Upload
phamminh
View
213
Download
0
Embed Size (px)
Citation preview
Application: 15-05-xxx (U 39 M) Exhibit No.: Date: May 1, 2015 Witness(es): Various
PACIFIC GAS AND ELECTRIC COMPANY
SAFETY MODEL ASSESSMENT PROCEEDING
PREPARED TESTIMONY
-i-
PACIFIC GAS AND ELECTRIC COMPANY SAFETY MODEL ASSESSMENT PROCEEDING (S-MAP)
PREPARED TESTIMONY
TABLE OF CONTENTS
Chapter Title Witness
1 OVERVIEW AND SUMMARY Shelly J. Sharp
2 COMPANYWIDE MODELS AND APPROACHES FOR ASSESSING RISK
Janaize Markland
3 COMPANYWIDE MODELS AND APPROACHES
TO RISK INFORMED BUDGET ALLOCATION Jamie L. Martin
4 ELECTRIC OPERATIONS AND NUCLEAR
POWER GENERATION Eric Back Cary D. Harbor
5 GAS OPERATIONS Christine C. Chapman
6 RISK LEXICON Janaize Markland
Appendix A STATEMENTS OF QUALIFICATIONS Eric Back
Christine C. Chapman Cary D. Harbor Janaize Markland Jamie L. Martin Shelly J. Sharp
1-i
PACIFIC GAS AND ELECTRIC COMPANY CHAPTER 1
OVERVIEW AND SUMMARY
TABLE OF CONTENTS
A. Introduction ....................................................................................................... 1-1
1. General Principles Guiding This Filing ....................................................... 1-1
a. PG&E Welcomes a Sharing of Risk Management Practices ............... 1-1
b. Cooperation Among the Parties Will Advance the Industry ................. 1-2
c. PG&E Has Focused on the Management of Safety Risks ................... 1-2
d. Uniform Standards Are Appropriate in Some Areas and Inadvisable in Others ........................................................................... 1-2
e. The S-MAP Should Not Be Assumed to Be Open-Ended.................... 1-3
2. Organization of This Testimony ................................................................. 1-3
3. Relationship of This Filing to PG&E’s Upcoming GRC............................... 1-4
4. Risk and PG&E’s Integrated Planning Process .......................................... 1-5
B. Approach to This S-MAP .................................................................................. 1-6
1. Content of This S-MAP and Future Filings ................................................. 1-7
2. The Role of Workshops .............................................................................. 1-8
3. Commission and Stakeholder Expertise .................................................. 1-10
C. Relief Requested ............................................................................................ 1-10
1-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 1 2
OVERVIEW AND SUMMARY 3
A. Introduction 4
In this proceeding, Pacific Gas and Electric Company (PG&E) provides an 5
introduction and overview of its models and methodologies used to prioritize and 6
mitigate safety risks. This proceeding—known as the Safety Model Assessment 7
Proceeding (S-MAP)—is submitted in accordance with Decision 14-12-025 of 8
the California Public Utilities Commission (CPUC or Commission). 9
1. General Principles Guiding This Filing 10
PG&E has embraced risk-informed decision-making in its planning and 11
budgeting process and fully supports the Commission’s increased focus in 12
this area. In the rapidly developing area of risk assessment and mitigation, 13
utilities will continue to identify areas of improvement for their processes.1 14
Similarly, the Commission and stakeholders may need to increase their own 15
technical capabilities for evaluating the risks facing utilities and the proposed 16
strategies for mitigating those risks. All participants in this new dialogue will 17
also need to ensure that they share a common understanding of terms. If 18
not, misunderstandings likely will ensue. 19
Utilities, the Commission and stakeholders are in this together. 20
Accordingly, PG&E has approached this proceeding with the following 21
general principles in mind. 22
a. PG&E Welcomes a Sharing of Risk Management Practices 23
PG&E welcomes a sharing of risk management practices—both 24
formally and informally—among stakeholders in California. In addition 25
to this proceeding, PG&E has reached out to other participants in the 26
State and around the country to share lessons learned. This sharing will 27
continue beyond the issues contemplated for this first S-MAP. 28
1 While PG&E provides its principal risk models and methodologies in this filing, PG&E
expects to develop additional tools, models and standards as its risk management process matures.
1-2
b. Cooperation Among the Parties Will Advance the Industry 1
In the developing area of utility risk management, cooperation 2
among the parties will best serve to advance the industry’s efforts. All of 3
the S-MAP participants have a common interest in advancing the art 4
and science of utility risk management. To that end, PG&E aims to 5
promote a cooperative atmosphere in this proceeding. The topics to be 6
covered in the S-MAP lend themselves well to workshops and 7
multimedia demonstrations, not the formality of evidentiary hearings. 8
c. PG&E Has Focused on the Management of Safety Risks 9
PG&E expects that the S-MAP—and future Risk Assessment and 10
Mitigation Proceedings’ (RAMP) and General Rate Cases’ (GRC) 11
discussion of risks—will focus primarily on key safety risks. PG&E 12
manages other important risks, such as environmental and financial 13
risks, although PG&E expects that such risks will not be the focus in the 14
S-MAP. 15
d. Uniform Standards Are Appropriate in Some Areas and Inadvisable 16
in Others 17
In the decision, the CPUC questions whether or not “uniform or 18
common standards” is a goal that should be pursued.2 Some areas 19
lend themselves well to common standards. Others do not. The former 20
category could include, for example, the development of a risk lexicon; 21
the application of a common framework—ISO 31000; and the use of a 22
common process as described in the Cycla Corporation’s (Cycla) 23
May 16, 2013 report in PG&E’s 2014 GRC.3 The latter category 24
includes algorithms and programs for addressing risk, which are likely to 25
differ from company-to-company, based on the characteristics of that 26
company’s assets, environment and customers. 27
2 D.14-12-025, mimeo, p. 30 (“The S-MAP decision can also address whether uniform or
common standards must be used by the energy utilities in the next S-MAP filings, or direct the energy utilities to pursue the issue further.”).
3 Cycla’s 10-step process is presented in Section B.1. below.
1-3
e. The S-MAP Should Not Be Assumed to Be Open-Ended 1
The decision states that the S-MAP will take place “every 2
three years…unless directed otherwise by the Commission.”4 At this 3
juncture, it would be inappropriate to assume that the number of 4
S-MAPs will be open-ended. One must be cognizant of the impacts of 5
new proceedings. Such proceedings translate to higher administrative 6
costs for the utilities and, of course, stress the limited resources of the 7
Commission and stakeholders. 8
In addition to our concerns about the number of S-MAPs going 9
forward, PG&E is equally concerned that the S-MAPs are resolved 10
timely. The Commission’s Decision 14-12-025 requires that the S-MAP 11
decision be issued prior to the first RAMP filing in order to improve the 12
incorporation of risk and safety into utility rate cases. Accordingly, 13
PG&E would like to see this proceeding move forward efficiently and 14
conclude promptly. 15
2. Organization of This Testimony 16
PG&E’s testimony is comprised of five chapters. The first two chapters 17
address enterprisewide models. In Chapter 2, PG&E presents its Enterprise 18
and Operational Risk Management Program (EORM) and Risk Evaluation 19
Tool (RET), which are used to identify and rank enterprisewide and 20
operational risks. In Chapter 3, PG&E presents its risk-informed budget 21
allocation (RIBA) process, which is used to prioritize work in the core lines of 22
business according to risk scores. Thereafter, PG&E presents line of 23
business-specific approaches to risk management. Chapter 4 presents 24
PG&E’s approach in Electric Operations and Nuclear Power Generation. 25
Chapter 5 presents PG&E’s approach in Gas Operations. Chapter 6 26
presents a risk lexicon developed in conjunction with Southern California 27
Edison Company (SCE) and the Sempra utilities (Sempra). The definitions 28
in Chapter 6 are thus jointly sponsored by SCE, Sempra and PG&E. 29
4 D.14-12-025, mimeo, p. 55 (Ordering Paragraph 5).
1-4
The testimony takes the following structure: 1
TABLE 1-1 PACIFIC GAS AND ELECTRIC COMPANY
STRUCTURE OF TESTIMONY
Chapter Title Witness
1 Overview and Summary S. Sharp
2 Companywide Models and Approaches for Assessing Risk
J. Markland
3 Companywide Models and Approaches to Risk Informed Budget Allocation
J. Martin
4 Electric Operations and Nuclear Power Generation
E. Back and C. Harbor
5 Gas Operations C. Chapman
6 Risk Lexicon J. Markland
Appendix A Statements of Qualifications All
3. Relationship of This Filing to PG&E’s Upcoming GRC 2
This S-MAP is not a formal precursor to PG&E’s 2017 GRC. (PG&E will 3
file its 2017 GRC on September 1, 2015.) PG&E’s 2020 GRC will be the 4
first PG&E GRC to incorporate the results of this S-MAP and to have a 5
formal RAMP. PG&E expects to submit the RAMP for the 2020 GRC in 6
October 2017. 7
Although the new risk proceedings instituted through 8
Decision 14-12-025 will not be fully incorporated until PG&E’s 2020 GRC, 9
PG&E will follow the spirit of Decision 14-12-025 in the preparation of its 10
2017 case. To that end, PG&E will provide more extensive testimony on 11
safety and risk and PG&E will explain how its forecast relates to safety and 12
risk priorities. The 2017 GRC testimony will also follow the Commission’s 13
directive from PG&E’s 2014 GRC, namely: 14
PG&E will provide additional testimony on its Integrated Planning 15
Process; affirmatively showing that risk management through integrated 16
planning forms the foundation of the system safety and compliance 17
projects and programs forecast in its 2017 GRC. 18
PG&E will prioritize projects and programs in the 2017 GRC by using 19
risk-based criteria and will describe how the projects and programs it is 20
1-5
forecasting mitigate the system safety risks listed on PG&E’s Risk 1
Register. 2
PG&E will provide enhanced testimony on its overall risk program from 3
its Chief Risk Officer as well as line of business-specific risk testimony 4
from the risk or asset management leads from Electric Operations, 5
Energy Supply and Gas Operations.5 6
4. Risk and PG&E’s Integrated Planning Process 7
As described above, PG&E will provide additional testimony on its 8
Integrated Planning Process in its 2017 GRC. The annual Integrated 9
Planning Process consists of four primary steps.6 The first step is 10
establishing “Executive Guidance,” where PG&E sets forth its goals for the 11
next five years. The second step is Session D—developed from January 12
through April—which is used to review and discuss progress made to 13
manage PG&E’s top compliance, enterprise and operational risks. The 14
third step in the process is Session 1—developed from April through July—15
which outlines PG&E’s 5-year Operating Plan, including goals and 16
strategies. The fourth step is Session 2—developed from August through 17
October—which sets forth PG&E’s 2-year execution plan. The Integrated 18
Planning Process is an iterative cycle and adjustments can be made to 19
PG&E’s plan to incorporate emerging information. For example, while 20
Session D reviews are completed in April, senior management—through 21
their risk and compliance committees—regularly review the status of risks 22
and mitigation activities. Additionally, the Risk Policy Committee, which is 23
chaired by the Chief Executive Officer, conducts a “mid-cycle check in” 24
where the Committee reviews progress relative to PG&E’s risk profile and 25
implementation of the EORM program. The leadership team will collectively 26
make a decision to address newly identified gaps in PG&E’s work plan if 27
warranted. 28
5 D.14-08-032, mimeo, p. 12. 6 PG&E’s Integrated Planning Process also contains an additional step, Session C, for
the Company’s senior leadership development and succession planning.
1-6
Figure 1-1 below illustrates the Integrated Planning Process cycle and 1
the key outputs of the process and the tools used in each step of the 2
process. 3 FIGURE 1-1
PACIFIC GAS AND ELECTRIC COMPANY INTEGRATED PLANNING PROCESS
B. Approach to This S-MAP 4
PG&E has approached this S-MAP in accordance with the expectations of 5
the Refined Straw Proposal, which envisioned: 6
the initial S-MAP [would] ‘serve primarily an informational and education 7 function – acquainting parties with the utilities’ models – and provide utilities 8 an opportunity to hear reactions from Commission staff and parties and 9 modify their models as they deem appropriate in response to Staff/parties’ 10 concerns and recommendations.7 11
PG&E understands that the Commission’s expectations and scope of the 12
S-MAP will change over time. Not everything can be accomplished in the first 13
S-MAP.8 14
7 D.14-12-025, mimeo, pp. 22-23. 8 D.14-12-025, mimeo, p. 26.
1-7
While the Commission considers the longer term goal of evaluating “uniform 1
and common standards,” the Commission raised three topics for consideration.9 2
First is “whether the S-MAP should be a recurring proceeding, and if so, how 3
often should that be.”10 Second is whether workshops or an S-MAP working 4
group should determine whether common standards can be developed.11 Third 5
is whether Commission staff and other parties have sufficient expertise to 6
understand and analyze the S-MAP methods and methodologies.12 7
PG&E addresses these three topics below. 8
1. Content of This S-MAP and Future Filings 9
The Commission has concluded that S-MAPs “should be held at least 10
two times, at an interval of three years.”13 And, “[i]n the second proceeding, 11
the Commission can decide whether the S-MAP proceedings should 12
continue in the future or be terminated.”14 13
PG&E has set forth a framework in Table 1-2 for the content of 14
two S-MAPs. This framework is tied to Cycla’s 10-step process reflecting 15
the elements of a risk-informed resource allocation process. Cycla 16
presented this 10-step process in PG&E’s 2014 GRC. As shown in 17
Table 1-2, PG&E proposes addressing five of the ten steps in this first 18
S-MAP and deferring two steps to the second S-MAP. (The remaining 19
three steps are already addressed in the GRC process.) PG&E would defer 20
those steps (1) pertaining to evaluating risk reduction; and (2) monitoring the 21
effectiveness of risk control measures. As explained more fully in 22
Chapter 2, Sections D.2.a. and D.3., quantifying risk reduction is in a 23
particularly early state of development. S-MAP discussions in this area 24
would benefit from additional time to mature. 25
9 D.14-12-025, mimeo, p. 26. 10 D.14-12-025, mimeo, p. 26. 11 D.14-12-025, mimeo, p. 26. 12 D.14-12-025, mimeo, pp. 26-27. 13 D.14-12-025, mimeo, p. 27. 14 D.14-12-025, mimeo, p. 27.
1-8
TABLE 1-2 PACIFIC GAS AND ELECTRIC COMPANY
CYCLA’S 10-STEP RISK PROCESS
Step Cycla Process Model/Method/Process
Proceeding Where Process Step Should
Be Addressed
1 Identify Threats EORM Program Session D – Risk RET
This First S-MAP (Chapters 2, 4, 5)
2 Characterize Sources of Risk
EORM Program Session D – Risk RET
This First S-MAP (Chapters 2, 4, 5)
3 Identify Candidate Risk Control Measures (RCM)
EORM Program Session D – Risk Session 1 – Strategy Session 2 – Execution Plan RIBA
This First S-MAP (Chapters 2, 3, 4, 5)
4 Evaluate the Anticipated Risk Reduction for Identified RCM
EORM Program Session D – Risk
Second S-MAP
5 Determine Resource Requirements for Identified RCMs
EORM Program Session 1 – Strategy Session 2 – Execution Plan RIBA
This First S-MAP (Chapters 3, 4, 5)
6 Select RCMs Considering Resource Requirements and Anticipated Risk Reduction
EORM Program Session 1 – Strategy Session 2 – Execution Plan RIBA
This First S-MAP (Chapters 3, 4, 5)
7 Determine Total Resource Requirement for Selected RCMs
EORM Program Session 1 – Strategy Session 2 – Execution Plan RIBA
General Rate Case
8 Adjust the Set of RCMs to be presented in GRC Considering Resource Constraints
EORM Program Session 1 – Strategy Session 2 – Execution Plan RIBA
General Rate Case
9 Adjust RCMs for Implementation following CPUC decision on Allowed Resources
EORM Program Session 2 – Execution Plan RIBA
General Rate Case
10 Monitor the Effectiveness of RCMs
EORM Program Session D – Risk
Second S-MAP
2. The Role of Workshops 1
On the topic of how to involve workshops in the S-MAP, the Commission 2
concluded that they “could be useful toward reaching a consensus about 3
uniform or common standards. These additional workshops or working 4
1-9
groups are something the parties and the ALJ in the S-MAP proceedings 1
should consider.”15 2
PG&E agrees that workshops would be useful. Indeed, PG&E believes 3
that workshops are likely to be more fruitful than evidentiary hearings for the 4
topics under consideration. These topics are technical and include 5
calculations, algorithms, and complex concepts. These issues are best, and 6
most easily, explored through workshop discussions, not formal 7
cross-examination. 8
For these reasons, PG&E proposes a series of workshops in lieu of 9
evidentiary hearings. These workshops should cover the following topics: 10
Risk Lexicon – this session would have the parties work together to 11
develop a risk lexicon based upon that jointly put forward by the utilities. 12
PG&E envisions that this lexicon would be an educational resource, 13
maintained by the Commission, that could be used by the Commission, 14
utilities and stakeholders. 15
Benchmarking of Utility Risk Processes – this session would examine 16
the current state of utility risk management outside of California. 17
Presentation of Utility Risk Models – this session would allow for more 18
in-depth presentations and discussions concerning the utility risk 19
models. This session could include live demonstrations of the models. 20
Data Issues – this session would address data issues such as the 21
relative value of qualitative and quantitative data, as well as the use of 22
predictive vs. lagging indicators. 23
Areas for Common Standards – this session would address the 24
Commission’s interest in exploring whether common standards would be 25
useful and have the parties work together to identify possible areas for 26
such standards. 27
If the Commission wishes to develop a record concerning these 28
workshops, PG&E would support videotaping/webcasting the workshops, 29
working with staff to develop reports, or otherwise formalizing the content of 30
the workshops. 31
15 D.14-12-025, mimeo, p. 28.
1-10
3. Commission and Stakeholder Expertise 1
PG&E is not in the best position to assess whether or not the 2
Commission and stakeholders currently have the requisite expertise to 3
review the utility models and methodologies. In the past, both Commission 4
staff and intervenors have expressed concerns about the level of their 5
expertise. To the extent that additional expertise is required, PG&E 6
supports the Commission and parties obtaining such expertise through 7
internal staff (in the long-term) or external consultants (in the short-term). 8
The more expertise at the table, the more productive this proceeding is likely 9
to be. In this regard, PG&E supported the hiring of experts by the Safety 10
and Enforcement Division during PG&E’s 2014 GRC. 11
C. Relief Requested 12
PG&E understands the main purpose of this first S-MAP proceeding to be 13
an informational and educational one.16 Accordingly, the formal relief requested 14
by PG&E is relatively limited. 15
PG&E seeks: 16
The Commission’s development of a risk lexicon based on the definitions 17
proposed herein. 18
The Commission’s guidance for the content of the next S-MAP. PG&E 19
recommends that the next S-MAP focus on: 20
– A methodology for evaluating anticipated risk reduction and monitoring 21
the effectiveness of identified risk control measures. 22
– The evaluation of common standards in areas where the Commission in 23
this S-MAP deems such standards to be advisable. 24
16 D.14-12-025, mimeo, pp. 22-23.
2-i
PACIFIC GAS AND ELECTRIC COMPANY CHAPTER 2
COMPANYWIDE MODELS AND APPROACHES FOR ASSESSING RISK
TABLE OF CONTENTS
A. Introduction ....................................................................................................... 2-1
B. EORM Program Overview ................................................................................ 2-1
1. People and Processes ............................................................................... 2-2
a. Personnel ............................................................................................ 2-2
b. Committees ......................................................................................... 2-2
c. Monitoring and Metrics ........................................................................ 2-3
2. History of the Program ............................................................................... 2-4
3. Integration With PG&E’s Planning Processes ............................................ 2-4
C. The Risk Evaluation Tool .................................................................................. 2-4
1. Purpose ...................................................................................................... 2-4
2. Evolution of the Tool .................................................................................. 2-5
3. RET2.1 ....................................................................................................... 2-6
a. Inputs ................................................................................................... 2-6
1) Risk Score ..................................................................................... 2-6
2) Risk Status .................................................................................... 2-6
b. Output .................................................................................................. 2-7
4. Illustrative Example .................................................................................... 2-8
D. Areas for Focus and Improvement ................................................................. 2-10
1. Where PG&E Is Compared to Our Peers ................................................. 2-10
2. Key Challenges ........................................................................................ 2-11
a. Risk Quantification ............................................................................. 2-11
b. Risk Tolerance ................................................................................... 2-12
3. Areas of Future Activities ......................................................................... 2-13
2-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 2 2
COMPANYWIDE MODELS AND APPROACHES FOR ASSESSING 3
RISK 4
A. Introduction 5
Pacific Gas and Electric Company’s (PG&E) goal is to deliver safe, reliable 6
and affordable gas and electric service to the millions of homes and businesses 7
that depend on us. Numerous operational risks affect the provision of gas and 8
electric service, including natural hazards such as seismic activity and wildfires. 9
Although risk cannot be eliminated, PG&E is committed to managing these risks 10
and taking all reasonable measures to provide gas and electric service to our 11
customers in a way that protects the safety of the public and our employees. 12
This chapter describes the progress PG&E has made in implementing an 13
industry-leading Enterprise and Operational Risk Management (EORM) Program 14
since 2011. It also includes a description of the EORM process, including an 15
in-depth look at PG&E’s Risk Evaluation Tool (RET) that is used to assess and 16
rank risks across PG&E. This chapter concludes with an assessment of where 17
PG&E is compared to other companies in the industry and a look at current 18
challenges and future areas for improvement. 19
B. EORM Program Overview 20
PG&E’s program is based on International Standards Organization-31000 21
principles and is squarely focused on providing an in-depth analysis of the 22
enterprise and operational risks inherent in our business, the current state of 23
controls around those risks, and the options for mitigating them further. 24
PG&E’s EORM Program includes a robust governance structure, standard 25
criteria and tools for assessing Company risks, dedicated resources within the 26
Chief Risk Officer’s (CRO) organization and within all PG&E’s lines of business 27
(LOB), defined mechanisms for cross-company collaboration, active 28
management of LOB-specific risk registers, and integration with PG&E’s 29
Integrated Planning Process. 30
2-2
1. People and Processes 1
a. Personnel 2
PG&E’s Enterprise and Operational Risk Management Department 3
resides in the Chief Risk Officer Organization and reports to the CRO. 4
The CRO reports to PG&E’s Chief Financial Officer. Led by the Director 5
of EORM and Insurance, the EORM Department: 6
Develops, implements and maintains enterprise-wide risk 7
management guidance for the business. 8
Partners with, and coaches, LOB risk managers and other key 9
individuals to help identify, evaluate and mitigate risks. 10
Provides process support, advice, and recommendations to ensure 11
effective risk management within the business. 12
Evaluates quality and tracks the implementation of mitigation 13
activities. 14
Leads the risk components (Session D as previously described in 15
Chapter 1) of PG&E’s Integrated Planning Process. 16
Each LOB also employs dedicated staff to implement the EORM 17
Program standards and procedures within their own LOB. These 18
employees are responsible for: 19
Managing the LOB’s risk register. 20
Leading risk identification and evaluation workshops within the LOB. 21
Working with subject matter experts (SME) to develop a risk 22
response strategy, including alternatives analysis. 23
Ensuring risk mitigation activities are implemented according to an 24
agreed upon schedule. 25
Developing metrics to track progress and assess the effectiveness 26
of mitigations. 27
b. Committees 28
Committees serve an important oversight role within the EORM 29
Program. At the Board of Directors, PG&E’s audit committee is 30
responsible for overseeing the EORM Program. Oversight of specific 31
enterprise-level risks are addressed by the various Board committees, 32
primarily the Nuclear, Operations and Safety Committee. Board 33
2-3
committees complete in-depth reviews of each enterprise-level risk at 1
least once every 12 months. 2
PG&E’s Risk Policy Committee, comprised of PG&E’s most senior 3
officers, annually reviews progress made by each LOB in implementing 4
the EORM Program and how PG&E’s risk profile may be changing 5
over time. 6
In addition, each LOB has its own Risk and Compliance Committee. 7
Chaired by the most senior officer of the LOB, these Risk and 8
Compliance Committees typically meet at least four times per year and 9
are responsible for overseeing EORM activities within their LOB, 10
including reviews of risk assessments and progress made in 11
implementing mitigation activities. 12
c. Monitoring and Metrics 13
Once PG&E has identified and evaluated risks, determined which 14
ones must be mitigated further, and secured the resources to do so, 15
PG&E’s standards require LOBs to monitor progress. Mitigations are 16
tracked and reported at regular LOB Risk and Compliance Committee 17
meetings and, on a quarterly basis, mitigation progress is discussed at 18
PG&E’s Business Plan Review meeting chaired by the President. If 19
mitigation plans are delayed, an action plan is created. 20
PG&E’s EORM standard includes identification of metrics to help 21
evaluate the results of mitigation plans and to detect if conditions are 22
changing in a way that would trigger a re-evaluation of the risk. These 23
metrics can help determine if the risk reduction plan has been 24
successful, or if the LOB needs to adjust its course. In many cases, 25
LOBs have developed and are monitoring these metrics. In other cases, 26
these metrics are under development or are being refined. 27
Lastly, the EORM team oversees the implementation of risk 28
response activities, and the LOBs’ implementation of the EORM process 29
to ensure that standards are adhered to and progress is being made in 30
implementing the right mitigations to reduce the risk. 31
2-4
2. History of the Program 1
After establishing the standards and procedures for implementing 2
EORM in 2011, PG&E’s Risk and Audit Organization focused on 3
implementing PG&E’s vision of data-driven, risk-based decision making to 4
support safe, reliable, and affordable electric and gas service that is 5
integrated into PG&E’s planning process and becomes the foundation for 6
our regulatory rate cases. 7
In 2012, each LOB began working with the standards and procedures 8
issued by the Chief Risk and Audit Officer and began to build LOB-specific 9
risk registers. Through this work, PG&E began to use a common risk 10
language and developed a deeper understanding of the risks PG&E faces 11
and the drivers behind them. 12
The development of formal risk registers began in 2012, although at this 13
time, the risk identification effort took place as a stand-alone process. 14
3. Integration With PG&E’s Planning Processes 15
Once risk registers were established in each LOB, the focus shifted to 16
integrating risk into how PG&E plans and prioritizes work. In 2013, PG&E 17
held its first annual Session D, which is a senior management discussion of 18
the top risks and compliance requirements facing PG&E. Session D—which 19
began as a one-day meeting and has now expanded to two days—remains 20
an annual event where the senior officers spend time discussing how top 21
risks are being managed, where collaboration across LOBs is required, and 22
where additional resources may be needed. 23
As one of the first steps in PG&E’s Integrated Planning Process, 24
Session D helps to develop an understanding of the top risks and 25
compliance requirements and that knowledge informs PG&E’s strategy and 26
execution plans. As mentioned in Chapter 1, these strategy and execution 27
plans are called Session 1 and Session 2, respectively, and are informed by 28
Session D. 29
C. The Risk Evaluation Tool 30
1. Purpose 31
Central to PG&E’s EORM Program was the development and use of 32
PG&E’s RET. The EORM team created RET as a means of facilitating an 33
2-5
apples-to-apples comparison of risks across LOBs, and to ensure that the 1
risks that rise to the top of the priority list are those that have the largest 2
potential of preventing PG&E from achieving its objective of providing safe, 3
reliable, and affordable service to its customers. RET is used to establish a 4
risk score for each risk and to establish a relative priority for discussion and 5
management purposes. The RET score is a product of the potential impact 6
and the frequency of a risk event. Each risk event is further described as a 7
SME-proposed Probable Worst Case (P95)1 scenario. 8
2. Evolution of the Tool 9
The initial RET Model (referred to as RET1) was modified in 2013 to 10
produce RET2, and again in 2014 to create what is now referred to as 11
RET2.1. The RET1 Model used a 3 × 3 matrix of high, medium, and low 12
impact vs. high, medium, and low frequency. Additionally, the RET1 13
algorithm was linear in nature and placed more emphasis on frequency than 14
impact. Given concerns about the inability to correctly predict frequency, 15
there was less confidence in the RET1 output. RET1 also resulted in 16
less-than-desired differentiation of risks. That is, many risks were high 17
impact, low frequency and occupied the same spot on the graphic output, 18
described below as a “heat map,” limiting its usefulness in identifying areas 19
of focus. 20
RET2 was developed to address these deficiencies. RET2 employed a 21
7 × 7 matrix with additional specificity included in the criteria definitions. 22
The algorithm was changed to a logarithmic scale to increase differentiation 23
between risks and provide a better view of relative priority of risks. One year 24
after implementing RET2, the EORM team revisited the definitions within the 25
impact criteria and made adjustments to the descriptions in the “Reliability” 26
impact category2 to address LOB feedback. Although relative ranking did 27
not change significantly between RET2 and RET2.1, the descriptions within 28
Reliability better resonated with the LOBs using the tool. 29
1 The P95 scenario is based on the concept of plotting a range of outcomes along a
distribution and choosing the 95th percentile event for the purposes of the risk discussion. In practice, for many risks—in the absence of quantitative support—PG&E identifies a reasonably probable worst case scenario rather than a range of outcomes.
