    Patricia Egen Consulting 1

    Microsoft Project

    Tips & Techniques Lab

    August 2004 New York Session 1482Patricia Egen

    www.egenconsulting.com

  • 8/3/2019 Ms Project Using

    2/20

    Patricia Egen Consulting 2

    Summary Slide

    Changing Row Height

    Clear Baseline

    Roll Up Tasks for Project

    Use Month as a Duration Unit

    Fill Handles

  • 8/3/2019 Ms Project Using

    3/20

    Patricia Egen Consulting 3

    Summary Slide (cont.)

    Layout tips

    Layout Tips 2

    Gantt Chart Tips

    Printing Gantt Charts

    Working with Tasks

    Working with Dates Resource Leveling

    Reports

  • 8/3/2019 Ms Project Using

    4/20

    Patricia Egen Consulting 4

    Summary Slide (cont.)

    Why does Project ignore priorities?

    Why dont subtasks get included in

    summary tasks' timelines?

    Why does Project leave gaps?

  • 8/3/2019 Ms Project Using

    5/20

    Patricia Egen Consulting 5

    Changing Row Height

    Single row:

    Drag the row line between tasks to the height

    you want.

    All Rows

    Click the upper left hand corner to highlight all

    rows then adjust row size

  • 8/3/2019 Ms Project Using

    6/20

    Patricia Egen Consulting 6

    Clear Baseline

    Point to Tracking on the Tools menu, and thenclick Clear Baseline.

    To clear baseline information for specific tasks only,select those tasks.

    To clear baseline information for the entire project, startwith next step.

    Click Clear baseline plan or Clear interim plan. To

    clear an interim plan, you need to select it in thelist box.

    Click Entire project or Selected tasks.

  • 8/3/2019 Ms Project Using

    7/20

    Patricia Egen Consulting7

    Roll Up Tasks for Project

    To easily display multiple Gantt bars on a

    single task line for the whole project.

    On the Format menu, click Layout.

    Click Always roll up Gantt bars.

  • 8/3/2019 Ms Project Using

    8/20

    Patricia Egen Consulting8

    Use Month as a Duration Unit

    Typing 3mos in the duration field is recognized as

    three months.

    By default, a month has 20 days, but you can alsospecify how many days constitute a month.

    On the Tools menu, click Options, and then click

    the Calendar tab.

    Specify the number of days in the Days per month

    box.

  • 8/3/2019 Ms Project Using

    9/20

    Patricia Egen Consulting9

    Fill Handles

    Use fill handles to copy task or resourceinformation up or down in the sheet portion of anyview, such as the left-hand portion of the GanttChart.

    Select the cell that contains the information you want tocopy.

    Click and drag the square in the lower right hand corner

    to highlight cells up or down. Release the mouse button to fill highlighted cells with

    the contents of the original cell.

  • 8/3/2019 Ms Project Using

    10/20

    Patricia Egen Consulting10

    Layout tips

    In the Gantt Chart, double click on the right edge of acolumn header to "best fit" the column.

    To quickly change the name of a column, doubleclick in the column header and enter a new name for

    the field in the Title field. Example, abbreviate the Duration field name to Dur

    To quickly change the field in a column, double clickin the column header and select the new field from

    the Field Name list. While in the Field Name list, press the first letter of the

    desired field to go to that field.

  • 8/3/2019 Ms Project Using

    11/20

    Patricia Egen Consulting11

    Layout Tips 2

    To quickly modify or delete a dependency, double click on

    the dependency line between the two tasks to display the

    Task Dependency form

    In any drop down list such as the list of Resource Names

    or the list of Filters you can press the first letter of the item

    you are looking for to quickly go that item.

    Use the Insert key on your keyboard to quickly insert rows

    and columns.

    In the Gantt chart, click on a row and press the Insert key to insert

    a blank row above the selected row. Click on a column header to highlight a column and press Insert to

    insert a column to the left of the selected column.

    Use the Delete key to reverse this process

  • 8/3/2019 Ms Project Using

    12/20

  • 8/3/2019 Ms Project Using

    13/20

    Patricia Egen Consulting13

    Printing Gantt Charts

    When printing any timescaled charts such as Gantt

    Charts you can adjust the width of the timescale to

    fit the page without changing the timescale units.

    Double click on the Timescale and increase the number

    in the % field to make the timescale take up more of the

    page or decrease the number in the % field to make the

    timescale narrower.

    The latter step is useful when a chart is just a little toowide to fit on a page.

  • 8/3/2019 Ms Project Using

    14/20

    Patricia Egen Consulting14

    Working with Tasks

    To select two or more non-adjacent tasks, click on a

    task (in the table area), hold down the Ctrl Key and

    click on another task in the chart.

    Continue holding the Ctrl key to select other tasks. This

    is especially useful for linking or unlinking tasks that are

    not on consecutive rows.

    To change information for a number of tasks at

    once, highlight the desired tasks and select the Task

    Information button. Enter the common information in one of the fields

    displayed in the "Multiple Task Information" dialog box.

  • 8/3/2019 Ms Project Using

    15/20

    Patricia Egen Consulting15

    Working with Dates To remove a date constraint from a task, select the task (or

    multiple tasks) and select the Task Information button.

    Click in the Advanced tab, change the Type field to As Soon

    As Possible and click OK. This removes any date constraint

    in the task and allows it to be scheduled based on the

    dependencies rather than a date. If a task does not move (reschedule) based on a dependency, it

    may contain a "fixed" date of some kind.

    A fixed date could be an Actual Start or a constraint such as

    Must Start On or Start No Earlier Than. Use the Tasks with Fixed Dates Filter to view only those

    tasks in a plan that contain fixed dates.

  • 8/3/2019 Ms Project Using

    16/20

    Patricia Egen Consulting16

    Resource Leveling

    If after removing the Actual Start and anyconstraint a task still does not reschedule based ona dependency, check the Resource Levelingfeature.

    Make sure Automatic Leveling is turned off byselecting Resource Leveling from the Tools menu andchoosing Manual.

    If a task still does not move, it may contain a delaybased on a previous Resource Level.

    Select Resource Leveling again from the Tools menuand choose Clear Leveling.

    Select whether or not to remove Leveling from theselected tasks or for the entire project.

  • 8/3/2019 Ms Project Using

    17/20

    Patricia Egen Consulting17

    Reports

    A handy report is the Calendar view using aResource Filter.

    Select Calendar from the View menu.

    Select the Using Resource Filter and type inthe name of the desired resource to display theCalendar for a particular resource.

    This produces a nice printout of a resources

    tasks with each month of a project on a separatepage.

  • 8/3/2019 Ms Project Using

    18/20

  • 8/3/2019 Ms Project Using

    19/20

  • 8/3/2019 Ms Project Using

    20/20

    Patricia Egen Consulting20

    Why does Project leave gaps?

    You have collapsed some summary tasks.

    Subtasks that are collapsed don't show up

    anywhere, leaving gaps. To fix this, select all tasks, and click on Expand (the

    plus sign).