Description Cost Comments
Design $74,625 TLC - encumbered
$2,695 TLC - proposed additional services to complete design for Attachment F items
GMP $937,553 Wharton SmithReserve $100,000
Subtotal $1,114,873
Project Manager / Field Coordinator $25,000Admin / Support $10,000Permitting / Inspections $10,000Accounting $5,000
Subtotal $50,000
TOTAL $1,164,873
Ocean Breeze ESFacilities Renewal
Administrative Costs
GMP scope of work includes central mechanical plant renewal and air conditioning and air distribution system renewal per Attachment F - Sales Tax Funded Detail Report
NOTE: TLC has unused design funds that will be utilized to complete the design for most Attachment F Facility Renewal items. Upon completion of the design, these items will be priced by Wharton Smith and submitted to the Board as a change order.