Upload
dinhminh
View
221
Download
4
Embed Size (px)
Citation preview
Page 0 of 30
PRE FEASIBILITY REPORT
of
KANAKADRIPALLI LIMESTONE MINE Mining lease area: 435.24 Ha
(Non-forest land)
Petnikota & Itikyala Villages Kolimigundla Mandal, Kurnool District, Andhra Pradesh.
for
PRODUCTION OF 1.0 MTPA OF LIMESTONE
Captive Limestone Mine
of
The Ramco Cements Limited (Formerly Madras Cements Ltd) K S R Nagar, Krishna District
Andhra Pradesh - 521457
Page 1 of 30
Table of Contents
1. Executive summary
2. Introduction of the project/ Background information
3 Project Description
4 Site Analysis
5. Planning Brief
6 Proposed Infrastructure
7. Rehabilitation and Resettlement (R & R) Plan
8. Project Schedule & Cost Estimates
9. Analysis of Proposal (Final Recommendations)
Page 2 of 30
CHAPTER – 1
EXECUTIVE SUMMARY
1. Executive Summary
The Ramco Cements Limited (formerly Madras Cements Ltd) is
proposing to install a Cement plant of capacity 3.15 Million Tonnes Per
Annum (MTPA) of cement at Kolimigundla Mandal of Kurnool Dist
Andhra Pradesh.
The cement plant will be supported by the following Captive limestone
mines to meet the requirement of limestone.
1. Chintalayapalle Limestone Mine
2. Kanakadripalle Limestone Mine
3. Kolimigundla Limestone Mine
4. Nayanapalle Limestone Mine
The subject mine spreading over an area of 435.24 Ha ( 1075.48 Ac.) out
of which 419.08 Ha. (1035.54 Ac.) own patta lands and 16.16 ha. (39.94
Ac.) of Govt. land under the jurisdiction of Petnikota & Itikyala Villages,
Kolimigundla Mandal, Kurnool District, Andhra Pradesh. Government of
Andhra Pradesh. Industries & Commerce (M-III) Department, issued
Order vide Memo No. 576/M.III(1)/2015, dated: 16.10.2015. The copy of
the same is enclosed as Annexure - I. Mining Lease were granted by
Govt of A.P vide GOMs No.136 dated 15.02.2000 is enclosed as
Annexure – II. The subject area will be a captive Limestone mine of
Ramco Cement plant which will be located at 3.5 km.
The mine has about 45.253 Million Tonnes of mineable reserves
(approx.) which will last for about 47 years with proposed production
capacity of 1.0 Million Tonnes Per Annum (MTPA) as the proposed total
production in first five years is 3.00 Million Tonnes only.
The mine operation will be by Opencast Mechanized method of mining.
Limestone produced from this mine will be transported to crusher
located at cement plant through haul roads.
The interstitial clay and waste rock that will be generated during the
course of mining will be transported to the dump yard. This material
will ultimately be utilized for backfilling once the entire mineral is
Page 3 of 30
mined out. It is not possible to refill the entire mined out area, hence a
part of the area will be retained as water reservoir for future use.
Water requirement for the proposed mine is about 100 m3/day for dust
suppression, plantation and domestic purposes. This requirement will
be initially met from Ground water and will be used for the purpose of
domestic, dust suppression and afforestation in mines. Later the rain
water collected in the mine pit will be used.
There is no wildlife sanctuary, national park, Tiger Reserve, Elephant
Corridor, eco-sensitive area within the 10 km radius of the project site.
All infrastructure facilities such as education, health facilities and other
social facilities are adequate at nearest populated area.
The capital Investment Cost for environment management is estimated
as Rs. 39 Lakhs. All the infrastructural facilities will be provided.
The capital Investment Cost is estimated as Rs.3.76 Crores.
Page 4 of 30
CHAPTER – 2
INTRODUCTION OF THE PROJECT /
BACKGROUND INFORMATION
2.0 Introduction of the Project / Background information
i. Identification of project and project proponent. In case of mining
project, a copy of mining lease / letter of intent should be given.
The Ramco Cements Limited (TRCL) proposes to produce 1.0 million
tonnes per annum of limestone from the subject mine i.e
KANAKADRIPALLI LIMESTONE MINE (435.24 Ha) located at Petnikota
& Itikyala Villages, Kolimigundla Mandal, Kurnool District, Andhra
Pradesh.
