108

NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section
Page 2: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION

SECTION 015639 - TEMPORARY TREE PROTECTION PART 1 - GENERAL 1.1 SUMMARY

A. Section includes general protection and pruning of existing trees that are affected by execution of the Work, whether temporary or permanent construction.

1. Protect existing trees indicated to remain.

1.2 DEFINITIONS

A. Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction, and defined by a circle concentric with each tree with a radius 1.5 times the diameter of the drip line unless otherwise indicated.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated: Protection-zone fencing Protection-zone signage

B. Samples: For each type of product indicated in sealed plastic bags labeled with

composition of materials by percentage of weight: Topsoil Organic mulch

C. Tree Pruning Schedule: Written schedule detailing scope and extent of pruning of trees to

remain that interfere with or are affected by construction. D. Existing Conditions: Documentation of existing trees indicated to remain, which

establishes preconstruction conditions that might be misconstrued as damage caused by construction activities.

1.4 QUALITY ASSURANCE

A. Prior to start of construction, the Contractor shall coordinate with the Owner’s representative to review the installed tree protection measures. Construction shall not proceed until tree protection measures have been approved by the Owner’s representative. The Contractor shall maintain tree protection measures throughout project construction.

Page 3: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 015639 - 2 TEMPORARY TREE PROTECTION

PART 2 - PRODUCTS 2.1 MATERIALS

A. Topsoil: Natural or cultivated top layer of the soil profile or manufactured topsoil; containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 1 inch (25 mm) in diameter; and free of weeds, roots, and toxic and other non-soil materials.

B. Organic Mulch: Shredded bark and bark chips free from deleterious materials. C. Protection-Zone Fencing: Fencing fixed in position and meeting one of the following

requirements. Previously used materials may be used when approved by Owner’s Representative.

1. Temporary chain link construction fence. 2. Plastic construction fencing constructed of high-density extruded and stretched

polyethylene fabric with 2-inch (50-mm) maximum opening in pattern and supported by tubular or T-shape galvanized-steel posts spaced not more than 8 feet (2.4 m) apart. Color: high-visibility orange, non-fading. Height: 6 feet.

D. Protection-Zone Signage: Shop-fabricated, rigid plastic or metal sheet with attachment

holes pre-punched and reinforced; “Tree Protection Zone. Do Not Enter” legibly printed with non-fading lettering.

PART 3 - EXECUTION 3.1 EXAMINATION AND PREPARATION

A. General: Contractor shall be responsible for care and preservation of existing trees indicated to remain.

B. Erosion and Sedimentation Control: Examine the site to verify that temporary erosion-

and sedimentation-control measures are in place. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.

C. Protect tree root systems from damage caused by runoff or spillage of noxious materials

while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations.

D. Protection Zones: Mulch areas inside protection zones with 4-inch average thickness of

organic mulch. Do not place mulch within 6 inches of tree trunks. E. Trees Indicated to Remain: The following trees shall remain: 1. As indicated in the Contract Documents.

Page 4: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 015639 - 3 TEMPORARY TREE PROTECTION

2. As tagged by Owner’s Representative in the field prior to commencement of demolition operations.

3.2 PROTECTION ZONES

A. Protection-Zone Fencing: Install protection-zone fencing along edges of protection zones in a manner that will prevent people from easily entering protected area except by entrance gates. Provide temporary barriers around each tree, or around each group of trees at drip line. 1. Access Gates: Install where needed for access.

B. Protection-Zone Signage: Install protection-zone signage in visibly prominent locations in a manner approved by Owner’s Representative.

C. Maintain protection-zone fencing and signage in good condition as acceptable to Owner’s

Representative and remove when construction operations are complete and equipment has been removed from the site.

D. Carefully supervise excavating, grading, filling, and subsequent construction operations

to ensure that tree protection zone is not impacted and to ensure there is no damage to tree roots, bark, or other features.

F. The following actions are prohibited within protection zone:

1. Vehicular traffic or parking. 2. Storage of construction materials, debris, or excavated material. 3. Dumping of refuse or chemicals, or liquids. 4. Puddling or continuously running water. 5. Diesel or gasoline equipment running adjacent to protection zone. 6. Foot traffic. 7. Erection of sheds or structures.

3.3 INSTALLATION OF UTILITIES

A. If irrigation or utility work is required within root zones, irrigation lines or utilities shall

be installed by hand excavating under roots or boring under the root zone. Minimum 12 inch clearance shall be provided between the hand excavation or bore and the tree roots. Do not cut tree roots over 1” diameter.

3.4 ROOT PRUNING

A. Prune only with Owner’s Representative’s approval. Prune only roots that are outside tree protection zone and are affected by temporary and permanent construction. Prune roots as follows:

1. Cut roots manually by digging a trench and cutting exposed roots with sharp pruning instruments; do not break, tear, chop, or slant the cuts. Do not use a backhoe or other equipment that rips, tears, or pulls roots.

Page 5: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 015639 - 4 TEMPORARY TREE PROTECTION

2. Temporarily support and protect roots from damage until they are permanently covered with soil. 3. Maintain natural cover of dirt or duff around root systems. Replace natural cover if necessary. 4. Cover exposed roots with burlap and water regularly. 5. Backfill as soon as possible. 6. Employ qualified tree surgeon to cut and remove roots, and to treat cuts. 7. Prune under Owner’s Representative’s direction. 8. Do not cut roots greater than one inch in diameter without advance notice to Owner’s Representative. B. Stockpiles: Place stockpiles of topsoil and other excavated material to prevent slough off onto root systems of existing trees. C. Contaminants: Dispose of solvents, oils and other materials, harmful to plant life, in containers and remove from site. Remove and replace contaminated soil with topsoil at Substantial Completion of Work. 3.5 CROWN PRUNING A. Prune branches that are affected by temporary and permanent construction. Prune branches as follows: 1. Prune only with Owner’s Representative’s approval. 2. Employ qualified tree surgeon to prune and remove branches, and to treat cuts. 3. Prune trees to remain to compensate for root loss caused by damaging or cutting root system. Provide subsequent maintenance during Contract period as recommended by certified arborist. 4. Cut branches with sharp pruning instruments; do not break or chop. 5. Do not apply pruning paint to wounds, excepted for scars resulting from removal of branches over one (1) inch in diameter which shall be treated with heavy coat of accepted tree paint. 6. Cut close to boles in manner that tree will present balanced appearance. 3.6 REGRADING A. Lowering Grade: Where new finish grade is indicated below existing grade around trees, slope grade beyond the protection zone. Maintain existing grades within the protection zone. B. Raising Grade: Where new finish grade is indicated above existing grade around trees, slope grade beyond the protection zone. Maintain existing grades within the protection zone.

C. Minor Fill within Protection Zone: Where existing grade is 2 inches (50 mm) or less below elevation of proposed finish grade, fill with topsoil. Place topsoil in a single uncompacted layer and hand grade to required finish elevations.

Page 6: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 015639 - 5 TEMPORARY TREE PROTECTION

3.7 WATERING

A. Trees: Water at least every fourteen (14) days during construction period by forming suitable dikes and soaking devices at drip line and applying approximately six (6) inches of water each time. Water frequency during winter rain season may be reduced upon approval by Owner’s Representative, which approval may be granted or withheld in Owner’s Representative’s sole discretion.

3.8 REPAIR AND REPLACEMENT A. General: Repair or replace trees indicated to remain that are damaged by construction operations, in a manner approved by Owner’s Representative.

1. Owner’s Representative will determine repair and replacement requirements. 2. The Contractor shall have a certified arborist perform root cutting, branch

pruning, and all other repairs required due to damage of trees. 3. Treatment of damaged trunks, limbs, and roots shall be in accordance with

certified arborist's written instructions. 4. Treatment and repairs shall be performed within 24 hours of damage. 5. If it is determined that a damaged tree must be removed and replaced, the tree

shall be replaced with a tree of the same species and size. If a replacement tree is not available in a size equal to the damaged tree, a suitable replacement and associated monetary credit to the Owner will be determined by the Owner and the Owner’s Representative, whose decision shall be final.

3.9 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Disposal: Remove trash and debris, and dispose of them in a licensed land fill or other legally approved waste disposal site.

END OF SECTION

Page 7: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 1 ELECTRICAL GENERAL PROVISIONS

SECTION 260000 – ELECTRICAL GENERAL PROVISIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, and Division 1 Specification sections, apply to work of this section.

1.2 DESCRIPTION OF WORK

A. General: This section specifies several categories of provisions for electrical work including: 1) Certain adaptive expansions of requirements specified in Division 1, 2) General performance requirements within the electrical systems as a whole, and 3) General work to be performed as electrical work, because of its close association.

1.3 SUMMARY OF ELECTRICAL WORK A. Drawings: Refer to the E-series drawings for graphic representations, schedules and

notations showing electrical work. B. Specifications: Refer to the Division 26 sections for the primary technical specifications of

electrical work.

C. General Outline: The facilities and systems of the electrical work can be described (but not by way of limitation) as follows: 1) Power distribution system, including the electrical connecting of equipment not specified to be connected as work of another division, 2) Motor starters and control/protection work as indicated, 3) Systems of branch circuits for lighting and convenience outlets, 4) Fire alarm system.

1.4 COORDINATION OF ELECTRICAL WORK

A. General: Refer to the Division 1 sections for general coordination requirements applicable to the entire work. It is recognized that the contract documents are diagrammatic in showing certain physical relationships which must be established within the electrical work and in its interface with other work including utilities and mechanical work, and that such establishment is the exclusive responsibility of the Contractor.

1. Arrange electrical work in a neat, well organized manner with conduit and similar

services running parallel with primary lines of the building construction. 2. Locate operating and control equipment properly to provide easy access, and

arrange entire electrical work with adequate access for operation and maintenance. 3. Advise other trades of openings required in their work for the subsequent move-in

of large units of electrical work (equipment). B. Coordination Drawings: For areas, where several elements of electrical (or combined

Page 8: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 2 ELECTRICAL GENERAL PROVISIONS

mechanical and electrical) work must be sequenced and positioned with precision in order to fit into the available space, prepare coordination drawings (shop drawings) showing the actual physical dimensions (at accurate scale) required for the installation. Prepare and submit these coordination drawings, if required, prior to purchase –fabrication purchase-fabrication-installation of any of these elements involved in the coordination.

C. The drawings and these specifications are complementary, each one to the other, and what

is called for by one shall be as binding as if called for by both. Carefully examine the drawings and specifications and report any discrepancies affecting the work to the Architect. The Architect will issue such written instructions or interpretations as may be required.

D. The electrical plans are diagrammatic, but shall be followed as closely as actual

construction and the work of the other trades will allow. Such minor changes as are necessary to make the electrical work conform to the work of other trades and to the building shall be made without cost to the Owner. Minor changes are things such as moving a light switch within a room to be on the proper side of the door swing, or moving a light fixture over one or two ceiling tiles.

E. Branch circuit numbers are for guidance only and need not necessarily conform to the

finished job. Actual circuit numbers used shall be recorded on the record documents, and noted correctly on the panel schedules.

F. The maximum number of circuits combined in one raceway shall be three; no circuit shall be combined without prior approval of the Architect or unless specifically shown on the drawings.

1.5 QUALITY ASSURANCE AND STANDARDS

A. General: Refer to the General conditions, Supplementary conditions and Division 1 for general administrative/procedural requirements related to compliance with codes and standards. Specifically, for the electrical work (in addition to standards specified in individual work sections), the following standards are imposed, as applicable to the work in each instance:

1. AWS standards for welding. 2. ANSI C 2, National Electrical Safety Code. 3. ANSI C 73, Dimensions of attachment plugs and receptacles. 4. NECA standards for installation. 5. NEMA standards for materials and products.

1.6 LAWS, CODES AND ORDINANCES A. All work and material shall conform to the requirements of OSHA and all national and

state Laws and ordinances having jurisdiction at the job site. The (NEC) National Electrical Code, 2008 Edition, or latest edition being enforced, shall be strictly adhered to NEC

Page 9: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 3 ELECTRICAL GENERAL PROVISIONS

requirements are considered "minimum requirements". Where requirements of the contract documents exceed NEC, the contract documents govern.

B. Contractors shall be duly licensed to perform the work required, as noted in the

Supplementary Conditions. C. Permits are required as noted in the General Conditions.

D. Upon completion of the work, furnish to the Owner a certificate of final inspection and approval from the Electrical inspection bureau having jurisdiction.

E. All electrical systems shall be grounded in strict accordance with the requirements of the

National Electrical Code.

1.7 INDUSTRY PUBLICATION STANDARDS

A. The publications and standards of the latest issue at the time of bid, of the following organizations, where referenced in these specifications or on the drawings, shall apply:

1. ANSI--- American National Standards Institute 2. ASTM--- American Society of Testing and Materials 3. CBM---- Certified Ballast Manufacturers Association 4. IEEE--- Institute of Electrical and Electronic Architects 5. IPCEA- -Insulated Power Cable Engineer’s Association 6. NEC-- -- National Electrical Code 7. NECA--- National Electrical Contractors Association 8. NEMA--- National Electrical Manufacturers Association

9. NESC- - National Electrical Safety Code

10. NFPA-- National Fire Protection Association 11. UL--- -- Underwriters Laboratory 12. IESNA- -Illuminating Engineering Society of North America 1.8 SUBMITTALS

A. General: Refer to the General Conditions, Supplementary Conditions and Division1 for general requirements concerning work related and administrative submittals.

B. General:

Page 10: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 4 ELECTRICAL GENERAL PROVISIONS

1. Submittal data shall be bound in a 3 ring, 8-1/2 inches by 11 inches binder with a table of contents listing items in order of specification section and paragraph number.

2. Submittals shall consist of detailed shop drawings, specifications, catalog "cuts"

and data sheets containing physical and dimensioned information, performance data, electrical characteristics, materials used in fabrication, material finish and those which are excluded.

3. Contractor agrees that shop drawing submittals are not change orders; that the

purpose of shop drawing submittals by the contractor is to demonstrate that the contractor understands the design concept, that he demonstrates his understanding by indicating which equipment and material he intends to furnish and install and by detailing the fabrication and installation methods he intends to use.

C. Specific Requirements: The following items shall be submitted (as a minimum) in accordance with Paragraphs 1.08.B.1 through 3 (above): 1. Conduit and fittings.

2. 120-600 Volt Wiring

3. Wiring devices and plates.

4. Light fixtures and lamps

5. Panels, starters, contactors, relays, etc.

6. Safety switches.

7. Grounding.

8. Fire alarm equipment and calculations.

1.9 PRODUCT HANDLING

A. Use all means necessary to protect electrical materials and equipment before, during and after installation and to protect the installed work of other trades. In the event of damage, immediately make all repairs and replacements necessary to the approval of the Architect and at no extra cost .

1.10 WARRANTY, GUARANTEE

A. As described in the General Conditions and Supplementary Conditions the work to be performed shall be guaranteed for a period of one year after substantial completion.

PART 2 - PRODUCTS

A. General: Refer to the General Conditions, Supplementary Conditions and Division 1 sections for general requirements on products, materials and equipment. The following

Page 11: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 5 ELECTRICAL GENERAL PROVISIONS

provisions expand the requirements as applicable to electrical work: 1. All material shall be new and shall bear the label of the Underwriter's Laboratories,

Inc.,or be listed under reexamination service. All materials shall be of the best grade and latest pattern of manufacturer as specified.

2. All work shall be performed in a neat, workmanlike manner and shall present a

neat mechanical appearance when completed. 3. All similar materials and equipment shall be the product of the same manufacturer. 4. Where no specific material, apparatus or appliance is mentioned, any first-class

product made by a reputable manufacturer may be used, providing it conforms to the contract requirements and meets the approval of the Architect.

5. Materials and equipment shall be the standard products of manufacturers regularly

engaged in the production of such material and shall be the manufacturer's current and standard design.

a. Altitude: Equipment affected by altitude shall perform satisfactorily for

the function intended at the altitude of the project site.

b. Compatibility: Provide products which are compatible with other products of the electrical work, and with other work requiring interface with the electrical work, including electrical connections and control devices. For exposed electrical work, coordinate colors and finishes with other work.

c. Substitution: Refer to the General Conditions and Supplementary

Conditions for substitution guidelines.

d. Work Quality: Fabrication, erection and installation of the complete electrical system shall be done in a first class workmanlike manner by qualified personnel experienced in such work and shall proceed in an orderly manner so as not to hold up the progress of the project. The Contractor shall check all areas and surfaces where electrical equipment material is to be installed, removed or relocated and report any unsatisfactory conditions to the Architect before starting work. Commencement of work signifies this Contractor's acceptance of existing conditions. In the acceptance or rejection of the finished installation, no allowance will be made for lack of skill on the part of the workmen.

PART 3 - EXECUTION 3.1 ELECTRICAL SYSTEM IDENTIFICATION

A. General: Provide engraved plastic laminated nameplates at all locations of major units of electrical equipment including panelboards, control centers, alarm and similar systems. Nameplates shall be constructed from laminated phenolic plastic, 1/8 inch thick, 3-ply with black surfaces and white core. Engraving shall be with Roman Gothic lettering, 3/16 inch high, appropriately spaced. Nameplates shall be attached to control devices by use of self

Page 12: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 6 ELECTRICAL GENERAL PROVISIONS

tapping flat head chromium plated screws unless approved otherwise. Screw tips on inside of device cover shall be filed to provide a smooth, non-abrasive finish. Gluing, taping and riveting of nameplate to control device is not acceptable. Nameplate information shall include name of panel/equipment, panel electrical characteristics and branch/feeder circuit designation which feeds it. Nomenclature on nameplate(s) shall be similar to the following examples:

Panelboards: Panel L1CA 120/208V, 3PH, 4W CCT. A-28 Air Handler AHU-2 CCT. M2-2 Exhaust Fan EF-5 CCT. P-4

3.2 CUTTING AND PATCHING A. General: Comply with the requirements of the General Conditions, Supplementary

Conditions and Division 1 for the cutting and patching of other work to accommodate the installation of electrical work, except as individually authorized by the Architect, cutting and patching of electrical work to accommodate the installation of other work is not permitted.

B. Structural Limitations: Do not cut structural framing, walls, floors decks and other

members intended to withstand stress, except with the Architect's written authorization. Authorization will be granted only where there is no other reasonable method for completing the electrical work, and where the proposed cutting clearly does not materially weaken the structure.

C. Patching: Where patching is required to restore other work because of either cutting or

other damage inflicted during the installation of electrical work, engage the original installer to complete the patching of the other work. Restore the other work in every respect, including the elimination of visual defects

in exposed finishes, as judged by the Architect. 3.3 EXCAVATING FOR ELECTRICAL WORK A. General: The work of this article is defined to include whatever excavating and backfilling

is necessary to install the electrical work. Coordinate the work with other excavating and backfilling in the same area, including dewatering, flood protection provisions and other temporary facilities. Coordinate the work with other work in the same area, including other underground services (existing and new), landscape development, paving, and floor slabs on grade. Coordinate with weather conditions and provide temporary facilities needed for protection and proper performance of excavating and backfilling.

3.4 CONCRETE FOR ELECTRICAL WORK A. General: The work of this article is defined to include whatever concrete work is necessary

or shown specifically to install the electrical work; but excluding equipment base grouting.

Page 13: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 7 ELECTRICAL GENERAL PROVISIONS

Coordinate the work with other work, particularly other concrete work and accessories.

1. General Standards: Except as otherwise indicated, comply with applicable provisions of Division 3 sections for electrical work concrete, including formwork, reinforcement, mix design, materials (if not noted on drawings, use mix designs and materials accepted for Division 3 work where possible), admixtures, accessories (including waterstops), placing of wet concrete, finishing, curing, protecting, testing, submittals, and other requirements of the concrete work. Refer instances of uncertain applicability to the Architect for resolution

before proceeding. 3.5 TESTING AND COORDINATION

A. General: Refer to the General Conditions, Supplementary Conditions and Division 1 ections for general closeout requirements for the project. Upon completion of the work, the various systems operated under load conditions shall be tested for short circuits and grounds in accordance with the method and resistance values outlined in the National Electrical Code and for load balance on feeders and branch circuits.

B. The complete system shall operate satisfactorily in every respect. Make any repairs or

adjustments necessary to this end to the satisfaction of the Architect. C. Furnish all instruments and labor for testing. D. Coordination with Mechanical: Coordinate closeout operations with closeout of

mechanical systems and other power consuming equipment. Accurately record on record documents locations of all conduits which are underground. Test run electrical equipment in coordination with test runs of mechanical system. Clean and lubricate operational equipment. Instruct Owner's operating personnel thoroughly in the operation, sequencing, maintenance and safety/emergency provisions of the electrical systems. Turn over the operations to the Owner's personnel at the time(s) of substantial completion. Until the time of final acceptance of the total work of the contract, respond promptly with consultation and services to assist the Owner's personnel with operation of the electrical systems.

3.6 SAFETY A. Contractor shall not connect permanent utility power to the electrical distribution system

until it is safe. Contractor shall secure all panel locations or utilize lock-out/tag-out procedures. Perform work in accordance with OSHA, NFPA 70, NFPA 70E, NESC and other applicable codes to maintain electrical safety at the construction site.

3.7 MISCELLANEOUS ITEMS

A. Miscellaneous items not covered in these specifications shall be as indicated on the drawings, installed and connected by the proper method and as recommended by the manufacturer.

3.8 RECORD DOCUMENTS

Page 14: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260000 - 8 ELECTRICAL GENERAL PROVISIONS

A. During progress of the Work, maintain an accurate record of the installation of the system. Maintain these drawings as called for in the General Conditions, Supplementary Conditions and Division 1 specification section.

Page 15: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 1 ELECTRICAL CONNECTIONS FOR EQUIPMENT

SECTION 260503 – ELECTRICAL CONNECTIONS FOR EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this section.

B. This section is a Division 26 Basic Materials and Methods section, and is part of each

Division-25 and Division -26 section making reference to electrical connections for equipment specified herein.

1.2 DESCRIPTION OF WORK

A. Extent of electrical connections for equipment is indicated by drawings and schedules. Electrical connections are hereby defined to include connections used for providing electrical power to equipment.

B. Applications of electrical connections specified in this section include the following:

1. From electrical source to motor starters. 2. From motor starters to motors. 3. To lighting fixtures. 4. To transformers and similar current adjustment features of equipment. 5. To grounds including earthing connections. 6. To master units of communication, signal, alarm, (clock, public address, sound, and

video system).

C. Electrical connections for equipment, not furnished as integral part of equipment, are specified in Division-25 and other Division-26 sections, and are work of this section.

D. Motor starters and controllers, not furnished as integral part of equipment, are specified in

applicable Division-26 sections, and are work of this section.

E. Refer to Division-25 sections for motor starters and controllers furnished integrally with equipment; not work of this section.

F. Junction boxes and disconnect switches required for connecting motors and other electrical

units of equipment are specified in applicable Division-26 sections, and are work of this section.

