Addendum No. 1Page 1 of 2
Project No.: 17120
Date: July 31, 2017
Project: Toronto District School BoardDining Hall to Classrooms ConversionIsland Public/Natural Science School30 Centre Island ParkToronto, Ontario
The following information supplements and/or supersedes the original bid documents.
This Addendum forms part of the contract documents and is to be read, interpreted, and coordinated withall other parts. The cost of all contained herein is to be included in the contract sum. The followingrevisions supersede the information contained in the original drawings and specifications issued for theabove-named project to the extent referenced and shall become part thereof.
0.0 General
0.1 Answers to Bidder Questions:1. Q1: Floor Plan A201 states that privacy film is required in two places for this project,
but there is no mention of what type of privacy film this is meant to be.
A1: Privacy film is to be 3M Sandblast Film. Contact Convenience Group at 1-888-835-5885. Clean glazing and install the 3M Sandblast Film on the interior roomside of the glazing.
2. Q2: Who is the base building sprinkler contractor we are required to use for this job?
A2: From the existing school Sprinkler Diagram, the fire alarm and sprinklercontractor is Tyco/Simplex Grinnell. Contact Nabeel Mian at 905-212-4472 orcell 416-209-8740. His e-mail is [email protected].
1.0 Request for Tender Classroom Conversion at Island PS
1.1 Tender Price Schedule
1. Add a Cash Allowance in amount of $10,000 for Door Hardware.
2.0 Island School Permit and Tender Drawings July 7-17
2.1 Architectural Drawings:1. A100: Location Plan, Key Floor Plan and OBC Matrix, and attached Detail Drawing
SKA-01 and photos:1. At the existing electrical panel near the Change Rooms (see attached Photo 1),
break existing block above the panel to accommodate new branch circuits andspare conduits. Add 5/8" gypsum board to cover damaged block. Patch, makegood and paint.
2. Patch bulkhead shown in the attached Photo 2. The bulkhead requires cutting,patching and painting to accommodate the installation of new electrical conduits. Provide 3-5/8" metal studs and 5/8" gypsum board to enclose conduits. Patch,make good and paint.
3. Paint all new exposed electrical conduits to match colour of adjacent surfaces.
17120Addendum1july31.wpd
Page 2 of 2
2.2 Mechanical Drawings:1. Attached is Mechanical Addendum ADDM1, dated July 27, 2017, from Madonna Engineering
Inc.
2.3 Electrical Drawings:1. Attached is Electrical Addendum #E-01, dated July 19, 2017, from HCC Engineering Limited.
2.4 Communications Drawings:1. Attached is Communications Addendum #C-01, dated July 19, 2017, from HCC Engineering
Limited.
END OF ADDENDUM NO. 1
17120Addendum1july31.wpd
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
KEY FLOOR PLAN
1" = 30'-0"
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
LOCATION PLAN, KEY
FLOOR PLAN AND OBC
MATRIX
17120 A100
Toronto
SchoolBoard
District
LOCATION PLAN
NTS
NAME OF PROJECT :
LOCATION OF PROJECT :
CERTIFICATE OF PRACTICE NUMBER : 5192
250 WATER STREET, SUITE 201
WHITBY, ONTARIO, CANADA. LIN 0G5
TEL : (905) - 666 - 5252
(Toronto) (905) - 427 - 4495
FAX : (905) - 666 - 5256
DINING AREA TO CLASSROOMS CONVERSION
ISLAND PUBLIC / NATURAL SCIENCE SCHOOL
3O CENTRE ISLAND PARK, TORONTO, ONTARIO
DATE :
JULY 7,2017
BARRY BRYAN ASSOCIATESNAME OF PROJECT :
OBC Reference
Addition Addition and Renovation11.01 Project Type:
Change of use
Ontario Building Code Data Matrix
Part 11 - Renovation of Existing Building
11.00Building Code Version: O. Reg. 332/12 Last Amendment: O. Reg. 191/14
Renovation
Description ____________________________________________________-
[A] 1.1.2.
Major Occupancy
Classification:
3.1.2.1.(1)Use
___________________________________________
___________________________________________
___________________________________________
Occupancy
_________________
_________________
_________________
Group A, Division 2
-
-
School
-
-
Superimposed
Major Occupancies:
Yes No
Description ____________________________________________________-
Building Area (m²) Existing
_________
_________
_________
_________
Description
_________________________________
_________________________________
_________________________________
Total=
Ground Floor including 224 m² reno
-
5,103 m²
-
New
_________
_________
_________
_________
0
-
-
Total
_________
_________
_________
_________
5,103 m²
-
5,103 m² 0 5,103 m²
[A] 1.4.1.2.