2 The six impact categories in the RET model are described in the next section.
2-6
Additionally, RET2.1 included increased flexibility in the frequency 1
criteria. No longer are risk assessments limited to seven frequency 2
categories. If there are data to support a specific frequency, e.g., through 3
the use of probabilistic risk assessments, LOBs may use that data to 4
calculate the risk score. 5
3. RET2.1 6
a. Inputs 7
1) Risk Score 8
As mentioned above, the RET2.1 is used to establish a number, 9
called a risk score for each risk to establish relative priority for 10
discussion purposes. The RET2.1 score is a calculation based on a 11
SME discussion of the risk associated with the P95 scenario. 12
The potential impacts of the scenario across six impact categories 13
are then scored between 1 and 7 (7 being the greatest impact). 14
The six impact categories are: Safety, Environmental, Compliance, 15
Reliability, Trust and Financial. Once the impact is articulated, 16
a frequency or probability based on data and subject matter 17
expertise is assigned to each risk scenario. The algorithm 18
discussed in Attachment A is then applied to create a score 19
between 1 and 10,000. 20
2) Risk Status 21
When a risk is first identified, its status is denoted as “black” 22
indicating that a risk assessment must be completed to determine a 23
current residual risk score. During the risk assessment, the risk 24
owner will gather as much data and expertise on the subject to fully 25
characterize the risk drivers and controls and to score the risk. 26
Once the risk assessment is complete, the team determines 27
what level of control status should be recommended to the LOB 28
Risk and Compliance Committee. The following statuses are 29
available: 30
Red – controls not adequate 31
Amber – controls need strengthening 32
Green – controls are adequate 33
2-7
A risk response plan is created for a risk with Red or Amber 1
status. The response plan includes a set of mitigations based on an 2
alternatives analysis to determine the best course of action to 3
reduce the risk and strengthen controls. 4
Over time, risk scores tend to be more static than the risk 5
status. The risk status should change toward green as the 6
mitigations are implemented and the controls are strengthened to an 7
adequate level. The risk score will only change if mitigations 8
fundamentally adjust the impact or frequency levels. In other words, 9
impact scores may change only if mitigations can physically prevent 10
or reduce the impact of the P95 scenario. 11
For example, if the P95 scenario risk is “a car accident which 12
may result in a death,” a mitigant such as a physical divider between 13
the lanes could change the worst case probable P95 scenario from 14
fatality (head-on collision), to “a car accident which may result in a 15
serious injury (i.e., hitting the divider).” This will drop the impact 16
score and, likely the frequency as well. However, physical mitigants 17
are not always possible or practical. More often, mitigations are 18
more likely to impact the frequency side of the equation. For 19
instance, if a substation were to fail catastrophically, the impact 20
always would likely be catastrophic. But it may be possible to make 21
catastrophic failure less likely to occur by addressing the drivers of 22
the risk by maintaining, inspecting and replacing equipment, and 23
installing physical and cyber security measures. 24
b. Output 25
The output of RET 2.1 is a risk score for each risk. These scores 26
can be mapped on a “heat map” that graphically portrays the frequency 27
and impact scores. An illustrative heat map is shown in Figure 2-1. 28
2-8
FIGURE 2-1 PACIFIC GAS AND ELECTRIC COMPANY
ILLUSTRATIVE HEAT MAP
The y-axis on the heat map represents the frequency score, while 1
the x-axis represents the impact score. The upper right hand corner of 2
the heat map represents the highest risks; the lower left hand corner 3
represents the lowest risks. 4
Because each LOB calculates its own risk scores, LOBs participate 5
in calibration sessions to ensure consistency in scoring. SMEs and risk 6
managers calibrate risks internal to their LOB and then the EORM team 7
facilitates cross-LOB calibration sessions to ensure risks from different 8
parts of the business are evaluated consistently. During each of these 9
sessions, participants challenge assumptions and other inputs to risk 10
scores to ensure there is alignment in how risks were evaluated. Once 11
the calibration is complete, top risks to PG&E are selected for 12
discussion in PG&E’s Session D meeting. 13
4. Illustrative Example 14
An example helps to illustrate how RET 2.1is used to create a risk score 15
from a risk assessment. Consider the risk of “Failure of Distribution 16
Overhead Primary Conductor,” defined as: 17
2-9
The failure of or contact with energized electric distribution primary 1 conductor may result in public or employee safety issues, significant 2 environmental damage (fire), prolonged outages, or significant property 3 damage. Energized wires down events are also considered part of this 4 risk. 5
In this case, the P95 scenario is described as: A fatality due to 6
unintentional third-party tree worker contact with an in place conductor, in 7
conjunction with an investigation that finds compliance violations such as 8
lack of signage, or insufficient clearance. 9
Once defined, the risk assessment team scores the risk by determining 10
the impacts across the six impact categories (see Attachment B) and the 11
frequency of such an event, and captures those determinations in the RET. 12
In this case, the following scores were assigned: 13
Safety impact: A 6 (Severe) impact captures the potential for a fatality 14
to occur if contact was made with a distribution conductor. This is based 15
on industry data and experience. 16
Environmental impact: Under the scenario, there would be a 17
1 (Negligible) impact on the environment. 18
Compliance impact: The scenario assumes a compliance violation, 19
which was rated as a 3 (Moderate) impact by the team based on 20
industry experience. 21
Reliability impact: The team reviewed outage history that would occur 22
relative to the incident and determined that a 3 (Moderate) impact 23
described the potential impact. 24
Trust impact: The team determined a 2 (Minor) impact believing that 25
there may be a single report of the event in a media outlet near the 26
location of the incident, were it to occur. 27
Financial impact: Available data supports a 4 (Major) impact. 28
Finally the team reviewed the scenario, the impact scores, and the data 29
around the drivers and controls and determined that a frequency level of 5, 30
or once every one to three years, was appropriate. 31
The six impact scores and the frequency level are then input into the 32
tool, producing a final risk score of 408. The results of the scoring of the 33
Overhead Conductor Risk can be displayed on the heat maps as shown. 34
2-10
FIGURE 2-2 PACIFIC GAS AND ELECTRIC COMPANY
MAPPED RISK SCORE FOR OVERHEAD CONDUCTOR
D. Areas for Focus and Improvement 1
1. Where PG&E Is Compared to Our Peers 2
Informed by industry benchmarking studies, the recommendations of the 3
Independent Review Panel, and a third-party consultant, PG&E has moved 4
from having an “industry standard” enterprise risk management program to 5
having an “industry-leading” EORM Program. PG&E’s EORM Program is 6
leading as evidenced by the risk-informed process of integrated planning 7
and the widespread support for risk management in terms of personnel and 8
management attention. Senior management regularly engages in 9
discussions about risk, the state of controls and mitigation plans, and has 10
increased the focus on developing and monitoring key measures that 11
provide insight into how risks are being managed. 12
Today, PG&E is in a position where each LOB knows and understands 13
the risks associated with their business and the relative importance of those 14
risks with respect to the potential impact they could have on the 15
achievement of objectives. And the LOBs use this information to inform 16
strategies and resource allocation. 17
PG&E is proud of where it is today in terms of risk management. That is 18
not to say there is no room for improvement. 19
Distribution Overhead Conductor Primary
2-11
2. Key Challenges 1
Effective risk management is an iterative process. As new data 2
becomes available, operating and environmental conditions change, and 3
technology improves, so does PG&E’s ability to identify, evaluate, prioritize 4
and mitigate risks. As does PG&E’s ability to dedicate the appropriate 5
amount of resources to manage our most important risks and to 6
demonstrate the risk reduction benefits of the investments PG&E is making. 7
As PG&E identifies and integrates new data sources, it will develop a 8
deeper, more granular understanding of the risks it faces and will be able to 9
make better decisions as a result. When new information becomes 10
available, risk management priorities may shift over time and it is important 11
that PG&E remains dynamic in its response to that new information. 12
This means that changes will be made to PG&E’s plans and it will deploy 13
resources accordingly. PG&E will identify risk mitigations that do not have 14
the intended effect and will have to change course. PG&E will also identify 15
new risks. As new information becomes available, risks that PG&E thought 16
were important, may take a back seat to other, more pressing risks. PG&E’s 17
focus on data-driven decision making combined with the ability to pivot to 18
address mitigation needs in a timely manner, will help PG&E operate in a 19
safer and more efficient manner to the benefit of PG&E’s customers, 20
employees and the public. 21
a. Risk Quantification 22
As PG&E’s EORM process has matured and progress has started to 23
be documented, there has been an increased focus on data and 24
quantification of risk to answer two basic questions: (1) Are we making 25
progress in managing risk; and (2) How do we know? 26
In 2014, the EORM team in the Risk and Audit Organization 27
implemented a risk management database to provide better oversight of 28
risk management activities. Risk managers in each of the LOBs began 29
identifying data needs and fulfilling them by gathering information from 30
PG&E and industry sources, and analyzing it to better understand risks. 31
The outcome of that work has been the development of metrics to track 32
and manage risks. The availability of relevant data remains a challenge, 33
however. 34
2-12
Often, it is not possible to tie mitigations directly to the absence of a 1
risk event. For example, PG&E has invested in a number of activities to 2
educate the public about the dangers of contact with energized 3
conductors—a top public safety risk included on the Electric Operations 4
Risk Register. It is very difficult to prove that someone did not touch an 5
energized conductor because they heard an advertisement on the radio, 6
or paid attention to a mobile pop-up advertisement while they were 7
shopping at Home Depot, or were already aware of the danger. 8
In some cases, data can be obtained to confirm that mitigations are 9
effective, but often PG&E must rely on the fact that it went through a 10
reasonable process to identify the right things to do and PG&E may not 11
be able to determine the effectiveness of an individual mitigation. 12
PG&E’s goal remains to achieve the vision of data-driven, 13
risk-based decision making to support safe, reliable, and affordable 14
electric and gas service that is integrated into our planning process and 15
becomes the foundation for our rate cases. With the core foundational 16
components of an industry leading EORM program now in place, PG&E 17
is working on refining its approach and improving the maturity of the 18
process, with a focus on data and its application within EORM. 19
b. Risk Tolerance 20
Risk cannot be completely driven out of PG&E’s—or any—business. 21
Today, risk tolerance is implicitly defined by the resources allocated to 22
manage specific risks. For example, PG&E has a robust program to 23
manage Wildfire Risk that consists of an award-winning vegetation 24
management program, equipment retrofits in high-risk areas, and 25
enhanced inspections. As a result, tree-related outages are in the 26
neighborhood of 17 per 1,000 miles, < 0.02 percent of trees in contact, 27
and there are a small number of wildfires caused by PG&E equipment 28
each year. It may be possible to drive tree-related outages to less 29
than 17 per 1,000 miles, or to have less than 0.02 percent of trees in 30
contact, but that would require a level of investment greater than what 31
PG&E is making today. With limited resources—PG&E cannot do 32
everything and must decide at what point it is okay to not mitigate the 33
risk further—tradeoff decisions must be made. For example, additional 34
2-13
investment in managing wildfire risk requires that customers either pay 1
more, or accept higher risk in another area. PG&E is using the EORM 2
process to help decide where to dedicate additional resources, and 3
specifically where it has determined the risk has a current residual risk 4
that is higher than desired. PG&E’s Risk Informed Budget Allocation 5
process, described in Chapter 3, also helps direct resources to projects 6
and programs that have the largest risk reduction impact. 7
In the 2017 General Rate Case showing, PG&E will illustrate the 8
projects and programs intended to address key risks in each operational 9
LOB. By showing how these activities for which PG&E is requesting 10
funding relate to risk reduction, intervenors and other stakeholders can 11
see what risks are affected when reductions in specific programs or 12
elimination of specific projects are recommended. As a result of this 13
discussion, the Commission, intervenors, and PG&E will together define 14
risk tolerance for PG&E. 15
3. Areas of Future Activities 16
PG&E’s EORM focus for the foreseeable future can be broadly 17
categorized as “Continuous Improvement.” PG&E is focused on refining our 18
current processes and improving the specific mechanics of risk 19
management, i.e., how PG&E measures risk, the analysis PG&E does 20
around alternatives for mitigation, and how PG&E calculates progress in risk 21
management through the use of effectiveness metrics. 22
The EORM team also will continue to work with the LOBs to: 23
Develop data plans for top risks, identifying what data PG&E needs, 24
what data it has, and how to fill the gaps. 25
Improve existing guidance and support for alternatives analysis and 26
documenting decisions related to mitigation activities. 27
Develop more effectiveness metrics that measure the impact of 28
mitigation activities on risks or drivers of risk, and those that provide 29
insight into how a risk is performing over time, i.e., is the risk increasing 30
or decreasing? 31
With the basic elements of industry-leading risk management now in 32
place, PG&E’s focus is on collectively “upping our game” in the area of risk 33
management. In support of this, the EORM team will continue to sponsor 34
2-14
expert training on specific risk management topics (annual training that is 1
provided to all risk managers across PG&E); conduct benchmarking and 2
share best practices from internal and external sources across LOBs; and 3
continue to promote a risk-aware culture through the continued inclusion of 4
risk in our Integrated Planning Process. 5
In the coming years, PG&E will consider analytical approaches for 6
quantifying risk reduction (meaning a reduction to the RET risk score). 7
To do so will require appropriate data, perhaps over an extended period of 8
time. This data will need to address (or avoid) the causation challenges 9
described above. Based on the outcome of this effort, PG&E hopes to 10
identify and implement techniques for quantifying risk reduction and their 11
applicability to specific risks. 12
2-AtchA-1
CHAPTER 2 ATTACHMENT A
RISK EVALUATION TOOL (RET) ALGORITHM
The algorithm used to calculate the risk score for each P95 risk scenario is
divided into two parts. The first part assesses how often a risk event occurs (frequency). The second part assesses the significance of the overall impact of
each risk event. The overall impact is the log of the resulting product of the
weighted impact scores in the six categories: Safety; Environmental; Compliance; Reliability; Trust; and Financial.
The risk score is expressed by the following equation in the figure below,
where f(Event) represents the frequency component of the algorithm and I(Event) represents the impact component:
RISK SCORE ALGORITHM
The risk score calculation enables risk managers to calculate the “net risk
impact” over a range of potential outcomes that occur at different frequencies.
For example, gas leaks of various grades occur at various frequencies, and some of those leaks – if left unaddressed – could cause a range of impacts
ranging from negligible to potentially catastrophic. The calculation enables risk
managers to take that data and generate a risk score that contemplates the probable worst case, or a 95th percentile event.
“k” is a scalar used to calibrate the risk scores to cover a range of 1
to 10,000 to create adequate separation between risks for the purposes of facilitating a management discussion.
Where f is the number of occurrences expected over a one-year time horizon
And I is the weighted impact of the event
And k is the scalar and is a fixed value of 3.16 (the square root of 10)
And 0.5 s a standard factor used to calculate the variance of the aggregate impact of uncorrelated events.
RS(Event)
= k
[0.5 Log ( f(Event)
) + I(Event)
]
2-AtchA-2
PG&E has mapped the six categories to our goals of safe, reliable and
affordable service, and weighted them, as follows:
GOAL MAPPING TO RET IMPACT CATEGORIES
Company Goal Company Goal
Weight (%) RET Impact Categories
RET Category Weight (%)
Safe 40%
Safety 30%
Environmental 5
Compliance 5
Reliable 30 Reliability 25
Trust 5
Affordable 30 Financial 30
Total 100% 100%
The weighting shown above places more importance on certain objectives over others. To balance the importance of the weighting and the magnitude of
the impact, the weightings are applied at the magnitude level (10 I) of the impact
groups. Therefore, I(Event) can be expressed as shown in the figure below:
IMPACT WEIGHTING
Where
Ij (Safety, Environmental, Reliability, Financial, Reputation, Compliance) is the impact level of an impact group of an event
And
Wj (Safety, Environmental, Reliability, Financial, Reputation, Compliance) is the weight
applied to the impact group of an event
I(Event)
= Log ( )
CHAPTER 2 ATTACHMENT B
RISK ASSESSMENT CATEGORIES
FREQUENCY DESCRIPTIONS
Frequency Level Frequency Description Frequency per Year
Common (7)
> 10 times per year F = > 10
Regular (6)
1-10 times per year F = 1 – 10
Frequent (5)
Once every 1-3 years F = 1 - 0.3
Occasional (4)
Once every 3-10 years F = 0.3 - 0.1
Infrequent (3)
Once every 10-30 years F = 0.1 - 0.033
Rare (2)
Once every 30-100 years F = 0.033 - 0.01
Remote (1)
Once every 100 + years F = <0.01
SAFETY IMPACT DESCRIPTIONS
Impact Level Description
Catastrophic (7)
Fatalities: Many fatalities and life threatening injuries to the public or employees.
Severe (6)
Fatalities: Few fatalities and life threatening injuries to the public or employees.
Extensive (5)
Permanent/Serious Injuries or Illnesses: Many serious injuries or illnesses to the public or employees.
Major (4)
Permanent/Serious Injuries or Illnesses: Few serious injuries or illnesses to the public or employees.
Moderate (3)
Minor Injuries or illnesses: Minor injuries or illnesses to many public members or employees.
Minor (2)
Minor Injuries or illnesses: Minor injuries or illnesses to few public members or employees.
Negligible (1)
No injury or illness or up to an un-reported negligible injury.
2-AtchB-1
ENVIORNMENTAL IMPACT DESCRIPTIONS
Impact Level Description
Catastrophic (7)
Duration: Permanent or long-term damage greater than 100 years; or
Hazard Level/Toxicity: Release of toxic material with immediate, acute and irreversible impacts to surrounding environment; or
Location: Event causes destruction of a place of international cultural significance; or
Size: Event results in extinction of a species.
Severe (6)
Duration: Long-term damage between 11 years and 100 years; or
Hazard Level/Toxicity: Release of toxic material with acute and long-term impacts to surrounding environment; or
Location: Event causes destruction of a place of national cultural significance; or
Size: Event results in elimination of a significant population of a protected species.
Extensive (5)
Duration: Medium-term damage between 2 and 10 years; or
Hazard Level/Toxicity: Release of toxic material with a significant threat to the environment and/or release with medium-term reversible impact; or
Location: Event causes destruction of a place of regional cultural significance; or
Size: Event results in harm to multiple individuals of a protected species.
Major (4)
Duration: Short-term damage of up to 2 years; or
Hazard Level/Toxicity: Release of material with a significant threat to the environment and/or release with short-term reversible impact; or
Location: Event causes destruction of an individual cultural site; or
Size: Event results in harm to a single individual of a protected species.
Moderate (3)
Duration: Short-term damage of a few months; or
Hazard Level/Toxicity: Release of material with a moderate threat to the environment and/or release with short-term reversible impact; or
Location: Event causes damage to an individual cultural site; or
Size: Event results in damage to the known habitat of a protected species.
Minor (2)
Duration: Immediately correctable; or contained within a small area.
Negligible (1)
Negligible to no damage to the environment.
2-AtchB-2
COMPLIANCE IMPACT DESCRIPTIONS
Impact Level Description
Catastrophic (7)
Adverse Regulatory Actions: Action resulting in closure, split, or sale of PG&E.
Severe (6)
Adverse Regulatory Actions: Cease and desist orders are delivered by regulators. Critical assets and facilities are forced by regulators to be shutdown.
Extensive (5)
Adverse Regulatory Actions: Governmental, regulator investigations, and enforcement actions, lasting longer than a year. Violations that result in multiple large non-financial sanctions; or
Increased Regulatory Oversight: Regulators force the removal and replacement of management positions. Regulators begin Company monitoring activities.
Major (4)
Adverse Regulatory Actions: Violations that result in significant fines or penalties above and beyond what is codified or a regulator enforces non-financial sanctions; or
Expanded Regulations: Significant new and updated regulations are enacted as a result of an event
Moderate (3)
Adverse Regulatory Actions: Violations that result in fines or penalties
Minor (2)
Adverse Regulatory Actions: Self-reported or regulator identified violations with no fines or penalties.
Negligible (1)
No compliance impact up to an administrative impact.
2-AtchB-3
RELIABILITY IMPACT DESCRPTIONS
Impact Level Description
Catastrophic (7)
Location: Impacts an entire metropolitan area, including critical customers, or is systemwide; and
Duration: Disruption of service of more than a year due to a permanent loss to a nuclear facility, hydro facility, critical gas or electric asset; or
Customer Impact: Unplanned outage (net of replacement) impacts more than 1 million customers; or
EO: 14 million total customer hours, or more than 1 million mega-watt hours (MWh) total load
GO: 10 million total customer hours, or reduction of capacity greater than or equal to 2.1 Bcf/d for seven months
ES: 40 percent of utility-owned generating fleet unavailable for one year
Severe (6)
Location: Impacts multiple critical locations and critical customers; or
Duration: Substantial disruption of service greater than 100 days; or
Customer Impact: Unplanned outage (net of replacement) impacts more than 100k customers; or
EO: 1.2 million total customer hours, or more than 100 thousand MWh total load
GO: one million total customer hours, or reduction of capacity greater than 1.2 billion cubic feet per day (Bcf/d), but less than for seven months
ES: 20 percent of utility-owned generating fleet unavailable for one year
Extensive (5)
Location: Impacts multiple critical locations or customers; or
Duration: Disruption of service greater than 10 days; or
Customer Impact: Unplanned outage (net of replacement) impacts more than 10k customers; or
EO: 100 thousand total customer hours, or more than 10 thousand MWh total load;
GO: 100 thousand total customer hours, or reduction of capacity greater than or equal to 0.6 Bcf/d for seven months
ES: 10 percent of utility-owned generating fleet unavailable for one year
Major (4)
Location: Impacts a single critical location; or
Duration: Disruption of service greater than one day; or
Customer Impact: Unplanned outage (net of replacement) impacts more than one thousand customers; or
EO: 8 thousand total customer hours, or more than one thousand MWh total load
GO: 10 thousand total customer hours, or reduction of capacity greater than or equal to 0.3 Bcf/d for seven months
ES: 2 percent of utility-owned generating fleet unavailable for one year
2-AtchB-4
RELIABILITY IMPACT DESCRIPTIONS (CONTINUED)
Moderate (3)
Location: Impacts a small area with no disruption of service to critical locations; or
Duration: Disruption of service of up to one full day; or
Customer Impact: Unplanned outage (net of replacement) impacts more than 100 customers; or
EO: 600 total customer hours, or more than 100 MWh total load
GO: one thousand total customer hours, or reduction of capacity greater than or equal to 0.1 Bcf/d for seven months
ES: one percent of utility-owned generating fleet unavailable for one year
Minor (2)
Location: Impacts a small localized area with no disruption of service to critical locations; or
Duration: Disruption of up to three hours; or
Customer Impact: Unplanned outage (net of replacement) impacts less than 100 customers; or
EO: Less than 600 total customer hours, or less than 100 MWh total load;
GO: Less than one thousand total customer hours, or reduction of capacity greater than or equal to 0.01 Bcf/d for seven months
ES: 0.1 percent of utility-owned generating fleet unavailable for one year
Negligible (1)
No reliability to negligible impacts.
2-AtchB-5
TRUST IMPACT DESCRIPTIONS
Impact Level Description
Catastrophic (7)
Duration: Ongoing impacts for more than 10 years; and
Media: Event is heavily reported from local through international media outlets and social media channels, with influential third parties dominating media coverage; various inaccurate information is widely reported; or
Political: Devastating nationwide broad-based political pressure demanding intense long term outreach to policymakers and key stakeholders; or
Customer Satisfaction: Greater than 50 percent loss of customer satisfaction through survey results; or
Company Brand: Relationships are severed and trust is completely lost
Severe (6)
Duration: Ongoing impacts between 1 and 10 years; and
Media: Event is heavily reported from local through national media outlets and social media channels, with influential third parties dominating media coverage, and various inaccurate information is widely reported; or
Political: Extreme statewide broad-based political pressure demanding concentrated outreach to policymakers and key stakeholders; or
Customer Satisfaction: 21-50 percent loss of customer satisfaction through survey results; or
Company Brand: Event creates outrage and trust can't be fully recovered
Extensive (5)
Duration: Ongoing impacts between one quarter and one year; or
Media: Event is widely reported in national media outlets and social media channels, with influential third parties dominating media coverage, and inaccurate information is reported; or
Political: Severe territory wide political pressure demanding extensive outreach to policymakers and key stakeholders; or
Customer Satisfaction: 4-20 percent loss of customer satisfaction through survey results; or
Company Brand: Event creates serious concerns of company management while trust is severely diminished
Major (4)
Duration: Ongoing impacts between one week and one quarter; or
Media: Event is heavily reported in local through national media outlets and social media channels, with influential third parties dominating media coverage, and inaccurate information is reported; or
Political: Major territory wide political pressure demanding major outreach to policymakers and key stakeholders; or
Customer Satisfaction: one to three percent loss of customer satisfaction through survey results; or
Company Brand: Management is questioned and trust is diminished
2-AtchB-6
TRUST IMPACT DESCRIPTIONS (CONTINUED)
Moderate (3)
Duration: Short term coverage for up to one week.