G. Electrical identification for wire/cable conductors is specified in Division-26 section, "Electrical Identification", and is work of this section.

Page 16: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 2 ELECTRICAL CONNECTIONS FOR EQUIPMENT

H. Raceways and wires/cables required for connecting motors and other electrical units of equipment are specified in applicable Division-26 sections, and are work of this section.

I. Refer to other Division-26 sections for junction boxes and disconnect switches required for

connecting motors and other electrical units of equipment; not work of this section.

J. Refer to Division-25 for control system wiring; not work of this section.

K. Refer to sections of other Divisions for specific individual equipment power requirements, not work of this section.

1.3 QUALITY ASSURANCE

A. Manufacturer: Firms regularly engaged in manufacture of electrical connectors and terminals, of types and ratings required, and ancillary connection materials, including electrical insulating tape, soldering fluxes, and cable ties, whose products have been in satisfactory use in similar service for not less than 5 years.

B. Installer's Qualifications: Firms with at least 2 years of successful installation experience

with projects utilizing electrical connections for equipment similar to that required for this project.

C. NEC Compliance: Comply with applicable portions of NEC as to type of products used

and installation of electrical power connections (terminals and splices), junction boxes, motor starters, and disconnect switches.

D. IEEE Compliance: Comply with Std. 241, "IEEE Recommended Practice for Electric

Power Systems in Commercial Buildings" pertaining to connections and terminations.

E. ANSI Compliance: Comply with applicable ANSI/NEMA and ANSI/EIA standards pertaining to products and installation of electrical connections for equipment.

F. UL Compliance: Comply with Ul Std. 486A, "Wire Connectors and Soldering Lugs for

Use with Copper Conductors" including, but not limited to, tightening of electrical connectors to torque values indicated. Provide electrical connection products and materials which are UL-listed and -labeled.

G. ETL Compliance: Provide electrical connection products and materials which are ETL-listed and -labeled.

1.4 SUBMITTALS

A. Product Data: Submit manufacturer's data on electrical connections for equipment products and materials.

Page 17: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 3 ELECTRICAL CONNECTIONS FOR EQUIPMENT

B. None Required. 1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver electrical connection products wrapped in proper factory-fabricated type containers.

B. Store electrical connection products in original cartons and protect from weather, construction traffic and debris.

C. Handle electrical connection products carefully to prevent breakage, denting, and scoring

finish. PART 2 - PRODUCTS 2.1 MATERIALS AND COMPONENTS

A. General: For each electrical connection indicated, provide a complete assembly of materials, including but not necessarily limited to, pressure connectors, terminals (lugs), electrical insulating tape, heat-shrinkable insulating tubing, cable ties, solderless wire nuts, and other items and accessories as needed to complete splices and terminations of the type indicated.

B. Metal Conduit, Tubing and Fittings:

1. General: Provide metal conduit, tubing and fittings of the types, grades, sizes and

weights (wall thicknesses) indicated for each type service. Where types and grades are not indicated, provide proper selection as determined by Installer to fulfill wiring requirements and comply with NEC requirements for raceways. Provide products complying with Division-26 basic materials and methods section "Raceways", and in accordance with the following listing of metal conduit, tubing and fittings.

a. Rigid steel conduit. b. Rigid metal conduit fittings. c. Electrical metallic tubing. d. EMT fittings. e. Flexible metal conduit. f. Flexible metal conduit fittings. g. Liquid-tight flexible metal conduit. h. Liquid-tight flexible metal conduit fittings.

C. Wire, Cable, and Connectors:

1. General: Provide wires, cables and connectors complying with Division 26 basic

electrical materials and methods section "Wires and Cables".

2. Wires/Cables: Unless otherwise indicated, provide wires/cables (conductors) for electrical connections which match, including sizes and ratings, of wires/cables

Page 18: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 4 ELECTRICAL CONNECTIONS FOR EQUIPMENT

which are supplying electrical power. Provide copper conductors with conductivity of not less than 98% at 20 degrees C (68 degrees F).

3. Connectors and Terminals: Provide electrical connectors and terminals which mate

and match, including sizes and ratings, with equipment terminals and are recommended by equipment manufacturer for intended applications.

4. Electrical Connection Accessories: Provide electrical insulating tape, heat-shrinkable

insulating tubing and boots, electrical solder, electrical soldering flux, wirenuts and cable ties as recommended for use by accessories manufacturers for type services indicated.

PART 3 - EXECUTION 3.1 INSPECTION

A. Inspect area and conditions under which electrical connections for equipment are to be installed and notify General Contractor in writing of conditions detrimental to proper completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected in a manner acceptable to Installer. Contractor has full responsibility to verify whether circuit is energized or not and to perform all necessary lock-out/tag-out.

3.2 INSTALLATION OF ELECTRICAL CONNECTIONS

A. Install electrical connections as indicated; in accordance with equipment manufacturer's written instructions and with recognized industry practices, and complying with requirements of UL, NEC and NECA's "Standard of Installation" to ensure that products fulfill requirements.

B. Coordinate with other work, including wires/cables, raceway and equipment installation, as

necessary to properly interface installation of electrical connections for equipment with other work.

C. Connect electrical power supply conductors to equipment conductors in accordance with

equipment manufacturer's written instructions and wiring diagrams. Mate and match conductors of electrical connections for proper interface between electrical power supplies and installed equipment.

D. Cover splices with electrical insulation equivalent to, or of greater insulation resistivity

rating, than electrical insulation rating of those conductors being spliced.

E. Prepare cables and wires, by cutting and stripping covering, armor, jacket and insulation properly to ensure a uniform and neat appearance where cables and wires are terminated. Exercise care to avoid cutting through tapes which will remain on conductors. Also avoid "ringing" copper conductors while skinning wire.

F. Trim cables and wires as short as practicable and arrange routing to facilitate inspection,

testing and maintenance.

Page 19: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 5 ELECTRICAL CONNECTIONS FOR EQUIPMENT

G. Tighten connectors and terminals, including screws and bolts, in accordance with equipment

manufacturers published torque tightening values for equipment connectors. Accomplish tightening by utilizing proper torquing tools, including torque screwdriver, beam-type torque wrench, and ratchet wrench with adjustable torque settings. Where manufacturer's torquing requirements are not available, tighten connectors and terminals to comply with torquing values contained in UL's 486A.

H. Provide flexible conduit for motor connections, and other electrical equipment connections,

where subject to movement and vibration.

I. Provide liquid-tight flexible conduit for connection of motors and other electrical equipment where subject

to movement and vibration, and also where connections are subjected to one or more of the following conditions:

1. Exterior location. 2. Moist or humid atmosphere where condensate can be expected to accumulate. 3. Corrosive atmosphere. 4. Water spray. 5. Dripping oil, grease, or water.

J. Coordinate installation of electrical connections for equipment with equipment installation.

K. Perform all work in conformance with job requirements, other applicable sections of these

specifications, governing codes and ordinances, and manufacturer's instructions.

3.3 EQUIPMENT REQUIREMENTS

A. The electrical requirements for equipment specified or indicated on the drawings are based on information available at the time of design. If equipment furnished for installation has electrical requirements other than indicated on the electrical drawings, the Electrical Subcontractor shall make any required changes to wire and conduit size, controls, overcurrent protection and installation as required to accommodate the equipment supplied, at no additional charge to the Owner. The complete responsibility and costs for such adjustments shall be assigned to the respective section of this specification under which the equipment is furnished.

B. Motor starters and motor control devices that are not an integral part of the mechanical

equipment but are furnished with equipment will be turned over to the Electrical Subcontractor for installation and connection.

C. *RESPONSIBILITY LISTING

Wired: Power/Control Motors Furnished by Installed by Contr.

Page 20: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260503 - 6 ELECTRICAL CONNECTIONS FOR EQUIPMENT

Disc switches, thermal EC EC EC overload switches, manual on-off switches Magnetic motor starters- EC EC EC loose Magnetic motor starters- MC MC MC integral w/equipment Motorized valves, damper MC MC MC motors, solenoids, relays thermostats, E-P and P-E switches, etc. Temperature control panels MC MC MC boiler controls MC = Mechanical Subcontractor under Division 25. EC = Electrical Subcontractor under Division 26. * General Contractor shall be responsible for coordination of efforts between

Divisions 25 and 26.

D. Obtain from Mechanical Subcontractor a complete list of all mechanical equipment including load, voltage, phase, etc., at beginning of job prior to installation of any related electrical services. Advise Architect/Engineer of changes and adjust to meet requirements.

E. Electrical equipment shall be identified by the attachment of engraved nameplates as

specified.

F. Complete all identification cards for switches, starters and other devices in all distribution panelboards and similar pieces of equipment, on a typewriter in a neat manner and insert the card in the card holder behind a piece of clear plastic. Where the card size is insufficient for the proper identification of all circuits, the index shall be made on a large sheet of paper of proper proportion, and then photo-reduced to fit the card holder.

3.4 FIELD QUALITY CONTROL

A. Upon completion of installation of electrical connections, and after circuitry has been energized with rated power source, test connections to demonstrate capability and compliance with requirements. Ensure that direction of rotation of each motor fulfills requirement. Correct malfunctioning units at site, then retest to demonstrate compliance.

Page 21: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260519 - 1 WIRES AND CABLES

SECTION 260519- WIRES AND CABLES

PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the General Conditions,

Supplementary Conditions, and Division 1 Specification sections, apply to work of this section.

B. This section is a Division 26 Basic Materials and Methods section, and is part of each

Division 16 section making reference to wires and cables specified herein. 1.2 SUMMARY A. This Section includes wires, cables, and connectors for power, lighting, signal, control and

related systems rated 600 volts and less. Wiring for fire alarm is described in its section, wiring for voice, data and video is described in Division 26 specifications.

B. The applications for cable, wire and connectors required on the project are as follows:

1. Power distribution circuitry 2. Lighting circuitry 3. Equipment connections and controls circuitry 4. Special systems

1.3 SUBMITTALS A. Provide product literature submittal on wiring.

1.4 QUALITY ASSURANCE A. Regulatory Requirements: Comply with provisions of the following code:

1. NFPA 70 "National Electrical Code."

B. Conform to applicable codes and regulations regarding toxicity of combustion products of insulating materials.

C. UL Compliance: Provide components, which are listed and labeled by UL under the

following standards. 1. UL Std. 83 Thermoplastic-Insulated Wires and Cables. 2. UL Std. 486A Wire Connectors and Soldering Lugs for Use with Copper

Page 22: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260519 - 2 WIRES AND CABLES

Conductors.

D. NEMA/ICEA Compliance: Provide components which comply with the following standards:

1. WC-5 Thermoplastic-Insulated Wire and Cable for the Transmission and

Distribution of Electrical Energy. PART 2 - PRODUCTS 2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products which may be incorporated in the work include, but are not limited to, the following: 1. Wire and Cable:

a. American Insulated Wire Corp. b. Carol Cable Co. Inc. c. Senator Wire and Cable Co. d. Southwire Company.

2. Connectors for Wires and Cable Conductors:

a. AMP b. 3M Company c. O-Z/Gedney Co. d. Square D Company.

2.2 WIRING INSTALLED IN RACEWAYS

A. General: Provide wiring suitable for the temperature, conditions and location where installed. The following criteria is for single-insulated conductors installed in rigid conduit IMC, EMT, PVC, FMC, and liquidtight flexible conduit.

B. Conductors: Provide solid conductors for power and lighting circuits no. 10 AWG and

smaller. Provide stranded conductors for sizes no. 8 AWG and larger. C. Conductor Material: Copper, 98% conductivity, for all wires and cables. D. Insulation: Provide XHHW-2 insulation for all service entrance wires and, feeders larger

than #6. Forall other sizes provide THHN/THWN insulation. Color Coding for Phase Identification: All wiring #8 AWG and smaller shall have coloring integral to insulation.

Color code on the project is as follows:

Page 23: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260519 - 3 WIRES AND CABLES

208Y/120 Volts Phase Black A Red B Blue White Neutral Green Ground

E. For wire #6 AWG and larger that does not require color code integral to its insulation, colored electrical tape may be used for color coding, it shall cover not less than 6" of conductor within enclosure wherever possible. Color coding shall be with Scotch 35 tape by 3M Company or equal.

F. All wire on this project shall be new, unused, in good condition and shall be delivered in

standard coils, packages and reels. Samples of all wire shall be submitted by the Contractor when so requested by the Architect for the purpose of determining acceptability of the wire. Wire which has been rejected by the Architect shall not be used again. Such rejected wire shall be removed from the Owner's premises forthwith. Decisions as to the quality of the wire furnished and the acceptance of such wire shall be made by the Architect.

G. Size of conductors shall be not less than indicated. Branch circuit conductors shall be not

smaller than No. 12 AWG. Conductors for branch circuits of 120 volts more than 75 feet long, from panel to utilization point shall be No. 10 AWG. The selection of wire sizes for both feeder and branch circuits are used so that voltage drop conforms to the following: Voltage drop in the case of 120/208 volt branch circuits shall not exceed 3.0% at maximum load and 70.0% power factor. Service and feeders shall not exceed 2.0% voltage drop at maximum load and 85% power factor, iron conduit only considered.

H. Remote control wires other than class 2 remote control and signal circuits, shall be no

smaller than #14 conductors. Control wires shall be run in separate conduits. I. Lighting fixtures shall not be used for raceways for circuits other than parallel wiring of

fixtures. Install 90 degree C. minimum insulation wire within fixture wireways of fluorescent lighting fixtures.

J. When leaving a metal raceway or conduit in a cabinet, box, switch enclosure, control

enclosure or any other like member, conductors shall be protected by means of insulated bushings or end fittings.

K. Conductors may be run in multiple sizes 1/0 to 500 MCM inclusive provided all multiple

conductors are the same size, length and type of insulation. When run in multiple they shall be so arranged and terminated as to insure equal division of the total current between all conductors involved.

2.3 CONNECTORS FOR CONDUCTORS A. Provide UL-listed factory fabricated, solderless metal connectors of sizes, ampacity ratings,

materials, types and classes for applications and for services indicated. Use connectors with temperature ratings equal to or greater than those of the wires upon which used.

Page 24: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260519 - 4 WIRES AND CABLES

B. No splices or taps shall be made to any conductors except in outlet boxes, pullboxes, junction boxes, panelboard boxes, manholes, splice boxes or other accessible locations. All taps and splices shall be made with solderless connections and insulated in a manner providing an effective insulation equal to that of the adjoining wire insulation. Any splice or tap shall be made only on such conductors as are a component part of a single circuit.

PART 3 - EXECUTION 3.1 WIRING METHOD A. Use the following wiring methods: 1. Wire: install insulated conductors in raceways.

B. General: Install electrical cables, wires and connectors in compliance with NEC. C. Coordinate cable and wire installation work with electrical raceway and equipment

installation work, as necessary for proper interface. Prior to pulling cables or conductors into raceways, inspect interiors of raceways; remove burrs, dirt and construction debris.

D. Pull conductors simultaneously together where more than one is being installed in same

raceway. Use UL listed pulling compound or lubricant, when necessary. Care shall be exercised while installing wire in conduits so as not to injure conductor insulation. Bending radius of insulated wire or cable shall not exceed manufacturer's recommended values.

E. Use pulling means including, fish tape, cable, rope and basket weave wire/cable grips,

which will not damage cables or raceways. Maximum pulling tension on any wire or cable shall not exceed manufacturer's recommended values.

F. For wired systems not requiring wire in conduit, conceal all cable in finished spaces. G. Conductors shall not be pulled into conduits until after all plastering or concrete work is

completed and all conduits in which moisture has collected have been swabbed out. H. Keep conductor splices to a minimum. Splices shall not be permitted except in junction

boxes, outlet boxes or as previously listed in this section. Splices must be accessible. I. Install splices and taps connectors, which possess equivalent or better mechanical strength

and insulation rating conductors being spliced. J. Use splice and tap conductors which are compatible with the conductor material.

K. Provide adequate length of conductors within electrical enclosures and train the conductors to terminal points with no excess. Make terminations so there is no bare conductor at the terminal.

L. Tighten electrical connectors and terminals, including screws and bolts, in accordance with

manufacturer's published torque tightening values. Where manufacturer's torqueing

Page 25: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260519 - 5 WIRES AND CABLES

requirements are not indicated, tighten connectors and terminals to comply with tightening torques specified in UL 486A and UL 486B.

3.2 FIELD QUALITY CONTROL

A. Contractor shall perform meggar tests on all service entrance conductors, all feeders and any other conductors 250 kcmil and larger. The contractor shall submit the test results to the Architect within 48 hours of test, and at least 72 hours prior to permanent connection or energization. All test failures shall result in cable replacement.

B. Prior to energization, test wires for electrical continuity and for short circuits.

C. Prior to Contractor connecting of utility permanent power to the permanent electrical

distribution system, all panels and wiring circuits shall be fully terminated and all panel covers completely installed. If the above cannot be complied with, and the Contractor deviates from this, then he bears all the responsibility to provide lock-out/tag-outs and security of electrical rooms or rooms containing panels.

D. Subsequent to wire and cable hook-ups, energize circuits and demonstrate proper

functioning. Correct malfunctioning units, and retest to demonstrate compliance.

Page 26: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260526 - 1 GROUNDING

SECTION 260526 - GROUNDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including the General Conditions, Supplementary Conditions, and Division 1 Specification sections, apply to work of this section.

B. Division 26 Basic Materials and Methods sections apply to work of this section. 1.2 DESCRIPTION OF WORK A. Extent of grounding is indicated by drawings. B. Types of grounding in this section include the following: 1. Enclosures 2. Systems 3. Equipment 1.3 QUALITY ASSURANCE A. NEC Compliance: Comply with NEC as applicable to electrical grounding. B. ANSI/UL Compliance: Comply with requirements of ANSI/UL and UL

standards pertaining to grounding. Provide products which have been UL listed and labeled.

1.4 SUBMITTALS A. Product Data: Submit manufacturer's data on grounding devices and accessories. PART 2 - PRODUCTS 2.1 GROUNDING

A. Materials and Components: 1. General: Except as otherwise indicated, provide for each electrical

grounding indicated, with assembly of materials including, but not necessarily limited to, cables/wires, connectors, terminals (solderless lugs), grounding rods/electrodes and plate electrodes, bonding jumper braid, and other items and accessories needed for complete installation. Where more than one type meets indicated requirements, selection is

Page 27: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260526 - 2 GROUNDING

installer's option. Where materials or components are not otherwise indicated, comply with NEC, NEMA and established industry standards for applications indicated.

A. Electrical Bonding Jumpers: 1. Bonding Jumper Braid: Copper braided tape, constructed of 30 gauge

bare copper wires and properly sized for indicated applications. 2. Flexible Jumper Strap: Flexible flat conductor, 480 strands of 30 gauge

bare copper wire; 3/4" wide, 9-1/2" long; 48.250 CM. Protect braid with copper bolt hole ends with holes sized for 3/8 dia. bolts.

3. Electrical Grounding Conductors: Unless otherwise indicated, provide

electrical grounding conductors for grounding connections matching power supply wiring materials and sized according to NEC. All conduits and ducts shall have grounding conductors as noted on the drawings or required by NEC.

4. Bonding Plates, Connectors, Terminals and Clamps: Provide electrical

bonding plates, connectors, terminals and clamps as recommended by bonding plate, connector, terminal and clamp manufacturer for indicated applications.

PART 3 - EXECUTION 3.1 INSTALLATION OF ELECTRICAL GROUNDING A. General: Install electrical grounding systems as indicated on the drawings,

in accordance with recognized industry practices to ensure grounding protection complies with requirements. Comply with requirements of NEC, and NEMA standards for installation of grounding systems and devices. All non-metallic conduits and ducts shall have grounding conductors as noted on the drawings or required by NEC.

B. Coordinate with other electrical work as necessary to interface installation of

electrical grounding system and ground-fault protection devices with other work. C. Install clamp-on connectors only on thoroughly cleaned metal contact surfaces,

to ensure electrical conductivity and circuit integrity. 3.2 EQUIPMENT GROUNDING SYSTEM A. General: Provide a complete equipment grounding system in accordance with

the minimum code requirements and as further indicated on the drawings or specified. The equipment ground (green conductor) consists of metallic connections to ground non-current carrying metal parts of the wiring system or apparatus connected to the system.

Page 28: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260526 - 3 GROUNDING

B. Conduits: Where metallic conduits terminate without mechanical connection, provide ground bushing connected with a bare copper conductor to the ground bar in the electrical equipment. Install grounding conductor in each conduit or duct and in all conduit that does not have a built-in ground conductor. Those raceways used for telephone, sound, or low-voltage signals do not require a grounding conductor. All conduits terminating at communication backboards shall be provided with grounding bushings.

C. Feeders and Branch Circuits: Provide a separate green insulated equipment

grounding conductor for each single or three-phase feeder and each branch circuit with a three-phase protective device. Provide a separate green insulated equipment ground conductor for single phase branch circuits where indicated on the drawings. Where there are parallel feeders installed in more than one raceway each raceway shall have a green insulated equipment ground conductor.

D. Devices: Where a branch circuit ground conductor is not available, install a

minimum No. 12 green insulated equipment bonding conductor. Bond conductor from a grounding terminal in the respective outlet or junction box to the green ground terminal of all receptacles. This will be required regardless of receptacle being approved for application without separate bond conductor.

E. Motors: Install a separate green insulated equipment grounding conductor from

each separate starter through the conduit and flexible conduit to the ground terminal in the connection box mounted on the motor.

3.3 GROUNDING CONDUCTORS A. The grounding conductors shall be insulated copper, sized in accordance with

NEC 250.122. The conductors shall be continuous without joint or splice and shall be installed in conduit with the conduit bonded to the conductor at each end. Equipment grounding conductors shall be green insulated conductors with insulation equivalent to the insulation on the associated phase conductor, but not less than Type THW. The equipment grounding conductor or straps shall be sized in accordance with NEC. Where one feeder serves a series of panelboards or transformers, the equipment grounding conductor shall be continuous without splices. All connections shall be available for inspection and maintenance.

1. Connections: Clean surfaces thoroughly to bare metal before applying

ground lugs or clamps. Where galvanizing is removed from metal it shall be painted or touched up with "Galvanox", or equal. All grounding system connections which are made in inaccessible locations, i.e. underground, within concrete slabs, shall be made with Cadweld connections or approved equal.

Page 29: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260529 - 1 SUPPORTING DEVICES

SECTION 260529 –SUPPORTING DEVICES PART 1 - GENERAL 1.1 SECTION INCLUDES

A. Conduit and equipment supports.

B. Anchors and fasteners. 1.2 REFERENCES

A. Quality Control: Requirements for references and standards.

B. NECA - National Electrical Contractors Association.

C. ANSI/NFPA 70 - National Electrical Code.

1.3 SUBMITTALS – None Required. 1.4 REGULATORY REQUIREMENTS

A. Conform to requirements of ANSI/NFPA 70.

B. Furnish products listed and classified by Underwriters Laboratories, Inc., as suitable for purpose specified and shown.

