2000 2005 2010 2015

Antony Park Bords de Seine Campus SFR

Les Allées Royales Cités Jardins Carré des Arts

Clinique des Platanes

Clinique Ronsard

Résidence Sainte Geneviève

Commercial Facilities

Residential Facilities

Medical Facilities

Timeline of projects

Content

Commercial FacilitiesAntony Park

Bords de SeineCampus SFR

Residential FacilitiesLes allées royales

Cités JardinsCarré des Arts

Medical FacilitiesClinique des Platanes

Résidence Sainte GenevièveClinique Ronsard

Commercial Facilities

ANTONY PARK

• Client : Tertial (ICADE group)• Architect : Henri LAFONTA• Location : Antony (94) south of Paris• Construction cost : 25 M€• Period : 2000-2002• Position : General Contractor, Assistant Site Manager• Responsability : Coordination of structural work• Project description : 17,000m2 office building

Six basements built with top and down method

Top and down contruction progress

* Down structure progress as below :

* Top structure progress upward

--> Top and down structures progress at the same time

BORDS DE SEINE

• Client : COGEDIM• Architect : ARTE & CHARPENTIER• Location : Saint Cloud (92) west of Paris• Construction cost : 5 M€• Period : 2005-2006• Position : General Contractor, Construction Manager• Responsability : Construction supervision and design

review of structure, MEP and finishes• Project description : 5,000m2 office building

Airplane’s wing shape’s zinc roofPrefabricated wall panels

Prefabricated wall panels

Prefabricated wall panels delivery Prefabricated wall panels in position

CAMPUS SFR

• Client : VINCI IMMOBILIER• Architect : JP VIGUIER• Location : Saint Denis (93) north of Paris• Construction cost : 150 M€• Period : 2012-2013• Position : Construction Project Manager for VINCI

ENERGIE• Responsability : Supervision and design review of

MEP (40M€)• Project description : 240,000m2 office building

HVAC equipment Mixed steel and concrete framework

Residential Facilities

LES ALLEES ROYALES

• Client : NEXITY• Architect : Christian GIRAT• Location : Versailles (78) west of Paris• Construction cost : 15 M€• Period : 2003-2005• Position : General Contractor, Construction Manager• Responsability : Coordination and design review of

structure, MEP and finishes• Project description : 118 high standing housing

Traditionnal carpentry with slate roofHeavy rehabilitation of historical building

CITES JARDINS

• Client : OPHLM 92• Architect : Architecture 3A• Location : Plessis Robinson (94) south of Paris• Construction cost : 10 M€• Period : 2006-2007• Position : General Contractor, Construction Manager• Responsability : Coordination and design review of

structure, MEP and finishes• Project description : 95 social housing

Traditionnal dome carpentry White concrete modenature

CARRE DES ARTS

• Client : KAUFMAN & BROAD• Architect : ERAM & SCHAFIE• Location : Saint Maur (94) south of Paris• Construction cost : 13 M€• Period : 2007-2008• Position : General Contractor, Construction Manager• Responsability : Coordination and design review of

structure, MEP and finishes• Project description : 129 housing condo

Mixed materials facades (stones, tiles, lime plaster)Double floor concrete break roof

Medical Facilities

CLINIQUE DES PLATANES

• Client : GENERALE DE SANTE• Architect : Olivier LEQUERTIER• Location : Epinay sur Seine (93) north of Paris• Construction cost : 6 M€• Period : 2009-2010• Position : Construction Project Manager• Responsability : Supervision and design review of

structure, MEP and finishes• Project description : 80 beds drug rehabilitation

Vegetalized facadeVegetalized main lobby

RESIDENCE SAINTE GENEVIEVE

• Client : Association Monsieur Vincent• Architect : François GACHET• Location : Nanterre (92) west of Paris• Construction cost : 16 M€• Period : 2010-2012• Position : Construction Project Manager• Responsability : Supervision and design review of

structure, MEP and finishes• Project description : 120 beds elderly community

Prefabricated Plumbing shaftHeated or cooling floor (water pipes) using geothermal well drilling

CLINIQUE RONSARD

• Client : GENERALE DE SANTE / ISMS• Architect : Claude BLANCHET• Location : Joue les Tours (37) 200km south of Paris• Construction cost : 14 M€• Period : 2011-2012• Position : Construction Project Manager• Responsability : Supervision and design review of

structure, MEP and finishes• Project description : 100 beds psychiatric clinic

Matrice concrete facade Standard double bedroom