Upload
dixon
View
44
Download
0
Embed Size (px)
DESCRIPTION
Power Supply Status. George Ganetis Power Supply Status ASAC Review October 22-23, 2009. Outline. Storage Ring Overview Short Term Goals Multipole PS Corrector PS PS Controller DCCT & DVM Calibration Transport Line & Booster PS Look Ahead – Short & Long Term Conclusions. - PowerPoint PPT Presentation
Citation preview
1 BROOKHAVEN SCIENCE ASSOCIATES
Power Supply Status
George GanetisPower Supply Status
ASAC Review October 22-23, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Storage Ring Overview • Short Term Goals• Multipole PS• Corrector PS• PS Controller• DCCT & DVM Calibration• Transport Line & Booster PS• Look Ahead – Short & Long Term• Conclusions
3 BROOKHAVEN SCIENCE ASSOCIATES
Overview – Storage Ring Power SuppliesThis summary table includes approved and pending controlled changes
Power Supply-Model
Qty Max. Voltage
Max Current
Configuration Stability /Resolutionppm of max I
Operation
Main Dipole 1 1200 V 450 A Unipolar Switch-Mode , Digital Regulatorcenter point tied to GND
25 3.8
DC 1 Quadrant
Large ApertureTrim
1 300 V 13 A Unipolar Switch-ModeAnalog Curr. Regulator
10015
DC1 Quadrant
Quadrupole -A -B -C -D
601206060
16 V22 V30 V30 V
175 A175 A175 A215 A
Unipolar Switch-ModeAnalog Curr. Regulator1 PS per Magnet
503.8
DC1 Quadrant
Sextupole -A -B -C -D
355512
40 V60 V80 V16 V
120 A165 A120 A120 A
Unipolar Switch-ModeAnalog Curr. RegulatorModel A & B = 1 PS per 6 MagnetsModel C = 1 PS per 12 MagnetsModel D = 1 PS per 2 Magnets
10015
DC1 Quadrant
Global Horz. & Vert.Correctors -A
90 12 V 1.25 A 2 Channel Bipolar Linear Analog Curr. Regulator
10015
10000 Hz4 Quadrant
Insertion Horz. Correctors -B
12 30 V 30 A Unipolar Switch-ModeAnalog Curr. Regulator
503.8
DC1 Quadrant
Skew Quad Corrector-C
30 20 A 20 A Bipolar LinearAnalog Curr. Regulator
10015
DC4 Quadrant
Alignment Horz. & Vert. Correctors -D
180 25 V 22A 2 Channel Bipolar Linear / Pre-RegulatorAnalog Curr. Regulator
253.8
3 Hz2 Quadrant
Dipole Trim –Corrector -E
27 20 V 5 A 2 Channel Bipolar Linear / Pre-RegulatorAnalog Curr. Regulator
10015
DC4 Quadrant
Dipole Trim –Corrector -F
3 20 V 10 A 2 Channel Bipolar Linear / Pre-RegulatorAnalog Curr. Regulator
10015
DC4 Quadrant
4 BROOKHAVEN SCIENCE ASSOCIATES
Short Term Goals
• Main Dipole PS• Engineering analysis for switch-mode topology• Assemble & test prototype digital current regulator• Test series pass filter• Start final design
• Multipole PS• Build & test prototype major system components - current regulator , ps interface, ps controller, & AC control
module.• Test ps components for a complete ps in the nominal rack configuration.• Assemble multiple ps in rack for long term testing and software development.• Start final design of major system components.
• Corrector PS• Build & test prototype major system components - current regulator , ps interface, ps controller, & AC control
module.• Build & Test Power Amplifiers for Type A & D models ( New 2 channel designs )• Test ps components for a complete ps in the nominal rack configuration.• Assemble multiple ps in rack for long term testing and software development.• Start final design of some major system components.
5 BROOKHAVEN SCIENCE ASSOCIATES
Main Dipole Power Supply
• Decision was made to use a switch mode topology for the power converter section.
• Detailed circuit models for the power converter, filter, and series pass have been made and we are in the process of analyzing results.
• Procurement specifications will start soon.
• Detailed design on digital current regulator has started
6 BROOKHAVEN SCIENCE ASSOCIATES
Main Dipole Power SupplyCurrent Regulator Controls Prototype
Test setup is build for digitalcurrent regulator.Software work on the prototype regulator was just started this summer.
Switch mode PSLow voltage
DCCTElectronics
DSPElectronics
Series Pass Filter
DCCTHead
ResistiveLoad
Preliminary results of current output stability = + 1 ppm
DVM
ADC
7 BROOKHAVEN SCIENCE ASSOCIATES
Multipole Power Supplies
This configuration used for Quadrupole & Sextupole magnet circuits.
Standard commercial power converter are being used.
Three prototypes ps have been constructed and are under test.
These ps are installed in the temperature controlled racks.
Systems are under test using thecurrent regulator and power supply interface.