PART 2 - PRODUCTS 2.1 PRODUCT REQUIREMENTS

A. Materials and Finishes: Provide adequate corrosion resistance.

B. Provide materials, sizes, and types of anchors, fasteners and supports to carry the loads of equipment and conduit. Consider weight of wire in conduit when selecting products.

C. Anchors and Fasteners:

a. Concrete Structural Elements: Use expansion anchors. b. Steel Structural Elements: Use beam clamps, spring steel clips. c. Concrete Surfaces: Use self-drilling anchors and expansion anchors. d. Hollow Masonry, Plaster, and Gypsum Board Partitions: Use toggle bolts. e. Solid Masonry Walls: Use expansion anchors and preset inserts. f. Sheet Metal: Use sheet metal screws. g. Wood Elements: Use wood screws.

2.2 STEEL CHANNEL

A. Manufacturer:

Page 30: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260529 - 2 SUPPORTING DEVICES

a. Unistrut. b. B-Line. c. Substitutions: Permitted.

B. Description: Painted steel. 2.3 SPRING STEEL CLIPS

A. Manufacturer:

a B-Line. b. Caddy. c. Substitutions: Permitted.

PART 3 -EXECUTION 3.1 INSTALLATION

A. Install products in accordance with manufacturer's instructions.

B. Provide anchors, fasteners, and supports in accordance with NECA "Standard of installation".

C. Do not fasten supports to pipes, ducts, mechanical equipment, and conduit.

D. Do not use powder-actuated anchors.

E. Obtain permission from Architect/Engineer before drilling or cutting structural members.

F. Fabricate supports from structural steel or steel channel. Rigidly weld members or use

hexagon head bolts to present neat appearance with adequate strength and rigidity. Use spring lock washers under all nuts.

G. Install surface-mounted cabinets and panelboards with minimum of four anchors.

H. In wet and damp locations use steel channel supports to stand cabinets and panelboards one

inch (25 mm) off wall.

I. Use sheet metal channel to bridge studs above and below cabinets and panelboards recessed in hollow partitions.

Page 31: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 1 ELECTRICAL BOXES AND FITTINGS

SECTION 260533 – ELECTRICAL BOXES AND FITTINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, the General Conditions, Supplementary

Conditions, and Division 1 Specification sections, apply to work of this section. 1.2 DESCRIPTION OF WORK A. Extent of electrical box and associated fitting work is indicated by drawings.

B. Types of electrical boxes and fittings specified in this section include the following:

1. Outlet boxes 2. Junction boxes 3. Pull boxes 4. Bushings 5. Locknuts 6. Knockout closures 1.3 QUALITY ASSURANCE A. NFPA Compliance: Comply with NEC as applicable to construction and installation of

electrical boxes and fittings.

B. UL Compliance: Comply with applicable requirements of UL 50, UL 514-Series, and UL 886 pertaining to electrical boxes and fittings. Provide electrical boxes and fittings which are UL-listed and labeled.

C. NEMA Compliance: Comply with applicable requirements of NEMA Stds/ Pub No.'s

OS1, OS2 and Pub 250 pertaining to outlet and device boxes, covers and box supports. D. Federal Specification Compliance: Comply with applicable requirements of FS W-C-

586, "Electrical Cast Metal Conduit Outlet Boxes, Bodies and Entrance Caps". 1.4 SUBMITTALS

A. Product Data: Submit manufacturer’s data on electrical boxes and fittings.

Page 32: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 2 ELECTRICAL BOXES AND FITTINGS

PART 2 - PRODUCTS 2.1 FABRICATED MATERIALS - STEEL A. Outlet Boxes: Provide galvanized coated flat rolled sheet-steel outlet wiring boxes, of

shapes, cubic inch capacities, and sizes, including box depths as indicated, suitable for installation at respective locations. Construct outlet boxes with mounting holes, and with cable and conduit-size knockout openings in bottom and sides. Provide boxes with thread screw holes, with corrosion-resistant cover and grounding screws for fastening surface and device type box covers, and for equipment type grounding.

B. Outlet Box Accessories: Provide outlet box accessories as required for each installation,

including box support mounting ears and brackets, wallboard hangers, box extension rings, fixture studs,cable clamps and metal straps for supporting outlet boxes, which are compatible with outlet boxes being used to fulfill installation requirements of individual wiring situations.

C. Device Boxes: Provide galvanized coated flat rolled sheet-steel non-gangable device

boxes, of shapes, cubic inch capacities, and sizes, including box depths as indicated, suitable for installation at respective locations. Construct device boxes for flush mounting with mounting holes, and with cable-size knockout openings in bottom and ends, and with threaded screw holes in end plates for fastening devices. Provide cable clamps and corrosion-resistant screws for fastening cable clamps, and for equipment type grounding.

D. Device Box Accessories: Provide device box accessories as required for each

installation, including mounting brackets, device box extensions, switch box supports, plaster ears, and plaster board expandable grip fasteners, which are compatible with device boxes being utilized to fulfill installation requirements for individual wiring situations.

E. Boxes for use with raceway systems shall not be less than 2-1/8 inches deep except

where shallower boxes required by structural conditions are approved. Boxes for other than lighting fixture and power shall be not less than 4 inches square.

F. Outlet boxes for various uses shall be Appleton boxes, or equal in quality and function of

the following order; Appleton nos. listed first, universal numbers listed in parenthesis: 1. In standard partitions and suspended ceilings for lighting fixture installations

where 3/4" conduits are employed, #40D3/4 (#54l7l 3/4) boxes shall be used; for 1/2" conduits #40D1/2 (#54171 1/2) shall be used.

2. In standard partitions and suspended ceiling areas where conduits of 1" size or

greater are employed, #4SD1 (#52171-1) boxes having a depth of 2-1/8" shall be used.

3. Wall switch and convenience outlets in standard partitions and where 3/4"

conduits are employed, #4SD 3/4 (#52171-3/4) boxes shall be used; for 1/2" conduits #4SD 1/2 (#52171-1/2) boxes shall be used.

Page 33: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 3 ELECTRICAL BOXES AND FITTINGS

4. In thin partitions measuring 3-1/2" or less and where 3/4" conduits are

employed, #4S 3/4 (#52151 3/4) boxes shall be used; for 1/2" conduits #4S 1/2 (52151 1/2) boxes shall be used.

5. Voices, Data, Video outlets shall be as detailed on the plans and described in

Division 26 specifications. G. The following requirements shall apply to exposed as well as concealed conduit systems.

When "gang" arrangements of outlets are employed, 2-3/4" deep "gang" boxes shall be used. These "gang" boxes shall have dimensions which are not smaller than those shown in the following table.

Number in Gang Size 3 4 - 1/2" X 8- 5/8" 4 4 - 1/2" X 10- 1/2" 5 4 - 1/2" X 12- 1/4" 6 4 - 1/2" X 14" 7 4 - 1/2" X 16" 8 4 - 1/2" X 17- 3/4" Where "gang" boxes are located in woodwork or in wooden partitions, the depth of the

boxes (shall) may be reduced to 1 - 3/4" H. Raintight Outlet Boxes: Provide corrosion-resistant cast metal raintight outlet wiring

boxes, of types, shapes and sizes, including depth of boxes, with threaded conduit holes for fastening electrical conduit,

I. Junction and Pull Boxes: Provide galvanized code gauge sheet steel junction and pull

boxes with screw on covers; of types, shapes and sizes to suit each respective location and installation; with welded seams and equipped with stainless steel nuts, bolts, screws and washers.

J. Terminal Cabinets: Junction boxes called for to be used as terminal cabinets for special

systems (Fire Alarm) shall be of NEMA Type I, surface mounting minimum 16 gauge steel thickness as manufactured by Circle A-W Products or approved equal. Boxes shall be provided with a ¾” plywood thick backboard sized for full area of box wall mounting surface. Furnish with hinged cover. Furnish terminal blocks where required or noted on the drawings for all wire splicing or terminations, Kulka 672 or equal in quality and construction. Number of terminal blocks shall be as required for all wires in terminal cabinets plus 50% spare.

K. Conduit Bodies: Provide galvanized cast-metal conduit bodies, of types, shapes and

sizes, to suit respective locations and installation, constructed with threaded-conduit-entrance ends, removable covers, and corrosion-resistant screws.

`L. Bushings, Knockout Closures and Locknuts: Provide corrosion resistant punched steel

Page 34: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 4 ELECTRICAL BOXES AND FITTINGS

box knockout closures, conduit locknuts and malleable iron conduit bushings, offset connectors, of types and sizes to suit respective installation requirements and applications.

PART 3 - EXECUTION 3.1 PERMITTED USES A. Steel boxes shall be used in all areas. 3.2 INSTALLATION OF BOXES AND FITTINGS A. General: Install electrical boxes and fittings as indicated, in accordance with

manufacturer's written instructions, applicable requirements of NEC and NECA's "Standard of Installation", and in accordance with recognized industry practices to fulfill project requirements.

B. Coordinate installation of electrical boxes and fittings with wire/cable and raceway

work. C. Provide weatherproof outlets for interior and exterior locations exposed to weather or

moisture. D. Provide knockout closures to cap all unused knockout holes where blanks have been

removed. E. Install electrical boxes and conduit bodies in those locations, which ensure ready

accessibility to enclosed electrical wiring. F. Avoid installing boxes back-to-back in walls. Provide not less than 6" (150 mm)

horizontal separation. If boxes are installed with less than 6” separation in fire rated walls then the contractor shall provide fire stop material around the boxes.

G. Avoid installing aluminum products in concrete. H. Position recessed outlet boxes accurately to allow for surface finish thickness. I. Boxes shall be square and flush with finished surfaces and suitably anchored in place.

The front edges of the boxes or plaster rings shall be flush with the finished wall or ceiling line or if installed in walls and ceilings of combustible construction, not more than 1/4 inch back of same. Mount boxes with the long axis of devices vertical, unless specifically noted otherwise.

J. Boxes in plastered walls and ceilings shall be provided with plaster rings. A multiple of

box extensions and/or covers will not be permitted. Rough-in installations which require box extensions shall be abandoned and the rough-in work redone. Install in a rigid and satisfactory manner with suitable metal bar hangers, box cleats, adjustable box hangers, etc. Use wood screws on wood, expansion shields on masonry and machine screws on steel work.

Page 35: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 5 ELECTRICAL BOXES AND FITTINGS

K. Avoid using round boxes where conduit must enter box through side of box, which

would result in difficult and insecure connections when fastened with locknut or bushing on rounded surface.

L. Fasten boxes firmly and rigidly to substrates, or structural surfaces to which attached, or

solidly embed electrical boxes in concrete or masonry. Wire shall not be used to anchor boxes to structure.

M. Provide electrical connections for installed boxes. Where several feeders pass through a

common pullbox, the feeders shall be tagged to indicate clearly the electrical characteristics, circuit number, and panel designation.

N. Splices in switch boxes shall be kept to a minimum. O. On all ceiling outlets involving fixture hanging from boxes, 3/8" no-bolt fixture studs

shall be used for light load and 1/2" no-bolt fixture studs shall be used for heavy loads. P. Where an atmosphere laden with moisture exists, Type FD Series Unilet Boxes shall be

used with standard devices. The covers employed shall be adapted for the particular application involved. In such cases, brass screws shall be used and due provision shall be made in all cases, for the escape of any condensate which might accumulate.

Q. Mounting Heights: The mounting height of a wall mounted outlet box shall mean the

height from the finished floor to the horizontal center line of the cover plate. On exposed tile, block or brick construction, mount outlet boxes at the nearest bed joint to the mounting height indicated. Any change in height made by the Contractor shall not place the box out of the range of acceptable height to comply with ADA. Verify with the Architect. Once mounting height is adjusted because of mortar bed joint, all similar wiring devices within the room or within view shall be adjusted accordingly.

R. Wall Mounted Switch, Receptacle and Signal Outlets: On columns, pilasters, etc., mount

so the centers of the columns are clear for future installation of partitions. Install outlet boxes near the doors on the lock sides as shown on Architectural drawings, unless locations are shown otherwise because of sidelites, and approved by the Architect.

S. Pull Boxes: Provide additional pull boxes wherever necessary to meet requirements for

maximum length of conduit runs and maximum number of bends. Conduit runs with not more than two ninety degree bends shall not exceed 200 feet.

T. Grounding: Upon completion of installation, properly ground electrical boxes and

demonstrate compliance with requirements. U. Identification: All junction and pull boxes above the ceiling shall be labeled as to the

circuits contained. Blank steel covers on 4 square boxes may be labeled with permanent black marker, hand written with panel name and circuit numbers unless noted otherwise on the plans. Larger boxes may have handwritten labeling if neatly performed.

V. Grounding: Upon completion of installation work, properly ground electrical boxes and

Page 36: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260533 - 6 ELECTRICAL BOXES AND FITTINGS

demonstrate compliance with requirements.

W. Identification: Identify junction and pull boxes installed for fire alarm wiring by painting red. Paint box and cover.

Page 37: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 1 RACEWAYS

SECTION 260535 - RACEWAYS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the General Conditions,

Supplementary Conditions, and Division 1 Specification Sections, apply to work of this section.

B. This section is a Division 26 Basic Materials and Methods section, and is part of each

Division 16 section making reference to electrical raceways specified herein. 1.2 SUMMARY A. This Section includes raceways for electrical wiring 600v and below, control wiring, and

Fire Alarm System Wiring. Types of raceways in this section include the following: 1. Type FMC conduit NEC Article 348. 2. Type EMT conduit NEC Article 358. 3. Liquidtight flexible conduit NEC Article 350. 4. Rigid metal conduit NEC Article 344. 5. Rigid nonmetallic conduit NEC Article 352. 6. Intermediate Metal Conduit NEC Article 342. B. Wiring methods shall be as described by the Division 16 specifications and permitted by

the State of New Mexico Electrical Code. Selection of wiring method is at the contractor’s option. Use of Type “NM” cable, NEC Article 334 is prohibited for this project.

1.3 SUBMITTALS A. General: Submit the following in accordance with the General Conditions,

Supplementary Conditions and Division 1 Specifications Sections. B. Product Data for the following products: 1. Metal conduits and fittings. 2. Flexible conduits and fittings. 3. PVC conduits and fittings.

Page 38: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 2 RACEWAYS

1.4 QUALITY ASSURANCE

A. Electrical Component Standard: Components and installation shall comply with NFPA 70 "National Electrical Code."

B. NEMA Compliance: Comply with applicable portions of NEMA standards pertaining to

raceways. C. UL Compliance and Labeling: Comply with applicable requirements of UL standards

pertaining to electrical raceway systems. Provide raceway products and components listed and labeled by UL, ETL, or CSA.

1.5 SEQUENCING AND SCHEDULING

A. Coordinate with other Work, including metal framing, wood framing and concrete deck installation, as necessary to interface installation of electrical raceways and components with other Work.

PART 2 - PRODUCTS 2.1 MATERIALS AND COMPONENTS

A. General: For each electrical raceway system indicated, provide assembly of conduit, tubing or duct, and fittings including, but not necessarily limited to, connectors, couplings, offsets, elbows, straps, bushings, expansion joints, hangers and other components and accessories as needed for a complete system. Minimum size conduit shall be 1/2".

B. Each length of rigid/IMC conduit shall have both ends threaded. The extremities shall,

moreover, be reamed to remove all burrs and sharp edges. Each length of conduit shall be marked with the name and trademark of the manufacturer and the stamp of approval of the Underwriters Laboratories, Inc.

C. Where shown on the plans or specifically called for in the specifications, electrical

conductors shall be installed in hot-dipped galvanized rigid steel conduit or IMC. Exposed conduit in damp OUTDOOR locations shall be rigid steel conduit or IMC. If EMT conduit is used outdoors as part of the new construction, it shall be REMOVED wherever found and replaced with rigid steel conduit. Each length of conduit shall be provided with one coupling attached and the threads of the end of the conduits having no coupling shall be protected by use of suitable thread protectors. All couplings and other fittings such as bends or elbows shall be protected against corrosion in the same manner in which the conduit itself is protected. All bends for conduit of 1-1/4" or larger shall either be factory manufactured elbows or be made by the use of a bending machine meeting the approval of Architect. Under no circumstances shall any bend be installed if the conduit from which it is fabricated is injured in any manner in the course of, or by, the bending process. The radius of the curve of the inner edge of any field bend shall not be less than the recommendation of the National Electrical Code. Under no circumstances shall the internal cross sectional area of any conduit be appreciably

Page 39: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 3 RACEWAYS

reduced by any bending process.

D. Rigid steel conduit, IMC and EMT fittings shall be either steel or malleable iron only.

E. EMT connectors and couplings shall be of the steel set screw or threaded compression type, having steel gland nuts. Connectors shall have insulated throats.

F. 1/2" and 3/4" trade size conduits may be installed in concrete slabs, as near the center of

the slab as possible. Material shall be IMC, rigid, or PVC.

G. Conduits installed in direct contact with the earth, except where PVC is used, shall be rigid galvanized steel, field spirally wrapped (half-lapped) with one layer of 1" wide 3M Scotchrap #50 plastic tape with a 50 percent overlap, including all joints or couplings, or shall be coated with a bonded 20 mil minimum thickness PVC, permanently fused at the factory, Pittsburgh Standard Co., "Plasti-Bond", or equal. Contractor shall patch with Scotchrap tape all holes or abrasions to conduit tape wrapping which expose the metal conduit surface. All buried wrapped or coated conduit shall be checked by Owner's duly authorized representative prior to covering up with fill. Branch circuit and feeder conduit runs when direct buried may be PVC schedule 40. The Contractor has the option of PVC conduit or rigid metal tape wrapped conduit. EMT conduit is not acceptable for burial applications. If PVC conduit is used, transition to rigid metal tape wrapped conduit shall be made before beginning sweep for conduit stub-up. Metal conduit must be wrapped throughout buried portion, including risers.

2.2 METAL CONDUIT AND TUBING

A. General: Provide metal conduit, tubing and fittings of types, grades, sizes and weights (wall thicknesses) for each service indicated. Where types and grades are not indicated, provide proper selection determined by Contractor to fulfill wiring requirements and comply with applicable portions of NEC for raceways.

B. Sealing Fittings: Threaded, zinc or cadmium plated, cast or malleable iron type for steel

conduits. C. Rigid Aluminum Conduit: Not acceptable on this project. D. Rigid Steel Conduit: ANSI C80.1

E. Intermediate Steel Conduit: UL 1242. Intermediate metal conduit (IMC) may be used in lieu of rigid conduit, but only where permitted by 2005 NEC, and with manufacturer's recommended fittings. Threading and bending of IMC shall be with approved equipment for the purpose and as recommended by the manufacturer of the raceway. Threadless fittings shall not be permitted for rigid or IMC.

F. Electrical Metallic Tubing and Fittings: ANSI C80.3. Steel tubing, in lieu of rigid or

IMC conduit, may be used in sizes up to and including 4 inches in all interior work, except that it shall not be used in concrete, underground, in any damp or outdoor locations, or in any locations where there is a likelihood of mechanical injury.

Page 40: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 4 RACEWAYS

G. Flexible Metal Conduit: UL 1, aluminum, not acceptable.

H. Flexible Metal Conduit: UL 1, with a separate grounding bond wire installed in the flex in addition to other wires.

I. Flexible Metal Conduit Fittings: Either steel or malleable iron only, with insulated

throats.

J. Liquid-Tight Flexible Metal Conduit and Fittings: UL 360. Provide liquid-tight flexible metal conduit; constructed of single strip, flexible, continuous, interlocked, and double-wrapped steel, galvanized inside and outside; coated with liquid-tight jacket of flexible polyvinyl chloride (PVC) and a continuous copper bonding conductor wound spirally between the convolutions. To be UL labeled Sealtite type UA or Liquidtite type LA.

K. Liquid tight flexible conduit fittings shall be provided with threaded grounding cone, a

steel, nylon or equal plastic compression ring and a gland for tightening. Either steel or malleable iron only with insulated throats and male thread and locknut or male bushing with or without "O" ring seat.

2.3 NONMETALLIC CONDUIT AND DUCTS

A. General: Provide nonmetallic conduit, ducts and fittings of types, sizes and weights (wall thicknesses) for each service indicated. Where types and grades are not indicated, provide proper section determined by Contractor to fulfill wiring requirements, and comply with applicable portions of NEC for raceways.

B. Rigid Nonmetallic Conduit (PVC): NEMA TC 2 and UL 651, Schedule 40 or 80 PVC.

C. PVC Conduit and Tubing Fittings: NEMA TC 3; match to conduit or conduit/tubing

type and material.

D. Conduit, Tubing and Duct Accessories: Types, sizes, and materials complying with manufacturer's published product information. Mate and match accessories with raceway.

2.4 CONDUIT BODIES

A. General: Types, shapes, and sizes as required to suit individual applications and NEC requirements. Provide matching gasketed covers secured with corrosion-resistant screws.

B. Metallic Conduit and Tubing: Use metallic conduit bodies. Use bodies with threaded

hubs for threaded raceways.

C. Conduit Bodies 1 Inch and Smaller: Use bodies with compression-type EMT connectors. PART 3 - EXECUTION

Page 41: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 5 RACEWAYS

3.1 WIRING METHOD A. Outdoors: Use the following wiring methods: 1. Exposed: IMC or rigid metal conduit. 2. Underground: IMC, rigid metal conduit, or PVC.

3. Connection to Vibrating Equipment: Including transformers and hydraulic, pneumatic, or electric solenoid or motor-driven equipment: liquidtight flexible metal conduit.

4. Indoors or Outdoors: Connection to vibrating equipment and hydraulic,

pneumatic, or electric solenoid or motor-driven equipment in moist or humid location or corrosive atmosphere, or where subject to water spray or dripping oil, grease, or water: liquidtight flexible metal conduit.

B. Indoors: Use the following wiring methods:

1. Connection to Vibrating Equipment: Including transformers and hydraulic, pneumatic or electric solenoid or motor-operated equipment: flexible metal conduit.

2. Exposed: EMT, IMC, or rigid metallic conduit. 3. Concealed: EMT, IMC, or rigid metallic conduit.

4. Slab on grade concrete: IMC, rigid, or PVC. 3.2 INSTALLATION

A. General: Install electrical raceways for all wiring circuits in accordance with manufacturer's written instructions, applicable requirements of NEC, and as follows:

B. Conceal raceways, unless indicated otherwise, within finished walls, ceilings, and floors.

Keep raceways at least 6 inches away from parallel runs of flues and steam or hot water pipes. Install raceways level and square and at proper elevations. Run all conduits in a manner satisfactory to the Architect. On exposed systems, support shall be provided at intervals of 6 feet or closer depending on wiring method. On concealed conduits, support shall be provided at intervals of no more than 8 feet or closer depending on wiring method. No feeder conduit run shall be longer than 80 feet between junction boxes, cabinets or circuit interrupting devices unless there are no direction changes, and only a straight-in-line pull of wire is involved. In such straight-in-line runs between junction boxes, cabinets or circuit interrupting devices, a run not to exceed 120 feet in length may be made.

