for general physical exercise.
7. Forest based industry.
8. Processing of aromatic and medicinal plants and herbs.
9. Pharmaceuticals including bulk drugs.
10. Silk reeling, weaving, processing printing and made-ups, Yarn and yarn spun
from silk waste.
11. Cutting and polishing of stones, gems and jewellery.
12. Precision engineering.
13. Wool processing, Spinning, weaving and finishing, woven fabrics of wool.
14. Woven fabrics of cotton.
15. Industries related to the promotion of tourism e.g., units manufacturing camp
equipments, fibre boats etc. souvenirs for tourists.
16. Knowledge industry, including information technology, bio-technology etc.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 47
17. Auto ancillaries.
18. Exploration of minerals.
19. Green houses (only Ladakh)
The government may add new industrial activities to the thrust areas from
time to time. The industrial projects in these areas will be accorded priority in the
matter of allotment of land, sanction of power and other clearances as also in the
matter of grant of incentives. With regard to Prestigious projects, with investment
above Rs.25 crores, the government may consider special package of incentives, to
be documented in the form of a MOU, on a case to case basis, on merits.
Notification of a prestigious project shall be made by State Level Committee – I for
granting Capital Investment Subsidy.
4.15 Research & Development
Encouraging Research & Development (R&D) in important economic sectors
and transferring the results of these to the industrial sector are the needs of the hour.
This is particularly necessary in agriculture, forest mining and mineral sectors,
medicinal and herbal plants which provide a substantial base for value addition.
Design cum Resource centres shall be set for supporting Handicrafts/Handloom
sector. Central government assistance for such purposes shall be fully availed.
National level organisations of excellence shall be pursued to provide support for
these programmes.
5.0 Implementation Effective and efficient implementation of the policy must be ensured. In order to
achieve this and also to provide for a regular interaction between the government at
the highest level and the industry at large, the government will set up an Advisory
Committee for Industries with the Hon’ble Chief Minister as the Chairman. Besides
the Hon’ble Deputy Chief Minister in charge of Industries and Commerce and
Hon’ble Minister of State for Industries and Commerce, this committee will consist of
all Principal Secretaries in charge of economic departments such as agriculture,
consumer affairs, environment, forests, finance, information technology, planning
and power development. Representatives of Chambers of Commerce of Industry
and Federations of Industries of Jammu and Kashmir Divisions and also senior
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 48
officials of the Ministry of Commerce and Industry, Government of India, will be
invited to join this committee. Principal Secretary I&C will act as the Member
Secretary of the Committee. This committee will meet at least once in three months
and provide a forum for timely discussion on major issues agitating the industry and
arriving at prompt decisions, a dire necessity in these days of high level of
competition among the states of promoting industrialization.
6. Conclusion
It is earnestly hoped that the Industrial Policy 2004 will receive the support of
the existing industry of the state as well as potential entrepreneurs. It is also
expected that this will be able to attract entrepreneurs from other parts of the country
and also from other countries. The government will endeavour to implement the
policy in right earnest and do all it can to make the atmosphere for investment in the
industrial sector of the state inviting and invigorating.
PACKAGE OF INCENTIVES*
1.0 Definitions.
Under this package unless the context otherwise requires : i) “Capital Investment” shall mean and include investment on land/premium on
leased land, cost of all civil engineering works including buildings and sheds, cost of
plant and machinery, cost of installation of plant and machinery, control panels,
quality control equipment, cost of consultancy during the execution of project and
cost of technical know-how.
ii) “Effective steps” means one or more of the following steps :- a) that 10% or more of the capital issued for the industrial unit has been paid up.
b) that any part of the factory building required for manufacturing activity has been
constructed.
c) that a firm order has been placed for any plant and machinery required for the
industrial unit.
iii) “Existing unit” means an industrial unit, which had gone into trial/commercial
production prior to 01-02-2004.
iv) “Fixed capital investment” means investment in land, building, plant and
machinery.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 49
v) “Government” means Government of Jammu & Kashmir.
vi) “Industrial Backward Blocks” means the blocks with boundaries to be notified
by the State
Government.
vii) “New industrial unit” means an industrial unit which has started/gone into
trial/commercial
production after 31-01-2004 and is formally registered.
viii) “Prestigious unit” means an unit having capital investment of Rs.25 Crores or
above and
declared as Prestigious unit by the State Level Committee - I constituted for
sanctioning Capital
Investment Subsidy.
ix) “Substantial Expansion” means an existing unit which increases its installed
capacity, with prior
approval of competent authority, in terms of the relevant Government of India
notification.