The cement plant at Kolimigundla will be supported by four Captive
limestone mines to meet the limestone requirement. To conserve the
mineral by blending the limestone obtained from various mines, the
subject mine i.e Kanakadripalli Limestone Mine located at Petnikota &
Itikyala Villages, Kolimigundla Mandal, Kurnool District, Andhra
Pradesh is identified which is having good quality of limestone.
The mine has about 45.25 Million Tonnes of mineable reserves
(approx.) which will last for about 47 years with proposed production
capacity of 1.0 Million Tonnes Per Annum (MTPA) as the proposed total
production in first five years is 3.00 Million Tonnes only.
The present proposal is for obtaining Environmental Clearance for
KANAKADRIPALLI LIMESTONE MINE (435.24 Ha) from Ministry of
Environment, Forests & Climate Change (MoEF&CC) as per EIA
notification SO1533 dated 14th Sep. 2006 and subsequent
amendments.
Project proponent
RAMCO group of companies have diversified industrial ventures, which
include manufacture of cement, asbestos sheets, surgical dressing,
textiles, windmill farms, ready mix concrete, as well as information
technology. This 6200 Crore group has achieved international
recognition for its quality products and services.
Page 5 of 30
The Ramco Cements Limited having its corporate office in Chennai,
Tamilnadu, operates the following cement plants in the country.
S.No. LOCATION CEMENT
CAPACITY
1 Ramaswamy Rajanagar, Virudhunagar Dist,
Tamilnadu
1.5 MTPA
2 KSR Nagar, Krishna Dist, Andhra Pradesh 3.65 MTPA
3 Alathiyur Village, Ariyalur Dist, Tamilnadu 3.05 MTPA
4 Ariyalur, Ariyalur Dist, Tamilnadu 3.50 MTPA
5 Mathodu Village, Chitradurga Dist, Karnataka 0.3 MTPA
The Ramco Cements Limited have been in cement manufacture and
allied fields for more than 5 decades and its products command a
valuable brand image in cement market in South India as well as other
parts of India.
ii. Brief description of nature of the project
The limestone mine is spread over 435.24 Ha with 48.32 Million Tonne
of limestone. It is proposed to produce 1.0 MTPA of Limestone from
subject mine i.e., KANAKADRIPALLI LIMESTONE MINE located at
Petnikota & Itikyala Villages, Kolimigundla Mandal, Kurnool District,
Andhra Pradesh.
The method of working is opencast mechanized mining with deep hole
drilling & blasting. It is proposed to work this deposit by maintaining 8
m bench height and with an ultimate pit slope of 450. The width of
working bench will be not less than the height of the bench. The mine
approach ramp gradient will be kept at a minimum of 1 in 16.
It is proposed to stack the generated waste soil in temporary dump yard
within the mining lease area. This stacked waste soil will be utilized for
afforestation and reclamation for part of the mined out areas (i.e., at
the conceptual stage of 47 years). No overburden is anticipated during
life of the mine. The afforestation will be taken up all along the ML
boundary with 7.5 mts width.
Page 6 of 30
iii. Need for the project and its importance to the country and or
region.
Cement industry is one of the main beneficiaries of the infrastructure
boom. While on the one hand several big and small cement companies
are actively considering expansion plans in anticipation of further
growth in demand for cement, on the other, a phase of acquisitions and
mergers among the existing players is also going on.
In India, the South consumes maximum of 30% followed by East at
17%, North at 19%, central at 16%, and West 18%. Also, there is an
increase in the consumption of PPC cement from 48% to 50%.
Weaker section’s housing, construction of public toilets, schools in
rural area apart from several private and public infrastructure projects
will also give tremendous boost to the cement consumption in the state.
Most importantly, irrigation projects, worth nearly Rs 1 lakh crore, will
trigger unprecedented demand for the next 5-7 years.
As per the industry sources, demand has mainly come from the
construction sector with the three main cities in the South - Bangalore,
Chennai and Hyderabad - witnessing hectic construction activity, be it
for the information technology sector, shopping malls or integrated
townships. The growth in demand has prompted many cement
industries to consider for proposal of present Limestone mines in
present locations and in Greenfield locations.