Instrumentation ( DVM/Scanner & 1-wire sensors ) are being used in testing.
PS Controller is in detailed design
8 BROOKHAVEN SCIENCE ASSOCIATES
Current Regulator Card
Prototype low noise current regulator.
Two built by hand, 8 more have been assembled at a vendor by machine.
Electronic adjustment of offset & gain of critical circuits.
Diagnostic signals brought out to both slow high precision DVM and fast ADC on PSI.
Preliminary tests show < 5ppm current stability for 1 hour.
1
1
1 2
35
1= Switch mode low level power supplies2= Low noise power conditioning filters3= Micro-controller used for state control & interlocks4= Precision burden resistors to convert current from DCCT to voltage5= High gain low noise analog current regulator
4
9 BROOKHAVEN SCIENCE ASSOCIATES
Power Supply Interface Card
1= Switch mode low level power supplies2= Low noise power conditioning filters3= FPGA used to convert fiber optic data to DACs & ADCs4= Micro-controller used for temperature Control of DACs5= Temperature stabilized DAC daughter board6= Analog signal connector to Current Regulator Card
1
2
34
5
Ten prototypes built by vender assembled by machine.PS Current Setpoint-Two 18 bit DACsDiagnostic signals-Nine 16 Bit ADC – -3 High Precision ADC-6 Low Precision ADCState Control & Status-8 Digital Outputs-16 Digital InputsFiber Optic Data Transfer to PSC is 10 kHz.Slow Serial Port Preliminary tests show < 5ppm DAC stability for 1 hour.
6
10 BROOKHAVEN SCIENCE ASSOCIATES
Power Supplies Rack Tests
Sextupole
Quadrupole
Quadrupole
Corrector
Corrector
AC Input Module
DCCTs
Regulator
Pwr Converter
Cold Air Blower
TemperatureControlled
Rack
Power supply test are done in temperature controlled racks that are close to the final design that will be installed in the machine.
Test with multiple power supplies - Will be looking for electrical noise interactions and thermal issues.
Rack configuration was reviewed by BNL fire safety personal and found no issues with the design or materials selection.
11 BROOKHAVEN SCIENCE ASSOCIATES
Test of Complete Multipole PSThis is both Current Regulator & PSI
Initial Results
12 BROOKHAVEN SCIENCE ASSOCIATES
Test of Complete Multipole PSThis is both Current Regulator & PSI
Initial Results
13 BROOKHAVEN SCIENCE ASSOCIATES
Corrector Power Supplies
Separated function corrector scheme will replace the combined function correctors.
There will be 6 slow alignment & 3 fast small corrector magnets per cell.
The new scheme added 180 new magnet circuits for the fast small correctors.
To cover the cost of the new circuits, we developed a new ps configuration – a 2 channel ps.The design shares some main components to reduce
costs.
It required the addition of components in the regulator and psi to make it a 2 channel version.
Engineering studies has determined that the extra components will fit into the exiting form factors
The power converter and amplifier are being re-designed to fit in ½ the nominal space. ( Less rack space )
(Highlighted)
14 BROOKHAVEN SCIENCE ASSOCIATES
Corrector Power Supplies
The new fast small corrector requires a much smaller AC bend strength then the baseline design. 80 urad vs 10 urad at 10 Hz.
The reduced size of the magnet also required less amp-turns for the 10 urad bend strength.
1 amp coil design was chosen to minimize the cost of the power supply system. This allowed the use of precision shunts to be used instead of more costly DCCTs.
The stability requirements were relaxed compared to the alignment correctors. ( Less Cost )
This design will use the same the same regulator and psi as in the alignment correctors. ( 2 Cha. )
The low current of this ps and the use of shunts as the feedback element will also allow a higher bandwidth then what could have been achieved with DCCTs.
15 BROOKHAVEN SCIENCE ASSOCIATES
Controls System Interface
Controls Group Responsibility
PS Group Responsibility
Very close working relations with Controls Group
Clear hardware interface boundaries.
Good software support to date.
16 BROOKHAVEN SCIENCE ASSOCIATES
Power Supply Controller
1st Rear Board
50Ω
50Ω
Rea
r b
oar
d c
on
ne
cto
rRJ45
RJ45IC SPARTAN-3A
FPGA
XC3S1400A-5FGG676C
1st Front Board
50Ω2222
LocalDC/DC
converters
100MHz PLLTx
Rx
2
3
Read readyWrite data
Write ready5
141 F
ron
t bo
ard co
nn
ecto
r
JTAG
Read data
FPGA programmingB
ackp
lan
e w
ith
fee
d t
hro
ug
h c
on
nec
tor
LocalDC/DC
converters
InterfaceRx
Tx
J8064D628ANL10/100 Base-TX To SDI
Optical Fibersto PSI
Address/Command
4
1R/W* Command
50Ω50Ω50Ω
CY7C68013AUSB FX2
USB2
Timing/Event Interface (Bussed) 16
128Mx8, 256MBx8 or 512Mx8
DDR2 Memory
MT47HxxxM8 60-63 BGA
128Mx8, 256MBx8 or 512Mx8
DDR2 Memory
MT47HxxxM8 60-63 BGA
KSZ8851
KSZ8851 Magnetic
MagneticLED 01,02
LED 03,04
LED 05,06
LED 07,08
LED 09,10
LED 11,12
LED 13,14
LED 15,16
RJ45 Magnetic 50Ω50Ω
Active Terminations
Slots 1 & 21 only
Permit Interface (Daisy chained) 4Pull-
Down
PSC Chassis can hold up to 20 main & transition cards
One main card can control a single or dual channel PSI
FPGA has DSP capabilities for waveform generation & diagnostic functions analysis.