3.2.2.7
11.02
11.03
11.04
Building Height [A] 1.4.1.2 &
3.2.1.1
1
______________ Storeys above grade ________ (m) Above grade
______________ Storeys below grade
0
-
Number of streets/
fire fighter access:
3.2.2.10 & 3.2.5
1
____________ street(s)
11.05
11.06
Building Size: Small Medium Large > Large T.11.2.1.1.B.-N.11.07
Existing Building
Classification:
11.08 Change in Major Occupancy: Not Applicable
(no change of major occupancy)
Yes
Construction Index: ______________5
Hazard Index: ______________6
Importance Category: Low
High
Normal
Post-disaster
to N, 4.1.2.1(3)
& 5.2.2.1.(2)
T11.2.1.1B
T11.2.1.1A
11.2.1
Renovation Type: Basic Renovation Extensive Renovation11.0911.3.3.1 & 11.3.3.2
Occupant Load: Floor Level/ Area Occupancy Type Based On Occup. Load
__________________ ________________ _________ ________
__________________ _______________ _________ ________
-
-
-
-
-
-
-
-
3.1.17
Plumbing Fixture
Requipments:
Ratio: Male/Female = 50:50 Except as noted otherwise
Floor level/ Area Occupant OBC Fixtures Fixtures
Load Reference Required Provided
__________ _____ ____ ________ ______ _______
__________ _____ ____ ________ _______ _______
__________ ____ ____ ________ _______ _______
__________ _____ ____ ________ _______ _______
3.7.4
11.10
11.11
Barrier-free Design: Yes Explanation ______________________________________
No
11.3.3.2.(2)11.12
Structural No YesReduction in
Performance Level:
11.4.2.1
By Increase in occupant load: No Yes 11.4.2.2
By change of major occupancy: No Yes 11.4.2.3
Plumbing No Yes 11.4.2.4
Sewage - system: No Yes 11.4.2.5
11.13
Compensating
Construction:
11.14 Yes No ____________________________________________
Structural No Yes _____________________________
11.4.2.1
By Increase in occupant load: No Yes _____________________________
11.4.2.2
By change of major occupancy: No Yes ____________________________
11.4.2.3
Plumbing No Yes _____________________________
11.4.2.4
Sewage - system: No Yes _____________________________
11.4.2.5
11.4.2.6
Extension of Combustible
Construction:
No Yes _____________________________ 11.4.2.7
Compliance
Alternatives
Proposed:
11.15 Yes ______________________________________ No
Notes:11.16
11.5.1.
11.5.1
5,103 m² INCLUDING 224 m² RENOVATION
ADDENDUM ADDM1
MEI MADONNA ENGINEERING INC. 93 Woodstream Blvd, Unit 10 Woodbridge, Ontario L4L 7Y7 T: (905) 265‐1911 F: (905) 265‐1998
Page 1 of 1
URGENT FOR REVIEW PLEASE COMMENT PLEASE REPLY BY HAND
BY EMAIL BY COURIER BY FAX BY PICK‐UP
This Addendum ADDM1 forms part of the contract documents.
1. Reference 1. Drawing M‐1, Part Ground Floor Plan – Mechanical HVAC, Rev. 02, July 27, 2017. Issued with
this ADDM1.
2. Description
1. 1/M‐1: 1. Existing kitchen equipment return grille added to drawing. 2. Drawing note #7 added.
2. 2/M‐1: 1. New location of existing kitchen equipment return grille added to drawing. 2. Drawing note #10 added.
3. Reason for Revision
1. Coordination with Architect/Interior Designer.
End of ADDM1
To: Barry Bryan Associates 201‐250 Water St., Whitby, Ontario L1N 0G5
From: Madonna Engineering Inc. Ray Ravikanthan
Phone: 905‐666‐5252 Date: July 27, 2017
Re: Dining Area To Classrooms Conversion 30 Centre Island Park, Toronto ON
CC: Nicholas Vallestero
Attn: John Moses Project No.: 17‐0127
HCC ENGINEERING LIMITED Design and Technology Services Group 40 Eglinton Avenue East
Suite 401
Toronto, Ontario
M4P 3A2
Tel: (416) 932-2423
Tender Addendum #E-01
Project: Dining Area to Classrooms Conversion
Island Public/Natural Science School
30 Centre Island Park
Toronto, Ontario
HCC Engineering Project No.: 17133
BCIN# 28954
Date: July 19, 2017
1. General
1. This tender addendum is an integral part of the Specifications and Drawings and shall form
an integral part of the Contract Documents.