2.0 Eligibility
i) All existing and new industrial units unless otherwise explicitly provided in this
package and subject to fulfillment of such requirements as may be specified
by the Government from time to time shall be eligible for the incentives.
ii) Provided that wherever an identical scheme of Government of India exists,
the unit would draw the incentives from Government of India scheme first, if
eligible. The balance amount of the incentives, if any, under the State
Government scheme would be sanctioned if otherwise eligible under the state
scheme.
iii) The incentives under this policy are provided under the discretionary powers
of the State
Government. The State Government may decide to amend, alter, delete or
revise any or all of the incentives notified under this policy and no claim on
account of such a decision will be entertained.
iv) The Industrial Policy shall cover all the new industrial units that may be
established in
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 50
the State. In respect of units where the promoter may have taken effective
steps for implementation of the project as on 01-02-2004 and as such may
claim to avail incentives under the old package which was in force
immediately before announcement of this policy, he will be given option to do
so. However, such option shall have to be explicitly communicated to the
Director, I&C within 3months of announcement of this policy. This option shall,
however, be not applicable to tax related incentives, for which the new policy
will apply.
3.0 For achieving the objectives of the industrial policy, the State Government extends the following incentives:-
3.1 Land allotment The government shall allot land on long lease of 90 years in the industrial estates and developed areas on first come first serve basis. In case of large area requirements, land may be acquired in specific locations selected by the entrepreneur, and allotted on lease. a) The allotment of land/industrial plots/sheds and flats shall be on lease basis for a period of 90 years. b) The rent charged for the period of lease shall be invested in maintenance of facilities in the industrial estate. In case of lands outside the industrial estates, where no maintenance is required to be done by any Government Agency, only a nominal lease rent shall be chargeable if the entire expenditure on the cost of land and its development has been incurred by the promoter.
3.2 Capital Investment Subsidy (CIS) and Financial Support on Investment : 1. Government of India has announced a new scheme of capital investment
subsidy for the State of Jammu & Kashmir. The existing Capital Investment
Subsidy (CIS) of the State government shall stand replaced by the
Government of India scheme for CIS.
2. In the Industrially Backward Blocks, which will be notified separately, the
existing state government scheme would continue. However, in such Blocks
the industrial units will first draw CIS of the Government of India scheme, if
applicable. Balance amount, if any, as per State Government scheme would
be sanctioned by the competent authority, if other-wise eligible under the state
scheme.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 51
3. In such locations (which do not fall within backward blocks) where the CIS
scheme of GOI does not apply, the State Government will extend the benefits
as per the norms of Central Scheme.
4. The CIS applicable to the notified backward blocks of the State is as
follows :
a) CIS shall be available if the item of manufacture does not figure on the negative
list.
b) CIS shall be available to the new SSI, Medium and Large units, @ 30% of the
capital investment subject to upper limit of Rs.30 lakhs.
c) In case of prestigious unit, the upper limit of CIS shall be Rs. 60 lakhs.
d) In case of the thrust areas, the upper limit of the CIS shall be Rs.45 lakhs and Rs.
75 lakhs in case the unit also falls in the prestigious category.
5. In areas where CIS under the central scheme is available the Government
does not want to place the thrust area units, prestigious units and prestigious
units in thrust areas in a disadvantageous position. In such areas if the eligible
amount of CIS under the central scheme exceeds Rs.30 lakhsfor an industrial
unit, which is maximum limit under that scheme, the State Government
shallprovide the amount exceeding Rs.30 lakhs subject to a ceiling of Rs.15
lakhs, Rs.30 lakhs and Rs.45 lakhs, in case of thrust area units, prestigious
units and prestigious units in thrust areas,respectively.
