MM Mechanical FINAL

Embed Size (px)

Citation preview

  • 7/30/2019 MM Mechanical FINAL

    1/3

    Success in handing over a completely commissioned

    facility to the operator, whether a new build or brown-

    field modif ication, is contingent upon the completion

    of numerous phases of the project, from the front end design and

    engineering through fabrication and final commissioning. Before

    final hookup and installation can be accomplished, three interrelated

    phases are undertaken, Mechanical Completion (MC), Pre-

    Commissioning and Commissioning (PC/C). Planning for them

    is critical to the schedule adherence, cost containment, successful

    installation and ultimate handoff for operation of the facility. This

    article will focus on the important Mechanical Completion phase

    in which Mustang plays an integral role.

    Mechanical Completion DefinedTo be mechanically complete, the construction activities on a

    specific portion of the project, such as the topsides, have been

    completed and accepted by the appropriate parties. In most

    instances, it is an integral part of the transition from construction

    into the pre-commissioning phase, but Mechanical Completion has

    specific attributes that lend themselves to being separately planned

    and conducted. Mechanical Completion, as the f inal phase of

    construction is, mostly undertaken by area or by discipline and is

    performed by construction-type personnel with participation fromspecialized equipment suppliers, the engineering firm, and other

    contractors as needed. It involves fabrication, assembly and non-

    functional testing to confirm the integrity of the construction and

    installation. To verify that a facility is mechanically completed,

    inspection or an oversight team must ensure that the final con-

    struction is in accordance with the project drawings, specifications,

    industry standards as well as all regulatory requirements from the

    authorities having jurisdiction. By mechanically completing the

    scope of work and verifying with proper inspection prior to moving

    the facility/equipment to the next phase of the work (e.g. the deck

    fabricator, integration facility or offshore), considerable schedule

    delays and excessive labor costs can be averted.

    What Mechanical Completion (MC) EntailsThe MC phase addresses structural, mechanical, piping, electrical,

    instrumentation and automation as well as topsides interfaces with

    export pipelines and subsea flowlines. Each of these areas needs to

    be thoroughly confirmed as complete, tested to the applicable

    codes and turned over with documentation to the Pre-Commission/

    Commissioning team as mechanically complete. During this phase

    of the work, depending on the regulatory agencies involved and

    the area of installation, the authority having jurisdiction (USCG,

    BOEMER, NRC, ABS, EPA, etc), will be involved in many

    aspects of the testing and approvals to allow the project to proceed

    further.

    One Mustang project consisted of large modules assembled in a

    fabrication yard and then shipped to a remote location where they

    were installed followed by joining interconnecting pieces for the

    piping, instrumentation and electrical. During Mechanical

    Completion, all systems and components were inspected by

    Mustang and verified. Any incorrect component was identified,tagged and later corrected prior to shipment of any modules from

    the fabrication yard. When the modules were finally shipped,

    limited personnel were only needed briefly at the remote site.

    These actions minimized the overall project schedule resulting in

    a significant savings and allowed production to commence earlier

    than originally planned.

    Structural, Mechanical and Piping Mechanical Completion

    of the structural, mechanical and piping portion of the project

  • 7/30/2019 MM Mechanical FINAL

    2/3

    includes, but is not limited to,

    verification that the piping systems,

    mechanical equipment and their

    supporting structure are installed,

    non-destructively examined,

    hydrostatically tested and flushed

    clean. Equipment and piping

    which required stress analysis and

    the resulting line stops, piping

    spring hangers, anchors, guides,

    etc, should be verified that

    installation is in accordance

    with the design data. Rotating

    equipment, including specialized

    larger pumps, compressors,

    generators and engine driven

    equipment, are handled differently.

    The equipments complex nature,

    and typically the limited knowl-

    edge of this type equipment by

    the fabricator, necessitates relying

    upon contracting vendors for field

    support of their equipment. These representatives assist and

    confirm the installation of such equipment, verifying alignment,

    completeness of preservation and operating fluids during this

    phase of the work. This assistance ensures warranties for such

    equipment are maintained and the equipment is ready for service

    when required. When the facility is installed offshore, the required

    work to assist start-up is largely completed in a few days and has

    no impact to the schedule.