The chemical characteristics of limestone extracted from this mine do
not warrant any mineral beneficiation, since the quality of limestone
produced from this mine is suitable for cement.
To meet the limestone requirement of the proposed plant, RAMCO has
applied the lease for the subject mine, and it is proposed to produce 1.0
MTPA of limestone from this mine.
iv. Demand– supply Gap
Since Limestone is the main raw material for cement production, the
demand is always there with that of cement. Moreover, the subject
mine produces good grade limestone leading to conservation of mineral
resources.
Page 7 of 30
The cement market has growth due to the central government
liberalization policies and new schemes for housing, road projects.
Cement demand growth is anticipated to be about 11% increase mainly
through road projects & Housing Projects.
Continuous demand for exports to China and other South-East Asian
countries along with the increased requirement of the domestic sector
has been lead all the cement manufacturers in the country to plan for
increased capacities.
v. Imports Vs Indigenous production.
The limestone produced from the subject mine will be used for the
captive consumption in the cement plant.
vi. Export possibility
No exports of limestone are proposed.
vii. Domestic / export markets
The limestone produced from the subject mine will be used for the
captive consumption in the cement plant.
viii. Employment generation (direct and indirect) due to the project.
Since the Mechanized method of mining will be adopted, the transport
of limestone from the mines to Cement plant will be done by
trucks/tippers/dumper.
Most of the workmen will be employed from local villages at different
levels. The Managerial, supervisory, skilled, semi-skilled and unskilled
labor totaling to 40 will be engaged as per requirement.
Page 8 of 30
CHAPTER – 3
PROJECT DESCRIPTION
3.0 Project Description
i. Type of project including interlinked and interdependent projects,
if any.
The proposed project (Kanakadripalli Limestone Mine) is a limestone
mine of 435.24 Ha with production capacity of 1.0 MTPA and spread at
Petnikota & Itikyala Villages, Kolimigundla Mandal, Kurnool District of
Andhra Pradesh.
With about proved mineral reserve of 45.25 Million Tonne will last for
47 years. The limestone produced from the mine is of good grade
limestone and can be utilized for blending with other limestone mines.
Status of the interlinked/interdependent projects:-
Project Location Capacity Approvals
Proposed Cement
Plant
Itikyala, Kalavatala & Nandipadu Villages,
Kolimigundla Mandal, Kurnool District, Andhra
Pradesh
3.15 MTPA Cement
EC Under process
Mineral produced will be utilized in Proposed Cement plant at Itikyala,
Kalavatala & Nandipadu Villages, Kolimigundla Mandal, Kurnool
District, Andhra Pradesh, which is at a distance of about 3.5 km from
the mine.
It is categorized as Category A Project under Schedule 1(a) as the
mining lease area is more than 50.00 Ha hence it necessitates
obtaining Environment Clearance from Ministry of Environment, Forest
& Climate Change (MoEF&CC).
ii. Location (map showing general location, specific location, and
project boundary & project site layout) with coordinates.
The Mine is located at Petnikota & Itikyala Villages, Kolimigundla
Mandal, Kurnool District of Andhra Pradesh.
Page 9 of 30
The Mining Lease area is a part of the Survey of India Topo sheet No.
57/I/4. The site falls between Latitude 15°02'23.9"N - 15°04'13.1"N
and Longitude 78°03'31.3"E - 78°04'54.5"E with an altitude varying
from 302 to 334 m above MSL.
The location map of the mine site is shown in Fig – 1.
Nearest railway line connecting Gooty Junction– Kadapa of South
Central Railway line is located at a distance of 19.0 km to SW direction
from the Mining Lease Area. Key map showing the location of various
features around the Mining Lease Area is shown in Fig – 2. Kadapa is
major town is located at a distance of 105.0 km in SE direction.
The National Highway (NH-18) connecting Kurnool – Kadapa is located
at a distance of about 47.0 km in ENE direction. The National Highway
(NH-7) connecting Kurnool – Anantapur is located at a distance of
about 41.0 km in WNW direction. The State Highway (SH-57)
connecting Kolimigundla – Gooty is located at a distance of about 0.7
km in SE direction. The nearest railway station is Tadiptri RS at a
distance of 19.0 km in SW direction.