6. In the entire state, 75% subsidy shall be allowed on cost of construction of a
captive tube-well or building a captive water lifting plant incurred by a
prestigious unit in any of the thrust areas. The maximum amount of subsidy
shall be Rs.22.50 lakhs. This shall be in addition to the financiallimits for CIS
prescribed above.
3.3 Modernisation of existing units
With a view to encourage modernisation of existing small scale industrial
units, to enable it to achieve higher productivity, energy efficiency and better
environment protection, and thus improve its sustainability in the competitive
environment, capital investment subsidy of the state government will be applicable to
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 52
such units all over the state subject to a limit of Rs.30 lakhs. Units availing incentives
under the definition of ‘substantial expansion’ shall not be entitled to this. Application
for modernisation must be submitted to the Director, Industries and Commerce, in
the prescribed form, obtainable from his office and only after the scheme is approved
by a committee consisting of Principal Secretary (Finance), Principal Secretary
(Planning) and Principal Secretary (Industries and Commerce), the applicant shall
commence work thereon. Approval and disbursement of the incentives will be done
on the same pattern as the CIS of the state government.
3.4 Brand Promotion
In order to help such manufacturers of consumer products who are in a highly
competitive market, the government will provide assistance to them in promoting
brands within and outside the state. The assistance will be in the shape of subsidy at
the rate of 50% of expenses incurred in the first year subject to a limit of Rs.20
Lakhs, 30% of expenses incurred in the second year, subject to a limit of Rs.
15lakhs and 10% of expenses incurred in the third year subject to a limit of Rs.10
lakhs. Application is prescribed form obtainable from the office of the Director
Industries and Commerce must be submitted prior to undertaking the activity. Such
applications shall be scrutinised by a committee consisting of the Principal Secretary
(Finance), Principal Secretary (Planning) and Principal Secretary (Industries and
Commerce), and only after the scheme is approved, the applicant may begin its
implementation, if the incentive is to be availed. A system of monitoring shall be
instituted and if the applicant deviates from the approved scheme, without prior
approval, the incentive will be denied to him and the moneys already paid to him
may be recalled at the discretion of the approving authority.
3.5 Pre-Investment Studies/Feasibility reports a) Project profiles shall be prepared by the Directorate of I&C, SIDCO and
SICOP and made available off the shelf to the promoters at a nominal price.
b) The promoters may get a project feasibility report prepared from J&K, ITCO,
SIDCO, SISI or any other agency as may be approved by the Director, I&C
from time to time. The expenditure incurred on such feasibility reports shall
qualify for 100% subsidy at the time of execution of the project subject to a
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 53
limit of Rs.2.00 lakhs. The promoter may get a report prepared also from any
other specialist agency/reputed consultants with prior approval of Director,
I&C.
3.6 Power tariff/DG sets
Power tariff for the industrial sector is subsidised. The Power Development
Department shall revise and announce the tariff from time to time. Keeping in view
the policy of he government to encourage the development of industry in the State
and till such time as assured power supply is made available to industrial units 100%
subsidy shall be allowed on new DG sets form 10KW to 1000 KW capacity
purchased from reputed/standard companies subject to the maximum limit of Rs. 25
Lakhs. The subsidy shall be available to he unit after it has been verified that the DG
set has been actually installed.
a) The amount of subsidy on purchase of DG set shall be paid only through a
bank (or the concerned financing agency, if any) even if the promoter may not have
taken any loan for purchase of theDG set.
b) 50% of the amount of subsidy on DG set shall be paid on verification of
installation and the remaining 50% shall be paid after expiry of one year of
installation.
c) The DG set shall not be shifted from the State for a period of ten years
counted from the date of installation or to any other unit except with the approval of
the Director I&C. If the unit makes any such request to shift the DG set to outside the
State, the same shall be considered only in case the unit deposits the entire amount
of the subsidy availed of together with interest thereon at the prevailing rate of
interest on term loans.
d) The amount of subsidy claimed as part of Government of India’s CIS scheme
for this item shall be deducted from the amount to be calculated under the state
government scheme.
e) Government shall allow setting up of Captive Power Generating units and
also mini/micro power generating unit anywhere in the state, subject to obtaining
usual clearances required including from the State Pollution Control Board. There
shall be no electricity duty/state excise on generation of electrical energy through
such Power Generating Stations for a period of 25 years.The station may be set up
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 54
by an individual promoter or a group of promoters and the energy thus generated
may be shared by them or sold to other consumer(s). In case the energy thus
generated is given to the State Government at the point of production, the promoter
shall be eligible to draw an equivalent amount of energy for his own bona fide
industrial purpose, from the PDD anywhere else in the State. If his requirement is
less than what is generated by him, the excess power can be sold to the state as
per the policy of Power Development Department.