C. Elevation of Raceway: Install horizontal raceway runs above water and steam piping to

the fullest extent possible.

Page 42: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 6 RACEWAYS

D. Complete installation of electrical raceways before starting installation of conductors within raceways. All ends of the conduit shall be properly reamed to remove rough edges and whenever a conduit enters a box or other fitting, it shall be securely fastened by the use of a locknut inside and outside of the box or fitting. An approved bushing shall be installed on the ends of all conduit in such a manner as to protect the wire from abrasion. Completed raceways shall be inspected; inspect interiors of raceways, remove burrs, moisture, and dirt and construction debris.

E. Support raceways rigidly by means of straps or hangers best suited for the work.

Conduit shall not be supported from ceiling support system. Multiple runs of conduits shall be racked on trapeze hangers. All support materials shall be rustproof. Perforated tape or wire shall not be used.

SUPPORTS SHALL COMPLY WITH NEW MEXICO ELECTRICAL CODE.

A. Prevent foreign matter from entering raceways by using temporary closure protection. Seal raceways after installation to prevent accumulation of water, dirt and other foreign materials. Conduit in which such accumulation occurs shall be cleaned to the satisfaction of the Architect or replaced.

B. Conduit crossing expansion joints shall be provided with suitable expansion fitting.

C. Protect stub-ups from damage where conduits rise from floor slabs. Arrange so curved

portion of bends is not visible above the finished slab. Conduit crushed or otherwise deformed shall not be installed and shall be removed from the job site without delay.

D. Make bends and offsets so the inside diameter is not effectively reduced. Unless

otherwise indicated, keep the legs of a bend in the same plane and the straight legs of offsets parallel.

E. Use raceway fittings that are of types compatible with the associated raceway and

suitable for the use and location. For intermediate steel conduit, use threaded rigid steel conduit fittings except as otherwise indicated.

F. Run concealed raceways with a minimum of bends in the shortest practical distance

considering the type of building construction and obstructions, except as otherwise indicated.

G. All non-metallic conduit or duct runs shall have a ground bonding conductor, size as

noted or required by NEC. The bond or equipment served shall be bonded to grounding conductor to provide a good ground return path to service panel.

H. Install exposed raceways parallel and perpendicular to nearby surfaces or structural

members and follow the surface contours as much as practical. Paint conduit that will be exposed to the public. Paint shall match surface color.

I. Run exposed, parallel, or banked raceways together. Make bends in parallel or banked

runs from the same center line so that the bends are parallel. Factory elbows may be used in banked runs only where they can be installed parallel. This requires that there be

Page 43: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 7 RACEWAYS

a change in the plane of the run such as from wall to ceiling and that the raceways be of the same size. In other cases provided field bends for parallel raceways.

J. Join raceways with fittings designed and approved for the purpose and make joints tight.

Where joints cannot be made tight, use bonding jumpers to provide electrical continuity of the raceway system. Make raceway terminations tight. Where terminations are subject to vibration, use bonding busings or wedges to assure electrical continuity. Where subject to vibration or dampness, use insulating bushings to protect conductors.

K. Tighten set screws of threadless fittings with suitable tool.

L. Terminations: Where raceways are terminated with locknuts and bushings, align the

raceway to enter squarely and install the locknuts with dished part against the box. Where terminations cannot be made secure with one locknut, use two locknuts, one inside and one outside the box.

M. Where terminating in threaded hubs, screw the raceway or fitting tight into the hub so the

end bears against the wire protection shoulder. Where chase nipples are used, align the raceway so the coupling is square to the box, and tighten the chase nipple so no threads are exposed.

N. Install pull wires in empty raceways over 4 feet long. Use no. 14 AWG zinc-coated steel

or monofilament plastic line having not less than 200-lb tensile strength. Leave not less than 12 inches of slack at each end of the pull wire. Identify each terminus of pull wire with linen tags marked with complete information as to service and location of the terminus of the line/wire.

O. Install raceway sealing fittings in accordance with the manufacturer's written

instructions. Locate fittings at suitable, approved, accessible locations and fill them with UL-listed sealing compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing fittings at the following points and elsewhere as indicated:

1. Where conduits pass from warm locations to cold locations, such as the

boundaries of refrigerated spaces and air-conditioned spaces. 2. Where required by the NEC.

P. Conduit Stub-up Through Roof: All conduits up through roof shall be properly sealed. Where applicable Contractor shall provide special adapters designed for the specific type of roofing system. See the drawings for special details and instructions for this specific purpose.

Q. Flexible Connections: Use short length (maximum of 6 ft.) of flexible conduit for

recessed and semi recessed lighting fixtures, where EMT and FMC is used, for equipment subject to vibration, noise transmission, or movement; and for all motors. Use liquidtight flexible metal conduit in wet locations. Install separate ground conductor across flexible connections.

Page 44: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260535 - 8 RACEWAYS

R. Conduits above acoustical "lay-in" ceilings shall be anchored to the building structure and not on the ceiling or ceiling support wires. Wire shall not be used to anchor boxes to structure. Junction boxes shall be installed on the structural members and flexible conduit, extended down to light fixtures, length not to exceed 6 ft.

S. Do not install aluminum conduit.

T. PVC externally coated rigid steel conduit: Use only fittings approved for use with that

material. Patch all nicks and scrapes in PVC coating after installing conduit.

U. Lighting fixtures shall not be used for raceways for circuits other than parallel wiring of fixtures.

V. Fire Barriers: Contractor shall be responsible for sealing all conduit penetrations through

fire rated walls and ceilings. The seal shall be acceptable to Architect and maintain the integrity of the wall or ceiling fire rating. 3M brand fire barrier caulk #CP 25 and putty #303 are considered acceptable for this purpose. Refer to Architectural drawings for these locations.

3.3 ADJUSTING AND CLEANING

A. Upon completion of installation of raceways, inspect interiors of raceways; clear all blockages and remove burrs, dirt, and construction debris.

Page 45: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260553 - 1 ELECTRICAL IDENTIFICATION

SECTION 260553 – ELECTRICAL IDENTIFICATION PART 1 -GENERAL 1.1 SECTION INCLUDES

A. Nameplates and labels.

B. Wire and cable markers.

C. Conduit markers.

1.2 RELATED SECTIONS

A. Painting. 1.3 REFERENCES

A. Quality Control: Requirements for references and standards.

B. ANSI/NFPA 70 - National Electrical Code. 1.4 SUBMITTALS – None Required. 1.5 REGULATORY REQUIREMENTS

A. Conform to requirements of ANSI/NFPA 70.

B. Furnish products listed and classified by Underwriters Laboratories, Inc., as suitable for purpose specified and shown.

PART 2 - PRODUCTS 2.1 NAMEPLATES AND LABELS

A. Nameplates: Engraved three-layer laminated plastic, white letters on black background. B. Locations:

1. Each electrical distribution and control equipment enclosure. Provide new labels

on all equipment, existing and new.

2. Communication cabinets.

A. Letter Size:

1. Use 1/8 inch letters for identifying individual equipment and loads.

Page 46: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 260553 - 2 ELECTRICAL IDENTIFICATION

A. Labels: Embossed adhesive tape, with 3/16 inch white letters on black background. PART 3 - EXECUTION 3.1 PREPARATION

A. Degrease and clean surfaces to receive nameplates and labels. 3.2 APPLICATION

A. Install nameplate and label parallel to equipment lines.

B. Secure nameplate to equipment front using screws, rivets, or adhesive.

C. Secure nameplate to inside surface of door on panelboard that is recessed in finished 3 locations.

D. Color:

a. 208 Volt System: Black, Red, Blue, White, Green.

Page 47: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262716-1 CABINETS & ENCLOSURES

SECTION 262716 - CABINETS & ENCLOSURES PART 1 - GENERAL 1.1 SECTION INCLUDES

A. Hinged cover enclosures.

B. Cabinets.

C. Terminal blocks.

D. Accessories. 1.2 RELATED SECTIONS

A. Section 26 05 29 - Supporting Devices.

B. Firestopping 1.3 REFERENCES

A. NECA Standard of Installation (National Electrical Contractors Association).

B. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).

C. NEMA ICS 4 - Terminal Blocks for Industrial Control Equipment and Systems.

D. NFPA 70 - National Electrical Code. 1.4 SUBMITTALS FOR REVIEW – None Required. 1.5 REGULATORY REQUIREMENTS

A. Conform to requirements of NFPA 70.

B. Products: Listed and classified by Underwriters Laboratories, Inc. as suitable for the purpose specified and indicated.

PART 2 - PRODUCTS 2.1 MANUFACTURERS

A. Hoffman.

B. Circle A-W.

Page 48: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262716-2 CABINETS & ENCLOSURES

C. Wiegmann.

D. Substitutions: Permitted. 2.2 HINGED COVER ENCLOSURES

A. Construction: NEMA 250, Type 1 or 3R steel enclosure.

B. Covers: Continuous hinge, held closed by flush latch operable by key.

C. Provide interior plywood panel for mounting terminal blocks and electrical components; finish with white enamel.

D. Enclosure Finish: Manufacturer's standard enamel.

2.3 CABINETS

A. Boxes: Galvanized steel.

B. Box Size: As indicated on drawings.

C. Backboard: Provide 3/4-inch thick plywood backboard for mounting terminal blocks. Paint matte white.

D. Fronts: Steel door with concealed hinge, and flush lock. Finish with gray baked

enamel.

E. Knockouts: Pre-punched.

F. Provide metal barriers to form separate compartments wiring of different systems and voltages.

G. Provide accessory feet for free-standing equipment.

2.4 TERMINAL BLOCKS

A. Manufacturers:

1. Siemon.

2. Substitutions: Refer to Section 26 00 00.

B. Terminal Blocks: NEMA ICS 4.

C. Power Terminals: Unit construction type with closed back and tubular pressure screw connectors, rated 600 volts.

D. Signal and Control Terminals: Modular construction type, suitable for channel

Page 49: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262716-3 CABINETS & ENCLOSURES

mounting, with tubular pressure screw connectors, rated 300 volts.

E. Provide ground bus terminal block, with each connector bonded to enclosure. PART 3 - EXECUTION 3.1 INSTALLATION

A. Quality Control: Manufacturer's instructions.

B. Install in accordance with NECA "Standard of Installation."

C. Install enclosures and boxes plumb. Anchor securely to wall and structural supports at each corner under the provisions of Section 16190.

D. Install cabinet fronts plumb.

3.2 CLEANING

A. Contract Closeout: Cleaning installed work.

B. Clean electrical parts to remove conductive and harmful materials.

C. Remove dirt and debris from enclosure.

D. Clean finishes and touch up damage.

Page 50: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 1 WIRING DEVICES

SECTION 262726 – WIRING DEVICES

PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the General Conditions,

Supplementary Conditions, and Division 1 Specification sections, apply to work of this section. .

1.2 SUMMARY A. This Section includes the following:

1. Receptacles 2. Ground Fault Circuit Interrupter Receptacles 3. Plugs 4. Plug Connections 5. Snap Switches 6. Wall Plates

1.3 SUBMITTALS A. Product data for each type of product specified. B. All wiring devices shall be by the same manufacturer unless authorized by Architect.

Unauthorized mixing of device brands is unacceptable. C. Samples: The Contractor shall submit when requested a sample of the standard single pole

switch and of the standard 15 and 20 Amp duplex convenience outlet as part of submittals. All wiring devices shall be by the same manufacturer unless authorized by Architect. Mixing of device brands is unacceptable.

1.4 QUALITY ASSURANCE A. Regulatory Requirements: Comply with provisions of the following codes.

1. NFPA 70 "National Electrical Code".

B. UL and NEMA Compliance: Provide wiring devices which are listed and labeled by UL and comply with applicable UL and NEMA standards.

1.5 SEQUENCE AND SCHEDULING

Page 51: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 2 WIRING DEVICES

A. Schedule installation of finish plates after the surface upon which they are installed has

received final finish. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufactures: Subject to compliance with requirements, provide products of one of the

following or equal (for each type of wiring device): 1. General Electric Co. 2. Harvey Hubbell, Inc.

3. Pass and Seymour, Inc. 4. Bryant Electric Div. 5. Arrow Hart 6. Leviton

7. Lutron

8. Carlon

2.2 WIRING DEVICES

A. General: Provide wiring devices in types, characteristics, grades, colors, and electrical ratings for applications indicated which are UL listed and comply with NEMA WD1 and other applicable UL and NEMA standards. Where types and grades are not indicated, provide proper selection as determined by Contractor to fulfill wiring requirements, and comply with NEC and NEMA standards for wiring devices. Provide ivory color devices throughout. Provide stainless steel wall plates except as otherwiseindicated. Verify color selection of devices with the Architect.

B. Receptacles:

1. General: Configuration and requirements for all connector or outlet receptacles shall be in accordance with the NEMA Publication WD1 and UL 498. Fire-resistant, non-absorptive, hot-welded, phenolic composition or equal bodies and based with metal plaster ears (integral with the supporting members). Single or duplex as shown or noted on the drawings. Double grip contacts for each prong. Convenience outlets shall be installed with grounding pin connection for plugs at top (outlets installed vertically). All outlets not installed with ground post connection point on top shall be repositioned to meet this requirement.

2. Grounding type: All receptacles shall be grounding type with a green colored

hexagonal equipment ground screw and shall be connected to green circuit ground

Page 52: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 3 WIRING DEVICES

conductor. Grounding terminals of all receptacles shall be internally connected to the receptacle mounting yoke.

3. Duplex convenience outlets, rated 20 amps, 125 volts, 2 pole, 3 wire, NEMA

5-20R, specification grade, back or side wiring, shall be Hubbell #5362-I, Pass & Seymour #5362-I, General Electric GE 5362-2 or Bryant 5362I.

4. Weather proof outlets on exterior walls (except on the roof) shall be GFCI

receptacles installed in recessed “Taymac Masque” or equal covered recessed receptacle box. Contractor shall install Taymac #72204 or equal with GFCI outlet. Taymac #72204 or equal consists of metal box, plastic extension ring and gasketed outlet bucket with cover. Verify color of cover prior to entering.

5. Weather proof outlets on roof for NEC 210.63 rule shall be GFCI outlet in FS cast

metal box with Taymac #20510 or equal deep cover. C. Ground Fault Interrupter Outlets: 1. The ground fault circuit interrupter (GFCI) receptacles, rated 15 amps, 125 volts, 2

pole, 3 wire, NEMA 5-15R, shall be UL listed (UL 498 and UL 943 Class A) and shall comply with ANSI C73.11. GFCI receptacles shall not have the "feed-through" feature to provide GFCI protection to receptacles connected downstream. The GFCI shall operate in the 4 - 6 milliamp range. The GFCI receptacles shall be Hubbell #GF-5262I, Pass & Seymour #1591-F-I, or Bryant #GFR52FTI. Receptacles shall be furnished with appropriate device wall coverplate.

D. Switches:

1. Unless otherwise specified, each snap switch (flush tumbler-toggle) shall be of the AC general use type fully rated 20 amperes minimum at 120/277 volts, conforming to minimum requirements of the latest revision of the Underwriters Laboratories, Inc., UL 20, NEMA Stds. Publ. No. WD1, and further requirements herein specified. Specification grade, heavy duty, single pole, 3-way, or 4-way of the maintained, momentary, or lock type as indicated on the drawings. Switches shall operate in any position and shall be fully enclosed cup type with entire body of phenolic, urea or melamine. Fiber, paper or similar insulating material shall not be used for body or cover. Silver or silver alloy contacts. AC 120/277 volt general use snap switches shall be capable of withstanding tests as outlined in NEMA publication WD1 and shall be as follows or an Architect approved equal, unless otherwise noted.

2. Single pole switches, rated 20A, 120-277 volts, shall be Hubbell #1221-I, General

Electric #5951-2G, Pass & Seymour #20AC1-I or Bryant 4901I.

3. Single pole switch with pilot light shall be spec. grade red lighted handle, rated 20 amps, 120V, Hubbell #1221-PL, General Electric #SP121-8G, Pass & Seymour #20AC1-RPL or Bryant #4901 PLR 120.

4. Three-way switches, rated 20A, 120-277 volts, shall be Hubbell #1223-I, Bryant

#4903I, Pass & Seymour #20AC3-I or General Electric #5953-2G.

Page 53: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 4 WIRING DEVICES

5. Four-way switches, rated 20A, 120-277 volts, shall be Hubbell #1224-I, Bryant

4904I, Pass & Seymour #20AC4-I or General Electric #5954-2G.

6. Weatherproof switches shall include the type of snap switch indicated on the drawings and specified herein, enclosed with a Crouse-Hinds #DS 181 cover and gasket mounted in an FS cast box. Substitutions must be Architect approved. Flip top covers exposing switch handle to rain are not acceptable. Orientation of the cover must be vertical.

2.3 WIRING DEVICE ACCESSORIES A. Wall plates: single and combination, of types, sizes, and with ganging and cutouts as

indicated. Provide plates which mate and match with wiring devices to which attached. Provide metal screws for securing plates to devices with screw heads colored to match finish of plates. Conform to requirements of "Electrical Identification." Provide plates possessing the following additional construction features:

B. Material and Finish Recessed Box: 0.04 inch thick, type 302 satin finished stainless steel,

non-residential areas.

C. Material and Finish Surface Box: steel plate, galvanized, non-residential areas.

D. Engraving: Wall plates located in finished areas which would require identification shall be engraved stainless steel plates. All lettering shall be 1/8" minimum in height, nine characters per inch and filled with black paint. Identification wording/lettering shall be as noted on the drawings and shall be centered on coverplate.

E. Plates for special purpose outlets shall be of a design suitable for the particular

application.

F. Wall plates covering flush boxes in CMU walls shall have oversize plates.

PART 3 - EXECUTION 3.1 INSPECTION A. Wiring device locations shown are approximate. Contractor shall adjust lateral locations

shown up to 18” to accommodate final room layouts. The outlet locations shall be modified from those shown on the plans to accommodate changes in door swings or to clear other interferences that may arise from job construction details as well as modification within room spaces. The Contractor shall check these conditions throughout the entire job and shall notify the Architect of discrepancies as they may occur before proceeding with the installation of the work to verify the modifications, if any.

3.2 INSTALLATION OF WIRING DEVICES AND ACCESSORIES A. Install wiring devices and accessories as indicated, in accordance with manufacturer's

written instructions, applicable requirements of NEC and in accordance with recognized

Page 54: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 5 WIRING DEVICES

industry practices to fulfill project requirements. B. Coordinate with other Work, including painting, electrical boxes and wiring installations,

as necessary to interface installation of wiring devices with other Work. Install wiring devices only in electrical boxes, which are clean; free from building materials, dirt and debris.

C. Install galvanized steel wallplates in unfinished spaces.

D. Install wiring devices after wiring work is completed. Switches shall be mounted 44" and

convenience outlets 18" minimum, center of box above the finished floor level except as otherwise specified on the drawings. Align devices and plates horizontally and vertically.

E. Wall boxes shall be set in advance of the wall construction, shall be blocked in place and

secured. All wall boxes shall be set flush with the finished building construction. Contractor shall vacuum clean all wiring device boxes.

F. Coordinate with other work, including painting, electrical box and wiring work, as

necessary to interface installation of wiring devices with other work. G. Delay installation of wall plates until after painting work is completed.

H. The Contractor shall be responsible for coordinating with other trades the actual installation

of his outlet boxes in walls. The wall building material (cinder block, brick, sheetrock or whatever) shall provide an even trim around outlet boxes not exceeding a 1/4" gap. The device coverplate should be able to cover up wall openings around outlet boxes. Wherever an outlet box installation fails to comply with the above listed condition, the Contractor shall arrange to have the problem corrected. Caulking, spackling material or any other sealer to be used shall be kept out of the outlet box area.

I. Wiring device yokes shall be installed in physical contact with the plaster ring. Spiral

wound bare wire supports to act as spacers between plaster extension ring/box and device yokes are not acceptable. Where condition occurs, the plaster ring/box shall be replaced as required to provide the proper contact.

J. Device coverplates for each and every device shall be furnished and installed by this

contractor. K. Tighten connectors and terminals, including screws and bolts, in accordance with

equipment manufacturer's published torque tightening values for wiring devices. Where manufacturer's torquing requirements are not indicated, tighten connectors and terminals to comply with tightening torques specified in UL Standard 486A. Use properly scaled torque indicating hand tool.

3.3 PROTECTION OF WALL PLATES AND RECEPTACLES A. Upon installation of wall plates and receptacles, advise the Contractor regarding proper and

cautious use of convenience outlets. At time of Substantial Completion, replace those items which have been damaged, including those burned and scorched by faulty plugs.

Page 55: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 262726 - 6 WIRING DEVICES

3.4 GROUNDING A. Provide electrically continuous, tight grounding connections for wiring devices, unless

otherwise noted. 3.5 FIELD QUALITY CONTROL A. Testing: Prior to energizing circuits, test wiring for electrical continuity, and for short-

circuits. Ensure proper polarity of connections is maintained. Subsequent to energizing, test wiring devices and demonstrate compliance with requirements, operating each operable device at least six times.

B. Test ground fault interruptor operation with both local and remote fault simulations in

accordance with manufacturer recommendations.

Page 56: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 265600 - 1 EXTERIOR LUMINAIRES

SECTION 265600 - EXTERIOR LUMINAIRES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections, apply to work of this section.

B. Division-26 Basic Electrical Materials and Methods sections apply to work specified in this

section. 1.2 SUMMARY

A. Extent, location, and details of electrical poles and standards work are indicated on drawings and in schedules.

B. Applications of lighting poles and fixtures specified in this section include the following:

1. Soccer Field Lighting

C. Excavation and backfilling for poles, standards, and foundations are specified in Division

2.

D. Raceways and electrical boxes and fittings, which are required in connection with electrical poles and standards, are specified in Division-26 Basic Materials and Methods sections, "Raceways" and "Electrical Boxes and Fittings."

E. Exterior lighting fixtures (luminaries) and brackets, which are required in connection with

electrical poles and standards, are specified in another Division-16 section, "Exterior Lighting."

1.3 SUBMITTALS

A. Product Data: Submit manufacturer's data on electrical poles, and fixtures; include certified dimension drawings for fabricated poles, standards and mast arms, if any. Submit pole calculations proving compliance with the wind loading requirements.

B. Shop Drawings: Submit shop drawings of electrical poles and standards, including mast

arms and wire/cable connections which are custom work. 1.4 QUALITY ASSURANCE

A. Manufacturer's Qualifications: Firms regularly engaged in manufacture of electrical poles and fixtures of types and sizes required, whose products have been unsatisfactory use in similar service for not less than 5 years.

B. Codes and Standards:

Page 57: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 265600 - 2 EXTERIOR LUMINAIRES

C. Electrical Code Compliance: Comply with applicable local code requirements of the authority having jurisdiction and NEC.

D. UL Compliance: Comply with standards, including 486A and B, pertaining to electrical

poles and standards. Provide lighting fixtures which are UL-1572 listed and labeled.

