Portf olio Thant Zin Oo Project Manager Architect MSc in Construction Project Management (HWU, UK) B. Architecture (YTU, Myanmar) ICIOB, UK Registered Architect, Myanmar Autodesk ® Revit® Architecture 2013 Certified Professional

Portfolio of Thant Zin Oo (Compressed)

Embed Size (px)

Citation preview

Page 1: Portfolio of Thant Zin Oo (Compressed)

Portfolio Thant Zin OoProject Manager Architect MSc in Construction Project Management (HWU, UK) B. Architecture (YTU, Myanmar) ICIOB, UK Registered Architect, Myanmar Autodesk® Revit® Architecture 2013 Certified Professional

Page 2: Portfolio of Thant Zin Oo (Compressed)

Project ListFrom 2004 – 2016 in reversed chronological order

1. Conservation and Redevelopment of Novena Church, Singapore

2. D&B of Mayflower MRT station (Thomson-East Coast Line), Singapore

3. Construction of Intra-island cable way which includes with 3 stations at Sentosa Island, Singapore

4. D&B of pedestrian bridge and tower access to fort Siloso at Sentosa island, Singapore

5. Construction of extension to the existing to Nanyang Polytechnic which consist 5 buildings, Singapore

6. Construction of Bugis Station and its associated tunnels, Singapore

7. Architectural, M&E, and system fit-out and installation of Universal Studios, Singapore

8. Construction of Bartley Christian Church, Singapore

9. Construction of Singapore Islamic Hub, Singapore

10. Designing of Burmese style Pagodas, Meditation Centres, USA

11. D&B of Yankin House, a luxury 3 storey residence in Yangon, Myanmar

Page 3: Portfolio of Thant Zin Oo (Compressed)

Conservation and Redevelopment of Novena ChurchAbout the project: Conservation and Redevelopment of Novena Church Consisting of an existing single-storey conservation building, erection of a 2-wtorey church building with 2 basement carpark. The contract sum is approximately SGD 37M

Role: Assistant Project Manager

Responsibilities:

• Responsible for contract administration and project management.

• Responsible for overall planning of the project. Planning for the strategies of the overall completion of the project.

• Responsible for the progress and cash floor for the project against contract document and master programmed. Ensured the cost is within budget and increase profitability. Above: Artist impression of Novena Church (Source: http://goo.gl/Zcby6w)

Below: Site condition from pedestrian bridge

Page 4: Portfolio of Thant Zin Oo (Compressed)

D&B of Mayflower MRT station (Thomson-East Coast Line) About the project: Underground MRT station with 4 basements and 7 entrances for Thomson-East Cost Line. The contract sum is approximately SGD 174M.

Role: Architectural Coordinator (Corporate)

Responsibilities:

• Oversee the design process and ensure clients’ needs are met in a timely and cost effective manner.

• Work with designers (Architect (Ong & Ong) and Engineers (Meinhardt)), System Wide Contractors (SWCs) and government agencies to develop MRT station design.

• Ensure that the project complies with Land Transport Authority (LTA)’s Architectural Design Criteria (ADC), Civil Defence (CD) requirement and other regulations, which include revising the project design as necessary to achieve client satisfaction.

Page 5: Portfolio of Thant Zin Oo (Compressed)

Construction of Intra-island cable way which includes with 3 stations at Sentosa IslandAbout the project: Intra-island cable way which includes with 3 stations at Sentosa Island (Approx. SGD 18.6M)

Role: Architectural Coordinator (Corporate)

Responsibilities: • Filling the vacancy of Architectural

Coordinator and ensure the project to attain the Temporary Occupancy Permit (TOP) in time.

• Led the team to achieve timely completion of Architectural works as per contractual terms.

• Frequently visited the construction site to monitor the progress and catch any problems that may occur.

Siloso Point Station

Imbiah Lookout StationMerlion Station

Page 6: Portfolio of Thant Zin Oo (Compressed)

Siloso Point Station

View from Siloso Beach View from the top of Fort Siloso Tower

Page 7: Portfolio of Thant Zin Oo (Compressed)

Siloso Point Station

View from Cable Car Interior of the station

Page 8: Portfolio of Thant Zin Oo (Compressed)

Imbiah Lookout Station

View from the road to Tiger tower View from the walkway

Page 9: Portfolio of Thant Zin Oo (Compressed)

Imbiah Lookout Station

Interior of the Station: Platform area Interior of the Station: Escalators

Page 10: Portfolio of Thant Zin Oo (Compressed)

Merlion Station

View from Cable Car Interior of the Station: Ticket Sales Office

Page 11: Portfolio of Thant Zin Oo (Compressed)

Merlion Station

View from Fire Engine Access Area View to the main entrance from pedestrian access

Page 12: Portfolio of Thant Zin Oo (Compressed)

D&B of pedestrian bridge and tower access to fort Siloso at Sentosa islandAbout the project: Design and construction of pedestrian bridge and tower access to fort Siloso at Sentosa island (Approx. SGD 3M)

Role: Architectural Coordinator (Corporate)

Responsibilities:

• Filling the vacancy of Architectural Coordinator and ensure the project to attain the Temporary Occupancy Permit (TOP) in time

• Worked with designers (Architect (CPG) and Engineers (CPG)) to develop the design.