There are no wild life sanctuaries, national parks, elephant/tiger
reserves within 10km radius of the study area.
Nearby Settlements from the Mine site
Kanakadripalle village adjacent to the Mine at SE
Raghavarajupalle village adjacent to the Mine at SE
Petnikota – 1.5 km – N
Nayanipalle – 1.8 km – NNE
Itikyala – 1.4 km - E
Salient features of Mine site are given in Table – 1 and Fig - 3 shows
the study area of 10 km radius around the Mine site.
iii. Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental considerations gone
into should be highlighted.
No alternate sites were considered as the project is mineral specific.
Page 12 of 30
TABLE – 1.1
SALIENT FEATURES OF THE MINING LEASE AREA
Feature Details
Altitude 302 to 334 m above MSL
Latitude and Longitude Latitude 15°02'23.9"N - 15°04'13.1"N and Longitude 78°03'31.3"E - 78°04'54.5"E.
Village, Tehsil, District, State
Petnikota & Itikyala Villages of Kolimigundla Mandal,
Kurnool District, Andhra Pradesh.
District Headquarters Kurnool - 87.0 km - N
Max. Temp., oC 45.6
Min. Temp., oC 6.7
Relative Humidity,% 25-77
Annual rainfall, 726 mm
Nearest Water Bodies
Pedda Vanka – 1.8 km – N
Mada Vagu – 6.0 km – E Owk Reservoir – 11.0 km - NNE
Nearest Highway National Highway (NH-7) connecting-Kurnool – Anantapur – 41.0 km – WNW
State Highway (SH-57) connecting Kolimigundla –Gooty - 0.7 km - SE
Nearest Railway station Tadiptri RS – 19.0 km - SW
National Parks/Bird Sanctuaries
None within 10 km
Nearest Industries Ultratech cements - 5.3 km –WSW Ultratech mine - 2.7 km – W Penna cement – 9.9 km - S
Penna talaricheruvu mine – 8.7 km – S Penna Korumanipalli mine – 7.8km - SSE
Nearest Villages Kanakadripalle village adjacent to the Mine at
SE
Raghavarajupalle village adjacent to the Mine
at SE
Petnikota – 1.5 km – N
Nayanipalle – 1.8 km – NNE
Itikyala – 1.4 km - E
Nearest Town Kurnool - 87.0 km - N
Inter State Boundary None within 10 km
Nearest Air port YSR Kadapa – 96.0 km – SE
Nearest Forest None within 10 km radius
Historical places None within 10 km radius *all distances mentioned in the above table are aerial distances
Page 14 of 30
iv. Size or magnitude of operation.
Mine area is 435.24 ha. The proposed rate of production of limestone is
1.0 MTPA.
v. Project description with process details (a schematic diagram/ flow
chart showing the project layout, components of the project etc.
should be given)
The mining will be opencast mechanized mining, employing DTH
drilling for blast holes, after blasting the mineral will be loaded into the
tippers using hydraulic excavator. The limestone will be transported to
the plant by tippers.
The bench height proposed is 8 m and mining will be carried up to a
depth of 283m RL (as per the present proved mineral reserves).
a) Drilling
Primary Drilling
Down The Hole Drilling with 115/ 150mm dia drilling machine will be
deployed for drilling of Blast holes.
Bench Height
It is proposed to work with 8 m benches and width of working bench
will be not less than the height of the bench. The mine approach ramp
gradient will be kept at a minimum of 1 in 16.
Burden
30% to 40% of the bench height i.e. 3.0 to 3.5m depending on the
height of the bench and also depends upon the thickness of individual
litho unit.
Spacing
Based on geological condition of this area, we use grid pattern with 3.0
to 3.5 m Burden and 4.0 to 5.0m spacing for blast hole drilling
Angular Holes
The blast hole shall be sloped at angle of 100 to 150 from vertical.
Page 15 of 30
Depth of Holes
The depth of the hole shall be kept at 8.5 m with sub grade drilling.