E. ANSI/ASTM Compliance: Comply with applicable requirements of ANSI C 2, "National Electrical Safety Code," pertaining to construction and installation of lighting poles and standards.

F. NEMA Compliance: Comply with NEMA Stds Pub/No's. LE 2 and TT 1 pertaining to

electrical pole and standard units, materials, and installation. 1.5 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Deliver electrical pole and standard products, and fittings in factory-fabricated containers or wrappings, which properly protect products from damage.

B. Store electrical pole and standard products, and fittings in original cartons in well-

ventilated space protected from moisture, construction traffic and debris.

C. Handle electrical pole and standard products carefully to prevent breakage, denting and scoring finish. Wrap mast arms individually, in heavy-duty moisture-resistant paper for protection in transit. Do not install damaged units or components; replace with new.

1.6 SEQUENCING AND SCHEDULING

A. Coordinate with other electrical work including wires/cables, electrical boxes and fittings, and raceways, to properly interface installation of electrical pole and standard work with other work.

B. Sequence electrical pole and standard installation work with other work to minimize

possibility of damage and soiling during remainder of construction period. PART 2 - PRODUCTS 2.1 ELECTRICAL POLES AND STANDARDS: Soccer Field Lighting.

A. Lighting Standards: Provide square Straight Steel, raceway-type, lighting poles and standards, of sizes and types indicated, comprised of shafts and tenon joints. Equip with grounding connections readily accessible from handhole.

B. Design poles to withstand loads developed by 80 MPH wind pressure with a 1.3 gust factor,

as adjusted for number of luminaries and accessories, height aboveground level, structural shapes and cable/wire loading. Provide tamper-resistant fasteners for handhole cover.

2.2 LIGHTING FIXTURES - Soccer Field Lighting.

A. Fixture Schedule: All fixtures to be as scheduled on the drawings or approved equal

Page 58: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 265600 - 3 EXTERIOR LUMINAIRES

fixtures. Any substitute fixture to have the same characteristics, both photometric and physically as the scheduled fixture.

B. General: All fixtures, ballasts and supports shall be quiet in operation.

2.3 BALLASTS – Soccer Field Lighting.

A. Ballast to be constant wattage autotransformer, core and coil type. Ballast minimum starting temperature to be -20 degrees F.

B. Ballast to be multi-tap 120/208/240/277V, connected for the voltage on which they are

circuited on the drawing.

C. Ballasts to be as manufactured by Advance, Universal, or equal. 2.4 LAMPS

A. As scheduled on the drawings.

B. Manufacturers: General Electric, Sylvania, Philips, or an equal.

PART 3 - EXECUTION 3.1 EXAMINATION

A. Examine areas and conditions under which pole and standard equipment and components are to be installed, and substrate, which will support equipment.

3.2 GROUNDING

A. Provide equipment-grounding connections for poles and standards as indicated. Tighten connections to comply with tightening torques specified in UL 486A to assure permanent and effective grounding.

Page 59: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 031000 - 1 CONCRETE FORMING AND ACCESSORIES

SECTION 031000 – CONCRETE FORMING AND ACCESSORIES PART 1 - GENERAL 1.1 WORK INCLUDED

A. This section includes formwork for cast-in-place concrete, including installation of embedded items.

1.2 RELATED WORK SPECIFIED ELSEWHERE A. Concrete Reinforcement – Section 032000 B. Cast-In-Place Concrete – Section 033000 1.4 REFERENCE STANDARDS

A. Comply with the requirements of the following specifications and standards. 1. American Concrete Institute (ACI)

a. ACI 347-04 Guide to Formwork for Concrete b. ACI 347-78 Recommended Practice for Concrete Formwork.

2. American Society for Testing Materials (ASTM)

a. ASTM D 1751-04 Specification for Preformed Expansion Joint Filler for

Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

PART 2 – PRODUCTS 2.1 MATERIALS

A. Forms for Exposed Finish Concrete: Plywood complying with U.S. Product Standard PS-1-83 “B-B (Concrete Form) Plywood”, Class I, Exterior Grade or better or metal, metal-framed plywood or other acceptable panel-type materials. Plywood shall be mill-oiled and edge-sealed, with each piece bearing legible inspection trademark. Furnish in largest practicable sizes to minimize number of joints. Provide form material with sufficient thickness to withstand pressure of newly placed concrete without bow or deflection.

B. Forms for Unexposed Finish Concrete: Plywood, lumber, metal or other acceptable

material. Provide lumber dressed on at least 2 edges and one side for tight fit. C. Form Coatings: Commercial formulation that will not bond with, stain, or adversely

affected concrete surfaces, and will not impair subsequent treatments of concrete surfaces.

Page 60: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 031000 - 2 CONCRETE FORMING AND ACCESSORIES

D. Chamfer Strips: ¾” by ¾” wood, PVC, or rubber. E. Preformed Construction Joint: 24-gauge steel, galvanized, shaped to form a continuous

tongue and groove key. F. Preformed Control Joint: Rigid plastic or metal strip with removable top section. G. Expansion Joint Material: Asphalt saturated fiberboard, ½” thick, meeting the

requirements of ASTM D 1751.

PART 3 – EXECUTION 3.1 COORDINATION

A. Coordinate the installation of joint materials with placement of forms and reinforcing steel. Set screeds accurately. Embedded items shall be accurately aligned and adequately supported. Correct any unsatisfactory condition before proceeding further.

3.2 PREPARATION

A. Form Coating: Coat contact surfaces of forms with a form coating compound before reinforcement is placed. Thin form-coating compounds with thinning agent and apply in accordance with manufacturer’s specifications and instructions. Do not allow excess form-coating material to accumulate on forms or to come into contact with concrete surfaces against which fresh concrete will be placed.

3.3 INSTALLATION

A. Formwork: Formwork shall support vertical and lateral loads that are applied until such loads can be supported by concrete structure. Formwork shall be readily removable without impact, shock or damage to cast-in-place concrete surfaces and adjacent materials. Construct forms to shapes, lines and dimensions shown on the Drawings. Perform surveys to obtain accurate alignment. Provide for recesses, chamfers, blocking, anchorages, inserts, and other features required in work. Select materials to obtain required finishes.

B. Chamfer Strips: Provide at exposed corners and edges. C. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive

concrete. Remove dirt or other debris before concrete is placed. Retighten forms and bracing after concrete placement as required to maintain proper alignment.

3.4 INSTALLATION OF EMBEDDED ITEMS:

A. General: Set anchorage devices and other embedded items accurately. Secure embedded items such that they are not displaced during placement of concrete.

Page 61: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 031000 - 3 CONCRETE FORMING AND ACCESSORIES

3.5 JOINTS:

A. Construction Joints: Locate and install construction joints so as not to impair strength and appearance of the structure. Place construction joints perpendicular to the main reinforcement. Continue reinforcement across construction joints unless noted otherwise.

B. Keyways: Provide keyways at least 1-1/2” deep in construction joints in slabs. C. Preformed Construction Joint for Slabs on Grade: Secure with galvanized steel stakes,

1/8” thick by 1-1/8 inches wide with ½” rib and tapered point. Splice adjoining joints with 24 gauge galvanized steel splice plates.

D. Isolation Joints in Slabs on Grade: Provide joints at points of contact between slabs on

grade and adjacent hard surfaces with ½” thick expansion joint material. E. Control Joints in Slabs-on-Grade:

1. Preformed Strip: Insert premolded rigid plastic, or metal strip into fresh concrete.

Cut groove for strip using 10-foot long straight edge cutting tool. Depths of strip shall be one fourth of slab thickness. Press strip into groove such that top of strip is level with the concrete surface. Pull off removable top section, if any, prior to troweling.

2. Saw Cut: Contractor may saw cut control joints instead of using preformed strips.

Saw cut joints shall be 1/8 inch wide. Saw cut depth shall equal 1/3 of slab depth. Cut joints after concrete has hardened sufficiently to prevent raveling; usually 4 to 12 hours after slab has been cast and finished. Use diamond or silicone-carbide blades.

3.6 REMOVAL OF FORMWORK:

A. General: Prevent excessive deflection, distortion, and damages to concrete when forms are stripped. Provide crush plates or wrecking plates where stripping may damage cast concrete surfaces.

B. Formwork and supports at sides of concrete shall remain in place for 24 hours after

concrete placement. This period represents cumulative number of hours, not consecutive, during which the temperature of the air surrounding the concrete is above 50 degrees F. Formwork which supports the weight of concrete shall not be removed until concrete has attained its specified compressive strength.

C. Do not superimpose any load on concrete until forms are removed and concrete is cured.

3.7 RE-USE OF FORMS:

A. General: Clean and repair surfaces of forms to be re-used in work. Split, frayed, delaminated, or otherwise damaged form facing material shall not be used. Apply new form coating compound as specified for new formwork.

Page 62: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 031000 - 4 CONCRETE FORMING AND ACCESSORIES

B. When forms are intended for successive concrete placement, thoroughly clean surfaces and remove fins and latence. Align and secure joints to avoid offsets. Do not use “patched” forms for exposed concrete surfaces.

END OF SECTION

Page 63: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 032000-1 CONCRETE REINFORCEMENT

SECTION 032000 – CONCRETE REINFORCEMENT PART 1 – GENERAL 1.1 WORK INCLUDED

A. This section includes fabrication and installation of reinforcing steel. 1.2 RELATED WORK SPECIFIED ELSEWHERE

A. Concrete Formwork – Section 031000. B. Cast In Place Concrete – Section 033000.

1.3 REFERENCE STANDARDS

A. Comply with the requirements of the following specifications and standards.

1. American Concrete Institute (ACI)

a. ACI 315-99 Details and Detailing of Concrete Reinforcement b. ACI 318-02 Building Code Requirements for Structural Concrete

2. American Society for Testing Materials (ASTM)

a. ASTM A82 / A82M05 Standard Specification for Steel Welded Wire

Reinforcement, Plain, for Concrete b. ASTM A1064 / A0164M Standard Specification for Carbon-Steel Wire and

Welded Wire Reinforcement, Plain and Deformed, for Concrete

c. ASTM A615 / A615M06 Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

3. Concrete Reinforcing Steel Institute (CRSI)

a. Design Handbook – 2002 Edition.

PART 2 – PRODUCTS 2.1 MATERIALS

A. Reinforcing Bars: ASTM A615, Grade 60. Stirrups and ties may be Grade 40. B. Welded Wire Fabric: ASTM A185, flat sheets. C. Steel Wire: ASTM A 82, 16 gauge.

Page 64: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 032000-2 CONCRETE REINFORCEMENT

D. Supports for Reinforcing Steel: Wire bar type meeting the requirements of CRSI Manual of Standard Practice.

2.2 FABRICATION

A. Fabricate reinforcing steel in accordance with fabricating tolerances in ACI 315.

PART 3 – EXECUTION 3.1 PLACING BAR SUPPORTS

A. General: Provide bar supports meeting the requirements of CRSI Specification for Placing Bar Supports.

B. Slabs-on-grade: Use supports with sand plates or precast concrete blocks or horizontal

runners where base material will not support chair legs.

3.2 PLACING REINFORCING STEEL

A. General: Comply with CRSI Code of Standard Practice for “Placing Reinforcing Bars”. B. Clean reinforcing steel of loose rust and mill scale, earth, ice, and other materials, which

reduce or destroy bond with concrete. C. Accurately position, support and secure reinforcing steel against displacement by

formwork, construction, or concrete placement operations. Place reinforcing steel to obtain minimum coverages. Arrange, space and securely tie bars and bar supports to hold reinforcing steel in position during concrete placement operations. Set wire ties so ends are directed into concrete, not toward exposed concrete surfaces.

1. Concrete Cover: a. Bars larger than No. 5 2” b. Bars No. 5 and smaller 1-1/2”

c. Concrete cast against and permanently exposed to earth 3”

D. Rebar Splices: Locate at points of minimum stress. Unless noted otherwise, provide lap

splices 30 bar diameters (18” minimum) in length. E. Welded Wire Fabric Splices: Lap one complete wire spacing. F. Corner Reinforcing: Provide corner bars of same size and spacing as horizontal

reinforcing steel. Lap with horizontal reinforcing 30 bar diameters of 18” minimum length.

G. Reinforcing at Construction/Control Joints: Continue reinforcing steel through

construction joints unless noted otherwise. Discontinue reinforcing steel 2 inches from performed construction joints in slabs-on-grade.

END OF SECTION

Page 65: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-1 CAST-IN-PLACE CONCRETE

SECTION 033000 – CAST IN PLACE CONCRETE PART 1 – GENERAL 1.1 WORK INCLUDED

A. This section covers cast-in-place concrete including finishing and curing. 1.2 RELATED WORK SPECIFIED ELSEWHERE

A. Concrete Forming and Accessories – Section 031000. B. Concrete Reinforcement – Section 032000.

1.3 REFERENCE STANDARDS

A. Comply with the requirements of the following specifications and standards.

1. American Concrete Institute (ACI)

a. ACI 306-90 Standard Specification for Cold Weather Concreting b. ACI 301 Standard Specifications for Structural Concrete c. ACI 306 Cold Weather Concreting

2. American Society for Testing Materials (ASTM)

a. ASTM C 31/ Standard Practice for Making and Curing Concrete C 31M-3a Test Specimens in the Field b. ASTM C 33-03 Standard Specification for Concrete Aggregates c. ASTM C 39/ Standard Test Method for Compressive C 39M-05 Strength of Cylindrical Concrete Specimens d. ASTM C 94/ Standard Specification for Ready-Mixed C 94M-05 Concrete e. ASTM C 131-03 Standard Test Method for Resistance to Degradation of

Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angles Machine

f. ASTM C 136-06 Standard Test Method for Sieve Analysis of Fine and

Coarse Aggregates g. ASTM C 143 Standard Test Method for Slump of Hydraulic C 143M-05a Cement Concrete h. ASTM C 150-05 Standard Specification for Portland Cement

Page 66: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-2 CAST-IN-PLACE CONCRETE

i. ASTM C 171-03 Standard Specification for Sheet Materials for Curing Concrete

j. ASTM C 172-04 Standard Practice for Sampling Freshly Mixed Concrete k. ASTM C 173/ Standard Test Method for Air Content of Freshly C 173M-91 Mixed Concrete by the Volumetric Method l. ASTM C 231-04 Standard Test Method for Air Content of Freshly Mixed

Concrete by the Pressure Method m. ASTM C 260-01 Standard Specification for Air Entraining Admixtures

for Concrete n. ASTM C 309-03 Standard Specification for Liquid Membrane-Forming

Compounds for Curing Concrete o. ASTM C330 Standard Specification for Concrete Lightweight

Aggregates p. ASTM C 494/ Standard Specification for Chemical Admixtures for C 494M-05a Concrete q. ASTM C 618-05 Standard Specification for Coal Fly Ash and Raw or

Calcined natural Pozzolan for Use in Concrete r. ASTM D 4318-05 Standard Test Method for Liquid Limit, Plastic Limit,

and Plasticity Index of Soils 1.4 SUBMITTALS

A. Product Data: Submit manufacturer’s product data with application and installation instructions for proprietary materials and admixtures.

B. Concrete Mix Design: 1. Submit mix design in accordance with ACI-301, Section 4.

2. Submit with mix design results of laboratory tests performed within previous

6 months indicating aggregates from the proposed source comply with the requirements of ASTM C 33 or C 330 as applicable.

3. Submit the proposed area of use for each mix design submitted.

C. Test Reports: Submit copies of test reports for concrete compressive strength, air content, temperature and slump.

Page 67: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-3 CAST-IN-PLACE CONCRETE

PART 2 – PRODUCTS 2.1 MATERIALS

A. Portland Cement: ASTM C 150, Type I or II, low alkali. Use one brand of cement throughout project.

B. Normal Weight Aggregates: ASTM C 33. Provide aggregates from a single source for

exposed concrete. C. Lightweight Aggregates: ASTM C 330. Provide aggregates from single source for each

class of concrete. D. Water: Potable. E. Air-Entraining Admixture: ASTM C 260. F. Water Reducing Admixture: ASTM C 494. G. Fly-Ash: ASTM C 618, Class F. H. Moisture-Retaining Cover: Provide waterproof paper, polyethylene film, or

polyethylene-coated burlap meeting the requirements of ASTM C 171. I. Liquid Membrane-Forming Curing Compound: Liquid type membrane-forming curing

compound meeting the requirements of ASTM C 309; Type 2, white pigmented, for exposed exterior concrete.

J. Granular base shall meet the following grading requirements when tested in accordance

with ASTM C 136.

Sieve Size Percent Passing (Square Openings) by Weight 1 inch 100 ¾ inch 85-100 No. 4 45-95 No. 200 0-8

The plasticity index shall be no greater than 3 when tested in accordance with ASTM D 4318. The coarse aggregate shall have a percent wear of 50 or less than tested in accordance with ASTM C 33.

2.2 PROPORTIONING AND DESIGN OF MIXES

A. Prepare design mixes for each type and strength of concrete by either laboratory trial mixture or field experience methods as specified in ACI 301, Section 4. If trial mixture method is used, employ an independent testing facility, acceptable to the Owner’s Representative, for preparing and reporting proposed mix designs.

Page 68: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-4 CAST-IN-PLACE CONCRETE

B. Submit written reports to Owner’s Representative, of each proposed mix for each class of concrete at least 15 days prior to start of work. Do not begin concrete production until mixes have been approved.

C. Refer to the Drawings for concrete strengths. D. Admixtures

1. Use air-entraining admixture in all concrete, except air entrainment may be

omitted from concrete to receive a steel trowel finish. The entrained air content shall be 4-7 percent.

2. Use water reducing admixture conforming to ASTM C 494, Type A, in all

concrete unless approved otherwise by the Owner’s Representative. 3. Use high range water reducing admixture conforming to ASTM C 494, Type F,

in all concrete slabs unless approved otherwise by the Owner’s Representative. 4. All other admixtures shall have the written approval of the Owner’s

Representative. 5. Calcium chloride is not permitted. 6. All admixtures, except high range water reducers, shall be added to the concrete

at the batch plant. 7. Concrete for slabs to receive a steel trowel or float finish shall not contain both

fly ash and high range water reducer.

PART 3 – EXECUTION 3.1 COORDINATION

A. Coordinate the installation of joint materials with placement of forms and reinforcing steel. Set screeds accurately. Embedded items shall be accurately aligned and adequately supported. Verify installation of mechanical, plumbing, and electrical items to be embedded in concrete. Correct any unsatisfactory condition before proceeding further.

3.2 PREPARATION

A. Before placing concrete, clean and roughen surface of previously placed concrete. Clean reinforcing steel. Remove debris, providing clean-outs at bottom of forms when necessary. Moisten surfaces to receive concrete unless otherwise prepared. Remove excess water before placing concrete.

3.3 CONCRETE PLACEMENT

A. General: Comply with ACI 301.

Page 69: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-5 CAST-IN-PLACE CONCRETE

B. Place concrete continuously in layers not deeper than 24 inches. Concrete shall not be placed against concrete which has hardened sufficiently to cause the formation of seams or planes of weakness. If a section cannot be placed continuously, provide construction joints. Deposit concrete as nearly as practicable to its final location to avoid segregation. Do not use vibrators to transport concrete.

C. Maintain reinforcing in proper position during concrete placement operations. D. Consolidate concrete, immediately after placing, by mechanical vibrating equipment

supplemented by hand-spading, rodding or tamping. Use equipment and procedures for consolidation of concrete in accordance with ACI recommended practices.

E. Bring slab surfaces to correct level with straightedge and strike off. Use bull floats or

darbies to smooth surface. Do no disturb slab surfaces prior to beginning finishing operations.

F. Cold Weather Concreting: Protect concrete work from physical damage or reduced

strength caused by frost, freezing or low temperatures. Comply with ACI 306.1. G. Hot Weather Concreting: When hot weather conditions exist that would impair quality

and strength of concrete, reduce delivery time of ready mix concrete, lower the temperature of materials, or add retarder to ensure that the concrete is plastic. Retempering with water is not allowed.

3.4 FINISH OF FORMED SURFACES

A. Rough Form Finish: Provide where formed concrete surfaces are not exposed to view in accordance with ACI 301. Surface imperfections shall be repaired and patched and projections exceeding ¼” in height rubbed down or chipped off, otherwise leaving the surface with the texture imparted by the form.

B. Smooth Form Finish: Provide where formed concrete surfaces are to view in accordance

with ACI 301. The surface shall be smooth and free of imperfections. Projections rubbed down or chipped off.

3.5 SLAB FINISHES

A. Float Finish: Begin floating when surface water has disappeared and when concrete has stiffened sufficiently to permit operation of power-driven or hand floats. Consolidate surface with power-driven floats, or by hand-floating if area is small or inaccessible to power units. The final surface finish shall have a minimum FF =35 and a minimum FL =25 per ALI requirements.

B. Trowel Finish: Apply trowel finish to slab surfaces as specified on the Drawings. After

floating, begin first trowel finish using a hand trowel. Finish concrete surface by final hand-troweling operation, free of trowel marks, uniform in texture and appearance. The finish surface shall have a minimum FF =35 and a minimum FL =25 per ALI requirements.

Page 70: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033000-6 CAST-IN-PLACE CONCRETE

C. Broom Finish: Apply broom finish as specified on the Drawings. Immediately after concrete has received a float finish, draw a broom across the surface to give a course transverse scored texture.

3.6 CONCRETE CURING AND PROTECTION

A. General: Protect freshly placed concrete form premature drying and excessive cold or hot temperatures. Start initial curing as soon as free water has disappeared from concrete surface after placing and finishing. Continue curing for at least 7 days.

B. Moisture-retaining cover curing: Cover concrete surfaces with moisture-retaining cover

for curing concrete, placed in widest practicable width with sides and ends lapped at least 3” and sealed. Repair any holes or tears in cover during curing period.

C. Curing compound: At the Contractor’s option, exterior concrete slabs may be cured

using curing compound. Apply curing compound uniformly in accordance with the manufacturer’s printed instructions.

3.7 FIELD QUALITY CONTROL

A. The Contractor shall employ and pay for the services of a qualified testing laboratory to perform the following tests in accordance with the cited standards and shall submit test reports to the Owner’s Representative.

1. Sampling Fresh Concrete: ASTM C 172. 2. Slump: ASTM C 143. Perform one test for each set of compressive strength test

specimens. 3. Air Content: ASTM C 173 or C 231. Perform one test for each set of

compressive strength test specimens. 4. Concrete Temperature: Test hourly when air temperature is 40 degrees F and

below, when 80 degrees F and above, and when compression test specimens are made.

5. Compression Test Specimen: ASTM C 31. Provide one set of 4 standard

cylinders for each compressive strength test, unless otherwise directed. Mold and store cylinders for laboratory cured test specimens except when field cure test specimens are required. Mold one set of standard cylinders each 30 yards of concrete or fraction thereof.