• Led the team to achieve timely completion of Architectural works as per contractual terms.

View from the road

Page 13: Portfolio of Thant Zin Oo (Compressed)

Pedestrian bridge and tower access to fort Siloso

Top of the bridge View from Pedestrian walk way

Page 14: Portfolio of Thant Zin Oo (Compressed)

Pedestrian bridge and tower access to fort Siloso

Jungle trail and tree log seat under the bridge View from Jungle trail

Page 15: Portfolio of Thant Zin Oo (Compressed)

Construction of extension to the existing to Nanyang Polytechnic which consist 5 buildingsAbout the project: Construction and completion of extension to the existing to Nanyang Polytechnic (Approx. SGD 137M). This work includes 4-storey and 7-storey academic blocks, 2-storey and 3-storey ancillary facility blocks and additional & alteration to the existing block A.

Role: Architectural Coordinator (Corporate)

Responsibilities:

• Reviewed project specifications, construction drawings and some technical clarifications.

• Liaised with Architect & Engineer (RSP), Site Engineers, Sub-contractors and Suppliers for quality and timely completion of works.

• Tracked & managed contemplated change notices and change orders in the database.

Nanyang Polytechnic Expansion site map

Page 16: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 1 (Canteen & Administrative)

View to the site 1 building main entrance Interior of site 1 building

Page 17: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 2 (Recreation Centre)

View to the site 2 building main entrance Interior of site 2 building

Page 18: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 3 (Classrooms)

View to the site 3 building exterior (Rear) View to the site 3 building exterior (Front)

Page 19: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 5 (Classrooms and Labs)

Site 5 building Interior (Level 2 - Hall) Site 5 building Interior (Level 7 - Labs)

Page 20: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 6 (Multi-purpose hall)

View from the opposite to site 6 building Façade and main entrance of Site 6 building

Page 21: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 7 (Singapore Institute of Technology)

View from the opposite to site 7 building Façade and main entrance of Site 7 building

Page 22: Portfolio of Thant Zin Oo (Compressed)

Nanyang Polytechnic Extension: Site 7 (Singapore Institute of Technology)

Resting area of site 7 building Lecture theater of Site 7 building

Page 23: Portfolio of Thant Zin Oo (Compressed)

Construction of Bugis Station and its associated tunnelsAbout the project: The construction and completion of DTL1 Bugis Station and its associated tunnels (Approx. SGD 582M)

Role: from Architectural Coordinator to Design Manager

Responsibilities:

• Responsible for the serving as a bridge between the site construction and engineering team. Act as a single point of contact for all coordination issues on the project among the Client (LTA), Consultants (Architect (Aedas) and Engineers (Arup)), and System Wide Contractors (SWCs).

• Established, implemented and maintained the procedure for coordination meeting for resolving the interface issues.

• Ensured timely release of the drawing for construction by the engineering team by coordinating the various inputs

• Contributed ideas for improving company’s design, change management and claim processes.

• Prepared substantial completion certificates and ensure all required project close out documents are obtained

Interior of the station on Platform level

Page 24: Portfolio of Thant Zin Oo (Compressed)

Bugis Station (Downtown Line)

Featured glass wall and art work Featured wall and ceiling

Page 25: Portfolio of Thant Zin Oo (Compressed)

Bugis Station (Downtown Line)

Opening ceremony of Bugis Station Entrance 1 of Bugis Station

Page 26: Portfolio of Thant Zin Oo (Compressed)

Architectural, M&E, and system fit-out and installation of Universal Studios SingaporeAbout the project: Architectural, M&E, audio, visual and system fit-out and installation of UNIVERSAL STUDIO SINGAPORE’s main facilities including Shrek 4D theatres (Approx SGD 50M) and Madagascar Crate Adventure Water ride (Approx SGD 100M).

Role: Site Coordinator

Responsibilities:

• Responsible for coordinating construction efforts through in-house and contract labour for new construction projects.

• Responsible for construction personnel safety and quality of work performed.

• Responsible for site progress.

• Maintained a clean health and safety record and overseeing the resolution of any problems.