Media: Event is reported in multiple local media outlets and/or social media channels, with limited exposure beyond the coverage area; or
Political: Moderate county level political pressure demanding moderate outreach to policymakers and key stakeholders; or
Customer Satisfaction: Less than one percent loss of customer satisfaction through survey results; or Company Brand: Event isn’t anticipated and trust is impacted; or
Minor (2)
Duration: Single report of the event.
Media: Event is reported in a single local media outlet in the location where the event took place; or
Political: Minimal political pressure demanding minimal outreach to policymakers and key stakeholders; or
Negligible (1)
No known reputation impact reported to a non-featured report.
2-AtchB-7
FINANCIAL IMPACT DESCRIPTIONS
Impact Level Description
Catastrophic (7)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact > $5 billion in costs; or
Capital/Liquidity: Ability to raise capital significantly impacted. Dramatic decrease in stock price of more than 50 percent for more than one year; or
Bankruptcy: Risk of bankruptcy is imminent.
Severe (6)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact between $500 million and $5 billion in costs; or
Capital/Liquidity: Ability to raise capital is challenged. Dramatic decrease in stock price of more than 25 percent for more than one year.
Extensive (5)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact between $50 million and $500 million in costs; or
Capital/Liquidity: Ability to raise capital is hindered. Dramatic decrease in stock price of more than 10 percent for up to one year.
Major (4)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact between $5 million and $50 million in costs.
Moderate (3)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact between $500 thousand and $5 million in costs.
Minor (2)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact between $50 thousand and $500 thousand in costs.
Negligible (1)
Financial Costs: Damage to third-party properties, loss of assets and facilities, fines, lawsuits, restitution, remediation, restoration, cost of replacement energy, redistributed customer costs, amounting to a total impact of less than $50 thousand in costs.
2-AtchB-8
PACIFIC GAS AND ELECTRIC COMPANY
CHAPTER 3
COMPANYWIDE MODELS AND APPROACHES TO RISK
INFORMED BUDGET ALLOCATION
3-i
PACIFIC GAS AND ELECTRIC COMPANY CHAPTER 3
COMPANYWIDE MODELS AND APPROACHES TO RISK INFORMED BUDGET ALLOCATION
TABLE OF CONTENTS
A. Overview .......................................................................................................... 3-1
B. PG&E’s Risk Informed Budget Allocation Process ........................................... 3-1
1. Purpose ...................................................................................................... 3-1
2. Approach and Methodologies .................................................................... 3-1
a. Personnel ............................................................................................ 3-1
b. Committees ......................................................................................... 3-2
c. Processes and Timing ......................................................................... 3-2
3. The Model .................................................................................................. 3-3
a. Inputs ................................................................................................... 3-4
b. Outputs ................................................................................................ 3-5
4. Illustrative Examples .................................................................................. 3-6
C. Areas of Focus and Improvement..................................................................... 3-8
3-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 3 2
COMPANYWIDE MODELS AND APPROACHES TO RISK 3
INFORMED BUDGET ALLOCATION 4
A. Overview 5
Pacific Gas and Electric Company (PG&E) uses a Risk Informed Budget 6
Allocation (RIBA) process to inform the prioritization of budget for risk mitigation 7
measures and other work in its portfolio. More specifically, the RIBA process 8
provides scores for projects and programs by evaluating the worst reasonable 9
direct impact (WRDI) of not performing the work. The RIBA process is used for 10
capital and expense projects and programs in Electric Transmission, Electric 11
Distribution, Power Generation, Gas Operations, and Diablo Canyon Power 12
Plant, and is not currently used in other parts of the company. RIBA is an 13
integral part of the Integrated Planning Process, and is also used throughout the 14
year when budget tradeoff decisions are required due to changing 15
circumstances. 16
B. PG&E’s Risk Informed Budget Allocation Process 17
1. Purpose 18
RIBA’s purpose is to provide a framework for making risk-informed 19
budget decisions by risk scoring and categorizing proposed projects and 20
programs in the operational lines of business (LOBs) capital and expense 21
portfolios. These scores and categories provide data that are used in 22
PG&E’s Integrated Planning Process described in Chapter 1. The outputs 23
of the process, the RIBA graphs,1 are used during prioritization discussions 24
within and across the LOBs. 25
2. Approach and Methodologies 26
a. Personnel 27
PG&E’s Finance Department is responsible for: (i) maintaining the 28
RIBA scoring model; (ii) leading the RIBA working group (discussed 29
1 PG&E has included an illustrative RIBA graph in Section B.3.b. of this chapter.
3-2
below); (iii) promoting consistent use of the RIBA process across the 1
LOBs; and (iv) incorporating the RIBA output into PG&E’s Integrated 2
Planning Process. The personnel within PG&E’s Finance Department 3
responsible for the RIBA process report to the Director of Economic and 4
Project Analysis, who reports to the Vice President of Finance. 5
b. Committees 6
The RIBA team leads a RIBA working group that is comprised of 7
representatives from Finance, Risk Management, Electric Operations, 8
Gas Operations, and Nuclear Power Generation. The working group 9
has a variety of responsibilities. It defines the scoring methodology and 10
the risk and categorization flag taxonomies.2 It resolves issues relating 11
to consistency across the participating LOBs. The RIBA team also 12
works closely with PG&E’s Enterprise and Operational Risk 13
Management (EORM) Program discussed in Chapter 2. 14
c. Processes and Timing 15
The RIBA cycle begins around April of each year after the 16
conclusion of Session D in PG&E’s Integrated Planning Process. At that 17
point, investment planning teams within the LOBs develop a list of 18
proposed projects and programs to meet the Company’s strategies and 19
goals. These projects and programs will include the risk control 20
measures and mitigations identified in Session D. New projects and 21
programs are risk scored by asset owners, engineers, project and 22
program managers, and other subject matter experts (SME), and 23
existing scores are reviewed to ensure they reflect current conditions. 24
After the projects are scored, the RIBA team holds calibration sessions 25
to promote consistent use of the risk criteria and categorization flags 26
across the participating LOBs. These calibration sessions are attended 27
by representatives from Finance, Risk Management, and the 28
participating LOBs. 29
The calibration sessions are typically held in June prior to submittal 30
of the LOB Session 1 material. RIBA stacked graphs and detailed risk 31
2 Categorization flags are described in Section 3.a. below and Attachment B.
3-3
information about projects and programs are submitted to Finance in 1
late July, to support Session 1 prioritization discussions. It is during 2
these prioritization discussions when resource and other constraints 3
may drive adjustments to the proposed work portfolios of the LOBs. 4
Additional calibration sessions—if required—would be held in August, 5
and updated RIBA output would be submitted to Finance prior to 6
Session 2 prioritization discussions, which are held in early October. 7
Final budget letters3 are usually sent to the LOBs in late November for 8
the upcoming year. RIBA scores and categorizations are used 9
throughout the year when budget trade-off decisions are required by 10
changing circumstances. 11
FIGURE 3-1 PACIFIC GAS AND ELECTRIC COMPANY
PLANNING TIMELINE
3. The Model 12
RIBA scores are calculated in an Excel model. The template for the 13
model is maintained by PG&E’s Finance Department. Capital and expense 14
projects and programs are risk scored based on the impact of the work on 15
safety, reliability, and the environment. Work is also categorized based on 16
compliance requirements, commitments and other considerations such as 17
whether a project is in flight or is related to another project. For example, 18
3 Budget letters are formal notifications to each of the LOBs, typically distributed in
November, that set expense and capital targets for the following year.
3-4
related projects may be flagged together if it is prudent to complete such 1
projects during the same plant outage or electric transmission clearance. 2
a. Inputs 3
The first step in risk scoring is to determine the WRDI of not 4
performing the work. As in the RET2.1 model, the risk scores are based 5
on the impact and likelihood of occurrence. The safety, environmental, 6
and reliability impact and frequency scores are assigned based on the 7
scoring taxonomy shown in Attachment A, and are summarized below, 8
with 1 being negligible impact and 7 being catastrophic: 9
Range Summary
Safety 7. Many fatalities and life threatening injuries to the public or employees.
1. No injury or illness or up to an un-reported negligible injury.
Environmental 7. Permanent or long-term damage greater than 100 years.
1. Negligible to no damage to the environment.
Reliability 7. Impacts an entire metropolitan area, including critical customers, or is systemwide.
1. Negligible to no reliability impacts.
Frequency 7. Imminent or already failed.
1. Once every 100+ years.
The process is as follows: 10
1. Use the prescribed 1-7 scoring scale to determine the WRDI on 11
safety, reliability, and the environment of not doing the work; the 12
model provides fields to enter each score and fields to enter notes to 13
support the chosen score. 14
2. Use the prescribed 1-7 scoring scale to estimate the timing or 15
frequency of these WRDI; enter the score and notes in the model. 16
3. Review and flag each proposed work item to reflect other non-risk 17
drivers of the work. Required work categories are Mandatory, 18
Compliance, Work Requested by Others (WRO), or Commitment. 19
Additionally, all work may be flagged as In-Flight, Financial Benefits, 20
Capacity, Inter-Relationship with other projects, and/or Support. 21
These flags provide additional information that informs budget 22
3-5
decisions, as they identify key business reasons for performing the 1
work.4 2
b. Outputs 3
Using the algorithm discussed in Attachment C, the output of the 4
RIBA process is a risk scored portfolio that can be sorted in multiple 5
ways (by flag, risk score, safety score, etc.) The results are also 6
presented to management graphically. A simulated graph for illustrative 7
purposes is shown below. 8
FIGURE 3-3 PACIFIC GAS AND ELECTRIC COMPANY
ILLUSTRATIVE RIBA GRAPH
4 See Attachment B, Flag Taxonomy, for a complete definition of the work categorization
flags.
3-6
Dollars are shown on the x-axis and the RIBA score is shown on the 1
y-axis, thus the width of the bar represents the proposed budget, and its 2
height represents the RIBA score. The color of each bar represents the 3
categorization of the work. The Mandatory, WRO, Compliance, and 4
Commitment flags are mutually exclusive and designed to capture all 5
required work. Any work assigned one of those flags would be graphed 6
as such. The other flags are not mutually exclusive, and multiple flags 7
may be assigned to non-required work. The LOBs can choose which 8
flags to identify for purposes of generating a RIBA graph. Similar 9
graphs can be generated that are sorted by risk score, program, or other 10
means. 11
4. Illustrative Examples 12
The following projects illustrate the RIBA data and scoring of 13
two projects associated with overhead conductor risk mitigation. The text is 14
paraphrased from a RIBA scoring template submitted to Finance by Electric 15
Operations. The scoring was done by SMEs in Electric Operations. 16
The purpose of the first project is to reconductor 1,440 circuit feet of 17
copper conductor due to the number of splices on the line.5 18
Safety: This project received a Safety Impact Score of 6 and a Safety 19
Frequency Score of 1. This was based on the possibility of a fatality as a 20
result of the public contacting down overhead primary conductor. The 21
conductor is located across the street from a public school. Historical data 22
indicates 0.79 fatalities per year associated with the public contacting a 23
down overhead primary conductor. PG&E estimates that 2,700 wire-down 24
events will occur annually. The frequency of a fatal event is therefore 25
0.0003 (0.79/2,700) which translates to a frequency score of 1. These 26
assumptions provide an overall Safety Risk Score of 178. 27
Environment: This project received an Environmental Impact Score of 1 28
and an Environmental Frequency Score of 1. This was based on the 29
location of the line in an urban neighborhood, across the street from a public 30
5 Internally, the project is called “MADERA 1104 ‒ RECONDUCTOR SUNSET AVE.”
3-7
school. These assumptions provide an overall Environmental Risk Score 1
of 1. 2
Reliability: This project received a Reliability Impact Score of 4 and a 3
Reliability Frequency Score of 6. This was because these broken wires 4
would lead to 3,161 Customers Experiencing a Sustained Outage (CESO) 5
(CESO = 3,161, duration 6 + hours), impacts a middle school, and there 6
have been four wires down outages on this line in the last three years. 7
These assumptions provide an overall Reliability Risk Score of 178. 8
Total Risk Score: Summing the Safety, Environmental and Reliability 9
Risk Scores gives a Total Risk Score for this Project of 357. 10
In terms of “flags,” this project is not a required project, so in a RIBA 11
graph it would appear within the discretionary work as No Flag showing an 12
overall risk score of 357. 13
The purpose of the second project is to reconductor 200 circuit feet of 14
Aluminum Conductor Steel Reinforced overhead conductor with Aluminum 15
conductor and install two overhead cutouts.6 This work will provide higher 16
reliability and operational flexibility on the Tidewater 2107 circuit and will 17
reduce the likelihood of a wire-down event. 18
Safety: This project received a Safety Impact Score of 6 and a Safety 19
Frequency Score of 1, using the same scoring assumptions described for 20
the first project. These assumptions provide an overall Safety Risk Score 21
of 178. 22
Environment: This project received an Environmental Impact Score of 1 23
and an Environmental Frequency Score of 1. This was based on the 24
location of the line in an urban neighborhood. These assumptions provide 25
an overall Environmental Risk Score of 1. 26
Reliability: This project received a Reliability Impact Score of 3 and a 27
Reliability Frequency Score of 5. This was because these broken wires 28
would lead to 43 customers experiencing a sustained outage (CESO) 29
(CESO = 43, duration 10 hours) and there have been two wires down 30
6 Internally, the project is called “RECON 1 SPAN LINE SIDE FU 1829 TW 2107.”
3-8
outages on this line in the last three years. These assumptions provide an 1
overall Reliability Risk Score of 23. 2
Total Risk Score: Combining the Safety, Environmental and Reliability 3
Risk Scores gives a Total Risk Score for this Project of 202. 4
In terms of “flags,” this project is not a required project, so in a RIBA 5
graph it would appear within the discretionary work as No Flag showing an 6
overall risk score of 202. 7
C. Areas of Focus and Improvement 8
Over the next three years, PG&E expects to work on the following areas of 9
possible improvement for the RIBA process. 10
First, the RIBA team, the EORM team, and the LOBs will evaluate current 11
differences in the weighting algorithms between RIBA and RET. PG&E intends 12
to work toward alignment wherever possible, and validate differences where 13
appropriate. The RIBA team will work closely with the EORM team to assure 14
that improvements made in the EORM program are incorporated into RIBA. 15
These types of improvements would include topics such as risk quantification 16
and risk tolerance. 17
Second, the RIBA team is working with PG&E’s Information Technology 18
Department to incorporate RIBA into SAP Project Portfolio Management (PPM), 19
which PG&E is currently implementing across the enterprise. PPM is an 20
end-to-end solution that will enable PG&E to plan and manage its portfolio of 21
work more effectively, efficiently and in a consistent manner across the entire 22
company. PPM will allow standardized planning and management of work at the 23
portfolio and program levels and will integrate the RIBA scoring model with other 24
work attributes such as cost, schedule, approval status, resource availability, 25
and accounting information. PPM will be integrated with SAP to facilitate rate 26
case, Session 1 and Session 2 planning and reporting. 27
Third, PG&E is exploring the practicality of extending the RIBA process to 28
other LOBs within PG&E. RIBA’s initial focus was asset based, and focused on 29
the core operational LOBs. The RIBA team is working with the investment 30
planning and risk teams in the other LOBs to develop a risk-informed 31
prioritization process that will improve the decision-making process in those 32
organizations. 33
3-AtchA-1
CHAPTER 3 ATTACHMENT A
SCORING TAXONOMY
The entire scoring taxonomy is presented here for completeness. The Safety
and Environmental taxonomies are exactly the same as those used in RET2.1. There are some minor differences between RET2.1 and RIBA in the Reliability and
Frequency taxonomies.
Impact Level Safety
Catastrophic (7)
o Fatalities: Many fatalities and life threatening injuries to the public or employees.
Severe (6)
o Fatalities: Few fatalities and life threatening injuries to the public or employees.
Extensive (5)
o Permanent/Serious Injuries or Illnesses: Many serious injuries or illnesses to the public or employees.
Major (4)
o Permanent/Serious Injuries or Illnesses: Few serious injuries or illnesses to the public or employees.
Moderate (3)
o Minor Injuries or illnesses: Minor injuries or illnesses to many public members or employees.
Minor (2)
o Minor Injuries or illnesses: Minor injuries or illnesses to few public members or employees.
Negligible (1)
o No injury or illness or up to an un-reported negligible injury.
3-AtchA-2
Impact
Level Environmental
Catastrophic (7)
Duration: Permanent or long-term damage greater than 100 years; or Hazard Level/Toxicity: Release of toxic material with immediate, acute and irreversible impacts to surrounding environment; or Location: Event causes destruction of a place of international cultural significance; or Size: Event results in extinction of a species.
Severe (6)
Duration: Long-term damage between 11 years and 100 years; or Hazard Level/Toxicity: Release of toxic material with acute and long-term impacts to surrounding environment; or Location: Event causes destruction of a place of national cultural significance; or Size: Event results in elimination of a significant population of a protected species.
Extensive (5)
Duration: Medium-term damage between 2 and 10 years; or Hazard Level/Toxicity: Release of toxic material with a significant threat to the environment and/or release with medium-term reversible impact; or Location: Event causes destruction of a place of regional cultural significance; or Size: Event results in harm to multiple individuals of a protected species.
Major (4)
Duration: Short-term damage of up to 2 years; or Hazard Level/Toxicity: Release of material with a significant threat to the environment and/or release with short-term reversible impact; or Location: Event causes destruction of an individual cultural site; or Size: Event results in harm to a single individual of a protected species.
Moderate (3)
Duration: Short-term damage of a few months; or Hazard Level/Toxicity: Release of material with a moderate threat to the environment and/or release with short-term reversible impact; or Location: Event causes damage to an individual cultural site; or Size: Event results in damage to the known habitat of a protected species.
Minor (2)
Duration: Immediately correctable; or contained within a small area.
Negligible (1)
Negligible to no damage to the environment.
3-AtchA-3
Impact
Level Reliability
Catastrophic (7)
Location: Impacts an entire metropolitan area, including critical customers, or is system-wide; and Duration: Disruption of service of more than a year due to a permanent loss to a nuclear facility, hydro facility, critical gas or electric asset; or Customer Impact: Unplanned outage (net of replacement) impacts more than 1 million customers; or EO: 50 million total customer hours, or more than 1 million mwh total load; GO: 10 million total customer hours, or reduction of capacity greater than or equal to 2.1 Bcf/d for 7 months DCPP: 4,000% miss of equivalent forced outage factor and/or availability target PG: 40% or more of utility-owned generating fleet unavailable for 1 year
Severe (6)
Location: Impacts multiple critical locations and critical customers; or Duration: Substantial disruption of service greater than 100 days; or Customer Impact: Unplanned outage (net of replacement) impacts more than 100k customers; or EO: 5 million total customer hours, or more than 100k mwh total load; GO: 1 million total customer hours, or reduction of capacity greater than or equal to 1.2 Bcf/d for 7 months; DCPP: 2,000% miss of equivalent forced outage factor and/or availability target PG: 10% or more of utility-owned generating fleet unavailable for 1 year
Extensive (5)
Location: Impacts multiple critical locations or customers; or Duration: Disruption of service greater than 10 days; or Customer Impact: Unplanned outage (net of replacement) impacts more than 10k customers; or EO: 500k total customer hours, or more than 10k mwh total load; GO: 100k total customer hours, or reduction of capacity greater than or equal to 0.6 Bcf/d for 7 months; DCPP: 500% miss of equivalent forced outage factor and/or availability target PG: 2.75% or more of utility-owned generating fleet unavailable for 1 year
3-AtchA-4
Major
(4) Location: Impacts a single critical location; or
Duration: Disruption of service greater than 1 day; or Customer Impact: Unplanned outage (net of replacement) impacts more than 1k customers; or EO: 50k total customer hours, or more than 1k mwh total load; GO: 10k total customer hours, or reduction of capacity greater than or equal to 0.3 Bcf/d for 7 months; DCPP: 100% miss of equivalent forced outage factor and/or availability target PG: 0.75% or more of utility-owned generating fleet unavailable for 1 year
Moderate (3)
Location: Impacts a small area with no disruption of service to critical locations; or Duration: Disruption of service of up to 1 full day; or Customer Impact: Unplanned outage (net of replacement) impacts more than 100 customers; or EO: 5k total customer hours, or more than 100 mwh total load; GO: 1k total customer hours, or reduction of capacity greater than or equal to 0.1 Bcf/d for 7 months; DCPP: 50% miss of ES equivalent forced outage factor and/or availability target PG: 0.20% or more of utility-owned generating fleet unavailable for 1 year
Minor (2)
Location: Impacts a small localized area with no disruption of service to critical locations; or Duration: Disruption of up to 3 hours; or Customer Impact: Unplanned outage (net of replacement) impacts less than 100 customers; or EO: Less than 5k total customer hours, or less than 100 mwh total load; GO: Less than 1k total customer hours, or reduction of capacity greater than or equal to 0.01 Bcf/d for 7 months; DCPP: 5% miss of ES equivalent forced outage factor and/or availability target PG: 0.05% or more of utility-owned generating fleet unavailable for 1 year
Negligible (1)
o No reliability to negligible impacts.
3-AtchA-5
Frequency Taxonomy
Level Description Frequency Description Frequency per year
7 Imminent or Already failed > 10 times per year F = 10 - 100
6 Within 1 year 1 - 10 times per year F = 1 - 10
5 Within 3 years Once every 1-3 years F = 0.3 -1.0
4.5 Within 5 years Once every 3 - 5 years F= 0.2 -0.3
4 Within 10 years Once every 5-10 years F = 0.1 -0.2
3 Within 30 years Once every 10 - 30 years F = 0.033 - 0.1
2 Within 100 years Once every 30 - 100 years F = 0.01 - 0.033
1 100+ years Once every 100 + years F = 0.001 - 0.01
RIBA Scoring Matrix
Impact Levels
Negligible Minor Moderate Major Extensive Severe Catastrophic
Frequency Level 1 2 3 4 5 6 7
Common (7)
10 32 100 316 1,000 3,162 10,000
Regular (6)
6 18 56 178 562 1,778 5,623
Frequent (5)
2 7 23 74 234 740 2,340
Often (4.5)
2 7 21 67 211 668 2,113
Occasional (4)
2 6 18 56 178 562 1,778
Infrequent (3)
1 4 14 43 135 427 1,351
Rare (2)
1 3 10 32 100 316 1,000
Remote (1)
1 2 6 18 56 178 562
3-AtchB-1
CHAPTER 3 ATTACHMENT B
FLAG TAXONOMY
Commitments and requirements (Choose one of the following, or None) Mandatory Must be conducted in the budget or forecast year to
comply with a regulation
Regulatory Compliance
Work that is required to comply with a regulation, but that does not meet the definition of ‘Mandatory’
Commitment The company has made a specific commitment to completing the proposed work in a public forum or to regulators. Includes Rule 20A work
WRO Work requested by others spans agricultural-related requests, and new business (customer connections)
Other Considerations (Select YES OR NO for each of the following) In-flight Under construction or 50% of total expected cost
committed as of the beginning of the budget year (e.g., if in 2014 planning for 2015, then as of 1/1/2015). Applies to project work that has a defined scope. For a complete definition of a project refer to the Project approval Procedure, Utility Procedure: PM-1001P-01.
Inter-relationships with other projects
Used to indicate that the proposed work either must, or should, be done in conjunction with other work (e.g., opportunity created by a planned outage or having a trench open).
Capacity Work meant to meet changes in system demand or load growth in the future
Support IT Apps & Infrastructure; Tools & Equipment; Fleet; Buildings, Roads and Physical Infrastructure; Training
Financial Impact (Select Hard, Soft, or None) Hard financial benefits
Any sustainable net cost reduction (measured in dollars) from an established point of reference.
Soft financial benefits
Any productivity or business improvement from an established business standard.
None If there are no financial benefits.
PACIFIC GAS AND ELECTRIC COMPANY
CHAPTER 3
ATTACHMENT C
RISK-INFORMED BUDGET ALLOCATION TOOL ALGORITHM
3-AtchC-1
CHAPTER 3 ATTACHMENT C
RISK-INFORMED BUDGET ALLOCATION TOOL ALGORITHM
The equation for each risk score is the same equation in RET2.1 and is:
𝑅𝑆 = 𝑘(0.5 𝐿𝑜𝑔 ( 𝑓 ) + 𝐼)
Log (f) is determined from the following table
Frequency Level 1 2 3 4 4.5 5 6 7
Log (f) -3.0 -2.0 -1.5 -1.0 -0.7 -0.5 1.0 2.0
Just as in RET2.1 the RIBA algorithm also allows for a direct input of the
frequency by the scorer. The RIBA algorithm also allows a Frequency Level of 4.5.
This option was added because SMEs performing the RIBA scoring felt that in many cases they had sufficient knowledge and data to make the distinction between a
failure every three to five years and a failure every three to ten years. The resulting
scores are shown below.
RIBA SCORING MATRIX
Impact Levels
Negligible Minor Moderate Major Extensive Severe Catastrophic
Frequency Level 1 2 3 4 5 6 7
Common (7)
10 32 100 316 1,000 3,162 10,000
Regular (6)
6 18 56 178 562 1,778 5,623
Frequent (5)
2 7 23 74 234 740 2,340
Often (4.5)
2 7 21 67 211 668 2,113
Occasional (4)
2 6 18 56 178 562 1,778
Infrequent (3)
1 4 14 43 135 427 1,351
Rare (2)
1 3 10 32 100 316 1,000
Remote (1)
1 2 6 18 56 178 562
3-AtchC-2
The total risk score is the sum of the Safety, Environmental, and Reliability
scores (therefore all three are weighted equally). The component scores are available to reviewers in order to provide a more detailed view into the work portfolio.