6. Compressive Strength Tests: ASTM C 39; test 1 specimen at 7 days, 2

specimens at 28 days, and retain one specimen in reserve for later testing. Additional Tests: The testing laboratory shall make additional tests of in-place concrete when test results indicate specified concrete strengths and other characteristics have not been attained in the structure as directed by the Owner’s Representative. The Contractor shall pay for such tests conducted, and any other additional testing as may be required, when unacceptable concrete is verified.

END OF SECTION

Page 71: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 033100-1 SCULPTURE FOUNDATIONS

SECTION 033100 – SCULPTURE FOUNDATIONS PART 1 – GENERAL 1.1 WORK INCLUDED

A. This section covers concrete foundations for art sculptures. 1.2 RELATED WORK SPECIFIED ELSEWHERE

A. Concrete Forming and Accessories – Section 031000. B. Concrete Reinforcement – Section 032000. C. Cast in Place Concrete -Section 33000

PART 2 – EXECUTION 2.1 Sculpture foundations shall be constructed in accordance with the following details.

Page 72: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section
Page 73: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section
Page 74: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321400 - 1 CONCRETE UNIT PAVERS

SECTION 321400 – CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 WORK INCLUDED

A. This section covers furnish and installation of concrete unit pavers and associated concrete base, bedding sand, and joint sand as specified on the Drawings and in accordance with these Specifications.

1.2 QUALITY ASSURANCE

A. The Contractor shall hold a current Basic Level Certificate from the Interlocking Concrete

Pavement Institute (ICPI) contractor certification program. 1.3 SUBMITTALS

A. Prior to delivery of the associated material to the site, the Contractor shall submit the

following product specific documentation for approval:

1. Four full size samples of pavers of each concrete paver type, size and color specified on the Drawings for approval by the Owner’s representative prior to installation.

2. Test results from an independent testing laboratory for concrete paver compliance to

ASTM C936. 1.4 NOTIFICATION

A. Notify Owner’s Representative two (2) days prior to the placement of any pavers. 1.5 PRODUCT HANDLING

A. Concrete unit pavers shall be delivered to the site in steel banded, plastic banded, or plastic wrapped cubes capable of transfer by fork lift or clamp lift. Concrete unit pavers shall be delivered and unloaded in such a manner that no damage occurs to the product during handling, hauling and unloading.

PART 2 - MATERIALS 2.1 CONCRETE PAVERS

A. Concrete unit pavers shape, size and color shall be as specified on the Drawings and shall conform with ASTM C936.

B. Concrete pavers shall be made from no-slump concrete. C. Pavers shall have an average compressive strength of 8,000 psi with no individual unit under

7,200 psi when tested in accordance with ASTM C140. D. Pavers shall have an average water absorption of 5% with no unit greater than 7% per ASTM C140.

Page 75: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321400 - 2 CONCRETE UNIT PAVERS

E. At freeze-thaw testing, the average mass loss of all specimens tested shall not be greater than (A) 225 g/m2 when subject to 28 freeze thaw cycles, or (b) 500 g/m2 when subject to 49 freeze thaw cycles. Testing shall be conducted using a 3% saline solution in according to ASTM C-1645.

F. Measured length or width of individual unit pavers shall not differ by more than +/- 0.063

inches and measured thickness shall not differ by more than +/- 0.125 inches from the specified standard dimensions.

G. Pigment in pavers shall conform to ASTM C979.

2.2 BEDDING COURSE SAND

A. Clean, non-plastic sand, free from deleterious or foreign matter, natural or manufactured from crushed rock. B. Do not use limestone screenings or stone dust. C. Micro Deval Degradation shall be less than 8% as per ASTM D-7428. D. Percent combined of sub-angular and sub-rounded shall be greater than 60% as per ASTM D-

2488. E. LA Abrasion <40 as per ASTM C-131. F. Minimum CBR of 80% as per ASTM D-1883. G. Gradation shall conform to ASTM C-33 requirements for concrete sand (listed in Table 1) as

tested in accordance to ASTM C-136.

Table 1 Grading Requirements for Bedding Sand

Sieve Size Percent Passing 3/8 in.(9.5 mm) 100 No. 4 (4.75 mm) 95 to 100 No. 8 (2.36 mm) 85 to 100 No. 16 (1.18 mm) 50 to 85 No. 30 (0.600 mm) 25 to 60 No. 50 (0.300 mm) 5 to 30 No. 100 (0.150 mm) 0 to 10 No. 200 (0.075 mm) 0 to 1

2.3 JOINTING SAND

A. Clean, non-plastic, free from deleterious or foreign matter, natural or manufactured from

crushed rock.

Page 76: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321400 - 3 CONCRETE UNIT PAVERS

B. Gradation shall conform to ASTM C-144 requirements for mortar sand (listed in Table 2) as tested in accordance to ASTM C-136.

Table 2 Grading Requirements for Joint Filling Sand

Sieve Size Percent Passing No. 4 (4.75 mm) 100

No. 8 (2.36 mm) 95 to 100 No. 16 (1.18 mm) 70 to 100 No. 30 (0.600 mm) 40 to 100 No. 50 (0.300 mm) 10 to 35 No. 100 (0.150 mm) 2 to 15 No. 200 (0.075 mm) 0 to 5

2.4 CONCRETE BASE

A. Concrete base shall be in accordance with Specification Sections 031000, 032000, 033000

and the Drawings. PART 3 – EXECUTION 3.1 ENVIRONMENTAL CONDITONS

A. Do not install pavers during rain, snow or freezing conditions.

B. Do not install frozen bedding course sand or jointing sand.

3.2 MOCK-UPS

A. Install a 10 ft x 10 ft mock-up paver area for each type of paver and pattern specified on the Drawings, following the installation practices described herein for review and approval by the Owner’s Representative.

B. Mock-up shall demonstrate surcharge of the sand bedding course, laying pattern, joint sizes,

surface profile and color blend. C. The approved mock-up shall be the standard to which the work shall comply. D. Contractor shall not proceed with the installation of the pavers until each mock-up is reviewed

and approved by the Owner’s Representative. E. Subject to approval by the Owner’s Representative, the mock-up may be retained as part of

the finished work. If mock-up is not retained, remove and dispose of mock-up at the completion of the project.

3.2 CONCRETE BASE

A. Prior to installing base course, subgrade shall be compacted to minimum 95% modified

Proctor density per ASTM D1557.

Page 77: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321400 - 4 CONCRETE UNIT PAVERS

B. Density testing of subgrade shall be conducted to verify conformance with the requirements of the Drawings and Specifications.

C. The concrete base shall be constructed in accordance with Specification Sections 031000,

032000, 033000 and the Drawings. D. Concrete base shall be cleaned of any foreign materials before installation of the bedding

sand.

3.3 SAND BEDDING COURSE

A. The finished concrete base shall be approved by the Owner’s representative prior to the placement of the sand bedding course.

B. The uncompacted sand bedding course shall be spread evenly over the area to be paved and

screeded to a level that will produce 1" (25 mm) thickness after the paving stones have been placed and vibrated. Screeding shall be performed with a mechanical spreader (e.g.: an asphalt paver) or by the use of screed rails and boards.

C. Once screeded and leveled to the desired elevation, sand bedding course shall not be

disturbed in any way.

3.4 PLACING PAVERS

A. Concrete pavers shall be installed in the pattern(s) shown on the Drawings. Maintain straight pattern lines. B. Concrete pavers shall be installed from a minimum of three (3) bundles if installed by hand,

or a minimum of six (6) bundles if installed by mechanical methods. Pavers shall be selected evenly from bundles to ensure even blending of the natural variations in color.

C. Joints between individual concrete pavers and between pavers and edge restraints shall be

between 1/16" and 3/16" wide. D. Contractor shall ensure that the sand bedding course is not stepped on or otherwise disturbed

during placement of pavers. Contractor shall work from side of pavers during installation. Tamp concrete unit pavers into place.

E. String lines shall be used to hold all pattern lines true. F. The final surface elevation of pavers shall not deviate more than 3 /8 in. (10 mm) under a 10

ft (3 m) long straightedge. G. The surface elevation of pavers shall be 1 /8 in. to 1 /4 in. (3 mm to 6 mm) above adjacent

drainage inlets, concrete collars or channels.

Page 78: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321400 - 5 CONCRETE UNIT PAVERS

H. Gaps at the edge of the paver surface shall be filled with standard edge unit pavers or with pavers cut to fit. Cutting shall be accomplished using a masonry saw and shall leave a clean edge. No cuts shall result with a paver less than 1/3 of original dimension. Where gaps at edges are less than 1-5/8" (40 mm), the gaps shall be filled with a sand cement mortar no leaner than 4:1.

I. Paving stones shall be compacted into the sand bedding course with the surface clean and

joints open using a low amplitude plate compactor with minimum centrifugal compaction force of 5,000 pounds at a frequency of 75 hz to 100 hz. The pavers shall be compacted to achieve consolidation of the sand bedding and brought to a level and even profile by not less than three passes. Initial compaction shall proceed as closely as possible following the installation of the paving units.

J. Any concrete pavers that are damaged during compaction operations shall be removed and replaced.

K. After compaction, dry joint sand shall be spread over the paving stone surface and swept into

the joints. Vibrate with minimum two passes of the compactor until the joints are completely filled. Do not compact within three (3) feet of unrestrained edges of the unit pavers.

L. All work to within 3 ft (1 m) of the laying face shall be left fully compacted with sand-filled

joints at the end of each day. The laying face shall be covered with plastic sheets overnight if not closed with cut and compacted pavers.

M. Surplus sand shall be swept from the surface upon completion of the work.

3.5 MAINTENANCE MATERIALS

A. Provide 100 square feet of additional pavers for use by the Owner for maintenance and repair.

B. Additional pavers shall be from the same production run as the installed pavers.

C. Store pavers in area designated by the Owner.

END OF SECTION

Page 79: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321500 - 1 CONCRETE UNIT GRID PAVERS

SECTION 321500 – CONCRETE UNIT GRID PAVERS PART 1 - GENERAL 1.1 WORK INCLUDED

A. This section covers furnish and installation of unit concrete unit grid pavers and associated base course and bedding sand as specified on the Drawings and in accordance with these Specifications.

1.2 QUALITY ASSURANCE

A. The Contractor shall hold a current Basic Level Certificate from the Interlocking Concrete

Pavement Institute (ICPI) contractor certification program. 1.3 SUBMITTALS

A. Prior to delivery of the associated material to the site, the Contractor shall submit the following

product specific documentation for approval:

1. Four full size samples of pavers of type, size and color specified on the Drawings for approval by the Owner’s representative prior to installation.

2. Test results from an independent testing laboratory for concrete unit grid paver

compliance to ASTM C1319. 3. Sieve analysis of base course aggregate per ASTM C-136. Durability of aggregate

using Micro Deval Degradation using ASTM D6928. Percentage of angular and sub-angular particles of aggregate per ASTM D2488.

1.4 NOTIFICATION

A. Notify Owner’s Representative two (2) days prior to the placement of any pavers. 1.5 PRODUCT HANDLING

A. Concrete unit grid pavers shall be delivered to the site in steel banded, plastic banded, or plastic wrapped cubes capable of transfer by fork lift or clamp lift. Concrete unit grid pavers shall be delivered and unloaded in such a manner that no damage occurs to the product during handling, hauling and unloading.

PART 2 - MATERIALS 2.1 CONCRETE PAVERS

A. Concrete unit grid paver shape, size and color shall be as specified on the Drawings and shall conform with ASTM C1319.

B. Pavers shall have an average compressive strength of 5,000 psi with no individual unit under

4,500 psi when tested in accordance with ASTM C140.

Page 80: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321500 - 2 CONCRETE UNIT GRID PAVERS

C. Pavers shall have a maximum water absorption of 10 pounds/cubic foot with no unit greater than 12 pounds/cubic foot when tested in accordance with ASTM C140.

D. Measured length or width of test specimens shall not differ by more than +/- 0.125 inches and

measured thickness shall not differ by more than +/- 0.125 in from the specified standard dimensions.

E. Pigment in pavers shall conform to ASTM C979.

2.2 BEDDING COURSE SAND

A. Clean, non-plastic sand, free from deleterious or foreign matter, natural or manufactured from crushed rock.

B. Do not use limestone screenings or stone dust. C. Micro Deval Degradation shall be less than 8% as per ASTM D7428. D. Percent combined of sub-angular and sub-rounded shall be greater than 60% as per ASTM

D2488. E. LA Abrasion <40 as per ASTM C131 F. Minimum CBR of 80% as per ASTM D1883. G. Gradation shall conform to ASTM C-33 requirements for concrete sand (listed in Table 1) as

tested in accordance to ASTM C136.

Table 1 Grading Requirements for Bedding Sand

Sieve Size Percent Passing 3/8 in.(9.5 mm) 100 No. 4 (4.75 mm) 95 to 100 No. 8 (2.36 mm) 85 to 100 No. 16 (1.18 mm) 50 to 85 No. 30 (0.600 mm) 25 to 60 No. 50 (0.300 mm) 5 to 30 No. 100 (0.150 mm) 0 to 10 No. 200 (0.075 mm) 0 to 1

2.3 JOINT FILL

A. Soil in unit grid paver voids shall be amended soil per Specification Section 329223. B. Sod shall be as specified on the Drawings.

2.4 BASE COURSE

A. Base course shall be clean, non-plastic, free from deleterious or foreign matter, natural or manufactured from crushed rock.

Page 81: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321500 - 3 CONCRETE UNIT GRID PAVERS

B. Gradation shall conform to ASTM D2940 as listed in Table 2.

Table 2 Grading Requirements for Base Course Material

Sieve Size Percent Passing

2 in (50 mm) 100 1 ½ in (37.5 mm) 95 to 100 ¾ in (19 mm) 70 to 92 3/8 in (9.5 mm) 50 to 70 No. 4 (4.75 mm) 35 to 55

No. 30 (0.600 mm) 12 to 25 No. 200 (0.075 mm) 0 to 8

2.5 Edge Restraints

A. Edge restraints shall be metal edging with ½ inch diameter by 12 inch long galvanized steel anchor spikes, as specified on the Drawings.

PART 3 – EXECUTION 3.1 ENVIRONMENTAL CONDITONS

A. Do not install pavers during rain, snow or freezing conditions.

B. Do not install frozen bedding course sand or jointing sand.

3.2 MOCK-UPS

A. Install a 6 ft x 6 ft mock-up paver area for paver and pattern specified on the Drawings, following the installation practices described herein for review and approval by the Owner’s Representative.

B. Mock-up shall demonstrate surcharge of the sand bedding course, laying pattern, joint sizes

and surface profile. C. The approved mock-up shall be the standard to which the work shall comply. D. Contractor shall not proceed with the installation of the pavers until each mock-up is reviewed

and approved by the Owner’s Representative. E. Subject to approval by the Owner’s Representative, the mock-up may be retained as part of the

finished work. If mock-up is not retained, remove and dispose of mock-up at the completion of the project.

3.2 BASE COURSE

1. Prior to installing base course, subgrade shall be compacted to minimum 95% modified

Proctor density per ASTM D1557.

Page 82: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321500 - 4 CONCRETE UNIT GRID PAVERS

2. The base course aggregate shall be spread and compacted in uniform layers not exceeding 6 inch loose thickness.

3. Base course shall be compacted to minimum 98% modified Proctor density according to ASTM D1557.

4. Density testing of subgrade and base course shall be conducted to verify conformance with

the requirements of the Drawings and Specifications. 5. Surface tolerance shall be plus or minus 3/8 in. (10 mm) over a 10 ft. (3 m) straight edge laid

in any direction. 6. The upper surface of the base shall be sufficiently well graded and compacted to prevent

infiltration of the bedding sand into the base both during construction and throughout its service life. Segregated areas of the granular base shall be blended by the application of crushed fines that have been watered and compacted into the surface.

3.3 EDGE RESTRAINTS

A. Edge restraints shall be installed along the entire perimeter of the paving where a stationary

object does not exist.

B. Edge restraints shall be installed directly on the base course. Individual pieces shall be connected in accordance with the manufacturer’s specifications.

C. Install metal spike anchors to secure the edge restraints in place. Spike placement shall be

maximum 12 inches on center.

3.3 SAND BEDDING COURSE:

A. The finished base course shall be approved by the Owner’s representative prior to the placement of the sand bedding course.

B. The uncompacted sand bedding course shall be spread evenly over the base course and

screeded to a level that will produce 1" (25 mm) thickness after the unit grid pavers have been placed and vibrated. Screeding shall be performed with a mechanical spreader (e.g.: an asphalt paver) or by the use of screed rails and boards.

C. Once screeded and leveled to the desired elevation, sand bedding course shall not be

disturbed in any way.

3.4 PLACING PAVERS

A. Concrete pavers shall be installed in the pattern shown on the Drawings. Maintain straight pattern lines. B. Joints between individual concrete pavers and between pavers and edge restraints shall be

between 1/8" and 1/4" (3 mm to 6 mm) wide. Individual units shall not be pushed or hammered such that they touch each other.

C. Contractor shall ensure that the sand bedding course is not stepped on or otherwise disturbed

during placement of pavers. Contractor shall work from side of pavers during installation.

Page 83: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 321500 - 5 CONCRETE UNIT GRID PAVERS

D. String lines shall be used to hold all pattern lines true.

The final surface elevation of pavers shall not deviate more than 3 /8 in. (10 mm) under a 10

ft (3 m) long straightedge. E. The surface elevation of the unit grid pavers shall be 1 /8 in. to 1 /4 in. (3 mm to 6 mm) above

adjacent drainage inlets, concrete collars or channels. G. Gaps at the edge of the paver surface shall be filled with pavers cut to fit. Cutting shall be

accomplished using a masonry saw and shall leave a clean edge. H. Paving stones shall be compacted into the sand bedding course with the surface clean and

joints open using a low amplitude plate compactor with minimum centrifugal compaction force of 4,000 pounds at a frequency of 75 hz to 100 hz. If required to prevent cracking and chipping of unit grid pavers, install a rubber or neoprene pad between the compactor and the unit grid pavers.

I. The pavers shall be compacted to achieve consolidation of the sand bedding and brought to a

level and even profile by not less than three passes. Initial compaction shall proceed as closely as possible following the installation of the paving units.

J. Any concrete unit grid pavers that are damaged during compaction operations shall be

removed and replaced. K. After compaction, spread amended soil into the joints and openings, then vibrate until the soil

is within ½ inch (13 mm) of the top surface of the unit grid pavers throughout. Vibrate with minimum two passes until the joints and openings are filled to within ½ inch of the top. Do not compact within three (3) feet of unrestrained edges of the unit grid pavers.

L. All work to within 3 ft (1 m) of the laying face shall be left fully compacted with sand-filled

joints at the end of each day. The laying face shall be covered with plastic sheets overnight if not closed with cut and compacted pavers.

M. Install sod in unit grid paver openings as specified on the Drawings. N. Surplus material shall be swept from the surface upon completion of the work.

3.5 MAINTENANCE MATERIALS

A. Provide 100 square feet of additional pavers for use by the Owner for maintenance and repair.

B. Additional pavers shall be from the same production run as the installed pavers.

C. Store pavers in area designated by the Owner.

END OF SECTION

Page 84: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328300-1 PLANT MATERIAL PRESERVATION

SECTION 328300 - PLANT MATERIAL PRESERVATION PART 1 – DESCRIPTION OF WORK 1.1 Protection of existing plant material designated to remain. PART 2 - PRODUCTS Not applicable. PART 3 - EXECUTION 3.1 The Contractor shall not damage existing trees, shrubs, perennials or sod that are within the project

limits and are designated to remain or are outside the limits of construction, unless otherwise noted on the Drawings.

3.2 No alteration of grade, including removal of soil, shall be permitted within the drip line of existing

tree or shrub designated to remain. 3.3 Compaction shall not be permitted within the drip line of any tree or shrub designated to remain. 3.5 The Contractor shall not cut roots of plants designated to remain. 3.6 If irrigation or utility work is required within root zones, irrigation lines or utilities shall be

installed by hand excavating under roots or boring under the root zone. Minimum 12 inch clearance shall be provided between the hand excavation or bore and the roots. Do not cut roots over 1” diameter.

3.7 No concrete trucks shall be allowed to clean chutes or dump excess concrete or any other

cementitious product in any portion of the site. The waste of other cementitious materials shall be cleaned from the surface and shall not be turned under during final grading.

3.8 Protective barriers (fencing) shall be erected at shrubs designated to remain as necessary to prevent

damage to bark, leaf, and root tissue of plants designated to remain. Protective barriers at trees shall be in accordance with Specification Section 015639.

3.9 In the event a plant designated to remain is damaged or destroyed, it shall be replaced with an

approved specimen of the same species and of equal size. If a replacement plant is not available in a size equal to the damaged plant, a suitable replacement and associated monetary credit to the Owner will be determined by the Owner and the Owner’s Representative, whose decision shall be final.

END OF SECTION

Page 85: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 1 IRRIGATION SYSTEM

SECTION 328400 - LANDSCAPE IRRIGATION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION OF WORK

A. The work consists of installing a complete underground irrigation system as shown on the Drawings and as specified hereafter. The Contractor shall furnish all labor, equipment, materials and permits necessary for the completion of the system, unless otherwise specified to be furnished by others. Unless otherwise specified or indicated on the Drawings, the construction of the irrigation system shall include the furnishing, installing and testing of all pipe, fittings, valves, heads, wires, valve boxes and all other components pertinent to the system. The Contractor shall perform all trenching, excavating, boring, backfilling, compacting, concrete work, electrical work, welding, and any other work necessary for the completion of the irrigation system.

1.2 SITE INVESTIGATION

A. The Contractor shall examine related work and surfaces before starting the work of this section. The Contractor shall report to the Owner’s Representative, in writing, conditions which will prevent the proper execution of irrigation installation. Deviations from Drawings and Specifications shall be executed only with the express permission of the Owner’s Representative and at no cost to the Owner. If obvious inadequacies or inappropriate design are found on the Drawings, they shall be promptly brought to the attention of the Owner’s Representative in writing before proceeding with installation of the system.

1.3 CODES, RULES AND SAFETY ORDERS

A. All work and materials shall be in full accordance with the latest local rules and regulations of safety.

1.4 PROTECTION

A. The Contractor shall furnish and maintain all warning signs, shoring, barricades, red lanterns, and other protection devices, as required by the Safety Orders of the Division of Industrial Safety and local ordinances.

1.5 DEVIATIONS OF LAYOUT

A. Reasonable changes in the location of piping, valves or other irrigation components shown on the Drawings will be considered prior to installation. Deviations from specified locations must be approved by the Owner’s Representative prior to installation. Any changes in location of irrigation components shall be effected at no cost to the Owner.

1.6 COORDINATION

A. The Contractor shall coordinate and cooperate with other contractors on site to ensure rapid and efficient completion of all contracted work.