3.7 Price /Purchase Preference i) Upto 15% Price Preference shall be available on the landed cost of the
product to the local SSI units, in all government purchases. The price preference
shall also apply in case of any goods purchased by the public sector
undertakings/boards purchased for their own non-commercial use.
3.8 Toll Taxes i) There will be no additional toll tax on the raw materials, fuel and
consumables, procured from outside the state by the existing or new SSI units fill 31-
01-2015 except for items brought on the negative list from time to time.
ii) There will be no additional toll tax on finished goods manufactured by the existing
or new SSI,Medium and Large units and sent outside the state upto 31-03-2015
except for items brought on the negative list from time to time.
iii) There will be no additional toll tax on the Raw materials, fuels, consumables
brought from theexisting new medium and large units upto 31-03-2015 except in
case of items brought on the
Negative list from time to time.
iv) There will be no additional toll tax on components, machinery, plant and other
equipments
procured from outside the state for building the factory, for a period of five years from
the date of registration of the unit in SSI, Medium or large sector.
v) There will be no additional toll tax on 100% export oriented units on the goods
exported under proper export documents from the state to any foreign country.
vi) There will be no additional toll tax on empty containers brought into the state
which are used for stuffing products of industry for export out of the state.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 55
3.9 Special Provision for Prestigious Units Prestigious units shall avail of full exemption from payment of GST (Till VAT is
implemented)/CST and additional toll tax untill 31-3-2015 or until such amount of
exemption reaches the levels of 150% of capital investment in the project whichever
occurs earlier. It may be clarified that negative lists issued for various tax related
incentives for medium and large industries shall also be applicable mutatis mutandis
to prestigious units.
3.10 Interest Subsidy i) The Government of India has announced a new scheme for Interest subsidy in the
state of Jammu & Kashmir. The existing incentive of Interest subsidy of the State
Government will be replaced by the Government of India scheme, except for existing
and any other new units which are not otherwise eligible for claim or interest subsidy
under the Government of India scheme.
ii) 3% subsidy shall be payable on the working capital facilities available from the
commercial banks to all existing units for the remaining period of their eligibility,
subject to the conditions prescribed, under the Government Order No. 202-Ind of
1998 dated 27-5-1998.
iii) This incentive will be extended to any new unit not covered by the Central
Government Package by the state Government, on the same terms as contained in
the Central Package.
iv) No interest subsidy shall be available on penal interest or on default payments.
3.11 Testing Equipment 100% Capital subsidy shall be provided by the Government on installation of Testing
Equipment, subject to a maximum amount of Rs.25 Lakhs and also restricted to
25% of the total capital investment if the cost of testing equipment exceed 25% of
the total investment provided that the same is installed within 31-3-2015.
ii) The incentive shall be disbursed only after the unit availing this incentive obtains a
national/ international quality mark.
Prefeasibility Report of Proposed cement Plant(3500TPD) at village:Kheru,Distt. Pulwama Srinagar, J&K
Page 56
iii) To the extent incentive for such equipment is availed under the CIS scheme of
Government of India, deductions will be made from the amount due under the state
scheme.
3.12 30% Subsidy on Pollution Control Equipment 30% subsidy shall be extended for purchase of pollution control equipment subject to
ceiling of Rs.20.00 lac per unit and this will be in addition to the entitlement of CIS
unde G.O.I scheme if it exceeds Rs.30.00 lacs limit of CIS notified by G.O.I. If
subsidy on such equipment is availed under CIS notification of GOI, to that extent,
the amount shall be reduced out of the entitlement under the state scheme.
3.13 Interest Subsidy for Technocrats 5% interest subsidy on term loan shall be available for Engineering Graduate/MBA’s/postgraduates on term loan availed from financing institutions.