4-i
PACIFIC GAS AND ELECTRIC COMPANY CHAPTER 4
ELECTRIC OPERATIONS AND NUCLEAR POWER GENERATION
TABLE OF CONTENTS
A. Introduction ....................................................................................................... 4-1
B. General Processes ........................................................................................... 4-1
1. Electric Operations ..................................................................................... 4-1
a. Organizational Structure ...................................................................... 4-3
b. Risk Register ....................................................................................... 4-3
c. Risk Evaluation .................................................................................... 4-4
d. Risk Management Software Applications ............................................ 4-8
1) System Tool for Asset Risk ........................................................... 4-9
2) Generation Risk Information Tool ................................................ 4-12
e. Risk Informed Budget Allocation ........................................................ 4-13
2. Nuclear Power Generation ....................................................................... 4-13
C. Areas of Focus and Improvement................................................................... 4-14
1. Electric Operations ................................................................................... 4-14
2. Nuclear Power Generation ....................................................................... 4-15
4-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 4 2
ELECTRIC OPERATIONS AND NUCLEAR POWER GENERATION 3
A. Introduction 4
This chapter describes how Pacific Gas and Electric Company’s (PG&E) 5
Electric Operations (EO) organization is using the Enterprise and Operational 6
Risk Management (EORM) Program to manage electric system risks. This 7
portion is sponsored by Eric Back, Director, Compliance and Risk Management 8
for Electric Operations. EO is responsible for the electric transmission and 9
distribution (T&D) systems, fossil, hydro, and other non-nuclear generating 10
facilities and energy procurement. 11
This chapter also describes how PG&E’s Nuclear Power Generation 12
organization is managing risks associated with PG&E’s nuclear facilities. 13
The nuclear portion is sponsored by Cary D. Harbor, Director, Compliance 14
Alliance and Risk for Nuclear Power Generation. 15
B. General Processes 16
1. Electric Operations 17
EO is implementing the EORM Program described in Chapter 2, 18
“Companywide Models and Approaches for Assessing Risk,” to manage 19
electric system risks. This program requires EO to identify, evaluate, 20
mitigate, and monitor risks. The process provides a repeatable and 21
consistent method of managing risks and is an important element of PG&E’s 22
Integrated Planning Process. Figure 4-1, is a high-level illustration of the 23
risk management framework. 24
4-2
FIGURE 4-1 PACIFIC GAS AND ELECTRIC COMPANY
RISK MANAGEMENT FRAMEWORK
The remainder of this EO section is organized as follows: 1
Organizational Structure – Describes EO risk management personnel 2
and committees. 3
Risk Register – Describes the codification of identified risks. 4
Risk Evaluation – Describes the tools EO uses to score items on the 5
Risk Register. 6
Risk Management Software Applications – Describes software 7
applications that PG&E is developing to assist with risk management 8
activities. 9
Risk Informed Budget Allocation (RIBA) – As generally described in 10
Chapter 3, the process EO uses to “risk score” projects and programs to 11
inform budgeting decisions. 12
In addition to the models described in Chapters 2 (Risk Evaluation Tool) 13
and 3 (RIBA), EO also uses a variety of tools (e.g., spreadsheets and 14
databases) that provide information regarding asset condition and in some 15
instances potential replacement priority. In some cases the information from 16
these tools is used to inform the models described in Chapters 2 and 3 and 17
is also used in analysis by subject matter experts (SME) during the risk 18
assessment process. 19
4-3
a. Organizational Structure 1
Chapter 2 describes how each line of business (LOB) has resources 2
dedicated to coordinating risk management activities within the LOB; 3
and collaborating on risk management activities across the LOBs. The 4
risk management organization within EO is the System Safety and Risk 5
team and consists of a senior manager and several full-time risk 6
analysts. This team reports to the Director for Compliance and Risk 7
Management, who reports to the Vice President for Electric Operations 8
Asset Management. 9
The System Safety and Risk team is responsible for implementing 10
the EORM Program for the following areas: 11
Electric Transmission Lines 12
Electric Transmission and Distribution Substations 13
Electric Distribution Lines 14
Non-Nuclear Power Generation Facilities 15
Energy Procurement 16
Items in the Risk Register (described in the next section) are 17
assigned to a risk owner (typically a director) who is responsible for 18
ensuring the accuracy of a risk’s evaluation and implementing risk 19
response plans and mitigations. SMEs working within EO assist the risk 20
owners and the EO System Safety and Risk team when evaluating risks 21
and creating risk response plans. 22
Also, EO has a Risk and Compliance Committee (RCC). The RCC 23
is chaired by EO’s Executive Vice President and is comprised of her 24
executive leadership team. This committee meets monthly to review 25
current risk-related topics and approve various items such as risk 26
assessments, risk mitigation measures, and changes to the 27
Risk Register. 28
b. Risk Register 29
PG&E uses risk registers to log and classify risks. The EO Risk 30
Register currently includes 72 risks.1 The risks are categorized as 31
1 For a full list of all risks sorted by score and category, see Attachment A of this chapter.
4-4
enterprise risks, asset risks, process risks, or energy policy risks. These 1
different types of risk are defined below. 2
Enterprise Risks (5): Enterprise risks are risks that could have a 3
catastrophic impact on PG&E if they were to occur. 4
Asset Risks (43): Risks that have consequences associated with 5
component failure or malfunction. These are further divided into: 6
Transmission Overhead Risks 7
Distribution Overhead Risks 8
Transmission and Distribution Underground Risks 9
Substation Risks 10
Power Generation Risks 11
Process Risks (14): Process-based risks have consequences 12
associated with business processes, programs, PG&E personnel, etc. 13
Energy Policy Risks (10): These risks are generally financial risks 14
related to bulk power operations, energy markets, portfolio 15
management, etc. 16
Examples of key public safety risks from the EO Risk Register 17
include wildfire, hydro system safety, and asset-related risks associated 18
with the electric T&D system. Energy policy and the majority of process 19
risks are not considered key public safety risks. 20
c. Risk Evaluation 21
EO uses two tools to evaluate items on the Risk Register: 22
The Risk Evaluation Tool (RET) 23
Risk Assessments 24
1) Application of RET to Electric Operations 25
EO uses RET, described in Chapter 2, Section C, to establish a 26
risk score for each risk in the Risk Register. For the majority of 27
uses, EO uses the RET as directed by the EORM Program and no 28
modifications are made to the algorithm, frequency scales, or impact 29
group weightings. While EO does not modify the RET model itself, 30
a variety of data and judgment are inherent when applying the 31
frequency and impact scales of the model and in the formulation of 32
4-5
the P95 scoring scenarios.2 How the RET is used in EO’s risk 1
assessment process is described more fully in the next section. 2
It is important to note that there are distinctions between (i) Risk 3
Register scores, (ii) program/project risk scores (which are 4
discussed later in the Risk Informed Budget Allocation section of this 5
chapter), and (iii) an individual asset risk score which is discussed in 6
the System Tool for Asset Risk (STAR) and Generation Risk 7
Information Tool (GRIT) sections, later in this chapter. 8
2) Risk Assessments 9
The purpose of a risk assessment is to identify potential hazards 10
and analyze what might happen if a hazard event occurs. Within 11
EO, risk assessments are used to provide a systematic 12
understanding of the items on the Risk Register. 13
EO uses a common framework to perform risk assessments and 14
upon completion, the assessments are presented to the EO RCC for 15
review and approval of the Risk Register scores and recommended 16
mitigations. 17
The components of a risk assessment include: 18
Risk definition and scope 19
A scoring scenario (the “P95” scenario) and the application of the 20
RET to determine a Risk Register score 21
Identification of risk drivers and consequences 22
Identification and assessment of risk controls 23
Identification of current gaps and potential mitigations 24
Assessments typically take 60 to 90 days to complete, and are 25
performed by a team of SMEs led by a risk analyst from the System 26
Safety and Risk Management team. The team compiles and analyzes 27
data from a variety of sources (e.g., asset condition data, event reports, 28
reliability data, etc.) to perform the assessment. 29
The team also identifies and assesses existing controls and 30
identifies potential new mitigations (or strengthening of existing controls) 31
during the assessment. Periodic reviews with the risk owner are 32
2 See Chapter 2, Section C for a definition.
4-6
conducted during the assessment. Decisions regarding what mitigations 1
to recommend to the RCC are often made during these sessions. After 2
the RCC approves a risk assessment, the approved mitigations are 3
tracked to ensure completion. 4
EO is currently working to complete a formal risk assessment for all 5
items on the Risk Register. When all the risk assessments are 6
completed, EO will have established a common basis for relative risk 7
scores for assets, processes, and events that rely on a common 8
framework, particularly with respect to the application of the RET for 9
scoring. 10
Illustrative Example: The example below—on overhead conductor 11
risk—demonstrates aspects of the EO risk assessment process. This 12
information is taken from the distribution primary overhead conductor 13
risk assessment, which was presented to the EO RCC on November 14, 14
2013.3 15
Risk Name: Distribution Primary Overhead Conductor. 16
Risk Definition: Failure of or contact with, energized electric 17
distribution primary conductor may result in public or employee safety 18
issues, significant environmental damage (fire), prolonged outages, or 19
significant property damage. 20
Scenario Evaluated (P95): A fatality due to unintentional contact, 21
such as by a third-party tree worker, with an in-place conductor, 22
partnered with an investigation that finds a compliance violation such as 23
lack of signage, or insufficient clearance. Energized wire-down events 24
are also considered as part of this risk. 25
As part of the risk assessment, the team identified types of events 26
that could occur: (1) contact with intact wire (or conductor situated in 27
proper operating position); or (2) contact with a wire that has fallen 28
down. Figure 4-2 displays the list of controls identified during this risk 29
assessment sorted by the type of conductor contact that could occur. 30
3 Attachment B of this chapter contains excerpts from the risk assessment for primary
overhead conductor.
4-7
FIGURE 4-2 PACIFIC GAS AND ELECTRIC COMPANY
ELECTRIC OPERATIONS PRIMARY OVERHEAD CONDUCTOR RISK CONTROLS
Control
Type of Contact
Intact Wire Down
Vegetation Management
Routine trimming and removal x x Work at historic outage locations x x Pilot analyzing failure characteristics of otherwise healthy trees in wildfire areas x x
Design, Construction and Operating Requirements
Clearance requirements x Warning signs x Bulletins addressing the use of 6 Cu and automatic splices x Expanding corrosion area boundaries x Review of minimum wire sizes x Review of splices per span and application of shunt splices x
Public Awareness Programs
Wire Down awareness x Tree Trimmers awareness x Need awareness program for specific third parties such as painters, roofers, cable, crane operators
x
Other
Overhead conductor replacement program x Infrared and splice inventory program x System protection x Overhead line maintenance program x x 911 response x
Figure 4-3 contains a list of additional mitigations approved as a 1
result of this risk assessment. These mitigations are also sorted by the 2
type of conductor contact that could occur. 3
4-8
FIGURE 4-3 PACIFIC GAS AND ELECTRIC COMPANY
ELECTRIC OPERATIONS DISTRIBUTION OVERHEAD CONDUCTOR PRIMARY RISK ASSESSMENT MITIGATIONS
Control
Type of Contact
Intact Wire Down
Expand public safety outreach program to (1) focus on specific third parties such as painters, roofers, cable, crane operators beyond veg; (2) expanded metrics and reporting to ensure efforts are effective.
x x
Review tree trimming practices to explore opportunities to focus on historical wire down locations.
x x
Revise STAR Tool to assign additional risk to small and copper wires and locations with higher failure rates.
x
Develop a plan, including quantities and schedules, to replace certain small wire (such as 4 Cu, 6 Cu and ACSR) in wild fire areas, urban areas and high corrosion areas.
x
Electric distribution standards to issue guidelines for threshold limit on maximum number of in-line connectors on existing lines as well as criteria/driver for nominating OH wire for replacement.
x
Revisit existing distribution protection practices and explore potential application of new technology options to reduce likelihood of a down primary wire remaining energized. Prepare a report summarizing the findings and recommendations.
x
These controls and mitigations represent the work that PG&E 1
performs to address PG&E’s distribution overhead conductor primary 2
risk. Other ongoing work such as line patrols and the daily operations of 3
vegetation management also contributes to the mitigation of this risk. 4
d. Risk Management Software Applications 5
PG&E’s electric system is extensive, including: 142,000 miles of 6
distribution lines; 18,600 miles of transmission lines; 855 substations; 7
107 hydro generating units at 67 powerhouses; 170 dams; 8
approximately 368 miles of conveyance facilities (including canals, 9
flumes, tunnels, pipes, and natural waterways); 93 total penstocks; and 10
3 fossil generating stations. 11
Within these systems and facilities there are millions of individual 12
assets with a variety of processes and analytical methodologies to 13
manage risk. While risk management processes and methods are 14
becoming more uniform, a more systematic and consistent approach 15
that integrates the concepts of probability and severity for asset failures 16
4-9
is needed. Towards this end, PG&E is developing software applications 1
that will serve as platforms to drive consistency and improve risk 2
management within and across asset classes. 3
1) System Tool for Asset Risk 4
The software that PG&E is developing to address transmission 5
and distribution assets is the System Tool for Asset Risk (STAR). 6
When fully developed, the STAR application is envisioned to be the 7
source system for risk elements (e.g., asset health indices, risk 8
impact factors and resultant risk scores)4 for asset classes 9
(e.g., poles, transformers, and conductors) that can have a 10
significant impact on safety, reliability, and the environment. The 11
STAR platform will: 12
Calculate asset health indices and risk scores 13
Represent the indices and scores geospatially and graphically 14
Facilitate risk analysis at an asset and system level 15
STAR will accomplish this by automating the collection of data 16
from a variety of sources (e.g., geospatial information systems, 17
financial and asset management systems, equipment condition 18
databases) to standardize and facilitate the risk calculations across 19
the EO T&D asset base. The system will be flexible and enable an 20
evolutionary process in both risk calculations and new data sources 21
as they are identified. Ultimately, the application would be an 22
integral part of the risk management process within EO. 23
Since STAR will draw data from existing sources, PG&E 24
anticipates that information gathering methods related to asset 25
characteristics and condition will generally remain the same. 26
Examples include: 27
Substation Assets – Dissolved gas analysis tests, equipment 28
test results, loading history, substation inspection results, input from 29
4 Asset health indices reflect the condition of an asset. Risk impact factors include
elements such as safety, reliability, financial, etc. and the effect a risk can have on those elements. A risk score is the product of: (1) probability of failure; and (2) consequence of failure. It’s currently envisioned that STAR will use the RET scoring framework.
4-10
substation maintenance personnel and asset characteristics such as 1
equipment manufacturer, year installed, etc. 2
Transmission and Distribution Line Assets – Pole test and 3
treat programs, General Order 165 patrol and inspection programs, 4
equipment inspection results, load flow programs, transformer 5
loading programs, vegetation management information, and asset 6
characteristics such as equipment size and type, manufacturer, year 7
installed, etc. 8
To support the STAR effort, PG&E has used Electric Program 9
Investment Charge (EPIC)5 funding to create a prototype of the 10
application. The STAR prototype calculates and visually displays 11
risk scores at an individual asset level for electric distribution wood 12
poles, overhead primary conductor line sections, distribution circuit 13
breakers and distribution substation transformers for a portion of 14
PG&E’s territory. By creating a prototype of STAR as part of the 15
EPIC Program, it has been possible to research, develop, and 16
demonstrate risk scoring processes and algorithms. Figure 4-4 17
shows sample screenshots from the STAR prototype. 18
5 EPIC funding provides public interest investments in the areas of applied research and
development and technology demonstration and deployment.
4-11
FIGURE 4-4 PACIFIC GAS AND ELECTRIC COMPANY
STAR SAMPLE SCREENSHOTS
Overhead conductor from Rio Bravo Substation. Pop-up boxes displaying substation risk scores and single line diagram give additional information.
Geospatial visualization of transformers in the Central Valley. Health vs. Age and Duval triangle show fleet characteristics.
4-12
STAR will take several years to implement across all of EO 1
T&D. The implementation will likely face challenges in the areas of 2
data availability and consistency, interfacing with existing 3
applications, and the creation of algorithms. When complete, the 4
STAR tool will provide risk scores for EO T&D facilities that asset 5
management personnel will use to identify work and develop asset 6
strategies. PG&E anticipates that, as improvements in data quality 7
and analytic capabilities occur, the algorithms for asset health 8
indices and risk scores will also evolve. 9
2) Generation Risk Information Tool 10
The software application being developed for PG&E’s fossil, 11
hydro, and other non-nuclear generating facilities is the Generation 12
Risk Information Tool (GRIT). GRIT is an integrated asset 13
management application which provides data centralization, 14
standardization of asset management scoring, asset risk trending, 15
improved reporting, and analytics. GRIT interfaces with SAP Work 16
Management and is designed for logging, planning, and reporting on 17
assessments (tests, inspections, reviews, calculations, etc.), asset 18
condition indicators, and asset health and consequence scores. 19
Consequence scores are in line with the RET,6 as described earlier 20
in Section B of this chapter. Lastly, GRIT also tracks risk mitigation 21
activities, including projects, maintenance, and operational changes. 22
The GRIT application organizes and displays condition and 23
consequence data on equipment within major hydro areas. These 24
equipment records are categorized by program and geography. The 25
GRIT prototype became operational in 2014, and has 15 hydro 26
asset types in the tool today, with more expected soon. 27
6 PG&E notes that the current version of GRIT uses RET frequency and impact scores
and guidance as directed by the EORM Program. However, GRIT still uses the linear RET1 Model algorithm detailed in Chapter 2, Section C.
4-13
e. Risk Informed Budget Allocation 1
Chapter 3 describes PG&E’s Risk Informed Budget Allocation 2
(RIBA) process. EO uses RIBA as part of PG&E’s Integrated Planning 3
Process. 4
EO generally uses RIBA as directed by PG&E’s Finance 5
organization (i.e., no modifications to the frequency scales or the impact 6
groups of safety, reliability or environment). 7
2. Nuclear Power Generation 8
Risk is managed for Nuclear Power Generation by the Compliance and 9
Risk Department. The director of this department reports directly to the 10
Senior Vice President, Chief Nuclear Officer. Within the Compliance and 11
Risk Department, approximately two full time employees are focused on risk 12
issues. Their responsibilities include coordination of policies and 13
procedures developed to identify, quantify and mitigate or manage risk. Like 14
EO, Nuclear Power Generation maintains its own Risk Register, and 15
prepares Session D risk analyses as part of the Integrated Planning Process 16
previously described. 17
The tools used by Nuclear Power Generation to manage risk include the 18
RET and RIBA processes discussed above and in Chapters 2 and 3 of this 19
testimony. In addition, Nuclear Power Generation implements a number of 20
additional risk management tools specific to nuclear generation. These 21
tools are often prescribed by the Nuclear Regulatory Commission (NRC), 22
which provides extensive oversight of a broad range of plant activities.7 23
Some of the key additional procedures and risk tools used specifically at 24
the Diablo Canyon Power Plant (DCPP) include: 25
1) Probabilistic Risk Assessment. This tool is used to assess 26
vulnerabilities to a wide range of events and to risk-inform decisions and 27
changes, including priority, type, and controls applied to such activities. 28
2) A robust risk-informed work management program provides appropriate 29
priorities for performing maintenance on permanent plant equipment and 30
requires detailed instructions to assure the proper performance of 31
7 These tools are subject to the jurisdiction of the NRC and are provided here for
informational purposes.
4-14
maintenance, including specification of in-process and post- 1
maintenance quality checks, proper specification of materials to be 2
used, and post-maintenance testing to confirm functionality of 3
equipment following maintenance. 4
3) The NRC maintenance rule (10 Code of Federal Regulations 5
(CFR) 50.65) requires the reliability of permanent plant equipment 6
critical to mitigation of upset conditions or whose failure could cause 7
plant transients to be monitored, and actions initiated (such as increased 8
preventive maintenance or testing) to meet minimum reliability 9
standards. 10
4) DCPP maintains a robust corrective action program as required by 11
10 CFR 50 Attachment B to assure that performance shortcomings are 12
identified, captured, and evaluated for corrective action. 13
5) Diablo Canyon procedure ER1-DC1, “Component Classification,” 14
requires items whose failure could result in a plant trip, loss of 15
generation, or other plant level important function, to be flagged and 16
requires high levels of preventive maintenance to ensure equipment 17
reliability. 18
C. Areas of Focus and Improvement 19
1. Electric Operations 20
Though much progress has been made thus far, EO anticipates future 21
refinement of our risk management program. Potential areas of future focus 22
include: 23
Improving Quantitative Rigor Associated With Likelihood of Asset 24
Failure. To the extent possible, EO believes it is better to develop and 25
rely on leading rather than lagging asset failure indicators. This will 26
allow EO to predict and address failures before they occur and therefore 27
reduce the need for emergency replacement activity. Steps that can aid 28
in facilitating this goal include: (1) improving the collection and tracking 29
of asset health metrics; and (2) collaborating across the utility industry to 30
establish models that better predict asset failure. A continued focus on 31
strengthening the collection and tracking of metrics related to asset 32
health will improve process integrity, while EO works to establish 33
4-15
predictive indicators. Collaboration across the industry will be important 1
to setting the stage for validating new predictive indicators. 2
Implement STAR. STAR’s analytics-centered asset management 3
approach is designed to continuously update risk scores based on 4
regular updates to source data systems. STAR will: (1) allow EO to 5
incrementally update asset-level, and ultimately system-level, risk 6
scores; (2) facilitate the use of asset analytics to drive proactive asset 7
replacement; and (3) create a platform to better collect and track asset 8
health metrics. The continuous incremental updating of asset risk 9
scoring through the use of STAR can be used to strengthen financial 10
planning. This will be done by linking STAR to RIBA directly, thus 11
allowing STAR to inform financial planning through the Integrated 12
Planning Process. 13
Enhance GRIT. In future phases, data from additional sources will be 14
linked to GRIT to aid Power Generation users in making informed 15
decisions about equipment replacement and project costs. New 16
functionality (including a dashboard) will be built and GRIT will be further 17
integrated with other systems. Lastly, three to five more asset types will 18
be added to the system. 19
Further Develop and Refine the EO Risk Register to Address 20
Interactive Threats. To date, the EO risk assessment process has 21
focused primarily on an in-depth examination of individual risks and 22
individual risk drivers or threats. This method does not account for the 23
interaction between multiple risks and threats. With this in mind, EO will 24
consider ways to better understand the relationship between multiple 25
risks and/or multiple threats. 26
Improving the Relationship Between Risks and Expenditures. 27
Establishing a link between risks and expenditures for controls and 28
mitigations will help EO to better communicate how its expenditure 29
portfolios align with the Risk Register. 30
2. Nuclear Power Generation 31
Though much progress has been made thus far, Nuclear Power 32
Generation anticipates future expansion and refinement of our risk 33
management program. Potential areas of future focus may include: 34
4-16
Further Develop and Refine the Nuclear Power Generation Risk 1
Register to Expand the Population for Review. To date, the Nuclear 2
Power Generation risk assessment process has focused primarily on 3
major projects. Approximately 140 in-flight projects and major projects 4
in the long-term plan have been risk assessed. An additional 5
71 projects have been identified for risk assessment to be completed 6
over the next several months. Procedures for project review have been 7
modified to require all new projects to complete this risk assessment 8
before funds are committed beyond initial project scoping efforts. 9
Training materials for project managers and project leadership are also 10
being developed to ensure appropriate impact criteria are considered 11
and scoring is consistently applied. 12
Improving the Relationship Between Risks and Expenditures. 13
Establishing a stronger link between risks and required project 14
contingency will help Nuclear Power Generation better communicate 15
risks associated with the expenditure portfolio. 16
Elec
tric
Ope
ratio
ns R
isk
Reg
iste
r (1/
2)
As
of A
pril
7, 2
015
#
Ris
k N
ame
C
urr
ent
Re
sid
ual
R
isk
Sco
re
1
Wild
fire
6
26
2
Ch
angi
ng
GH
G R
egu
lati
on
s 4
17
3
D
istr
ibu
tio
n O
verh
ead
Co
nd
uct
or
Pri
mar
y 4
08
4
Fa
ilure
of
Sub
stat
ion
(Cat
astr
op
hic
) 4
01
5
H
ydro
Sys
tem
Saf
ety
- D
ams
34
9
6
Cyb
erse
curi
ty
32
7
7
Ab
ove
-Mar
ket
Stra
nd
ed C
ost
s 3
11
8
Dis
trib
uti
on
Ove
rhea
d C
on
du
cto
r Se
con
dar
y 3
10
9
Tr
ansm
issi
on
Ove
rhea
d C
on
du
cto
rs
31
0
10
P
ort
folio
Mix
3
08
1
1
Safe
ty S
tan
dar
ds
for
PP
As
30
8
12
Lo
ss o
f C
ust
om
er L
oad
2
98
1
3
Elec
tric
Gri
d R
est
ora
tio
n
28
3
14
Em
erge
ncy
Pre
par
edn
ess
and
Res
po
nse
to
C
atas
tro
ph
ic E
ven
ts
28
0
15
D
istr
ibu
tio
n U
nd
ergr
ou
nd
Cab
le
24
5
16
En
cro
ach
men
t o
n E
O A
sset
s 2
37
17
N
etw
ork
Co
mp
on
ents
(In
Urb
an/H
igh
Den
sity
Are
as)
23
7
18
R
eco
rds
Man
agem
ent
23
6
19
Tr
ansm
issi
on
Ove
rhea
d W
oo
d S
up
po
rt S
tru
ctu
res
23
5
20
Su
bst
atio
n S
wit
ches
2
15
# R
isk
Nam
e
Cu
rre
nt
Re
sid
ual
R
isk
Sco
re
21
Sy
stem
Inte
grit
y P
rote
ctio
n S
chem
es (
SIP
S)
21
4
22
V
olt
age
Pla
nn
ing
and
Op
erat
ion
2
14
23
D
istr
ibu
tio
n O
verh
ead
Su
pp
ort
Str
uct
ure
s 2
09
24
Fa
ilure
of
Gen
erat
ion
Fac
ility
(C
atas
tro
ph
ic)
18
9
25
C
riti
cal E
qu
ipm
ent
Pro
cure
men
t 1
87
26
Tr
ansm
issi
on
Un
der
gro
un
d C
able
an
d E
qu
ipm
ent
18
1
27
Su
bst
atio
n T
ran
sfo
rmer
s an
d V
olt
age
Reg
ula
tors
1
75
28
U
nit
Su
bst
atio
ns
17
5
29
D
istr
ibu
tio
n U
nd
ergr
ou
nd
Lin
e Eq
uip
men
t 1
74
3
0
Hyd
ro P
ub
lic A
cces
s 1
74
31
H
ydro
Su
pp
ort
Infr
astr
uct
ure
1
74
32
H
ydro
Tu
rbin
e –
Gen
erat
or
Syst
ems
17
4
33
Se
ism
ic R
esili
ency
1
70
34
C
on
tro
l Ro
om
Op
erat
ion
al A
war
enes
s 1
69
35
Su
bst
atio
n P
rote
ctiv
e R
elay
s, In
stru
men
t Tr
ansf
orm
ers
& S
tati
on
Bat
teri
es
15
9
36
B
ulk
Po
we
r O
per
atio
ns
12
8
37
Tr
ansm
issi
on
Ove
rhea
d S
teel
Su
pp
ort
Str
uct
ure
s 1
17
38
La
ck o
f R
eal-
tim
e O
per
atio
nal
Wo
rkar
ou
nd
fo
r Lo
ss
of
Cri
tica
l Sys
tem
s 1
10
39
N
ew P
olic
y &
Mar
ket
Dei
sgn
1
09
40
H
ydro
Pre
ssu
re In
tegr
ity
Syst
ems
10
4
4-AtchA-1
Elec
tric
Ope
ratio
ns R
isk
Reg
iste
r (2/
2)
As
of A
pril
7, 2
015
# R
isk
Nam
e
Cu
rre
nt
Re
sid
ual
R
isk
Sco
re
41
Fo
ssil
Fuel
Sys
tem
s 1
03
42
Si
gnif
ican
t N
atu
ral G
as P
rice
Incr
ease
9
9
43
Fo
ssil
Ch
emic
al S
yste
ms
98
44
Fo
ssil
Turb
ine –
Gen
erat
or
Syst
ems
98
45
A
B 3
2 /
Cap
-an
d-T
rad
e 9
7
46
R
isk
of
No
n-C
om
plia
nce
8
2
47
Em
plo
yee
Qu
alif
icat
ion
s 8
1
48
W
ork
forc
e P
lan
nin
g 8
1
49
M
arke
t Fl
aws
/ M
anip
ula
tio
n
76
50
Lo
ss o
f Tr
ansm
issi
on
Co
rrid
or
73
51
Su
bst
atio
n B
us
Stru
ctu
res
69
5
2
Co
ver-
up
/ Fr
aud
6
1
53
La
ck o
f Tr
ansm
issi
on
Pro
ject
Del
iver
y 5
4
54
Su
bst
atio
n C
ircu
it B
reak
ers
and
Sw
itch
gear
5
3
55
H
ydro
In-s
tre
am F
low
Rel
ease
(IF
R)
Val
ve a
nd
Byp
ass
42
56
H
ydro
Pro
tect
ion
an
d C
on
tro
l Sys
tem
s 3
7
57
Fo
ssil
Hig
h E
ner
gy S
yste
ms
33
58
Su
bst
atio
n V
olt
age
and
Flo
w C
on
tro
l Eq
uip
men
t 3
2
59
Tr
ansm
issi
on
Ove
rhea
d S
wit
ches
3
2
60
D
istr
ibu
ted
Gen
erat
ion
3
1
#
Ris
k N
ame
C
urr
en
t R
esi
du
al
Ris
k Sc
ore
61
D
istr
ibu
tio
n U
nd
ergr
ou
nd
Su
bsu
rfac
e an
d P
ad-
Mo
un
t Tr
ansf
orm
ers
31
62
Fo
ssil
Pro
tect
ion
an
d C
on
tro
l Sys
tem
s 2
7
63
D
istr
ibu
tio
n O
verh
ead
Str
eetl
igh
t St
ruct
ure
s 2
5
64
D
istr
ibu
tio
n O
verh
ead
Lin
e Eq
uip
men
t –
Pro
tect
ive
2
4
65
Fo
ssil
Bal
ance
of
Pla
nt
23
66
H
ydro
Bal
ance
of
Pla
nt
23
67
D
istr
ibu
tio
n O
verh
ead
Lin
e Eq
uip
men
t –
Vo
ltag
e R
egu
lato
rs, B
oo
ster
s, a
nd
Cap
acit
ors
1
8
68
D
istr
ibu
tio
n O
verh
ead
Tra
nsf
orm
ers
18
69
Fu
el C
ell S
yste
ms
18
70
P
ho
tovo
ltai
c Sy
stem
s 1
8
71
Su
bst
atio
n G
rou
nd
ing
Syst
ems
18
72
H
ydro
Mat
eri
al R
elea
se in
to W
ate
r 1
3
No
te:
The
Elec
tric
Op
erat
ion
s R
isk
Reg
iste
r is
a d
ynam
ic d
ocu
men
t.