Secondary drilling
No secondary drilling will be carried out. The boulders will be broken by
deploying rock breaker or by using secondary blasting of plaster
shooting if required. However with the precise method of blasting and
adopting the method of decking in between the fractured zone, shall try
to avoid the boulder formation.
b) Blasting
The blasting operation will be carried out by using milli second delay
detonators with sequential blasting using slurry explosives along with
ANFO to achieve better fragmentation, less fly rock and ground
vibrations.
c) Loading
Loading of limestone will be carried out with Hydraulic Excavator of 3.0
to 3.50 CUM bucket capacity.
d) Hauling
Tippers of 20 tonne capacity will be used for transport of limestone
from pit to crusher.
e) Raw material required along with estimated quantity, likely
source, marketing area of final product/s, mode of transport of raw
material and finished product.
No raw material is required.
f) Resource optimization / recycling and reuse envisaged in the
Project, if any, should be briefly outlined.
There is no specific spoil will be generated in the project area. The
waste soil generated will be stacked in respective temporary dump
yards and will be used for reclamation at conceptual stage. No
overburden is anticipated during life of the mine.
Page 16 of 30
g) Availability of water its source, energy /power requirement
Water requirement for the proposed mine is about 100 m3/day for dust
suppression, plantation and domestic purposes. Initially Ground water
will be used; later rain water collected in the mine pit will be used.
The power required for illumination will be supplied from grid initially
and later by Captive Power Plant of Cement Plant.
vi. Quantity of wastes to be generated (liquid and solid) and scheme
for their management / disposal.
There is no specific spoil will be generated in the project area. The
waste soil generated will be stacked in respective temporary dump
yards and will be used for reclamation at conceptual stage. No
overburden is anticipated during life of the mine.
Wastewater generated from domestic use will be treated in septic tank
followed by soak pit.
Page 17 of 30
vii. Schematic representations of the feasibility drawing which give information of EIA purpose.
Page 18 of 30
CHAPTER – 4
SITE ANALYSIS
4.0 Site Analysis
i. Connectivity.
The mine area under reference extends over an area of 435.24 ha
Petnikota & Itikyala Villages, Kolimigundla Mandal, Kurnool District of Andhra Pradesh.
Nearest railway line connecting Nandyal – Proddutur (Yerraguntla) of South Central Railway line is located at a distance of 28.5 km to ENE direction from the site.
Nearest railway line connecting Gooty Junction– Kadapa of South
Central Railway line is located at a distance of 19.0 km to SW direction from the site.
The National Highway (NH-18) connecting Kurnool – Kadapa is located at a distance of about 47.0 km in ENE direction,
The National Highway (NH-7) connecting Kurnool – Anantapur is located at a distance of about 41.0 km in WNW direction,
The State Highway (SH-57) connecting Kolimigundla – Gooty is located at a distance of about 0.7 km in SE direction, The nearest railway
station is located at Tadiptri RS which 19.0 km in SW direction.
Infrastructural facilities like Post Office, Telephone, Police Station and Primary Health Center etc., are available in the cement plant of RAMCO. The nearest airport YSR Kadapa – 96.0 km – SE
ii. Land form, land use and land ownership.
Land use:
The total Mining lease area is 435.24 Ha, consisting of waste land of 419.08 Ha. (1035.54 Ac.) own patta lands and 16.16 ha. (39.94 Ac.) of Govt. land. Present use is waste land and with outcrops of limestone at
some places.
Page 19 of 30
Topography (along with map)
The topography of the area is generally flat terrain with an average altitude of 330 m above MSL. Fig - 4 shows the surface plan of mining
lease area.
Page 20 of 30
iii. Existing land use pattern (agriculture, non-agriculture, forest,
water bodies (including area under CRZ), shortest distances from
the periphery of the project to periphery of the forests, national
park, wild life sanctuary, eco sensitive areas, water bodies
(distance from the HFL of the river), CRZ, in case of notified
industrial area, a copy of the Gazette notification should be given.
The total Mining lease area is 435.24 Ha, consisting of waste land of
419.08 Ha. (1035.54 Ac.) own patta lands and 16.16 ha. (39.94 Ac.) of Govt. land. Present use is waste land and with outcrops of limestone at
some places.
One No. of old pit and dump yard exist in the Mining Lease area at
West of South West, which were worked out by others over an areas of
4.98 and 3.34 Ha. respectively. The volume of exploited mineral in the
existing old pit is 298717 m3.