Page 86: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 2 IRRIGATION SYSTEM

1.7 SUBMITTALS

A. The Contractor shall prepare submittals providing manufacturer’s specifications and “cut sheets” on the following components:

Manual and automatic valves Heads Enclosures Valve boxes 24 Volt wire Wire splicing materials Piping PVC fittings Joint materials Detectable line marking tape PVC primer and cement Emitter modules Threaded joint sealant or tape

B. The submittal shall be bound or provided electronically in PDF format, and shall be clearly labeled with the project name and date. If the submittal is bound, the Contractor shall provide five sets of the submittal.

C. The Contractor shall not proceed with the irrigation system work until receiving approval

of the irrigation submittals from the Owner’s Representative.

1.8 RECORD DRAWINGS

A. The Contractor shall provide and keep up to date a complete set of “Record Drawings” which shall be corrected daily to show all changes in the location of heads, valves, points of connection, pull boxes and wire splice boxes, pipe and wire routing and other changes that may have been made from the original Drawings and Specifications.

B. At the time of final acceptance, the Contractor shall furnish one electronic copy (on CD)

and one paper copy of “Record Drawings” prepared by a qualified draftsperson in AutoCAD format, showing the entire completed system as actually installed. This is the responsibility of the Contractor and shall not be construed to be the responsibility of any other party. This drawing shall be accurate and to scale. The symbols for valves, heads, and piping and other components shall be the same as originally shown on the Drawings. The legend shall be modified to designate any “record” changes. This “Record Drawing” shall be drawn on a project base sheet provided by the Owner’s Representative. The final drawings shall be dated and clearly labeled “RECORD DRAWING”.

1.9 CONTROLLER CHART

A. The Contractor shall update the existing irrigation controller chart(s) (maximum two each) to show changes made to the irrigation system within the limits of the project. The chart updates shall show the area covered by each automatic valve station within the limits of the project with a different color used to show the area of coverage for each valve. Contractor shall install one chart in the controller enclosure and shall provide one chart to the Owner’s Representative.

B. If an existing controller chart is not available, the Contractor shall provide two new controller charts showing the area covered by each automatic valve station within the limits of the project. Charts shall be a reduced drawing of the actual “Record Drawing” system. The size of the charts shall be the maximum size that the controller door will allow. If controller sequence is not legible when the drawing is reduced, drawing shall be enlarged to a size that is readable. When completed and approved, charts shall be

Page 87: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 3 IRRIGATION SYSTEM

hermetically sealed between two pieces of plastic, each piece being minimum 20 mils thick. Contractor shall install one chart in the controller enclosure and shall provide one chart to the Owner’s Representative.

C. Charts shall be completed and approved prior to final observation and acceptance of the

irrigation system. PART 2 - PRODUCTS 2.1 MATERIALS

A. All materials shall be new and without flaws or defects of any type and shall be the best of their class and kind. All materials shall have a minimum warranty of one year against material defects or defective workmanship.

B. All material shall be the brands and types noted on the Drawings or as specified herein, or

approved equal (refer to Section 6.7 of the New Mexico Standard Specifications for Public Works Construction, 1979 Edition).

C. The irrigation system was designed around equipment manufactured by specific

companies as a standard. Approved equal equipment by other manufacturers may be used only with the approval of the Owner’s Representative. Request for approval of non-specified materials shall be submitted to the Owner’s Representative a minimum of seven (7) days prior to the opening of bids. Submission of irrigation sprinkler heads for approval as equal shall only be considered if submitted heads match the precipitation rate, gallons per minute and coverage area of specified sprinkler heads.

2.2 PLASTIC PIPE AND FITTINGS

A. Plastic Pipe: All mainline pipe, from the point of connection to the zone valve shall be Schedule 40 PVC and shall conform to ASTM D 1785. Lateral line piping downstream of the zone valves shall be Schedule 40 PVC and shall conform to ASTM D 1785. All PVC pipe shall be continuously marked with identification of the manufacturer, type, class, and size, and shall be free of holes, foreign material, blisters, wrinkles, dents or sunburn.

B. PVC Fittings: Fittings on PVC lines shall be Schedule 40 PVC, Type 1, Cell

Classification 12454 and shall comply with ASTM D 2466.

C. Threaded Nipples: All threaded PVC nipples shall be Schedule 80 molded PVC pipe. All galvanized nipples shall be Schedule 40 galvanized steel pipe.

2.3 VALVES AND VALVE BOXES

A. Valves: Valves for use in electrically controlled automatic control systems shall be diaphragm actuated and hydraulically operated solenoid valves as specified on the Drawings.

B. Gate valves shall be as specified on the Drawings.

Page 88: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 4 IRRIGATION SYSTEM

C. Valve Boxes: Valve boxes shall be as noted on the Drawings. Valve box colors shall be

as follows: 1. Green: Turf areas 2. Tan: Gravel mulch areas

2.4 HEADS AND EMITTER MODULES

A. Heads and emitter modules shall be as specified on the Drawings.

2.5 PRIMER, CEMENT AND THREADED JOINT SEALANT

A. Primer shall conform to ASTM F 656 and meet NSF. Cement shall be low VOC, NSF approved, and meet ASTM D 2564. Cement and primer shall be IPS Weld-On depending on size and schedule of pipe and fittings as follows:

Schedule 40 PVC Pipe and Fittings up to 6” Dia.: P-68 Primer and 705 Cement Schedule 80 PVC Pipe and Fittings up to 4” Dia.: P-70 Primer and 705 Cement Schedule 80 PVC Pipe and Fittings larger than 4” Dia.: P-70 Primer and 711 Cement

B. All threaded connections between metal to metal, PVC to metal, and PVC to PVC shall be

made using Spears Blue 75 thread sealant or Polytetrafluoroethylene (PTFE) thread seal tape. PTFE thread seal tape shall comply with MIL-T-27730A Specifications shall have a minimum thickness of 3.5 mils and shall be 99% pure PTFE. Thread sealing compound shall not be used on threaded connections between sprinkler and nipple or bubbler and nipple. Thread sealant or PTFE tape shall be used in accordance with manufacturer’s installation instructions.

2.6 WIRE

A. Wire for the 24 volt wiring shall be solid copper wire, PVC insulated, UL approved

underground feeder wire for direct burial in ground. Common wires shall be #12, white, except as noted on Drawings. The control wires shall be #14 of any color other than white unless otherwise indicated on Drawings. The wire shall be supplied in either 500’ or 2,500’ rolls.

B. Wire Splicing Materials: All wire splices shall be made water-tight using 3M DBR/Y

direct bury splice kit or approved equal.

C. Control wires shall be marked with the associated valve number with E-Z Coder WDR or equal wire marking tape at each valve, at the controller and at wire splices.

2.7 DETECTABLE LINE MARKING TAPE

A. Detectable line marking tape for irrigation main and lateral lines shall be manufactured by T.A. Christy Enterprises or approved equal and shall consist of a minimum 5.0 mil (0.0050”) overall thickness; five-ply composition; ultra high molecular weight; 100% virgin polyethylene; acid, alkaline, and corrosion resistant.

Page 89: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 5 IRRIGATION SYSTEM

B. The tape width shall be a minimum of 6”. C. Elongation properties shall be in accordance with ASTM D882-80A and shall be less than

150% at break. D. Tensile strength shall be in accordance with ASTM D882-80A and shall be not less than 7800

PSI.

E. The tape shall have a minimum 20 gauge (0.0020”) solid aluminum foil core, adhered to a 2.55 mil (0.00255”) polyethylene backing.

F. Tape color and legend combination shall be in accordance with APWA requirements. The

color shall be blue and the legend shall read “CAUTION: IRRIGATION LINE BURIED BELOW”.

2.8 OTHER MISCELLANEOUS FITTINGS AND MATERIALS

A. All other miscellaneous fittings and materials shall be as specified on the Drawings. PART 3 - EXECUTION 3.1 GENERAL

A. This section includes installation specifications for all items installed as a part of the irrigation system. Certain construction procedures or minor equipment installation procedures that are necessary for the proper installation of the system may have been omitted from these specifications. In any case, Contractor shall install all materials and equipment in a neat and workmanlike manner according to manufacturer's recommendations and specifications, local and state codes, as shown on the Drawings and as specified herein.

3.2 PRODUCT HANDLING

A. The Contractor shall be responsible for correct procedures in loading, unloading, staking,

transporting and handling all materials to be used in the system. The Contractor shall avoid rough handling which could affect the useful life of equipment. Pipe shall be handled in accordance with the manufacturer's recommendations on loading, unloading and storage.

3.3 POINT OF CONNECTION

A. Existing irrigation line locations shown on the Drawings are schematic. It shall be the Contractor’s responsibility to pot hole and field check to determine actual locations as an incidental requisite to the construction contract.

B. The location of the existing controller indicated on the Drawings is approximate. It shall be the Contractor’s responsibility to field check to determine actual location as an incidental requisite to the construction contract.

C. Where connections to existing pipe or stub out is required, the Contractor shall make necessary adjustments should pipe or stub out not be located exactly as shown, at no

Page 90: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 6 IRRIGATION SYSTEM

additional cost to the Owner.

3.4 STATIC PRESSURE TEST

A. The design pressure of the irrigation system is shown on the Drawings. Prior to start of construction of the irrigation system, the Contractor shall, in the presence of the Owner’s Representative, provide a gauged test of available static pressure at the point of connection. In the event that the actual static pressure is less than the design static pressure, the Contractor shall not proceed with the work until receiving written direction from the Owner’s Representative.

3.5 EXCAVATION AND TRENCHING

A. The Contractor shall stake the location of each run of pipe and all sprinkler heads and valves prior to trenching. Each run of the system shall be approved by the Owner’s Representative prior to installation.

B. Excavation and trenching for pipe lines shall be a true and straight line with the trench

banks as nearly vertical as practical. The width of the trenches shall not be greater than necessary to permit proper joining, tamping, backfilling, bedding or any other installation procedures that may be necessary. Trench widths shall be wide enough to provide a minimum horizontal and vertical separation of 4" between pipes in the same trench.

C. In areas where trees are present, trench lines shall be adjusted on the site to eliminate any

damage to tree roots.

D. Trench depths shall be sufficient to provide the specified pipe cover as described elsewhere in these Specifications or as noted on the Drawings. In rocky areas the trench depth and width shall be increased as needed to provide for a minimum of 6"of pipe bedding at bottom and sides of pipe.

E. Depth of Bury: Minimum cover over mainline and lateral piping shall be as noted on the

Drawings. 3.6 PIPE AND FITTINGS INSTALLATION

A. Installation of plastic pipe and fittings shall be in accordance with ASTM D 2774, the

manufacturer’s recommendations and the procedures described in these Specifications.

B. Caution shall be exercised by the Contractor in handling, loading, unloading, and storing of PVC pipe and fittings. All PVC pipe shall be stored and transported in a vehicle with a bed long enough to allow the pipe to lie flat without subjecting it to undue bending or concentrated external load at any point. Pipe shall be protected from damage by exposure to sunlight. Any section of pipe that has been dented or damaged or in any other way found to be defective, either before or after laying shall be replaced with sound pipe at no cost to the Owner.

C. Before installation, the inside of the pipe shall be cleaned of all dirt and foreign matter and

shall be kept in a clean condition during and after laying of pipe. When work is not in progress, open ends of pipe and fittings shall be secured closed so that no trench water,

Page 91: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 7 IRRIGATION SYSTEM

earth or other foreign substances will enter the pipe or fittings. Where pipe ends are left for future expansion or connections, they shall be valved and capped as directed on the Drawings.

D. All PVC pipe and fittings shall be assembled to permit the pipe or fittings to be jointed at

the true parallel position of the fittings. Placement of pipe which cause excessive bending and stress on pipe and fittings will not be permitted. No excess piping or fittings shall be permitted in the installation of the system, as this may increase pressure loss or potential for blockage.

E. Before installing the pipe, all rocks over 1 inch diameter, rubbish and debris shall be removed from the trenches. If the adjacent soil is rocky, the trenches shall be bedded and filled with clean dirt or sand to provide a minimum of 6” clearance between the pipe and the native soil. Material used for pipe bedding and trench filling shall be approved by the Owner’s Representative. The full length of each section of the pipe shall rest solidly upon the pipe bed, with recesses excavated to accommodate bells, joints and couplings.

F. Pipe shall not be laid in water or when trench or weather conditions are unsuitable for the

work. Any water which may be encountered or may accumulate in the trenches or excavation shall be pumped out or otherwise removed as necessary to keep the bottom of the trench or excavation free and clear of water during the progress of the work. Pipe shall not be laid when the temperature is 32 degrees F or below.

G. PVC pipe will expand or contract at the rate of +/- 3/8” per 100’ per 10 degrees F change

of temperature. Therefore, the pipe shall be installed in a manner to provide for expansion and contraction as recommended by the manufacturer.

H. The minimum horizontal and vertical clearance between lines in the same trench shall be 4".

I. After all piping, risers, valves, thrust blocks, etc., have been installed and partially

backfilled as specified in other parts of these Specifications, the control valve shall be opened and a full head of water used to flush out the system. Caution shall be observed to provide for release of any entrapped air in the system. After the system is thoroughly flushed, risers shall be capped and the system pressure tested in accordance with the testing section of these Specifications. At the conclusion of the pressure test, the heads shall be installed and the backfill operation completed.

3.7 SOLVENT WELDING PROCEDURE

A. All solvent weld joints shall be made in accordance with the solvent manufacturer’s

recommendations and ASTM D 2855.

B. PVC plastic pipe shall be squarely cut utilizing a miter box mounted hacksaw or PVC specialty saw with a blade of 18 or 24 teeth per inch.

C. Interior and exterior burrs shall be removed and the exterior shall be beveled to produce a

10-15 degree bevel.

D. Thoroughly clean the mating pipe end and the fitting socket with a clean, dry cloth.

Page 92: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 8 IRRIGATION SYSTEM

E. Using a properly sized applicator (approximately ½ the diameter of the pipe), apply a light

coating of primer to the inside of the fitting socket, then apply a thin coat to the outside of the pipe end. Apply a second, light coat of primer to the inside of the fitting socket taking care to avoid puddling of primer in fitting.

F. Apply a uniform coat of cement to the outside of the pipe end with a properly sized

applicator (approximately ½ the diameter of the pipe).

G. In like manner, apply a thin coating of cement to the inside of the fitting socket. H. Re-apply a light coat of cement to the outside of the pipe end and quickly insert it into the

fitting to the full depth of the fitting socket, while rotating the pipe or fitting approximately ¼ turn to ensure even distribution of cement.

I. Hold in position for approximately 30 seconds.

J. Wipe off any excess solvent cement that forms as a bead around the outer shoulder. K. Contractor shall not use an excessive amount of solvent cement that could cause burrs or

obstructions to form on the inside of the pipe joint.

L. Solvent weld joints shall be allowed to cure for minimum 24 hours before pressure is applied to the system.

3.8 BACKFILLING

A. Upon completion of a particular section of the irrigation system, and after sufficient time has elapsed for the curing of solvent weld joints, partial backfilling shall begin, leaving all joints, risers and connections exposed for visual inspection during the hydrostatic testing. Only upon successful completion of the hydrostatic test shall the backfill operation be completed for any one particular section.

B. All backfill material shall be subject to approval by the Owner’s Representative. Backfill

material shall be free from rock, large stones, brush, sod, frozen material or other unsuitable substances that may damage pipe or compromise compaction during the backfilling operations.

C. In the event that the material from the excavation or trenching is found to be unsuitable for

use in backfill by the Owner’s Representative, it shall be removed from the site and properly disposed of by the Contractor at his own expense. The Contractor shall then, at no cost to the Owner, arrange for, purchase, and furnish suitable backfill material consisting of earth, loam, sandy clay, sand or other approved materials free of large clods of earth or sharp stones and capable of attaining the same relative density of the surrounding ground.

D. In rocky areas, the trench depth shall be 6” below the normal trench depth to allow for 6” of suitable backfill as padding for the pipe. In like manner, there shall be minimum 6” of suitable backfill on all sides of the pipe as padding against rock in the wall of the trench.

E. All mainline and lateral piping shall have detectable line marking tape installed in the

Page 93: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 9 IRRIGATION SYSTEM

trench six (6”) inches above the pipe. After pipe is placed in trench and the first 6" layer of backfill is placed and compacted, the detectable marking tape shall be placed continuously in all trenches prior to completion of backfill operations.

F. Backfill shall be placed in horizontal layers not exceeding 6” in depth and shall be

thoroughly tamped, or water compacted to near original density or so that no settling will result. Backfill shall be placed to the original ground level. If settlement of trenches occurs within one (1) year from date of completion, it shall be the Contractor's responsibility to refill trenches and re-sod or re-install landscape mulch in the repaired areas.

3.9 SADDLE TAPS

A. No saddle taps shall be permitted unless approved by the Owner’s Representative.

3.10 THRUST BLOCKS

A. Concrete thrust blocks shall be provided where necessary to resist system pressure, including at all direction changes, size changes, valves and terminations or at any other points of the system that will result in an unbalanced thrust line for equipment 2-1/2” and larger and as indicated on the Drawings. Thrust blocks shall not obstruct the outlets of fittings which are intended for future connections. Thrust blocks shall be poured against undisturbed earth and in accordance with the Drawings.

3.11 SLEEVED CROSSING

A. Unless otherwise noted on the Drawings, all piping installed under sidewalks, roadways, parking lots, etc., shall be sleeved in a Class 200 PVC pipe two (2) sizes larger than the pipe to be sleeved. Wire shall be placed in a separate sleeve from that of the pipe crossing and shall be Class 200 PVC minimum 2” size, or larger as required to accommodate the quantity of wire to be sleeved. Ends of sleeves shall be sealed with duct tape after installation of wire or piping.

3.12 HEAD INSTALLATION

A. Heads shall be of the type and make specified and shall be installed as shown on the Drawings. Heads shall be installed with a 4" space between the edge of the head and curbs, walks, walls, driveways, building walls, etc. Heads shall be installed in the vertical position and backfilled and compacted to 80% modified Proctor.

B. Head spacing shall not exceed the spacing shown on the Drawings and shall be in the

location and configuration as shown on the Drawings. Contractor shall verify turf area dimension while staking head location. Heads shall be spaced to achieve uniform coverage.

C. After all piping and risers are in place and connected and before installation of the heads,

all control valves for a given section shall be fully opened and a full head of water shall be used to flush out the system. If water pressure without the heads installed is not sufficient to provide adequate water flow from end risers, the Contractor shall cap off enough heads closest to the water source to provide adequate flushing of the end riser assemblies.

Page 94: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 10 IRRIGATION SYSTEM

3.13 AUTOMATIC CONTROL VALVE INSTALLATION

A. Automatic control valves shall be of the type and size indicated on the Drawings. Installation shall be according to these Specifications, the Drawings and the manufacturer's recommendations.

B. The valve boxes shall be of the size and type as shown on the Drawings.

C. Valve wire splices shall be waterproofed using 3M DBR/Y direct bury splice kit or

approved equal. The Contractor shall provide a 36" wire expansion coil to facilitate raising splices to ground level without cutting wires.

3.14 24 VOLT CONTROL VALVE WIRING

A. Wire installation procedures shall conform to local codes.

B. The Contractor shall install the 24 volt control valve wiring in the same trench as the

irrigation mainline. Only when it is not possible for the wires to be installed in the mainline trench, they shall be installed in the lateral pipe trench. All wires shall be laid below the pipe. In no case shall the wire be laid on top of the pipe. The wires shall be laid loose in the trench and taped together at 10'-0" intervals. When trenches used for piping are not appropriate for routing wire, Contractor shall install wire in a separate trench at 18" bury depth.

C. Wire splices, other than at valve box locations, shall be kept to a minimum and if needed

shall be made only at common splice points and placed in a wire splice box. Wire splices shall be waterproofed using 3M DBR/Y direct bury splice kit or approved equal.

D. At control wire splices, the Contractor shall provide a 36" wire expansion coil to facilitate

raising splices to ground level without cutting wires.

E. Continual wire shall be one color and in no case shall wires of different colors be spliced together.

F. All 24 volt wiring shall be installed in PVC conduit when inside a building. All 24 volt

wiring installed on exterior building walls shall be installed in metal conduit. 3.15 TESTING

A. Upon completion of the irrigation system's mainline, the entire mainline shall be tested

with the Owner’s Representative present, for a one hour period at 100 psi, unless otherwise noted. Prior to testing, the mainline shall be partially backfilled, leaving all joints and connections exposed for visual inspection. All dirt shall be flushed from the system and the line filled with water to remove air. The mainline shall be brought to static pressure. A pressure gauge and temporary valve shall be installed at the end of the mainline to permit air pressure to be applied to the main. A pressure of 100 psi shall be retained for a one hour period. Any leaks occurring during the one hour pressure test shall be repaired and the system retested until the system passes the test.

Page 95: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 11 IRRIGATION SYSTEM

B. Upon completion of the lateral piping sections, each lateral system shall be pressure tested, with the Owner’s Representative present for one hour at 100 psi. On systems using flex nipples or swing joints, the lateral system shall be tested prior to installation of the flex nipples or swing joints. Prior to testing, the lateral lines shall be partially backfilled leaving all joints and connections exposed for visual inspection. All air and dirt shall be flushed from the system and all open fittings shall be capped. The testing procedure shall be the same as used for the main line. Any leaks occurring during the hydrostatic test shall be repaired and the system retested until the system passes the test. If after one hour 100 psi pressure has been retained, the heads shall be installed, and the backfill operation completed.

C. The Contractor shall be responsible for payment of construction observations for retesting

of any lines or system components that fail initial pressure or performance test. Costs shall include the time of the observer at the observer’s standard rate, travel time and travel expenses.

3.16 ADJUSTING OF SYSTEM

A. After completion of testing and installation, the Contractor shall adjust all valves for the proper operating pressure and adjust all heads for uniform coverage and even flow. Contractor shall wire the controller to have station numbers correspond with valve numbers indicated on the Drawings or as directed by the Owner’s Representative. The valve number shall be indicated on the controller panel for each station. Contractor shall program the controller to provide optimum system performance.

3.17 CLEAN UP

A. The Contractor shall continuously keep a neat and orderly area in which he is installing the system. Disposal of rubbish and waste material resulting from the installation shall be continual. Upon completion of the system, the Contractor shall remove from the Owner's property at his own expense, all temporary structures, rubbish, waste material, tools and equipment resulting from or used in the installation of the system.

3.18 PROTECTION OF EXISTING UTILITIES

A. The Contractor shall be responsible for locating all existing cables, conduits, piping, and

any other utilities or structures that may be encountered either above or below ground. All necessary precautions shall be taken by the Contractor to prevent any damage to the existing utilities and improvements. In the event that such damage should occur from his operations, the Contractor shall repair or replace damaged utilities to their original condition at no expense to the Owner.

3.19 ROCK

A. If the Contractor encounters rock or other unfavorable trenching conditions, no additional compensation will be paid. When material from the excavation or trenching is unsuitable for use as backfill, additional backfill material suitable for this purpose shall be brought in at the expense of the Contractor. It shall be the Contractor's responsibility to remove and dispose of all unsuitable materials removed from the trench that cannot be used in the backfill operation.