2. Drawings
1. Drawing No. E-1.1 (Reissued with Addendum)
2. Drawing No. E-1.2 (Reissued with Addendum)
3. Drawing No. E-1.3 (Reissued with Addendum)
4. Drawing No. E-1.4 (Reissued with Addendum)
5. Drawing No. E-2.0 (Reissued with Addendum)
6. Drawing No. E-2.1 (Reissued with Addendum)
7. Drawing No. E-3.1 (Reissued with Addendum)
3. Panel Schedule
1. RP-1I (Reissued with Addendum)
End of Tender Addendum #E-01
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL LEGEND AND
DETAILS
17133 E-1.1
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL DETAILS
17133 E-1.2
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL DETAILS
17133 E-1.3
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL DETAILS
17133 E-1.4
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL PLAN -
GROUND FLOOR
17133 E-2.0
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
ELECTRICAL PLANS
17133 E-2.1
Toronto
SchoolBoard
District
7JUL
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
REFLECTED CEILING
PLANS
17133 E-3.1
Toronto
SchoolBoard
District
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
Project: 17133
Panelboard: RP-1IVoltage (V): Phase/Wire: Bus and Lugs Rating (A):
CCT Load Breaker CCT Load BreakerNO Amp Pole NO Amp Pole
1 CLASSROOM B101A MISC 20 1 2 CLASSROOM B101 LIGHTING 20 13 CLASSROOM B101A MISC 20 1 45 CLASSROOM B101B MISC 20 1 67 CLASSROOM B101B MISC 20 1 89 CLASSROOM B101B MISC 20 1 10
11 HOUSEKEEPING 20 1 1213 CONTROL CCT 15 1 1415 CONTROL CCT 15 1 1617 CONTROL CCT 15 1 1819 SPARE 20 1 20 SPARE 15 121 SPARE 20 1 22 SPARE 15 123 SPARE 20 1 24 SPARE 15 125 2627 2829 3031 3233 3435 3637 3839 4041 42
HCC ENGINEERING LIMITED JULY 6, 2017
Project: 17133
Panelboard: RP-1IVoltage (V): Phase/Wire: Bus and Lugs Rating (A):
CCT Load Breaker CCT Load BreakerNO Amp Pole NO Amp Pole
43 4445 4647 4849 5051 5253 5455 5657 5859 6061 6263 6465 6667 6869 7071 7273 7475 7677 7879 8081 8283 84
HCC ENGINEERING LIMITED JULY 6, 2017
HCC ENGINEERING LIMITED Design and Technology Services Group 40 Eglinton Avenue East
Suite 401
Toronto, Ontario
M4P 3A2
Tel: (416) 932-2423
Tender Addendum #C-01
Project: Dining Area to Classrooms Conversion
Island Public/Natural Science School
30 Centre Island Park
Toronto, Ontario
HCC Engineering Project No.: 17133
BCIN# 28954
Date: July 19, 2017
1. General
1. This tender addendum is an integral part of the Specifications and Drawings and shall form
an integral part of the Contract Documents.
2. Drawings
1. Drawing No. C-1.1 (Reissued with Addendum)
2. Drawing No. C-2.0 (Reissued with Addendum)
End of Tender Addendum #C-01
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
COMMUNICATIONS
LEGEND AND DETAILS
17133 C-1.1
Toronto
SchoolBoard
District
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
7JUL
7JUL
ASSOCIATESBARRY BRYAN
PROJECT NO:
FILE:
DRAWING NO:
SCALE:
DATE:
CHECKED BY:
DRAWN BY:
DESIGN BY:
DRAWING:
PROJECT:
REVISIONSNO. DATE BY
DRAWINGS ARE NOT TO BE USED FOR CONSTRUCTION UNTIL SIGNED
UPON REQUEST. REPRODUCTION OF DRAWINGS IN PART OR WHOLECOPYRIGHT PROPERTY OF THE CONSULTANT AND MUST BE RETURNEDALL DRAWINGS, SPECIFICATIONS AND RELATED DOCUMENTS ARE THE
AND SEALED BY THE CONSULTANT.
WITHOUT THE PERMISSION OF THE CONSULTANT IS FORBIDDEN.
CHECK AND VERIFY ALL DIMENSIONS AT THE SITE.
ISSUESNO. DATE BY
30 CENTRE ISLAND PARK,
TORONTO, ONTARIO
TORONTO DISTRICT SCHOOL BOARD
COMMUNICATIONS PLAN -
GROUND FLOOR
17133 C-2.0
Toronto
SchoolBoard
District
HCC ENGINEERING LIMITED40 EGLINTON AVENUE EAST, SUITE 600
TORONTO, ONTARIO, M4P 3A2Tel: (416) 932-2423
7JUL
7JUL