Pedda Vanka is at 1.8 km in N and Mada Vagu is at 6.0 km in E
direction to the Mine site.
There are no wild life sanctuaries, national parks, elephant/tiger
reserves within 10km radius of the study area.
Nearest Settlements from the Mine site
Kanakadripalle village adjacent to the Mine at SE
Raghavarajupalle village adjacent to the Mine at SE
Petnikota – 1.5 km – N
Nayanipalle – 1.8 km – NNE
Itikyala – 1.4 km - E
No forests are located within 10 km radius of the mine site.
The nearest industries to the mine site are
Ultratech cements - 5.3 km –WSW
Ultratech mine - 2.7 km – W Penna cement – 9.9 km - S Penna Talaricheruvu mine – 8.7 km – S
Penna Korumanipalli mine – 7.8km - SSE
Page 21 of 30
iv. Existing infrastructure
None within the mining lease.
v. Soil classification
The limestone formations are covered by waste soil all through the mine
area. The thickness of soil varies from 0.0 m to 1.0 m with an average
thickness of 0.5 m.
vi. Climatic data from secondary sources
The tropical climate of the region is manifested in hot and humid
summer, moderately monsoon and mild winter seasons. May is the
hottest month in the year. The maximum temperature during the day
time was recorded as 45.60C and December the coldest with the
temperature during the day time falling down to about 6.70C. The
months of December, January & February are considered to have
pleasant climate.
The rainy season is generally from June to September represented by
South West Monsoon. The rainfall during last year in the subject area
is around 726 mm.
vii. Social infrastructure available
Kanakadripalle is the nearest populated area situated adjacent on SE
side of Mine site. It is a major village with well connected to all major
cities by rail/road. All basic amenities such as school, hospital, market,
etc. are available here. Kurnool is major city and administrative
headquarters around 87 km from Mine site.
Page 22 of 30
CHAPTER – 5
PLANINIG BRIEF
5.0 Planning Brief
i. Planning concept (type of industries, facilities, transportation etc.)
Town and country planning / development authority classification
Not applicable.
The subject mine is located at Petnikota & Itikyala Villages,
Kolimigundla Mandal, Kurnool District of Andhra Pradesh. The subject
mine is captive limestone mine of Ramco Cement limited with mine
extent of 435.24 ha and the proposal is for limestone production of 1.0
MTPA.
ii. Population projection
Total employment potential in the mine is 40 covering the Mining
Engineer, Geologist, Skilled, semiskilled and unskilled etc.
iii. Land use planning (breakup along with greenbelt etc.,)
Post Mining Land use pattern:
The post mining land use pattern is furnished in the following table
based on the anticipated excavation of total mineable reserves.
Sl.
No
Nature of Activity Extent in Ha
1. Mining 416.94
2. Infrastructure 5.70
3. Green Belt 12.60
Total 435.24 Ha
The Greenbelt will be developed on the reclamation area to stabilize the
area at the end of the life of the mine and part of the mined out area
will be converted into water reservoir
Page 23 of 30
iv. Assessment of infrastructure demand (physical & social)
The mining operations would aid in the overall social and economic
development of the region. The mine will give employment to about 40
people in addition there will be indirect employment to many more
people, in the form of contractual jobs, business opportunities, service
facilities etc. This will enhance the economic status.
Apart from the jobs, the company will provide medical and educational
facilities to the employees which can also be availed by the people
around the plant. Adequate recreational facilities for the staff of the
company will be provided.
v. Amenities / Facilities.
Infrastructural facilities like Telephone and Occupational Health Centre
etc., will be provided at proposed cement plant colony. The nearest
Police Station is at Kolimigundla at distance of 4.00 kms. The mine
office with first aid room, rest shelters, toilets, tool/store room etc., will
be provided at site.
Page 24 of 30
CHAPTER – 6
PROPOSED INFRASTRUCTURE
6.0 Proposed infrastructure
i. Industrial area (processing area)
No processing is involved
The mine will be operated by means of opencast fully mechanised
method of mining which includes deep drilling and blasting, loading the
broken material by heavy machinery like hydraulic excavators and
tippers for transporting the limestone to crusher by road.
ii. Residential area (non-processing area)
No residential area is proposed at mine.
iii. Greenbelt.