Ris
ks a
nd
ris
k sc
ore
s ca
n c
han
ge.
4-AtchA-2
Ris
k A
sses
smen
t Exa
mpl
e:
Prim
ary
Ove
rhea
d C
ondu
ctor
The
follo
win
g do
cum
ent c
onta
ins
exce
rpts
from
PG
&E’
s ris
k as
sess
men
t on
Prim
ary
Ove
rhea
d C
ondu
ctor
s co
nduc
ted
in N
ovem
ber o
f 201
3.
4-AtchB-1
Syst
em S
afet
y –
Ove
rhea
d Pr
imar
y C
ondu
ctor
s
Nov
embe
r 201
3
•D
efin
eo
Ris
k D
efin
ition
and
Sco
pe
•M
easu
reo
Ass
et O
verv
iew
•A
naly
zeo
Bow
Tie
Ana
lysi
so
Ove
rhea
d P
rimar
y E
vent
so
Con
tact
with
“Int
act”
Ene
rgiz
edC
ondu
ctor
so
Vege
tatio
no
Con
tact
with
Wire
s D
own
oC
urre
nt C
ontro
l Miti
gatio
nso
Cur
rent
Con
trols
Ass
essm
ent
•Im
prov
eo
Rec
omm
enda
tions
oA
sses
smen
t of P
ropo
sed
Con
trols
•A
ppen
dix
4-AtchB-2
Ris
k D
efin
ition
and
Sco
pe
Ris
k D
efin
ition
: Fa
ilure
of o
r con
tact
with
, ene
rgiz
ed e
lect
ric
dist
ribut
ion
prim
ary
cond
ucto
r res
ults
in p
ublic
or
empl
oyee
saf
ety
issu
es, s
igni
fican
t env
ironm
enta
l da
mag
e, p
rolo
nged
out
ages
, or s
igni
fican
t pr
oper
ty d
amag
e
In S
cope
•
All 2
.4kV
to 2
1kV
dist
ribut
ion
over
head
con
duct
ors
incl
udin
g sp
lices
, con
nect
ors
and
jum
pers
•Ev
ents
invo
lvin
g in
-pla
ce a
sset
s op
erat
ing
as-
desi
gned
and
failu
re o
r wire
dow
n•
Even
t con
sequ
ence
s in
term
s of
inju
ry/fa
talit
ies
and
prop
erty
dam
age,
incl
udin
g no
n-ca
tast
roph
ic fi
res
Out
of S
cope
•
Supp
ort s
truct
ures
•Tr
ansm
issi
on a
nd s
econ
dary
ove
rhea
d co
nduc
tors
•Sy
stem
pro
tect
ion
•Ig
nitio
n of
cat
astro
phic
wild
fire
Prim
ary
Ove
rhea
d C
ondu
ctor
s
Impa
ct
Probability
Ris
k P
riorit
izat
ion
Cut
off L
ine
0102030405060708090100
01
23
45
Res
idua
l Ris
k H
eat M
ap
Prim
ary
O
verh
ead
Con
duct
or
Ana
lysi
s in
pro
gres
s, ri
sk s
tatu
s un
know
n
Cur
rent
con
trols
not
suf
ficie
nt
Cur
rent
con
trols
not
suf
ficie
nt, n
ew c
ontro
ls a
re
bein
g im
plem
ente
d C
urre
nt c
ontro
ls a
re s
uffic
ient
4-AtchB-3
Ass
et O
verv
iew
Con
duct
or S
ize
(sm
all t
o la
rge)
N
umbe
r of
Circ
uit M
iles
Perc
ent o
f To
tal
6 C
u22
,157
20%
4 C
u6,
310
6%4
ACSR
47,5
5542
%2
ACSR
9,83
69%
2 C
u3,
826
3%1/
0 AC
SR1,
791
2%1/
0 C
u2,
105
2%4/
0 Al
5,08
14%
397
Al5,
435
5%71
5 Al
4,97
04%
Oth
er S
izes
4,38
14%
Tota
l 11
3,44
7 10
0%
•11
3,50
0 ov
erhe
ad c
ircui
t mile
s
•A
CS
R --
53%
•C
oppe
r -- 3
1%
•A
lum
inum
-- 1
3%
•91
,000
circ
uit m
iles
smal
ler t
han
1/0
•27
% o
f con
duct
ors
olde
r tha
n 50
yrs
“Oth
er S
izes
” inc
lude
app
roxi
mat
ely
250
mile
s of
cop
perw
eld
cond
ucto
r and
ver
y sm
all s
izes
(i.e
., 8
Cu)
– T
his
is li
kely
ver
y ol
d co
nduc
tor.
Woo
d Po
le A
ge a
s a
Prox
y fo
r Con
duct
or A
ge
Prim
ary
Ove
rhea
d C
ondu
ctor
s
33
%
18
%
19
%
16
%
9%
5%
0%
5%
10
%
15
%
20
%
25
%
30
%
35
%
> 5
0 y
rs4
0-5
0 y
rs3
0-4
0 y
rs2
0-3
0 y
rs1
0-2
0 y
rs<
10
yrs
4-AtchB-4
Bow
Tie
Ana
lysi
s
Fata
lity
Inju
ry
Fire
Third
par
ty:
•Fo
reig
n ob
ject
•C
onst
ruct
ion
Equi
pmen
t•
Non
PG
&E W
orke
r
Inta
ct
Con
duct
or
Even
t
PG&E
Em
ploy
ee:
•W
PE
Equi
pmen
t Fai
lure
: •
Con
duct
or/s
plic
e•
Cor
rosi
on
Vege
tatio
n:
•C
ompl
iant
tree
s•
Non
com
plia
nt tr
ees
Pro
perty
Dam
age
Fata
lity
Inju
ry
Fire
Third
par
ty:
•Ve
geta
tion
•N
on P
G&E
Wor
ker
Wire
Dow
n C
ondu
ctor
Ev
ent
PG&E
Em
ploy
ee:
•W
PE
Anim
al
Con
sequ
ence
s D
river
s
Anim
al
Vege
tatio
n:
•C
ompl
iant
tree
s•
Non
com
plia
nt tr
ees
Pro
perty
Dam
age
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-5
OH
Prim
ary
Con
duct
ors
is S
econ
d Le
adin
g C
ause
of I
njur
y/Fa
talit
y Ev
ents
(ca
r pol
e is
1st
)
•86
inju
ry/fa
talit
y an
d pr
oper
tyda
mag
e ev
ents
in th
e pa
st e
ight
year
s in
volv
ed o
verh
ead
prim
ary
cond
ucto
rso
62 in
tact
faci
litie
so
24 w
ire d
own
•O
f the
86
even
ts, t
here
wer
e 29
fata
litie
s•
20 p
rope
rty d
amag
e (>
$50k
) eve
nts
o14
cau
sed
by w
ires
dow
n, fi
ve b
y 3r
d
party
and
one
by
PG
&E
con
tract
or
Inju
ry/F
atal
ity a
nd T
hird
Par
ty P
rope
rty
Dam
age
OH
Prim
ary
Con
duct
or --
200
5 to
201
2
Cat
egor
y 20
05
2006
20
07
2008
20
09
2010
20
11
2012
To
tal
Third
Par
ty In
jury
/Fat
ality
14
8
6 7
5 5
6 7
58
PG
&E
Inju
ry/F
atal
ity
1 2
0 2
1 1
1 0
8 Th
ird P
arty
Pro
perty
Dam
age
2 4
3 3
4 2
1 1
20
Tota
l 17
14
9
12
10
8 8
8 86
Inju
ry/F
atal
ity a
nd P
rope
rty
Dam
age
Even
ts
Invo
lvin
g O
H P
rimar
y C
ondu
ctor
-- 2
005
to 2
012
50
5
7
62
8
3
13
24
0
20
40
60
80
Thir
d P
arty
Inju
ry/F
atal
ity
Eve
nt
PG
&E
Inju
ry/F
atal
ity
Eve
nt
Pro
per
ty D
amag
eEv
en
tTo
tal E
ven
ts
Inta
ctW
ire
Do
wn
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-6
Con
tact
with
“In
tact
” En
ergi
zed
Prim
ary
Con
duct
or in
its
Nor
mal
Sta
te
•Th
ird p
arty
: 50
eve
nts
over
8 y
ears
; 22
fata
litie
s, 2
9 in
jurie
s
•P
G&
E E
mpl
oyee
s: 5
eve
nts
over
8 y
ears
; 2 fa
talit
ies,
3 in
jurie
so
3 ev
ents
– 1
dire
ct c
onta
ct, 2
whi
le in
stal
ling/
repl
acin
g fa
cilit
ies
o2
even
ts w
ith d
igge
r der
rick
boom
s
Prim
ary
Ove
rhea
d C
ondu
ctor
s
Fore
ign
Obj
ects
: 32
Eve
nts
Vehi
cles
stri
king
pol
es,
cons
truct
ion
equi
pmen
t co
ntac
ting
prim
ary
lines
, airc
raft,
pi
pes,
ant
enna
, ste
el b
eam
, pi
pes,
sur
vey
rod,
and
rain
gu
tters
/dow
n sp
outs
Th
eft a
nd O
ther
s: 6
Eve
nts
Atte
mpt
ed w
ire th
eft o
r un
auth
oriz
ed c
limbi
ng
Non
-PG
&E
Per
sonn
el:
12 E
vent
s Tr
ee tr
imm
ers
and
com
mun
icat
ion
wor
kers
4-AtchB-7
Loca
tion
of 3
rd P
arty
Con
tact
with
Con
duct
or
OH
Prim
ary
Third
Par
ty In
jury
/Fat
ality
Ev
ents
by
Cou
nty
2005
to 2
012
Cou
nty
Num
ber o
f Ev
ents
San
ta C
lara
6
Mad
era
5 S
an L
uis
Obi
spo
5 S
anta
Cru
z 4
Con
tra C
osta
3
El D
orad
o 3
Fres
no
3 M
onte
rey
3 S
an M
ateo
3
Sut
ter
3
Subt
otal
of 1
0 C
ount
ies
38
13 C
ount
ies
with
1 o
r 2 e
vent
s 20
25
Cou
ntie
s w
ith z
ero
even
ts
0
Syst
em T
otal
58
•P
G&
E c
over
s 48
cou
ntie
so
38 e
vent
s in
10
coun
ties
o20
eve
nts
in 1
3 ot
her c
ount
ies
oN
o ev
ent i
n 25
cou
ntie
s
•N
o st
rong
rela
tions
hip
betw
een
even
t cau
ses
and
loca
tion
•S
anta
Cla
ra, M
ader
a, S
an L
uis
Obi
spo
and
San
ta C
ruz
are
the
coun
ties
with
the
mos
tev
ents
:•
Non
-PG
&E
wor
ker a
ccou
nted
for h
alf o
fth
e S
anta
Cla
ra e
vent
s•
Fore
ign
obje
cts
are
the
maj
or c
ause
inM
ader
a, S
an L
uis
Obi
spo
and
San
ta C
ruz
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-8
Wire
Dow
n C
ondu
ctor
Eve
nt --
Driv
ers
Four
Bas
ic C
ause
s of
Wire
Dow
n
•E
quip
men
t fai
lure
oC
ondu
ctor
s, s
plic
es, c
onne
ctor
s, ju
mpe
rs
•“C
ompl
iant
” veg
etat
ion
still
cre
ate
wire
s do
wn
o90
% o
f veg
etat
ion-
rela
ted
wire
dow
n in
volv
e a
tree,
tree
-bra
nch,
or t
ree
bark
falli
ng o
n th
e lin
efro
m o
utsi
de th
e re
quire
d cl
eara
nce
dist
ance
o<
5% d
ue to
tree
gro
win
g in
to li
ne o
r PG
&E
cont
ract
or tr
imm
ing
•Th
ird-p
arty
-initi
ated
oVe
hicl
e/po
le (7
2%)
oB
allo
ons
(9%
)o
3rd p
arty
con
tact
(4%
)o
Gun
sho
t (4%
)o
Oth
er (1
1%) s
prea
d ov
er s
even
sub
-cat
egor
ies
•A
nim
al in
itiat
edo
Bird
(78%
)o
Squ
irrel
(12%
)o
Oth
er (1
0%)
An
imal
, 4
% Eq
uip
men
t Fa
ilure
/In
, 3
8%
Thir
d p
arty
, 1
4%
Veg
etat
ion
, 4
3%
2008
-201
2 W
ire D
own
by B
asic
Cau
se
2008
20
09
2010
20
11
2012
To
tal
Vege
tatio
n 74
6 80
2 76
9 68
0 1,
202
4,19
9 Eq
uipm
ent F
ailu
re
743
623
653
604
1,11
8 3,
741
Third
par
ty
174
197
218
210
541
1,34
0 An
imal
74
75
72
74
10
1 39
6 C
ompa
ny In
itiat
ed
7 5
6 5
16
39
Unk
now
n ca
use
9 6
16
31
Tota
ls
1,75
3 1,
708
1,73
4 1,
573
2,97
8 9,
746
•20
12 o
utag
e re
porti
ng e
nhan
cem
ent s
igni
fican
tly in
crea
sed
the
num
ber o
f out
ages
and
acc
urac
y re
porte
d w
ith w
ire-d
own.
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-9
Wire
Dow
n - I
njur
y/Fa
talit
y &
Pro
pert
y D
amag
e
Prim
ary
Ove
rhea
d C
ondu
ctor
s
3rd P
arty
Fat
ality
/Inju
ry
PG
&E E
mpl
oyee
Fa
talit
y/In
jury
P
rope
rty D
amag
e
8 ev
ents
4
fata
litie
s, 5
inju
ries
3 ev
ents
1
fata
lity,
2 in
jurie
s 14
eve
nts
•3
vege
tatio
n•
1 bi
rd•
1 st
ruct
ure
fire
(fire
fight
er)
•1
snow
sto
rm•
1 w
ild la
nd fi
re (f
irefig
hter
)•
1 co
nduc
tor c
onta
ctin
g gu
ywire
(com
mun
icat
ion
wor
ker)
•1
tree
fell
on c
ondu
ctor
(inj
ury,
Janu
ary
2006
).•
1 co
nduc
tor c
onta
ctin
g x-
arm
(fata
lity,
Jan
uary
200
8)•
1 gu
y w
ire w
rapp
ed w
ithpr
imar
y co
nduc
tor f
ollo
win
g ca
rhi
tting
dow
n gu
y (in
jury
,D
ecem
ber 2
008)
•5
cond
ucto
r fai
lure
s•
4 ve
geta
tion
•2
pole
fire
s•
1 bi
rd•
1 eq
uipm
ent c
onne
ctor
•1
pole
failu
re
2005
to 2
012
4-AtchB-10
Wire
s D
own
-- Ve
geta
tion
Inju
ries/
Fata
litie
s •
3 co
ntac
ts a
s a
resu
lt of
a v
eget
atio
n re
late
d w
ire d
own
Fire
Igni
tions
•
Num
ber o
f eve
nts
is d
ecre
asin
g. T
ypic
al e
vent
invo
lves
less
than
10
acre
s bu
t the
pos
sibi
lity
of a
cat
astro
phic
fire
ex
ists
:
oS
outh
ern
Cal
iforn
ia:
2008
Witc
h C
reek
, Gue
jito
and
Ric
efir
es (S
DG
&E
) and
Mal
ibu
Can
yon
Fire
(SC
E)
oP
G&
E:
2008
Whi
skey
Fire
- 7,
783
acre
s (T
eham
a co
unty
)
•Th
e ris
k of
cat
astro
phic
wild
fire
will
be
addr
esse
d as
par
tth
e en
terp
rise
risk
man
agem
ent a
sses
smen
t
•S
yste
m P
rote
ctio
n w
ill h
ave
a se
para
te ri
sk a
sses
smen
tan
d w
ill in
clud
e a
reco
mm
enda
tion
to re
view
recl
ose
rela
yse
tting
s in
UW
F/O
WF/
SB
WF
area
s
Pro
perty
Dam
age
•4
prop
erty
dam
age
even
ts d
ue to
veg
etat
ion
rela
ted
wire
dow
n
10
3
89
73
11
0
60
6
7
86
8
7
50
63
5
3
0
20
40
60
80
10
0
12
0
Vege
tatio
n-R
elat
ed Ig
nitio
ns --
200
1 to
201
2
Data not collected
Fire
Siz
e N
umbe
r
≤ 10
acr
es
338
10 to
100
acr
es9
100
to 1
,000
acr
es3
1,00
0 to
10,
000
acre
s1
> 10
,000
acr
es0
Tota
l 35
1
OH
Prim
ary
Con
duct
or
Fire
s by
Siz
e 20
07 to
201
2
1 ac
re ≈
1 fo
otba
ll fil
ed
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-11
•Th
e sy
stem
ave
rage
of w
ire d
own
even
ts d
ue to
equ
ipm
ent f
ailu
re is
0.7
7 pe
r 100
mile
s
•E
ast B
ay, S
an F
ranc
isco
, Pen
insu
la, C
entra
l Coa
st a
nd S
acra
men
to h
ave
valu
es >
150
% o
f the
syst
em a
vera
ge.
Exc
ept f
or S
acra
men
to, a
ll th
e di
visi
ons
have
cor
rosi
on a
reas
.
Wire
Dow
n --
Equi
pmen
t Fai
lure
0.4
9
0.4
9
0.5
1
0.5
4
0.5
8
0.5
9
0.6
7
0.7
3
0.7
3
0.7
6
0.8
9
0.9
1
0.9
2
1.0
0
1.1
9
1.2
7
1.5
5
1.7
6
1.9
8
-
0.5
0
1.0
0
1.5
0
2.0
0
2.5
0
WD per 100 miles of OH Conductor
Wir
e-D
ow
n p
er
10
0 M
iles
of
OH
Co
nd
uct
or
(20
12
- 2
01
3 E
qu
ip F
ailu
re R
ela
ted
)
syst
em
ave
rage
= 0
.77
per
10
0 M
ile
•W
ire s
ize,
type
and
loca
tion
are
attri
bute
s
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-12
Con
duct
or S
ize
•S
ma
ll w
ire
(< 1
/0) w
ire d
own
rate
is 9
% h
ighe
r tha
n th
e sy
stem
ave
rage
(0.8
4 vs
. 0.7
7)
Con
duct
or T
ype
•Th
e pe
rform
ance
of c
op
per
cond
ucto
r is
sign
ifica
ntly
wor
se th
an th
e sy
stem
val
ue(1
.15
vs. 0
.77)
Cor
rosi
on Z
one
•Th
e pe
rform
ance
of c
ondu
ctor
s in
co
rro
sio
n z
ones
is w
orse
than
non
-cor
rosi
on z
ones
o6
Cu
is e
stim
ated
to b
e 2.
5 tim
es h
ighe
r in
corr
osio
n zo
neo
4 A
CS
R is
est
imat
ed to
be
13 ti
mes
hig
her i
n co
rros
ion
zone
•Th
e fo
llow
ing
divi
sion
s ha
ve c
orro
sion
zon
es
Equi
pmen
t Rel
ated
Wire
Dow
n - A
ttrib
utes
H
umbo
ldt
P
enin
sula
S
onom
a
Cen
tral C
oast
N
orth
Bay
Lo
s P
adre
s
Mis
sion
S
an F
ranc
isco
E
ast B
ay
•S
ix o
f the
se d
ivis
ions
hav
e w
ire d
own
rate
s gr
eate
r tha
n th
e sy
stem
ave
ragePrim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-13
Attr
ibut
es T
hat P
oten
tially
Incr
ease
the
Con
sequ
ence
s of
a W
ire D
own
Even
t
Attr
ibut
e #
6 C
u #
4 C
u
Oth
er S
mal
l C
oppe
r C
ondu
ctor
s Su
b To
tal
Cop
per
4 AC
SR
2 AC
SR
Sub
Tota
l AC
SR
Tota
l Sm
all
Con
duct
or
Wild
Fire
Are
a 31
0 10
4 67
48
1 54
9 98
64
7 1,
128
Urb
an P
opul
atio
n A
rea
7,73
8 1,
931
660
10,3
29
8,40
9 27
6 8,
685
19,1
04
Cor
rosi
on A
rea
2,34
1 58
6 21
8 3,
145
683
16
699
3,84
4
•A
sset
loca
tion
is a
n at
tribu
te th
at in
crea
ses
the
nega
tive
cons
eque
nce
of a
wire
dow
n ev
ent
oW
ild F
ire A
rea
(Urb
an, O
ther
, San
ta B
arba
ra)
oU
rban
Pop
ulat
ion
Are
as (u
sing
GIS
def
initi
on o
f 1,0
00 p
eopl
e/sq
uare
mi)
oC
orro
sion
Are
aso
Maj
or ro
adw
ays
and
wat
erw
ays
•W
ire d
own
even
ts w
here
con
duct
or re
mai
ns e
nerg
ized
is a
noth
er a
ttrib
ute
that
pot
entia
llyin
crea
ses
the
cons
eque
nces
of w
ire d
own
even
tso
Ene
rgiz
ed c
ondu
ctor
dat
a va
ries
cons
ider
ably
bet
wee
n di
visi
ons.
Im
prov
ed d
ata
colle
ctio
n is
nee
ded
•N
umbe
r of i
n-lin
e co
nnec
tors
als
o in
fluen
ces
likel
ihoo
d of
failu
re
Estim
ated
Am
ount
s of
Sm
all W
ire S
izes
by
Attr
ibut
e
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-14
Cur
rent
Con
trol
Miti
gatio
ns --
Inta
ct C
onta
ct
V
eget
atio
n M
anag
emen
to
Rou
tine
trim
min
g &
rem
oval
(~ 1
.3 m
illion
uni
ts/y
ear)
o99
.5 %
com
plia
nce
with
regu
lato
ry re
quire
men
ts
oW
ork
at h
isto
ric o
utag
e lo
catio
ns
oP
ilot a
naly
zing
failu
re c
hara
cter
istic
s of
oth
erw
ise
heal
thy
trees
in w
ildfir
e ar
eas
D
esig
n, C
onst
ruct
ion
and
Ope
ratin
gR
equi
rem
ents
oC
lear
ance
requ
irem
ents
oW
arni
ng s
igns
O
verh
ead
Line
Mai
nten
ance
Pro
gram
oV
isua
l pat
rols
and
insp
ectio
ns th
at c
an p
oten
tially
iden
tify
issu
es s
uch
as e
xces
sive
sag
, in
adeq
uate
clea
ranc
es, v
eget
atio
n pr
oble
ms,
etc
.
P
ublic
Aw
aren
ess
Pro
gram
so
Wire
Dow
n aw
aren
ess
oTr
ee T
rimm
ers
awar
enes
s
oN
eed
awar
enes
s pr
ogra
m fo
r spe
cific
third
par
ties
such
as
pain
ters
, roo
fers
, cab
le, c
rane
ope
rato
rs
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-15
Cur
rent
Con
trol
Miti
gatio
ns --
Wire
Dow
n C
onta
ct
Ve
geta
tion
Man
agem
ent (
see
prio
r pag
e)
P
ublic
Aw
aren
ess
Pro
gram
so
Wire
Dow
n aw
aren
ess
oTr
ee T
rimm
ers
awar
enes
s
D
esig
n, C
onst
ruct
ion
and
Ope
ratin
g R
equi
rem
ents
oB
ulle
tins
addr
essi
ng th
e us
e of
6 C
u an
d au
tom
atic
splic
es
oE
xpan
ding
cor
rosi
on a
rea
boun
darie
s
oR
evie
w o
f min
imum
wire
siz
es
oR
evie
w o
f spl
ices
per
spa
n an
d ap
plic
atio
n of
shu
ntsp
lices
O
H C
ondu
ctor
Rep
lace
men
t Pro
gram
oR
epla
ced
96 m
iles
in 2
013.
201
4 pl
an is
to re
plac
e 18
7ci
rcui
t mile
s (c
apac
ity a
nd re
liabi
lity
prog
ram
s)
In
frare
d an
d S
plic
e In
vent
ory
Pro
gram
oA
sses
sed
10,0
00 m
iles
in 2
013.
201
4 pl
an to
infra
red
and
inve
ntor
y sp
lices
on
anot
her 1
0,00
0 m
iles.