Page 96: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 12 IRRIGATION SYSTEM

3.20 FINAL ACCEPTANCE

A. When the Contractor is satisfied that the system is operating properly, that it is balanced

and adjusted and that all work and clean-up is completed, he shall issue a notice of completion to the Owner’s Representative requesting a final observation. The Owner’s Representative will respond to the notice of completion and shall appear with the Owner for an observation of the project. At that time the Contractor shall demonstrate the operation of each system in its entirety. In reviewing the work, no allowance for deviation from the original Drawings and Specifications will be made unless prior approval has been obtained.

B. Any inconsistency to the Specifications or the Drawings will be noted by the Owner’s Representative and a written copy of required corrections shall be given to the Contractor. The Contractor shall complete all corrections in a timely manner and then shall issue a request to the Owner’s Representative for an inspection of corrected work. Final acceptance will not occur until correction of all items work is complete.

3.21 OPERATIONAL INSTRUCTION

A. After the system has been tested and accepted, the Contractor shall instruct the Owner’s Representative on the operation and maintenance of the system.

B. The Contractor shall provide the Owner with two (2) keys for each of the following:

1. manual gate valves

2. valve boxes 3. any locking assembly in need of key access

C. The Contractor shall provide the Owner with two copies of a Maintenance Manual bound

in a three ring binder. The maintenance manual shall include copies of the approved submittals, operation manuals and manufacturer’s warranties on all irrigation products.

3.22 SYSTEM MAINTENANCE AND GUARANTEE

A. Maintenance of the irrigation system shall begin immediately following the installation of

the system and shall continue until the entire project is accepted. Maintenance shall include repair of defects or damages, adjustments and fine tuning of the system, and repairs of damages resulting from vandalism, erosion, weather, and the like.

B. For a period of one (1) year from final acceptance of the entire project, the Contractor

shall promptly furnish and install, without cost to Owner, any and all parts or materials which prove defective in material or workmanship. Damage to the landscape or other property due to irrigation system line breaks shall be repaired and brought to original condition by the Contractor at no expense to the Owner.

C. For a period of one (1) year from final acceptance of the system, the Contractor shall

repair any settlement of trenches by one of the following methods as directed by the Owner’s Representative.

1. Sod areas: Bring to grade by top-dressing (raking topsoil into the grass).

Page 97: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 328400 - 13 IRRIGATION SYSTEM

2. Sod areas or tree/shrub planting areas: Remove existing sod or mulch. Fill depression with planting soil mixture, and replace with new sod or mulch to match existing.

Repair by any of the above methods shall result in a smooth, level area.

3.23 OBSERVATIONS

A. The following observations shall be the minimum required observations during the course of construction. Additional observations shall be made at any time at the discretion of the Owner’s Representative. It shall be the responsibility of the Contractor to notify the Owner’s Representative, in writing, 48 hours in advance of each required observation. The sequence of required observations shall not be changed from the sequence listed below. The Contractor shall not proceed with work of the next sequence without written approval of the work of the previous sequence. The Contractor shall attach a copy of the written observation approvals to all applications for payment.

1. Observe staked locations of mainline, valves, laterals and heads. 2. Observe installation and pressure test of mainline. 3. Observe 24 volt control wire installation and ensure that existing controller operates

all valve zones properly. 4. Observe installation and pressure test of automatic valves and lateral lines prior to installation of flex nipples and heads. 5. Observe head placement, coverage and operating pressure prior to planting. 6. Observe at final project review. 7. Observe 11 months after final project acceptance.

END OF SECTION

Page 98: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329223-1 SODDING

SECTION 329223 - SODDING PART 1 - GENERAL 1.1 DESCRIPTION OF WORK

A. Work under this section consists of preparing all areas indicated on the Drawings for grass sodding according to the specifications and furnishing and installing all sod, fertilizer and soil amendments as specified herein.

1.2 REFERENCE STANDARDS

A. ASPA (American Sod Producers Association) - Guideline Specifications to Sodding. 1.3 SUBMITTALS

A. Furnish samples of the following prior to construction:

1. Organic amendments

B. Furnish soil test results for any fill that has been imported into landscape areas prior to start of landscape construction.

C. Furnish supplier literature and chemical analysis (or botanical analysis for sod) of the

following prior to construction:

1. Fertilizer 2. Organic amendments 3. Iron 4. Boron 5. Additional fertilizers and amendments if specified on the recommendations of the

Soil Test Results (see 329223.3.1.F). 6. Sod

D. Furnish the following the same day materials are delivered to the project site:

1. Delivery tickets indicating quantity of material delivered for:

a. Fertilizer b. Organic amendments c. Iron d. Boron e. Additional fertilizers and amendments if specified on the

recommendations of the Soil Test Results (see 329223.3.1.C). PART 2 - PRODUCTS

2.1 SOD

A. Sod shall be as specified on the Drawings. A sample of sod and a written submittal of the seed mix shall be submitted a minimum of fifteen (15) days prior to laying of sod. Sod

Page 99: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329223-2 SODDING

shall be vigorous, well rooted healthy turf free from disease, insect pests, weeds, other grasses, stones and other harmful or deleterious matter.

B. Sod shall be cut by an approved mechanical sod cutter to a thickness of not less than 1" or

more than 2". Sod pieces shall be cut a maximum of 18" wide. Handling of sod shall be done in a manner that will prevent tearing, breaking, drying or any other damage. Sod shall be installed in place on the site not more than 24 hours after cutting.

C. Sod shall have no more than 2" of loose thatch. The sod shall be dense enough so that an

entire strip can be lifted by the top 10% without breaking.

2.2 FERTILIZER

A. Granular form nitrogen

B. Granular form phosphate

C. Additional fertilizer if specified on the recommendations of the Soil Test Results (see 329223.3.1.F).

2.3 ORGANIC AMENDMENTS

Organic amendment shall consist of:

A. 70% by volume, organic compost. Compost shall be screened to 2" minus, pH not to exceed 7.3. Electrical conductivity (EC) of compost shall not exceed 3.5 MS/cm. Percentage of organic matter shall be not less than 80%, tested by simple combustion. Total nitrogen (TKN+N03-N) shall not be less than 1%, by weight. Carbon to nitrogen ratio of compost shall not exceed 50:1.

B. 10% by volume, “Ecolite” (clinoptilolite zeolite). Ecolite shall be screened to pass a #40

mesh screen.

C. 20% by volume, “Moisturelite”, screened to pass a #40 mesh.

D. Components to be homogeneously mixed, in ten cubic yard batches to provide a uniform product, free from weed seeds, sticks, rocks, or other deleterious material.

F. Each Delivery shall have a load ticket. The load ticket shall list:

Type of Mixture Source of Mixture. Approximate volume of load. Date of delivery of loading. Name of individual representing the source.

Tickets shall be collected and provided to the Owner’s Representative.

Page 100: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329223-3 SODDING

2.4 ADDITIONAL AMENDMENTS

A. Iron

B. Boron C. Additional amendments if specified on the recommendations of the Soil Test Results (see

329223.3.1.F).

PART 3 - EXECUTION 3.1 SOD BED PREPARATION

A. Prior to start of soil preparation soil shall be cleared of rocks and lumps of 1” diameter and greater, vegetation and debris to a minimum depth of 12”. Finish grade shall be established and approved as meeting the requirements of the grading plan.

B. Rip all areas to be sodded to a depth of 12.” Apply a uniform 2" layer of organic

amendment, 1.0 pounds phosphate per each 1000 square feet, and 0.5 pounds iron per each 1000 square feet to the entire area to be sodded. After application of organic amendment, phosphate and iron, all areas to be sodded shall be thoroughly rototilled at cross directions to a minimum depth of 6 inches.

C. After rototilling is complete at cross directions, apply nitrogen to the entire area to be

sodded at a rate of 1.0 pounds per each1000 square feet. D. After application of nitrogen, spray the entire area to be sodded with boron at a rate of

0.02 pounds per 1000 square feet. Boron shall be dissolved in water prior to application. (Note: Approved equal to boron is 20 mule team borax. Borax shall be mixed into water at the rate of 1 tbsp borax per 5 gallons of water. Borax/water mixture shall be applied to all areas to be sodded at a rate of 2 gallons of solution per 1000 square feet.)

E. After application of boron/water mixture, drag areas to be sodded to an even grade and

then roll for firmness.

F. If the Contractor has imported fill (or has cut below existing finish grade) in an area to be sodded, the Contractor shall coordinate with the Owner’s Representative to have samples of the fill (or the soil at the cut grade) submitted to an independent soil testing laboratory for nutritional analysis. The cost of the soil testing shall be paid by the Contractor. If recommended by the soil test laboratory, the Contractor shall revise the specified fertilizer, organic amendments and additional amendments to be in accordance with the recommendations specified on the soil test report. If recommended by the soil test laboratory, the Contractor shall provide and incorporate additional fertilizers and amendments into the fill and/or cut to be in accordance with the recommendations specified on the soil test report.

3.2 SOD INSTALLATION

A. Before laying sod, the finish grade shall be brought to a firm, even surface, free from

stones and lumps 1” diameter and greater, and shaped to provide drainage in accordance

Page 101: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329223-4 SODDING

with the Drawings. The finish grade shall be inspected and approved by the Owner’s Representative prior to laying any sod.

B. Lay sod over moistened soil lightly raking the soil ahead of each sod strip. Sod shall be

laid perpendicular to the direction of slope and shall have staggered joints. Pieces shall be fitted together tightly so that no joint is visible, and sod tamped firmly and evenly by hand. Stake as required on slopes.

C. After sodding is completed, all sod areas shall be rolled. Rolling shall be done in two

directions perpendicular to each other. After rolling, repair and reroll any areas where depressions or other irregularities occur.

D. Water all sodded areas immediately after final rolling with fine spray to a depth of 4".

Irrigate by means of the automatic underground irrigation system all sodded areas as often as necessary to promote healthy grass growth. Mowing during the maintenance period shall be scheduled so that the grass is maintained at a height no shorter than two (2) inches and no greater than three (3) inches.

E. Contractor shall not lay sod during freezing temperatures or over frozen soil. If sod cannot

be installed due to freezing temperatures and/or frozen soil, Contractor shall postpone installation of sod until the temperature and soil conditions meet the requirements of these specifications.

3.3 MAINTENANCE AND PROTECTION

A. Maintenance and protection shall continue until the entire project is accepted. Acceptance shall occur after all sod is well rooted.

B. Maintenance shall include watering, weeding, cultivating, fertilizing, removal of dead

material and debris, and such other operations as may be necessary for the health of the sod and the general appearance of the landscaped areas. Protection shall include care or replacement of the sod from damages resulting from trespass, erosion (including watering), weather, vandalism, disease and the like.

3.4 WARRANTY

A. Sod shall be guaranteed to be in a live, healthy, and normal growing condition through twelve months from the date of final acceptance by the Owner’s Representative. The Contractor shall not be held responsible for replacement of sod lost through vandalism and/or other destruction after contract final acceptance.

B. The Contractor shall monitor the condition of the sod at regular intervals during the

warranty period to verify that the sod is receiving proper maintenance. Frequency of monitoring visits shall be as required to ensure proper maintenance. If at any time during the warranty period the Contractor should encounter at the site conditions unfavorable to the health of the sod, he shall notify the Owner and Owner’s Representative of such in writing. Inadequate or improper maintenance by the Owner during the warranty period will not relieve the Contractor of his warranty obligation, unless such improper maintenance continues beyond the date the Contractor has notified the Owner and Owner’s Representative.

Page 102: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329223-5 SODDING

C. Sod that is dead or in an unhealthy, impaired growth condition during the warranty period

shall be removed and replaced by the Contractor. Replacement material shall match quality and species of the sod originally specified and shall be approved by the Owner’s Representative prior to installation. Sod replaced during the first six months of the warranty period shall be under warranty until the end of the warranty period. Sod replaced after the first six months of the warranty period shall be under warranty for six months after the replanting date.

3.5 OBSERVATIONS

A. The following observations shall be the minimum required inspections during the course of construction. Additional observations shall be made at any time at the discretion of the Owner’s Representative.

B. It shall be the responsibility of the Contractor to notify the Owner’s Representative, in

writing, 48 hours in advance of each required observation.

C. The sequence of required observations shall not be changed from the sequence listed below. The Contractor shall not proceed with work of the next sequence without written approval of the work of the previous sequence.

1. Automatic irrigation system shall be installed, tested, and approved. 2. Each phase of soil preparation shall be observed in process. 3. Finish grade shall be observed. 4. Sod shall be observed prior to laying. 5. Sod shall be observed after installation. 6. Sod shall be observed at final project review. 7. Sod shall be observed 11 months after final project acceptance.

END OF SECTION

Page 103: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-1 PLANTS

SECTION 329300 - PLANTS PART 1 - GENERAL 1.1 SUMMARY

A. Work under this section consists of the planting of trees and shrubs, including the

furnishing of all labor, equipment, and materials and performing all work in connection therewith in accordance with the Drawings and Specifications.

1.2 PLANT NAMES

A. The botanic and common names used for the plants called for on the Drawings are generally in conformity with the approved names given in Standardized Plant Names, 1980 Edition, published by The American Joint Committee on Horticultural Nomenclature. The names of varieties not included therein are generally in conformity with the names accepted in the nursery trade.

1.3 PLANT MATERIAL SUBSTITUTIONS

A. Plant material substitutions shall not be made without the written permission of the Owner’s Representative. The use of materials differing in kind, quality or size from that specified shall be allowed only after the Owner’s Representative is convinced that all means of obtaining the specified materials have been exhausted. At the time bids are submitted, the Contractor is assumed to have located the materials necessary to complete the job as specified. All requests for substitutions shall be submitted no later than seven (7) working days prior to the opening of bids.

1.4 SUBMITTALS

A. Furnish samples of the following prior to construction:

1. Backfill amendment 2. Mulch 3. Weed barrier fabric

B. Furnish supplier literature and chemical analysis of the following prior to construction:

1. Backfill amendment

C. Furnish the following the same day materials are delivered to the project site:

1. Delivery tickets indicating quantity of material delivered for:

a. Backfill amendment

Page 104: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-2 PLANTS

PART 2 – MATERIALS 2.1 PLANT MATERIALS

A. A complete plant list, including quantities, sizes and other requirements is shown on the Drawings. In the event that discrepancies occur between quantities of plants indicated in the plant list and on the planting plan, the plant quantities indicated on the planting plan shall govern.

2.2 PLANT MATERIAL QUALITY

A. Plant material quality, size and condition shall be in accordance with American Standard for Nursery Stock, 1986, as published by the Committee on Horticultural Standards of the American Association of Nurserymen, Inc., the Drawings, and the following requirements:

1. All plants shall be typical of their species or variety. All plants shall have normal,

well developed branches and vigorous root systems. They shall be sound, healthy, vigorous, and free from defects, disfiguring knots, abrasions of the bark, sunscale injuries, plant diseases, insect eggs, borers, and all other forms of infections.

2. Unless otherwise stated on the Drawings or approved by the Owner’s

Representative, all plants shall be nursery grown and shall be tagged with nursery labels indicating species and variety.

3. Container grown plant material shall have been grown in its delivery container for

not less than six (6) months, but for not more than two (2) years. Any rootbound material will not be accepted.

4. Multi-stem: All countable stems, in aggregate, shall average the size specified.

To be considered a stem, the division of the trunk shall be no more than six inches from ground level.

5. Balled and burlapped plant material shall have a solid ball of earth of minimum

specified size held in place securely by burlap and stout twine or rope. Light poultry binding is acceptable. Stout wire or wire baskets are acceptable only as a temporary means for securing burlap until tree is in place. Broken or loose balls will be rejected.

6. Unless specifically noted on the Drawings, all trees shall have a single trunk that

is straight and free of “dog legs”, “crooks”, “Y-crotches”, or other disfiguring shapes. The central leader of all trees shall not have been pruned. Trees with double leaders are not acceptable.

7. All plant material shall have a uniform shape around its complete circumference.

Plant material with irregular branching patterns or with branching patterns more highly developed on one side than on other sides will not be accepted.

8. All plant material shall be reviewed by the Owner’s Representative at the

Contractor’s yard prior to delivery to the job site. All material shall then be reviewed at the job site prior to planting and after planting.

Page 105: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-3 PLANTS

9. At the option of the Contractor, the Owner’s Representative will review plant material at a wholesale nursery of the Contractor’s choice prior to delivery of materials to the Contractor’s yard. However, at no expense to the Owner, the Contractor shall be responsible for all travel expenses incurred by the Owner’s Representative for any travel outside of the Las Cruces metropolitan area.

10. The Contractor shall mark each plant intended for use on the project with an identifying tag prior to the Owner’s Representative’s review of the plants.

11. The Owner’s Representative shall be the judge of the quality and acceptability of all plant material. All rejected material shall be immediately removed from the site and replaced with acceptable material at no additional cost to the Owner.

2.3 PLANTING SOIL MIXTURE

A. Planting Soil Mixture shall be a mixture of one part backfill amendment to two parts existing soil.

The backfill amendment shall consist of:

1. 70% by volume, organic compost. Compost to be screened to 1/2" minus, pH not

to exceed 7.3. Electrical conductivity (EC) of compost not to exceed 3.5 MS/cm. Percentage of organic matter shall be not less than 80%, tested by simple combustion. Total nitrogen (TKN+NO3-N) shall be not less than 1%, by weight. Carbon to nitrogen ratio of compost shall not exceed 50:1.

2. 30% by volume, “Moisture-Lite” or approved (clean, screened, white vitric tuff,

graded to 3/16" x 5/16").

3. Components to be homogeneously mixed, in ten cubic yard batches to provide a uniform product, free from weed seeds, sticks, rocks, or other deleterious material.

4. Each delivery shall have a load ticket. The load ticket shall list:

Type of Mixture Source of Mixture. Approximate volume of load. Date of delivery or loading. Name of individual representing the source. Ticket shall be collected and provided to the Owner’s Representative.

2.4 ADDITIONAL SOIL AMENDMENT

A. Iron

2.5 MULCH

A. Mulch shall be as specified on the Drawings.

Page 106: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-4 PLANTS

PART 3 - EXECUTION 3.1 PLANTING OPERATIONS

A. Prior to planting operations, landscape areas shall be cleared of rocks and lumps greater

than 1" diameter, vegetation, and debris to a minimum depth of 12” and finish grading shall be complete and accepted by the Owner’s Representative. Planting operations shall be performed only during favorable weather conditions in accordance with accepted practice.

B. In any one day, only those plant materials intended to be planted that day shall be

delivered to the project site. Unless otherwise approved by Owner’s Representative, all plant materials shall be located where shown on the Drawings except when adjustments due to field conditions are required. The location of all trees and shrubs shall be staked by the Contractor and reviewed by the Owner’s Representative prior to installation. Tree locations shall be represented by using 1" x 2" x 12" wood stakes or colored flags. The name of the tree shall be indicated on the stake or flag so it is readily identified. Shrub locations shall be determined by colored flags or by placement of containerized plant material.

3.2 PLANTING

A. Planting and backfilling shall be performed in accordance with accepted nursery practice, the Drawings, and the following requirements:

1. The Contractor shall take care when backfilling planters to provide adequate

compaction of the fill material in order to prevent settling.

2. Prepare all planting pits and install plants as shown on Drawings. Plants shall be set plumb and straight.

3. Remove wire basket, wood box, plastic, twine, and/or rope prior to backfill.

Remove burlap except from bottom of root ball prior to backfill.

4. Backfill for planting pits shall consist of the specified planting soil mixture and 0.05 pounds iron per cubic foot of backfill. The plant shall be positioned in the hole, and backfilled. The backfilling shall be completed, and material tamped. When pit is nearly filled, water thoroughly and allow water to soak away. If settling of backfill occurs after watering, add more backfill to bring to finish grade.

5. After completion of planting, trees shall be pruned at the direction of the Owner’s

Representative. 3.3 MULCH

A. Mulch shall be completed as indicated on the Drawings.

3.4 MAINTENANCE AND PROTECTION

Page 107: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-5 PLANTS

A. Maintenance and protection of trees and shrubs shall begin immediately following the installation of each plant and shall continue until the entire project is accepted. Maintenance shall include watering, weeding, cultivating, removal and replacement of dead plant material, removal of debris, resetting of trees to upright positions, restoration of earth basins, and such other operations as may be necessary for the health of the planted stock and the general appearance of the landscaped areas. Maintenance and protection shall include repair of damage to plants and replacement of severely damaged plants resulting from trespass, erosion (including erosion from application of irrigation water), weather, vandalism, disease or other condition or action.

3.5 WARRANTY

A. All plants shall be guaranteed to be in a live, healthy, and normal growing condition from the date of final project acceptance through one twelve month period. The Contractor shall not be held responsible for replacement of plants and materials lost through vandalism and/or other destruction after final project acceptance.

B. The Contractor shall monitor the condition of the landscape at regular intervals during the

warranty period to verify that the landscape is receiving proper maintenance. Frequency of monitoring visits shall be as required to ensure proper maintenance. If at any time during the warranty period the Contractor should encounter at the site conditions unfavorable to the health of the planted stock, he shall notify the Owner and Owner’s Representative of such in writing. Inadequate or improper maintenance by the Owner during the warranty period will not relieve the Contractor of his warranty obligation, unless such improper maintenance continues beyond the date the Contractor has notified the Owner and Owner’s Representative.

C. Plants that are dead or in an unhealthy, impaired growth condition during the warranty

period shall be removed and replaced by the Contractor as directed by the Owner’s Representative at no additional cost to the Owner. Replacement material shall be of equal quality, size, and species as that which is being replaced and shall be approved by the Owner’s Representative prior to planting. Plants replaced during the first six months of the warranty period shall be under warranty until the end of the warranty period. Plants replaced after the first six months of the warranty period shall be under warranty for six months after the replanting date.

3.6 REVIEWS

A. The following observations shall be the minimum required observations during the course of construction. Additional observations shall be made at any time at the discretion of the Owner’s Representative. It shall be the responsibility of the Contractor to notify the Owner’s Representative, in writing, 48 hours in advance of each required observation. The sequence of required observations shall not be changed from the sequence listed below. The Contractor shall not proceed with work of the next sequence without written approval of the work of the previous sequence.

1. Automatic irrigation system shall be installed, tested, and approved. 2. Review plant material at the Contractor’s yard or wholesale nursery prior to

delivery to the job site. 3. Review staked locations of plant material prior to planting.

Page 108: NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE...NMSU HJLC GREEN 015639 - 1 TEMPORARY TREE PROTECTION SECTION 015639 - TEMPORARY TREE PROTECTION . PART 1 - GENERAL . 1.1 SUMMARY . A. Section

NMSU HJLC GREEN 329300-6 PLANTS

4. Review of planting holes and planting soil mixture preparation prior to planting operations.

5. Review plant material at the job site prior to and during planting. 6. Review of planting operations. 7. Review at final project completion. 8. Review 11 months after final project acceptance.

END OF SECTION