7.5 m of mine periphery will be under plantation in an area of 5.70 ha.
Afforestation will be done every year covering an area of 0.50 ha with
500 saplings along haul roads.
The Greenbelt will be developed on the reclamation area to stabilize the
area at the end of the life of the mine.
Native species like Species like Sisoo, ganuga, Neredu, Neem, Mango,
chinta and Amala, etc., are proposed.
iv. Social infrastructure
The mining activity carried out in the area rather has a positive socio-
economic impact upon the nearby human settlement as indirect
employment potential is created due to mining and allied activities in
the area. Apart from these, the company promotes health and
education awareness in the area time to time by organizing health and
education camps.
Page 25 of 30
In addition Ramco shall take various social welfare programmes in the
surrounding villages. The focus areas include:
Economic development ( Training )
Drinking Water
Sanitation
Health & Hygiene
Relief & Rehabilitation
Temples & Religion Related Assistance
Education
v. Connectivity (traffic and transportation road/ rail/ metro/ water
ways etc.,)
The mine site is connected by State Highway (SH-57) connecting
Kolimigundla – Gooty, at a distance of about 0.7 km in SE Direction.
The nearest railway station is located at Tadiptri RS which 19.0 km in
SW direction.
The nearest airport is at YSR Kadapa – 96.0 km – SE from the
proposed mine site and is well connected by road for transport of
material.
vi. Drinking water management (source & supply of water)
Water requirement for the proposed mine is about 100 m3/day for dust
suppression, plantation and domestic purposes. This requirement will
be initially met from Ground water and will be used for the purpose of
domestic, dust suppression and afforestation in mines. Later the rain
water collected in the mine pit will be used.
vii. Sewerage system
Domestic waste water from mines office will be treated in septic tank
followed by soak pit.
viii. Industrial waste management
The waste water from Auto garage will be treated in oil and grease trap.
The treated waste water will be used for plantation.
Page 26 of 30
ix. Solid waste management.
There is no specific spoil will be generated in the project area. The
waste soil generated will be stacked in respective temporary dump
yards and will be used for reclamation at conceptual stage. No
overburden is anticipated during life of the mine.
x. Power requirement & supply / source.
The power required for bore well and office will be supplied from grid
initially, later through captive thermal power plant.
Page 27 of 30
CHAPTER – 7
REHABILITATION AND RESETTLEMENT (R & R) PLAN
7.0 Rehabilitation and resettlement (R & R) Plan
i. Policy to be adopted (central / state) in respect of the project
affected persons including home oustees, land oustees and landless
labourers (a brief out line to be given).
The mine area does not cover any habitation. Hence the mining
activities do not involve any displacement of human settlement. No
public buildings, places, monuments etc., exist within the lease area or
in the vicinity. The mining operations will not disturb / relocate any
village.
Page 28 of 30
CHAPTER – 8
PROJECT SCHEDULE & COST ESTIMATES
8.0 Project schedule & Cost Estimates
i. Likely date of start of construction and likely date of completion
(time schedule for the project to be given).
Mine will be started after getting EC, CTE, CTO and all other regulatory
clearances. Life of the mine @ 1.0 Million Tonnes Per Annum for the
mineable reserves of 45.25 million tonnes would be 47 years.
ii. Estimated project cost along with analysis in terms of economic
viability of the project.
The estimated project cost for the limestone production will be about
Rs. 3.76 Crores.
Page 29 of 30
CHAPTER – 9
ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.0 Analysis of proposal (Final Recommendations)
i. Financial and social benefits with special emphasis on the benefit
to the local people including tribal population, if any, in the area.
Economic development of the region depends largely upon the nature
of activities undertaken in the surrounding region. Corporate
development invariably contributes towards acceleration of the
process of socio-economic upliftment of the rural society by means of
employment, health & study programme, medical camps etc.,
Employment: Preference will be given for locals for employment based
on qualifications & requirement.
Medical facilities: Medical facilities are being provided for employees
as well as people of nearby villages.
Educational facilities: Basic educational and vocational facilities are
being provided for the children of employees as well as nearby villages.
Infrastructure facilities: Approach roads will be developed at par with
mine roads.
Additional: The establishment of factory will facilitate additional
auxiliary facilities like banking, post office & recreation facilities.