S
yste
m P
rote
ctio
no
2012
revi
ew c
oncl
uded
that
PG
&E
’s p
ract
ices
refle
ctw
hat i
s cu
rrent
ly c
onsi
dere
d go
od p
ract
ice
in th
ein
dust
ry
Li
ne M
aint
enan
ce P
rogr
amo
Visu
al p
atro
ls a
nd in
spec
tions
that
can
pot
entia
llyid
entif
y is
sues
suc
h as
exc
essi
ve s
ag,
inad
equa
tecl
eara
nces
, veg
etat
ion
prob
lem
s, e
tc.
91
1 R
espo
nse
oP
roce
sses
and
met
rics
to re
spon
d in
a ti
mel
ym
anne
r to
emer
genc
y si
tuat
ionsPrim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-16
Cur
rent
Con
trol
s A
sses
smen
t - A
mbe
r
Ris
k D
river
s
Current Controls
Con
trol D
escr
iptio
nFr
eque
ncy/
Impa
ct
Con
trol T
ype
Thi
rd-P
arty
E
quip
men
t Fa
ilure
V
eget
atio
n W
ork
Pro
cedu
re
Err
or
Ani
mal
Pub
lic A
war
enes
s P
rogr
ams
(Wire
Dow
n/Tr
ee
Wor
kers
) Fr
eque
ncy
Pre
vent
ive
(adm
inis
trativ
e)
Veg
etat
ion
Man
agem
ent
Freq
uenc
y P
reve
ntiv
e
Line
Mai
nten
ance
Pro
gram
Fr
eque
ncy
Pre
vent
ive
Des
ign,
Con
stru
ctio
n an
d O
pera
ting
Pro
cedu
res
Bot
h P
reve
ntiv
e (a
dmin
istra
tive)
Con
duct
or R
epla
cem
ent P
rogr
am
Freq
uenc
y P
reve
ntiv
e
Infra
red
Insp
ectio
n /S
plic
e In
vent
ory
Freq
uenc
y P
reve
ntiv
e
Site
Inve
stig
atio
n (w
ire d
own,
veg
etat
ion,
wor
k pr
oced
ure)
Fr
eque
ncy
Pre
vent
ive
Sys
tem
Pro
tect
ion
(sep
arat
e ris
k ev
alua
tion)
Im
pact
D
etec
tive
911
Res
pons
e Im
pact
P
reve
ntiv
e
Adeq
uate
Con
trol
Wea
k C
ontro
l St
rong
Con
trol
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-17
Rec
omm
enda
tions
– N
ew R
isk
Miti
gatio
ns
Wor
k R
ecom
men
ded
Ris
k D
river
Af
fect
ed
Addr
esse
s Im
pact
/ Fr
eque
ncy
Prop
osed
Ac
tion
Ow
ner
Tim
ing
Com
men
ts
Exp
and
publ
ic s
afet
y ou
treac
h pr
ogra
m to
(1) f
ocus
on
spec
ific
third
par
ties
such
as
pain
ters
, ro
ofer
s, c
able
, cra
ne o
pera
tors
be
yond
veg
; (2)
exp
ande
d m
etric
s an
d re
porti
ng to
ens
ure
effo
rts a
re e
ffect
ive
3rd p
arty
Fr
eque
ncy
& Im
pact
C
ompl
ete
plan
by
Q2
2014
Coo
rdin
ate
with
Ext
erna
l C
omm
unic
atio
ns a
nd C
usto
mer
C
are.
Low
er th
e ris
k of
ac
cide
ntal
con
tact
with
di
strib
utio
n co
nduc
tors
Rev
iew
tree
trim
min
g pr
actic
es
to e
xplo
re o
ppor
tuni
ties
to fo
cus
on h
isto
rical
wire
dow
n lo
catio
ns
Vege
tatio
n Fr
eque
ncy
Com
plet
e E
valu
atio
n an
d Fi
naliz
e P
lan
by
Q2
2014
Fina
l GR
C d
ecis
ion
will
spec
ify
vege
tatio
n ba
lanc
ing
acco
unt
amou
nt
Rev
ise
STA
R T
ool t
o as
sign
ad
ditio
nal r
isk
to s
mal
l and
co
pper
wire
s an
d lo
catio
ns w
ith
high
er fa
ilure
rate
s
Equ
ipm
ent
Freq
uenc
y C
ompl
ete
by Q
2 20
14
Add
ress
hig
h co
nseq
uenc
e lo
catio
ns s
uch
as fr
eew
ay
cros
sing
, fro
m a
impa
ct
pote
ntia
l, to
bet
ter p
riorit
ize
repl
acem
ent o
r upg
rade
s
Dev
elop
a p
lan,
incl
udin
g qu
antit
ies
and
sche
dule
s, to
re
plac
e ce
rtain
sm
all w
ire (s
uch
as 4
Cu,
6 C
u &
AC
SR
) in
wild
fir
e ar
eas,
urb
an a
reas
and
hig
h co
rrosi
on a
reas
.
Equ
ipm
ent
Failu
re
Freq
uenc
y
Pla
n: Q
2 20
14
Impl
emen
t:
Q3
2014
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-18
Rec
omm
enda
tions
– N
ew R
isk
Miti
gatio
ns
Wor
k R
ecom
men
ded
Ris
k D
river
Af
fect
ed
Addr
esse
s Im
pact
/ Fr
eque
ncy
Prop
osed
Act
ion
Ow
ner
Tim
ing
Com
men
ts
Ele
ctric
dis
tribu
tion
stan
dard
s to
issu
e gu
idel
ines
for t
hres
hold
lim
it on
max
imum
num
ber
of in
-line
con
nect
ors
on
exis
ting
lines
as
wel
l as
crite
ria/d
river
for
nom
inat
ing
OH
wire
for
repl
acem
ent.
Equ
ipm
ent
Failu
re
Freq
uenc
y C
ompl
ete
Q1,
201
4
Gui
danc
e on
the
allo
wab
le
num
ber o
f spl
ices
in n
ew
span
s al
read
y ex
ists
.
Rev
isit
exis
ting
dist
ribut
ion
prot
ectio
n pr
actic
es a
nd e
xplo
re
pote
ntia
l app
licat
ion
of
new
tech
nolo
gy o
ptio
ns to
re
duce
like
lihoo
d of
a
dow
n pr
imar
y w
ire
rem
aini
ng
ener
gize
d.
Pre
pare
a
repo
rt su
mm
ariz
ing
the
findi
ngs
and
reco
mm
enda
tions
.
Third
Par
ty
Freq
uenc
y &
Im
pact
C
ompl
ete
Q2,
201
4
Prim
ary
Ove
rhea
d C
ondu
ctor
s
Prio
r to
exec
utin
g ne
w re
com
men
datio
ns, w
e fin
d th
e cu
rren
t res
idua
l ris
k of
ED
OH
Con
duct
or is
“a
mbe
r”.
Upo
n im
plem
enta
tion
of p
ropo
sed
incr
emen
tal c
ontro
ls a
nd c
ontin
uatio
n of
exi
stin
g co
ntro
ls, w
e an
ticip
ate
the
futu
re re
sidu
al ri
sk w
ill c
ontin
ue to
be
“am
ber.”
4-AtchB-19
Ris
k Sc
enar
ios
– C
urre
nt R
esid
ual R
isk
Typi
cal r
esul
t of a
n as
set f
ailu
re:
A se
rvic
e in
terr
uptio
n to
app
roxi
mat
ely
350
cust
omer
s fo
r app
roxi
mat
ely
two
hour
s (e
xclu
ding
maj
or e
vent
da
ys) a
nd d
oes
not r
esul
t in
an e
lect
ric c
onta
ct o
r fire
igni
tion.
Extr
eme
resu
lt of
an
asse
t fai
lure
: A
cond
ucto
r fai
lure
or t
ree
cont
act c
ausi
ng:
(a) A
rela
tivel
y sm
all (
<100
0 ac
res)
fire
in a
den
sely
pop
ulat
ed a
rea
(e.g
., O
akla
nd H
ills)
resu
lting
in
sign
ifica
nt p
rope
rty d
amag
e, fa
talit
ies
and
inju
ries;
or
(b) A
larg
e fir
e in
a ru
ral a
rea
invo
lvin
g m
ore
than
100
squ
are
mile
s (a
ppro
xim
atel
y 64
,000
acr
es)
resu
lting
in li
mite
d pr
oper
ty d
amag
e bu
t wou
ld in
clud
e fa
talit
ies
and
inju
ries
Thes
e sc
enar
ios
are
used
to s
core
and
prio
ritiz
e ou
r rel
ativ
e ris
k in
the
Ris
k R
egis
ter f
or E
lect
ric O
pera
tions
Ris
k Sc
enar
io
Freq
uenc
y Le
vel*
Impa
ct L
evel
*
Safe
ty
Envi
ronm
enta
lC
ompl
ianc
e R
elia
bilit
y R
eput
atio
nal
Fina
ncia
l
Typi
cal
7
11
13
1
1
Extr
eme
3
66
54
6
5
Ris
k Ev
alua
tion
Tool
(7x7
) sco
ring
of s
cena
rios:
*Def
initi
ons
of ra
nkin
g le
vels
are
bas
ed o
n th
e en
terp
rise
risk
man
agem
ent 7
x7 m
atrix
v5.
Current Residual
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-20
Targ
etin
g lo
catio
ns u
sing
like
lihoo
d an
d co
nseq
uenc
e fa
ctor
s
GIS
Ove
rlay
of:
•C
orro
sion
Zon
es•
Urb
an p
opul
atio
nde
nsity
•U
WF/
OW
F/ S
BW
F
Wou
ld n
eed
to o
verla
y sm
all c
oppe
r di
strib
utio
n co
nduc
tor
on th
is, a
nd a
djus
t to
show
HC
A ve
rsus
st
rictly
“urb
aniz
ed
area
s”
4-AtchB-21
Con
duct
or A
ge D
ata
•C
ondu
ctor
age
dat
a in
CE
DS
A is
inac
cura
te –
the
sign
ifica
nt in
crea
se in
con
duct
or a
mou
nts
is a
resu
ltof
a te
chno
logy
sys
tem
con
vers
ion
in th
e la
te 1
980’
s w
here
the
year
inst
alle
d fie
ld b
ecam
e m
anda
tory
and
1988
, 198
9 an
d 19
90 w
as e
nter
ed fo
r man
y p
revi
ousl
y-bl
ank
line
sect
ion
reco
rds
•U
sing
dis
tribu
tion
pole
age
we
can
estim
ate
that
:
25%
of O
H c
ondu
ctor
is o
ver 5
0 ye
ars
old
50
% o
f OH
con
duct
or is
40
year
s ol
d
75%
of O
H is
ove
r 27
year
s ol
d•
Ther
e is
no
age
data
for s
plic
es/c
onne
ctor
s.
0%
25
%
50
%
75
%
10
0%
46
48
50
52
54
56
58
60
62
64
66
68
70
72
74
76
78
80
82
84
86
88
90
92
94
96
98
00
02
04
06
08
10
Cumulative %
Year
Inst
alle
d
Dis
trib
uti
on
Po
les
and
OH
Pri
mar
y C
on
du
cto
r b
y Ye
ar In
stal
led
OH
Pri
mar
y C
on
du
cto
r
Dis
trib
uti
on
Po
les
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-22
Ass
et P
erfo
rman
ce
Bas
ic C
ause
20
08
2009
20
10
2011
20
12
Tota
l 5
Year
Av
g %
of
Tota
l Ve
geta
tion
2,26
62,
226
2,23
62,
083
2,41
211
,223
2,24
541
%Eq
uipm
ent F
ailu
re2,
505
2,15
52,
037
1,95
62,
133
10,7
862,
157
39%
Third
-par
ty
508
496
503
570
586
2,66
353
310
%An
imal
367
403
463
633
652
2,51
850
49%
Com
pany
Initi
ated
4742
4055
6024
449
1%U
nkno
wn
caus
e43
4356
5134
227
451%
Tota
l5,
736
5,36
55,
335
5,34
85,
877
27,6
615,
532
100%
Sust
aine
d O
utag
es b
y B
asic
Cau
se --
200
8 to
201
2 (e
xclu
ding
maj
or e
vent
day
s) Th
e le
adin
g ris
k dr
iver
s ar
e:
Ve
geta
tion
(41%
)
Equ
ipm
ent F
ailu
re (3
9%)
Th
ird-p
arty
(10%
)
Ani
mal
(9%
)
OH
Ass
et T
ype
2008
20
09
2010
20
11
2012
To
tal
5 Ye
ar
Avg
% o
f To
tal
Con
duct
or, O
verh
ead
4,64
64,
359
4,41
24,
466
4,83
022
,713
4,54
382
%
Con
nect
or o
r spl
ice
350
340
345
358
450
1,84
336
97%
Jum
per
724
653
566
517
589
3,04
961
011
%PG
's, K
earn
eys
1613
127
856
110%
Tota
l5,
736
5,36
55,
335
5,34
85,
877
27,6
615,
532
100%
•P
erso
nnel
fam
iliar w
ith s
plic
e &
conn
ecto
r per
form
ance
and
PG
&E
’sda
ta re
cord
ing
prac
tices
con
side
r the
splic
e/co
nnec
tor d
ata
inac
cura
te.
Impr
oved
dat
a in
this
are
a is
nece
ssar
y.
•Th
e ta
bles
bel
ow s
how
sus
tain
ed o
utag
es b
y:
Bas
ic c
ause
– w
hich
iden
tifie
s le
adin
g ris
k dr
iver
s
Ass
et ty
pe –
whi
ch is
pot
entia
lly u
sefu
l in
unde
rsta
ndin
g pe
rform
ance
from
a c
ondu
ctor
vs.
con
nect
or/s
plic
e pe
rspe
ctiv
e
Sust
aine
d O
utag
es b
y As
set T
ype
-- 20
08 to
201
2 (e
xclu
ding
maj
or e
vent
day
s)
Prim
ary
Ove
rhea
d C
ondu
ctor
s
4-AtchB-23
5-i
PACIFIC GAS AND ELECTRIC COMPANY CHAPTER 5
GAS OPERATIONS
TABLE OF CONTENTS
A. Introduction ....................................................................................................... 5-1
B. General Processes ........................................................................................... 5-1
1. Organizational Structure ............................................................................ 5-1
2. Enterprise and Operational Risk Management and Integrated Planning Processes ................................................................................... 5-3
3. Risk-Based Prioritization Methodologies .................................................... 5-4
a. DIMP.................................................................................................... 5-5
1) Know the PG&E System ............................................................... 5-6
2) Identify Threats ............................................................................. 5-7
3) Evaluate and Rank Risks .............................................................. 5-8
4) Implement Measures to Address Risks ....................................... 5-12
5) Measure Performance, Monitor Results and Evaluate Effectiveness ............................................................................... 5-13
6) Conduct Complete Program Evaluations and Make Improvements ............................................................................. 5-13
7) Report Results ............................................................................ 5-13
b. Program-Specific Prioritization Methodologies .................................. 5-13
4. Gas Operations Integrated Planning Process .......................................... 5-14
a. Session D and Risk Register ............................................................. 5-14
b. Session 1 and Risk Informed Budget Allocation ................................ 5-16
c. Session 2 and a Risk-Informed, Executable Work Plan .................... 5-16
C. Areas of Focus and Improvement................................................................... 5-17
5-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 5 2
GAS OPERATIONS 3
A. Introduction 4
This chapter describes how Pacific Gas and Electric Company’s (PG&E) 5
Gas Operations organization is using the Enterprise and Operational Risk 6
Management (EORM) Standard, its Integrity Management program, and other 7
tools to manage gas system risks. 8
B. General Processes 9
1. Organizational Structure 10
Within Gas Operations, risk management is owned by the Risk Register, 11
Asset Knowledge and Integrity Management, and Investment Planning 12
departments. 13
The Risk Register team is responsible for overseeing risk management 14
activities driven by the EORM Program. This includes maintenance of 15
Gas Operations’ Risk Register and implementation of the Session D 16
process. 17
The Asset Knowledge and Integrity Management (AK&IM) Department 18
is responsible for overseeing PG&E’s Transmission Integrity 19
Management Program (TIMP), Distribution Integrity Management 20
Program (DIMP), and Facility Integrity Management Program (FIMP). 21
These programs are driven by federal requirements1 and involve risk 22
management programs that are focused on asset-related threats and 23
risks. The Senior Director of AK&IM is also accountable for the asset 24
management planning processes within Gas Operations2 and oversees 25
the development of asset management plans for each of Gas 26
1 TIMP is driven by Title 49 of the Code of Federal Regulations – Transportation
(49 CFR) 192 Subpart O. DIMP is driven by 49 CFR 192 Subpart P. FIMP is a new concept that has been discussed as part of the Pipeline and Hazardous Materials Safety Administration’s (PHMSA) proposed rulemaking related to the Integrity Verification Process.
2 Gas Operations’ asset management activities are executed in line with the PAS-55/ISO-55001 Asset Management standard.
5-2
Operations’ asset families. Asset families and asset management plans 1
are described in more detail below. 2
The Investment Planning team is responsible for overseeing Gas 3
Operations’ implementation of the Risk Informed Budget Allocation 4
(RIBA) process described in Chapter 2. 5
In mid-2012, PG&E introduced a new paradigm into Gas Operations. 6
PG&E divided its assets into families and designated an individual—the 7
Asset Family Owner (AFO)—for each asset family who is accountable for 8
managing the health of those assets. 9
PG&E has identified eight asset families within Gas Operations. These 10
are outlined in Figure 5-1 below. 11
FIGURE 5-1 PACIFIC GAS AND ELECTRIC COMPANY
GAS OPERATIONS ASSET FAMILIES
Risks are identified and included in the Gas Operations Risk Register 12
based on the asset family structure, and investment decisions are made 13
5-3
within and across asset families aligned with the investment planning, 1
budgeting, and rate case frameworks. 2
In addition, Gas Operations implemented a new risk and asset 3
management process and strengthened senior leadership oversight through 4
its Risk and Compliance Committee (RCC). The RCC is chaired by the 5
Executive Vice President, who appoints representatives from Gas 6
Operations to participate on the committee. RCC members have a broad 7
understanding of the business, its processes, and associated risks. The 8
RCC meets monthly to review current risk-related topics and approve items 9
such as risk assessments, risk mitigation measures and changes to the Risk 10
Register. 11
2. Enterprise and Operational Risk Management and Integrated Planning 12
Processes 13
As described in Chapter 2, PG&E’s EORM Program allows PG&E to 14
manage assets and risks at both an enterprise and operational level. The 15
enterprise risks are those that could threaten the viability of PG&E and 16
typically span multiple lines of business (LOBs). Operational risks arise 17
from assets, people, processes and technologies within specific LOBs, such 18
as Gas Operations. By assessing and managing risks from both points of 19
view, PG&E can better manage the interdependencies and drive for 20
consistency among LOBs. 21
Gas Operations has adopted a risk management process that provides 22
a repeatable and consistent method to identify, assess, rank and mitigate 23
risk. This risk management process is fully integrated into PG&E’s 24
Integrated Planning Process to ensure risk informs the chosen strategies, 25
which in turn drives the allocation of resources. Gas Operations has been 26
advancing its risk management methodology over the last three years, and 27
continues to (i) increase the rigor and documentation of the risk 28
management process; (ii) use more data; (iii) expand the scope of risks 29
assessed as part of the process; and (iv) improve consistency of risk scoring 30
across Gas Operations. 31
The three phases of Gas Operations’ risk management and planning 32
process—(1) Identify threats and assess risks by Asset Family; (2) Develop 33
proposed mitigation programs within Asset Families; and (3) Develop 34
5-4
executable Investment Plan—are aligned with the PG&E’s Integrated 1
Planning Process. The three phases are depicted in Figure 5-2. 2
FIGURE 5-2 PACIFIC GAS AND ELECTRIC COMPANY
RISK MANAGEMENT PROCESS AND PLANNING
Additional information on PG&E’s Integrated Planning Process can be 3
found in Chapters 1, 2 and 3. 4
3. Risk-Based Prioritization Methodologies 5
To support decision making in the Integrated Planning Process, Gas 6
Operations uses several methodologies to prioritize programs and projects. 7
Some examples of these approaches are outlined in this section. 8
5-5
a. DIMP 1
Federal regulations3 require Gas Operators to develop an approach 2
to ensure the integrity of its distribution system. PG&E’s overarching 3
DIMP framework is outlined in Figure 5-3 below: 4
FIGURE 5-3 PACIFIC GAS AND ELECTRIC COMPANY
DIMP CONTINUOUS IMPROVEMENT CYCLE
Consistent with other gas operators within California, PG&E uses a 5
leak-based risk model to assess the risk of distribution pipelines. 6
This model considers five years of historical leak data to identify 7
geographical areas with elevated risk. A negative trend of leak repairs 8
for a geographic area for each threat helps identify where additional 9
mitigation may be applied. 10
The California Public Utilities Commission (CPUC) oversees DIMP 11
and periodically performs audits in accordance with State and Federal 12
3 49 CFR, Part 192-Transportation of Natural and Other Gas by Pipeline: Minimum
Federal Standards, Subpart P – Gas Distribution Pipeline Integrity Management.
5-6
Guidelines.4 Some of the topics addressed in the audits include a 1
review of how operators identify threats, perform risk evaluation, and 2
identify mitigation.5 3
Each of the seven steps in PG&E’s DIMP cycle is summarized 4
below. 5
1) Know the PG&E System 6
System knowledge is the core foundation of DIMP and improves 7
the overall safety and reliability of the distribution pipeline system. 8
At the beginning of each DIMP cycle, the DIMP Mitigation and DIMP 9
Risk teams review the data sources. Consideration is given to 10
information gained from design records, operations, and 11
maintenance as well as knowledge gained from the DIMP Steering 12
Committee, which is comprised of members of the DIMP team and 13
is supplemented with subject matter experts (SME) in each of the 14
DIMP threat categories. 15
PG&E’s DIMP Risk team uses the data, outlined in Figure 5-4, 16
to provide a comprehensive dataset for risk evaluation. As shown in 17
Figure 5-4, a majority of the data used is entered into SAP.6 18
This data is entered by field personnel conducting leak surveys, 19
excavation activities, or other field activities along the pipeline. 20
PG&E uses 20 attribute data fields for its risk analysis. 21
4 49 CFR 190.203 authorizes PHMSA to perform inspections. General Order 112-E
refers to CFR 190 and PHMSA relegates its authority to the CPUC to oversee operators.
5 PHMSA Form 24 (192.1005-192.1011) Gas Distribution System DIMP Implementation Inspection, July 7, 2014, Rev 0.
6 SAP is PG&E’s system of record for asset registry and work management.
5-7
FIGURE 5-4 PACIFIC GAS AND ELECTRIC COMPANY
PRIMARY AND SECONDARY DATA SOURCES FOR RISK ATTRIBUTES
Attribute Primary Data
Source Secondary Data Source
Leak Number SAP n/a
Division SAP Pathfinder GIS
District SAP Pathfinder GIS
City SAP Pathfinder GIS
Line Use SAP Plat sheet
Leak grade SAP n/a
Reported Leak Cause SAP n/a
Leak Source SAP n/a
Material of Leaking Component SAP (Pipe Data) SAP (Inspection)
Pressure SAP SynerGEE
Diameter SAP (Pipe) SAP (Inspection)
Surface Over Pipe SAP (Inspection) SAP (Surface Over Read Location)
Repair Date SAP n/a
Proximity to Areas of Public Assembly SAP GIS Public Assembly Data
Employee and Other Injury RiskMaster SAP
Employee and Other Fatality RiskMaster SAP
Damage Cost RiskMaster SAP
Wall to Wall Paving SAP n/a
Injury/Fatality Metric PHMSA n/a
Injury/Fatality Ratio PHMSA n/a
Other data fields extracted from SAP are reviewed and help in 1
determining appropriate mitigation activities. 2
2) Identify Threats 3
PG&E uses leak data and SME input for threat identification and 4
risk evaluation. The DIMP Risk team reviews the collected dataset 5
and assigns one of eight threat categories (identified in 49 CFR 6
Part 192, Subpart P) to each leak. The DIMP Risk team then 7
applies sub threats, which identify risk drivers and determines if 8
accelerated actions are needed to mitigate risk. 9
Additionally, PG&E monitors potential threats. These threats 10
are identified by data sources independent from leak repair 11
5-8
(Figure 5-5). This includes reviewing internal, industry and 1
government data sources to generate a potential threat list which is 2
annually reviewed and evaluated for risk. The identified potential 3
threat list, its validity and any action required is reviewed and 4
approved by the DIMP Steering Committee. 5
FIGURE 5-5 PACIFIC GAS AND ELECTRIC COMPANY
SOURCE DATA FOR MONITORING POTENTIAL THREATS
Database Monitoring Interval
PHMSA Bulletins Annually
National Transportation Safety Board Accident Reports
Quarterly
DIMP Field Review As Performed
Material Problem Reports Quarterly
Gas Corrective Action Plan Reporting Quarterly
Potential Threat Log Annually
3) Evaluate and Rank Risks 6
The risk assessment for the gas distribution system is informed 7
from its leak history. In the assessment, each leak receives a score 8
based on its Likelihood of Failure (LoF) and Consequence of Failure 9
(CoF). The LoF for each leak is equal to 1 since the failure has 10
already occurred. The CoF portion of the risk model is based on the 11
following components: Impact on Life; Consequence Potential; 12
Leak Magnitude; and Injury/Fatality statistics. Figure 5-6 outlines 13
the variables considered in each of these components. The 14
variables of each component are identified and the relative severity 15
of a variable’s points determines the contribution to the 16
consequence of a leak. 17
5-9
FIGURE 5-6 PACIFIC GAS AND ELECTRIC COMPANY
RISK EVALUATION CONSEQUENCE FACTORS AND EQUATION
Impact on Life Consequence Potential Leak Magnitude Injury Fatality Near Public Injury Fatality Damage
Wall to Wall Paving Surface Proximity
Pipeline Pressure
Pipeline Diameter
Leak Grade
Injury Fatality Metric
Injury Fatality Ratio
_______________
CoF = [(Impact on Life)+(Consequence Potential)]*[(Leak Magnitude)*(Injury Fatality)]
As shown in the equation below, the total consequence 1
associated with each threat is the sum of the applicable leak 2
consequence scores. 3
𝑅𝑇 = ∑ 𝐿𝑜𝐹𝑖 𝑋 𝐶𝑂𝐹𝑖
𝑛
𝑖=1
Where: RT = Total risk per threat N = Number of leak events LoFi = Likelihood of each recorded leak event (equal to 1) CoFi = Consequence of each leak event
The risk scores from this equation are aggregated by 4
geographical area to develop a relative risk ranking of all threats and 5
geographical areas. 6
Following the calculation of the risk scores, the DIMP Risk team 7
analyzes risk at the appropriate level of aggregation for each threat. 8
Excavation is a threat that varies at a local level, and therefore must 9
be managed and mitigated at the local level. Because of this, PG&E 10
separates out excavation threats from this analysis, and reviews this 11
risk at the city level. Figures 5-7 and 5-8 below show the risk 12
analysis done for excavation at the city level, and the analysis done 13
for all other threats at the district (subset of a PG&E division) level. 14
Values to the right of the vertical lines represent high risk, and the 15
values within the two lines define medium risk areas. 16
5-11
FIGURE 5-8 PACIFIC GAS AND ELECTRIC COMPANY
RISK FOR ALL CAUSES EXCEPT EXCAVATION – DISTRICT LEVEL
The DIMP Risk team uses standard deviations to define 1
distribution bands in determining geographic areas of low, medium, 2
or high risk for each of the two risk analyses shown in Figures 5-7 3
and 5-8. 4
System performance is identified based on a 5-year linear trend 5
of leak repairs for the same geographic area for each threat. The 6
leak data gathered (as summarized in Figure 5-4) is reviewed for 7
5-12
this analysis. Good performance is indicated by a decreasing 1
5-year linear trend. Fair performance is indicated by a flat (slope 2
equals zero) 5-year linear trend. Poor performance is indicated by 3
an increasing 5-year linear trend. 4
The combination of risk scores and system performance, 5
outlined below, determine if a Root Cause Analysis (RCA) is 6
needed. RCAs help determine the appropriate mitigation activities 7
for each threat. PG&E performs RCAs in cases as shown in 8
Figure 5-9. 9
FIGURE 5-9 PACIFIC GAS AND ELECTRIC COMPANY
NEED FOR ROOT CAUSE ANALYSIS DETERMINATION
Performance Good Fair Poor
Ris
k
Low Review Next DIMP Cycle
Review Next DIMP Cycle
Review Next DIMP Cycle
Medium Review Next DIMP Cycle
Review Next DIMP Cycle Perform RCA
High Review Next DIMP Cycle Perform RCA Perform RCA
4) Implement Measures to Address Risks 10
The DIMP Mitigation team considers all current and applicable 11
mitigation measures. During this review the DIMP Mitigation team 12
will identify new mitigation measures or changes to the program that 13
will reduce risk.7 If existing programs and activities do not 14
adequately address the risk, the team will work to develop a new 15
program or project to mitigate the risk. Program specific mitigation 16
actions such as the Aldyl-A Replacement program and the Gas 17
Pipeline Replacement Program are reviewed to ensure work is 18
prioritized accordingly. These programs and projects are included in 19
the Session 1 and Session 2 processes to be prioritized and 20
funded accordingly. 21
7 Order Instituting Rulemaking 15-01-008, issued March 18, 2015, provides criteria for
replacement and repair based on leak grade. The process for determining mitigation may change as additional clarity is provided through the rulemaking.