The main cards have large on board memory for waveform & diagnostic storage.
Transition boards have SDI & fiber optic connections
17 BROOKHAVEN SCIENCE ASSOCIATES
DCCT & DVM Calibration
National Standards
Portable 10 V
Standard
Portable 10 V
Standard
BNL DCCT Bridge
In-Situ Cal.
24 hour
90 day
180 day
1 year
V 0.5 2.5 4
Ω 1 5 8
BNL Primary Standards
DCV Transfer
Traveling DCCT
Standard
In-Situ Cal.
In PPM
We will test ~ 1800 DCCT before installation.
DVM
PS Rack
18 BROOKHAVEN SCIENCE ASSOCIATES
Transport Line PS
• Transport line power supplies will use same hardware as the storage line. Current Regulator, PSI, PSC, DVM/Scanner, 1-Wire devices, & Commercial Power Converters.
Power Supply-Model
Qty Max. Voltage
Max Current
Configuration Stability /Resolutionppm of max I
Operation
LBTL Dipole –A -B
1 1
75 V40 V
200 A125 A
Unipolar Switch-Mode Analog Curr. Regulator1 PS per Magnet
10015
DC 1 Quadrant
LBTL Quadrupole -A -B
12 6
16 V50 V
175 A175 A
Unipolar Switch-Mode Analog Curr. Regulator1 PS per Magnet
10015
DC1 Quadrant
LBTL Alignment Horz. & Vert. Correctors
8 20V 20A 2 Channel Bipolar Linear / Pre-RegulatorAnalog Curr. Regulator
10015
3 Hz2 Quadrant
BSRTL Dipole 5 75 V 200 A Unipolar Switch-Mode Analog Curr. Regulator1 PS per Magnet
100 15
DC 1 Quadrant
BSRTL Quadrupole -A -B
14 4
30 V16 V
175 A175 A
Unipolar Switch-Mode Analog Curr. Regulator1 PS per Magnet
10015
DC1 Quadrant
BSRTL Alignment Horz. & Vert. Correctors
6 25 V 20 A 2 Channel Bipolar Linear / Pre-RegulatorAnalog Curr. Regulator
10015
3 Hz2 Quadrant
19 BROOKHAVEN SCIENCE ASSOCIATES
Booster PS Controls
PSI # 1Dual Channel
PSI # 2Single Channel
PSI # K
PSCPower Supply Controller # 1
PSC Master- - - - - - - - - -
SDI
PSCPower Supply Controller # 2
PSCPower Supply Controller # M
Booster PS # 1
Booster PS # X
Booster PS # 2
Booster PS # 3
Fiber Optic Link 50Mbit/s
SDI protocol100Mbit
Booster Power Supply Control
SDI - LOOP
IOCVME Chassis
WithTiming Event
Reciever
Standard Ethernet
BoosterPower Supply
TimingSignals
• Booster power supplies will use BNL supplied controls PSI,PSC, & IOC
• Vendor will supply current regulator and state control & interlocks
20 BROOKHAVEN SCIENCE ASSOCIATES
Look Ahead – Short Term ( next 6 months )
• Continue testing single channel power supply interface ( PSI )• Finish design, build & test power supply controller ( PSC )• Design , build, & test two channel current regulator and two channel psi• Finish design , build, and test corrector D power amplifier ( Alignment
Corrector )• Design, build, & test corrector A power supply ( Fast Global Corrector )• Continue on software development for controls and instrumentation• Continue long term testing of power supplies and components.
21 BROOKHAVEN SCIENCE ASSOCIATES
Look Ahead – Long Term
Storage Ring Power Supply Schedule
22 BROOKHAVEN SCIENCE ASSOCIATES
Conclusions
• Good progress is being made in the main dipole ps with the addition of the new engineer.
• Multipole power supplies are in good shape, working prototype supply will easily meets requirements.
• We are a little behind in corrector work due to the re-direction of the requirements. We should be able to recover in the next 6 months with the prototypes being built.
• We have a rack system setup for long term testing and software development.
• Detailed procurement plans have been developed. We are actively working with vendors and NSLS II Procurement in developing manufacturing plans and specifications. We are using prototype builds to qualify vendors.