    Electrical Verification of the electrical installation / construction

    is more complicated, as much of it is field routed for best fit. In

    addition to normal inspection of each of the cables and wiring,

    all terminations should be validated for the quality and accuracy

    of the installation. Some areas of inspection during this phase

    include, but are not limited to, cable and tray support, tray f ill,

    grounding, integrity, stress cone installation for medium and high

    voltage cable, terminations, continuity and megger testing, as well

    as checking the bend radius of the f inal installation and tiedown.

    Instrumentation Mechanical Completion for instrumentation

    systems includes validation of the instruments, valves and valve

    operators compared to the original design data to assure that

    process flow conditions will be met. As with the electrical MC,

    all wiring will need to be verified, inspected for continuity and

    insulation as well as loop checks for confirmation to the automation

    system. Both hydraulic and pneumatic tubing will be cleaned,

    flushed and pressure tested to assure that there are no leaks and

    that cleanliness meets required quality for the system it controls.

    Surface Protection The best possible coating application can

    minimize work in later stages of the project. Inspections will reveal

    whether or not painting or coatings on specified surfaces has been

    completed and insulation has been finished and is as specified in

    the drawings. Fireproofing application or special coatings provide

    a challenge on all projects and need to be closely examined.

    New Build or BrownfieldAlthough the MC activities are very similar for both a new build

    facility and a brownfield project, each has its own challenges.

    With the new build not being operational, there is more latitude

    for making construction decisions regarding hotwork and

    pressurized systems. With an operating facility, however, planning,

    scheduling and logistics in verifying tie-ins and equipment

    operation can be more complex and critical to avoiding any

    shutdown or disruptions to operations. Construction limitations

    due to hydrocarbons restrict the types of work that can beperformed and the equipment utilized to perform the work.

    Many brownfield projects on an operating facility will require

    restricted hot work permits and utilize welding habitats that enable

    hot work to be performed without shutting down the facility.

    This minimizes production shutdowns but adds another layer of

    complexity and interfaces among disciplines. An additional problem

    on many operating facilities is the limited bed space availability

    required for both operations and MC personnel.

    A thorough Mechanical Completion phase can reduce the overallproject schedule.

  • 7/30/2019 MM Mechanical FINAL

    3/3

    Equipment Preservation

    Preservation of the equipment after it arrives on site is an activity

    most often overlooked yet potentially quite costly to any project.

    This activity plays a critical role in the efficiency and cost

    effectiveness of not only Mechanical Completion, but the overall

    success of achieving a planned startup date. Preservation defines

    the preventive maintenance tasks that are necessary to ensure that

    equipment and systems are appropriately cared for from the time

    they leave the manufacturing facility to when they are put into

    normal operation. The more complex a project or the longer it

    takes to complete, the more susceptible equipment and components

    are to be damaged or neglected, thus voiding manufacturers

    warranties.

    Materials procured for a project are usually stored on-site at the

    fabrication facility awaiting their installation. If the equipment is a

    component on the lower level of a multi-tiered deck, for instance,

    it might be installed at an early fabrication stage and subjected

    to weather for an extended period while the rest of the facility is

    being fabricated and assembled. The cost of repairing or replacing

    equipment due to inadequate preservation can be significant.

    It is an area where experienced Mustang inspectors can assist

    third-party specialists, often contracted to supervise equipment

    preservation during the project and can be a worthwhile investment

    to limit equipment damage on site and delays in Mechanical

    Completion and Pre-Commissioning.

    Handover

    Ideally, with good planning, inspection and engineering interface,

    the projects construction phase will conclude with a successful

    mechanical completion. Upon conclusion of Mechanical

    Completion activities, a certificate should be issued stating that the

    relevant inspections and tests have been carried out according to

    the contract. All of the support documentation and redline drawings

    and documents should be attached. The certificate will be accom-

    panied by the punch list if the sail dates dont allow completion of

    all MC activities prior to moving to the next location.

    The exercise of Mechanical Completion is a critical link between

    the engineering/design and construction of

    the facility and its ultimate installation and

    operation. Mustang has the expertise to fill

    many roles during this phase. Mustangs

    planning during early project stages, execution

    with experienced construction management

    and inspector oversight, proper equipment

    preservation supervision , and interface

    management make the pre-commissioning

    and commissioning phases more efficient

    and economical.

    For more information concerning Mustangscapabilities in Mechanical Completion and

    Pre-Commissioning/Commissioning, contact

    Richard Shirley or Dan Vela at

    [email protected] or

    [email protected].

    Mustang inspectors are critical to successful MechanicalCompletion.

    Equipment installed on the lower level of a multi-tiered deck can be subjected to weatherfor long periods.