5-13
5) Measure Performance, Monitor Results and Evaluate 1
Effectiveness 2
In accordance with the program evaluation requirements,8 3
PG&E performs reviews and evaluations annually. The review 4
includes refreshing leak data to incorporate new risks into the risk 5
management process. The process described above is applied to 6
the refreshed data, and included in the risk prioritization of the gas 7
distribution system. Additionally, the DIMP Risk team evaluates 8
existing algorithms and statistical methodologies used to derive the 9
overall risk score. 10
6) Conduct Complete Program Evaluations and Make 11
Improvements 12
PG&E performs reviews and evaluations of its threat 13
identification, risk analysis, and mitigation performance on a periodic 14
basis. PG&E also participates in internal quality assurance audits 15
as well as external audits performed by regulatory agencies to 16
ensure the program is meeting legal requirements. 17
7) Report Results 18
PG&E communicates the status of its reviews to key internal 19
stakeholders on an annual basis. Additionally PG&E completes 20
the following PHMSA forms: PHMSA F 7100.1-1 (Annual Report 21
Form)9 and PHMSA F 7100.1-2 (Mechanical Fitting Failure 22
Report Form). 23
b. Program-Specific Prioritization Methodologies 24
For most risk-based programs, it is necessary to have a prioritization 25
methodology that allows for risk ranking at the granular asset level to 26
allow for implementation of the program over multiple years while 27
maximizing risk reduction in the short term. Each program has either a 28
8 49 CFR, Part 192-Transportation of Natural and Other Gas by Pipeline: Minimum
Federal Standards, Subpart P – Gas Distribution Pipeline Integrity Management, 192.1007(f).
9 PG&E provides a copy of PHMSA F 7100.1-1 to the CPUC with a report outlining the major mitigation programs and accomplishments of the program during the previous year.
5-14
relative risk calculation methodology including components related to 1
likelihood of failure and consequence of failure, or a decision tree 2
methodology that prioritizes projects into tranches of equivalent risk. 3
Below are some of the risk mitigation programs included in the 4
Integrated Planning Process: 5
Aldyl-A Replacement Program – replacement of Aldyl-A pipe based 6
on vintage, material properties, leak history, and other factors. 7
Gas Pipeline Replacement Program – replacement of cast iron and 8
pre-1940 steel based on leak history, vintage, material properties, 9
corrosion potential, and other factors. 10
High-Pressure Regulator (HPR) Replacement Program – 11
replacement of HPRs based on vintage, material properties, and 12
other factors. 13
4. Gas Operations Integrated Planning Process 14
Gas Operations follows the PG&E Integrated Planning process for 15
identifying risks, developing mitigation programs, and prioritizing work to 16
address risks. The details of Gas Operations’ approach to this process are 17
outlined below. 18
a. Session D and Risk Register 19
Each AFO with the assistance of SMEs, is responsible for identifying 20
the risks associated with their asset family and scoring each risk based 21
on system knowledge, available data, and SME knowledge. The 22
categorization and evaluation of threats and risks are driven by 23
industry-adopted integrity management principles,10 PG&E’s obligation 24
to serve—both in terms of ensuring reliable delivery of natural gas and 25
increasing capacity to meet demand—as well as risks posed by an 26
inadequate response to and recovery from emergencies. 27
As stated above, PG&E has strengthened and advanced its risk 28
management methodology. By implementing the process improvements 29
noted below, PG&E has been able to effectively identify and score risks 30
within Gas Operations: 31
10 For transmission assets, threats follow American Society of Mechanical
Engineers B31.8S. For distribution assets, threats follow 49 CFR 192 Subpart P.
5-15
Greater Utilization and Integration of Data: Gas Operations has 1
increased visibility into potential risks by integrating Corrective 2
Action Plan (CAP) and process hazard analysis data into the risk 3
identification and scoring processes. 4
Increased Rigor and Documentation: SME input is used for 5
identification and validation of risks. Additionally, SME review and 6
sign-off is required for each asset family’s risk register. 7
Expanded Scope of Risk Assessment: Risks that fall outside the 8
asset families’ risk registers, such as Gas System Operations and 9
Employee Qualification risks, are identified, scored, and calibrated 10
against asset risks and are included in the Risk Register for 11
Gas Operations. 12
External Review: PG&E has leveraged the use of third-party 13
industry experts to validate Gas Operations’ risk methodology and 14
scoring. 15
Calibration of Risk: This is achieved through the consistent 16
application and calibration of risk categories and the risk scoring 17
across Gas Operations risks. 18
After identifying and scoring the risks, AFOs meet with the Gas 19
Operations’ Risk Register team to calibrate and validate ranking of each 20
threat. The AFOs document this ranking in a Risk Register 21
(Attachment A), which is updated and refined as additional information is 22
obtained and evaluated. Gas Operations communicates its top risks 23
(based on the Risk Register scoring) to PG&E leadership in Session D 24
of the Integrated Planning Process. Each risk is evaluated to determine 25
if existing mitigations are effectively managing the risk. During this step, 26
the AFOs also identify any interdependencies with other LOBs to 27
effectively manage the risk. As described below, to the extent that 28
additional mitigations are necessary, asset management plans and work 29
plans are built out in order to mitigate or reduce the risks. 30
In addition to the Session D effort, risk is also tracked within Gas 31
Operations during monthly RCC meetings described above. At these 32
meetings, AFOs highlight progress made on key risks and the status of 33
those risks. Furthermore, all Gas Operations risks included in the Risk 34
5-16
Register are stored in the Enterprise Compliance Tracking System for 1
further updates, review and reporting. 2
b. Session 1 and Risk Informed Budget Allocation 3
Based on the risks identified and scored during Session D, AFOs 4
then analyze and develop the proposed scope and pace of mitigation 5
programs. Each of the mitigation programs is designed to address the 6
identified threats and risks within the asset families to reduce those 7
risks. The AFOs submit the list of mitigation programs to the Investment 8
Planning team for further assessment and prioritization using the 9
RIBA process. 10
The RIBA risk scores are then used to develop the 5-year strategic 11
investment plan for Gas Operations, which is submitted for 12
consideration at the enterprise level as part of Session 1. Additional 13
details about RIBA can be found in Chapter 3. 14
c. Session 2 and a Risk-Informed, Executable Work Plan 15
In Session 2, individual projects are identified within the programs 16
identified in Session 1 and the RIBA framework is applied to assist in 17
developing an executable plan and scope of work for the following year. 18
The investment plan developed in Session 2 includes refinement and 19
additional details to inform execution plans. After the total portfolio of 20
proposed projects has been prioritized using a risk score, Investment 21
Planning applies additional factors such as constraints to the total 22
portfolio to ensure the work can be accomplished effectively. 23
Constraints include, for instance, resource constraints such as 24
availability of trained and qualified personnel, execution constraints such 25
as the time necessary to obtain required permits, and system 26
constraints such as the ability to deliver gas to customers while 27
performing the total portfolio of work. 28
Investment Planning then works with the AFOs to finalize the 29
proposed investment plan based on the risks and constraints identified. 30
This process requires discussion and rationalization among mitigation 31
programs across asset families. 32
5-17
C. Areas of Focus and Improvement 1
Gas Operations is exploring opportunities within its risk management 2
processes to develop a more structured optimization model that can enhance 3
prioritization based on risk, resource, budget, and system constraints as part of 4
the integrated planning process. Gas Operations will also continue to improve 5
asset data quality including integration of asset health condition assessments for 6
more informed risk assessments. Additionally, data gathered from root cause 7
analyses, CAP, quality assurance/quality control, monitoring of compliance 8
activities, and audit findings will help drive more informed risk processes. 9
In addition, in 2013, PG&E began working on the Pathfinder Program which 10
will establish a single database for gas distribution asset information. Pathfinder 11
will provide a “system of record” for all gas distribution asset data to facilitate risk 12
assessments required for DIMP and will provide the foundation for a new unified 13
Geographic Information System (GIS)/SAP model for storing gas distribution 14
asset data. Additionally, the DIMP team will be using Riskfinder, which is a set 15
of tools that helps automate the gathering of additional data streams. Another 16
tool embedded in Riskfinder is the Uptime tool, which performs GIS-based risk 17
analysis. This data will be used by the DIMP team to drive risk decisions and 18
identify appropriate mitigations. 19
The DIMP team will also be expanding their review to regulator stations and 20
meter sets. Regulator stations can potentially impact the integrity of 21
downstream assets. This provides additional data that the DIMP Team will use 22
to identify threats, assign a risk scoring, and develop mitigation work. 23
By leveraging technology and developing more consistent risk 24
methodologies for diverse assets, programs will be prioritized based on risk 25
across the system by making an asset-to-asset comparison rather than 26
prioritization occurring within individual programs. This change in methodology 27
will allow PG&E to ensure the highest risk assets, regardless of asset type, are 28
replaced first, thus maximizing risk reduction. 29
PG&E plans on additional benchmarking within and outside the industry to 30
validate and enhance its risk management framework and process. PG&E will 31
also continue to seek external review from industry experts and academic 32
research teams to help its risk management process validation and 33
improvement journey. 34
As
of A
pril
14, 2
015
Gas
Ope
ratio
ns R
isk
Reg
iste
r (1/
5)
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e
21
DM
S39
‒ E
xcav
atio
n D
amag
e, T
hird
Par
ty ‒
Rup
ture
N
on A
t-Fau
lt
406
22
TRA
11 ‒
Inco
rrec
t Ope
ratio
ns ‒
Ove
r Pre
ssur
izat
ion
34
8 23
TR
A9
‒ S
tress
Cor
rosi
on C
rack
ing
32
6 24
G
as C
ompl
ianc
e P
erfo
rman
ce R
isk
316
25
MC
14 ‒
Wel
ding
/Fab
ricat
ion
‒ O
verp
ress
ure
Com
plex
S
tatio
n 31
3
26
MC
10 ‒
Inco
rrec
t Ope
ratio
n ‒
Term
inal
/Lar
ge C
ompl
ex
313
27
MC
4 ‒
Inco
rrec
t Ope
ratio
ns ‒
Com
plex
Sta
tions
31
3 28
M
C6
‒ In
corr
ect O
pera
tions
‒ B
ackb
one
(PLS
) Sta
tions
31
3 29
S
TO17
‒ E
xter
nal C
orro
sion
‒ P
ipel
ine
313
30
MC
3 ‒
Inco
rrec
t Ope
ratio
ns ‒
LoC
Sim
ple
Sta
tions
31
2 31
M
C13
‒ W
eldi
ng/F
abric
atio
n ‒
LoC
Sim
ple
Sta
tion
312
32
STO
20 ‒
Man
ufac
turin
g ‒
Pip
elin
e 31
2 33
S
TO12
‒ E
rosi
on ‒
Met
ers
311
34
STO
15 ‒
Ero
sion
‒ V
alve
s 31
1 35
S
TO18
‒ F
atig
ue ‒
All
Seg
men
ts
311
36
DM
S42
‒ In
corr
ect O
pera
tions
‒ E
mpl
oyee
Qua
lific
atio
ns
311
37
TRA
16 ‒
Equ
ipm
ent R
elat
ed ‒
Ove
r-P
ress
ure
Eve
nt
311
38
MC
18 ‒
Equ
ipm
ent R
elat
ed ‒
LoC
Com
plex
/ S
impl
e S
tatio
n 31
1
39
MC
36 ‒
Equ
ipm
ent R
elat
ed ‒
Ter
min
al/L
arge
Com
plex
31
1 40
M
C19
‒ E
quip
men
t Rel
ated
‒ B
ackb
one
(PLS
) Sta
tions
31
1
41
DM
S8
‒ In
corr
ect O
pera
tions
‒ C
ross
Bor
e in
Sub
urba
n A
rea
310
42
CP
1 ‒
Ext
erna
l/Int
erna
l Cor
rosi
on
310
43
CP
2 ‒
Ext
erna
l Cor
rosi
on ‒
Und
er P
ipe
Insu
latio
n 31
0 44
C
P10
‒ In
tern
al C
orro
sion
and
Ero
sion
31
0 45
C
P18
‒ S
tress
Cra
ckin
g C
orro
sion
31
0 46
D
MS
5 ‒
Mat
eria
l or W
eld
‒ P
last
ic (S
yste
m S
afet
y)
310
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 1
GO
‒ C
yber
secu
rity
811
2 TR
A4
‒ C
atas
troph
ic P
ipel
ine
Failu
re ‒
Man
ufac
turin
g R
elat
ed D
efec
ts
807
3 TR
A1
‒ C
atas
troph
ic P
ipel
ine
Failu
re ‒
Ext
erna
l C
orro
sion
80
7
4 TR
A8
‒ C
atas
troph
ic P
ipel
ine
Failu
re ‒
Inte
rnal
C
orro
sion
80
7
5 TR
A3
‒ C
atas
troph
ic P
ipel
ine
Failu
re ‒
Wel
ding
/ Fa
bric
atio
n R
elat
ed ‒
Pre
-196
2 C
onst
ruct
ion
with
Lan
d M
ovem
ent
806
6 S
TO16
‒ In
tern
al C
orro
sion
and
/or E
rosi
on ‒
Pip
elin
e 80
4
7 D
MS
45 ‒
Inco
rrec
t Ope
ratio
ns ‒
Cro
ss B
ore
in U
rban
A
rea
617
8 C
P19
‒ T
hird
Par
ty/M
echa
nica
l Dam
age
‒ V
anda
lism
59
6
9 C
P22
‒ W
eath
er R
elat
ed/O
utsi
de F
orce
s ‒
Sei
smic
(M
anne
d)
596
10
DM
S40
‒ R
ecor
ds M
anag
emen
t ‒ D
istri
butio
n M
ains
and
S
ervi
ces
591
11
TRA
12 ‒
Cat
astro
phic
Pip
elin
e Fa
ilure
‒ W
eath
er
Rel
ated
and
Out
side
For
ces
‒ La
nd M
ovem
ent
579
12
MC
32 ‒
Wea
ther
Rel
ated
/Out
side
For
ces
‒ S
eism
ic
573
13
MC
15 ‒
Equ
ipm
ent R
elat
ed ‒
LoC
Com
plex
/ S
impl
e S
tatio
n
573
14
MC
1 ‒
Inco
rrec
t Ope
ratio
ns ‒
LoC
LP
Dis
tribu
tion
551
15
CP
12 ‒
Man
ufac
turin
g D
efec
ts
551
16
CP
8 ‒
Wel
ding
/Fab
ricat
ion
Rel
ated
55
1 17
S
TO26
‒ W
eath
er a
nd O
utsi
de F
orce
s ‒
Sei
smic
55
1 18
M
C16
‒ E
quip
men
t Rel
ated
‒ L
oC L
P D
istri
butio
n 54
8 19
C
P6
‒ In
corr
ect O
pera
tions
54
8
20
GS
O1
‒ Fa
ilure
to M
eet C
ore
Cus
tom
er D
eman
d fo
r D
esig
n S
tand
ard
Abn
orm
al P
eak
Day
(AP
D)
537
5-AtchA-1
As
of A
pril
14, 2
015
Gas
Ope
ratio
ns R
isk
Reg
iste
r (2/
5)
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 70
C
CE
11 ‒
Nat
ural
For
ces
(Flo
od)
234
71
LNG
15 ‒
Thi
rd-P
arty
Dam
age
‒ N
GV
Tan
k R
uptu
re
234
72
DM
S54
‒ O
ther
Out
side
For
ces
‒ In
acce
ssib
le
Equ
ipm
ent
202
73
CC
E33
‒ O
ther
Out
side
For
ce ‒
Inac
cess
ibilit
y to
Sys
tem
20
2 74
S
TO21
‒ C
onst
ruct
ion
‒ P
ipel
ine
191
75
STO
29 ‒
Thi
rd P
arty
Dam
age
‒ A
ll S
egm
ents
18
4
76
DM
S10
‒ In
corr
ect O
pera
tions
‒ R
egul
ator
(L
ow P
ress
ure)
18
4
77
MC
30 ‒
3rd
Par
ty/M
echa
nica
l Dam
age
‒ V
anda
lism
18
3 78
S
TO23
‒ W
eath
er a
nd O
utsi
de F
orce
‒ M
cDon
ald
Isla
nd
181
79
CP
21 ‒
Wea
ther
Rel
ated
/Out
side
For
ces
‒ S
eism
ic
(Unm
anne
d)
181
80
MC
33 ‒
BTU
Hea
ting
Val
ue
176
81
LNG
25 ‒
Equ
ipm
ent ‒
CN
G In
ject
ion
Equ
ipm
ent O
ps
Failu
re (S
afet
y)
175
82
MC
25 ‒
Ext
erna
l Cor
rosi
on
175
83
DM
S52
‒ M
ater
ial T
race
abili
ty
175
84
MC
30.1
‒ 3
rd P
arty
/Mec
hani
cal D
amag
e ‒
Veh
icul
ar
Dam
age
175
85
DM
S38
‒ O
utsi
de F
orce
‒ L
and
Mov
emen
t Due
to C
reep
17
4 86
D
MS
51 ‒
Co-
Loca
tion
of G
as a
nd E
lect
ric F
acili
ties
174
87
MC
2 ‒
Inco
rrec
t Ope
ratio
ns ‒
LoC
HP
Dis
tribu
tion
174
88
DM
S37
‒ O
verb
uild
s
174
89
CP
29 ‒
Equ
ipm
ent R
elat
ed ‒
Hin
kley
Non
-Ret
rofit
C
ompr
esso
r Rec
ipro
catin
g E
ngin
e 17
4
90
MC
7 ‒
Inco
rrec
t Ope
ratio
ns ‒
LoS
LP
Dis
tribu
tion
174
91
MC
21 ‒
Equ
ipm
ent R
elat
ed ‒
LoS
LP
Dis
tribu
tion
174
92
CC
E5
‒ M
ater
ial o
r Wel
d ‒
Inad
equa
te C
usto
mer
R
egul
ator
Des
ign
17
3
93
STO
13 ‒
Inco
rrec
t Ope
ratio
ns ‒
Val
ves
158
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 47
TR
A6
‒ Th
ird P
arty
/Mec
hani
cal D
amag
e
310
48
STO
3 ‒
Con
stru
ctio
n by
1st
and
2nd
Par
ty ‒
Res
ervo
ir 31
0 49
S
TO30
‒ 1
st, 2
nd, 3
rd P
arty
‒ A
ll S
egm
ents
31
0 50
C
P5
‒ M
anuf
actu
ring
Def
ects
‒ P
ipe
Qua
lity
310
51
STO
19 ‒
Thi
rd P
arty
Dam
age
‒ P
ipel
ine
310
52
DM
S1
‒ E
xcav
atio
n D
amag
e, T
hird
Par
ty ‒
Rup
ture
A
t-Fau
lt D
ue to
Mis
mar
king
by
PG
&E
30
8
53
CP
7 ‒
Inco
rrec
t Ope
ratio
ns ‒
Odo
rizat
ion
308
54
DM
S14
‒ N
atur
al F
orce
s
245
55
CC
E29
‒ M
ater
ial
237
56
CC
E30
‒ M
ater
ial T
race
abili
ty
237
57
DM
S53
‒ In
corr
ect O
pera
tions
(Wor
kman
ship
Tr
acea
bilit
y)
235
58
GS
O3
‒ R
isk
of U
sing
Man
ual O
pera
tions
23
5 59
C
P13
‒ E
quip
men
t Rel
ated
‒ E
lect
rical
Sys
tem
s 23
5
60
LNG
18 ‒
Thi
rd-P
arty
Dam
age
‒ C
NG
Tra
iler
Tran
spor
tatio
n In
cide
nt
235
61
CC
E31
‒ O
ther
Out
side
For
ces
‒ B
uild
ing
and
Met
er
Inte
ract
ion
235
62
DM
S15
‒ E
xter
nal C
orro
sion
‒ U
npro
tect
ed S
teel
Pip
e
234
63
DM
S23
‒ M
ater
ial a
nd W
eld
‒ S
teel
Inst
alle
d Th
roug
h th
e 19
50s
23
4
64
CC
E20
‒ E
quip
men
t ‒ In
door
Met
er S
ets
23
4
65
DM
S46
‒ In
corr
ect O
pera
tions
‒ A
pplic
ant I
nsta
lled
Faci
litie
s 23
4
66
DM
S4
‒ In
tern
al C
orro
sion
23
4
67
DM
S43
‒ O
utsi
de F
orce
‒ L
and
Mov
emen
t Due
to
Ero
sion
or S
ubsi
denc
e 23
4
68
CC
E7
‒ E
quip
men
t or O
ther
Out
side
For
ce ‒
End
of L
ife
Failu
re
234
69
DM
S22
‒ M
ater
ial a
nd W
eld
‒ C
ompo
site
Ris
ers
23
4
5-AtchA-2
As
of A
pril
14, 2
015
Gas
Ope
ratio
ns R
isk
Reg
iste
r (3/
5)
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 11
6 S
TO25
‒ E
quip
men
t ‒ S
tora
ge F
ield
Fac
ilitie
s 95
11
7 TR
A22
‒ In
corr
ect O
pera
tions
82
118
LNG
12 ‒
Thi
rd-P
arty
Dam
age
‒ Fu
elin
g S
tatio
n D
rive
Aw
ay
74
119
LNG
24.1
‒ E
quip
men
t ‒ L
NG
Vap
oriz
er O
utag
e (R
elia
bilit
y)
72
120
GS
O9
‒ S
ched
ulin
g R
isk
68
121
CP
15 ‒
Rec
ords
Man
agem
ent (
P50
) 68
122
TRA
20 ‒
Wea
ther
Rel
ated
and
Out
side
For
ces
‒ Tr
ee D
amag
e
58
123
TRA
10 ‒
Wea
ther
-Rel
ated
Out
side
For
ce ‒
W
ater
Cro
ssin
gs a
nd E
xpos
ed P
ipe
58
124
CP
24 ‒
Hin
kley
Sta
tion
Non
-Ret
rofit
ted
Com
pres
sor
Out
age
Due
to A
ny C
ause
53
125
CP
25 ‒
Del
evan
Sta
tion
Com
pres
sor O
utag
e D
ue to
A
ny C
ause
53
126
CP
32 ‒
San
ta R
osa
Sta
tion
Com
pres
sor O
utag
e D
ue to
A
ny C
ause
53
127
CC
E13
‒ N
atur
al F
orce
s (S
eism
ic)
50
128
CC
E32
‒ O
ther
Out
side
For
ce ‒
Spa
tial C
lear
ance
45
12
9 C
P9
‒ E
quip
men
t Rel
ated
‒ A
ir E
mis
sion
Reg
ulat
ion
44
130
STO
20.1
‒ M
anuf
actu
ring
‒ P
ipel
ine
43
131
LNG
31 ‒
Insu
ffici
ent P
orta
ble
Equ
ipm
ent
42
132
CC
E4
‒ O
ther
Out
side
For
ce ‒
Thi
rd P
arty
Dam
age
‒ C
onst
ruct
ion
and
Red
evel
opm
ent
41
133
STO
27 ‒
Inco
rrec
t Ope
ratio
ns ‒
Sto
rage
Fie
ld F
acili
ties
39
134
TRA
25 ‒
Equ
ipm
ent R
elat
ed ‒
Inop
erab
le V
alve
s
38
135
DM
S47
‒ O
ther
Out
side
For
ces
‒ Tr
ee R
oot D
amag
e to
P
last
ic P
ipe
34
136
STO
16.1
‒ In
tern
al C
orro
sion
and
/or E
rosi
on ‒
Pip
elin
e 34
13
7 C
CE
26 ‒
Equ
ipm
ent F
ailu
re ‒
Met
er/R
egul
ator
33
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e
94
TRA
19 ‒
Mec
hani
cal D
amag
e ‒
Ele
ctric
Sub
stat
ion
Dam
age
14
4
95
TRA
21 ‒
Mat
eria
l Tra
ceab
ility
14
4
96
MC
34 ‒
Rec
ords
Man
agem
ent ‒
Inad
equa
te R
ecor
ds
(P50
) 14
3
97
TRA
26 ‒
Equ
ipm
ent R
elat
ed ‒
Com
pone
nt F
ailu
re
(Drip
s, F
ittin
gs)
138
98
STO
5 ‒
Cor
rosi
on ‒
Wel
l Cas
ing
114
99
STO
31 ‒
Stre
ss C
orro
sion
Cra
ckin
g ‒
Pip
elin
e 10
8 10
0 S
TO10
‒ In
corr
ect O
pera
tions
‒ W
ells
10
7 10
1 S
TO11
‒ E
rosi
on ‒
Wel
ls
107
102
TRA
14 ‒
Mec
hani
cal D
amag
e ‒
Firs
t and
Sec
ond
Par
ty
Dam
age
10
3
103
STO
4 ‒
Inco
rrec
t Ope
ratio
ns ‒
Res
ervo
ir 10
3
104
LNG
24.0
‒ E
quip
men
t ‒ L
NG
Vap
oriz
er O
pera
tions
Fa
ilure
(Saf
ety)
10
3
105
LNG
17.0
‒ T
hird
-Par
ty D
amag
e ‒
LNG
Tan
ker P
arke
d (S
afet
y)
102
106
LNG
16 ‒
Thi
rd-P
arty
Dam
age
‒ LN
G T
anke
r Tr
ansp
orta
tion
Inci
dent
10
2
107
MC
29 ‒
Inte
rnal
Cor
rosi
on
98
108
MC
28 ‒
Stre
ss C
rack
ing
Cor
rosi
on
98
109
STO
22 ‒
Wea
ther
and
Out
side
For
ce ‒
LM
and
PC
98
110
MC
12 ‒
Wel
ding
/Fab
ricat
ion
‒ O
verp
ress
ure
Eve
nt
(Sys
tem
Saf
ety)
98
111
MC
17 ‒
Equ
ipm
ent R
elat
ed (S
yste
m S
afet
y)
98
112
MC
9 ‒
Inco
rrec
t Ope
ratio
ns (S
yste
m S
afet
y)
98
113
MC
22 ‒
Equ
ipm
ent R
elat
ed ‒
LoS
HP
Dis
tribu
tion
98
114
TRA
23 ‒
Thi
rd P
arty
/Mec
hani
cal D
amag
e ‒
Van
dalis
m
97
115
LNG
26 ‒
Thi
rd-P
arty
Dam
age
‒ O
RC
A T
rlr T
rans
po
Inci
dent
97
5-AtchA-3
As
of A
pril
14, 2
015
Gas
Ope
ratio
ns R
isk
Reg
iste
r (4/
5)
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e
158
CP
26 ‒
Tio
nest
a S
tatio
n C
ompr
esso
r Out
age
Due
to
Any
Cau
se (S
yste
m S
afet
y)
24
159
CP
27 ‒
Bur
ney
Sta
tion
Com
pres
sor O
utag
e D
ue to
Any
C
ause
(Sys
tem
Saf
ety)
24
160
CP
28 ‒
Ger
ber S
tatio
n C
ompr
esso
r Out
age
Due
to A
ny
Cau
se
24
161
CP
31 ‒
Bet
hany
Sta
tion
Com
pres
sor O
utag
e D
ue to
A
ny C
ause
24
162
CP
33 ‒
Top
ock
Sta
tion
Com
pres
sor O
utag
e D
ue to
Any
C
ause
24
163
CC
E28
‒ O
ther
Out
side
For
ce ‒
Gro
undi
ng
24
164
LNG
22 ‒
Inco
rrec
t Ope
ratio
ns ‒
CN
G Q
uick
Cha
nge
Bot
tle S
afet
y
24
165
GS
O6
‒ M
arke
t Liq
uidi
ty R
isk
23
166
GS
O8
‒ D
eman
d R
isk
23
167
LNG
19.1
‒ T
hird
-Par
ty D
amag
e ‒
CN
G T
ube
Trai
ler
Par
ked
(Rel
iabi
lity)
23
168
MC
24 ‒
Equ
ipm
ent R
elat
ed ‒
LoS
Com
plex
Sta
tion
22
169
MC
27 ‒
Equ
ipm
ent R
elat
ed ‒
Ter
min
al/L
arge
Com
plex
22
17
0 M
C35
‒ E
quip
men
t Rel
ated
‒ B
ackb
one
(PLS
) Sta
tions
22
17
1 S
TO30
.1 ‒
1st
, 2nd
, 3rd
Par
ty ‒
All
Seg
men
ts
22
172
STO
24 ‒
Wea
ther
and
Out
side
For
ces