• Coordinated structural details and design features within the project. Conducted meetings with designers and detailers as required

During installation of theme props, AV and animatronic at Madagascar Crate Adventure

Page 27: Portfolio of Thant Zin Oo (Compressed)

Universal Studios Singapore

During installation of fire prevention systems at Mummy ride

During installation of theme props, AV and animatronic at Shrek 4D theater

Page 28: Portfolio of Thant Zin Oo (Compressed)

Construction of Bartley Christian ChurchAbout the project: BARTLEY CHIRSTIAN CHURCH (BCC), a 3-storey Church building with a basement carpark. (Approx. SGD 10M)

Role: Draftsman cum. Architectural Coordinator

Responsibilities:

• Liaised with Consultants on matters of design & technical co-ordination issues and building regulations. Assisted Project Manager with shop drawing submission.

• Prepared setting out drawings, Coordinated Services Drawings (CSD) and M&E penetration drawings.

• Visited construction sites to collect measurements and dimensions as needed.

Bartley Christian Church from Opposite

Page 29: Portfolio of Thant Zin Oo (Compressed)

Construction of Singapore Islamic HubAbout the project:SINGAPORE ISLAMIC HUB (SIH) is the Hub of the Community and it is a landmark of progress for Islamic development in Singapore. The SIH comprises the Muhajirin Mosque, Madrasah Al-Irsyad Al-Islamiah (Quran School) and Majlis Ugama Islam Singapura Headquarters (Business Hub). (Approx. SGD 32M)

Role: Draftsman

Responsibilities:

• Assisted Project Manager with shop drawing submission.

• Prepared setting out drawings, Coordinated Services Drawings (CSD) and M&E penetration drawings.

• Visited construction sites to collect measurements and dimensions as needed.

Page 30: Portfolio of Thant Zin Oo (Compressed)

Designing of Pagodas, Meditation Centres in USAAbout the project: Clients from US decided to hire a group of Myanmar Architect and build Burmese style pagoda in the US for the merit of Burmese preserving Buddha’s meditation techniques over 2000 years.

Role: Assistant Architect

Responsibilities:

• Led local architectural teams to produce working drawings and liaised with US architectural team.

• Utilize 3D CAD tools to develop and communicate design concepts; direct the completion and models, layouts, and details for products assemblies and components.

• Responsible for the communication with Project Management team based in the US on design matters.

• Ensured completion and accuracy of a complete design documentation package for construction including appropriate design files, drawings, materials and workmanship specifications.

• Provided direction to the fibreglass contractor for the fabrication and assembly of prototypes of Burmese Pagodas.

California Vipassana Center main building

Page 31: Portfolio of Thant Zin Oo (Compressed)

Dhamma Mahāvana

Installation of fiberglass pagoda Installation of fiberglass pagoda

58503 Rd 225, North Fork, CA 93643, United States

Page 32: Portfolio of Thant Zin Oo (Compressed)

Dhamma Vahdhan

Temporary Dhamma Hall Design Temporary Dhamma Hall after completion

South California Vipassana Center (SCVC)68561 Twentynine Palms Hwy Twenty Palms, CA 92777 United States

Page 33: Portfolio of Thant Zin Oo (Compressed)

Dhamma Vahdhan

Student Residences ‘A’ Design Student Residences ‘A’ after completion

South California Vipassana Center (SCVC)68561 Twentynine Palms Hwy Twenty Palms, CA 92777 United States

Page 34: Portfolio of Thant Zin Oo (Compressed)

Dhamma Patapa

Student residence and Meditation Center design Student residence and Meditation Center after completion

Southeastern Vipassana Center476 Rogers Break, Jesup, GA 31646, United States

Page 35: Portfolio of Thant Zin Oo (Compressed)

Dhamma Patapa

Kitchen/dining hall design Kitchen/dining hall design after completion

Southeastern Vipassana Center476 Rogers Break, Jesup, GA 31646, United States

Page 36: Portfolio of Thant Zin Oo (Compressed)

D&B of Yankin House, a luxury 3 storey residence in MyanmarAbout the project: Yankin House is a luxury 3 storey resident in Yangon, Myanmar. (Approx. SGD 1M)

Role: Resident Architect

Responsibilities:

• Based at the site, liaised with design and construction teams and provided technical and design solutions to any problems encountered on site during construction phase development.

• Reviewed all architectural aspects submittals, drawings, methods documents and conducted inspection, material inspection and approval.

• Inspected the construction while in progress and upon completion for adherence to plans and specifications; advised contractors on the interpretation of plans and specifications; approved minor design changes in the course of construction and reviewed contractors' requests for payment. Yankin House during construction

Page 37: Portfolio of Thant Zin Oo (Compressed)

D&B of Yankin House, a luxury 3 storey residence in Myanmar

3D framing model for clash detection Step-by-step Construction sequence simulation