‒ M
cDon
ald
Isla
nd
20
173
DM
S2
‒ E
xcav
atio
n D
amag
e Th
ird P
arty
, No
Rup
ture
(P
50)
19
174
CP
30 ‒
Inco
rrec
t Ope
ratio
ns
18
175
CP
17 ‒
Equ
ipm
ent R
elat
ed ‒
Def
erre
d m
aint
enan
ce
18
176
DM
S41
‒ In
corr
ect O
pera
tions
‒ F
usio
n Jo
ints
(P
50)
18
177
STO
33 ‒
Dis
posa
l Wel
l ‒ G
ill R
anch
17
178
STO
34 ‒
Inte
rnal
/Ext
erna
l Cor
rosi
on ‒
Dis
posa
l ‒ W
ell ‒
G
ill R
anch
17
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e
138
LNG
30 ‒
Inco
rrec
t Ope
ratio
ns ‒
Sta
tion
Doc
umen
tatio
n S
afet
y
32
139
LNG
32.0
‒ E
quip
men
t ‒ S
tatio
n C
ompr
esso
r and
C
ompo
nent
(Saf
ety)
32
140
LNG
19.0
‒ T
hird
-Par
ty D
amag
e ‒
CN
G T
ube
Trai
ler
Par
ked
(Saf
ety)
32
141
DM
S50
‒ M
ilita
ry F
acili
ties
31
142
LNG
27 ‒
Thi
rd-P
arty
Dam
age
‒ O
RC
A L
NG
Saf
ety
Par
ked
31
143
LNG
32.1
‒ E
qpm
t ‒ C
ombi
ned
Sta
Com
pr a
nd
Com
pone
nt (R
elia
bilit
y)
30
144
GS
O2
‒ Fa
ilure
to m
eet N
on-C
ore
CW
D D
esig
n S
tand
ard
30
145
DM
S44
‒ E
xcav
atio
n D
amag
e ‒
Unl
ocat
able
Stu
bs
30
146
LNG
28 ‒
LN
G C
omm
odity
Sho
rtfal
l 30
14
7 S
TO14
‒ E
quip
men
t ‒ V
alve
s 30
14
8 M
C23
‒ E
quip
men
t Rel
ated
‒ L
oS S
impl
e S
tatio
n 29
14
9 M
C26
‒ M
anuf
actu
ring
Rel
ated
Def
ects
28
15
0 S
TO2
‒ C
onst
ruct
ion
by 3
rd P
arty
‒ R
eser
voir
28
151
LNG
29 ‒
CN
G C
omm
odity
Sho
rtfal
l (R
elia
bilit
y)
28
152
STO
31.1
‒ S
tress
Cor
rosi
on C
rack
ing
‒ P
ipel
ine
28
153
CP
4 ‒
Wea
ther
Rel
ated
/Out
side
For
ces
‒ Fl
oodi
ng
(Sys
tem
Saf
ety)
25
154
CC
E2
‒ O
ther
Out
side
For
ce ‒
Thi
rd P
arty
Dam
age
‒ V
ehic
les
25
155
CC
E6
‒ M
ater
ial o
r Wel
d ‒
Poo
r Qua
lity
Con
trol o
f R
egul
ator
/Met
er S
et M
anuf
actu
ring
25
156
LNG
30.1
‒ In
corr
ect S
tatio
n O
ps
25
157
CP
23 ‒
Ket
tlem
an S
tatio
n C
ompr
esso
r Out
age
Due
to
Any
Cau
se (S
yste
m S
afet
y)
24
5-AtchA-4
As
of A
pril
14, 2
015
Gas
Ope
ratio
ns R
isk
Reg
iste
r (5/
5)
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 20
3 TR
A7
‒ Th
ird P
arty
/Mec
hani
cal D
amag
e (P
50)
6
204
MC
11 ‒
Inco
rrec
t Ope
ratio
ns ‒
LoS
Com
plex
/Sim
ple
Sta
tion
5
205
LNG
13 ‒
Thi
rd-P
arty
Dam
age
‒ D
ispe
nser
Van
dalis
m
4
206
LNG
20 ‒
Thi
rd-P
arty
Dam
age
‒ C
NG
Bot
tle T
rlr
Tran
spo
Inci
dent
4
207
DM
S17
‒ A
tmos
pher
ic C
orro
sion
3
208
CC
E3
‒ O
ther
Out
side
For
ce ‒
Van
dalis
m
3 20
9 TR
A15
‒ In
tern
al C
orro
sion
(P50
) 3
210
DM
S6
‒ M
ater
ial o
r Wel
d ‒
T-C
aps
2
211
TRA
5 ‒
Man
ufac
turin
g R
elat
ed D
efec
ts (P
50)
2
212
LNG
21 ‒
Thi
rd-P
arty
Dam
age
‒ C
NG
Bot
tle T
rlr P
arke
d C
ollis
ion
(Saf
ety)
1
213
STO
35 ‒
Out
side
For
ces
(Geo
logi
cal)
‒ R
eser
voir
1
214
GS
O10
‒ R
isk
of M
ultip
le C
lear
ance
s in
the
Sam
e G
as
Sys
tem
0
215
GS
O11
‒ In
adeq
uate
Vis
ibili
ty in
to th
e P
ress
ures
and
Fl
ows
on th
e N
etw
orks
0
216
GS
O12
‒ G
as C
ontro
l Ope
rato
r Err
or
0 21
7 G
SO
13 ‒
SC
AD
A O
utag
e 0
218
GS
O14
‒ P
hysi
cal S
ecur
ity ‒
Gas
Con
trol C
ente
r Atta
ck
0
219
GS
O15
‒ G
OC
Sys
tem
Fai
lure
Effe
ctin
g Fi
eld
Coo
rdin
atio
n an
d R
espo
nse
0
220
MC
8.1
‒ In
corr
ect O
pera
tions
(Sys
tem
Saf
ety)
0
221
MC
10.1
‒ In
corr
ect O
pera
tions
(Sys
tem
Saf
ety)
0
# R
isk
Nam
e C
urre
nt
Res
idua
l R
isk
Scor
e 17
9 S
TO17
.1 ‒
Ext
erna
l Cor
rosi
on ‒
Pip
elin
e 17
180
GS
O4
‒ Lo
ss o
f Sup
ply
from
Inte
rcon
nect
ed P
ipel
ines
an
d Th
ird P
arty
Sto
rage
14
181
DM
S12
‒ M
ater
ial o
r Wel
d ‒
Mec
hani
cal F
ittin
gs
14
182
CP
23.1
‒ K
ettle
man
Sta
tion
Out
age
Due
to P
ower
O
utag
e 14
183
LNG
17.1
‒ T
hird
-Par
ty D
amag
e ‒
LNG
Tan
ker P
arke
d (R
elia
bilit
y)
13
184
DM
S3
‒ E
xter
nal C
orro
sion
on
Ste
el P
ipin
g
12
185
DM
S49
‒ M
ater
ial o
r Wel
d ‒
Isol
atio
n V
alve
Fai
lure
11
18
6 G
SO
5 ‒
Por
tfolio
Man
agem
ent R
isk
11
187
STO
5.1
‒ C
orro
sion
‒ W
ell C
asin
g 11
18
8 S
TO1‒
Thi
rd P
arty
Dam
age
‒ R
eser
voir
10
189
LNG
14 ‒
Thi
rd-P
arty
Dam
age
‒ Fu
el T
heft
10
19
0 D
MS
25 ‒
Mat
eria
l and
Wel
d ‒
Cur
b V
alve
s
10
191
CC
E23
‒ N
atur
al F
orce
s ‒
Set
tlem
ent o
f Soi
l 10
192
DM
S11
‒ In
corr
ect O
pera
tions
‒ R
egul
ator
(Sem
i-Hig
h or
Hig
h P
ress
ure)
10
193
MC
20 ‒
Equ
ipm
ent R
elat
ed ‒
LoS
Com
plex
/Sim
ple
Sta
tion
10
194
CC
E16
‒ O
ther
Out
side
For
ce ‒
Inop
erab
le o
r In
acce
ssib
le S
ervi
ce V
alve
9
195
DM
S7
‒ N
atur
al F
orce
s ‒
Cas
t Iro
n M
ater
ial
8 19
6 G
SO
7 ‒
Pric
e R
isk
8 19
7 D
MS
48 ‒
Inte
rnal
Cor
rosi
on ‒
Mai
nlin
e D
rips
7 19
8 C
CE
21 ‒
Oth
er O
utsi
de F
orce
‒ F
ire
7 19
9 C
CE
1 ‒
Inco
rrec
t Ope
ratio
ns
7 20
0 M
C8
‒ In
corr
ect O
pera
tion
‒ Te
rmin
al/L
arge
Com
plex
6
201
MC
5 ‒
Inco
rrec
t Ope
ratio
ns ‒
Bac
kbon
e (P
LS) S
tatio
ns
6 20
2 TR
A2
‒ E
xter
nal C
orro
sion
(P50
) 6
5-AtchA-5
6-1
PACIFIC GAS AND ELECTRIC COMPANY 1
CHAPTER 6 2
RISK LEXICON 3
This chapter provides a Risk Lexicon (Attachment A) that was developed in 4
collaboration with the other utilities participating in this proceeding. The Lexicon 5
includes terms that are used in risk management activities. Pacific Gas and Electric 6
Company (PG&E) views this Lexicon as a potentially valuable tool that can assist in 7
facilitating the discussion of risk and risk management. 8
PG&E’s opinion is that this Lexicon should be viewed as a living document that 9
can be added to and modified over time. To this end, PG&E proposes that this 10
Lexicon, and other terms as well, be made the subject of a workshop in this Safety 11
Model Assessment Proceeding. PG&E also proposes that the Commission publish 12
the Lexicon in a manner that provides for easy public access and use, and that it be 13
updated periodically. 14
Finally, there are two caveats that PG&E wishes to identify. First, it is not 15
always possible or practical to agree on only one definition for a term. The same 16
term is sometimes used somewhat differently in different companies or even within 17
the same company. Thus, it may be advisable in some circumstances to publish 18
more than one definition for a term. Second, the Commission should not mandate 19
the use of a particular definition or consider any penalties for the “misuse” of a term. 20
Rather these definitions should only be viewed as a tool with educational value that 21
over time will promote a common language about risk management. 22
6-AtchA-1
CHAPTER 6 ATTACHMENT A RISK LEXICON
Overview Based on the Refined Straw Proposal’s recommendations, PG&E, SCE, and
Sempra have developed a set of core key risk terms and definitions to be used “for
defining, acquiring, and disseminating risked-based information,”1 known as the Risk
Lexicon. The Risk Lexicon consists of a common set of terms and definitions to allow
for ease of communicating the risk-management activities described in this filing. In
addition to this set of core terms, each of the utilities may have additional risk terms and
definitions to describe their specific processes. As with the other tools, we expect the
Risk Lexicon to evolve as the ERM programs mature.
To develop the Risk Lexicon, PG&E, SCE, and Sempra looked first to the terms
and definitions in the ISO 31000 and DHS Risk Lexicon terminology documents. The
defined terms were further validated amongst a broader list of external sources common
in the risk community to ensure consistency. Below is the defined list of key terms
developed for the Risk Lexicon.
Terms Definitions
Alternatives Analysis Evaluation of different alternatives available to mitigate risk
Control Currently established measure that is modifying risk
Current Residual Risk Risk remaining after current controls
Enterprise Risk Management
Comprehensive approach to risk management that engages
organizational systems and processes together to improve the
quality of decision making for managing risks in order for an
organization to be able to achieve its objectives
1 Refined Straw Proposal, p. 10.
6-AtchA-2
Terms Definitions
Event Occurrence or change of a particular set of circumstances
Frequency Number of events generally defined per unit of time
Impact (or Consequence)
Result of an event, incident, or occurrence affecting objectives
Mitigation Measure or activity taken prior to the occurrence of an event,
designed to reduce impact and/or frequency of an event
Planned Residual Risk (or Forecasted Residual Risk)
Risk remaining after implementation of proposed mitigations
Risk Potential for an event that can impact company’s ability to achieve
its objectives
Risk-based Decision Making
Determination of a course of action predicated primarily on the
assessment of risk and the expected impact of that course of action
on that risk
Risk-informed Decision Making
Determination of a course of action predicated on the assessment
of risk, the expected impact of that course of action on that risk, as
well as other relevant factors
Risk Assessment Process
Overall process of risk identification, risk analysis and risk
evaluation
Risk Driver (or Risk Trigger)
Factor(s) that could cause risk to occur
Risk Response Plan (or Mitigation Plan)
Collection of Mitigations
Risk Score Numerical representation of a quantitative and/or qualitative risk
evaluation methodology
Risk Taxonomy A structure used to classify different types of risks across the
company at multiple levels of aggregation
EB-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF ERIC BACK 2
Q 1 Please state your name and business address. 3
A 1 My name is Eric Back, and my business address is Pacific Gas and Electric 4
Company, 245 Market Street, San Francisco, California. 5
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 6
(PG&E). 7
A 2 I am the director of the Compliance & Risk Management organization within 8
Electric Operations. 9
Q 3 Please summarize your educational and professional background. 10
A 3 I am the director for Risk Management, Compliance, and Vegetation 11
Management in Electric Operations. I joined PG&E in 2008 and worked in 12
the Utility Performance Improvement group focusing on electric transmission 13
and substation facilities and processes. Since then, I have been a 14
substation maintenance superintendent and a director in Transmission 15
Operations. Prior to joining PG&E, I worked in management and operations 16
consulting. I am a registered professional engineer in the state of California. 17
I have a bachelor of science degree in mechanical engineering from 18
University of California, Davis, a master of science degree in mechanical 19
engineering from Colorado State University and a master in business 20
administration degree from the London Business School. 21
Q 4 What is the purpose of your testimony? 22
A 4 I am sponsoring Chapter 4, “Electric Operations and Nuclear Power 23
Generation,” with the exception of Sections B.2. and C.2., in PG&E’s S-MAP 24
proceeding. Sections B.2. and C.2. relate to the risk processes and 25
programs at PG&E’s nuclear facilities and are sponsored by Cary D. Harbor. 26
Q 5 Does this conclude your statement of qualifications? 27
A 5 Yes, it does. 28
CCC-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF CHRISTINE C. CHAPMAN 2
Q 1 Please state your name and business address. 3
A 1 My name is Christine C. Chapman, and my business address is Pacific Gas 4
and Electric Company, 6111 Bollinger Canyon Road, San Ramon, 5
California. 6
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 7
(PG&E). 8
A 2 As senior director of Asset Knowledge and Integrity Management, within 9
Gas Operations, I am responsible for the leadership and oversight of an 10
organization focused on assessing the integrity of the transmission, 11
distribution, and facilities assets utilizing traceable, verifiable, and complete 12
asset knowledge and technological tools. I am also responsible for the 13
development of a strategic integrity management plan for the entirety of 14
these assets. In addition, I oversee Gas Operations’ Research and 15
Development Program. 16
Q 3 Please summarize your educational and professional background. 17
A 3 I received a bachelor of science degree in mechanical engineering from 18
University of California, Berkeley and a master’s degree in business 19
administration from UC Berkeley, Haas School of Business. I am also a 20
registered professional mechanical engineer in the state of California. 21
I started with PG&E in 2001 as a summer intern in the gas distribution 22
organization and after graduating from UC Berkeley began a full-time 23
position as a gas engineer. Since then, I have held a variety of positions 24
with increasing levels of responsibility in the Gas Engineering and 25
Operations organization, mainly focused on gas distribution functions. 26
In 2008, I transitioned to PG&E’s Human Resources Department where 27
I held various leadership roles. I returned to Gas Operations in 28
January 2012 as the director of Distribution Integrity Management. In 29
November 2013, I transitioned to the director of Transmission Integrity 30
Management, and in May 2014, I was promoted to the senior director of 31
Asset Knowledge and Integrity Management. 32
CCC-2
Q 4 What is the purpose of your testimony? 1
A 4 I am sponsoring Chapter 5, “Gas Operations,” in PG&E’s S-MAP 2
proceeding. 3
Q 5 Does this conclude your statement of qualifications? 4
A 5 Yes, it does. 5
CDH-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF CARY D. HARBOR 2
Q 1 Please state your name and business address. 3
A 1 My name is Cary D. Harbor, and my business address is Pacific Gas and 4
Electric Company, Diablo Canyon Power Plant. 5
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 6
(PG&E). 7
A 2 I am the director of Compliance, Alliance and Risk for the Diablo Canyon 8
Power Plant; in this capacity I am responsible for company compliance and 9
risk program oversight, matrixed organizations including business finance 10
and supply chain, and the PG&E management council representative to the 11
STARS LLC. 12
Q 3 Please summarize your educational and professional background. 13
A 3 I received a bachelor of science degree in nuclear engineering from 14
University of California, Santa Barbara, California, in 1989. I joined PG&E in 15
1989 as a power production engineer in the Engineering Department. 16
I have since held positions as the supervisor of Regulatory Services, 17
operations shift foreman/manager (senior reactor operator licensed by the 18
Nuclear Regulatory Commission), performance improvement manager, 19
quality verification director, and the Maintenance and Construction Services 20
director. Most recently I became the director of Compliance, Alliance and 21
Risk in 2012. 22
Q 4 What is the purpose of your testimony? 23
A 4 I am sponsoring Sections B.2. and C.2. of Chapter 4, “Electric Operations 24
and Nuclear Power Generation,” in PG&E’s S-MAP proceeding. 25
Q 5 Does this conclude your statement of qualifications? 26
A 5 Yes, it does. 27
JM-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF JANAIZE MARKLAND 2
Q 1 Please state your name and business address. 3
A 1 My name is Janaize Markland, and my business address is Pacific Gas and 4
Electric Company, 111 Stony Circle, Santa Rosa, California. 5
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 6
(PG&E). 7
A 2 I am the director of PG&E’s Enterprise and Operational Risk and Insurance 8
Department. My department is responsible for overseeing PG&E’s 9
Enterprise and Operational Risk Management (EORM) Program and for 10
procuring insurance to transfer PG&E’s residual financial risks that could 11
result from catastrophic property or casualty losses. 12
Q 3 Please summarize your educational and professional background. 13
A 3 I earned a bachelor of science degree in chemistry from the University of 14
British Columbia and a master of science degree in Environmental 15
Management from Royal Roads University in Victoria, British Columbia. 16
I am a member of the Enterprise Risk Management Utilities Roundtable 17
and serve as chair of the Edison Electric Institute Enterprise Risk 18
Management Task Force Steering Committee. 19
Prior to my career in the EORM and Insurance Department, I held a 20
variety of roles at PG&E, including manager of Compliance and Ethics and 21
positions in the Safety and Shared Services organization, where I provided 22
direct environmental compliance support to PG&E’s operating units. Before 23
joining PG&E, I worked at BC TEL, a telephone utility based in Burnaby, 24
British Columbia, and its successor company, Alberta-based TELUS 25
Corporation, where I developed an environmental program governing the 26
newly merged companies. 27
Q 4 What is the purpose of your testimony? 28
A 4 I am sponsoring the following testimony in PG&E’s S-MAP proceeding: 29
Chapter 2, “Companywide Models and Approaches for Assessing Risk.” 30
Chapter 6, “Risk Lexicon.” 31
Q 5 Does this conclude your statement of qualifications? 32
A 5 Yes, it does. 33
JLM-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF JAMIE L. MARTIN 2
Q 1 Please state your name and business address. 3
A 1 My name is Jamie L. Martin, and my business address is Pacific Gas and 4
Electric Company, 77 Beale Street, San Francisco, California. 5
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 6
(PG&E). 7
A 2 I currently hold the position of director of Economic and Project Analysis. In 8
this capacity, I supervise: 9
Financial analysis and economic evaluations concerning a range of 10
investment matters. 11
The Risk Informed Budget Allocation process as part of the Company’s 12
Integrated Planning Process. 13
Business case guidance and reviews of major capital project proposals. 14
I report to the Vice President, Finance, of PG&E. 15
Q 3 Please summarize your educational and professional background. 16
A 3 I graduated from the University of San Francisco, in 2004, with a bachelor of 17
science degree in finance. I joined PG&E in 2007 as a senior business 18
analyst in the Finance organization, specifically in Project Finance. I have 19
since held a succession of positions in the finance organization. In 2009, 20
I was promoted to supervisor in the Gas & Electric Transmission and 21
Distribution Business Finance organization, responsible for operational 22
financial planning, budgeting and forecasting. In 2010, I was promoted to 23
manager in the Power Generation Business Finance organization, where 24
I was responsible for managing a team that supported operational financial 25
planning, budgeting and forecasting. In 2012, I completed a 6-month 26
rotation as manager of Investor Relations, where I was responsible for 27
communication with the investment community and prepared senior 28
leadership for quarterly earnings calls and expectations for future 29
performance. In late 2012, I became manager of the Financial Forecasting 30
& Reporting team, where I was responsible for enterprise-level earnings 31
forecasts, year-over-year and long-term budgets and forecasts, functional 32
JLM-2
area income statement analysis and board of director financial materials. 1
I assumed my current position in March 2014. 2
Q 4 What is the purpose of your testimony? 3
A 4 I am sponsoring Chapter 3, “Companywide Models and Approaches to Risk 4
Informed Budget Allocation,” in PG&E’s S-MAP proceeding. 5
Q 5 Does this conclude your statement of qualifications? 6
A 5 Yes, it does. 7
SJS-1
PACIFIC GAS AND ELECTRIC COMPANY 1
STATEMENT OF QUALIFICATIONS OF SHELLY J. SHARP 2
Q 1 Please state your name and business address. 3
A 1 My name is Shelly J. Sharp, and my business address is Pacific Gas and 4
Electric Company, 77 Beale, San Francisco, California. 5
Q 2 Briefly describe your responsibilities at Pacific Gas and Electric Company 6
(PG&E). 7
A 2 I am currently the senior director, General Rate Case and Regulatory 8
Support. My responsibilities include overseeing the development of General 9
Rate Cases (GRC) as well as various other applications before the 10
California Public Utilities Commission, ensuring compliance with items from 11
prior GRCs, and directing the efforts of PG&E’s regulatory support functions. 12
Q 3 Please summarize your educational and professional background. 13
A 3 I graduated with a bachelor of science degree in business administration/ 14
finance from California State University, Sacramento, in 1984. In 1985, 15
I graduated from Golden Gate University in San Francisco, with a master’s 16
degree in business administration/finance. 17
I joined PG&E in 1985. From 1985 until 1997, I held various analyst and 18
supervisory positions within the regulatory area including: regulatory affairs 19
analyst, rates analyst, resource analyst, supervisor – Gas Rates, and 20
manager – Electric Rates. In 1997, I took over as the director of the Rates 21
Department, responsible for both gas and electric revenue allocation and 22
rate design. In 2003, I became the director of Billing, Revenue and 23
Records. In 2007, I became the senior director of Service and Sales in the 24
Customer Care organization. In February 2008, I became the senior 25
director of Customer Field Service within the Customer Care organization. 26
Q 4 What is the purpose of your testimony? 27
A 4 I am sponsoring Chapter 1, “Overview and Summary,” in PG&E’s S-MAP 28
proceeding. 29
Q 5 Does this conclude your statement of qualifications? 30
A 5 Yes, it does. 31